Comparative analysis of the functional features of PM software packages1
Parameters and Functions
MS
Project
Spider
Project
Lite
Primavera
Project
Management
Open Plan
Professional
Spider Project
Professional
MSP SPL P6 OPP SPP
STRUCTURES
Portfolio Breakdown Structure Yes No Yes Yes Yes1
Work Breakdown Structure Yes Yes Yes Yes Yes1
Resource Breakdown Structure Yes Yes Yes Yes Yes1
Cost Breakdown Structure No Yes Yes Yes Yes
ACTIVITY TYPES
Duration Yes Yes Yes Yes Yes
Effort Yes Yes Yes Yes Yes
Volume (physical) No Yes No No Yes
Hammock (LOE) Yes
2
Yes Yes Yes YesSwitch No Yes No No Yes
Milestone Yes Yes Yes Yes Yes
RESOURCE TYPES
Labor Yes Yes Yes Yes Yes
Material Yes Yes Yes Yes Yes
Production No No No No Yes
Skills No Yes4 No Yes3 Yes4
Multi-Resources (crews) No No No No Yes
DEPENDENCIES
Standard 4 types (FS, SS, FF, SF) Yes Yes Yes Yes Yes
Time Lags Yes Yes Yes Yes Yes
Volume Lags No Yes No No Yes
Strict Links No No No No Yes
Conditional Dependencies No Yes No No Yes
Multiple Links No Yes Yes Yes Yes
Double Dependencies No Yes No No Yes
Dependency Filters No Yes No No Yes
RESOURCE ASSIGNMENTS
Individual Yes Yes Yes Yes Yes
Multi-Resources No No No No Yes
Independent teams (Shifts) No No No No Yes
Partial Workload Yes Yes5 Yes Yes Yes5
Predefined Workload Profile Yes No Yes Yes No
Automatic Workload Profile Adjustment No No No Yes Yes
Material Consumption Yes Yes Yes Yes Yes
Material Production No No No No Yes
Materials consumed by Resources No Yes No No Yes
-
7/29/2019 Table - Comparative Analysis of the Functional Features of PM Software Packages
2/3
-
7/29/2019 Table - Comparative Analysis of the Functional Features of PM Software Packages
3/3
Comparative analysis of the functional features of PM software packages3
PROJECT PORTFOLIO
Portfolio Scheduling and Leveling No No Yes Yes Yes
Project Priorities Yes No Yes Yes Yes
Portfolio Budget Yes No Yes Yes Yes
Portfolio Budget by Cost Components and Centers No No No No YesPortfolio Cash Flow Including Profits Yes No No Yes Yes
WORK THROUGH WWW
Monitoring Performance Yes Yes10 Yes Yes Yes10
Remote Work With Project Model No Yes10 Yes No Yes10
Graphical Reports
Activity Gantt Chart Yes Yes Yes Yes Yes
Resource Gantt Chart No Yes No No Yes
Material Gantt Chart No Yes No No Yes
Network Diagram Yes Yes Yes Yes Yes
WBS and RBS Org Charts No Yes No No Yes
Time-Location Chart (Linear Diagram) No Yes No No Yes
Resource Histograms Yes Yes Yes Yes Yes
S-Curves Yes Yes Yes Yes Yes
1 - unlimited number of parallel WBS, RBS and other structures in one project
2 - may be created, does not work properly when resources are assigned.
3 - for resources with the same productivity4 - resources of the same skill may have different productivities, automatic resource assignments based on skills and availability5 - simulation of quantities and workloads, not just total workload6 - cost accounts but not cost components, impossible to define that resource cost consists of salary, taxes, indirect costs etc.7 - working calendars take into account both activity and resource calendars8 - with the simulation of material supply or production9 - with the simulation of project financing and income10 - using FTP and FTPS, access directly from Spider Project without using third party software.