System Integration Exit Criteria Issues Resolved or Addressed Preliminary Design Review/Critical...
-
Upload
elfrieda-newton -
Category
Documents
-
view
212 -
download
0
Transcript of System Integration Exit Criteria Issues Resolved or Addressed Preliminary Design Review/Critical...
System IntegrationExit Criteria Issues
Resolved or Addressed
Preliminary Design Review/Critical Design
Review, Audits
InitiateDesign Readiness Review
Planning Process
InitiateAcquisition CoordinationTeam (ACT) Planning
Conduct ACTMeetings
Plan and scheduleJROC, OIPT, DAB
(if required)
Begin Program DecisionBrief Updates Notify Participants
Documentation UpdatesCDD, Acquisition Strategy,TEMP, CARD, Threat, APB
Mature Design for Testing
System IntegrationExit Criteria Satisfied
System Integration Completed
Complete and SubmitProgram Decision Brief
DRRDecision
BriefWith PEO
DRRDecision
BriefWith MDA
PEO ApproveExit Criteria
ACATIII and IV
MDA ApproveExit Criteria
ACATI and II
START
System Integration status validated based on CDR results
Coordinate withSECDEF
Coordinate withSECNAV
Coordinate withOPNAV
Coordinate withSYSCOM
Schedule DRRDecision Meeting
DT & E PlansComplete & Provided
Cost, SchedulePerformance Trade Off
Analysis
FINISH
SEE DESIGNREADINESS
REVIEWPLANNINGCHECKLIST
SEE DESIGNREADINESS
REVIEW PRE-REVIEWCHECKLIST
SEE DESIGNREADINESS
REVIEWCHECKLIST
LONG RANGEPLANNING PHASE
PLANNING PHASEPRE-REVIEW
PHASE
• CAPABILITIES DEVELOPMENT DOCUMENT • ACQUISITION STRATEGY • APB • SYSTEM INTEGRATION EXIT CRITERIA•TEST PLANS (Especially for DT&E and IOT & E)• CCA Requirements• ADEQUACY OF RESOURCES (Manpower and Funding)• ICE AND MANPOWER ESTIMATE (10USC2434)• UPDATED C4ISR SUPPORT REQUIREMENTS•ISP UPDATE•TEMP• TECHNOLOGY READINESS ASSESSMENT•SEE DoDI 5000.2 ENCLOSURE (3) for additional requirements
At DRR, the MDAtypically emphasizes validation
of the following:
-ENTRY/EXIT CRITERIA FOR DRR HAVE BEEN MET- APPROVAL FOR SYSTEMDEMONSTRATON EFFORTS- EXIT CRITERIA FOR NEXT PHASE ESTABLISHED
30 DAYS(PRE-REVIEW PHASE)
LONG-RANGE(PLANNING PHASE)
~1 DAY(REVIEW PHASE)
EXIT CRITERIA FORSYSTEM INTEGRATION
SATISFIED
BEGINNING OF SYSTEM
DEMONSTRATION
BEGINNING OF PHASE B
180 DAYS
CONFIRM AVAILABILITY OF PRINCIPLESFor proposed briefing date
ENTRY CRITERIA FORSYSTEMS INTEGRATION
SATISFIED
CONDUCT THE DRR PRE-BRIEF(Closed Sessions)
REVIEW DRR PRE-REVIEW CHECKLIST
6 MONTHS(PLANNING PHASE)
TIMELINE~ Event Driven
BETWEEN MILESTONE B and DRR
PEO C4I and SPACEDESIGN READINESS REVIEW (DRR) TIMELINE
PHASESMS B DRR
ADM
PEO C4I and SPACE ACQUISITION PROGRAM STRUCTURE GUIDE
ENCLOSURE (14)Page T-1VERSION 3.0February 2004
NOTE: Design Readiness Review (DRR) is a discretionary review conducted after Milestone B and signifies the end of System Integration and the start of System Demonstration. Refer to DoDI 5000.2, Para 3.7.3 and SECNAVINST 5000.2C, Para 2.5.4.6.2 for Design Readiness Review requirements.
PROCESS
SYSTEM INTEGRATION
This effort, which is the first effort of the SDD phase, is intended to integrate subsystems,
complete detailed design, and reduce
system-level risk.
SEE DESIGNREADINESS
REVIEWLONG-RANGE
PLANNINGCHECKLIST
Draft ADM(Ready for System Demo
/ DT & E initiation /Entry/Exit Criteria Meant)
BEGINNING OF DRR PLANNING PHASE
REVIEW DRR CHECKLIST & PEO MAJOR REVIEW CHECKLIST
CONDUCT ACT MEETING – Obtain consensus to proceed.
(Email minutes to ACT Participants)90-180 DAYS
DRAFT ACT CHARTER 90-180 DAYS
PREPARE EXIT CRITERIA FOR SYSTEM INTEGRATION AND ANY ANTICIPATED ISSUES
WITH RESPECT TO SYSTEMS ACQUISITION ACTIVITIES
90 DAYS
DRAFT BRIEF AND ADM 90 DAYS
30 DAYS
SCHEDULE PRE-BRIEF AND BRIEFVIA ACQUISITION WEBSITE AND PEO
FRONT OFFICE CALENDAR
30 DAYSENSURE THE PDR AND CDR
HAVE BEEN COMPLETED
30 DAYS
ENSURE SYSTEMS ACQUISITION ACTIVITIES HAVE BEEN INITIATED 30 DAYS
SEND PRE-BRIEF TO ACT MEMBERS FOR REVIEW 20 DAYS
7 DAYS
SEND FINAL BRIEF AND ADM TO ACT FOR REVIEW 5 DAYS
30 DAYS
REFINE AoA PLAN, AS, CDD,ICD, TDS, AND TEMP 90-180 DAYS