Syngas Production from Petroleum Coke Gasification
description
Transcript of Syngas Production from Petroleum Coke Gasification
Syngas Production from Petroleum Coke Gasification
Team Hotel:Russell Cabral, Tomi Damo, Ryan Kosak, Vijeta Patel, Lipi Vahanwala
Advisors:Bill Keesom – Jacobs Consultancy Jeffery Perl, PhD – UIC Dept. Of Chemical Engineering
March 8, 2011 1
Project Purpose
What we are doing? Producing syngas from petcoke Using entrained flow gasifier Implementing a rigorous syngas
cleaning
Why we are doing this? Making syngas for acetic acid
production Chemical production team specs▪ CO to H2 molar ratio of 0.409▪ CO2 and N2 mixed in
2
http://coalgasificationnews.com/tag/petcoke-gasification/
3/8/2011
Overall Block Flow
3
Recap
Discussed the Shell™ membrane gasifier
Discussed our syngas processes Sulfur Removal Claus Process Water Gas Shift
Flow Sheets Early Material and Energy Balances
43/8/2011
Questions Brought Up Last Time
Why use N2 as a transport gas and not CO2?
How are we absorbing CO2?
53/8/2011
Agenda
Recent changes Using Selexol instead of MDEA Using the Superclaus
Aspen Simulation Heat Load Identification Economics
Aspen Price Evaluator (ICARUS) Equipment Sizing Location Update
63/8/2011
Flow Sheeting: Overall Process
73/8/2011
Gasification Sulfur Removal Claus Process
Water Gas ShiftCO2 Removal
Flow Sheeting: Gasification
83/8/2011
To Sulfur Remov
al
Flow Sheeting: Sulfur Removal
93/8/2011To WGS
To Claus
Flow Sheeting: WGS & CO2
103/8/2011
Capture
Ready CO2
To Chem Producti
on
Flow Sheeting: Claus Process
113/8/2011
To Supercl
aus
Flow Sheeting: Claus Cont.
123/8/2011
Heat Loads for Claus Plant
13
Claus Process Equipment Heat Load (MMBtu/hr)
Claus Furnace -3.26
Condenser 1 -31.3
Condenser 2 -11.2
Condenser 3 -5.97
Condenser 4 -3.92
Re-heater 1 9.72
Re-heater 2 5.29
Re-heater 3 3.46
Catalytic Reactor 1 3.03
Catalytic Reactor 2 1.72
Catalytic Reactor 3 -5.73
3/8/2011
Heat Sink Optimization
Stream Pre-heating Lower Heater / Cooler Duties Heat Duty and Heat Ex. Cost Tradeoff
14
Furnace Cooler
HX
Acid Gas Cold
Acid Gas Hot
To Claus Catalyst
s Hot Furnace
Gas
Cold Furnace
Gas
3/8/2011
WGS ReactorCO2 Absorption
Final syngasproduct
Claus Process
Gasification Price
$240,306,575
Solid Removal
3/8/2011 15
Sulfur Removal
Economics and Size
Gasification
SIZE INDIRECT COST
DIRECT COST
Air SeparationUnit
Facility N/A $100,000,000
Petroleum Coke Crusher TBD $ 5,401,890 $ 7,022,455
Gasifier (x2) 2000 TPD N/A $ 132,000,000
Heat Exchanger (x2)
3350 sq ft $611,480 $ 1,284,120 163/8/2011
WGS ReactorCO2 AbsorptionFinal syngas
product
Claus Process
Gasification Price
$240,306,575
Solid Removal$670,000
3/8/2011 17
Sulfur Removal
Equipment Cost and SizeCont.
Solid Removal
SizeINDIRECT
COSTDIRECT
COST
Filter 16 sq ft $ 364,770 $ 510,680
Cyclone (x3) 5 ft (diameter) $ 307,800 $ 477,000
183/8/2011
WGS ReactorCO2 AbsorptionFinal syngas
product
Claus Process
Gasification Price
$240,306,575
Solid Removal$670,000
3/8/2011 19
Sulfur Removal
$9,600,000
Equipment Cost and SizeCont.
Sulfur Removal
203/8/2011
SIZE EQUIP COST TOTAL COST
Absorber (x2) 12.7 x 60 ft $ 2,400,000 $ 4,800,000
Stripper (x2) 17 x 30 ft $ 1,560,000 $ 3,300,000
Flash Vessels (x2)383 cu. ft
$ 707,215 $ 808,1106980 cu ft
Heat Exchanger 1200 sq ft $ 121,980 $ 256,155
Reactor (x3)TBD $ (103,115)* $ (164,985)*
Cooler 6739 sq ft$ 185,500 $ 400,000
440 sq ft
WGS ReactorCO2
AbsorptionFinal syngasproduct
Claus Process$12,500,000
Gasification Price
$240,306,575
Solid Removal$670,000
3/8/2011 21
Sulfur Removal$9,600,000
Equipment Cost and SizeCont.
22
Equipment Used in Claus Process
Equipment Size Equip Cost Total Cost
Heat Exchanger 298 sq ft TBD TBD
Claus Furnace N/A TBD TBD
Cooler (x3) 439 sq ft
$ 148,300.00 $ 222,600.00257 sq ft
162 sq ft
Flash (x3) 680 cu ft$ 263,033.00 $ 358,000.00461 cu ft
461 cu ft
Heater (x2) 1574 sq ft TBD TBD
996 sq ft
3/8/2011
WGS ReactorCO2 Absorption$35,700,000
Final syngasproduct
Claus Process$12,500,000
Gasification Price
$240,306,575
Solid Removal$670,000
3/8/2011 23
Sulfur Removal$9,600,000
144 ft3$360,000
Equipment Cost and SizeCont.
CO2 Absorption
Equipment Size Equip Cost Direct Cost
CO2 Absorber (x2) 12.7 x 60 ft N/A $ 3,000,000
CO2 Stripper (x2) 17 x 30 ft $ 203,170 $ 256,800
Compressor N/A$ 272,889 $ 409,333
243/8/2011
Overall Summary of
Capital CostWGS Reactor
144 ft3$360,000
CO2 Absorption$35,700,000
Final syngasProduct$300,000,000
Claus Process$12,500,000
Gasification Price
$240,306,575
Solid Removal$670,000
3/8/2011 25
Sulfur Removal
$9,600,000
Other Fixed Cost
Other Fixed Cost
License Fees and Royalties
2% of Capital Cost
Maintenance
5% of Capital
Cost
Laboratory Cost
30% Labor Cost
Insurance1%
Capital Cost
Capital Cost as of now= $ 300,000,000Labor Cost as of now = $ 24,000,000
263/8/2011
Overall Expenses
Type Cost of year 1 ($ Million/year)
Cost at the end of 25th year
Loan $18 $ 1
Cooling water $2 $ 6
Electrical $2 $ 6
Salaries and Fringes $ 24 $ 77
Maintenance $15 $ 48
Royalties $ 6 $19
Insurance $3 $ 10
Raw materials $ 54 $175
Depreciation $12 $12
Total $136 $355 27
Capital Cost as of now = $ 300,000,000
Expected Revenue
Product and Side Products
Unit Price (per ton)
Revenue (In MM $ / year)
Syngas $200.00 $ 115.50
CO2 $40.00 $ 7.00
Sulfur $100.00 $ 3.50
Total $ 126.00
283/8/2011
293/8/2011
Economic Analysis($ million/year)
Total Capital Cost $300
Total Expense $136
Total Revenue $126
Income Before the Taxes -$10
40 % Tax on the Income -$4
Income After the Taxes -$6
Add Back Depreciation $12
Cash Flow $6
Net Present Value $-52
Internal Rate of Return 3.58% < 5%
Payback Period 19 years
30
Sensitivity Analysis
3/8/2011
$150.00 $170.00 $190.00 $210.00 $230.00 $250.00
-300
-250
-200
-150
-100
-50
0
50
100
150
200 NPV vs. Syngas Prices
NPV
Syngas($/ton)
Net
Pre
sen
t valu
e (
$m
illion
)
31
Sensitivity Analysis
3/8/2011
$150.00 $170.00 $190.00 $210.00 $230.00 $250.00
-8.00%
-6.00%
-4.00%
-2.00%
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%IRR vs. Syngas Price
NPV
Syngas ($/ton)
Inte
rnal R
ate
of
retu
rn
32
Sensitivity Analysis
3/8/2011
$20 $30 $40 $50 $60 $70 $80 $90
-$150.00
-$100.00
-$50.00
$0.00
$50.00
$100.00
$150.00
$200.00
$250.00
$300.00
NPV vs. Petcoke Cost
NPV
Petcoke Price ($/ton)
Net
Pre
sent
valu
e(
$ m
illions)
33
Sensitivity Analysis
3/8/2011
$20 $30 $40 $50 $60 $70 $80 $900.00%
2.00%
4.00%
6.00%
8.00%
10.00%
12.00%
IRR vs. Cost of Petcoke
IRR
Petcoke Price ($/ton)
Inte
rnal ra
te o
f re
turn
Location
Victoria, Texas Between Houston
and Corpus Christi 200 acres Kansas City
Southern, Union Pacific, and Burlington Northern Santa Fe railways
Gulf Intracoastal Waterway
343/8/2011
Possible Alternatives
Alberta, Canada Sits on excess
petroleum coke from refineries
Is it Economically viable? Demand Transportation costs
36
Conclusion
Overall ASPEN procedure Gasification Syngas Clean Up CO2 Removal
Rough Economics
Location: Victoria, Texas Possible Change
3/8/2011
37
Next Steps
Final process flow diagram Control scheme Optimize economy scale
Revise capital costs Major equipments list and plant layout Revise report
3/8/2011
38
Questions?
3/8/2011
References
http://fossil.energy.gov/images/programs/sequestration/what_sequestration_lg.jpg
http://coalgasificationnews.com/tag/petcoke-gasification/
http://www.huffingtonpost.com/dr-orin-levine/questions-as-mileposts-of_b_448870.html
http://www.chinaep-tech.com/upload/accessary/8173/DZY08092502.pdf
http://www.chemicals-technology.com/projects/gulfpetrochemicalsco/ 393/8/2011
Report Outline
Final Report: Executive Summary IP Discussion IP Recommendations IP
Appendices Design Basis: Done Block Flow Diagram: Done Process Flow Showing Major Equip.: IP
403/8/2011
Report Outline
Appendices (Continued) Material and Energy Balances: IP Calculations: IP Annotated Equip. List: IP Econ. Eval. Factored from Equip. Costs:
IP Utilities: IP Conceptual Control Scheme: N/A Major Equipment Layout: IP
413/8/2011
Report Outline
Appendices (Continued) Distribution and End-use Issues:
IP Constraints Review: IP Applicable Standards: IP Project Communications File: IP Information Sources and References:
IP
423/8/2011
Energy Balance Around WGS Reactor
Energy BalanceAround WGS ReactorInlet Fraction Clean Syngas Component
Flow for WGS Reactor (lbmoles/hr) for WGS Cp (btu/lbmole* F)
Outlet Syngas Comp (lbmole/hr) from
(WGS)
CO 4946.233 7.118 123.395
H2O 6424.688 15.367 1601.850
N2 199.954 7.158 199.954
H2* 2960.168 6.948 7783.006
CO2 469.211 10.559 5292.049
CH4* 0.255
12.432 0.255
H2S 0.000 0.000 0.000
COS 0.000 0.000 0.000
Total 15000.509 15000.509
443/8/2011
Heat Loads
Gasifier Equipment Heat Load (MMBtu/hr)
Gasifier -34.7
HP Steam Heat Exchanger 139.0
MP Steam Heat Exchanger 281
Cooler -106.8
Flash 2.99
Sulfur Clean Up Equipment Heat Load (MMBtu/hr)
Sulfur Stripper Reboiler 57.0
Sulfur Stripper Cooler -200.0
Selexol Cooler -40.7
Rich / Lean Heat Exchanger 274.93/8/2011 45
46
CO2 Sequestration
CO2 in our syngas is absorbed on Selexol to be selectively removed
Delete only one CO2 slide.
3/8/2011
47
http://fossil.energy.gov/images/programs/sequestration/what_sequestration_lg.jpg3/8/2011