T HR SS 80006 ST Renewable Energy Installations ... · T HR SS 80006 ST Renewable Energy...
Transcript of T HR SS 80006 ST Renewable Energy Installations ... · T HR SS 80006 ST Renewable Energy...
Renewable Energy Installations - Photovoltaic and Battery Systems
T HR SS 80006 ST
Standard
Version 1.0
Issue date: 09 April 2019
© State of NSW through Transport for NSW 2019
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
Important message This document is one of a set of standards developed solely and specifically for use on
Transport Assets (as defined in the Asset Standards Authority Charter). It is not suitable for any
other purpose.
The copyright and any other intellectual property in this document will at all times remain the
property of the State of New South Wales (Transport for NSW).
You must not use or adapt this document or rely upon it in any way unless you are providing
products or services to a NSW Government agency and that agency has expressly authorised
you in writing to do so. If this document forms part of a contract with, or is a condition of
approval by a NSW Government agency, use of the document is subject to the terms of the
contract or approval. To be clear, the content of this document is not licensed under any
Creative Commons Licence.
This document may contain third party material. The inclusion of third party material is for
illustrative purposes only and does not represent an endorsement by NSW Government of any
third party product or service.
If you use this document or rely upon it without authorisation under these terms, the State of
New South Wales (including Transport for NSW) and its personnel does not accept any liability
to you or any other person for any loss, damage, costs and expenses that you or anyone else
may suffer or incur from your use and reliance on the content contained in this document. Users
should exercise their own skill and care in the use of the document.
This document may not be current and is uncontrolled when printed or downloaded. Standards
may be accessed from the Transport for NSW website at www.transport.nsw.gov.au
For queries regarding this document, please email the ASA at [email protected] or visit www.transport.nsw.gov.au © State of NSW through Transport for NSW 2019
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
Standard governance
Owner: Lead Stations and Buildings Engineer and Lead Electrical Engineer, Asset Standards Authority
Authoriser: Chief Engineer, Asset Standards Authority
Approver: Executive Director, Asset Standards Authority on behalf of the ASA Configuration Control Board
Document history
Version Summary of changes
1.0 First issue
© State of NSW through Transport for NSW 2019 Page 3 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
Preface
The Asset Standards Authority (ASA) is a key strategic branch of Transport for NSW (TfNSW).
As the network design and standards authority for NSW Transport Assets, as specified in the
ASA Charter, the ASA identifies, selects, develops, publishes, maintains and controls a suite of
requirements documents on behalf of TfNSW, the asset owner.
The ASA deploys TfNSW requirements for asset and safety assurance by creating and
managing TfNSW's governance models, documents and processes. To achieve this, the ASA
focuses on four primary tasks:
• publishing and managing TfNSW's process and requirements documents including TfNSW
plans, standards, manuals and guides
• deploying TfNSW's Authorised Engineering Organisation (AEO) framework
• continuously improving TfNSW’s Asset Management Framework
• collaborating with the Transport cluster and industry through open engagement
The AEO framework authorises engineering organisations to supply and provide asset related
products and services to TfNSW. It works to assure the safety, quality and fitness for purpose of
those products and services over the asset's whole-of-life. AEOs are expected to demonstrate
how they have applied the requirements of ASA documents, including TfNSW plans, standards
and guides, when delivering assets and related services for TfNSW.
Compliance with ASA requirements by itself is not sufficient to ensure satisfactory outcomes for
NSW Transport Assets. The ASA expects that professional judgement be used by competent
personnel when using ASA requirements to produce those outcomes.
About this document
This standard sets the minimum requirements for photovoltaic installations, and provides
guidelines on how to achieve them.
This standard contains technical and operational requirements, and was developed by the ASA
in consultation with other TfNSW divisions and agencies.
This is a first issue.
© State of NSW through Transport for NSW 2019 Page 4 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
Table of contents 1. Introduction .............................................................................................................................................. 7
2. Purpose .................................................................................................................................................... 7 2.1. Scope ..................................................................................................................................................... 7 2.2. Application ............................................................................................................................................. 7
3. Reference documents ............................................................................................................................. 7
4. Terms and definitions ........................................................................................................................... 10
5. Rail environment.................................................................................................................................... 11 5.1. Safety and risk ..................................................................................................................................... 11 5.2. Electrical capacity augmentation for train stations .............................................................................. 12 5.3. Normal and alternative power source for train stations ....................................................................... 12
6. PVS design ............................................................................................................................................. 12 6.1. Design references ................................................................................................................................ 12 6.2. Feasibility study ................................................................................................................................... 14 6.3. Selection basis ..................................................................................................................................... 14 6.4. Energy efficiency of electrical installation ............................................................................................ 16 6.5. PVS integration with electrical installation ........................................................................................... 16 6.6. PVS connected to the RailCorp electrical network .............................................................................. 19 6.7. PVS connected to an LDNSP network ................................................................................................ 23 6.8. Location of PVS components .............................................................................................................. 24 6.9. PV panel orientation ............................................................................................................................ 24 6.10. PV panel tilt ...................................................................................................................................... 25 6.11. PV panel mounting .......................................................................................................................... 25 6.12. PV panel cleanliness ....................................................................................................................... 26 6.13. PV panel shading ............................................................................................................................. 26 6.14. Earthing, bonding and lightning protection ...................................................................................... 26 6.15. Battery storage ................................................................................................................................ 26 6.16. Emergency procedures .................................................................................................................... 29 6.17. Environmental conditions ................................................................................................................. 29 6.18. Heritage ........................................................................................................................................... 29 6.19. Evaluation methodology .................................................................................................................. 30 6.20. Further design stages ...................................................................................................................... 31 6.21. Alteration to approved design .......................................................................................................... 31 6.22. Critical review process ..................................................................................................................... 32
7. PVS equipment ...................................................................................................................................... 32 7.1. PV panels............................................................................................................................................. 33 7.2. Panel mounting system ....................................................................................................................... 33 7.3. Inverters ............................................................................................................................................... 33 7.4. Batteries ............................................................................................................................................... 35 7.5. PVS management ................................................................................................................................ 36 7.6. Wiring and protection ........................................................................................................................... 37 © State of NSW through Transport for NSW 2019 Page 5 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
7.7. Labelling............................................................................................................................................... 37 7.8. Documentation ..................................................................................................................................... 37
8. Installation, testing and commissioning ............................................................................................. 38 8.1. Performance monitoring ...................................................................................................................... 38 8.2. Periodic maintenance .......................................................................................................................... 38 8.3. Decommissioning and disposal ........................................................................................................... 39
9. Assurance .............................................................................................................................................. 39
Appendix A Feasibility study and evaluation methodology guide for PVS installations ................ 40
© State of NSW through Transport for NSW 2019 Page 6 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
1. Introduction Transport for NSW (TfNSW) aims at continual improvement in transport operation, achieving
better economic value and reducing adverse environmental effects.
The application of renewable energy sources should be complemented by usage of
energy-efficient equipment managed by intelligent control systems. Renewable energy sources
should not be used to compensate for energy wasted by inefficient equipment.
This standard includes photovoltaic systems (PVSs) using photovoltaic (PV) panels, with or
without battery storage.
2. Purpose This standard sets requirements for incorporating solar energy generation in TfNSW
installations in a consistent and efficient manner.
2.1. Scope Whilst there are two types of solar technology, PV and thermal, this standard sets requirements
for the design, construction, safe use and efficient operation of grid connected PVS with or
without battery storage.
Stand-alone (not connected to grid) photovoltaic systems as well as solar power generation
using thermal cells are not covered in this standard.
2.2. Application This standard applies to all stages of a PVS life cycle including planning, design, construction,
operation, maintenance and decommissioning. This standard applies to all new installations
including upgrades and additions or changes to existing installations.
While the document covers railway installations including stations, offices, car parks and other
rail facilities such as stabling yards, the guiding principles and requirements described in this
standard can be applied for other transport modes.
3. Reference documents The following documents are cited in the text. For dated references, only the cited edition
applies. For undated references, the latest edition of the referenced document applies.
International standards
IEC 61215-1 Ed.1.0 (all parts) Terrestrial photovoltaic (PV) modules - Design qualification and
type approval
© State of NSW through Transport for NSW 2019 Page 7 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
IEC 61730-1 Ed. 2.0 Photovoltaic (PV) module safety qualification - Part 1: Requirements for
construction
IEC 62109-1 Ed. 1.0 Safety of power converters for use in photovoltaic power systems - Part 1:
General requirements
IEC 62109-2 Ed. 1.0 Safety of power converters for use in photovoltaic power systems - Part 2:
Particular requirements for inverters
Australian standards
AS 2676.1-1992 Guide to the installation, maintenance, testing and replacement of secondary
batteries in buildings - Part 1: Vented cells.
AS 2676.2-1992 Guide to the installation, maintenance, testing and replacement of secondary
batteries in buildings - Part 2: Sealed cells
AS 3011.1 Electrical Installations - Secondary batteries installed in buildings – Part 1: Vented
cells
AS 3011.2 Electrical Installations - Secondary batteries installed in buildings - Part 2: Sealed
cells
AS 4086.1 Secondary batteries for use with stand-alone power systems - Part 1: General
requirements
AS 4086.2 Secondary batteries for use with stand-alone power systems - Part 2: Installation
and maintenance.
AS 60529 Degrees of protection provided by enclosures (IP Code)
AS IEC 62619:2017 Secondary cells and batteries containing alkaline or other non-acid
electrolytes - Safety requirements for secondary lithium cells and batteries, for use in industrial
applications
AS/NZS 1170.1 Structural design actions - Part 1: Permanent, imposed and other actions
AS/NZS 1170.2 Structural design actions - Part 2: Wind actions
AS/NZS 1768 Lightning protection
AS/NZS 3000 Electrical installations (known as the Australian/New Zealand Wiring Rules)
AS/NZS 3008.1.1 Electrical installations - Selection of cables – Part 1.1: Cables for alternating
voltages up to and including 0.6/1 kV - Typical Australian installation conditions
AS/NZS 3017 Electrical installations - Verification guidelines
AS/NZS 4509.1:2009 R2017 Stand-alone power systems - Part 1: Safety and installation
AS/NZS 4509.2:2010 R2017 Stand-alone power systems - Part 2: System design
© State of NSW through Transport for NSW 2019 Page 8 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
AS/NZS 4777.1:2016 Grid connection of energy systems via inverters - Part 1: Installation
requirements
AS/NZS 4777.2 Grid connection of energy systems via inverters - Part 2: Inverter requirements
AS/NZS 5033:2014 Installation and safety requirements for photovoltaic (PV) arrays
AS/NZS 61000 Electromagnetic compatibility (EMC) (series)
Transport for NSW standards
EP 03 00 00 01 TI Rectifier Transformer & Rectifier Characteristics
EP 12 10 00 20 SP Low Voltage Distribution Earthing
EP 12 10 00 21 SP Low Voltage Installations Earthing
EP 90 10 00 02 SP Standard Voltage Tolerances
T HR EL 17001 ST Electrical Distribution System Installation Connection and Inspection
T HR SS 80002 ST Low Voltage Electrical Installations
T MU AM 01001 ST Life Cycle Costing
T MU AM 01008 ST Technical Maintenance Plans and Coding System
Legislation
NSW Heritage Act 1977
Rail Safety National Law (NSW) 2012
Other reference documents
Clean Energy Council 2017, Battery Install Guidelines for Accredited Installers
Clean Energy Council 2017, Clean Energy Council Install and Supervise Guidelines for
Accredited Installers
Department of Planning & Environment, Division of Energy, Water and Portfolio Strategy, July
2018, Service and Installation Rules of New South Wales
Energy Networks Australia, ENA Doc 035 - 2014 Power Quality Guideline for Inverter Energy
Systems for Connection to Low Voltage Distribution Networks
Office of Environment and Heritage 2014, NSW Government Resource Efficiency Policy
Office of Environment and Heritage 2016, NSW Climate Change Policy Framework
PR D 78000 Electrical Network Safety Rules
RailCorp Section 170 Heritage and Conservation Register
© State of NSW through Transport for NSW 2019 Page 9 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
SA/SNZS TR IEC 61000.3.14:2013 Electromagnetic compatibility (EMC) – Part 3.14: Limits –
Assessment of emission limits of harmonics, interharmonics, voltage fluctuations and unbalance
for the connection of disturbing installations to LV power systems.
The Australian Building Codes Board, National Construction Code, volume one
Transport for NSW 2017, Sustainable Design Guidelines
4. Terms and definitions The following terms and definitions apply in this document:
ac alternating current
alternative power supply an independent supply to an installation connected using a change-
over arrangement. This does not include a UPS or battery backup
ASA Asset Standards Authority
AEO Authorised Engineering Organisation
BIPV building integrated photovoltaic
CEC Clean Energy Council
containment cable tray, cable ladder, wire basket, pipe, tube, duct, conduit or cable trunking for
the housing or protection of cables
dc direct current
DSMSB distribution supply main switchboard; the first LV switchboard between the transformer
terminals and the LV installation. The DSMSB is the location to establish the one and only
connection between earth and neutral.
EDU electrical distribution unit; the name of the business unit accountable for the rail transport
distribution network supply provider responsibilities. The EDU currently resides in Sydney
Trains.
installation means electrical installation unless otherwise required by the context
IP ingress protection
IMSB installation main switchboard; the low voltage switchboard from which the supply to the
whole installation can be controlled. The installation prefix is used in this standard to distinguish
the IMSB from the DSMSB
kWh kilowatt hour
LDNSP local distribution network supply provider
LV low voltage; voltage exceeding 50 V ac or 120 V ripple-free dc but not exceeding 1000 V ac
or 1500 V dc
© State of NSW through Transport for NSW 2019 Page 10 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
PCC point of common coupling
PV photovoltaic
PV panel solar photovoltaic panel
PVS photovoltaic system with or without battery storage
switchboard an assembly of circuit protective devices, with or without switchgear, instruments
or connecting devices, suitably arranged and mounted for distribution to, and protection of, one
or more submains or final subcircuits or a combination of both (AS/NZS 3000)
TfNSW Transport for NSW
5. Rail environment The rail environment is a high risk environment with technical and legal constraints that may not
be present in other areas where renewable energy is generated and used.
5.1. Safety and risk The PVS shall not impose a safety hazard to customers and members of the public and
personnel working on the network.
The Rail Safety National Law (NSW) 2012 requires that potential hazards be eliminated, or if
not possible, controlled so far as is reasonably practicable (SFAIRP), to ensure the safety of the
public and staff. Any risks associated with PVSs need to be assessed and addressed. The
requirements of the Rail Safety National Law (NSW) 2012 take precedence over legislated
requirements for non-rail applications.
Specific safety considerations for any transport application shall be, but not limited to, the
following:
• space, location and accommodation of all elements of a PVS
• fire hazards related any aspect of PVS operation
• hazards related to electrical energy and electrical safety
• earthing, bonding and lightning protection
• equipment-specific chemical and explosion hazards
• consequential hazards
• requirements related to people safety considering dynamic nature of passenger crowding
in transport facilities
• requirements related to ongoing operational continuity of public transport
© State of NSW through Transport for NSW 2019 Page 11 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
Additional requirements may need to be satisfied in addition to those specified in this standard.
Such requirements shall be identified and addressed as part of the project process.
5.2. Electrical capacity augmentation for train stations PVS with or without battery storage shall not be used for electrical capacity upgrades for
existing installations due to the requirement for a reliable power supply.
5.3. Normal and alternative power source for train stations PVSs, with or without battery storage, are not considered suitable as an alternative power
supply as defined in T HR SS 80002 ST Low Voltage Electrical Installations. This is because for
a PVS to be viable, the majority of energy needs to be consumed as it is produced.
6. PVS design Many factors contribute to choosing an appropriate renewable energy solution. Where used, a
PVS shall be developed as part of a holistic design solution for a particular facility and not
replace or preclude the requirements for energy-efficiency for any TfNSW facility or its part.
PVS installations can be integrated with buildings and other infrastructure. The appropriateness
and technical suitability of a PVS installation should be assessed based on the guidance in this
standard.
The design work shall be carried out by a suitably qualified professional accredited by the Clean
Energy Council (CEC) for the design of grid-connected photovoltaic power systems. Where the
system is connected to a storage battery then the designer shall also have CEC endorsement
for battery storage (for grid-connected systems).
PVS design and installation shall be assured by an AEO. If a PVS is procured as a stand-alone
contract to either TfNSW or Sydney Trains, Sydney Trains can assume the role of an AEO for
assurance purposes.
PVS design and connection to the network shall be reviewed and approved by the Electrical
Distribution Unit (EDU) prior to purchasing any PVS equipment and commencement of any work
on site.
6.1. Design references To ensure that potential effects of connecting a PVS to the low voltage (LV) network can be
assessed in a standardised way it is necessary to establish reference points at which such
change can be measured and compared.
© State of NSW through Transport for NSW 2019 Page 12 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
6.1.1. Point of common coupling
The point of common coupling (PCC) is defined as follows:
• for LDNSP networks, the PCC is defined in the NSW Department of Planning &
Environment, Division of Energy, Water and Portfolio Strategy Service and Installation
Rules of New South Wales
• for the RailCorp electrical network, the PCC is defined as the point at the distribution
supply main switchboard (DSMSB) to which the installation main switchboard (IMSB)
supply cable is connected
The electrical assets on the installation side of the PCC are dedicated for the use of that
electrical installation.
6.1.2. Point of supply The point of supply is defined as follows:
• for LDNSP networks, the point of supply is defined in AS/NZS 3000 Electrical installations
(known as the Australian/New Zealand Wiring Rules)
• for the RailCorp electrical network, the point of supply is the same as the PCC
6.1.3. Point of PVS connection to an electrical installation The following describes appropriate PVS to an electrical installation connection topology:
• for PVSs connected to an LDNSP network, the PVS connection point location shall be as
allowed by the Service and Installation Rules of New South Wales
• for PVSs connected to the RailCorp electrical network, but are prohibited to export energy
into the RailCorp electrical network, the PVS connection at the installation supply main
switchboard IMSB is preferable but other locations can be used where justified and
approved
• for PVSs that are connected to the RailCorp electrical network, and are allowed to export
energy into the RailCorp electrical network, the PVS connection point should be at the
switchboard with closest proximity to the PCC, which is the installation supply main
switchboard IMSB
6.1.4. Point of PVS connection to RailCorp LV distribution network The point of PVS connection shall be agreed with the EDU prior to commencement of the
project. Additional requirements may apply.
© State of NSW through Transport for NSW 2019 Page 13 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
6.1.5. Compliance prerequisites PVS installations described in this document shall comply with the following:
• relevant legislation, regulations and local authority requirements as applicable
• Service and Installation Rules of New South Wales
• Australian standards, including AS/NZS 5033:2014 Installation and safety requirements for
photovoltaic (PV) arrays and normative documents listed therein
• CEC, Clean Energy Council Install and Supervise Guidelines for Accredited Installers and
CEC, Battery Install Guidelines for Accredited Installers
• requirements of PR D 78000 Electrical Network Safety Rules (ENSR) and consideration of
the maintenance activities in accordance with ENSR
• requirements in this document
The EDU shall be consulted for each PVS project to obtain approval for the installation
methodology, connection to and the use of a particular switchboard.
6.2. Feasibility study Prior to commencing any PVS project, a feasibility study shall be carried out to assess the
technical, financial and environmental viability of installing and operating a PVS at a particular
site and to select the most optimal solution.
A feasibility study can be carried out by competent, suitably qualified internal staff or similarly
qualified external consultants. The feasibility study shall form the basis of any further work.
The feasibility study shall also investigate how the proposed PVS affects the existing
installation, including consideration of the installation power factor. The PVS shall not degrade
the installations power factor below a level of 0.90.
6.3. Selection basis PVS selection shall be guided by the NSW Government Resource Efficiency Policy that aims to
reduce operating costs and lead by example in increasing the efficiency of the resources it
uses.
While the capital cost of a PV panels and inverters has reduced, the cost of battery storage is
relatively high. The location and orientation of system elements can significantly affect the
efficiency and life cycle cost of a PVS. Rooftop-mounted systems are the most common.
Building-integrated or free-standing systems may be considered where feasible and supported
by a business case and approved by the operator and maintainer.
© State of NSW through Transport for NSW 2019 Page 14 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
Life cycle costing shall be used for evaluation of different PVS alternatives and available
options. The life cycle costing of various PVS choices shall use a time-base that is common to
all systems being compared. Unless, based on an appropriate justification, other length of time
is selected by project stakeholders, PVS system life of 25 years shall be used as a common
time-base for comparison of the life cycle costing calculations.
All assumptions and parameters used in the life cycle costing calculations shall be documented
as part of the assurance process.
A large number of transport facilities at various locations could be considered for PVS
installations. While priority should be given to installations providing the best economic benefit
and shortest payback periods, the cost should not be used as the only deciding factor in
selecting a system. Other factors include the following:
• Analysing costs and benefits not only in commercial but also in environmental and social
terms for each proposed system choice. Such considerations should include all relevant
factors from the time of the system purchase to the time of system disposal at the end of its
life –whole-of- life should be considered.
• Including embodied energy of materials and system parts (being the energy that was used
in the work of making a product and transport up to the point in time when the product was
acquired for a TfNSW project) in the considerations.
• Adopting cost effective products and services in accordance with the objectives of NSW
Government Resource Efficiency Policy.
• Innovation that supports TfNSW objectives.
6.3.1. Building integrated photovoltaics PVSs can be amalgamated into building structures by replacing traditional building materials or
elements such as windows, facades, louvres, roofing and so on with building integrated
photovoltaic (BIPV) components that retain or mimic the original material functionality whilst
producing electrical energy.
© State of NSW through Transport for NSW 2019 Page 15 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
These bespoke systems are more complex and can be relatively costly, but can provide
environmental and aesthetic benefits while reducing operational energy cost. The BIPV
electrical performance is often poorer compared to similar size traditional PVSs owing to the
following:
• non-optimal orientation and tilt due to design constraints, for example a south facing curtain
wall
• increased likelihood of partial shading for example, protruding objects and neighbouring
structures
• higher operating temperatures for example, solar tiles installed flush on a surface will have
minimal airflow, which may also increase module electrical degradation
BIPV design shall consider all aspects of the traditional building elements that are being
replaced by BIPV to account for different functionality, aesthetics, natural lighting, weather
protection, durability and so on. These considerations include the design life of BIPV and
determination of what degradation in a single function is acceptable before the building end of
life. As an example, a solar roof tile may be able to continue to function as a roof tile beyond 25
years but the electrical production will be severely degraded.
As BIPV systems combine builder and electrical works BIPV systems shall meet the
requirements of the relevant building codes and electrical standards.
An holistic approach to maximise the benefits while limiting the disadvantages is encouraged.
6.4. Energy efficiency of electrical installation Before a PVS is considered for a particular facility, existing electrical and other building services
installations shall be examined to identify any operational measures or retrofit solutions that
could improve the overall energy efficiency. Appropriate site-specific energy efficiency
measures shall be implemented before the addition of any renewable energy sources are
considered.
Possible measures include replacing inefficient equipment with energy efficient equipment,
introducing automated controls and better operational procedures. This process is also
applicable for new projects. As a minimum, the provisions of TfNSW Sustainable Design
Guidelines should be followed.
6.5. PVS integration with electrical installation All PVSs shall be grid connected systems. Requirements of Section 8 of Service and Installation
Rules of New South Wales apply.
Prior to PVS design, the electrical loads shall be analysed to estimate half-hourly power
demand profile in typical twenty-four-hour periods, separately for weekdays and weekends. This
© State of NSW through Transport for NSW 2019 Page 16 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
analysis will allow for the calculation of average, minimum and maximum electrical demand
during different months of a year (especially during winter and summer months). This will
facilitate understanding of when the renewable energy generation would be most needed and
best utilised.
The installation power demand can be quantified based on existing energy consumption data,
site measurements, or an informed estimate. The outcome shall be properly documented and
used as part of the basis for sizing the renewable energy installation.
6.5.1. PVS sizing PVSs may export energy to RailCorp or LDNSP networks as described in Section 6.6.2 and
Section 6.7.
Where no export is considered, the PVS shall be configured to comply with Section 6.6.1.
Where feasible and supported by a business case battery storage can be considered.
The size of the proposed PVS should be informed by the following:
• size and power demand profile of the existing (or proposed in case of a new) electrical
installation
• satisfactory operation, so that frequent shutdown and start-up of the inverter is prevented
• asserted goals (in terms of the renewable energy compared to total energy requirements)
• special circumstances, for example, where a battery storage option is considered
This will help to determine preliminary system size, configuration and design including the
number and dimensions of PV panels required. The sizing process shall include optimal PV
panels positioning and preliminary equipment selection.
The use of specialised software is recommended to aid sizing calculations.
6.5.2. Energy metering Energy generation data is reported by inverter control system for PVSs that are prohibited from
exporting energy into the RailCorp electrical network. No additional metering is required.
To measure and report the energy used by the installation for PVSs that are allowed to export
energy into RailCorp electrical network, the energy exported to the network plus the sum thereof
(equal to the total PVS generated energy) would be desirable.
© State of NSW through Transport for NSW 2019 Page 17 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
The following arrangements can be used, with the operator and maintainer making the
determination:
• Where net accounting for the energy usage from the RailCorp electrical network is not
required, the existing energy metering arrangement can be retained. Accounting for PVS
generated energy components (that is, usage and export) would be expected by accessing
PVS data with a detailed proposal being developed and approved before PVS design is
finalised.
• Where net accounting for the energy usage from the RailCorp electrical network is
required, the existing energy metering needs to be replaced with net metering.
For PVSs that are allowed to export energy into to an LDNSP network, net metering
arrangements are necessary. Detailed metering requirements are contained within the Service
and Installation Rules of New South Wales and the relevant LDNSP's documents.
Further information regarding metering arrangements can be obtained from the operator and
maintainer.
6.5.3. PVS connection to an existing or new electrical installation
Connection of a PVS to an existing or new electrical installation shall not create a situation
where the reliability of the supply network is degraded. Operation of the PVS shall not cause
undue interference with the supply to other parts of the installation or the supply network.
The PVS integration with the existing or new electrical installation shall comply with
AS/NZS 4777.1:2016 Grid connection of energy systems via inverters - Part 1: Installation
requirements and AS/NZS 4777.2 Grid connection of energy systems via inverters - Part 2:
Inverter requirements.
There may be additional requirements for installations in unique situations. These requirements
should be identified by the designer and operator and maintainer at the initial planning stage.
The operator and maintainer is an inspecting authority and no PVS installation can be
connected to either the RailCorp electrical network or an LDNSP network until that work has
been inspected and approved for connection by the EDU or other relevant inspecting authorities
as part of the mandatory inspection.
Application for connection in accordance with T HR EL 17001 ST Electrical Distribution System
Installation Connection and Inspection shall be submitted by the PVS designer as early as
practicable in the design phase.
© State of NSW through Transport for NSW 2019 Page 18 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
6.6. PVS connected to the RailCorp electrical network The requirements detailed in Section 6.6.1 to Section 6.6.2 shall apply to all PVS installations
connected to the RailCorp LV installation or distribution network. These requirements shall be
read in conjunction with the Service and Installation Rules of New South Wales.
6.6.1. Requirements for PVSs when export to the RailCorp electrical network is not permitted To prevent adverse impacts on safe and reliable operation of the network, unless explicit
approval is granted, the PVS shall not export power into the RailCorp LV distribution system.
That means the power generated by the PVS operating in parallel with RailCorp’s network may
only be consumed by the installation to which it is connected.
The nominated control logic and current thresholds are designed to concurrently achieve 'no
export'. The PVS shall be equipped with an anti-export controls which connect and disconnect
the inverter from the installation, via a contactor, as follows:
• in normal operation the IMSB incoming supply from the RailCorp LV distribution network
cable load is above 5 A per phase and the contactor is closed
• if the IMSB incoming supply cable load falls below 5 A on any phase the PVS inverters will
disconnect immediately, that is, the contactor is open
• if the IMSB incoming supply cable load has risen above 5 A but for less than 60 sec, the
contactor remains open
• if the IMSB incoming supply cable load remains greater than or equal to 5A for 60 seconds
the PVS inverters will be reconnected, that is, the contactor will close
Alternative means
The following alternative means of export prevention may be employed subject to written
approval from the EDU:
• the use of inverters equipped with suitable ramp rate management to ensure zero export
can be considered to prevent anti-export operation, however a PVS should be sized to
avoid frequent intervention of the inverter controls
• omission of anti-export controls can be considered if it can be demonstrated that a PVS will
never be able to export beyond the installation due to relatively small PVS when compared
with the total installation load
© State of NSW through Transport for NSW 2019 Page 19 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
6.6.2. Requirements for PVSs when export to the RailCorp electrical
network may be permitted Where there is ability to feed the excess energy back to the grid and there is a business case to
justify this approach, export to the RailCorp electrical network may be permitted.
Operation of the RailCorp LV network and feasibility of exporting PVS generated energy to the
network is limited by the network topology at the PVS point of connection, therefore the extent
of the permitted export needs be accurately determined, its size limited to a defined amount and
strictly controlled.
This is largely driven by the thermal capacity of the distributor feeders, the impedance of the
feeder (causing voltage rise), the distribution transformer rating and the combined effect of the
connected generation plant on RailCorp electrical network performance, operation and safety.
Permitted PVS capacity and export assessment criteria
The designer shall assess the feasibility of PVS connection at a particular point within the
network and select the optimal size of a PVS based on a number of criteria. These include, but
are not limited to, the following:
• the level of other generation already connected
• the proposed size of the PVS against the size of the transformer to which the installation is
connected
• the proposed export, which is the surplus of PVS generated energy at a given moment in
time over the energy consumed by the installation to which the PVS is connected
• the electrical strength, voltage and protection requirements of the RailCorp electrical
network at the PVS point of connection
• the requirements of T HR EL 17001 ST related to connection and inspection of electrical
installations
The PVS design shall demonstrate compliance with power quality requirements in accordance
with AS/NZS 4777 and comply with Energy Networks Australia ENA Doc 035 - 2014 Power
Quality Guideline for Inverter Energy Systems for Connection to Low Voltage Distribution
Networks and SA/SNZS TR IEC 61000.3.14:2013 Electromagnetic compatibility (EMC) – Part
3.14: Limits – Assessment of emission limits of harmonics, interharmonics, voltage fluctuations
and unbalance for the connection of disturbing installations to LV power systems.
© State of NSW through Transport for NSW 2019 Page 20 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
Installation that integrates a PVS intended to export energy into RailCorp LV network shall be
designed so that the following conditions are met:
• the voltage limits at the LV terminals of a RailCorp distribution transformer will not exceed +
5% - 8% for steady state and + 8% - 10% for transients (EP 90 10 00 02 SP Standard
Voltage Tolerances)
• maximum voltage rise between the IMSB and the PCC, that is the DSMSB, that is
measured on the cables linking DSMSB and the IMSB shall not exceed 1% of the nominal
PCC voltage
• maximum voltage rise between the PVS point of connection and the installation main
switchboard IMSB shall not exceed 1% of the nominal PCC voltage
• disconnection or failure of the PVS shall not cause the corresponding DSMSB voltage sag
to adversely affect the operation of the rail signalling system
The combined impedance of the cables between the point of the PVS connection to the
installation and the PCC (that is DSMSB) shall be low enough to ensure that the voltage rise
calculated between these two points shall not exceed values shown in diagram 1 and 2 below.
The voltage rise shall be calculated using full rated current of the PVS. The calculation can
substitute the full rated current of the PVS by an agreed export limit where curtailing of the PVS
output when the net export power exceeds the threshold of the agreed export limit is ensured.
Figure 1 and Figure 2 show typical PVS connection methods to the RailCorp electrical network.
DSMSB IMSB
Distribution board
Distribution board
RailCorp distribution
network
RailCorp distribution
networkLV installationLV installation
PCC and point of supplyPCC and point of supply Point of PVS connectionPoint of PVS connection
1% maximumvoltage rise
1% maximumvoltage rise
1% maximumvoltage rise
1% maximumvoltage rise
© State of NSW through Transport for NSW 2019 Page 21 of 41
Figure 1 - PVS connected downstream of IMSB
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
RailCorp
distributionRailCorp
distribution LV installationLV installation
DSMSB IMSB
Distribution board
Distribution board
PCC and point of supplyPCC and point of supply Point of PVS connectionPoint of PVS connection
1% maximumvoltage rise
1% maximumvoltage rise
Figure 2 - PVS connected at IMSB
In some instances, network augmentation or additional protection and control functions (for
either or both RailCorp electrical network and the PVS) may be required to ensure network
safety and performance standards are not compromised.
The EDU shall review the network study and advise the designer if additional work is required.
Network study
The technical considerations and resulting assurance that the PVS size and connection
topology shall not unduly degrade relevant electrical parameters at either the DSMSB or IMSB
shall be based on a network study.
The main purpose of the network study is to assess the extent of the proposed export in context
of the size and characteristics of relevant network elements to establish safe export limits. The
network study shall determine the maximum PVS capacity that can be connected to a particular
point at the RailCorp electrical network and the maximum export allowed. There may be cases
where the proposed system may be required to connect at a reduced capacity or where no
connection is allowed.
The network study shall determine the aggregate effect of the PVS and other embedded
generation during various load conditions on the LV network and the 11 kV network, and include
but not limited to the following considerations:
• network disturbances (for example, voltage and current harmonics and fluctuations)
• steady state voltage rise (on LV network, high voltage (HV) network or both)
• protection for anti-islanding
• current carrying capacity of the LV network
© State of NSW through Transport for NSW 2019 Page 22 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
The scope of the network study is shown in Table 1. To ensure that all relevant aspects are
adequately covered, the study scope shall be extended as deemed necessary by the designer.
Table 1
Task Description Procedure
1 Review enquiry form
• are location, capacity, voltage, connection and timing details provided?
2 Check inverter compliance to AS 4777
• CEC compliance • manufacturer's certificate available • AS 4777.2 compliance • witness testing if required
3 Model LV network • obtain data on connected load - minimum, maximum estimates, or confirm network data - feeder and service type, length, substation details
• model LV network downstream of distribution transformer including the PVS connection point and the PCC
4 Network studies • check 11 kV feeder loading level (% thermal rating) under minimum local load demand conditions
• check LV distributor loading level (% thermal rating) under minimum local load demand conditions
• check distribution transformer loading level (% thermal rating) under minimum and maximum local load demand conditions
• check voltage (% Vn) under minimum load at PCC • check voltage (% Vn) under maximum load at PCC • check fault level, that is, kA at IMSB and DSMSB • check voltage and current disturbance and harmonics against
limits for compliance • check power factor under all operating conditions • check protection methodology and satisfactory operation for
all types of network faults
5 Assess risk level of islanded operation. Increased risk if at least one of check 1 to check 4 is not met.
• check load generation match (Sinv: Sload <0.7) • check [Pinv]:[Pload] <0.8 or >1.2 • check [Qinv]:[Qload] <0.8 or >1.2 • number of single phase and three phase inverters on LV
feeder
Where the combined capacity of all PVSs connected to the same RailCorp distribution
transformer does not exceed 10% of the capacity of the transformer the network study is not
required.
6.7. PVS connected to an LDNSP network The connection and export of energy to an LDNSP LV network is not prohibited, however, it is
subject to an agreement with the EDU and the relevant LDNSP.
© State of NSW through Transport for NSW 2019 Page 23 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
In addition to LDNSP approval, approval shall be obtained from the EDU before a PVS is
permitted to export power into an LDNSP network.
Special care shall be given to installations connected to an LDNSP through an isolation
transformer. Installations supplied from an isolation transformer form part of the RailCorp
electrical network regardless of the LDNSP.
6.8. Location of PVS components The site and structure, or structures, on which PV panels are to be installed shall be selected to
facilitate compliance with the requirements of this standard.
The location and mounting of PV panels shall be chosen to ensure that they are easily
accessible for cleaning and maintenance but secure from vandalism.
PV panels or other parts of a PVS shall be mounted at least 2 m away from the 1500 V direct
current (dc) overhead wiring and its support structures. EP 12 10 00 21 SP Low Voltage
Installations Earthing provides further detailed requirements.
No equipment shall be located in areas where access for any maintenance can only be
achieved by securing a possession that is, taking a rail track or tracks out of use for work to be
able to proceed.
The location of PVS components shall be approved by the operator and maintainer.
Clear labelling shall be provided for emergency services to easily locate the relevant isolating
devices. These devices shall be accessible to emergency services at all times.
6.9. PV panel orientation The energy production of a PV panel is at its maximum when the sun is hitting the panel
perpendicular. That can be controlled by the panel's orientation (north, south, east or west) and
tilt (the angle of the panel from the surface of the earth).
Fixed installations are recommended. Installations that track the sun in real time (active solar
tracking) in order to achieve optimal panel position at different times of day are not
recommended for TfNSW applications as their life cycle cost is likely to exceed the expected
benefits.
To maximise year round energy production PV panels should be facing as close to true north as
possible. With north being 0 degrees or 360 degrees, any north-facing orientation between 60
degrees and 300 degrees is permitted. North-facing panel orientation between 90 degrees and
270 degrees may be acceptable where justified by relevant site factors. Installations where
panels are oriented outside these parameters are prohibited unless it can be shown that there is
a strong financial case for doing so.
© State of NSW through Transport for NSW 2019 Page 24 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
For example, if an installation's dominant loads (power demand) occur during mornings, PV
panel orientation towards the east (utilising the best of morning sun) would be more acceptable
than the PV panel orientation towards the west.
6.10. PV panel tilt To maximise year round energy production, PV panel tilt should be equal to the latitude angle of
the location of the panels (for example, 34 degrees in Sydney).
Panels located on roofs that are flat (that is, less than 34 degrees in Sydney) will yield more
energy in summer. These would be well suited where an installation's dominant loads occur
during summer.
Panels located on roofs that are steep (that is, more than 34 degrees in Sydney) will yield more
energy in winter. The steep roof installations would be more suited to contribute to winter loads,
responding to different sunlight incidence angles at that time of the year.
These factors shall be carefully considered against mounting the panels flush with the roof,
which, considering the cost of additional tilt frames, usually provide a better overall financial
outcome. Panels following the roofline would also be more acceptable for aesthetic reasons.
For example, for facilities with large air-conditioning loads (that predominantly occur on summer
afternoons), the PV panel orientation towards the north or north-west, on a flat roof, would result
in maximum electricity generation during these times.
6.11. PV panel mounting Panel mounting options considerations include the type, height and accessibility of roof or an
alternative mounting location, and whether tilt frames are required. The easiest mounting option
is where PV panel installation follows the angle of the roof.
An increase in panel temperature will considerably reduce a PV panel power output (typically by
15%-25% for panels mounted directly onto the roof). Consequently, a key consideration for
panel mounting is ability to reduce the panel temperature by convective cooling. This can
usually be achieved by providing a gap greater than 150 mm between the panels and the roof.
Other considerations for PV panel mounting include the following:
• site preparation needs, for example improving the condition of roofs, removal of trees or
other shading
• structural integrity as the building structure shall be capable of supporting the weight of PV
panels plus the weight of maintenance personnel at any one point of attachment
© State of NSW through Transport for NSW 2019 Page 25 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
6.12. PV panel cleanliness PV panel surfaces shall be periodically cleaned to maintain expected level of performance over
the life of the panel.
A larger tilt will contribute to self-cleaning, however self-cleaning is largely dependent on rainfall
and may be inadequate for soiling problems such as bird droppings, which can potentially lead
to other issues such as thermal hotspots and damage.
6.13. PV panel shading PV panel electrical output is extremely sensitive to shading. The panel location shall be chosen
to ensure that shading from local topography and features such as nearby structures or trees
(and their growth over time) is completely eliminated, as even partial shading has major adverse
effect on energy production.
Neighbouring topography shall be included in overall considerations to account for any other
factors that may affect energy production.
6.14. Earthing, bonding and lightning protection PVS earthing and bonding shall be designed and installed in conformance with AS/NZS 5033,
EP 12 10 00 21 SP and EP 12 10 00 20 SP Low Voltage Distribution Earthing.
A PVS shall be installed in conformance with AS/NZS 1768 Lightning protection. The location
and mounting of PV panels shall not interfere with or affect in any way the operation of a
lightning protection system nor shall lighting protection system interfere with the operation of PV
panels.
In any case, the minimum conductor size shall be 16 mm2 copper.
6.15. Battery storage A battery stores the excess energy produced by an energy generation system for use at times
when the system is not able to generate enough energy to meet the demand.
© State of NSW through Transport for NSW 2019 Page 26 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
For grid-connected system, energy stored in batteries can be used for the following:
• Reducing energy demand peaks in installations that are subject to a demand charge, also
known as capacity charge. Demand charge is an element of a commercial tariff where an
additional charge is determined by the installation's maximum half-hourly power reading
(load) during either a month or the 12 months prior to the bill being calculated.
• Reducing the energy costs during peak hours in installations that use peak, shoulder or off-
peak energy tariffs.
• Other forms of tariff optimisation that include charging batteries with cheap energy off-peak
and discharging (using the power) during times when the cost of energy is high.
Enabling the islanding function when utilising battery storage is prohibited.
Whilst many battery storage solutions are technically feasible, the energy tariff applicable to the
RailCorp electrical network does not involve any demand charge, and the difference between
peak and shoulder or off-peak tariff is smaller compared to other Australian commercial tariffs.
This significantly limits the attractiveness and possible monetary benefits of using battery
storage in TfNSW installations. Combined with relatively high initial acquisition cost it may make
battery storage uneconomical at present costs.
Currently there are a number of installations connected to the RailCorp electrical network where
surplus energy generated by a PVS could be stored in batteries for use at different times,
increasing consumption of renewable energy.
Depending on the battery type and chemistry, the losses associated with battery charging and
discharging amount to 10% to 15% of the stored energy. After adding the embodied energy
related to manufacturing and transport of the battery, from the sustainability point of view grid
export would be more efficient compared to using battery storage.
The basis of the battery sizing shall include the following:
• analysis of seasonal PVS energy generation and the installation energy consumption
patterns and differences during summer, winter, and intermediate seasons
• estimation of the amount of PVS generated energy (kWh) in the course of an average year
• estimation of the amount of PVS energy (kWh) that will be used directly (during daytime
hours) in the course of an average year
• comparison with the installation total energy use in the course of an average year
• consideration of various PV panels sizing compared to battery sizing options to best
address the particular project situation and maximise financial advantages of the proposed
solution over the installation life cycle
© State of NSW through Transport for NSW 2019 Page 27 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
• consideration of the battery depth of discharge (that varies according to the battery
chemistry) during everyday operation, as it can have a significant impact on the battery life
• the use of specialised design software
Several different types of batteries utilising various older and newer technologies are available
for use in a renewable energy system. The selection of a particular battery type shall be based
on life cycle costs that include not only the battery but also costs associated with the following:
• available location
• size and construction of battery room or enclosure
• environmental conditions that need to be provided for battery to safeguard optimal battery
performance over time
• maintenance costs related to a particular battery type, for example a lithium-ion battery, is
likely to require less maintenance than a lead acid battery
• safety precautions including fire risk and other hazards associated with the battery
chemistry
• ventilation provisions and the like
All batteries shall be accommodated, installed and maintained in compliance with the following,
as relevant:
• section 3 and section 4 of AS 2676.1-1992 Guide to the installation, maintenance, testing
and replacement of secondary batteries in buildings - Part 1: Vented cells
• section 3 and section 4 of AS 2676.2-1992 Guide to the installation, maintenance, testing
and replacement of secondary batteries in buildings - Part 2: Sealed cells
• AS 3011.1 Electrical installations - Secondary batteries installed in buildings – Part 1:
Vented cells
• AS 3011.2 Electrical installations - Secondary batteries installed in buildings - Part 2:
Sealed cells
• section 7 and section 8 of AS/NZS 4509.1:2009 R2017 Stand-alone power systems. Part
1: Safety and installation
• section 4.6 of AS/NZS 4509.2:2010 R2017 Stand-alone power systems. Part 2: System
design
• AS 4086.1 Secondary batteries for use with stand-alone power systems - Part 1: General
requirements
© State of NSW through Transport for NSW 2019 Page 28 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
• AS 4086.2 Secondary batteries for use with stand-alone power systems - Part 2:
Installation and maintenance
• AS IEC 62619:2017 Secondary cells and batteries containing alkaline or other non-acid
electrolytes - Safety requirements for secondary lithium cells and batteries, for use in
industrial applications
The design and installation of room ventilation, airconditioning, lighting and power provisions
shall take into account battery chemistry as explosive gasses may be present inside the room.
Batteries shall be separated from the remainder of the building with construction complying with
the National Construction Code, volume one. The fire resistance level (FRL) may have to be
increased if determined by the risk assessment of site-specific safety requirements.
Carbon dioxide or ABC powder type portable fire extinguishers shall be provided next to the
battery room entry door. Additional fire detection and fire protection measures commensurate
with the risks related to specific battery type and size shall be implemented.
6.16. Emergency procedures Safety requirements in AS/NZS 5033 and the CEC Battery Install Guidelines for Accredited
Installers shall be complied with.
System isolating switches shall be easily accessible at all times by the operator and maintainer
staff and emergency services. A copy of the shutdown procedure shall be displayed on the fire
indicator panel and in the fire control room, beside the PVS inverter, at the PVS connection
point to the network and the DSMSB.
6.17. Environmental conditions Environmental conditions in rooms housing inverters or battery storage shall comply with the
equipment manufacturer's recommendations. Emergency escape lighting shall be provided in
inverter rooms, battery storage rooms and in all locations where PVS mandatory on and off
switches are housed.
6.18. Heritage The use of PVSs within heritage precincts is generally discouraged due to the likelihood of
increased technical complexity and increased cost of installing a system, given the need to
consider adverse visual impacts and undesirable impacts to heritage fabric from system
elements.
Where a PVS is proposed within a heritage precinct, it shall be located on structures with no
identified heritage significance. For further information on heritage listed assets, refer to the
RailCorp Section 170 Heritage and Conservation Register.
© State of NSW through Transport for NSW 2019 Page 29 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
Heritage impacts of a PVS installation shall be adequately assessed by a competent heritage
professional and an application for works submitted, as required, in accordance with the NSW
Heritage Act 1977.
Where PVSs are required to be located on or adjacent to heritage structures, detailed design of
the proposed installation shall be undertaken by a competent heritage professional who is a
registered architect. The design shall not compromise significant heritage fabric, shall mitigate
any visual impact in consideration of the bulk, scale and reflectivity of the product and fixings,
and shall not conceal or damage heritage fabric or building fabric. Any fixings to heritage fabric
shall be reversible.
6.19. Evaluation methodology Evaluation of project feasibility shall be based on the considerations described in Section 6.2 to
Section 6.18 resulting in project-specific conceptual proposals detailed enough to facilitate life
cycle costing and cost benefit evaluation of various available options. The evaluation results will
inform the decision to proceed or not with the project.
The methodology and key feasibility assessment elements are shown in Appendix A. In
addition, the following shall be included in PVS feasibility evaluation:
• Integration with electrical installation including the need for installation upgrades, for
example, distribution board, meter or cabling. Any other work that may be required,
including provision of safe access, fences, walkways and so on.
• Costs of technical and regulatory compliance, including cost of professional services for
example, architectural and engineering services should be included in overall
considerations.
• Costs of the grid-connection process and costs of equipment that will be needed in order to
connect to installations powered from an LDNSP grid.
• Market availability of equipment of adequate efficiency, quality and reliability such as PV
panel, batteries, inverters, control and monitoring equipment.
• Operation, maintenance, servicing and any other costs.
• PVS life cycle costing assessment. For further guidance refer to T MU AM 01001 ST Life
Cycle Costing.
© State of NSW through Transport for NSW 2019 Page 30 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
The life cycle costing analysis shall be broadened by including consideration of revenues
(generated through LDNSP feed-in tariff) and cost savings (cost of energy generated by PVS
that would otherwise be derived from the RailCorp grid). The total energy generated by PVS
shall be compared to what would be spent with the current electricity provider during the same
period. The knowledge of relevant electrical energy tariffs is imperative to understanding the
costs and savings for the energy generated by the following PV systems:
• for systems connected to installations powered from an LDNSP grid, the PV energy
production should be calculated separately of the customer's installation energy
consumption to account for the difference between energy produced by the PV system and
consumed from the grid (net metering), refer to the relevant LDNSP for pricing details
• for systems connected to installations powered from the RailCorp grid, cost of energy
derived from RailCorp electrical network shall take into account peak 7am-9am and 5pm-
8pm on business days, shoulder 9am-5pm and 8pm-10pm on business days, and off-peak
(all times other than peak time and shoulder time) tariff; refer to the operator and
maintainer for pricing details
• estimate as to how will the energy tariffs change once a system is installed, as well as
informed assumptions on energy costs over the lifetime of the installation form part of the
evaluation
Non-financial considerations related to alignment with NSW Climate Change Policy Framework
should be taken into account where appropriate.
6.20. Further design stages Following project approval further design work is required to finalise all details of the system.
Depending on a procurement model, the final design may be carried out as a separate contract,
as a part of a design and build, or other arrangement. Final design of the PVS and network
connection details shall be approved by the EDU, who will consult with others as necessary.
6.21. Alteration to approved design The approved PVS design, settings of the protection devices and control equipment shall not be
modified without informing and receiving prior written authorisation from the EDU.
Upon receipt of a written request to modify the approved design or settings, the EDU will advise
if it is necessary for the requestor to undertake a new assessment of the PVS impact on the
RailCorp electrical network, the timeframe expected to complete a new network study and the
requirements for associated report.
© State of NSW through Transport for NSW 2019 Page 31 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
6.22. Critical review process Careful consideration is required to balance the life cycle cost with the requirements of high
quality, safety, reliability and maintainability of system components necessary to operate during
the life of the installation. The project initiator and relevant stakeholders shall review technical
and financial information to select the best option.
The final choice of system configuration and selection of particular equipment shall be
determined through a life cycle costing over a 25 year period (the design life of PV panels), with
considerations including, but not limited to, the following:
• fitness for purpose and technical correctness, based on requirements specified in this
standard
• quality and reliability of equipment used
• compliance with relevant law, regulations, standards and codes of practice
• capital costs, including all costs incurred from design inception to procurement, installation
and commissioning until handover to the operator and maintainer
• operation and maintenance costs of scheduled maintenance including periodic cleaning
and system inspection, an allowance for unscheduled maintenance and cost of disposal at
the end of system life
• renewable energy certificates that offset part of the system costs
• warranty conditions offered for major elements of the system and after sales service
agreements
• compliance with warranty requirements for the design, installation, environmental
conditions and any operational limitations
• any other relevant cost
7. PVS equipment High quality equipment from reputable manufacturers shall be used so that the likelihood of
manufacturer being able to attend to possible problems during the equipment life (for example,
25 years for PV panels) is maximised.
Only CEC approved manufacturers and equipment shall be used.
PVS equipment ingress protection (IP) rating shall be suitable for the prevailing environmental
conditions at the location. Externally mounted equipment IP rating shall be IP 65 or higher in
accordance with AS 60529 Degrees of protection provided by enclosures (IP Code). The IP
rating of individual components for example, PV panel junction boxes shall be increased where
necessary to ensure long term operation of equipment in the location.
© State of NSW through Transport for NSW 2019 Page 32 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
7.1. PV panels PV panels shall comply with AS/NZS 5033. All PV module applications shall comply with
IEC 61215-1 Ed. 1.0 (all parts) Terrestrial photovoltaic (PV) modules - Design qualification and
type approval as applicable, and IEC 61730-1 Ed. 2.0 Photovoltaic (PV) module safety
qualification - Part 1: Requirements for construction. The PV panels shall be selected from the
CEC's list of approved PV panels.
PV panels shall have a 0% (or 0W) negative power tolerance. Power tolerance is the actual
range a module can deviate from its maximum power specified under the standard test
conditions (that are laboratory conditions panels are tested under).
PV panels shall come with a minimum 25 year performance warranty assuring at least 80% of
nominal peak power output in the twenty-fifth year.
A minimum of 10 year product, workmanship, installation, and defects warranty is required.
7.2. Panel mounting system The PV panels mounting system shall comply with AS/NZS 1170.1 Structural design actions -
Part 1: Permanent, imposed and other actions and AS/NZS 1170.2 Structural design actions
Part 2: Wind actions and other relevant Australian standards. All system elements shall be
corrosion resistant and designed to withstand applicable static and dynamic (wind) loads. The
system design life shall match the design life of the panels (25 years). The installed panel
mounting system shall be guaranteed for a minimum of 10 years.
7.3. Inverters Solar PV inverters convert the dc electricity generated by PV panels into ac electricity.
Hybrid solar inverters (a multi-mode inverter) can simultaneously manage inputs from both PV
panels and a battery bank, including charging batteries with either PV panels or the electricity
from the grid (depending on which is more economical or preferred). They act as all-in-one
inverter solution for grid-connected solar-plus-storage systems.
Battery inverters manage the charging and discharging of a battery bank (converts dc electricity
into ac electricity, but also does the reverse – converting ac electricity to dc)
High quality inverters shall be used. The inverters shall be selected from the CEC's list of
approved inverters. A minimum 10 year performance warranty is required.
Inverters shall comply with AS/NZS 4777.2, IEC 62109-1 Ed.1.0 Safety of power converters for
use in photovoltaic power systems - Part 1: General requirements and IEC 62109-2 Ed. 1.0
Safety of power converters for use in photovoltaic power systems - Part 2: Particular
requirements for inverters.
Inverter installations shall comply with AS/NZS 4777.1:2016. © State of NSW through Transport for NSW 2019 Page 33 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
Single-phase or three-phase inverters can be used. Three phase installations can be served by
single phase inverters provided that the PV generation in different phases is balanced within
10% (+5% or -5%).
For three-phase inverters, all phases of an inverter shall simultaneously disconnect from or
connect to the network in response to protection or automatic controls (for example,
anti-islanding and subsequent reconnection).
For multiple phase installations where single phase inverters are used, the PVS designer shall
check and ensure that the disconnection or reconnection of an inverter in either one phase or
multiple phases is not going to create network conditions that are non-compliant with the
requirements of EP 90 10 00 02 SP.
Central inverters should be mounted indoors. Inverters shall not be installed in concealed
spaces and cavities. With the exception of electrical rooms, inverters shall not be collocated
with any equipment that is not part of the PVS installation. Inverters serving large installations
should be housed in dedicated rooms. Appropriate means to remove the waste heat generated
by the inverters shall be incorporated in the design.
Inverters mounted in external locations shall be designed to operate outdoors and shall be rated
IP65 or higher. Inverters shall be mounted so they are not exposed to direct sunlight or rain.
PV panel shading could be a consideration in determining the inverter type, as micro-inverters
which are usually installed on the back of PV panels, can help reduce losses related to partial
shading of a PV panel.
7.3.1. Inverter immunity to local supply harmonics The RailCorp LV network contains significant harmonic distortion due to the 6 pulse and
12 pulse traction rectifiers. Refer to EP 03 00 00 01 TI Rectifier Transformer & Rectifier
Characteristics for further information.
PVS inverters shall be equipped with controls that enable satisfactory operation over a variation
in network conditions. The PVS designer is responsible for ensuring that the PVS inverter is
compatible with the supply presented at each respective location and be suitable for full
integration with the power supply grid.
As part of the assurance process, the quality of power supply at each location should be
recorded before and after PVS connection using appropriate recording apparatus. The results
shall form part of the assurance documentation.
7.3.2. Power factor The PVS shall not degrade the installations power factor below 0.90.
Where necessary, inverters shall be equipped with reactive power control to produce both
active and reactive power, that is, an output that is at a non-unity power factor. © State of NSW through Transport for NSW 2019 Page 34 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
7.4. Batteries Storage batteries shall be selected from the list of CEC approved energy storage devices.
The following battery technologies are the most commonly used with PV systems:
• traditional lead-acid and nickel cadmium
• lithium (for example, lithium ion, lithium iron phosphate)
• flow (for example, zinc bromine, vanadium redox flow)
• hybrid ion (for example, aqueous)
The choice of technology can be affected by considerations of the following technical aspects:
• Power rating - the amount of electricity in kilowatts that a battery can deliver at one time.
• Prospective short circuit or fault current - the current during short circuit at the battery
terminals when overcurrent protection does not operate. The prospective short circuit or
fault current should be advised by the manufacturer, and overload protection provided to
match.
• Battery storage capacity - a measure of electrical energy in kWh that a battery can store.
As an example, a battery with a high capacity and a low power rating would be suitable for
delivering a low amount of electricity for a long time. A battery with a low capacity and a
high power rating would be suitable for delivering large amount of energy over a short time.
• Operational suitability - batteries used with PV systems should be able to be 80% charged
or 80% discharged within three hours (time corresponding to the period when highest
energy tariff applies).
• Battery round-trip efficiency - denotes the amount of energy stored as a percentage of the
amount of energy that it took to store it. Usually, a higher efficiency means more economic
value.
• Most batteries need to retain some charge due to their chemical composition. The depth of
discharge of a battery refers to the percentage of a battery’s capacity that can be used for
optimal performance without any danger of damaging the battery.
• Ambient temperature and battery operating temperature.
• Useful life - the battery’s ability to hold a charge will gradually decrease over time. The
minimum requirement is 10 years (with the minimum of 3650 cycles). The end of life
battery energy capacity shall be no less than 70% of a new battery design capacity.
• For some types of batteries, the installation of specific safety equipment, for example an
eyewash station, may be required.
© State of NSW through Transport for NSW 2019 Page 35 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
Batteries shall have a warranty that guarantees a specific number of years of useful life and
percentage of original capacity (ability to store energy) available at the end of the guarantee
period and the end of battery life.
Evaluation of the warranties shall be used as additional guidance for battery selection.
7.5. PVS management A PVS that is connected to the RailCorp electrical network shall be equipped with controls as
specified in Section 6.6.1 and Section 6.6.2 that enable satisfactory operation over a variety of
RailCorp electrical network-specific conditions.
7.5.1. PV generation management
PV panels need to be managed by dedicated intelligent controls to optimise panel operation and
achieve as high a power conversion efficiency as possible. The controls shall ensure fast
tracking of the irradiation changes and operation of the PV panels at the maximum power point
(MPP) to optimise energy production. The controls shall monitor energy flows, performance of
major system components and detect malfunctions within the PVS.
The generated output current of the inverter shall be in phase with the utility (RailCorp or
LDNSP) grid voltage. Anti-islanding protection shall immediately shut down the inverter
preventing it from generating ac power when electrical grid power is no longer present.
Energy metering shall measure the total energy production of a PVS and accumulate energy
units in both directions in real-time.
7.5.2. Battery management Battery storage supervisory controls shall ensure optimised energy management, manage the
battery charge controllers and monitor battery charge and discharge profiles. The topology,
configuration and capabilities of a battery management system are dictated by the battery type,
chemistry and battery application.
Battery management systems shall aim at damage prevention and increase of battery life while
balancing battery electrical and thermal management to achieve safe operation while
maintaining the battery in an accurate and reliable state. Measuring, data gathering, calculation,
analysis, intelligent appraisal and resultant action, and means of communication shall be
combined to form a modern battery management system.
7.5.3. Building management and control systems In locations where a building management and control system (BMCS) is available, PVS
controls should be integrated through an agreed interface to the BMCS for remote
management, fault indication, energy readings and other agreed performance data.
© State of NSW through Transport for NSW 2019 Page 36 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
Appropriate performance parameters shall be selected, with data from the PV panels and
inverter and battery storage retrieved and processed in real time. Loss of performance shall
generate agreed alarms.
7.6. Wiring and protection Wiring and protection shall comply with AS/NZS 3000 and T HR SS 80002 ST.
PVS wiring shall be accommodated in a separate containment not shared by any other wiring.
Collocation of AC and DC wiring in the same enclosure is not permitted.
External dc wiring shall be ultra violet (UV) protected. In addition, external wiring containment
and its mounting shall safeguard the wiring against the heat from exposure to sun and elevated
temperatures of various building elements (predominantly roofs).
The wiring shall meet the requirements of AS/NZS 3008.1.1 Electrical installations - Selection of
cables – Part 1.1 Cables for alternating voltages up to and including 0.6/1 kV - Typical
Australian installation conditions and Service and Installation Rules of New South Wales, with
specific attention to Section 8.6.
7.7. Labelling Clear labelling and fire services information, including the shutdown procedure, and directions
to the PV panels disconnect devices, inverters and battery storage location shall be provisioned
for emergency services in accordance with section 8.7 of Service and Installation Rules of New
South Wales, section 6 of AS/NZS 4777.1:2016, section 5 of AS/NZS 5033:2014 and Battery
Install Guidelines for Accredited Installers.
Compliance with T HR SS 80002 ST is also required.
The DSMSB shall be labelled with an engraved traffolyte label which reads ‘PVS installed at
<insert location>. The PVS must be shut down and isolated prior to working on this
switchboard’.
Additional labelling requirements may be necessary in complex or unusual installations.
7.8. Documentation PVS isolation procedure shall be provided at the DSMSB to provide specific guidance on the
PVS shutdown procedure to electrical staff.
An operator manual is to be provided for each installation with a hard copy installed in a suitable
holder at the IMSB and inverter location. The operator manual is to contain the information
required in section 5.7 of AS 5033:2014.
© State of NSW through Transport for NSW 2019 Page 37 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
8. Installation, testing and commissioning Installation shall be carried out in accordance with Clean Energy Council Install and Supervise
Guidelines for Accredited Installers and Battery Install Guidelines for Accredited Installers.
PVS testing and commissioning shall be carried out as described in Appendix D of
AS/NZS 5033:2014. All work shall be performed by CEC accredited installers in accordance –
Clean Energy Council Install and Supervise Guidelines for Accredited Installers. For systems
with battery storage, the requirements of the Battery Install Guidelines for Accredited Installers
shall also be followed. Testing of the PVS installation shall be in accordance with
AS/NZS 30177 Electrical installations - Verification guidelines.
A testing and commissioning plan including test plans, test methods, detailed test procedures
and protection settings shall be developed for approval of the operator and maintainer at least
three weeks prior to the testing and commissioning taking place.
Prior to the connection of the PVS to the RailCorp electrical network, the EDU will conduct a
mandatory inspection.
An EDU representative shall inspect those parts of the PVS that have an effect on the network
operation, witness the export prevention operation and any other tests as deemed necessary.
On satisfactory completion, the EDU shall approve the installation for connection to the network.
Hard and soft copies, as applicable, of commissioning tests results shall be submitted to
operator maintainer as part of the handover process.
8.1. Performance monitoring To optimise PVS operation management, performance of each system over time shall be
monitored and evaluated periodically with the aid of technical maintenance plans (TMPs).
Remedial action shall be taken when the efficiency of a PVS drops below the calculated
efficiency level expected at the point in time when the evaluation is conducted.
Performance shall be recoded and feedback in the form of an annual report shall be provided
for future reference.
Enhanced monitoring and reporting is required for PVSs with battery storage to facilitate
relevant information on battery storage performance and annualised economic efficiency of the
system.
8.2. Periodic maintenance All maintenance activities shall be recoded. All protection, control systems and equipment
associated with the PVS and its connection to the network shall be periodically tested, in
accordance with an agreed Technical Maintenance Plan developed in accordance with
T MU AM 01008 ST Technical Maintenance Plans and Coding System, to demonstrate correct © State of NSW through Transport for NSW 2019 Page 38 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
operation. The record of all such tests shall be provided to the operator and maintainer with a
certified copy of the test results.
Failure to comply with the testing requirements may result in the operator and maintainer
disconnecting the PVS from the network.
8.3. Decommissioning and disposal At the end of life, all equipment and materials that form a PVS shall not be placed in landfill but
recovered and dispatched to relevant specialist recycling plant. The cost of doing so shall be
included in PVS life cycle calculations.
9. Assurance The PVS assurance process shall comply with the requirements of T HR SS 80002 ST Low
Voltage Electrical Installations.
© State of NSW through Transport for NSW 2019 Page 39 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
Appendix A Feasibility study and evaluation methodology guide for PVS installations
Selection of a suitable facility or site where a PVS is to be deployed shall follow the
requirements specified in Section 6 and Section 7. Site specific concerns such as the
geographical orientation and roof inclination of the structures that accommodate PVS
installations have large impact on the ability of a PVS to generate power. The sites that offer the
best yield should be considered as a priority.
Following the requirements specified in Section 6.19, the methodology to be used in the
process shall include the following:
• Establishing the renewable energy target which amounts to matching the PVS size to the
energy requirements (power demand) of the installation and includes an evaluation of how
well the expected PV generation profile (given the number, size, orientation and tilt of PV
panels) matches the installation power demand profile, enabling an estimate of expected
self-consumption of the generated PV energy, and available PV energy surplus (if any).
• Establishing that technical requirements of the proposed PVS installation can be
adequately supported, including roof space and suitability (geographical orientation,
structural fitness), evaluation of what would be the largest solar PVS that could be
installed, and availability of adequate space to accommodate other system components
such as inverters, battery (if used), and so on.
Ability to export to grid can have a major impact on PVS design and cost. If export is not
permitted, in some atypical cases an inclusion of battery storage could be an option.
Figure 3 describes the minimum requirements that shall be addressed.
© State of NSW through Transport for NSW 2019 Page 40 of 41
T HR SS 80006 ST Renewable Energy Installations - Photovoltaic and Battery Systems
Version 1.0 Issue date: 09 April 2019
Estimate PVS peak power and energy kWh generatable by panels in selected location, orientation and tilt during an average summer and winter day
Are the installation energy usage & maximum demand calculations or records available?
Perform relevant calculations or install monitoring equipment over a sufficiently long period to properly
estimate energy usage patterns
No
Determine installation maximum demand (kW) & anticipated energy (kWh) use during peak, shoulder and off-peak times1 During daytime hours (when PVS-generated energy can be used directly)2 Outside daytime hours (unless stored in batteries, PVS-generated energy cannot be used during that period)
Is the installation able to useall generated energy?
No export to grid or battery storage
No Yes
Downsize PVS or export to LDNSP
RailCorp
LDNSP
Is battery storage economically feasible? Yes
Is there other justification? (the installation
will operate at a loss)
No
Yes
Yes
PVS design
Start
Determine orientation and inclination (tilt) of the roof proposed for the accommodation of PV panels. Determine the maximum size & number of PV panels that can be accommodated as set out in Section 6
Is batterystorage
an option?
Downsize thePV system
No
Yes
Abandon process
No
PV panels are able togenerate more energy than the
installation could consumeduring daylight hours
Is export toRailCorp
permitted?
No
Yes
© State of NSW through Transport for NSW 2019 Page 41 of 41
Figure 3 - PVS evaluation methodology