T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning … · 2019. 9....
Transcript of T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning … · 2019. 9....
Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
T HR SC 07111 ST
Standard
Version 1.0
Issue date: 04 September 2019
© State of NSW through Transport for NSW 2019
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Important message This document is one of a set of standards developed solely and specifically for use on
Transport Assets (as defined in the Asset Standards Authority Charter). It is not suitable for any
other purpose.
The copyright and any other intellectual property in this document will at all times remain the
property of the State of New South Wales (Transport for NSW).
You must not use or adapt this document or rely upon it in any way unless you are providing
products or services to a NSW Government agency and that agency has expressly authorised
you in writing to do so. If this document forms part of a contract with, or is a condition of
approval by a NSW Government agency, use of the document is subject to the terms of the
contract or approval. To be clear, the content of this document is not licensed under any
Creative Commons Licence.
This document may contain third party material. The inclusion of third party material is for
illustrative purposes only and does not represent an endorsement by NSW Government of any
third party product or service.
If you use this document or rely upon it without authorisation under these terms, the State of
New South Wales (including Transport for NSW) and its personnel does not accept any liability
to you or any other person for any loss, damage, costs and expenses that you or anyone else
may suffer or incur from your use and reliance on the content contained in this document. Users
should exercise their own skill and care in the use of the document.
This document may not be current and is uncontrolled when printed or downloaded. Standards
may be accessed from the Transport for NSW website at www.transport.nsw.gov.au
For queries regarding this document, please email the ASA at [email protected] or visit www.transport.nsw.gov.au © State of NSW through Transport for NSW 2019
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Standard governance
Owner: Lead Signals and Control Systems Engineer, Asset Standards Authority
Authoriser: Chief Engineer, Asset Standards Authority
Approver: Executive Director, Asset Standards Authority on behalf of the ASA Configuration Control Board
Document history
Version Summary of changes
1.0 First issue.
© State of NSW through Transport for NSW 2019 Page 3 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Preface
The Asset Standards Authority (ASA) is a key strategic branch of Transport for NSW (TfNSW).
As the network design and standards authority for NSW Transport Assets, as specified in the
ASA Charter, the ASA identifies, selects, develops, publishes, maintains and controls a suite of
requirements documents on behalf of TfNSW, the asset owner.
The ASA deploys TfNSW requirements for asset and safety assurance by creating and
managing TfNSW's governance models, documents and processes. To achieve this, the ASA
focuses on four primary tasks:
• publishing and managing TfNSW's process and requirements documents including TfNSW
plans, standards, manuals and guides
• deploying TfNSW's Authorised Engineering Organisation (AEO) framework
• continuously improving TfNSW’s Asset Management Framework
• collaborating with the Transport cluster and industry through open engagement
The AEO framework authorises engineering organisations to supply and provide asset related
products and services to TfNSW. It works to assure the safety, quality and fitness for purpose of
those products and services over the asset's whole-of-life. AEOs are expected to demonstrate
how they have applied the requirements of ASA documents, including TfNSW plans, standards
and guides, when delivering assets and related services for TfNSW.
Compliance with ASA requirements by itself is not sufficient to ensure satisfactory outcomes for
NSW Transport Assets. The ASA expects that professional judgement be used by competent
personnel when using ASA requirements to produce those outcomes.
About this document
This standard has been developed from the RailCorp standard SPG 0711.1 Roles,
Responsibilities and Authorities, version 1.8 and SPG 0711.6 Interface Requirements and
Procedures for Alternations, version 1.4. The contents encompass and contemporise such
essential components.
This document covers the requirements for AEO documentation (supporting their assurance
provision), ensuring quality of work, preserving signalling integrity, authority to work, roles and
responsibilities, interface coordination and competency.
This document supersedes SPG 0711.1 in full and partially supersedes SPG 0711.6.
This standard is a first issue.
© State of NSW through Transport for NSW 2019 Page 4 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Table of contents 1. Introduction .............................................................................................................................................. 7
2. Purpose .................................................................................................................................................... 7 2.1. Scope ..................................................................................................................................................... 8 2.2. Application ............................................................................................................................................. 8
3. Reference documents ............................................................................................................................. 9
4. Terms and definitions ........................................................................................................................... 10
5. AEO inspection, testing and commissioning documentation .......................................................... 12
6. Ensuring quality production, installation and integration of new or altered signalling ................ 13 6.1. Use of existing or spare equipment ..................................................................................................... 14 6.2. Stage work ........................................................................................................................................... 14 6.3. Wire crimpers and other specialised tools ........................................................................................... 15
7. Preserving the integrity of the existing signalling system ............................................................... 16 7.1. Work done on or near operating lines ................................................................................................. 16 7.2. Impacts caused by the work ................................................................................................................ 17 7.3. Disconnection of out of use equipment ............................................................................................... 17 7.4. Installed trackside equipment pending commissioning or removal ..................................................... 18 7.5. Special precautions for newly installed wires run within existing equipment and circuits ................... 18 7.6. Temporary wiring and equipment ........................................................................................................ 20 7.7. Security of signalling equipment and housings ................................................................................... 22 7.8. Risk mitigation strategy ........................................................................................................................ 23
8. Authority to work ................................................................................................................................... 24 8.1. Signalling permit to work ...................................................................................................................... 24 8.2. Working on operational signalling or applying signalling safeworking ................................................ 25 8.3. Working within operational signalling environments ............................................................................ 26 8.4. Non-operational signalling environments ............................................................................................ 28
9. Appointment of commissioning engineer .......................................................................................... 29
10. Engineering design authority ............................................................................................................... 30
11. Interface coordination ........................................................................................................................... 31 11.1. Interface coordination plan .............................................................................................................. 32 11.2. Coordination of multiple signalling projects ..................................................................................... 35 11.3. Decommissioning and disposal of redundant equipment ................................................................ 36
12. Roles and responsibilities of RIMs ...................................................................................................... 37 12.1. Project delivery RIM and commissioning AEO responsibilities ....................................................... 37 12.2. Operator and maintainer RIM responsibilities ................................................................................. 39
13. Roles and responsibilities of duty holders ......................................................................................... 42 13.1. Allocation of roles ............................................................................................................................ 42 13.2. Common responsibilities .................................................................................................................. 43 13.3. Commissioning engineer responsibilities ........................................................................................ 44 13.4. Signalling tester in-charge responsibilities ...................................................................................... 45 © State of NSW through Transport for NSW 2019 Page 5 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
13.5. Signalling system certifier responsibilities ....................................................................................... 48 13.6. Signalling subsystem certifier responsibilities ................................................................................. 49 13.7. Apparatus certifier responsibilities ................................................................................................... 50 13.8. Structural and ancillary certifier responsibilities............................................................................... 51 13.9. Signalling test assistant responsibilities .......................................................................................... 52 13.10. Licensed signalling personnel responsibilities ................................................................................. 53
14. Mapping duty holder roles to critical signalling functions ............................................................... 54 14.1. Specific functions for duty holders holding limited competencies ................................................... 61 14.2. Multiple roles .................................................................................................................................... 61 14.3. Independence of inspection and testing personnel ......................................................................... 62
15. Competency requirements ................................................................................................................... 62 15.1. Assessment of duty holders............................................................................................................. 63 15.2. Duty holder performance history ..................................................................................................... 64 15.3. Assessment pathways for attaining roles in critical signalling functions ......................................... 64
© State of NSW through Transport for NSW 2019 Page 6 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
1. Introduction The necessities for standards that pertain to the critical signalling functions relating to
inspection, testing and commissioning of new or altered signalling have emanated from the
outcomes of undesirable historical events. Such events included collisions, derailments and
near misses; many of which caused death and injury, property damage and loss, commuter
disruption, financial loss, reputational damage, as well as a lack of public confidence in the
transport system.
The reoccurrence of such events, particularly where deficiencies in signalling integration were
causal, can be vastly reduced or prevented when the critical signalling functions of inspection,
testing and commissioning are properly planned and executed using coherent and consistent
processes. Such processes would identify, control and mitigate all associated risk (so far as is
reasonably practical), so as to achieve a safe and desirable outcome. Equally important is the
selection of competent and proficient personnel who undertake such work, and that each
person involved clearly understands the requirements of their role and the responsibility they
hold for each task.
This series of standards has been developed from the knowledge and experience of learned
signal engineers, and from the lessons learnt of previous incidents (including those abroad)
stemming back many years. It prescribes the key responsibilities, principles, objectives,
requirements and guidance to ensure installations conform to intended designs as well as to
agreed functional and engineering requirements.
Additionally, this series of standards outline requirements that aim to preserve the integrity of
the existing operational system during the delivery of such work.
2. Purpose This series of standards set out the framework and high level requirements for rail infrastructure
managers (RIMs), Authorised Engineering Organisations (AEOs) and signalling personnel
involved with the critical signalling functions relating to inspection, testing and commissioning of
new or altered signalling work.
Mandatory requirements are stipulated for planning, controlling, monitoring and recording of the
aforementioned critical signalling functions, including the associated pre-requisite activities and
subsequent handover. It is intended that these requirements form the basis of the
commissioning AEO’s documentation relating to such activities.
The roles, responsibilities and competency requirements of signalling personnel who perform
critical signalling functions are outlined to enable a consistent approach across all signalling
commissionings.
© State of NSW through Transport for NSW 2019 Page 7 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
2.1. Scope This document contains the requirements for ensuring a quality installation, preservation of the
existing signalling system, engineering design authority, appointment of commissioning
engineer, roles and responsibilities, interface coordination, and competency and independence
requirements for work relating to inspection, testing and commissioning of new or altered
signalling.
This document pertains to signalling commissionings which also covers any decommissioning of
signalling and subsequent removal of associated redundant equipment. The requirements for
decommissioning shall be accordingly applied in the same context as commissioning.
This document does not cover non-signalling matters, such as work health and safety, worksite
protection or project management. This document also does not cover matters relating to
business or commercial requirements.
2.2. Application This document applies to the signalling systems (inclusive of associated subsystems and
apparatus) within the heavy rail network as governed by TfNSW.
Signalling referred to in this document includes all the various generational signalling
applications used in heavy rail, from traditional mechanical signalling through to modern
computer-based systems. The term signalling, as used in this document incorporates signalling
controls and indications, signalling interlockings, trackside signalling apparatus (including active
level crossing protection), signalling power and air supplies, signalling equipment housings, as
well as all connecting cables, hoses and operations critical data networks and other
communication systems used for signalling.
This document also pertains to the peripheral technological domain of signalling, such as
computerised train control and traffic management systems, any signalling infrastructure used
to support automatic train protection (ATP) and automatic selective door operation (ASDO), and
so on. It also refers to any future applications of signalling as they arise over time.
This document shall be read in conjunction with AS 7716 Signalling Testing Process, and
AS 7717 Signal Testing & Commissioning, as applicable. While this document generally
complements the Australian standards, it shall take precedence over requirements where
conflict exists, especially where this document applies a more stringent requirement.
This document shall also be read in conjunction with the operator and maintainer RIM signalling
safeworking procedures, as applicable. In all cases, the intent of this document shall remain
valid.
© State of NSW through Transport for NSW 2019 Page 8 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
3. Reference documents The following documents are cited in the text. For dated references, only the cited edition
applies. For undated references, the latest edition of the referenced document applies.
Australian standards
AS 4292.1 Railway safety management - Part 1: General requirements
AS 4292.4 Railway safety management - Part 4: Signalling and telecommunications systems
and equipment
AS 7716 Signalling Testing Process
AS 7717 Signal Testing & Commissioning
Note: AS 7716 and AS 7717 are published and maintained by RISSB.
Transport for NSW standards
ESG 100 Signal Design Principles
SPG 0703 Signalling Documentation and Drawings
SPG 0706 Installation of Trackside Equipment
SPG 0707 Installation of Equipment Racks and Termination of Cables and Wiring
T HR CY 03000 ST Competency Standard – Signalling
T HR SC 02000 ST Mandatory Requirements for Signalling Safeworking Procedures
T MU CY 10503 GU AEO Guide to Engineering Competence Management
Legislation
Rail Safety National Law (NSW)
Other reference documents
Australian Quality Training Framework
Australian Qualifications Framework
Signalling Safeworking Procedures (operator and maintainer RIM)
Network Rules and Network Procedures (operator and maintainer RIM)
© State of NSW through Transport for NSW 2019 Page 9 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
4. Terms and definitions The following terms and definitions apply in this document:
AEO Authorised Engineering Organisation
ASA Asset Standards Authority
ASDO automatic selective door operation
ATP automatic train protection
CBI computer based interlocking
certification of signalling (for the purpose of this document) the sign-off of signalling systems,
associated subsystems and apparatus (as applicable) by signalling personnel, attesting to its
correct operation following satisfactory testing in accordance with the relevant requirements, for
the purpose of booking the signalling into operational use
interlocking an electrical, electronic or mechanical means of making the operation of one piece
of apparatus dependent upon certain predetermined conditions being fulfilled by other
apparatus - the logic by which routes that conflict are prevented from being set at the same time
like for like renewal the renewal or temporary removal and subsequent reinstatement of
signalling equipment that can be performed without a signalling design authority
new or altered signalling new, additional or removed signalling, or a change of design or
configuration to the existing signalling system that is not considered like for like
RIM rail infrastructure manager, in relation to rail infrastructure of a railway, means the person
who has effective control and management of the rail infrastructure, whether or not the person -
(a) owns the rail infrastructure; or
(b) has a statutory or contractual right to use the rail infrastructure or to control, or provide,
access to it
responsible signal engineer (for the purpose of this document) a licensed signal engineer
(field) who acts in the interest of the operator and maintainer RIM for the continuous integrity of
signalling infrastructure within an assigned area of accountability (for example, a maintenance
signal engineer, asset signal engineer or similar)
operator and maintainer RIM (for the purpose of this document) the rail infrastructure manager
having effective control and management for the operation and maintenance of railway
infrastructure, applicable to their network
project delivery RIM (for the purpose of this document) the rail infrastructure manager having
effective control and management to deliver new or altered railway infrastructure
© State of NSW through Transport for NSW 2019 Page 10 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
signalling the signalling system that incorporates all of its subsystems and apparatus
associated with the engineered means for signalling the safe passage of rail vehicles as well as
the safe movements of users at level crossings (where fitted with active protection)
signalling authorisation an authority issued by the operator and maintainer RIM to personnel
required to perform specific work within an operational signalling environment (see Section 8.3
for further information)
signalling commissioning (for the purpose of this document) the period of time when the work
of new or altered signalling has reached the stage of certification and is formally brought into
use (or decommissioned), whether in its entirety or in stages
signalling commissioning AEO (referred in this document as commissioning AEO) the
authorised engineering organisation engaged by TfNSW to provide assurance for signalling
commissioning activities for the integration of new or altered signalling
signalling commissioning engineer (referred in this document as commissioning engineer) a
licensed signal engineer (field) who acts in the interest of TfNSW and relevant rail infrastructure
managers, to bring into use new or altered, safe and reliable signalling systems (see
Section 13.3 for further information)
signalling design AEO (referred in this document as design AEO) the authorised engineering
organisation engaged by TfNSW to provide assurance for the approved detailed signalling
design of new or altered signalling arrangements
signalling integrity the ability to sustain the signalling system's performance of safety and
reliability
signalling irregularity a failure of a signalling unit or its subsystem which is contrary to the
intended design requirement; is not fail-safe and which in combination with other failures or
circumstances can bring the system to an unsafe condition. Additionally, the definition of a
signalling irregularity is extended to items of signalling that are found with errors, where these
errors have the potential to falsely energise a vital relay or other vital function.
signalling licence an authority issued by the operator and maintainer RIM to signalling
personnel required to perform work on operational signalling and apply signalling safeworking
(see Section 8.2 for further information)
signalling permit to work a documented authority issued to signalling personnel by the
operator and maintainer RIM to enable work within an operating signalling environment
(including signalling commissioning)
signalling personnel (for the purpose of this document) persons who carry-out signalling work
signalling safeworking procedures the operator and maintainer RIM's document pertaining to
their domain signalling safeworking
TfNSW Transport for New South Wales
© State of NSW through Transport for NSW 2019 Page 11 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
5. AEO inspection, testing and commissioning documentation The commissioning AEO, engaged by TfNSW to assure the integration of new or altered
signalling shall provide suitable documentation that supports the assurance.
The requirements of this document shall be incorporated in documents administered by
commissioning AEOs in support of their assurance deliverables for inspection, testing and
commissioning when performing such work.
The commissioning AEO documentation shall specifically relate to the critical signalling
functions of inspection, testing and commissioning and comply with the requirements of this
document.
The documentation along with the commissioning AEO's processes shall form the basis of
certification, such that it attests the installation, as commissioned by them is in accordance with
the following:
• approved specific design and agreed functional requirements
• applicable engineering standards and codes, including ASA requirements and signalling
principles
• project delivery RIM requirements
• operator and maintainer RIM requirements
The documentation shall support elements of quality and safety for the work they assure
including the existing signalling system affected by the work. The extent of documentation shall
be commensurate with the complexity and scope of the signalling work.
Effective monitoring shall be deployed to ensure the work is done in accordance with such
documentation.
The following list provides examples of documentation that supports elements of quality and
safety assurance for new or altered signalling:
• installation planning, strategies and processes
• inspection and testing planning, strategies and processes
• commissioning planning, strategies and processes
• interface and stakeholder coordination planning, strategies and processes
• signalling safeworking and network operational planning, strategies and processes
• installation and commissioning work packages for major works
• commissioning work packages for minor or intermediary works
© State of NSW through Transport for NSW 2019 Page 12 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
• inspection and test forms, records and certificates
• handover requirements processes and documentation
• management of signalling design documentation (circuit books, signalling plans, and so on)
and data management processes (control tables, installed data sheets, and so on)
• management of any training, and spare equipment holding
6. Ensuring quality production, installation and integration of new or altered signalling The quality system of the commissioning AEO, as mandated by the AEO framework, shall
incorporate controls that initiate sound and effective practices so as to achieve quality
production, installation and integration of the new or altered signalling. The outcomes of these
controls shall aim to ensure that the new or altered signalling is built in accordance with relevant
standards, codes, requirements, its specific design and agreed functional requirements.
The following list provides the minimum requirements that shall be applied to achieve the
desired level of quality expected of new or altered signalling works:
• ensuring the signal design process applied to the production of specific designs for the new
or altered arrangements is in accordance with ASA signalling principles, signal design
requirements and agreed functional requirements
• ensuring the new or altered design correctly reflects the existing 'as-built' signalling
installation
• ensuring the work of installation and commissioning proceeds only pursuant of an
'approved for construction' signalling design issued by the engaged design AEO
• ensuring the work of installation and commissioning proceeds in accordance with the
commissioning AEO documentation and processes referenced in Section 5
• ensuring personnel who are tasked with critical signalling functions such as design,
installation, verification, validation, certification, signalling safeworking and integration are
competent and proficient for the work they undertake, and where necessary are licensed or
authorised by the operator and maintainer RIM
• ensuring personnel have a clear understanding of their responsibilities and requirements
for allocated work, particularly for the critical signalling functions they intend to perform
• ensuring effective interface coordination, strategic planning and systematic implementation
are in place to mitigate any risk exposure to existing infrastructure and railway operations
• ensuring compliance with relevant installation standards and requirements
© State of NSW through Transport for NSW 2019 Page 13 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
• ensuring the usage of signalling equipment, tools and test equipment meets type approval
requirements, as applicable
• ensuring any modifications applied use the same rigorous processes as were used for the
initial installation and for inspection, testing and commissioning
• ensuring compliance with the requirements stated in Section 7.5 for security of wiring at
interface locations, as applicable
• ensuring appropriate independence of personnel working on installation versus the
inspection, testing and certification components
• ensuring verification and validation methods are strategically planned, documented,
resourced, monitored, recorded and completely fulfilled to prove the new or altered
signalling is built in accordance with approved signalling designs, signalling principles and
agreed functional requirements
• ensuring effective verification and validation proves the work has changed the existing
signalling system only to the extent defined by the design
6.1. Use of existing or spare equipment Any use of existing or spare equipment shall be in accordance with the approved signal design
for the new or altered work; any deviation shall be agreed by the relevant stakeholders and
documented in the interface coordination plan or work package, as relevant.
Spare, existing or redundant wires, cable cores, contacts, and other items of equipment to be
used or reused shall first be inspected and tested to ensure the following requirements are
satisfied:
• they are spare without any connection at any point with other conductors, contacts, power
supplies, or other equipment
• they are properly insulated without any leak (or potential leak) of current to its frame,
sheath, other cores, earth or other circuits
• their condition complies with the required standard
Special attention shall be given to ensure that terminals are not connected together by jumper
bars (bussing) or other bridging.
6.2. Stage work Wiring and equipment to be commissioned or de-commissioned in stages shall be clearly
labelled to identify the stage level it is representing. On changeover, the stage labelling shall be
removed, the correct labelling applied and the arrangements made permanent.
© State of NSW through Transport for NSW 2019 Page 14 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
The stage work in progress at a signalling location shall be clearly posted in the associated
signalling housing.
The following list provides examples of inclusions in such posting:
• distinguishing colour of adhesive tape used on wiring and equipment
• stage level represented and date of staged-commissioning
• contact details of the responsible work team
Where a number of different work-stages are occurring at the same location, then the stage
work identification for each stage shall be of a different colour for ease of identification. The
commissioning engineer or signalling tester in-charge shall approve the colours.
Any temporary stage work wiring shall comply with the requirements stated in Section 7.6.
6.3. Wire crimpers and other specialised tools Wire crimpers used for signalling wiring shall be in accordance with SPG 0707 Installation of
Equipment Racks and Termination of Cables and Wiring.
Wire crimpers shall be subject to periodic calibration checks at the intervals specified in
SPG 0707. The results shall be recorded in the installation work package, for major work.
Similar requirements pertaining to other specialised tools having comparable critical
characteristics as wire crimpers shall apply. Such requirements can be specified by type
approval, manufacture’s manuals or guidelines, commissioning AEO processes or operator and
maintainer RIM stipulations. The required process shall be included in the commissioning
AEO’s documentation.
6.3.1. Test equipment Test equipment used to certify signalling, or (for any reason) on operational signalling shall
comply with the requirements stated in T HR SC 02000 ST Mandatory Requirements for
Signalling Safeworking Procedures.
The test equipment shall be fit for purpose and in good order. Where values are required to be
recorded for the purpose of certification, test instruments shall be calibrated and bear the
certificate of a recognised authority so as to attest their accuracy and precision.
© State of NSW through Transport for NSW 2019 Page 15 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
7. Preserving the integrity of the existing signalling system All work involving the installation and integration of new or altered signalling shall be done in a
manner that preserves the integrity of the existing signalling system at all times. This includes
work done at remote sites that can impact the operating network, such as at signalling control
centres.
Preserving the integrity of the existing signalling system is particularly relevant during signalling
installation, inspection, testing and commissioning works. Signalling can be subjected to
increased risk, especially where the work is done within operational environments. Personnel
shall be aware of the potential impact that their work can have on running lines and operating
equipment.
Interfaces with the existing signalling system require careful planning from the concept stage of
the project. The planning of design, work schedules, practices, inspections and testing shall aim
to minimise the day to day impacts to operating signalling apparatus. This is done to reduce
access requirements and risk exposure that can be caused by accidental damage or
interference.
New or altered works that interface with the existing signalling system shall only proceed
pursuant to effective interface planning and agreement with the operator and maintainer RIM
and other key stakeholders as applicable. The interface planning outcomes shall be
documented in the interface coordination plan. See Section 11 for further information on
interface coordination.
Prior to commencing interface work, the version of circuit books (including any associated
interim maintenance copy) and other relevant documentation used for correlation work, shall
reflect the as-built installation. Subsequently, an effective correlation of the affected portions
shall be done to verify its status, unless otherwise exempted (as noted in Section 7.8).
7.1. Work done on or near operating lines Work done on or near operating lines shall not cause disruption, ambiguity, or confusion for
train drivers, network operators, track workers or users of level crossings. The work shall not
endanger any railway operation.
Issues associated with signal ‘read-through’ and ‘read-across’ shall be taken into account when
new or altered signals are installed on or adjacent to operational lines.
© State of NSW through Transport for NSW 2019 Page 16 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
7.2. Impacts caused by the work Track circuits affected by the work (made seldom used), including those clear of the project
scope which are not used as a result of the project’s track possession, shall be tested and
assured to be capable of providing an effective track shunt prior to certifying the signalling back
into use. The commissioning engineer shall be accountable for this assurance.
Other impacts caused by the work, shall be taken into account. Impacts to third party operators,
such as electrical operation centres, traffic management centres, light rail operation control
centres, road traffic signals, passenger information systems, and the like shall be taken into
account. Impacts to these operators can include indications and inputs affected by the work.
Where installed signalling equipment pending commissioning or removal has the potential to
affect the safe and reliable operation of the railway, such as equipment (whole or part), which
remains in use, becomes in use, is taken out of use, is traversed upon, causes routing of trains,
infringes structure gauge, causes ambiguity and confusion, and so on, shall be scheduled for
maintenance to ensure the equipment's active components provide the necessary assurances
for safety and reliability. The maintenance scheduling of such components shall be done in
accordance with the requirements for safety critical and safety significant tasks, as stated in
T HR SC 02000 ST.
Tools and test equipment used on operational signalling shall comply with the requirements in
Section 6.3.
7.2.1. Using signalling controls
Signalling personnel, including testers shall not operate signalling controls for the purpose of
train running. Testing shall not interfere with the safe and correct operation of trains. In
particular, testing shall not result in the false clearing of signals or cause the movement of
points while they are still operating for trains. Further, no part of the vital signalling system (for
example, rail vehicle detection, active level crossing protection, route and point locking or
releasing, or other such vital control) shall be made to effect a less restrictive or unsafe state,
unless strict provisions are first implemented to protect the entire affected area in accordance
with signalling safeworking procedures.
7.3. Disconnection of out of use equipment Equipment taken out of use and disconnected from the interlocking shall be securely,
electrically isolated and labelled accordingly. It is not sufficient to only remove a fuse, open a
link or remove a signal lamp, and so on.
This requirement is to eliminate the risk of the disconnection being inadvertently reinstated,
resulting in a potentially unsafe situation. For this reason, the equipment shall be isolated in two
places where practical or other measures shall be applied to prevent inadvertent reinstatement. © State of NSW through Transport for NSW 2019 Page 17 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
7.4. Installed trackside equipment pending commissioning or removal Installed trackside equipment pending commissioning shall not be connected to the power
source except at commissioning or when required during testing, subject to testing processes
agreed by the operator and maintainer RIM. Busbar fuses and links, as well as links to external
equipment shall be reopened and secured immediately after testing is completed for the shift.
Newly installed signals and other trackside signalling equipment pending commissioning or
removal shall be made ‘out of use’ until commissioning (or decommissioning as applicable) in
accordance with SPG 0706 Installation of Trackside Equipment. The equipment shall be
disconnected, turned-off, covered, crossed, suppressed, secured, clipped and locked, and so
on, as relevant for the particular equipment and pertaining circumstances.
Installed points, not connected to the interlocking pending commissioning or removal shall
comply with the requirements stated in Section 100.14.16 Points of ESG 100 Signal Design
Principles.
Effective measures shall be employed to prevent new trackside equipment from being
inadvertently or improperly operated.
7.5. Special precautions for newly installed wires run within existing equipment and circuits All newly installed wires that run within existing signalling housings or trackside signalling
apparatus shall be effectively secured and insulated in a manner that prevents, in all
circumstances, any inadvertent electrical connection between the new wiring and the existing
equipment, circuits or metallic frames.
Any work on existing signalling equipment and circuits that involves booking out of use,
disconnection, disarrangement, disassembly, adjustment or alteration of the operating signalling
shall be performed in accordance with signalling safeworking procedures.
Note: References to existing signalling equipment and circuits include all
commissioned equipment and circuits whether in use or temporarily booked out of
use.
© State of NSW through Transport for NSW 2019 Page 18 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
7.5.1. Terminating and insulating wiring ends Newly installed wires shall only be terminated on existing signalling equipment such as spare
contacts of working relays or terminals of operating equipment, on meeting the following
conditions:
• the affected operating equipment is first booked out of use
• for relay terminations, the contact (point and armature) is vacant and voltage free, and
subjected to adequate testing processes
• for rack terminal terminations, the terminal is unused and voltage free, and is isolated from
the operating signalling system
The use of vacant contacts or terminals on existing signalling equipment and circuits shall be
confirmed to be isolated and voltage-free before terminating the new wiring.
Where newly installed wires are not immediately terminated, the following requirements apply:
• the wires shall be secured in a position at or as near as possible to the final connection
point
• the wires shall be clearly labelled to ensure that there is no possibility of mistaken
connection
• all unprepared wire ends shall be insulated by any of the following methods:
o crimped with blind-type insulated crimp connectors
o connected to insulated screw-type connectors
o by application of a suitable insulation tube securely fitted over the looped wire end and
extended sufficiently in order to prevent any possible metallic contact
• all prepared wire ends, such as crimp lugs, crimp pins, Q-type relay lugs, bootlace ferrules,
exposed single-strand wire ends, and the like, shall be wholly insulated by application of a
suitable insulation tube securely fitted over the exposed metallic portion and extended
sufficiently in order to prevent any possible metallic contact
The insulation effectiveness of wire ends shall be checked once applied. Where the wires
remain unterminated for an extended period of time, the checking of insulation effectiveness
shall be repeated at a frequency determined by risk assessment.
Adhesive insulating tape shall not be used directly on any prepared wire end, as the adhesive
residue can cause a high resistance connection. Adhesive tape may be used for other
purposes, such as for identification, wire wrapping, and so on; however, used tape shall not be
reused.
© State of NSW through Transport for NSW 2019 Page 19 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
7.5.2. Labelling of wires
To easily identify work in progress and the status of wiring at signalling housings and trackside
equipment, all newly run and proposed redundant wires shall be identified by distinctly different
colour-coded adhesive tape or other similar method. The identification shall be particularly
evident at the termination point. Care shall be taken to avoid colours already in use at the same
location (for example, other works in progress).
A legend of the distinct colours (or other methods) used shall be notably displayed inside the
associated signalling housing for reference by others.
Proposed redundant wiring shall be suitably labelled (by tagging, beading or other effective
means) to indicate the terminal to that it applied.
Note: Beading is used in association with a reference analysis.
Any wiring intended for temporary disconnection shall be suitably labelled to indicate its
disconnection status; for example, description of work, date of disconnection, and date of
reconnection and the terminal to that it applied.
New wiring intended for permanent installation shall be labelled in accordance with SPG 0707.
7.6. Temporary wiring and equipment Temporary wiring pertains to recent wiring run (by the project) that forms no part of the final
installation.
The following list provides typical examples of temporary wiring:
• wiring and equipment installed for the purpose of testing
• wiring and equipment installed as part of designed stage works, to facilitate an intermediate
configuration
• wiring and equipment installed as a designed interim arrangement, to enable continued rail
operations (such as installed trackside equipment pending full commissioning)
Temporary wiring and associated equipment shall comply with relevant Transport standards
including SPG 0707 and type approval (where applicable), so far as is reasonably practicable.
Where the application of standards in this context is not practicable, then the temporary work
shall be such that it does not compromise the safety and reliability of the operating signalling
system. The arrangement shall be first agreed by the operator and maintainer RIM.
The use and removal of temporary wiring and equipment shall be planned, controlled,
documented and subsequently fully tested prior to its activation, as if it were permanent.
Temporary wiring shall be of a unique, bright and distinct colour, and along with temporary
equipment shall be easily identifiable to indicate its temporary nature and purpose, including
any stage level as required. © State of NSW through Transport for NSW 2019 Page 20 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Additionally, temporary wiring shall be suitably labelled by tagging, beading or other effective
means at the point of connection to indicate its purpose, status (such as stage date) and
associated termination point.
Note: Beading is used in association with a reference analysis.
Temporary wiring and equipment shall be disconnected and removed as soon as its purpose is
served.
When returning the signalling to operational use, any wiring and equipment not in accordance
with the approved design (interim stage-design or final commissioned-design) shall not remain
active within the installation. This pertains to wiring and equipment such as test wiring, test-
straps, false feeds and bridges, test rigs and 'frig' wiring that can override system inputs and
outputs. This is to ensure that no part of the signalling interlocking, including trackside inputs
and outputs, controls and indications, and so on is falsely defeated or manipulated by any
unintended temporary wiring or equipment.
Note: Temporary bridging that forms part of an active, approved bridging authority
may be left connected.
7.6.1. Jumper wires and test-straps The use of jumper wires for temporary false feeds and bridges when connected to existing
(working) signalling circuits shall be in accordance with signalling safeworking procedures
(referring to bridging or false feeding of signalling circuits). The requirements of the operator
and maintainer RIM shall apply unless alternative arrangements are agreed by the operator and
maintainer RIM. Alternative arrangements shall not be less restrictive than that stated in
T HR SC 02000 ST (referring to temporary bridging of signalling circuits). The arrangements
shall be formally documented in the interface coordination plan or work package, as relevant.
Note: The application of jumper wires on existing circuits is deemed signalling
safeworking and therefore is performed only by suitably licenced signalling personnel.
The use of test-straps for testing new or altered wiring not connected to working circuits shall be
controlled so as to ensure their application does not impact the operational railway. All
associated risks, particularly those relating to test-straps inadvertently remaining when wiring
become ‘working’ circuits shall be mitigated by strict controls.
Jumper wires shall be authorised by the commissioning engineer or signalling tester in-charge,
subject to the signalling tester in-charge holding the relevant signalling licence. Test-straps used
for testing new or altered wiring that are not connected to working circuits may be authorised by
the signalling tester in-charge (unconditional of signalling licence).
© State of NSW through Transport for NSW 2019 Page 21 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Notwithstanding signalling safeworking procedures, the authorisation of jumper wires and test-
straps shall include the following assessment:
• effects to operational circuits and equipment so as to prevent any adverse impact to the
operational railway
• specific use of jumper wires and test-straps to ensure only the intended circuit portion is
affected
• type, length and colour of jumper wires and test-straps to ensure their application is
suitable and nature is obvious
• registration and control of jumper wires and test-straps to ensure their timely removal, and
all accounted and returned when intended
The application of jumper wires and test-straps shall be done accordingly by formal work
instruction. The instruction shall include the critical steps and diagrams (as necessary) to control
their use is as intended and accounted for upon their subsequent removal.
A record of false feeds, bridges and test-straps in use shall be kept in the relevant work
package (installation, commissioning work package, as applicable).
Jumper wires and test-straps shall be limited in quantity, be of bright and distinct colour and
suitably tagged for clear identification. They shall be registered and secured in a locked box
when not in use, restricting access only to those permitted to use. Ideally, the jumper wires
should be contained in a separate box to the test-straps, for ease of stocktake.
Jumper wires and test-straps shall be counted to ensure the same quantity is returned as
issued. Jumper wires shall be counted before application and again after application. Test-
straps shall be counted at the commencement and conclusion of each relevant shift (or test
application if testing exceeds a single shift).
7.7. Security of signalling equipment and housings Personnel working within operational signalling environments shall comply with the authority
requirements stated in Section 8.
When working within operational signalling environments, all precautions shall be taken to
ensure that working circuits and equipment cannot be interfered with or damaged, whether
accidently or otherwise. Additionally, that wiring and equipment are not short-circuited by loose
unterminated wires, tools, metal filings, drilling swarf, keys, loose relay nuts, washers, bits of
wire, or other metal objects.
Special care shall be taken to protect nearby equipment (including the base of plug-in relays)
from lodgement of any metal filings or drilling swarf to eliminate the possibility of transfer to a
working circuit. Following work, such material shall be removed and cleaned from all affected
surfaces, so that none remains.
© State of NSW through Transport for NSW 2019 Page 22 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
All trackside signalling equipment and housings shall be fitted with locks when unattended.
Before closing equipment and housings, signalling personnel shall check that everything is in
order and properly connected, and that nothing has been left loose, foul of standard clearances
or is in a potentially unsafe condition.
7.8. Risk mitigation strategy A risk mitigation strategy shall be in implemented by the commissioning AEO when working
within operational signalling environments. The following list provides examples of risk
mitigation elements that can be implemented, as applicable:
• ensuring personnel are competent and proficient for the intended function
• ensuring personnel working within operational signalling environments hold the correct
authority level to do so (a valid signalling licence or signalling authorisation) and a specific
signalling permit to work, or are supervised by suitable personnel holding same
Note: See Section 8 for further information regarding signalling licensing, signalling
authorisation and signalling permit to work.
• identifying stakeholders and initiating proper interface coordination, including a site integrity
agreement
• complying with site integrity agreements, including provision of emergency contact
information and works programme
• ensuring the most up-to-date version of circuit books and plans (including interim
maintenance copies) are used to correlate the as-built installation
• correlating the existing arrangement (by performing a documentation check, hand-trace,
apparatus inspection, wire count and null count) to ensure the installation before the build,
is commensurate with the specific design issued by the design AEO
Note: Correlation of existing circuitry may be restricted or exempted as determined by
risk assessment, subject to agreement by the operator and maintainer RIM. For
example, restricted to a documentation check, apparatus inspection, wire count and
null count where hand-tracing can cause damage to wiring or exempted following
recent work of the same circuits that involved documentation check, hand-trace,
apparatus inspection, wire count and null count.
• appropriately protecting railway operations affected by the works by securing signalling
apparatus out of use in accordance with signalling safeworking procedures
• electrically isolating live signalling circuitry from any worked-on portion
• securing and insulating unterminated wiring including spare conductors, in accordance with
Section 7.5
© State of NSW through Transport for NSW 2019 Page 23 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
• not connecting wires and equipment pending commissioning to working circuits, unless
strict conditions are met in accordance with signalling safeworking procedures and Section
7.5.1
• disconnecting and eventual removal of decommissioned wires and equipment from working
circuits and power supplies
• applying labels or distinct tags to wires and corresponding terminals before undertaking
any wiring connections or disconnections in accordance with Section 7.5.2
• providing unique and distinct colours for stage wiring and temporary wiring, including test
wiring in accordance with Section 7.6
• ensuring the timely removal of jumper wires used for false feeds and bridges from existing
working circuits, and test-straps at the end of each relevant shift in accordance with
signalling safeworking procedures and Section 7.6.1
• updating the as-built signalling documentation accordingly at the end of each
commissioned stage, with sufficient provision made for maintenance purposes
• ensuring adequate lighting and access are provided during the work
• ensuring only tools and test equipment that comply with requirements are used for
certification work, or on operational signalling
• maintaining proper housekeeping of the work area
• ensuring the equipment housings and trackside equipment worked-on are secured when
vacated
8. Authority to work The requirements in this section refer to authorities issued by the operator and maintainer RIM
required to enable the occurrence of works to take place on or within operating signalling
environments. The work is inclusive of all works done within the confines of operating signalling
equipment and housings, even where the work is of a non-invasive nature.
8.1. Signalling permit to work The commissioning engineer shall obtain an overall signalling permit to work prior to any
undertaking of signalling work (including inspection work) within the operational network. The
permit is granted by the operator and maintainer RIM or project delivery RIM (as delegated).
The permit enables the commissioning engineer to administer the overall signalling permit to
work process to signalling personnel working within the confines of the project scope. The
delivery of this process shall be done in accordance with T HR SC 02000 ST, the requirements
of operator and maintainer RIM including signalling safeworking procedures, and the
commissioning AEO's safety management system. © State of NSW through Transport for NSW 2019 Page 24 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Signalling permit to work requirements shall complement the interface coordination
requirements, as stated in Section 11.
As part of the signalling permit to work process, the commissioning engineer shall converse with
all duty holders expected to undertake critical signalling functions on or within operational
signalling environments. This is to ensure such duty holders understand their role,
responsibilities and work scope, and that they are aware of any signalling hazards. Additionally,
it assists the commissioning engineer to correspond (map) the duty holder's competency and
proficiency level with the intended task. Where evidence is required in support of the mapping
process, the commissioning engineer may request the duty holder to furnish such evidence.
The commissioning engineer, on satisfying these requirements, shall subsequently issue a
signalling permit to work to each individual duty holder.
An exception to the signalling permit to work requirement exists for work done within non-
operational signalling environments. In this case, the suitability of duty holders performing
critical signalling functions shall be managed using the commissioning AEO's safety
management system, which may be done independently of the signalling permit to work
process.
Note: Signalling work at a green-field site is deemed an operational signalling
environment once the work has reached the stage of commissioning.
8.2. Working on operational signalling or applying signalling safeworking Tasks that involve working on operational signalling or applying signalling safeworking shall be
done in accordance with signalling safeworking procedures, and network rules and network
procedures.
Where the work has a potential to cause an operational interference, suitable safeworking
arrangements shall be deployed to protect the running of trains and users at level crossings
before proceeding with the work. Network forms, such as infrastructure booking authorities shall
be duly compiled for the notification of securing signalling apparatus out of use.
The safeworking requirements to be deployed shall be first agreed and documented between
the commissioning engineer (or delegate) and the network operator. This is particularly
pertinent during the commissioning stage.
Personnel involved in critical signalling functions shall have a clear understanding of the
safeworking arrangements prior to commencing.
© State of NSW through Transport for NSW 2019 Page 25 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Details regarding the integration of new or altered signalling shall be published with adequate
notification, in accordance with the operator and maintainer RIM’s requirements. An example of
such publication is a 'weekly notice'. The notification shall describe the final system
arrangement and any interim arrangements that come into effect.
8.2.1. Authority to work on operational signalling or apply signalling safeworking Duty holders supporting the commissioning engineer in the course of performing work on
operational signalling or applying signalling safeworking shall hold the following elements of
authority to do so:
• signalling licence, valid for the relevant network
• specific signalling permit to work (see Section 8.1)
• current record (certificate) of competency, relevant for the work (see Section 15)
Signalling licences are issued to signalling personnel by the operator and maintainer RIM for
work done on operational signalling or applying signalling safeworking. They apply exclusively
to their network. Examples of licensed signalling personnel include signal electricians and signal
engineers (field).
The authority levels permitted by signalling licences are governed by signalling safeworking
procedures.
Note: See Figure 1 for guidance of the different assessment pathways for attaining
roles in critical signalling functions that include signalling licence.
Signalling licences ensure work performed on the operational signalling system or the
application of signalling safeworking is governed by the operator and maintainer RIM in order
for them to meet legislative and regulatory obligations, in accordance with the Rail Safety
National Law (NSW).
Where signalling safeworking work is planned by non-licensed personnel (such as when
compiling commissioning work packages, work instructions, and the like), the commissioning
engineer shall ensure that such work is within the planner's capability, and the outcomes comply
with signalling safeworking procedures, and network rules and network procedures.
8.3. Working within operational signalling environments An operational signalling environment has signalling infrastructure within its confines operating
for the purpose of train running, or the infrastructure is at the stage of being commissioned into
service.
© State of NSW through Transport for NSW 2019 Page 26 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Infrastructure constituting an operational signalling environment includes signalling control
centres (including local control panels and ground frames), signalling equipment housings,
trackside signalling equipment, and signalling-services routes.
In addition to operational infrastructure, signalling infrastructure within the confines of green-
field sites that have commenced the stage of commissioning shall also be deemed operational
signalling environments.
Excepting infrastructure when at the aforementioned stage of commissioning, signalling sites
that are not within the confines of operational signalling equipment and pose no potential for
impact to train running may be treated as non-operational signalling environments.
8.3.1. Authority to work within operational signalling environments Duty holders supporting the commissioning engineer in the course of performing or supervising
specific work within an operational signalling environment shall hold the following elements of
authority to do so:
• signalling authorisation, valid for the relevant network
• specific signalling permit to work (see Section 8.1)
• current record (certificate) of competency, relevant for the work (see Section 15)
Note: A valid signalling licence inherently includes the authorisation rights to work
within an operational signalling environment, subject to the provisions stated on the
duty holder’s signalling permit to work.
Signalling authorisations (referred also as ‘authorised’ signalling person) are issued by the
operator and maintainer RIM for work done within operational signalling environments. They
apply exclusively to their network. Examples of ‘authorised’ signalling personnel include
installers, testers and certifiers, as well as other discipline and trades personnel (such as air
conditioning technicians, fire control technicians, security technicians, and so on).
Signalling authorisations ensure work performed within operational signalling environments is
governed by the operator and maintainer RIM in order for them to meet legislative and
regulatory obligations, in accordance with the Rail Safety National Law (NSW).
‘Authorised’ signalling personnel are persons already deemed competent by AEOs to perform
work, who also hold authorisation from the operator and maintainer RIM to perform specific
work within their operational signalling environments.
Note: See Figure 1 for guidance of the different assessment pathways for attaining
roles in critical signalling functions that include ‘authorised’ signalling person.
Work within operational signalling environments may be undertaken by competent personnel
who are not ‘authorised’ on condition that the work is supervised by suitable signalling
© State of NSW through Transport for NSW 2019 Page 27 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
personnel holding the aforementioned authority, subject to any operator and maintainer RIM
restrictions.
The work performed or supervised by ‘authorised’ signalling personnel shall not involve
interfering with operational signalling or the application of signalling safeworking.
Note: Tasks involving working on operational signalling or applying signalling
safeworking are done by licensed signalling personnel in accordance with Section 8.2.
8.4. Non-operational signalling environments Non-operational signalling environments pertain to signalling equipment housings, trackside
signalling equipment and signalling-services routes that are totally in a non-operational state,
and therefore working on these items can pose no direct impact to train running.
Signalling equipment is deemed as non-operational when its interface is either pending
connection to the operating network or temporarily disconnected from the operating network
(such that it poses no adverse impact to train running) for the duration the deeming is applied.
Consideration shall be given to the risks associated with non-commissioned infrastructure that
can potentially affect nearby operational lines. An example of this situation includes newly
installed signals pending commissioning that can be misread by train drivers operating on or
adjacent to worked-on lines, or the disturbance of point detectors in crossovers.
Signalling-services routes are deemed non-operational where none of the electrical conductors
or air lines within the affected portion is in-use for train running.
Signalling work done at green-field sites shall be deemed an operational signalling environment
once the work has reached the stage of commissioning.
8.4.1. Temporarily enabling operational signalling environments to become non-operational Where operational signalling equipment (in housings or trackside) is disconnected and booked
out of use in accordance with signalling safeworking procedures, and a risk assessment has
determined that there can be no adverse impact to train running, then the associated signalling
may be treated as a non-operational.
This means the work done under this arrangement will generally be confined to occasions when
train operations have temporarily ceased; for example, a track possession.
This arrangement can enable specific unsupervised work to be done in such housings or
trackside equipment by non-authorised personnel. However, the personnel used shall be
competent and proficient to carry out their intended function.
Under this arrangement, the suitability of resources may be managed by the project as if the
environment was a green-field site (as opposed to the usual governance requirements for train
running conditions directed by the operator and maintainer RIM). © State of NSW through Transport for NSW 2019 Page 28 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Note: The aforementioned arrangement applies only where the signalling is booked
out of use, rendering the entire equipment housing (or secured portion as agreed by
the operator and maintainer RIM) and associated trackside equipment non-
operational.
When the signalling infrastructure has reached the stage of testing for the purpose of bringing
the booked-out signalling back into use, then the signalling environment shall once again be
deemed as operational. Consequently, all personnel performing work in this environment shall
comply with the requirements stated in Section 8.2 and Section 8.3.
9. Appointment of commissioning engineer The commissioning AEO shall engage a competent and proficient signalling person (referred in
this document as the commissioning engineer) to lead the inspection, testing and
commissioning team.
The selection of an appropriate commissioning engineer shall be done in accordance with a
defined process as governed by the project delivery RIM. This is to ensure that the candidate's
suitability (skills and experience) are commensurate with the complexity of the work.
The commissioning engineer shall hold a valid signalling licence equivalent to that of signal
engineer (field) as issued by the operator and maintainer RIM. This licence enables the
commissioning engineer to apply the domain-specific requirements that pertain to signalling
safeworking, inspection, testing and commissioning, as well as the relevant network rules and
procedures.
Note: The process for attaining a signalling licence is governed by the operator and
maintainer RIM.
The engagement of the commissioning engineer shall be timely, so as to ensure that all their
responsibilities can be met. These responsibilities are prescribed in Section 13.3 and include
requirements for planning, interface coordination and signalling safeworking.
The commissioning engineer's role shall continue until the final completion certificate is fulfilled,
along with the submission of specific design certified office copy (COC) and close-out of the
commissioning work package.
Note: After the final commissioning, the commissioning engineer may delegate the
close-out of any residual non-critical items of the commissioning work package to the
signalling tester in-charge.
The role of commissioning engineer should be held by the same person for the entire project
until the end of commissioning, including the close-out of post commissioning critical tasks.
© State of NSW through Transport for NSW 2019 Page 29 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
The commissioning engineer shall act in the interest of TfNSW and the relevant rail
infrastructure managers and not be adversely influenced by project constraints or commercial
implications.
10. Engineering design authority The ASA is the network design and standards authority for the Transport cluster. The ASA is
responsible for developing engineering governance and frameworks to support industry delivery
in the assurance of design, safety, integrity, construction and commissioning of transport assets
for the whole-of-asset life cycle.
The following elements represent the level of engineering design authority held by the
responsible entity, for the production of signalling design:
• Lead Signals and Control Systems Engineer, ASA holds the authority for the following:
o production or amendment of signalling standards, specifications and principles, as well
as other ASA signalling requirements
o type approval of signalling systems, associated subsystems and apparatus, as well as
specific products that form part of signalling infrastructure
o endorsement of signalling functional specifications for which ASA is a signatory
• The engaged design AEO holds authority for the following:
o approval and issue of specific designs for new or altered signalling in accordance with
agreed configuration changes
o production of supplementary signalling design documentation such as signalling
functional specifications, stage-commissioning plans, weekly notices, design integrity
(principles) test plans, and so on, as applicable
• The engaged commissioning AEO holds authority for the production of documentation and
records, in support of activities associated with inspection, testing, commissioning and
maintenance, as applicable
The commissioning engineer may be granted delegation of authority by the design AEO, limited
to the following elements:
• acceptance of signal sighting positioning outcomes (by signal sighting committee)
• approval of detailed site survey plans containing specific information about signalling-
services routes, including under-line crossings, under-road crossings, service pits and
chambers, joints, manifolds and route markers
• approval of type, capacity and positioning for equipment housings
• approval of minor allocation for items, such as cable cores, fuses and terminals
© State of NSW through Transport for NSW 2019 Page 30 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
• approval of minor mechanical drawings, such as labelling and tooling
• site certification of as-built installations in preparation for final design production
Determinations made by the commissioning engineer in this regard shall comply with ASA
signalling construction standards and type approvals.
Any subsequent alterations to signal sighting, shall be further approved by the signal sighting
committee.
11. Interface coordination Interface coordination involves agreement between the affected parties managing an interface.
Interface coordination and its planning aim to identify the changes, define the boundaries and
allocate responsibilities of each party, such that the interface issues are effectively managed.
Proper interface planning provides an effective measure in minimising the day to day impacts to
operational infrastructure caused by work, which can adversely affect the safety and reliability of
the operating railway.
Interface coordination shall consider the scope of work at interfaces, including any stage work
and temporary work. The following list provides examples of strategic elements that can enable
effective interface coordination:
• collaborate with the operator and maintainer RIM signalling representatives (including
signalling maintenance engineers, asset engineers, integrity engineers, and so on) to
discuss and agree on the scope, timing, maintenance, design requirements, and track
access
• minimise the scope that requires track possession to commission by completing all
possible construction, inspection and testing prior to the track possession
• include the interface inspection and testing activities and wire changeover strategy in the
inspection and testing plan
• identify the scope of works such as new equipment to be commissioned, redundant
equipment to be removed and equipment to be booked out of use
• making provision for work done by others affecting the same interface
• coordinating stage work and interface designs so that the interference to existing
equipment or wiring is minimised, in particular within relay rooms and other signalling
locations
• minimising the amount of temporary equipment mounted within an existing location
• clearly identifying commissioned circuits and items of equipment (including trackside
equipment) with that pending commissioning
© State of NSW through Transport for NSW 2019 Page 31 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
• clearly identifying temporary work in such a manner that is immediately clear and obvious
• removing temporary work that is no longer required and reinstating the situation to the
condition it was prior to the work commencing
11.1. Interface coordination plan The commissioning AEO shall identify the key interfaces, then develop and implement a
detailed interface coordination plan to ensure a successful and safe signalling commissioning.
The interface coordination plan shall form part of the AEO’s process for interface planning and
management.
The interface coordination plan shall identify, coordinate and manage with stakeholders, the
interface elements primarily associated with the safety and reliability of railway operations,
particularly in regards to the performance of the signalling system.
Stakeholder engagement for this purpose is typically done with network operators and
engineering discipline representatives (including maintenance and asset stewards). However,
interface engagements can extend to other business units within rail, as well as other transport
modes, road authorities, local councils, utility providers and so on.
Additionally, engagement with regulatory bodies may be necessary, such as with the rail
regulator (in accordance with the Rail Safety National Law (NSW)), TfNSW, ASA, independent
safety assessors, and the like.
The interface coordination plan shall take into account the following phases of the signalling
project:
• planning and preparation
• build and installation
• inspection and testing
• commissioning (including any decommissioning)
• handover and post commissioning (for example, documentation distribution or defect
rectification)
The commissioning engineer shall ensure that a clear understanding of work is defined at the
interfaces between the parties involved. These requirements shall be documented in the
interface coordination plan.
© State of NSW through Transport for NSW 2019 Page 32 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
The interface coordination plan shall record in detail, the key elements of the signalling project
as identified in the following list, as applicable:
• interface identification and stakeholder identification
• clear identification of changes and agreed responsibilities between stakeholders
• nomination of duty holders performing critical signalling functions
• installation and commissioning work packages (as applicable)
• schedule of notifications
• inspection and test plan
• configuration management including use or re-use of existing equipment
• type approval, trials and concessions for new or novel equipment
• site integrity agreement, including assessment of existing condition and hazards
• signalling access arrangements
• planned stage work
• signalling maintenance requirements
• operational issues arising from the works, including incident management
• commissioning requirements
• training requirements
• as-built signalling documentation and data file requirements
• signalling asset maintenance records
• handover requirements, including documentation and data files and finalisation schedule
11.1.1. Site integrity agreement A site integrity agreement is an on-site assessment, discussion and agreement between the
commissioning engineer (or delegate) and the operator and maintainer RIM’s representative.
The site integrity agreement shall form part of the interface coordination plan and shall be in
place prior to any installation or build works commencing within the operational interfaces.
The site integrity agreement shall include a detailed site assessment of the condition and
identification of any hazards in signalling locations and equipment to be worked on, including
the sensitivity of wiring and equipment in order to withstand any disturbances. Evidence of
condition and hazards shall be described and recorded by various mediums, such as
photography, video, text, measurements, and so on. The assessment shall include areas in the
© State of NSW through Transport for NSW 2019 Page 33 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
vicinity of the interface signalling location, such as trackside infrastructure, signalling-services
routes, fences, gates, structures, access paths and entry points.
The site integrity agreement agenda shall include the following items, as applicable:
• signalling permit to work arrangements
• access arrangements (for both project and maintenance workers)
• identification of specific work types and scopes within the interface area, including any
potential impacts to operations
• times and duration of specific work (for both project and maintenance works)
• identification of other works, particularly other signalling works affecting the same location
that require coordination, in accordance with Section 11.2
• exchange of contact information for project personnel, maintenance personnel, incident
response personnel, and associated managers
• restrictions of work, such as for peak periods, special events and the like
• identification of any signalling hazards, such as known defects, fragile wiring, shelf relays,
fragile mechanical equipment, shallow buried cables, signal sighting issues (including
obstruction, focus, ambiguous indications and distant limitations), minimal or nil spare
holdings, and so on
• identification of any other hazards (such as electrical hazards, working at heights, confined
spaces, minimal or nil trackside refuges (safe places), minimal or nil warning devices,
tunnels, bridges, and so on
• identification of relevant registers that deal with the management of active risks, such as
seldom used signalling apparatus (typically track circuits and points), temporary bridging,
temporary repairs, signalling apparatus booked out of use, points with wide-cut locks or
lock slides removed, and so on
• identification of other signalling safeworking arrangements
• location of relevant site signalling documentation and data files, such as circuit books
(including any interim maintenance copies), signalling plans, track insulation plans, working
sketches, control and locking tables, interlocking and ATP data files, and so on
• management of failures and other operational incidents
• status of safety critical or safety significant maintenance, such as insulation testing, points
testing, track circuit testing, interlocking testing, and so on
• colour of tape (or equivalent) to be used for identifying new, altered or redundant wires and
equipment
© State of NSW through Transport for NSW 2019 Page 34 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
• notification, methodology and agreement to use temporary wiring and stage wiring in both
internal and external applications
• requirements for maintenance documentation and data files, including interim copies,
timely updates, storage of copies, number of copies
• specific preferences, such as interim labelling, reinstatement of ducting lids, location of
items, test equipment in use, housekeeping, security, and so on
• authority to excavate within the vicinity of infrastructure
The site integrity agreement shall also include any intention to undertake temporary work, stage
work or preparatory work including the use of test rigs and the like, as well as any installed
signalling equipment not in use which is pending commissioning or removal.
Additionally, the site integrity agreement shall include an itemised proposal to re-use any
existing signalling equipment, if required as part of the works (for example, trackside or internal
equipment, cable cores and signalling-services routes). This shall be documented in the
interface coordination plan or works package, as relevant. The re-use of such equipment shall
be subject to an appraisal by the relevant experts to assess its condition and suitability.
The site integrity assessment shall extend to other interface areas as necessary, such as track,
civil, electrical and telecommunications assets, as relevant for reliability, availability,
maintainability and safety (RAMS) of the new or altered signalling.
Personnel shall work within the bounds of the site integrity agreement. They shall be
responsible for ensuring the operating signalling system is not endangered by their work.
11.2. Coordination of multiple signalling projects The operator and maintainer RIM shall be responsible for the identification and initial
coordination of multiple signalling projects where these works are (or will be) concurrent within
the same area; for example, two or more signalling projects within the same relay room.
In these cases, the operator and maintainer RIM shall provide the initial management to
mitigate the associated risks.
The operator and maintainer RIM shall appoint one of the AEO’s commissioning engineers to
subsequently coordinate the signalling interface requirements on behalf of the relevant projects.
The following are examples where coordination is required on multiple signalling projects:
• overlapping circuit or data design
• potential duplicate allocation (including field allocation) of cable cores, contacts, fuses,
terminals, equipment and rack space
© State of NSW through Transport for NSW 2019 Page 35 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
• potential interference of items worked-on, such as wiring, relays, fuses, terminals, data
files, equipment, as well as the co-use of signalling documentation, such as circuit books
and signalling plans
• impacts on each project from project stage works and testing
• designation of coloured tape used to identify new and redundant wiring for each project
The coordinating commissioning engineer shall refer conflicting design matters to the relevant
design AEOs for resolution before permitting construction of the affected portion to continue.
11.3. Decommissioning and disposal of redundant equipment The safe and efficient decommissioning and disposal of redundant equipment shall be planned
as part of the testing and commissioning activities. The decommissioning of operational
signalling and safety related systems shall be done similarly to commissioning infrastructure.
The commissioning engineer shall establish a strategy that manages the impact of
decommissioning and the subsequent disposal of redundant equipment. The strategy shall take
into consideration the following factors prior to decommissioning and disposal:
• continued integrity of a safe and reliable railway during the decommissioning, dismantling,
demolition and removal stages
• assurance that no ambiguity exists for the type of safeworking, signalling or communication
in force at any one location or time
• assurance that no ambiguity or confusion exists to train drivers and network operators of
which signal, route, block section, indication or control is in use or applies to them
• assurance that no ambiguity or confusion exists to third party users, including users of level
crossings and users of information systems, such that they understand the working status
of such equipment, and the clear applicability and meaning of associated indications, and
warning systems (in-keeping with requirements); additionally that associated passenger
information emanated is relevant
• clear identification of the redundant equipment
• prevention of inappropriate re-use of decommissioned equipment, as well as the allotment
of agreed equipment for return to the network maintainer
• safe return of loose releasing items, such as Annett keys, loose keys, point (EOL and
ESML) handles, and associated locking mechanisms
• safe disconnection of overhead traction return, including the elimination of any risk
associated with touch potential or electrolysis
• appropriate management of any residual risks resulting from removed equipment © State of NSW through Transport for NSW 2019 Page 36 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
The commissioning engineer shall engage with stakeholders, particularly the network
maintainer for the impact management of decommissioning and subsequent disposal of
redundant equipment. The engagement shall discuss specific operator and maintainer RIM
requirements for decommissioning, including any agreed allotment of redundant equipment to
the network maintainer.
The commissioning engineer shall liaise with network operators regarding the type of
safeworking, signalling and communication in force at any one location or time as a result of the
decommissioning process, particularly if done in stages.
12. Roles and responsibilities of RIMs The Rail Safety National Law (NSW) states the following:
“…a rail infrastructure manager is to ensure, so far as is reasonably practicable –
• the provision or maintenance of rail infrastructure that is safe; and
• that any design, construction, commissioning, use, installation, modification,
maintenance, repair or decommissioning of the manager's rail infrastructure is carried
out in a way that ensures the safety of the railway operation”
Where the project delivery RIM is not also the operator and maintainer, the elements for safety
(as stated in the Rail Safety National Law (NSW)) shall be allocated between the RIMs in
accordance with their business undertakings. The project delivery RIM, including relevant AEOs
is obliged to provide the operator and maintainer RIM with all the necessary assurances for
acceptance of the new or altered assets into their network.
Information shall be provided to assure the operator and maintainer RIM of the safety and
performance of the new or altered signalling. Additionally, the operator and maintainer RIM shall
be advised of any new or residual risks emanating from the project works that are to be
managed by them.
Both the project delivery RIM and the operator and maintainer RIM shall comply with the
requirements stated in AS 4292.1 Railway Safety Management - Part 1: General requirements
and AS 4292.4 Railway Safety Management - Part 4: Signalling and Telecommunications
Systems and Equipment, as relevant to their undertaking.
12.1. Project delivery RIM and commissioning AEO responsibilities The project delivery RIM shall be responsible for the delivery of safe and reliable new or altered
signalling infrastructure.
The project delivery RIM shall hold responsibility together with the operator and maintainer RIM
for the continued integrity of the operating signalling system during the project works.
© State of NSW through Transport for NSW 2019 Page 37 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
The commissioning AEO shall provide assurance for the functions which the commissioning
engineer is accountable.
The project delivery RIM shall be responsible for obtaining the necessary permissions from the
operator and maintainer RIM to carry out the intended project works prior to commencing any
undertakings within the network.
The project delivery RIM shall provide the commissioning AEO with any specific requirements
that are in addition to ASA requirements. This information can also include any known operator
and maintainer RIM requirements.
The commissioning AEO shall seek any specific operator and maintainer RIM requirements and
project delivery RIM requirements that are additional to ASA requirements.
The commissioning AEO, through their appointed signalling representative (commissioning
engineer) shall engage with the operator and maintainer RIM for the purpose of interface
coordination including, interface agreement, site integrity agreement, track possession and
stage work planning, signalling safeworking, incident response (relating to incidents caused by
the project), resource allocation, signalling hazard identification, event management, and so on.
The commissioning AEO shall make available to the operator and maintainer RIM (on request),
any key processes and systems deployed by them to deliver the signalling work, in order for the
operator and maintainer RIM to review such systems (as required). This is to satisfy the
operator and maintainer RIM of the testing strategy involved and the suitability of resources
used to perform critical signalling functions. Additionally, the commissioning AEO shall provide
to the operator and maintainer RIM (on request), the listing of signalling personnel undertaking
the project’s critical signalling functions.
The commissioning AEO shall ensure that the work of installation, inspection, testing and
commissioning for the new or altered signalling is done in accordance with relevant standards
and requirements, and to its specific design.
The commissioning AEO shall allocate the roles of duty holders for critical signalling functions in
accordance with Section 13.
The project delivery RIM and commissioning AEO shall comply with the requirements for
coordinating multiple signalling projects, in accordance with Section 11.2.
The project delivery RIM and commissioning AEO shall liaise with the operator and maintainer
RIM in order to provide them with the necessary project documentation and data files
throughout the project (as required) including handover, in accordance with SPG 0703
Signalling Documentation and Drawings. This provision shall include copies of signalling
designs associated with the new or altered works, such as circuit books, signalling plans, track
insulation plans, installed data sheets, data files, control tables, locking tables and diagrams,
detailed site surveys, and so on, as applicable.
© State of NSW through Transport for NSW 2019 Page 38 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
The commissioning AEO shall provide copies of signalling project documents to the operator
and maintainer RIM (as required), and such documents include signalling designs, work
packages, inspection and test plans, work and stage work programs, inspection and test
certificates, operational notices, infrastructure booking authorities, and so on.
The project delivery RIM and commissioning AEO shall liaise with the operator and maintainer
RIM for the provision of training (formal or informal, as agreed) and any related documentation,
including maintenance manuals, particularly for new or novel assets as introduced by the
project.
The commissioning AEO shall be responsible for the timely submission of COC of signalling
documentation attested by them, in accordance with SPG 0703.
The project delivery RIM shall be responsible for the timely completion of work including
practical completion, handover, and the finalisation of any outstanding defects.
12.2. Operator and maintainer RIM responsibilities The operator and maintainer RIM shall hold primary accountability for the safe and reliable
operation of the railway signalling system.
The operator and maintainer RIM shall be responsible for permitting access for worksites onto
its network and for providing track possessions, as agreed. The commencement of signalling
works is enabled by the operator and maintainer RIM through the 'signalling permit to work'
process. This process aligns with other engagement participations between the operator and
maintainer RIM and the relevant project delivery parties. These engagements include project
work interface agreements, interface coordination, track possession and stage work planning,
site integrity meetings and resource allocation.
In addition to ASA requirements, the operator and maintainer RIM shall provide any domain-
specific requirements to the commissioning AEO. Such requirements can include operator and
maintainer RIM engineering instructions and special notices, as well as specific engineering
requirements, such as equipment adjustment settings. This is required to ensure that the
operator and maintainer RIM is satisfied that the delivery of work is commensurate with their
acceptance criteria. Other information provided can pertain to the identification of specific
signalling hazards or the treatment of sensitive areas, such as old or brittle wiring and shelf
relays, or advice of specific operational arrangements that are in place for special events.
The operator and maintainer RIM shall make accessible any as-built signalling documentation
and data files as required by the commissioning AEO. Such documents include circuit books,
signalling plans, track insulation plans, control tables, installed data sheets, data files, detailed
site surveys, maintenance manuals, and so on.
© State of NSW through Transport for NSW 2019 Page 39 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
The operator and maintainer RIM shall provide to the commissioning AEO, on request, any
relevant signalling asset maintenance record. Such records include insulation test records and
associated defects, seldom used apparatus, temporary repairs, known defects, special
conditions, status of safety critical and safety significant maintenance, and so on.
The operator and maintainer RIM shall be responsible for identifying any multiple signalling
projects that are, or will be, concurrent within the same area; for example, two or more signalling
projects working within the same relay room. In these cases, the operator and maintainer RIM
shall provide the initial management to mitigate the associated risks. Subsequently, the operator
and maintainer RIM shall appoint one of the AEO's commissioning engineers to coordinate the
signalling interfacing requirements on behalf of the relevant projects. See Section 11.2 for
further information.
The operator and maintainer RIM should review the key processes or systems utilised by the
commissioning AEO; for example, reviewing the commissioning AEO's testing strategy and
competency management system. This is done as part of due diligence in order to gain an
assurance of the critical signalling functions performed. The review should be undertaken at the
earliest opportunity.
The operator and maintainer RIM should review a listing of signalling personnel utilised by the
commissioning AEO who perform the critical signalling functions. This is done to enable the
operator and maintainer RIM to exercise their obligations (in regards to rail safety work) in
accordance with the Rail Safety National Law (NSW).
The operator and maintainer RIM shall be responsible for the management of incidents that
occur on the railway, irrespective of whether the cause is borne from the project works or other
cause. An example of signalling related incidents include, right-side signalling failures, signalling
irregularities (including wrong-side failures), derailments, collisions, level crossing incidents and
operational impacts caused by personnel interfering with equipment.
The operator and maintainer RIM shall make contributions for their part, to achieve the
expected outcomes that pertain to signalling safety and reliability for the new or altered works.
The following list provides examples of where the operator and maintainer RIM can contribute to
achieving signalling safety and reliability:
• collaborating for interface coordination and site integrity
• providing network access and track possessions
• identifying other works (particularly signalling works) that are concurrent in the same area,
and where necessary, appoint a coordinating commissioning engineer to facilitate the
interface issues associated with such projects
• reviewing of key delivery processes and systems utilised by the commissioning AEO (such
as testing strategy and competency management system)
© State of NSW through Transport for NSW 2019 Page 40 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
• providing candidate pathways and assessments for RIM signalling licence and
authorisation, as requested
• providing timely operator and maintainer RIM requirements (that are in addition to ASA
requirements) to the commissioning AEO or project delivery RIM
• reviewing of signalling designs, where necessary
• providing local or specific information
• advising of special events and special train working
• specifying conditions for work done within operational signalling environments
• providing specific supervision for particular works done within operational signalling
environments
• providing as-built signalling documentation and data files
• providing signalling asset maintenance records
• ensuring existing asset information and configuration details are kept up to date
• responding to signalling failures and rail related incidents
• implementing updated technical maintenance plans to accommodate any interim
arrangements initiated by the project work
• arranging maintenance personnel to attend any training as required, and familiarisation of
the new or altered arrangements
• obtaining project handover and acceptance
The following list provides examples of operator and maintainer RIM roles that can offer the
aforementioned services:
• responsible signal engineer; for example, asset engineer or maintenance engineer
• licensed signalling personnel; for example, signal electrician
• authorised signalling personnel; for example, electrical installer or circuit tester
• signal design manager
• possession manager
• network manager
© State of NSW through Transport for NSW 2019 Page 41 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
13. Roles and responsibilities of duty holders Inspection, testing and commissioning, as well as the application of signalling safeworking are
critical signalling functions required for assuring the safe and reliable performance of railway
systems and equipment.
This document defines a set of roles and responsibilities for duty holders engaged to perform
such critical signalling functions. This notion provides a consistent and coherent application of
roles across all signalling commissionings, irrespective of which commissioning AEO is
engaged to do the work. Commissioning AEOs shall align their roles that pertain to critical
signalling functions, in accordance with the roles defined in this document. See Table 1 for a
listing of related critical signalling functions.
Duty holders of roles in critical signalling functions shall act as a representative of the
commissioning engineer. This requirement extends to those signalling design personnel when
performing interlocking testing and principles testing, irrespective of whether the testing is
conducted on-site or off-site.
Note: While this document allocates requirements specifically to the commissioning
AEO, the design AEO still holds accountability for the verification and validation
elements of signalling designs, as approved by them.
13.1. Allocation of roles The commissioning AEO shall ensure that all the critical signalling functions are thoroughly
identified and adequately resourced. Duty holders shall be appointed in sufficient time for them
to become acquainted with their roles, having due account for any up-skilling or knowledge
enhancements.
The roles for critical signalling functions shall be allocated by either the commissioning engineer
or signalling tester in-charge. However, where the specific subject matter exceeds the expertise
of the commissioning engineer or signalling tester in-charge, then the allocation of roles for
critical signalling functions may be delegated to the relevant subject matter expert.
Each duty holder shall be responsible for their allocated role. The commissioning engineer's
accountability shall not be delegated.
Critical signalling functions shall be allocated only to the following defined roles:
• commissioning engineer
• signalling tester in-charge
• signalling system certifier
• signalling subsystem certifier
• trackside apparatus certifier © State of NSW through Transport for NSW 2019 Page 42 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
• structural and ancillary certifier
• signalling test assistant
• licensed signalling personnel
The requirement for independence shall be considered when allocating the aforementioned
roles.
The commissioning engineer may undertake other roles such as signalling tester in-charge and
certifier, subject to holding appropriate competency, maintaining an appropriate level of
independence and sustaining a manageable work load.
Where the roles of commissioning engineer and signalling tester in-charge are performed by
separate individuals, then the allocation of responsibilities between the respective roles shall be
formally agreed and documented. These two roles shall continue until all the agreed signalling
works are completed and the final completion certificate issued. See Section 13.3 and
Section 13.4 for further information regarding these roles.
Duty holders may be allocated more than one role as deemed appropriate by the
commissioning scope; however, their work load shall remain within normal expectations.
Conversely, a complex role may be shared amongst a number of duty holders.
13.2. Common responsibilities All personnel involved in critical signalling functions shall be aware of their duties and
responsibilities.
Duty holders shall be responsible for understanding the requirements of their allocated role and
shall be responsible for their respective task.
Each duty holder shall carry out their allocated function completely and duly mark-up any
associated documentation or record with diligence. This shall be done in accordance with
applicable TfNSW standards, engineering specifications and approved designs, and in
accordance with the commissioning AEO's requirements and any specific operator and
maintainer RIM requirements (as imposed). These requirements include the adjustment of any
settings, so that they comply with stated specifications or otherwise expected limits.
Duty holders involved with inspection and testing shall check their work for completeness,
accuracy and quality. They shall remain vigilant throughout the entire task for defects, errors
and omissions that can be present, and duly report any such issue.
All required work instructions, test records, certificates and other associated documentation
(including those in electronic format) shall be completed and returned as instructed.
Duty holders leading inspection and testing activities shall accordingly direct their team to
ensure all work done by them is in accordance with relevant requirements, and is complete.
They shall also ensure the testing equipment used by them, for the purpose of certification, © State of NSW through Transport for NSW 2019 Page 43 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
conforms to industry specifications, type approval, ASA requirements, project delivery
requirements or operator and maintainer RIM requirements, as applicable.
13.3. Commissioning engineer responsibilities The commissioning engineer authorises the signing into use, the new or altered signalling when
commissioned.
The commissioning engineer shall hold ultimate accountability for the safe and reliable
integration of the new or altered signalling to the extent that it is built in accordance with the
following elements:
• approved signalling design
• type approved signalling equipment (as applicable)
• agreed functional requirements
• applicable signalling principles
• applicable engineering standards
• domain-specific requirements ( project delivery RIM requirements and operator and
maintainer RIM requirements that are in addition to ASA requirements)
The commissioning engineer's accountability shall cover the signalling scope for activities
relating to inspection, testing and certification, leading to commissioning. The accountability
shall extend to any part of the operational network that is affected by the signalling work and its
subsequent integration.
The commissioning engineer shall ensure that all new or altered signalling works ensue
pursuant to interface coordination requirements, including an agreed interface coordination
plan, done in collaboration with the operator and maintainer RIM and other key stakeholders.
The commissioning engineer shall ensure all signalling safeworking tasks for the work comply
with the signalling safeworking procedures, and network rules and network procedures.
The commissioning engineer shall hold overall accountability for the implementation of effective,
proven and auditable processes for verification and validation that deliver a safe and reliable
system, which is the integrity of the new or altered signalling.
The commissioning engineer shall have overall accountability for the inspection and testing
functions as defined by this document, and to ensure they are carried out and recorded as
prescribed.
The commissioning engineer shall obtain all the assurances necessary to prove the installation
is built in accordance with approved designs and agreed functional requirements, and is in
compliance with applicable standards and other requirements before bringing the work into use.
© State of NSW through Transport for NSW 2019 Page 44 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
The commissioning engineer shall be overall accountable for ensuring that the tasks allocated
to duty holders of critical signalling functions are mapped against the duty holder’s competency
and proficiency level.
The commissioning engineer shall be responsible for determining if a signalling commissioning
can go ahead. The commissioning engineer shall ensure that certification testing is not
jeopardised by its compression into tight timeframes, particularly where it over-extends testing
personnel.
The commissioning engineer shall investigate (or arrange investigation of) any reported defects,
errors or omissions related to the work, and duly initiate appropriate actions to resolve such
matters, particularly where they are serious. This shall be done prior to determining the
readiness of commissioning and the decision to permit any signalling operation (including
degraded operation) for the purpose of train running.
The commissioning engineer shall establish a strategy that manages the impact of
decommissioning and the subsequent disposal of redundant equipment in accordance with
Section 11.3.
The commissioning engineer shall ensure that track circuits affected by the work, including
those tracks clear of the project scope that are not used as a result of the project’s track
possession are capable of providing an effective track shunt. This shall be assured prior to
certifying the signalling back into use.
The commissioning engineer shall be the person who signs the COC relating to the approved
signal design and ensures it is returned to the relevant design AEO for updating and
subsequent field distribution. The commissioning engineer shall also ensure that all handover
deliverables are in accordance with agreements made during the interface coordination
meetings. These include signing the 'practical completion certificate' along with the rectification-
management of any associated defects.
Finally, the commissioning engineer shall sign the 'final completion certificate' when all the
agreed works are closed-out.
13.4. Signalling tester in-charge responsibilities The signalling tester in-charge is responsible for planning and directing the inspections and
tests required for a safe and effective integration of the new or altered signalling work. In this
regard, the signalling tester in-charge shall assist the commissioning engineer in ensuring that
the tasks allocated to duty holders of critical signalling functions are mapped against the duty
holder’s competency and proficiency level.
The signalling tester in-charge shall provide to the commissioning engineer an overall
assurance of the testing elements before commissioning into service (including stage
commissioning) the new or altered signalling.
© State of NSW through Transport for NSW 2019 Page 45 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
The signalling tester in-charge is responsible for the overall effective, proven and auditable
processes that ensure compliance, verification and validation of the work. These processes
shall yield sufficient evidences to prove the following elements:
• verification and validation of the signalling design such that it meets signalling principles
and agreed functional requirements
• verification and validation of the new or altered work to prove that it is in accordance with
the approved signalling design, signalling standards and specifications, signalling principles
and agreed functional requirements
• assurance that the inspection and test plan listed all the required elements of testing
• assurance that all items in the inspection and test plan were executed
• assurance that all inspections and tests were done in accordance with requirements
• assurance that each inspection and test was completely fulfilled
• assurance that satisfactory results were obtained for all inspections and tests
• assurance that compilation of records, mark-ups and test results corresponds with the
items stated in the inspection and test plan
• assurance that any omission, error or defect that becomes evident, was logged and
appropriately actioned
Additionally, the following functions and responsibilities are applicable to the signalling tester in-
charge role:
• overall directing of the inspection and testing resources, referring to the allocation of testing
personnel, considering suitability and independence as well as the utilisation of correct and
calibrated test equipment
• management and distribution (including registration and version control) of signalling field-
issued design documentation, such as correlation copies, build copies, test copies, certified
office copies, interim maintenance copies, and any modification sheets
• preparation of installation and commissioning work packages, and related work instructions
• preparation of operational notices, such as weekly notices
• monitoring, auditing and analysing the inspection and testing activities and records,
ensuring they are in accordance with requirements
• preparation of handover package and associated completion deliverables, including post
commissioning defect identification, defect rectification management, allocation of spares
(as required) and compilation of practical completion and final completion certificates
© State of NSW through Transport for NSW 2019 Page 46 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Where specialist expertise is required to assist with the planning and directing of inspections
and tests that lead to certification of the signalling system or subsystems, the signalling tester
in-charge shall co-plan and co-direct these tasks with the relevant signalling system certifier or
subsystem certifier (as applicable). Notwithstanding the responsibilities of such certifiers, the
signalling tester in-charge shall retain overall responsibility for the planning and directing tasks.
The signalling tester in-charge shall collaborate with relevant design AEOs to facilitate the
following outcomes for signalling system and subsystem testing:
• establish the functions and roles of duty holders required for the signalling system and
subsystem testing
• establish the independence requirements for the testing
• obtain an assurance that the approved signalling design is complete (without any
omissions or overlaps), especially where separate parts of the design are produced by
different AEOs
• establish the verification and validation requirements that ensures the signalling design
meets signalling principles and agreed functional requirements
• establish the verification and validation requirements that ensures signalling subsystems
(not yet integrated into the whole system) are in accordance with the signalling design,
signalling principles and agreed functional requirements
• establish the scope of residual on-site testing of signalling system and subsystems
subsequent to any off-site testing
• establish the verification and validation requirements that ensures the signalling system,
incorporating all its subsystems and apparatus are in accordance with the signalling
design, signalling principles and agreed functional requirements (to the extent affected by
the new or altered works)
The commissioning engineer may restrict the extent of delegation that is assigned to the
signalling tester in-charge, and as such shall retain the residual components of the role. The
functions and responsibilities that are delegated to the signalling tester in-charge and any
residual components of the role retained by the commissioning engineer shall be formally and
clearly recorded. Such records shall be included in the relevant work packages.
© State of NSW through Transport for NSW 2019 Page 47 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
13.5. Signalling system certifier responsibilities Signalling system certifiers conduct end to end testing of the signalling system, to the extent
affected by the work, to provide certification for commissioning.
The signalling system is wholly comprised of its subsystems and apparatus. It is inclusive of all
signalling elements, such as the signalling interlocking, train control and management system,
trackside apparatus, ATP system, connecting cables, distributed signalling power supply
network, generated signalling air supply and reticulation system, signalling communication
network and so on, as applicable.
Signalling system certifiers shall be responsible for verifying that the signalling system, as
affected by the work, performs in accordance with the signalling design, signalling principles
and agreed functional requirements. This shall only be done once all the subsystems and
apparatus are integrated to form the whole signalling system.
The expertise of the signalling system certifier can differ depending on the project scope,
complexity and effects the work has on the signalling system. For example, on a whole re-
signalling project, the signalling system testing shall encompass the entire system and all its
interfaces. The signalling system certifier in this case shall be sourced from a relevant design
AEO.
Conversely, where the work is of a minor nature and alters only a small part of the signalling
system, such as a turnout renewal or a signal upgraded to LED type, the system testing is less
extensive than the previous example. In this case, the signalling system certifier may be the
commissioning engineer or delegated tester, subject to holding relevant competency
commensurate with the task.
The type of interlocking can also influence the expertise required of the signalling system
certifier. For example, where the alteration is totally confined to a mechanical interlocking, an
interlocking tester holding appropriate competency may perform the system testing.
Note: A specific competency for interlocking testing (equivalent to an interlocking
certificate) is required to test mechanical interlocking frames greater than eight levers.
Refer to T HR SC 02000 ST for further information.
The signalling system certifier shall co-plan and co-direct the signalling system testing with the
signalling tester in-charge, particularly where the testing is of a specialty nature and the
planning requirements are beyond the base expectations of the signalling tester in-charge.
Examples of such systems can include computerised train control, CBI or ATP. However, the
signalling tester in-charge shall retain overall responsibility for the planning and directing tasks.
© State of NSW through Transport for NSW 2019 Page 48 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
The following list of functions is applicable to a signalling system certifier:
• design integrity (principles) testing of signalling systems
• function testing to control tables of signalling systems
• system indication function test, end function test, through function test of signalling systems
• interlocking testing of mechanical main frames
• aspect sequence testing of signalling systems
• correspondence testing (including any out of correspondence testing) of signalling systems
The aforementioned requirements for signalling system testing shall be established by the
signalling tester in-charge in collaboration with the relevant design AEOs. See Section 13.4 for
further information.
13.6. Signalling subsystem certifier responsibilities Signalling subsystem certifiers conduct testing of associated signalling subsystems, to provide
certification for commissioning.
Signalling subsystems are the major parts of the signalling system, when integrated form the
whole signalling system. Signalling subsystems include signalling interlocking, train control and
management system, trackside apparatus, ATP system, connecting cables, distributed
signalling power supply network, generated signalling air supply and reticulation system,
signalling communication network and so on, as applicable. Where determined by the relevant
inspection and test plan, signalling subsystems can also include the integration of ATP system
(trackside) with on-board systems.
Signalling subsystem certifiers may also certify individual signalling apparatus (such as
trackside equipment) for items relevant to the subsystem on the condition that they hold the
associated competency for the task. For example, a signalling subsystem certifier testing the
circuits of an interlocking related to a new or altered turnout, may also conduct the associated
relay or I/O testing for the points once the points are physically connected to the interlocking, on
condition that the tester holds the additional competency.
The testing of signalling subsystems may be apportioned into manageable and logical parts of
the whole subsystem and as such, the portions may be separately certified; for example,
attesting specific pages of a circuit book. In this case, the signalling tester in-charge shall
consolidate all the individual tested portions and attest the whole circuit book (as affected by the
work). The signalling tester in-charge shall assess and mitigate any risks associated with
apportioning the testing in this regard.
The signalling subsystem certifier shall co-plan and co-direct the signalling subsystem testing
with the signalling tester in-charge, particularly where the testing is of a specialty nature and the
planning or consolidation requirements are beyond the base expectations of the signalling tester © State of NSW through Transport for NSW 2019 Page 49 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
in-charge. Examples of such subsystems can include computerised train control, CBI or ATP.
This delegation extends to the consolidation of any apportioned testing done on the subsystem.
However, the signalling tester in-charge shall retain overall responsibility for the planning and
directing tasks.
Any determination to test the various elements of a subsystem, either off-site or on-site shall be
made by the signalling tester in-charge in collaboration with relevant design AEOs. See
Section 13.4 for further information.
Signalling subsystem certifiers shall apply a rigorous process to satisfy themselves of a safe
and reliable outcome for the subsystem tested by them.
The following list of functions is applicable to a signalling subsystem certifier:
• testing of signalling circuits
• function testing of signalling circuits
• function testing to control tables of signalling interlocking subsystems
• design integrity (principles) testing of signalling interlocking subsystems
• interlocking testing of mechanical ground frames
• testing of train control and management subsystems
• testing of signalling communication and telemetry subsystems
• testing of signalling power supply subsystems
• testing of signalling air supply and reticulation subsystems
• testing of ATP subsystems
13.7. Apparatus certifier responsibilities Apparatus certifiers conduct testing of individual signalling apparatus, to provide certification for
commissioning.
Signalling apparatus generally pertains to trackside signalling equipment, such as points,
signals, trainstops, track circuits, axle counters, traction bonding, level crossing protection
equipment, releasing devices, mechanical interlocking items, ATP and ASDO balises, cables,
individual air supply and reticulation items and so on. Additionally, this category includes
individual items installed in signalling housings, such as relays, power supply equipment, ATP
lineside equipment units (LEU), communication and telemetry equipment (such as remote
terminal units), and condition monitoring equipment.
Apparatus certifiers are not permitted to certify signalling subsystems, unless they also hold the
relevant signalling subsystem certifier role.
© State of NSW through Transport for NSW 2019 Page 50 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
The responsibility of apparatus certifiers shall be generally confined to the testing of individual
signalling equipment (or equipment sets such as points), when installed. However, the scope of
testing and certification may be extended beyond the realms of the individual equipment, up to
the point of interface with the interlocking; for example, control or indication relays, CBI outputs
and inputs, or ATP LEUs. The extent of testing shall depend on the specific competencies held
by the duty holder. For example, an apparatus certifier testing a trainstop may be permitted to
function test the trainstop detection relays (or CBI inputs) when certifying the associated
trainstop; or an apparatus certifier testing points may be permitted to function test the points
detection relays (or CBI inputs) when certifying the associated point equipment.
Such determinations shall be made by the signalling tester in-charge and shall be based on the
duty holder’s competency and proficiency level, commensurate with the complexity of the
prevailing arrangements.
The following list of testing and certification functions is applicable to an apparatus certifier:
• signals and trackside indicators
• trainstops
• points and associated equipment
• vital rail vehicle detection equipment
• level crossing protection equipment
• releasing devices
• ATP and ASDO trackside equipment (not subsystem)
• signalling communication and telemetry equipment (not subsystem)
• signalling power supply equipment (not subsystem)
• signalling air supply and reticulation equipment (not subsystem)
• electrical conductor insulation
• mechanical interlocking items (not interlocking frames)
• signalling plans and track insulation plans
13.8. Structural and ancillary certifier responsibilities Structural and ancillary certifiers conduct inspection of signalling buildings, structures, ground
excavations and foundations that are associated with signalling equipment, to provide
certification for commissioning. They also certify the ancillary systems fitted in signalling
housings for conformance to relevant building codes and standards, as they pertain.
Signalling buildings in this context are defined as signalling relays rooms, bungalows,
cupboards or other housings containing signalling equipment, including associated foundations, © State of NSW through Transport for NSW 2019 Page 51 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
pathways, fences and gates, as applicable. Signalling structures in this context are defined as
the signal posts, signal gantries, associated ladders, landings, railings, foundations and the like.
Additionally, items in this category include signalling-services routes, such as buried, ground
level and above ground routes.
Ancillary systems for this category are defined as those supporting systems fitted in signalling
housings, such as lighting, electrical outlets, ventilation and air conditioning, security items, fire
control equipment, water, drainage, telephones, intercoms, closed-circuit television (CCTV), and
the like.
Structural and ancillary certifiers shall be responsible for certifying the items inspected by them.
The provision of assurance shall be made to the commissioning engineer prior to the items
becoming operational.
The signalling tester in-charge shall ensure such certifiers are resourced, based on their
qualifications, competency and proficiency level, commensurate with the work type and
complexity of arrangements.
The following list of inspection and certification functions is applicable to a structural and
ancillary certifier:
• signalling buildings and cupboards, associated foundations, pathways, fences and gates
• signalling structures such as signal posts, signal gantries, associated ladders, landings,
railings, and foundations
• signalling-services routes, inclusive of any hold-point release inspections
• ancillary systems (supporting systems) such as lighting, electrical outlets, ventilation and
air conditioning, security items, fire control equipment, water, drainage, telephones,
intercoms, CCTV, and the like
13.9. Signalling test assistant responsibilities Signalling test assistants provide assistance to lead testers when testing signalling systems,
signalling subsystems and signalling apparatus, in preparation for commissioning.
The signalling test assistants may provide assistance for all tests, commensurate with their level
of competency.
Signalling test assistants shall be responsible for diligently following the instructions issued by
the lead tester. They shall remain alert to ensure that they apply the test only to the correct
circuit portion, terminal, apparatus or control. They shall enquire with the lead tester, if they are
unclear of any instruction or testing requirement, or if there is a doubt on the exact location of
any testing point.
© State of NSW through Transport for NSW 2019 Page 52 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Signalling test assistants shall be vigilant of any error, defect or omission that can be present
with the item under test or the test equipment used, and immediately advise the lead tester if
noted.
13.10. Licensed signalling personnel responsibilities Licensed signalling personnel are responsible for carrying out tasks on operational signalling or
applying signalling safeworking. Only personnel holding a valid signalling licence shall
undertake work on operational signalling or apply signalling safeworking.
The type of tasks allocated to licensed signalling personnel shall be commensurate with the
duty holder's competency and within the authority level provisions stated in signalling
safeworking procedures.
The following tasks are associated with licensed signalling personnel for the delivery of new or
altered works:
• booking (certifying) signalling apparatus into use or out of use
• disconnection and subsequent reconnection of operational signalling equipment for the
purpose of securing signalling out of use
• application of temporary wiring, temporary bridges or temporary repairs
• connection of any new or altered wiring or apparatus to working circuits or working power
supplies
• reinstatement of any dislodged wire or equipment
• investigation and rectification of signalling failures caused by the project work
• liaison with network operators for the purpose of signalling safeworking
• provision of manual releases, and so on
Additionally, licensed signalling personnel shall be allocated to tasks having a high potential for
causing disturbance to operational infrastructure, such as when hand-tracing fragile wiring
during correlation of existing installations.
Licensed signalling personnel shall be responsible for carrying out their tasks in accordance
with signalling safeworking procedures, and network rules and network procedures. They shall
not perform any task that is contrary to these requirements, unless special agreed provisions
have been arranged between the operator and maintainer RIM and the ASA.
© State of NSW through Transport for NSW 2019 Page 53 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
14. Mapping duty holder roles to critical signalling functions In most cases, testing of new or altered signalling encompasses many individual tests, which
when combined make up the whole test. For example, when circuit wiring is certified, the tester
is required to perform a number of tests in addition to continuity (bell) testing to enable a
complete certification of the wiring. The additional tests would include a documentation check,
wire count, null count, apparatus inspection, insulation test and possibly a wire hand-trace.
For this reason, duty holders tasked with testing functions shall be capable of performing all the
individual functions (tests, in this case) that are required of the role.
Each duty holder shall hold a set range of testing competencies, accordingly mapped to the
critical signalling functions listed in Table 1. This is to ensure the integrity and completeness of
the safety elements for the work being tested. For example, the duty holder role of circuit tester
shall be capable of performing a documentation check, continuity (bell) test, wire count, null
count, apparatus inspection, insulation test, and wire hand-trace.
Another example refers to the role of circuit-function tester, where the duty holder shall hold the
prerequisite competencies of the circuit tester, along with the competencies for performing other
tests. Such tests include contact proving test, strap and function test, circuit-function test,
through-circuit test, power supply isolation and earth leakage test, correspondence test, aspect
sequence test, and various system tests.
Table 1 provides the mapping of duty holder roles to the critical signalling functions.
© State of NSW through Transport for NSW 2019 Page 54 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Table 1 – Mapping of duty holder roles to the critical signalling functions
Critical signalling function
Commissioning engineer
Signalling tester in-charge
Signalling system certifier
Signalling subsystem certifiers Trackside apparatus certifier
Structural and ancillary certifier IXL CT CFT CS ATP PS AIR
Plan overall inspection and testing - - - - - - - - - -
Plan specific inspection and testing 1 1 1 1 1 1 1 1 1 1 1 1
Allocate resources for overall inspection and testing
- - - - - - - - - -
Allocate resources for specific inspection and testing
1 1 1 1 1 1 1 1 1 1 1 1
Issue signalling permit to work - - - - - - - - - - -
Approve work packages - - - - - - - - - - -
Overall control of field-issued signalling design documentation
- - - - - - - - - -
© State of NSW through Transport for NSW 2019 Page 55 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Critical signalling function
Commissioning engineer
Signalling tester in-charge
Signalling system certifier
Signalling subsystem certifiers Trackside apparatus certifier
Structural and ancillary certifier IXL CT CFT CS ATP PS AIR
Apply signalling safeworking (including booking existing signalling out and into use)
4 - - - - - - - - - - -
Certify documentation check 1 1 1 1 1 1 1 1 1 1 1 1
Certify apparatus inspection 1 1 1 1 1 1 1 1 1 1 1 1
Certify wire hand-trace - - - - - - - -
Certify wire count and null count - - - - - - - -
Certify continuity test (bell test) - - - - - - - -
Certify insulation test - - - - - - 1 -
Certify contact proving test - - - - - - - 1 -
Certify strap and function test - - - - - - - - -
Certify circuit function test - - - - - - - - -
© State of NSW through Transport for NSW 2019 Page 56 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Critical signalling function
Commissioning engineer
Signalling tester in-charge
Signalling system certifier
Signalling subsystem certifiers Trackside apparatus certifier
Structural and ancillary certifier IXL CT CFT CS ATP PS AIR
Certify circuit through function test - - - - - - - - -
Certify apparatus function test • trackside signalling
apparatus • Includes power
supply equipment (not sub-system)
• air supply and reticulation equipment (not subsystem)
• mechanical interlocking items (keys, locks, signage, warding)
• trackside ATP and ASDO equipment (not subsystem)
• communication and telemetry equipment (not subsystem)
1 1 - 1 1 1 1 1 1 1 -
© State of NSW through Transport for NSW 2019 Page 57 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Critical signalling function
Commissioning engineer
Signalling tester in-charge
Signalling system certifier
Signalling subsystem certifiers Trackside apparatus certifier
Structural and ancillary certifier IXL CT CFT CS ATP PS AIR
Certify signalling power supply isolation test and earth leakage test
- - - - - 1 -
Certify signalling power supply (subsystem) 1 1 - - - - - - - - -
Certify signalling air supply and reticulation (subsystem)
- - - - - - - - - - -
Certify ATP (subsystem) 1 1 - - - - - - - - -
Certify train control (sub-system) 1 1 - - - - - - - - -
Certify building, structure, foundation, excavation, ancillary equipment
- - - - - - - - - - - 1
Certify correspondence test (includes out of correspondence test)
- - - - - - - -
Certify aspect sequence test - - - - - - - -
© State of NSW through Transport for NSW 2019 Page 58 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Critical signalling function
Commissioning engineer
Signalling tester in-charge
Signalling system certifier
Signalling subsystem certifiers Trackside apparatus certifier
Structural and ancillary certifier IXL CT CFT CS ATP PS AIR
Certify system function tests (indication-function test, end-function test and through-function test)
- - - - - - - -
Certify interlocking function test to control tables mechanical frames up to eight levers
1 1 - - - - - - - -
Certify interlocking function test to control tables mechanical frames greater than eight levers
3 3 3 3 - - - - - - - -
Certify interlocking function test to control tables electrical and CBI interlockings
2 2 2 2 - - - - - - - -
Certify interlocking design integrity (principles) test
2 2 2 2 - - - - - - - -
Certify signalling and track insulation plans - - - 1 1 1 1 -
© State of NSW through Transport for NSW 2019 Page 59 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Critical signalling function
Commissioning engineer
Signalling tester in-charge
Signalling system certifier
Signalling subsystem certifiers Trackside apparatus certifier
Structural and ancillary certifier IXL CT CFT CS ATP PS AIR
Certify signalling design office copy documents (COC)
- - - - - - - - - - -
Commission new or altered signalling into operational use
- - - - - - - - - - -
Legend
IXL interlocking tester ATP ATP subsystem certifier
CT circuit tester PS signalling power supply subsystem certifier
CFT circuit function tester AIR signalling air supply and reticulation subsystem certifier
CS train control subsystem certifier
Denotations
1 subject to holding competency for specific equipment (product, brand and type) or specific subsystem
2 a competent tester, generally sourced from the design AEO is required to test complex new or altered signalling
3 a specific competency is required for testing mechanical frames greater than eight levers
4 signalling safeworking tasks may be allocated to other licensed signalling personnel in accordance with signalling safeworking procedures, subject to them holding relevant competency
The provisions of Table 1 are subject to any conditions or restrictions stated in the duty holder's signalling permit to work.
© State of NSW through Transport for NSW 2019 Page 60 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
14.1. Specific functions for duty holders holding limited competencies Duty holders holding limited competencies that enable them to perform only specific functions
(that are less than the bundled functions shown in Table 1), may be permitted to perform such
functions subject to a risk assessment. The assessment shall evaluate the integrity of each
individual test or functional component of a task when executed in isolation, as opposed to
when done together with other tests or tasks.
Certain basic tests may be done in isolation or with a lesser amount of combined individual
tests, or done as non-certified checks. For example, a tester may be assigned to perform only a
documentation check or a correlation check (comprising non-certification tests, such as wire
hand-trace, wire count, null count and apparatus inspection) of an existing installation. Further
examples include the certification tests of wire count and null count following removal of
redundant wiring at the end of a project, or insulation tests of newly installed cables. In these
cases, the competencies of duty holders may be less than the duty holder required to perform
the circuit continuity testing (circuit tester) as stated in Table 1.
The risk assessment shall be conducted by the signalling tester in-charge in collaboration with
the following entities, as necessary:
• commissioning engineer (where different to the signalling tester in-charge)
• commissioning AEO
• design AEO
• project delivery RIM
• operator and maintainer RIM
14.2. Multiple roles A duty holder may be allocated more than one role in performing their duties. For example, the
role of circuit tester may also be allocated the role of apparatus certifier; alternatively (or
additionally) this duty holder may also be the licensed signalling person who applies signalling
safeworking for the project.
The signalling tester in-charge shall assess the risks associated with allocating multiple testing
roles to the same individual.
© State of NSW through Transport for NSW 2019 Page 61 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
14.3. Independence of inspection and testing personnel The principle of independent inspection and testing of new or altered signalling work is that no
safety critical outcome should rely solely on one person doing and also certifying their own
work.
In essence, any person who has installed vital equipment or circuits, or written data files for new
or altered signalling shall not carry out the certification inspection and tests of the particular
elements that they have created.
In deciding the appropriate degree of independence, a balanced assessment shall be
necessary depending on the nature and complexity of the work. Additionally, the competency
and proficiency level, as well as the licence level (if applicable) of the duty holder performing the
work shall be taken into account. The lack of availability of suitable personnel shall not justify
any lessening or absence of the required independence.
The signalling tester in-charge shall assess the risks associated with independence of
inspection and testing personnel.
15. Competency requirements Competency requirements for roles pertaining to the critical signalling functions of inspection,
testing and commissioning shall comply with TfNSW competency standards, the Rail Safety
National Law (NSW) and the commissioning AEO's competency management system. The
commissioning AEO shall ensure the engineering activities are performed by suitably trained
and proficient personnel; that is, personnel designated as 'competent' persons. This is required
to meet the legislative and regulatory obligations of the Rail Safety National Law (NSW),
AS 4292.1 and the requirements outlined in T MU CY 10503 GU AEO Guide to Engineering
Competence Management and T HR CY 03000 ST Competency Standard - Signalling.
The roles for critical signalling functions shall be allocated only to competent personnel having a
suitable proficiency level for the intended function; such that they are capable of fulfilling the
entire task. They shall be capable of providing the necessary assurance with sufficient evidence
so that the commissioning engineer can sign-off the completed signalling works.
The commissioning engineer, together with the signalling tester in-charge shall be satisfied that
the resources used for performing roles in critical signalling functions meet competency and
proficiency requirements. They shall properly instruct duty holders of their intended tasks. The
signalling permit to work process is an enabler that supports these requirements.
© State of NSW through Transport for NSW 2019 Page 62 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
15.1. Assessment of duty holders The commissioning AEO shall conduct a formal assessment of each duty holder candidate
intended to perform critical signalling functions specified in this document. The assessment
shall seek demonstrable knowledge and experience by application of defined processes in
accordance with the Rail Safety National Law (NSW) (which refers to the Australian Quality
Training Framework, the Australian Qualifications Framework and other national regulations),
and T HR CY 03000 ST using assessment tools, performance criteria and evidence based
analysis.
The assessment shall evaluate the candidate in the following elements:
• behavioural competencies
• knowledge of applicable signalling principles
• subject matter expertise in the relevant product or service
• applied knowledge of related domain-specific requirements; namely ASA requirements,
project delivery RIM requirements and operator and maintainer RIM requirements as
applicable
Candidates shall hold the required pre-requisite qualifications for the intended role prior to the
assessment.
Where candidates already hold the required competency, as registered in the national rail
industry worker competency database, then the commissioning AEO shall ensure the
candidate's competency meets the following criteria:
• the competency is valid and current
• the competency is relevant for the intended network and role (meeting domain-specific
functional requirements)
• there are no restrictions, limitations or breach penalties that could impact the delivery of
work and provision of assurance for the intended role
• the attainment of competency meets the commissioning AEO’s own competency
management requirements
Although the accountability for competency management is held by commissioning AEOs, the
operator and maintainer RIM should review the AEO’s competency management system. This
is done as part of due diligence in order to gain an assurance of the critical signalling functions
performed. The review should be undertaken at the earliest opportunity.
Note: The attainment of network-specific signalling licences and authorisations are
done in accordance with operator and maintainer RIM requirements. See Section 8 for
more information on signalling licences and authorisations.
© State of NSW through Transport for NSW 2019 Page 63 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
15.2. Duty holder performance history The commissioning AEO shall be accountable for checking the duty holder’s performance
history in respect to any restrictions or prohibitions and as such, a disclosure shall be sought
from the duty holder. Additionally, where required, background checks shall be made with
industry peers, other AEOs, the project delivery RIM and the operator and maintainer RIM, as
applicable.
Duty holders shall not perform work contrary to such restrictions or exclusions.
The commissioning AEO shall keep a list of all personnel they intend to use for the performance
of critical signalling functions, irrespective of whether the work is planned to be done within
green-field sites (as managed by the project’s processes) or within operational areas (as
governed by the signalling permit to work process).
The list shall be made available to the operator and maintainer RIM (if requested) so as to
enable them to exercise their legislative and regulatory obligations as RIM in accordance with
the Rail Safety National Law (NSW).
15.3. Assessment pathways for attaining roles in critical signalling functions Figure 1 identifies the different candidate pathways for attaining duty holder roles to perform
critical signalling functions. Figure 1 specifically highlights the distinction between the attainment
of a competency and the attainment of an authorisation or licence, pertaining to critical
signalling functions.
While the outcomes shown in Figure 1 enable the duty holder to perform the stated work, the
level of work-complexity assigned shall be commensurate with the duty holder’s demonstrated
performance and proficiency level.
© State of NSW through Transport for NSW 2019 Page 64 of 65
T HR SC 07111 ST Mandatory Requirements for Inspection, Testing and Commissioning of New or Altered Signalling - Part 1
Version 1.0 Issue date: 04 September 2019
Assessment process governed by commissioning AEO
Assessment process governed by operator and maintainer RIM
Assessment process governed by operator and maintainer RIM
Competent signalling person Authorised signalling person Licensed signalling person
Possesses pre-requisite qualifications
Possesses pre-requisite qualifications and competencies
Possesses pre-requisite qualifications and competencies
Gains Knowledge(in accordance with ASA,project delivery RIMand operator and maintainer RIM requirements)• Behavioural• applicable signalling
principles• expertise in product/service• Domain-specific requirements
for product/service
Gains Knowledge(in accordance with operator and maintainer RIM domain requirements)• behavioural• signalling hazards• specific restrictions• RIM notifications & advices• management of operational
issues arising from the works
Gains Knowledge(in accordance with operator and maintainer RIM domain requirements)• behavioural• signalling principles• signalling safeworking• incident management• signalling requirements• network rules-procedures
Undertakes assessment Undertakes assessment Undertakes assessment
Authorisedto perform work within operational signalling environments for signalling commissioning functions(does not permit duty holder to interfere with operational signalling or apply signalling safeworking)
Licensedto work on operational signalling and apply signalling safeworking for signalling commissioning functions
Competentto perform work for signalling commissioning functions(does not permit duty holder to work within operational signalling environments)
© State of NSW through Transport for NSW 2019 Page 65 of 65
Figure 1 - Assessment pathways for roles in critical signalling functions