T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of...

24
© State of NSW through Transport for NSW 2020 Underground Installation Configurations for High Voltage and 1500 V DC Cables T HR EL 20003 ST Standard Version 2.0 Issue date: 24 December 2020

Transcript of T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of...

Page 1: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

© State of NSW through Transport for NSW 2020

Underground Installation Configurations for High Voltage and 1500 V DC Cables

T HR EL 20003 ST

Standard

Version 2.0

Issue date: 24 December 2020

Page 2: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020

Important message This document is one of a set of standards developed solely and specifically for use on

Transport Assets (as defined in the Asset Standards Authority Charter). It is not suitable for any

other purpose.

The copyright and any other intellectual property in this document will at all times remain the

property of the State of New South Wales (Transport for NSW).

You must not use or adapt this document or rely upon it in any way unless you are providing

products or services to a NSW Government agency and that agency has expressly authorised

you in writing to do so. If this document forms part of a contract with, or is a condition of

approval by a NSW Government agency, use of the document is subject to the terms of the

contract or approval. To be clear, the content of this document is not licensed under any

Creative Commons Licence.

This document may contain third party material. The inclusion of third party material is for

illustrative purposes only and does not represent an endorsement by NSW Government of any

third party product or service.

If you use this document or rely upon it without authorisation under these terms, the State of

New South Wales (including Transport for NSW) and its personnel does not accept any liability

to you or any other person for any loss, damage, costs and expenses that you or anyone else

may suffer or incur from your use and reliance on the content contained in this document. Users

should exercise their own skill and care in the use of the document.

This document may not be current and is uncontrolled when printed or downloaded. Standards

may be accessed from the Transport for NSW website at www.transport.nsw.gov.au

For queries regarding this document, please email the ASA at [email protected] or visit www.transport.nsw.gov.au

Page 3: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 3 of 24

Standard governance

Owner: Lead Electrical Engineer, Asset Standards Authority

Authoriser: Chief Engineer, Asset Standards Authority

Approver: Executive Director, Asset Standards Authority on behalf of the ASA Configuration Control Board

Document history

Version Summary of changes

1.0 Initial release, 25 June 2014.

2.0 Second issue. The changes from the previous version include updates to reflect organisational changes and resulting changes in responsibilities, minor amendments and clarification to content.

Page 4: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 4 of 24

Preface The Asset Standards Authority (ASA) is a key strategic branch of Transport for NSW (TfNSW).

As the network design and standards authority for NSW Transport Assets, as specified in the

ASA Charter, the ASA identifies, selects, develops, publishes, maintains and controls a suite of

requirements documents on behalf of TfNSW, the asset owner.

The ASA deploys TfNSW requirements for asset and safety assurance by creating and

managing TfNSW's governance models, documents and processes. To achieve this, the ASA

focuses on four primary tasks:

• publishing and managing TfNSW's process and requirements documents including TfNSW

plans, standards, manuals and guides

• deploying TfNSW's Authorised Engineering Organisation (AEO) framework

• continuously improving TfNSW’s Asset Management Framework

• collaborating with the Transport cluster and industry through open engagement

The AEO framework authorises engineering organisations to supply and provide asset related

products and services to TfNSW. It works to assure the safety, quality and fitness for purpose of

those products and services over the asset's whole-of-life. AEOs are expected to demonstrate

how they have applied the requirements of ASA documents, including TfNSW plans, standards

and guides, when delivering assets and related services for TfNSW.

Compliance with ASA requirements by itself is not sufficient to ensure satisfactory outcomes for

NSW Transport Assets. The ASA expects that professional judgement be used by competent

personnel when using ASA requirements to produce those outcomes.

About this document

This standard sets out the technical requirements for underground installation configurations for

high voltage ac and 1500 V dc cables in the TfNSW Metropolitan Heavy Rail Network.

This is the second issue of this standard. The changes to previous content include the following:

• updates to reflect organisational changes and resulting changes in responsibilities

• minor amendments and clarification to content

Page 5: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 5 of 24

Table of contents 1. Introduction .............................................................................................................................................. 6

2. Purpose .................................................................................................................................................... 6 2.1. Scope ..................................................................................................................................................... 6 2.2. Application ............................................................................................................................................. 7

3. Reference documents ............................................................................................................................. 7

4. Terms and definitions ............................................................................................................................. 8

5. General requirements ............................................................................................................................. 9 5.1. Installations within the rail corridor ........................................................................................................ 9 5.2. Installations outside of rail corridor ........................................................................................................ 9

6. Minimum depth of installation ................................................................................................................ 9 6.1. Reduced depth of installation .............................................................................................................. 11

7. Cable protection covers ........................................................................................................................ 12 7.1. Additional protection for direct buried cables ....................................................................................... 12 7.2. Protection of cables in a duct bank ...................................................................................................... 12

8. Warning marker tapes ........................................................................................................................... 12

9. Separation from other cables and services ........................................................................................ 12 9.1. Separation from cables and services that are not part of TfNSW Metropolitan Heavy Rail Network . 13 9.2. Separation from cables and services of the TfNSW Metropolitan Heavy Rail Network ...................... 13

10. Distributed temperature sensing fibre-optic cables and pilot wire cables ..................................... 14

11. Cable route markers .............................................................................................................................. 14 11.1. Cable route markers within the rail corridor ..................................................................................... 14 11.2. Cable route markers outside of the rail corridor .............................................................................. 14

12. Direct laid system .................................................................................................................................. 15

13. Duct laid system .................................................................................................................................... 15 13.1. Properties of ducts ........................................................................................................................... 16 13.2. Minimum duct diameter ................................................................................................................... 16 13.3. Provision of spare ducts .................................................................................................................. 16 13.4. Arrangement of ducts in a trench .................................................................................................... 17 13.5. Ducts installed by trenchless technology ......................................................................................... 17 13.6. Undertrack crossings ....................................................................................................................... 18

14. As-built design documentation ............................................................................................................ 19

Appendix A Typical installation configurations .................................................................................. 20

Page 6: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 6 of 24

1. Introduction The feeders of the RailCorp high voltage (HV) distribution system consist of both cables and

overhead conductors with nominal voltages of between 11 kV and 132 kV. Cables with a rated

voltage of 3.8/6.6 kV are also used in the 1500 V dc traction power supply system in the

RailCorp electrical network.

Refer to T HR EL 20004 ST High Voltage AC and 1500 V DC Traction Power Supply Cable

Infrastructure – Standards for Design and Construction for design and construction

requirements of these cables. Refer to T HR EL 20004 GU High Voltage AC and 1500 V DC

Traction Power Supply Cables – Design and Construction Guide for guidance on the

requirements of T HR EL 20004 ST.

Apart from cables of the RailCorp electrical network, HV cables of other organisations may also

be installed within the rail corridor.

2. Purpose This document aims to set out the requirements for underground installations of HV ac and

1500 V dc cables for the RailCorp electrical network.

2.1. Scope This document sets out the requirements for underground installations of HV ac cables with a

nominal voltage of up to 66 kV and 1500 V dc cables within the RailCorp electrical network.

This document also covers installation within the rail corridor of HV ac cables that are not part of

the RailCorp electrical network. See Section 5 for details.

This document covers the TfNSW Metropolitan Heavy Rail Network (formerly known as the

RailCorp network). Refer to TS TOC 1 Train Operating Conditions (TOC) Manual - General

Instructions, which defines the areas associated with the network. This document does not

cover the following:

• transition arrangements between underground and above ground cable installations, which

are covered in T HR EL 20006 ST High Voltage ac and 1500 V dc Cables – Transitions

Between Underground and Above Ground Installation Configurations

• cable pits, which are covered in T HR EL 20007 ST Cable Pits

• requirements for cables with a nominal voltage higher than 66 kV

Page 7: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 7 of 24

2.2. Application This document applies to underground installation of HV ac and 1500 V dc cables for all new

work, as well as alterations to existing installations. For alterations to existing installations, the

requirements of this document are applicable to the extent of new construction only.

This document applies to the underground installation of HV ac and 1500 V dc cables within

system substations of the RailCorp electrical network.

This document is not applicable to maintenance repairs to existing cable routes.

In addition to the requirements of this standard, asset decisions take into account the life cycle

cost considerations specified in T MU AM 01001 ST Life Cycle Costing.

If the intent of stated requirements in this standard is not clear, a clarification should be sought

from the Lead Electrical Engineer, ASA.

3. Reference documents The following documents are cited in the text. For dated references, only the cited edition

applies. For undated references, the latest edition of the referenced document applies.

Australian standards

AS 1379 Specification and supply of concrete

AS 1906.1 Retroreflective materials and devices for road traffic control purposes –

Retroreflective sheeting

AS 2067 Substations and high voltage installations exceeding 1 kV a.c.

AS 4702 Polymeric cable protection covers

AS 4799 Installation of underground utility services and pipelines within railway boundaries

AS/CA S009 Installation requirements for customer cabling

AS/NZS 1477 PVC pipes and fittings for pressure applications

AS/NZS 2053.2 Conduits and fittings for electrical installations – Rigid plain conduits and fittings

of insulating material

AS/NZS 2648.1 Underground marking tape – Non-detectable tape

AS/NZS 3000 Electrical Installations (known as the Australian/New Zealand Wiring Rules)

AS/NZS 4130 Polyethylene (PE) pipes for pressure applications

Transport for NSW standards

ESC 215 Transit Space

Page 8: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 8 of 24

M209 Road Openings and Restoration

Available at rms.nsw.gov.au

SPC 207 Track Monitoring Requirements for Undertrack Excavation

SPG 0705 Construction of Cable Routes and Signalling Civil Works

T HR CI 12190 ST Service Installations within the Rail Corridor

T HR EL 12002 GU Electrolysis from Stray DC Current

T HR EL 12005 ST Bonding for 1500 V DC Traction Systems

T HR EL 20004 GU High Voltage AC and 1500 V DC Traction Power Supply Cables – Design

and Construction Guide

T HR EL 20004 ST High Voltage AC and 1500 V DC Traction Power Supply Cable

Infrastructure – Standards for Design and Construction

T HR EL 20006 ST High Voltage ac and 1500 V dc Cables – Transitions Between Underground

and Above Ground Installation Configurations

T HR EL 20007 ST Cable Pits

T HR EL 20008 ST Underground Cables and Cable Enclosures – Location Data Recording

T HR TE 01001 ST Communication Outdoor Cabling

T MU AM 01001 ST Life Cycle Costing

TS TOC 1 Train Operating Conditions (TOC) Manual - General Instructions

Other reference documents

Australasian Society for Trenchless Technology 2009, Guidelines for Horizontal Directional

Drilling, Pipe Bursting, Microtunnelling and Pipe Jacking

NSW Streets Opening Coordination Council 2018, Guide to Codes and Practices for Streets

Opening

4. Terms and definitions The following terms and definitions apply in this document:

AEO Authorised Engineering Organisation

ASA Asset Standards Authority

HV high voltage; a voltage exceeding 1000 V ac or 1500 V dc (AS/NZS 3000)

LV low voltage; a voltage exceeding 50 V ac or 120 V ripple-free dc but not exceeding

1000 V ac or 1500 V dc (AS/NZS 3000)

TfNSW Transport for New South Wales

Page 9: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 9 of 24

5. General requirements Cables with a higher nominal voltage shall be installed at a depth greater than those with a

lower nominal voltage.

Within system substations, HV ac and 1500 V dc cable installations shall comply with AS 2067

Substations and high voltage installations exceeding 1 kV a.c.

Trenches shall not be covered until after location recording in accordance with

T HR EL 20008 ST Underground Cables and Cable Enclosures – Location Data Recording has

been made.

Ground line troughing (GLT) shall not be used in accordance with T HR EL 20004 ST.

Illustrations of typical installation configurations are included in Appendix A.

5.1. Installations within the rail corridor Installation of HV ac and 1500 V dc cable shall comply with T HR CI 12190 ST Service

Installations within the Rail Corridor.

Installation of HV ac cables that are not part of the RailCorp electrical network shall also comply

with AS 4799 Installation of underground utility services and pipelines within railway boundaries.

5.2. Installations outside of rail corridor Installation of HV ac and 1500 V dc cables within a registered easement of TfNSW shall comply

with the requirements for installations within the rail corridor.

Elsewhere, underground installations of HV ac and 1500 V dc cables outside of rail corridors

shall follow the requirements of the NSW Streets Opening Coordination Council (SOCC)

guideline Guide to Codes and Practices for Streets Opening for HV cables and the

requirements of the controlling authorities of the area. Agreement shall be obtained from the

relevant controlling authorities for any deviation from the requirements.

Installation of HV ac and 1500 V dc cables under roads controlled by TfNSW shall comply with

the requirements of M209 Road Openings and Restoration.

6. Minimum depth of installation For direct laid systems, the depth of installation is the vertical distance from the ground level to

the top of the cable. For duct laid systems, the depth of installation is the vertical distance from

the ground level to the top of the duct.

Within the rail corridor, the minimum depth of installation of HV ac and 1500 V dc underground

cables and their enclosures shall comply with AS 4799.

Page 10: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 10 of 24

Outside of the rail corridor, the minimum depth of installation of HV ac and 1500 V dc cables

shall follow the SOCC Guide for HV cables and the requirements of the controlling authorities of

the area.

Where HV ac and 1500 V dc cables are installed by trenchless technology, the top of the cable

duct shall be at a depth of not less than 1 m from ground level.

The minimum depths of installation for HV ac and 1500 V dc cables are summarised in Table 1

and Table 2.

Table 1 - Minimum depths of installation for HV ac and 1500 V dc cables within rail corridor

Location Minimum depth of installation

Notes

At undertrack crossings 2000 mm from top of rail In accordance with AS 4799

Within system substations 750 mm Installation by trenching; Protected in accordance with Section 7 and Section 8

Within system substations 1000 mm Installation by trenchless technology

Elsewhere 1000 mm In accordance with AS 4799

Elsewhere with reduced depth of installation in accordance with Section 6.1

500 mm Not to be constructed with trenchless technology

Table 2 - Minimum depths of installation for HV ac and 1500 V dc cables outside rail corridor

Location Nominal voltage (kV)

Minimum depth of installation

Notes

State roads controlled by TfNSW

All 1200 mm Unprotected; see M209

State roads controlled by TfNSW

All 1000 mm Protected; sleeved within concrete encasement; see M209

Regional and local roads controlled by councils

All See SOCC Guide to Codes and Practices for Streets Opening

Installation by trenching; See Section 6.1 for arrangements with reduced depth of installation

Regional and local roads controlled by councils

All 1000 mm Installation by trenchless technology

Page 11: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 11 of 24

Location Nominal voltage (kV)

Minimum depth of installation

Notes

Footways All See SOCC Guide to Codes and Practices for Streets Opening

Installation by trenching; See Section 6.1 for arrangements with reduced depth of installation

Footways All 1000 mm Installation by trenchless technology

6.1. Reduced depth of installation Where obstructions are present in the cable route and it is not reasonably practicable to remove

the obstructions, HV ac and 1500 V dc cables may be installed at a reduced depth, provided

that it satisfies all of the following conditions:

• the cables are laid in ducts

• the minimum depth of installation is 500 mm

• cable protection covers are provided

• adequate mechanical protection is provided around the ducts to prevent damage from

excavation as well as mechanical loads at the surface; where such protection is provided

by encasing the ducts in concrete, the concrete encasement shall extend beyond the edge

of the outermost duct by at least 100 mm at the top and bottom and 75 mm on each side

Cable protection covers may be omitted if the thickness of concrete encasement above the

top layer of ducts is 300 mm or more.

• additional warning labels located at or above ground level shall be installed at intervals of

not more than 3 m along the entire length with reduced depth of installation

• other provisions as required by the controlling authority of the area

Where mechanical protection is provided by encasing the ducts in concrete, the concrete

encasement materials shall be in accordance with all of the following:

• AS 1379 Specification and supply of concrete

• 20 MPa minimum strength grade

• 20 mm nominal aggregate size

• 120 mm slump

The minimum separation between ducts that are encased in concrete shall be 50 mm to allow

for the flow of the concrete.

Page 12: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 12 of 24

7. Cable protection covers Polymeric cable protection covers in accordance with AS 4702 Polymeric cable protection

covers or approved equivalent shall be provided above the bedding layer around cables and

their enclosures.

Cable protection covers shall be located directly above and overlap each cable or duct by not

less than 50 mm on each side.

7.1. Additional protection for direct buried cables For direct buried cables, cable protection covers in accordance with AS 4702 or approved

equivalent shall also be provided between cables of different circuits and between cables and

other services.

7.2. Protection of cables in a duct bank Where cables are installed in ducts in a shared trench arrangement and where ducts of other

services are installed directly above the HV ac and 1500 V dc cable ducts, the arrangement is

deemed to provide adequate protection for the HV ac and 1500 V dc cables. The protection

arrangement for the duct bank shall then be determined by the requirements of the services

occupying the top row of ducts. Refer to SPG 0705 Construction of Cable Routes and Signalling

Civil Works for cable protection arrangements for shared trenches with signals and

communications.

8. Warning marker tapes Orange warning marker tapes that comply with AS/NZS 2648.1 Underground marking tape –

Non-detectable tape shall be installed above the cable protection covers. The warning marker

tapes shall cover all areas directly above the cable protection covers.

Where cable protection covers are omitted for configurations with reduced depth of installation,

the warning marker tapes shall cover all areas directly above the concrete encasement.

Warning marker tapes may be omitted for configurations with reduced depth of installation if the

concrete encasement is extended to the ground level.

9. Separation from other cables and services Separation refers to the shortest distance measured between edges of cable ducts and edges

of cables for direct buried cables.

Separation distances greater than the minimum requirements may be required when the

following are considered:

• requirements of the controlling authority of the assets involved

Page 13: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 13 of 24

• maintenance and safeworking arrangements of the assets involved

• mutual heating effects on cable ratings

• risk of damage to cables as a result of fault conditions of other cables and services

9.1. Separation from cables and services that are not part of TfNSW Metropolitan Heavy Rail Network The separation between HV ac and 1500 V dc cables from cables and services that are not part

of the TfNSW Metropolitan Heavy Rail Network shall comply with the SOCC Guide, and shall

not be less than 300 mm.

9.2. Separation from cables and services of the TfNSW Metropolitan Heavy Rail Network Separation requirements exist between HV ac and 1500 V dc cables and other cables and

services of the TfNSW Metropolitan Heavy rail Network.

9.2.1. Separation from other HV ac and 1500 V dc cables The minimum separation between HV ac and 1500 V dc cables of different circuits shall be

150 mm horizontal and 225 mm vertical for direct buried cables. For cables in ducts, the

minimum separation between ducts shall be 50 mm.

Where a design proposes to have HV ac and 1500 V dc cables of different circuits separated by

a distance of less than 1000 mm, the designer shall assess the risk to network reliability caused

by the failure of more than one circuit from a single event. The design configuration shall be

approved by the relevant authority of the operation and maintenance AEO.

9.2.2. Separation from low voltage cable Minimum separation from low voltage cables shall be 150 mm horizontal and 225 mm vertical

for direct buried cables. For cables in ducts, the minimum separation between the ducts shall be

50 mm.

9.2.3. Separation from signalling cables Separation from signalling cables shall comply with the requirements of SPG 0705.

9.2.4. Separation from communication cables Separation from communication cables shall comply with the requirements of

T HR TE 01001 ST Communication Outdoor Cabling and AS/CA S009 Installation requirements

for customer cabling.

Page 14: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 14 of 24

9.2.5. Separation from other services The separation between HV ac and 1500 V dc cables and other services such as gas and water

shall not be less than 300 mm.

10. Distributed temperature sensing fibre-optic cables and pilot wire cables Where distributed temperature sensing fibre-optic cables and pilot wire cables (metallic or fibre-

optic) for a HV feeder are installed along the same route as the power cables, they are

considered to be part of the HV cable circuit. The separation requirements between power and

communication cables do not apply to these cables.

Where the power cables are installed in ducts, a separate duct shall be provided for the pilot

wire cable.

Pilot wire cables shall be installed below the associated power cables.

11. Cable route markers Cable route markers complying with AS 4799 shall be provided to indicate the location of the

underground cables.

The heights of markers above ground level and their orientation may be varied from the

requirements of AS 4799 to suit local conditions. The dimensional and installation details of

markers shall be approved by the controlling authority of the area.

11.1. Cable route markers within the rail corridor Cable route markers shall be provided in accordance with AS 4799. The following requirements

shall also be satisfied:

• Markers shall be located to satisfy the clearance requirements of ESC 215 Transit Space.

• Markers shall not obstruct footpaths, walkways or vehicle access ways. Marker plates shall

be made from Class 1100 retroreflective sheeting with yellow background in accordance

with AS 1906.1 Retroreflective materials and devices for road traffic control purposes –

Retroreflective sheeting.

11.2. Cable route markers outside of the rail corridor Cable route markers shall be provided in accordance with AS 4799, except for the following:

The minimum distance between consecutive markers may be more than 200 m, but not less

than the line of sight.

The installation details and materials may be varied to suit local conditions.

Page 15: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 15 of 24

12. Direct laid system Cables directly buried in a trench shall be buried in clean sand. The clean sand shall provide

bedding at the bottom and across the entire width of the trench in order to achieve the following:

• the distance between the bottom of the trench and the bottom of cables is 150 mm

minimum

• the thickness of the clean sand above the top of cables is 100 mm minimum

• the outermost edge of cables is located at a distance of at least 100 mm from the side of

the trench

Where there is a risk of erosion, a 14:1 sand cement mix may be used instead of clean sand.

Cable protection covers shall be placed immediately above the bedding.

On top of the cable protection covers excavated backfill may be used.

Outside of the rail corridor, the top of the trench shall be restored in accordance with the

requirements of the controlling authority of the area.

Unless otherwise specified in design, single core HV ac cables shall be installed in close trefoil

formation. Justification shall be provided in the design documentation if other arrangements are

used.

Illustrations of typical direct laid system configurations are provided in Appendix A.

13. Duct laid system Cables shall be enclosed in ducts at the following installations:

• undertrack crossings

• crossings of main roads

• installations using trenchless technology

HV ac cables of different circuits shall not be installed within the same duct. 1500 V dc positive

cables of different feeders shall not be installed within the same duct.

Single core HV ac cables shall be installed with one of the following configurations:

• all cores of the same circuit are in close trefoil formation within one duct

• each core is installed in a separate duct, with the ducts arranged in a trefoil formation as far

as practicable; the trefoil formation shall be maintained when any one of the cables is

replaced by a new one in the spare duct

Ducts with cables shall not be filled with grouts.

Illustrations of typical duct laid system configurations are provided in Appendix A.

Page 16: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 16 of 24

13.1. Properties of ducts Ducts shall be rigid unplasticised polyvinyl chloride (PVC-U) orange heavy duty conduits that

complies with AS/NZS 2053.2 Conduits and fittings for electrical installations – Rigid plain

conduits and fittings of insulating material or AS/NZS 1477 PVC pipes and fittings for pressure

applications class PN12. Polyethylene (PE) pipes in accordance with AS/NZS 4130

Polyethylene (PE) pipes for pressure applications may be used where ducts are installed by

trenchless technology.

Ducts, including joints, shall be impervious to water, smooth on the inside and chemically inert.

13.1.1. Duct entries Duct entries into pits or other structures shall not cause damage to cables during installation

and subsequent operation and maintenance. Refer to T HR EL 20007 ST Cable Pits for

examples of satisfactory arrangements.

13.2. Minimum duct diameter The internal diameter of a duct shall at a minimum comply with the following:

• 1.7 times the cable diameter for a duct containing a single cable

• 3 times the cable diameter for a duct with up to 3 cables in the duct

• 3.5 times the cable diameter for a duct with 4 cables in the duct

Smaller ducts and clearances may be used with approval of the design and cable installation

methodology by the appropriate design authority.

13.3. Provision of spare ducts Spare ducts shall be provided for future use.

The minimum number of spare ducts for each HV circuit shall be 30% of the total number of

ducts occupied by cables of the circuit, with at least one for each circuit. Where a pilot wire

cable is installed for the circuit, a separate spare duct shall be provided for the pilot wire cable.

The minimum number of spare ducts for 1500 V dc cables shall be 30% of the total number of

ducts occupied by 1500 V dc positive and negative cables, with at least one spare duct.

Spare ducts shall be sealed to prevent the ingress of moisture and other foreign matters.

Ducts shall be allocated such that spare ducts are at or above the levels of ducts containing

cables of the same circuit.

Page 17: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 17 of 24

13.4. Arrangement of ducts in a trench Ducts shall be embedded in 14:1 sand cement mix. Sand cement mix with different mix ratios

may be used where specified by the design AEO, provided that the design documentation

clearly demonstrates that the following conditions are satisfied for the design life of the

installation:

• the required cable rating is achieved

• the mechanical strength of the sand cement mix is suitable for the loading conditions at the

site

• curing of the sand cement mix does not have any adverse effects on the ducts

The sand cement mix shall provide bedding at the bottom and across the entire width of the

trench in order to achieve the following:

• the distance between the bottom of the trench and the bottom of ducts is 100 mm minimum

• the thickness of the sand cement mix above the top of ducts is 100 mm minimum

• the outermost edge of ducts is located at a distance of at least 75 mm from the side of the

trench

Cable protection covers shall be placed immediately above the bedding.

On top of the cable protection covers excavated backfill may be used. Outside of the rail

corridor, the top of the trench shall be restored in accordance with the requirements of the

controlling authority of the area.

Ducts shall be arranged with a minimum separation of 50 mm. Spacers shall be provided to

maintain the arrangement of the duct bank along the cable route.

Appropriate conduit bends shall be used to ensure that the minimum cable bending radius is not

exceeded.

13.5. Ducts installed by trenchless technology Where ducts are installed by trenchless technology, the voids between ducts shall be filled with

pumpable slurry.

Where an encasing pipe is used, the void between the encasing pipe and the bored hole shall

be filled with pumpable slurry.

Details of the pumpable slurry shall be specified by the designer after consideration of the

thermal and mechanical strength requirements of the installation.

The ducts shall be of sufficient strength to withstand the heat from the curing of the slurry.

Ducts shall be arranged with a minimum separation of 50 mm.

Page 18: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 18 of 24

Spacers and suitable restraining devices shall be provided to maintain the arrangement of the

duct bank along the cable route.

Ducts shall be installed with a minimum depth of 1.0 m.

Cable protection covers and warning marker tapes are not required for cable installations using

trenchless technology.

Trenchless technology shall not be used for areas with reduced depth of installation.

Where trenchless technology is used, the following shall be complied with:

• the selected technology shall provide for accurate location recording of the underground

installation

• a geotechnical investigation shall be done in accordance with Australasian Society for

Trenchless Technology guide Guidelines for Horizontal Directional Drilling, Pipe Bursting,

Microtunnelling and Pipe Jacking

• the relative positions of ducts in the as installed configuration shall comply with the

requirements in Section 10 and Section 13.3

13.6. Undertrack crossings Undertrack crossings shall comply with the requirements of AS 4799 and T HR CI 12190 ST.

Track monitoring shall comply with SPC 207 Track Monitoring Requirements for Undertrack

Excavation.

Metallic encasing pipe shall not be used within one kilometre of electrified areas.

Reinforced concrete encasing pipe may be used in the electrified area, provided that the design

AEO has determined that the integrity of the encasing pipe and any adjacent structures or pipes

will not be compromised by the effects of dc stray current. Refer to T HR EL 12005 ST Bonding

for 1500 V DC Traction Systems for requirements and strategies for assessing and managing

the hazards associated with stray dc currents from the 1500 V dc traction system. Refer to

T HR EL 12002 GU Electrolysis from Stray DC Current for techniques to minimise the hazards

from electrolysis.

The voids between ducts within the encasing pipe and between the encasing pipe and the

bored hole shall be filled with pumpable slurry.

The ducts shall be of sufficient strength to withstand the heat from the curing of the slurry.

Details of the pumpable slurry shall be specified by the designer after consideration of the

thermal and mechanical strength requirements of the installation.

Spacers and suitable restraining devices shall be provided to maintain the arrangement of the

ducts through the undertrack crossing.

Page 19: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 19 of 24

Illustrations of typical undertrack crossing duct arrangements within an encasing pipe are

provided in Appendix A.

14. As-built design documentation The location and installation configuration of underground cables shall be surveyed and

recorded in accordance with T HR EL 20004 ST and T HR EL 20008 ST.

The records shall be included in the as-built design documentation of the project.

Page 20: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 20 of 24

Appendix A Typical installation configurations Figure 1 through to Figure 7 are illustrations of typical underground installations for HV ac and

1500 V dc cables.

Refer to the relevant sections of the standard for details of the requirements applicable to each

arrangement.

Depth of installation

Orange warning tape

Cable protection cover

Clean sand

Cable

Back fill

300 mm approx

50 mm min.

150 mm min.

Ground level

100 mm min.

100 mm min.

Figure 1 - Typical direct laid configuration with single cable

Page 21: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 21 of 24

Depth of installation

Orange warning tape

Cable protection cover

14:1 sand: cementorClean sand

Cable

Back fill

300 mm approx

150 mm min.

Ground level

100 mm min.

100 mm min.

Figure 2 - Typical direct laid configuration with multiple 1500 V dc negative cables

Depth of installation

Orange warning tape

Cable protection cover

Clean sand

Cable

Back fill

300 mm approx

150 mm min.

Ground level

100 mm min.

150 mm min.100 mm

min.

Figure 3 - Typical direct laid configuration with cables of different circuits run in parallel

Page 22: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 22 of 24

Orange warning tape

Cable protection cover

Clean sand

Cable

Back fill

300 mm approx

Ground level

100 mm min.

225 mm min.100 mm min.

100 mm min. Cable protection cover

Cable

150 mm min.

Figure 4 - Typical direct laid configuration with cables crossing

Page 23: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 23 of 24

Orange warning tape

Cable protection cover

14:1 Sand : Cement mix

Ducts

Back fill

300 mm approx

Ground level

100 mm min.

100 mm min.

50 mm min.

50 mm min.

Depth of installation

75 mm min.

Figure 5 - Typical duct laid configuration

Encasing pipe

Pumpable slurry

Ducts

Figure 6 - Typical cross-section of a 16 duct, bored undertrack crossing

Page 24: T HR EL 20003 ST Underground Installation Configurations ... · AS 1379 Specification and supply of concrete . AS 1906.1 Retroreflective materials and devices for road traffic control

T HR EL 20003 ST Underground Installation Configurations for High Voltage and 1500 V DC Cables

Version 2.0 Issue date: 24 December 2020

© State of NSW through Transport for NSW 2020 Page 24 of 24

Encasing pipe

Pumpable slurry

Ducts

Figure 7 - Typical cross-section of a five duct, bored undertrack crossing