System Integration Exit Criteria Issues Resolved or Addressed Preliminary Design Review/Critical Design Review, Audits Initiate Design Readiness Review Planning Process Initiate Acquisition Coordination Team (ACT) Planning Conduct ACT Meetings Plan and schedule JROC, OIPT, DAB (if required) Begin Program Decision Brief Updates Notify Participants Documentation Updates CDD, Acquisition Strategy, TEMP, CARD, Threat, APB Mature Design for Testing System Integration Exit Criteria Satisfied System Integration Completed Complete and Submit Program Decision Brief DRR Decision Brief With PEO DRR Decision Brief With MDA PEO Approve Exit Criteria ACAT III and IV MDA Approve Exit Criteria ACAT I and II START System Integration status validated based on CDR results Coordinate with SECDEF Coordinate with SECNAV Coordinate with OPNAV Coordinate with SYSCOM Schedule DRR Decision Meeting DT & E Plans Complete & Provided Cost, Schedule Performance Trade Off Analysis FINISH SEE DESIGN READINESS REVIEW PLANNING CHECKLIST SEE DESIGN READINESS REVIEW PRE-REVIEW CHECKLIST SEE DESIGN READINESS REVIEW CHECKLIST LONG RANGE PLANNING PHASE PLANNING PHASE PRE-REVIEW PHASE CAPABILITIES DEVELOPMENT DOCUMENT ACQUISITION STRATEGY APB SYSTEM INTEGRATION EXIT CRITERIA TEST PLANS (Especially for DT&E and IOT & E) CCA Requirements ADEQUACY OF RESOURCES (Manpower and Funding) ICE AND MANPOWER ESTIMATE (10USC2434) UPDATED C4ISR SUPPORT REQUIREMENTS ISP UPDATE TEMP TECHNOLOGY READINESS ASSESSMENT SEE DoDI 5000.2 ENCLOSURE (3) for additional requirements At DRR, the MDA typically emphasizes validation of the following: -ENTRY/EXIT CRITERIA FOR DRR HAVE BEEN MET - APPROVAL FOR SYSTEM DEMONSTRATON EFFORTS - EXIT CRITERIA FOR NEXT PHASE ESTABLISHED 30 DAYS (PRE-REVIEW PHASE) LONG-RANGE (PLANNING PHASE) ~1 DAY (REVIEW PHASE) EXIT CRITERIA FOR SYSTEM INTEGRATION SATISFIED BEGINNING OF SYSTEM DEMONSTRATION BEGINNING OF PHASE B 180 DAYS CONFIRM AVAILABILITY OF PRINCIPLES For proposed briefing date ENTRY CRITERIA FOR SYSTEMS INTEGRATION SATISFIED CONDUCT THE DRR PRE-BRIEF (Closed Sessions) REVIEW DRR PRE-REVIEW CHECKLIST 6 MONTHS (PLANNING PHASE) TIMELINE ~ Event Driven BETWEEN MILESTONE B and DRR PEO C4I and SPACE DESIGN READINESS REVIEW (DRR) TIMELINE PHASES MS B DRR ADM PEO C4I and SPACE ACQUISITION PROGRAM STRUCTURE GUIDE ENCLOSURE (14) Page T-1 VERSION 3.0 February 2004 NOTE: Design Readiness Review (DRR) is a discretionary review conducted after Milestone B and signifies the end of System Integration and the start of System Demonstration. Refer to DoDI 5000.2, Para 3.7.3 and SECNAVINST 5000.2C, Para 2.5.4.6.2 for Design Readiness Review requirements. PROCESS SYSTEM INTEGRATION This effort, which is the first effort of the SDD phase, is intended to integrate subsystems, complete detailed design, and reduce system-level risk. SEE DESIGN READINESS REVIEW LONG-RANGE PLANNING CHECKLIST Draft ADM (Ready for System Demo / DT & E initiation / Entry/Exit Criteria Meant) BEGINNING OF DRR PLANNING PHASE REVIEW DRR CHECKLIST & PEO MAJOR REVIEW CHECKLIST CONDUCT ACT MEETING Obtain consensus to proceed. (Email minutes to ACT Participants) 90-180 DAYS DRAFT ACT CHARTER 90-180 DAYS PREPARE EXIT CRITERIA FOR SYSTEM INTEGRATION AND ANY ANTICIPATED ISSUES WITH RESPECT TO SYSTEMS ACQUISITION ACTIVITIES 90 DAYS DRAFT BRIEF AND ADM 90 DAYS 30 DAYS SCHEDULE PRE-BRIEF AND BRIEF VIA ACQUISITION WEBSITE AND PEO FRONT OFFICE CALENDAR 30 DAYS ENSURE THE PDR AND CDR HAVE BEEN COMPLETED 30 DAYS ENSURE SYSTEMS ACQUISITION ACTIVITIES HAVE BEEN INITIATED 30 DAYS SEND PRE-BRIEF TO ACT MEMBERS FOR REVIEW 20 DAYS 7 DAYS SEND FINAL BRIEF AND ADM TO ACT FOR REVIEW 5 DAYS 30 DAYS REFINE AoA PLAN, AS, CDD, ICD, TDS, AND TEMP 90-180 DAYS

Transcript of System Integration Exit Criteria Issues Resolved or Addressed Preliminary Design Review/Critical...

Page 1: System Integration Exit Criteria Issues Resolved or Addressed Preliminary Design Review/Critical Design Review, Audits Initiate Design Readiness Review.

System IntegrationExit Criteria Issues

Resolved or Addressed

Preliminary Design Review/Critical Design

Review, Audits

InitiateDesign Readiness Review

Planning Process

InitiateAcquisition CoordinationTeam (ACT) Planning

Conduct ACTMeetings

Plan and scheduleJROC, OIPT, DAB

(if required)

Begin Program DecisionBrief Updates Notify Participants

Documentation UpdatesCDD, Acquisition Strategy,TEMP, CARD, Threat, APB

Mature Design for Testing

System IntegrationExit Criteria Satisfied

System Integration Completed

Complete and SubmitProgram Decision Brief

DRRDecision

BriefWith PEO

DRRDecision

BriefWith MDA

PEO ApproveExit Criteria

ACATIII and IV

MDA ApproveExit Criteria

ACATI and II

START

System Integration status validated based on CDR results

Coordinate withSECDEF

Coordinate withSECNAV

Coordinate withOPNAV

Coordinate withSYSCOM

Schedule DRRDecision Meeting

DT & E PlansComplete & Provided

Cost, SchedulePerformance Trade Off

Analysis

FINISH

SEE DESIGNREADINESS

REVIEWPLANNINGCHECKLIST

SEE DESIGNREADINESS

REVIEW PRE-REVIEWCHECKLIST

SEE DESIGNREADINESS

REVIEWCHECKLIST

LONG RANGEPLANNING PHASE

PLANNING PHASEPRE-REVIEW

PHASE

• CAPABILITIES DEVELOPMENT DOCUMENT • ACQUISITION STRATEGY • APB • SYSTEM INTEGRATION EXIT CRITERIA•TEST PLANS (Especially for DT&E and IOT & E)• CCA Requirements• ADEQUACY OF RESOURCES (Manpower and Funding)• ICE AND MANPOWER ESTIMATE (10USC2434)• UPDATED C4ISR SUPPORT REQUIREMENTS•ISP UPDATE•TEMP• TECHNOLOGY READINESS ASSESSMENT•SEE DoDI 5000.2 ENCLOSURE (3) for additional requirements

At DRR, the MDAtypically emphasizes validation

of the following:

-ENTRY/EXIT CRITERIA FOR DRR HAVE BEEN MET- APPROVAL FOR SYSTEMDEMONSTRATON EFFORTS- EXIT CRITERIA FOR NEXT PHASE ESTABLISHED

30 DAYS(PRE-REVIEW PHASE)

LONG-RANGE(PLANNING PHASE)

~1 DAY(REVIEW PHASE)

EXIT CRITERIA FORSYSTEM INTEGRATION

SATISFIED

BEGINNING OF SYSTEM

DEMONSTRATION

BEGINNING OF PHASE B

180 DAYS

CONFIRM AVAILABILITY OF PRINCIPLESFor proposed briefing date

ENTRY CRITERIA FORSYSTEMS INTEGRATION

SATISFIED

CONDUCT THE DRR PRE-BRIEF(Closed Sessions)

REVIEW DRR PRE-REVIEW CHECKLIST

6 MONTHS(PLANNING PHASE)

TIMELINE~ Event Driven

BETWEEN MILESTONE B and DRR

PEO C4I and SPACEDESIGN READINESS REVIEW (DRR) TIMELINE

PHASESMS B DRR

ADM

PEO C4I and SPACE ACQUISITION PROGRAM STRUCTURE GUIDE

ENCLOSURE (14)Page T-1VERSION 3.0February 2004

NOTE: Design Readiness Review (DRR) is a discretionary review conducted after Milestone B and signifies the end of System Integration and the start of System Demonstration. Refer to DoDI 5000.2, Para 3.7.3 and SECNAVINST 5000.2C, Para 2.5.4.6.2 for Design Readiness Review requirements.

PROCESS

SYSTEM INTEGRATION

This effort, which is the first effort of the SDD phase, is intended to integrate subsystems,

complete detailed design, and reduce

system-level risk.

SEE DESIGNREADINESS

REVIEWLONG-RANGE

PLANNINGCHECKLIST

Draft ADM(Ready for System Demo

/ DT & E initiation /Entry/Exit Criteria Meant)

BEGINNING OF DRR PLANNING PHASE

REVIEW DRR CHECKLIST & PEO MAJOR REVIEW CHECKLIST

CONDUCT ACT MEETING – Obtain consensus to proceed.

(Email minutes to ACT Participants)90-180 DAYS

DRAFT ACT CHARTER 90-180 DAYS

PREPARE EXIT CRITERIA FOR SYSTEM INTEGRATION AND ANY ANTICIPATED ISSUES

WITH RESPECT TO SYSTEMS ACQUISITION ACTIVITIES

90 DAYS

DRAFT BRIEF AND ADM 90 DAYS

30 DAYS

SCHEDULE PRE-BRIEF AND BRIEFVIA ACQUISITION WEBSITE AND PEO

FRONT OFFICE CALENDAR

30 DAYSENSURE THE PDR AND CDR

HAVE BEEN COMPLETED

30 DAYS

ENSURE SYSTEMS ACQUISITION ACTIVITIES HAVE BEEN INITIATED 30 DAYS

SEND PRE-BRIEF TO ACT MEMBERS FOR REVIEW 20 DAYS

7 DAYS

SEND FINAL BRIEF AND ADM TO ACT FOR REVIEW 5 DAYS

30 DAYS

REFINE AoA PLAN, AS, CDD,ICD, TDS, AND TEMP 90-180 DAYS