  • L&T Infrastructure Engineering Ltd.

    Client: M/s. Nana Layja Power Company Limited Project: EIA Study for 6x660 (3960) MW TPP &

    60 MLD Desalination Plant in Layja Mota Village, Kutch District, Gujarat

    Project No.:

    C1101308

    Title: Revised Form 1

    Document No.:

    RP007 Rev.:

    0 This document is the property of L&T-RAMBØLL CONSULTING ENGINEERS LIMITED and must not be passed on to any person or body not authorised by us to receive it nor be copied or otherwise made use of either in full or in part by such person or body without our prior permission in writing.

    File path: l:\ports\2010\c1101308 - eia-4000 mw tpp at gujarat\outputs\reports\moef clarifications\25.05.2015\007-brt-r0-revised form 1-25.05.2015.doc

    Notes:

    Revision Details:

    0 26.05.2015 First Submission ALJ BRT CVS

    Rev. Date Details Init. Sign. Init. Sign. Init. Sign.

    Prepared Checked Approved

  • Table of Contents

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    Table of Contents Page i

    TABLE OF CONTENTS

    1 Basic Information ...........................................................................................................................1

    2 Activity .............................................................................................................................................5

    3 Environmental Sensitivity ........................................................................................................... 25

    LIST OF FIGURES

    Figure 1: Location Map Figure 2: Location of Proposed TPP and Desalination Plant Site on Toposheet Figure 3: Thermal Power Plant Layout (Both Imported Coal and Blended Coal Options)

    LIST OF ENCLOSURES

    Appendix A: Survey no.s covered under Project site

  • REVISED FORM 1

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    1 Basic Information Page 1

    Form 1

    1 Basic Information S. No Item Details

    1. Name of the Project 3960 MW Coal based Thermal Power Plant (TPP) and 60 MLD Desalination Plant. 2 S.No. in the schedule Activity 1(D)

    3

    Proposed capacity/area/length/tonnage to be handled / command area/lease area/number of wells to be drilled

    6x660 (3960)1 MW Power Project with Supercritical technology & 60 MLD Desalination Plant with Reverse Osmosis technology

    Total Land: For Imported Coal Option: 1135 Acres2; For Blended Coal Option: 1298 Acres

    4 New/ Expansion/Modernisation New 5 Existing Capacity/Area etc Not Applicable 6 Category of Project i.e., „A „or ‟B‟ Category „A‟

    7 Does it attract the general condition? If yes, please specify No

    8

    Does it attract the specific condition? If yes, please specify

    Yes. As per the specific condition of EIA notification, 2006 (as amended), If any Industrial Estate/Complex / Export processing Zones /Special Economic Zones/Biotech Parks / Leather Complex with homogeneous type of industries such as chloro-alkali industries, leather/skin/hide processing industries, petrochemical based processing industries and synthetic organic chemicals industries or those Industrial estates with pre defined set of activities (not necessarily homogeneous), obtains prior environmental clearance, individual industries including proposed industrial housing within such estates/complexes will not be required to take prior environmental clearance, so long as the Terms and Conditions for the industrial estate/complex are complied with (Such estates/complexes must have a clearly identified management with the legal responsibility of ensuring adherence to the Terms and Conditions of prior environmental clearance, who may be

    1 As committed by NLPCL to MoEF through its Letter dated January 29, 2015. 2 Fuel Linkage for Imported coal option is submitted to MoEF and EAC(T) has appraised the project primarily for imported coal during their 30th meeting on January 29, 2015 and has recommended for grant of EC based on imported coal option vide its Minutes of the meeting. NLPCL shall obtain requisite amendment regarding quality of coal, transportation plan etc. after allocation of domestic coal block/coal linkage for the blended coal option.

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    1 Basic Information Page 2

    S. No Item Details held responsible for violation of the same throughout the life of the complex/estate). The 6X660 (3960) MW is an Anchor Industry in the proposed Multi-Product SEZ/FTWZ, DTA. However, considering the higher capacity of the project, Separate ToR was obtained for 6X660 (3960) MW Coal based Power Plant, EIA study has been carried out considering all ToRs (SEZ & Power and Desalination Plants) and Public Hearing has been conducted for all the project components.

    9

    Location Project Site located at Latitude 22056‟35”N and Longitude 69012‟50” E Location map is given as Figure 1.

    Plot/Survey/Khasra No. Survey no.s covered under Project site is given as Appendix A.

    Village Layja Mota

    Tehsil Mandvi

    District Kutch

    State Gujarat

    10 Nearest railway station/airport along with distance in km

    Nearest Railway station: Kothara - 33km

    Nearest Airport: Bhuj - 60 km

    11 Nearest Town, City, District Headquarters along with distance in km

    Nearest Town: Mandvi- 14.0 km District Headquarters: Bhuj - 58km

    12

    Village Panchayats, Zilla Parishad, Municipal Corporation, Local body (Complete Postal addresses with telephone nos. to be given)

    Layja Mota village Mandvi Taluk Kutch District

    13 Name of the applicant M/s. Nana Layja Power Company Limited

    14 Registered Address 301-303, Kaivanna Complex,

    Panchwati, Ahmedabad – 380 006.

    15

    Address for correspondence: C/o. IL&FS Energy Development Company Limited, 1st Floor, Corporate Office Tower, Ambience Mall Complex, Ambience Island, NH-8, Gurgaon, Haryana-122 001.

    Name Mr. Akhil Agarwal

    Designation( Owner/Partner/CEO) Director

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    1 Basic Information Page 3

    S. No Item Details Address C/o. IL&FS Energy Development Company

    Limited, 1st Floor, Corporate Office Tower, Ambience Mall Complex, Ambience Island, NH-8, Gurgaon, Haryana.

    Pin code 122 001 E-mail [email protected] Telephone No +91-124-4716104 Fax No +91-124-4716120

    16

    Details of Alternative Sites examined, if any. Location of these sites should be shown on a Toposheet.

    The proposed TPP and desalination plant site is falling in the area earmarked for Multi product SEZ near Mota Layja Village of Kutch district of Gujarat.

    Location of proposed TPP and desalination plant Site on Survey of India (SoI) Toposheet is given as Figure 2 The following three sites were examined to set up the proposed Multi-Product SEZ and FTWZ.

    Alternative Site 1: Near Khambhat village in Anand District, Gujarat

    Alternative Site 2: Western Shore of Okha, Jamnagar District, Gujarat

    Alternative Site 3: Near Layja Mota village in Kutch District, Gujarat

    Based on site analysis, Site 3 (near Layja Mota village) was found most Suitable.

    17

    Interlinked Projects Proposed Multi Product SEZ/FTWZ and DTA at Mota Layja & Shipyard Cum Captive Jetties including LNG Terminal at Nana Layja, Kutch District, Gujarat

    18 Whether separate application of interlinked project has been submitted. Yes.

    19

    If yes, date of submission Multi Product SEZ/FTWZ and DTA ToR Dated: 05.03.2013 (F.No:21-68/2011-IA-III). Shipyard Cum Captive Jetties Including LNG Terminal, ToR Dated: 14.11.2013 (F.No.11-87/2011-IA-III). ToRs were granted Public Hearing Completed and GCZMA Appraisal for CRZ Clearance is in progress.

    20 If no, reason Not Applicable

    21

    Whether the proposal involves approval/ clearance under:

    The Forest (Conservation) Act, 1980

    The Wildlife (Protection)

    Yes Project site is located at about eight (08) km from the HTL of open sea and about six (06) km away from tidal influenced (CRZ) area of river Kharod. The project

    mailto:[email protected]

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    1 Basic Information Page 4

    S. No Item Details Act,1972

    The CRZ Notification,2011(As amended)

    development area does not fall or contain any environmentally sensitive areas as specified in CRZ Notification and that the project area meets the regulations of CRZ Notification, 2011. The proposed fuel transportation system and water/ wastewater conveyance system in the utility corridor is a permissible activity as per the CRZ Notification 2011. Physical demarcation of HTL, LTL and delineation of CRZ boundaries for the project site and the intake/outfall and coal conveyor corridor were carried out by the NIO, Visakhapatnam.

    The application for CRZ clearance has been filed by the SEZ/FTWZ and DTA developers for entire SEZ/FTWZ and DTA including the power and Desalination projects and its associated facilities in UC. The proposal was considered during the 25th Meeting of Gujarat Coastal Zone Management Authority (GCZMA) on April 10, 2015 and after detailed discussions, the GCZMA decided to carry out the site visit by its Technical Committee which is expected during first week of June 2015.

    22

    Whether there is any Government Order/Policy relevant/relating to the site?

    Proposed SEZ/FTWZ has been granted In-Principle approval in June, 2010 by the SEZ Board of Approval (BoA).

    The land identified for SEZ/FTWZ development is certified by “Industries Commissionerate”, Government of Gujarat for bonafide industrial purposes.

    23 Forest land involved (hectare) Nil

    24

    Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up

    Name of the court Case no Orders/ directions of the court,

    if any and its relevance with the proposed project.

    None

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 5

    2 Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

    S. No.

    Information / Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever

    possible) with source of information data

    1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan)

    Yes Land requirement for development of the power plant is estimated at about 1135 acres for imported coal option and 1298 acres for blended coal option. MoU between NLPCL and SEZ/FTWZ developers (Sealand Ports Private Limited/ Avash Logistic Park Private Limited) has been signed for transfer of required land on long term lease basis. Around 61% of the land required for the power project has been already acquired by the SEZ Developers. There will be a permanent change in land use, land cover and topography due to the development of TPP and desalination plant. Change in the land use to industrial purpose is envisaged due to the proposed project. The land identified for the SEZ development is certified by “Industries Commissionerate”, Government of Gujarat for industrial purposes. Land cover will be improved by developing greenbelt/cover.

    1.2 Clearance of existing land, vegetation and buildings?

    Yes The land uses of the site are mostly fallow and open/barren land, partly open/degraded vegetation. The land identified for the SEZ development is certified by “Industries Commissionerate”, Government of Gujarat for industrial purposes. Clearance of vegetation will be carried out as per project requirement. The existing vacant land will be levelled and graded.

    1.3 Creation of new land uses? Yes As per requirement for the construction of proposed power plant and desalination plant as well

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 6

    S. No.

    Information / Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever

    possible) with source of information data

    as other infrastructure facilities. Plant Layout is given as Figure 3.

    1.4 Pre-construction investigations e.g. bore houses, soil testing?

    Yes Detailed soil investigations involving borehole and electrical resistivity tests were carried out to ascertain the soil characteristics including strength parameters.

    1.5 Construction works? Yes

    Office buildings and Civil structures will be constructed to accommodate Boiler, Turbine, Generator, Condenser, Natural Draft Cooling Towers, Chimney, Coal handling system, Ash handling system, ESP, Switchyard and other Mechanical and electrical plant and equipment

    Seawater intake system and Marine outfall system to dispose return cooling water and reject brine into Arabian Sea, which is designed based on mathematical modelling to minimise impacts.

    Covered Coal Conveyor system from Proposed Port at Nana Layja village to the plant site.

    1.6 Demolition works? No There are no structures in the proposed site.

    1.7 Temporary sites used for construction works or housing of construction workers?

    Yes Unskilled Workforce from nearby villages and towns will be engaged for construction work. Temporary construction workers camps for semi skilled and skilled workers will be located near the project site and adequate provision of water, fuel, medical facilities and sanitation will be ensured.

    1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations

    Yes Site development, construction of boundary walls, roads and other buildings.

    Above ground structures like plant buildings, coal handling system,

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 7

    S. No.

    Information / Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever

    possible) with source of information data

    cranes, hoists, power plant stack, Cooling towers, power transmission towers, ash handling system, water treatment systems, etc will be constructed.

    Storm water, effluent and Sewage conveyance networks and ETP/STP will be developed.

    Intake/outfall pipeline, Coal conveyor corridor will also be developed.

    Cut and fill quantities will be managed within the project site and the natural elevation of the project site shall be maintained to the extent possible.

    1.9 Underground works including mining or tunneling?

    Yes

    As per the project requirement such as:

    Power distribution systems within the plant premises

    Telecom facilities Water Supply, Sanitation

    and sewage systems, etc 1.10 Reclamation works? No - 1.11 Dredging? No Only Trenching is envisaged during

    laying of seawater intake/marine outfall pipelines

    1.12 Offshore structures? Yes Sea water intake system and marine outfall system for the disposal of reject brine & Return Cooling water along with its associated pipelines will be constructed.

    1.13 Production and manufacturing processes?

    Yes Thermal Power Plant:

    The Imported Coal (100%) or blended coal (30% of Imported: 70% of Indigenous) will be burnt in the furnace to generate steam in the boiler. The steam generator will be designed to generate main steam. The steam generated in the boiler is expanded in the HP, LP & IP turbines and power is generated in the generator which will be

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 8

    S. No.

    Information / Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever

    possible) with source of information data

    transmitted to grid through switchyard. The steam after expansion in the turbine is condensed in the condenser and condensed steam is recycled back to the boiler. The hot gases from the furnace after loosing heat in different areas goes through the Electrostatic Precipitators (ESP) where Fly ash is trapped. The clean gas goes through the chimney of 275 m height.

    Desalination Plant:

    Desalination Plant works on Reverse osmosis principle. In this system a high pressure pump pumps the feed water against membrane, which allows passing of good quality water (permeate) through it and rest water goes as reject. Considering 35% RO recovery, about 171 MLD sea water shall be required for producing 60 MLD of desalinated water.

    1.14 Facilities for storage of goods or materials?

    Yes The following facilities will be provided for storage of goods or materials.

    Stores Workshop Coal Yard/ Stock Pile (30

    days storage) Ash pond Water treatment chemicals

    such as Chlorine storage etc.,

    Fuel(LDO/HFO) tanks Temporary storage sheds

    are proposed during construction.

    1.15 Facilities for treatment or disposal of solid waste or liquid effluents?

    Yes Ash will be transported to ash pond through pipes. Dry fly ash will be sent to nearby cement, concrete, bricks and allied products manufacturing units. Bottom ash will be sent to ash pond lined with LDPE.

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 9

    S. No.

    Information / Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever

    possible) with source of information data

    Reject brine from the desalination plant along with the cooling water return from the power plant cooling tower shall be disposed off into the sea through the marine outfall system.

    Effluent streams emanating from the power station will be treated individually based on effluent quality. Treated effluents will be collected in monitoring basin for final monitoring before discharge. Sewage will be treated in the sewage treatment unit and will be used for the development of green belt.

    1.16 Facilities for long term housing of operational workers?

    No Housing for operational workers will be a part of SEZ project

    1.17 New road, rail or sea traffic during construction or operation?

    Yes Construction Phase:

    Vehicles involved in men and material transportation

    Construction equipment/ machinery and material shall be brought to the site by road.

    Heavy plant (power plant and desalination plant) machinery required for the power plant operations shall be brought by ships upto the nearby port

    Operation Phase:

    Coal requirement (Option 1) Imported coal – 13.8 MTPA; and (Option 2) Blended Coal – 16.0 MTPA will be brought by ships up to the nearby port.

    Trucks and tankers bringing in auxiliary fuel oil and chemicals to be used in pre-treatment, utilities etc.

    Closed trucks will be used to handle the dry fly ash

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 10

    S. No.

    Information / Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever

    possible) with source of information data

    generated as a result of power plant operations for transportation to end-users

    1.18 New road, rail, air waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc?

    Yes Internal roads inside project site for the movement of men and material.

    Existing roads in the region to be used after upgradation /augmentation/ strengthening

    1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements?

    No -

    1.20 New or diverted transmission lines or pipelines?

    Yes New Power transmission lines to evacuate the power generated into the regional/national grid

    Seawater Intake/Marine outfall Pipeline Corridor

    1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers?

    Yes Realignment of rainwater drainage/ surface runoff which will be limited to project site as per the requirement. Necessary studies have been carried out by appointing NIH, Roorkee and mitigation measures are proposed to maintain the natural drainage pattern of the project area.

    1.22 Stream crossings? Yes Proposed Seawater Intake/ marine outfall pipelines and Coal conveyor corridor will cross the Kharod Nadi towards South of plant site.

    1.23 Abstraction or transfers of water from ground or surface waters?

    Yes Construction Phase Water Requirement – 0.5

    MLD Source: Gujarat Water

    Supply & Sewerage Board (GWSSB)

    Operation Phase: Total Sea water for the

    project including Desalination Plant– 988.728 MLD

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 11

    S. No.

    Information / Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever

    possible) with source of information data

    Source: Sea water Fresh water - 22.8 MLD

    Source: Desalination Plant3 1.24 Changes in water bodies or the land

    surface affecting drainage or run-off? No Grading within the project site will be planned such a way that there shall be negligible impacts on the existing natural drainage system/ pattern

    1.25 Transport of personnel or materials for construction, operation or decommissioning?

    Yes

    Construction Phase:

    Movement of construction material including cement, aggregates, rock, sand and reinforcement

    Movement of construction workers by vans/buses

    Operation Phase:

    Transportation of fly ash through Road Transport, Coal from nearby port through closed conveyors. Spares and consumable material for Plant use through road transport

    Movement of workforce from the townships/ habitations to the plant site

    1.26 Long-term dismantling or decommissioning or restoration works?

    No -

    1.27 Ongoing activity during decommissioning which could have an impact on the environment?

    No -

    1.28 Influx of people to an area in either temporarily or permanently?

    Yes

    Temporary and limited during construction phase

    Marginal and permanent during operation phase (primarily skilled worker not available locally)

    1.29 Introduction of alien species? No - 1.30 Loss of native species or genetic

    diversity? No -

    1.31 Any other actions? No -

    3 Desalinated Water for Other Establishments in the SEZ/FTWZ, DTA and Proposed Shipyard cum Captive Jetties including LNG Terminal will be about 37.2 MLD.

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 12

    2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources that are non-renewable or in short supply):

    S. No.

    Information /Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever

    possible) with source of information data

    2.1 Land especially undeveloped or agricultural land (ha)

    Yes

    About 11354 acres for Plant with Imported coal option and 1298 acres for Plant with Blended Coal Option earmarked for TPP and Desalination Plant in the proposed Multi Product SEZ area is mostly fallow and Open/ barren land and partly with open/degraded vegetation.

    2.2 Water (expected source & competing users) unit: KLD

    Yes Construction Phase

    Water Requirement – 0.5 MLD

    Source: Gujarat Water Supply & Sewerage Board (GWSSB)

    Operation Phase:

    Total Sea water for the project including Desalination Plant– 988.728 MLD

    Source: Sea water Fresh water - 22.8 MLD

    Source: Desalination Plant

    2.3 Minerals (MT) Yes Option 1: Imported coal requirement – 13.8 MTPA

    Option 2: Blended Coal – 16.0 MTPA (Blend ratio of 70:30; i.e. Indian Coal (11.2 MTPA): Imported Coal (4.8 MTPA) respectively.

    2.4 Construction material – stone, aggregates, sand / soil (expected source – MT)

    Yes Soil, sand, gravel and stone aggregates will be procured from nearby sources. Cement and steel from reputed manufacturers as per availability.

    2.5 Forests and timber (source –MT) No -

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 13

    S. No.

    Information /Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever

    possible) with source of information data

    2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT), energy (MW)

    Yes Construction Phase- 5 MVA, will be met from 66 kV at Bayat village and partly from DG sets.

    Operation Phase –260 MW will be met from the generated power.

    Fuel: 13.8 MTPA (Imported Coal option), 16.0 MTPA (For Blended Coal Option).

    LDO/HFO for start up and secondary fuel – Total storage of 12000 m3 per annum (2x 5000 m3 for HFO and 1X2000 m3 for LDO)

    2.7 Any other natural resources (use appropriate standard units)

    No -

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 14

    3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

    S. No.

    Information / Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever

    possible) with source of information data

    3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies)

    Yes Coal will be handled through a covered conveyor system provided with fugitive dust suppression measures

    LDO/HFO intermittently for start-up and as a Secondary fuel.

    Chemicals required for pre-treatment and DM Plant such as Chlorine, Hydrazine, Coagulants etc.,

    Impact assessment study carried out covering the risks associated with coal and other chemicals handling and accordingly mitigation measures are suggested.

    3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases)

    No -

    3.3 Affect the welfare of people e.g. by changing living conditions?

    Yes Improved living conditions of local people Direct and Indirect

    employment during construction and operation phases of the project.

    3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc.,

    No

    -

    3.5 Any other causes No -

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 15

    4. Production of solid wastes during construction or operation or decommissioning (MT/month)

    S. No.

    Information / Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever

    possible) with source of information data

    4.1 Spoil, overburden or mine wastes No -

    4.2 Municipal waste (domestic and or commercial wastes)

    Yes Municipal wastes in the form of kitchen wastes, domestic wastes, papers etc.

    Details regarding quantifications, collection, handling and disposal / management are covered in the EIA study.

    4.3 Hazardous wastes (as per Hazardous Waste Management Rules)

    Yes Chemical Sludge From Waste Water Treatment - 5000 - M.T,

    Used Oil/Waste Oil & Spent Lubricants - 50 - M.T

    Discarded Containers / Barrels / Liners contaminated with Hazardous Wastes / Chemicals - 50 - M.T

    4.4 Other industrial process wastes Yes Bottom Ash Generation @ 85% PLF:

    Option 1: Imported Coal - 3.311 Lakhs TPA

    Option 2: Blended Coal – 8.790 Lakhs TPA

    Fly Ash Generation @ 85% PLF:

    Option 1: Imported Coal - 13.243 Lakhs TPA

    Option 2: Blended Coal –35.160 Lakhs TPA

    4.5 Surplus product No -

    4.6 Sewage sludge or other sludge from effluent treatment

    Yes Sewage sludge from the STP shall be appropriately utilised for land application in the greenbelt area.

    Sludge generated from Oil water separator shall be disposed off as per GPCB/CPCB guidelines or norms.

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 16

    S. No.

    Information / Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever

    possible) with source of information data

    4.7 Construction or demolition wastes Yes During construction phase, some amount of construction debris may be generated which will be segregated and whatever is re-saleable will be sold to buyers and rest of the waste will be used for filling up of low lying areas and development of internal roads and boundary walls.

    4.8 Redundant machinery or equipment No -

    4.9 Contaminated soils or other materials No Not envisaged during normal operation. Accidental spills if any, will be recovered and appropriate remedial measure will be carried out.

    4.10 Agricultural wastes No -

    4.11 Other solid wastes No Sludge generation from clarification of feed seawater for Desalination plant. Sludge generated is non-hazardous and non-toxic.

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 17

    5. Release of pollutants or any hazardous, toxic or noxious substances to air

    S. No.

    Information / Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever

    possible) with source of information data

    5.1 Emissions from combustion of fossil fuels from stationary or mobile sources

    Yes Construction Phase:

    From the operation of diesel engine driven construction equipment and movement of trucks/ vehicles carrying men and material

    Operation Phase:

    From power plants stacks, coal handling and coal stack yard, Conveyor Transfer Points etc.,

    5.2 Emissions from production processes Yes Construction Phase: From the operation of diesel engine driven construction equipment and movement of trucks/ vehicles carrying men and material.

    Operation Phase:

    Emissions from the power plant stacks/ chimney and its impacts were studied in the EIA considering the emission norms/ standards stipulated.

    SO2 – < 2000 mg/Nm3 NOX – 750 mg/Nm3 PM – 50 mg/Nm3

    The emissions from the plant shall be kept below the above mentioned standards.

    5.3 Emissions from materials handling including storage or transport

    Yes Fugitive Emission from

    Stock pile Ash Pond Coal Conveyor etc.,

    Potential fugitive emissions were assessed and suitable control measures including required greenbelt development, dust

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 18

    S. No.

    Information / Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever

    possible) with source of information data

    suppression system to minimise the impacts were included in the EIA Study.

    5.4 Emissions from construction activities including plant and equipment

    Yes Temporary in nature which may originate during construction of buildings or roads, this will be taken care by proper dust suppression by sprinkling of water.

    5.5 Dust or odours from handling of materials including construction materials, sewage and waste

    Yes Dust generated due to handling of construction material will be controlled by sprinkling of water

    Odour from Sewage Treatment Plant (STP) is envisaged, odour mitigation measures will be followed.

    Dust Suppression system and Greenbelt will be provided.

    5.6 Emissions from incineration of waste No Not Applicable

    5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris)

    No Not Applicable

    5.8 Emissions from any other sources No Nil

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 19

    6. Generation of Noise and Vibration, and Emissions of Light and Heat

    S. No.

    Information/Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities /rates, wherever

    possible) with source of information data

    6.1 From operation of equipment e.g. engines, ventilation plant, crushers

    Yes Noise

    Construction Phase – 70-85 dB (A) very near to the source such as DG set or heavy equipment etc. and PPEs will be provided to the workers. The typical sources are:

    Vehicular movement Construction equipment Construction activities

    All major sound generating activities will be scheduled during daytime. However, the effect of the noise is mostly localised and temporary, i.e. will cease on completion of construction activity

    Operation Phase – not exceeding 85 dB (A).

    Seawater intake pumps/BFW Pumps and RO feed Pumps

    Vehicular movement Power plant auxiliaries and

    utilities

    Heat

    Heat will be generated from the operational works. Cooling water will be used to extract the heat in steam turbine condensers and from auxiliary cooling water circuits etc.

    6.2 From industrial or similar processes Yes From the plant areas/ compressors etc.,

    Noise generation at sources shall be complied with the prescribed standard.

    6.3 From construction or demolition Yes Excavation, drilling and welding will be carried out during construction phase which will be temporary in nature. Measures will be taken to

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 20

    S. No.

    Information/Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities /rates, wherever

    possible) with source of information data

    ensure that noise from construction activity is limited to plant site.

    6.4 From blasting or piling Yes No blasting

    Piling will be done and necessary PPEs will be provided to the workers.

    6.5 From construction or operational traffic

    Yes During the construction activities, utmost care will be taken to control the noise levels within the standards. While operation traffic will contribute some noise level and mitigation measures will be followed.

    6.6 From lighting or cooling systems Yes Heat rejection is envisaged from industrial cooling systems.

    6.7 From any other sources Yes Coal (un)loading operations, handling operation including crushing and during Coal Transport, Noise generation is envisaged.

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 21

    7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea

    S. No. Information/Checklist confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever possible) with source of information data

    7.1 From handling, storage, use or spillage of hazardous materials

    No In case of accidental spillage if any, spill contingency measures will be taken to prevent the release of pollutants in to the environment and managed as per the guidelines of the MSIHC rules.

    7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge)

    Yes Reject brine and Return Cooling water of 612.7 MLD will be discharged into sea after meeting stipulated standards.

    Treated sewage (0.384 MLD) will be recycled for horticulture and the sludge shall be used for greenbelt development.

    Oily wastewater shall be treated in the oil water separator; oil will be collected and disposed as per GPCB norms.

    7.3 By deposition of pollutants emitted to air, onto the land or into water

    Yes Construction Phase: Fugitive dust due to construction activities, equipment/vehicular emissions and transportation of raw materials. Suitable mitigation measures will be followed. Operation Phase: Air: Stack emissions, Vehicular

    emissions, Fugitive emissions from stack yards, and spillage at handling areas.

    Appropriate technological mitigation measures will be followed to avoid the deposition of pollutants.

    Water: Reject brine and Return Cooling water of 612.7 MLD will be discharged into the sea after careful examination of discharge

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 22

    S. No. Information/Checklist confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever possible) with source of information data

    characteristics. The intake/outfall locations are selected based on the mathematical modelling studies in order to minimise the impacts on the marine environment.

    Land: Fly Ash, gradually to be sold to cement plants/ brick manufacturers or exported to meet MoEF guidelines. Bottom ash, conveyed to ash dyke initially and to be sold for local construction works

    The sludge generated from the oily waste treatment system will be collected separately and disposed to the GPCB approved vendors. Municipal solid wastes shall be sent for composting/ landfill

    7.4 From any other sources No Not envisaged during normal operations

    7.5 Is there a risk of long term build up of pollutants in the environment from these sources?

    No Not envisaged during normal operation in view of proposed pollution preventive and control measures to comply with the prescribed statutory norms. The dilution capacity of air and water bodies being large the assimilative capacity will be high. All the emissions and discharges from the TPP will meet the prevailing standards.

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 23

    8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment

    S. No.

    Information / Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever possible) with source

    of information data

    8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances

    Yes Risk Analysis was carried out as a part of EIA study. Risk mitigation measures are accordingly suggested.

    8.2 From any other causes No -

    8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst, etc.)?

    Yes The project site is falling in seismic Zone V (Very high risk earthquakes). Based on the Probabilistic Seismic Hazard Assessment (PSHA) carried out for the project site, recommendations were made for the strong ground motion at the site in terms of design response spectra for various return periods along with appropriate strong motion time histories.

    The Peak Ground Acceleration (PGA) values for the Maximum Considered Earthquake (MCE) and Design Basis Earthquake (DBE) conditions are estimated as 0.34 g and 0.09 g, respectively, for both horizontal components from PSHA.

    However, considering that the project site lies in Zone V of the IS: 1893 (Part-I 2002) the PGA may be adopted as 0.36 g and 0.18 g for MCE and DBE conditions, respectively. A factor of 2/3 may be considered for vertical component.

    Necessary precautionary measures would be built-in / implemented.

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    2 Activity Page 24

    9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

    S. No.

    Information / Checklist Confirmation

    Yes / No

    Details thereof (with approximate quantities / rates, wherever possible) with source

    of information data

    9.1 Lead to development of supporting utilities, ancillary development or development stimulated by the project which could have impact on the environment e.g.:

    1. Supporting infrastructure (roads, power supply, waste or wastewater treatment, etc.)

    2. Housing development

    3. Extractive industries

    4. Supply industries

    5. Other

    Yes

    Induced development due to the proposed project in the region, which will create better infrastructure and will attract migration of people

    Necessary supportive utilities, infrastructure, housing etc to cater the requirements of the project would be developed as a part of the project

    9.2 Lead to after-use of the site, which could have an impact on the environment

    No The proposed project would be a permanent establishment

    9.3 Set a precedent for later developments

    Yes The region has potential for industrial investments in the form of power plants, industries, seaport, SEZs etc

    9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects

    Yes 6x660 (3960) MW Coal Based Thermal Power Plant will be located in the proposed Multi Product SEZ. The possible cumulative effects on the study area are considered and addressed adequately in the EIA.

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    3 Environmental Sensitivity Page 25

    3 Environmental Sensitivity S.

    No. Areas Name/

    Identity Aerial distance (within 15 km.)

    1

    Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value

    Nil Nil

    2

    Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests

    Dhuva Reserve Forest 12.0 km, South East

    3

    Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration

    Nil Nil

    4 Inland, coastal, marine or underground waters

    Vengadi Nadi 2.3 km, West Kharod River 2.1 km, South East Kharod Dam 16.2 km, NE Rajada Reservoir 5.4 km, ENE Vengadi Reservoir 1.45 km, NE Don Reservoir 8.8 km, E Sai Nadi 12.3 km, North West Arabian Sea ~8.0 km, South Rukmavati River 14.0 km, ESE

    5 State, National boundaries Nil Nil

    6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas

    National Highway - NH 8 A (Extension) 0.7 km, SW

    7 Defence installations Nil Nil 8 Densely populated or built-up area Mandvi 14 km, SE

    9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities)

    Study Area Villages

    Mostly every village in the study area has Primary Health Centre and Primary school

    Asharmata Temple 7.3 km, South Jain Temple at M. Layja 1.6 km, South

    10

    Areas containing important, high quality or scarce resources, (groundwater resources, surface resources, forestry, agriculture, fisheries, tourism, minerals)

    Nil Nil

    11

    Areas already subjected to pollution or environmental damage. (those where existing legal environmental standards are exceeded)

    Nil Nil

    12

    Areas susceptible to natural hazard which could cause the project to present environmental problems, (earthquakes, subsidence, landslides, erosion or extreme or adverse climatic conditions)

    Project site is prone to Earthquake (Seismic Zone V)

    The project site is falling in seismic Zone V (Very high risk earthquakes). Based on the Probabilistic Seismic Hazard Assessment

  • EIA Study for 6x660 (3960) MW TPP & 60 MLD Desalination Plant in Layja Mota Village, Kutch District, GujaratC1101308 Revised Form 1 RP007 rev. 0

    3 Environmental Sensitivity Page 26

    S. No. Areas

    Name/ Identity

    Aerial distance (within 15 km.)

    (PSHA) carried out for the project site, recommendations were made for the strong ground motion at the site in terms of design response spectra for various return periods along with appropriate strong motion time histories.

    The Peak Ground Acceleration (PGA) values for the Maximum Considered Earthquake (MCE) and Design Basis Earthquake (DBE) conditions are estimated as 0.34 g and 0.09 g, respectively, for both horizontal components from PSHA.

    However, considering that the project site lies in Zone V of the IS: 1893 (Part-I 2002) the PGA may be adopted as 0.36 g and 0.18 g for MCE and DBE conditions, respectively. A factor of 2/3 may be considered for vertical component.

    Necessary precautionary measures would be built-in / implemented.

    Note: Distances (Aerial) are from the nearest boundary of Project Site.

  • mailto:[email protected]

  • LOCATION MAP

  • LOCATION OF PROPOSED

    TPP AND DESALINATION

    PLANT SITE ON

    TOPOSHEET

  • THERMAL POWER PLANT

    LAYOUTS (BOTH IMPORTED

    AND BLENDED COAL

    OPTIONS)

  • APPENDIX A – SURVEYS

    NOS COVERED UNDER

    PROJECT SITE

  • l:\ports\2010\c1101308 - eia-4000 mw tpp at gujarat\outputs\reports\moef clarifications\25.05.2015\appendix a -survey nos..doc Page 1

    APPENDIX A: Survey Numbers of Project Site

    S.No Survey No Village Name

    Area (acres)

    1 607/106 Baytha 2.23

    2 177 Undoth 11.16

    3 178/1 Undoth 7.27

    4 178/2 Undoth

    5 182 Undoth 12.08

    6 207 Undoth 13.06

    7 208 Undoth 16.54

    8 196 Undoth 15.91

    9 193/1 Undoth 11.48

    10 193/2 Undoth 4.03

    11 198 Undoth 5.10

    12 197 Undoth 9.39

    13 204 Undoth 6.40

    14 203/1 Undoth 11.90

    15 218 Undoth 11.74

    16 212 Undoth 0.67

    17 213 Undoth 2.92

    18 220 Undoth 6.04

    19 186 Undoth 10.21

    20 187 Undoth 4.26

    21 189 Undoth 4.07

    22 190 Undoth 11.49

    23 526 Layja Mota 6.94

    24 527 Layja Mota 6.50

    25 528 Layja Mota 11.83

    26 516 Layja Mota 20.85

    27 517 Layja Mota 8.75

    28 518 Layja Mota 4.69

    29 519 Layja Mota 7.90

    30 520 Layja Mota 13.93

    31 521 Layja Mota 7.83

    32 522 Layja Mota 8.39

    33 523/1 Layja Mota

    14.71

    34 523/2 Layja Mota

    35 523/3 Layja Mota

    36 523/4 Layja Mota

    37 523/5 Layja Mota

    38 524 Layja Mota 8.38

    39 525 Layja Mota 8.87

    40 513/1 Layja Mota 8.02

    41 513/2 Layja Mota 5.55

    42 511/1 Layja Mota 5.51

    S.No Survey No Village Name

    Area (acres)

    43 511/2 Layja Mota 3.90

    44 512 Layja Mota 5.75

    45 478 Layja Mota 5.34

    46 479 Layja Mota 10.92

    47 473 Layja Mota 8.28

    48 481 Layja Mota 15.01

    49 480 Layja Mota 13.30

    50 468 Layja Mota 8.04

    51 467 Layja Mota 10.93

    52 482 Layja Mota 9.74

    53 483 Layja Mota 17.36

    54 507 Layja Mota 16.38

    55 508 Layja Mota 10.33

    56 509 Layja Mota 12.39

    57 484 Layja Mota 11.19

    58 485 Layja Mota 15.51

    59 486/1

    Layja Mota 15.21

    60 486/2

    61 486/3

    62 486/4

    63 486/5

    64 487/1 Layja Mota 10.13

    65 487/2

    66 488 Layja Mota 15.59

    67 489 Layja Mota 9.79

    68 503 Layja Mota 10.96

    69 504 Layja Mota 11.84

    70 490/1 Layja Mota

    9.67

    71 490/2 9.10

    72 251 Bayatha 4.76

    73 252 Bayatha 12.05

    74 253 Bayatha 11.72

    75 254 Bayatha 10.85

    76 255 Bayatha 9.57

    77 258 Bayatha 7.79

    78 259/1 Bayatha 18.33

    79 259/2 Bayatha

    80 260 Bayatha 11.01

    81 262 Bayatha 3.02

    82 263 Bayatha 2.70

    83 264 Bayatha 22.18

    84 265 Bayatha 7.61

  • l:\ports\2010\c1101308 - eia-4000 mw tpp at gujarat\outputs\reports\moef clarifications\25.05.2015\appendix a -survey nos..doc Page 2

    S.No Survey No Village Name

    Area (acres)

    85 267 Bayatha 15.56

    86 268 Bayatha 8.00

    87 269 Bayatha 8.19

    88 607/92 Bayatha 10.86

    89 607/93 Bayatha 11.75

    90 607/95 Bayatha 12.85

    91 607/109 Bayatha 9.13

    92 610/1 Bayatha 2.35

    93 191 Undoth 8.20

    94 199 Undoth 18.51

    95 200 Undoth 15.11

    96 188 Undoth 5.45

    97 477 Layja Mota 4.69

    98 510/1 Layja Mota

    2.20

    99 510/2 11.91

    100 192 Undoth 7.53

    101 185 Undoth 114.96

    102 216 Undoth 1.95

    103 243/P

    Undoth& Bayatha

    29.38

    104 607 Bayatha 7.85

    105 261 Bayatha 12.68

    106 266 Bayatha 4.16

    107 529 Layja Mota 8.47

    108 530 Layja Mota 25.48

    109 531 Layja Mota 2.04

    110 532 Layja Mota 14.36

    111 533 Layja Mota 10.00

    112 539 Layja Mota 8.34

    113 540 Layja Mota 5.02

    114 542 Layja Mota 8.39

    115 538 Layja Mota 10.04

    116 256 Bayatha 7.64

    S.No Survey No Village Name

    Area (acres)

    117 257 Bayatha 6.45

    118 W2 Undoth 3.29

    119 U2 Bayatha 3.54

    120 U1 Undoth 2.08

    121 LU1 Layja Mota 0.52

    122 LW4 Layja Mota 1.98

    123 LW3 Layja Mota 2.49

    124 LW1 Layja Mota 0.85

    125 LW2 Layja Mota 1.48

    126 W1 Layja Mota 2.80

    127 534/1a Layja Mota 2.26

    128 2a Layja Mota 0.94

    129 713 Layja Mota 2.49

    130 607/P Bayatha 7.42

    131 Other Unidentified 4.35

    132 217 Undoth 8.14

    133 206 Undoth 7.39

    134 205 Undoth 5.02

    135 514 Layja Mota 6.09

    136 476/1 Layja Mota 13.62

    137 469 Layja Mota 6.26

    138 465/1 Layja Mota

    6.52 139 465/2 Layja Mota

    140 465/3 Layja Mota

    141 465/4/4 Layja Mota

    142 506 Layja Mota 19.08

    143 505 Layja Mota 13.17

    144 502 Layja Mota 11.04

    145 501 Layja Mota 10.72

    146 203/2 Undoth 3.15

    147 203/3 Undoth 7.05

    1298.00

  • L&T INFRASTRUCTURE ENGINEERING LIMITED (Formerly Known as L&T-RAMBØLL CONSULTING ENGINEERS LIMITED)

    6-3-1192/1/1, 5th Floor, Block No.3,

    White House, Kundan Bagh, Begumpet, Hyderabad – 500 016

    Ph: 91-040-40354444; Fax: 91-040-40354430