  • Slide 1
  • T1 status and plans INFN Genova November 2014 Collaboration Meeting
  • Slide 2
  • T1 at Point 5 F.Ferro - T1 status and plans
  • Slide 3
  • Already done Readout Replaced out-of-sync VFATs Extensive check of ground connections Replaced VFATs with bad occupancy patterns Replaced position sensors Sensors measuring z still to be checked by Joao Mechanics Installation test and mechanics checks on both halves Commissioning DAQ tested on all quarters HV tested on all quarters with Ar/CO 2 /CF 4 mix Test of trigger To be done Replace radiation monitor (waiting for Federico) Stoppers preparation (Roman) Commissioning Set up thresholds Maintenance & commissioning F.Ferro - T1 status and plans Status to be checked... Likely during 15-19 Dec. week
  • Slide 4
  • Installation: outlook F.Ferro - T1 status and plans CMS schedule is being deeply reviewed T1 installation schedule is strongly affected (T1 probably installed in February) Tasks 1 and 2 done in October (before magnet test). Tasks 3-12 to be done as soon as CMS ready to receive T1 (overall time needed for one side of T1 when HF on 2 risers is ~2 days).
  • Slide 5
  • T1 services on YE4 T1 services on YE4 Petals and cables installed on YE4 Minus side Plus side
  • Slide 6
  • T1 Maratons 4 repaired Maratons installed (2 per side)
  • Slide 7
  • Looking forward to... F.Ferro - T1 status and plans...reinstalling both T 1 s during LS1(February?)