Synchrophasors Intiatives in India Dec 13 - wrldc.org Initiatives in India Decmber 2013... ·...

184

Transcript of Synchrophasors Intiatives in India Dec 13 - wrldc.org Initiatives in India Decmber 2013... ·...

DECEMBER - 2013 POSOCO

Synchrophasors - Initiative in India

Power System Operation Corporation Limited(A wholly owned subsidiary of POWERGRID)

B-9, Qutab Institutional Area, Katwaria Sarai,New Delhi-110016

In i t ia t ive in India

(December-2013)

Synchrophasors

DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

DECEMBER - 2013 POSOCO

Synchrophasors - Initiative in India

EXECUTIVE SUMMARY 1

ACKNOWLEDGEMENT 5

DISCLAIMER 6

CHAPTER 1 : BACKGROUND 7

1.1. Introduction 7

1.2. Objective of this Report 8

1.3. Chapter-wise overview. 9

1.4. Literature survey 9

CHAPTER 2 : OVERVIEW OF SYNCHROPHASOR PROJECTS 13

CHAPTER 3 : ARCHITECTURE OF SYNCHROPHASOR PROJECT 15

3.1. Eastern Region 15

3.2. North Eastern Region 16

3.3. Northern Region 18

3.4. Southern Region 19

3.5. Western Region 20

CHAPTER 4 : NATIONAL LEVEL INTEGRATION OF SYNCHROPHASORS 21

4.1. National WAMS Project Architecture 21

4.2. WAMS Infrastructure at NLDC 23

4.3. ERLDC PDC Integration 23

4.4. NERLDC PDC Integration 23

4.5. NRLDC PDC Integration 23

4.6. SRLDC PDC Integration 23

4.7. WRLDC PDC Integration 24

CHAPTER 5 : USE OF SYNCHROPHASOR DATA -CASE STUDIES 25

5.1. Fault Detection, Classification and Analysis 25

5.1.1. Transmission Line Fault 27

5.1.2. Faults occurring at Power station & Grid Sub-station 33

5.1.3. Tripping due to lack of protection co-ordination / Instrument Error 42

5.1.4. High Impedance Fault 49

5.1.5. Detection of faults cleared by back up protections 60

5.2. Low Frequency Oscillation 67

5.2.1. Detection of Low Frequency Oscillations using Synchrophasor Measurements 68

5.2.2. Analysis of Low frequency oscillations 69

5.2.3. Inter-Area Oscillations Observed in the Grid 69

TABLE OF CONTENTS

(iii)

DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

5.2.4. Inter-Plant Oscillations Observed in the Grid 74

5.2.5. Inter and Intra-Plant Oscillations Observed in the Grid 75

5.3. Detection of Coherent Group of Generators 88

5.3.1. Coherency observed in NEW grid during Bus fault at Parli S/s on 03-03-2013. 88

5.4. Island Detection and Resynchronization in the Grid 89

5.4.1. Islanding of NR Grid from Rest of the NEW Grid on 30-07-2012 90

5.4.2. Islanding of NR, ER and NER Grid from Rest of the NEW Grid on 31-07-2012 91

5.4.3. Islanding of NER Grid from Rest of the NEW Grid on 29-09-2013 92

5.5. Dynamic Model Validation Using Synchrophasor data 97

5.5.1. Validation of Electrode Current limitation characteristics of HVDC Talcher-Kolar. 97

5.5.2. Model Validation of Frequency Control of HVDC 100

5.5.3. Validation of Angular Separation calculated from EMS & measured from PMU 103

5.5.4. Cross validation of DR, Offline simulation and Synchrophasor measurements 103

5.6. Visualization of PSS testing . 108

5.6.1. PSS tuning at Karcham Wangtoo HEP on 11-12 April 2013 108

5.7. Monitoring during Natural Disasters 110

5.7.1 Monitoring during Phailin cyclone in Odisha 110

5.7.2 Monitoring during fog condition in Northern Region 114

CHAPTER 6 : EXPERIENCE ON UTILIZATION OF SYNCHROPHASOR TECHNOLOGY 119

6.1. Utilization of Synchrophasor data in real-time 119

6.2. Suggestions for Improved Visualization and Situational Awareness in real time 123

6.3. Visualization Improvement for faster event detection 128

6.4. Utilization of Synchrophasor data in offline mode 130

CHAPTER 7 : IMPLEMENTATION EXPERIENCE & INTEGRATION CHALLENGES 131

7.1. Implementation Experience in a Multi-vendor System 131

7.2. Communication Challenges in Integrating PMU 134

7.3. Synchrophasor data in Multi Cast 136

7.4. Challenges in handling of Synchrophasor data 136

7.5. Phasor Data recording and Exchange in COMTRADE Format 140

7.6. Phasor Event Data Exchange in COMFEDE Standard. 140

7.7. Compliance to IEEE C37.244 PDC Guide 140

7.8. Synchrophasor Data Storage related Experience and Challenges 140

7.9. Integration with SCADA State Estimator/EMS challenges 141

7.10. Challenges in Usage of Synchrophasor event Analysis 142

CHAPTER 8 : WAY FORWARD 143

REFERENCES 145

Appendix-A. 149

Appendix-B. 152

Appendix-C. 155

Appendix-D. 169

(iv)

DECEMBER - 2013 POSOCO

Synchrophasors - Initiative in India

LIST OF TABLES

Table 2-1 : Project Details 13

Table 5-1 : Sequence of events during multiple tripping due to CT failure at Hassan S/s 34

Table 5-2 : SOE from Balia Sub-station 42

Table 5-3 : O/V Setting of 400 kV lines from Ballia S/s 43

Table 5-4 : Overvoltage Stage 1 Protection of various lines from Bhadrawati and Chandrapur S/s 46

Table 5-5 : Sequence of events during high impedance fault in SR Grid 52

Table 5-6 : Sequence of Event during tripping of NAPS units 53

Table 5-7 : Summary of PMU Typical Delays and typical ranges 66

Table 5-8 : Fault clearance time based on DR and PMU 66

Table 5-9 : Cases analyzed using Synchrophasor (April’13 – Nov’13) 67

Table 5-10 : Low frequency oscillation observed during tripping at Budhipadar, Sterlite and IBTPS 71

Table 5-11 : Mode observed during the oscillation 73

Table 5-12 : Mode observed during the oscillation 74

Table 5-13 : Dominant Modes observed during the 213-241 Seconds 85

Table 5-14 : Dominant Modes observed during the 253-280 Seconds 86

Table 5-15 : Low frequency Oscillation observed in Indian grid 87

Table 5-16 : Major Mode observed after the combined analysis of several PMU of NEW grid 96

Table 7-1 : Vendor Distribution 131

Table 7-2 : Average Latency observed with different communication channels and PMUs 135

Table A-1 : Phasor Measurement Unit Details 149

Table A-2 : Phasor Data Concentrator System 150

Table A-3 : Historian details 150

Table A-4 : Visualization features 151

Table B-1 : Location of PMUs in Eastern region 152

Table B-2 : Location of PMUs in North Eastern Region 152

Table B-3 : Location of PMUs in Northern region 153

Table B-4 : Location of PMUs in Southern region 153

Table B-5 : Location of PMUs in Western region 154

Table B-6 : Location of PDCs all over India 154

Table D-1 : Project cost implication for each region 169

(v)

DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

LIST OF FIGURES

Figure 3-1 : Architecture of PMU pilot project in Eastern region 15

Figure 3-2 : Location of PMUs in Eastern region 16

Figure 3-3 : Architecture of PMU pilot project in North Eastern region 17

Figure 3-4 : Geographical Locations of PMUs in North Eastern region 17

Figure 3-5 : Architecture of PMU pilot project in Northern Region 18

Figure 3-6 : Geographical locations of PMU pilot project in Northern Region 18

Figure 3-7 : Architecture of PMU pilot project in Southern region 19

Figure 3-8 : Geographical locations of PMU 19

Figure 3-9 : Architecture of PMU project in Western region 20

Figure 3-10 : Geographical locations of PMUs in Western region 20

Figure 4-1 : National WAMS Project Architecture in India 21

Figure 4-2 : Geographical Locations of PMUs in India 22

Figure 5-1 : Connectivity diagram showing PMUs at Dehgam, Sugen, Boisar and Bhadrawati Sub-stations. 27

Figure 5-2 : Frequency and ROCOF from Various PMUs in Western Region 28

Figure 5-3 : Voltages from the PMU at Dehgam end. 28

Figure 5-4 : Zero Sequence voltage from the PMU at Dehgam end. 28

Figure 5-5 : Current plot of 400 kV Dehgam-Gandhar II circuit from the PMU at Dehgam end. 29

Figure 5-6 : Frequency plot obtained from the PSS/E Simulation for L-G Fault on 400 kV Sami Dehgam 1. 29

Figure 5-7 : Bhadrawati Phase voltage during the fault on 400 kV Ranchi-Sipat-I. 30

Figure 5-8 : Bhadrawati Zero sequence voltage during the fault on 400 kV Ranchi-Sipat-I. 30

Figure 5-9 : Bhadrawati Raipur II Current plot during the fault on 400 kV Ranchi-Sipat-I. 30

Figure 5-10 : DR of 400 kV Ranchi Sipat 1 from Sipat end during the fault. 31

Figure 5-11 : Phase voltage of Dadri bus from PMU during three phase fault. 31

Figure 5-12 : Current of HVDC Dadri I/C from PMU during three phase fault. 32

Figure 5-13 : DR of 400 kV Dadri –Muradnagar Ckt from Dadri end during three phase fault 32

Figure 5-14 : Schematic Diagram of Affected Area during CT failure at Hassan S/s 32

Figure 5-15 : SLD of Hassan sub-station. 33

Figure 5-16 : 400kV Somanhalli bus voltage from PMU during the CT failure at Hassan S/s. 33

Figure 5-17 : Negative and Zero sequence current for 400 kV Somanhalli-Salem Line from Somanhalli PMU 34

Figure 5-18 : DR of 400kV Hassan-Mysore line-2 (Hassan end). 35

Figure 5-19 : Fault time line. 35

Figure 5-20 : Schematic Diagram of LANCO S/s and its connectivity with nearby system. 36

Figure 5-21 : Frequency Measured from Sugen and Raipur during fault at LANCO. 36

Figure 5-22 : Voltage plot from the Raipur PMU during B phase to ground fault at LANCO. 36

Figure 5-23 : Voltage from DR of 400 kV LANCO -Sipat line from LANCO. 36

Figure 5-24 : Current from the PMU at Raipur for Raipur-Bhadrawati 1 Ckt during B phase to ground fault at LANCO. 37

Figure 5-25 : Current from DR of 400 kV LANCO -Sipat line from LANCO. 37

Figure 5-26 : PMU Voltage from the Raipur end during Y-B phase to ground fault at LANCO. 37

Figure 5-27 : Voltage from DR of 400 kV LANCO-Korba from LANCO. 37

Figure 5-28 : Current in Raipur-Bhadrawati 1 (Raipur end) during Y-B phase to ground fault at LANCO. 37

Figure 5-29 : Current in 400 kV LANCO -Korba line from LANCO. 37

Figure 5-30 : Schematic Diagram of the Area affected during multiple tripping at Mamidapalli. 38

Figure 5-31 : SLD of 400/220 kV Mamidapalli s/s 38

Figure 5-32 : 400 kV Ramagundam bus voltage during fault at Mamidapalli S/s. 39

Figure 5-33 : Negative and Zero sequence current at 400 kV Gooty-Neelamangla line from PMU. 39

Figure 5-34 : Frequency change due to ICTs tripping at Mamidapalli resulting in Load Loss. 39

Figure 5-35 : SCADA diagram displaying the Area affected. 40

(vi)

DECEMBER - 2013 POSOCO

Synchrophasors - Initiative in India

Figure 5-36 : SLD of Vijayawada TPS 40

Figure 5-37 : 400 kV Ramagundam bus voltage during tripping of Vijaywada TPS. 41

Figure 5-38 : Negative & zero sequence current of 400 kV Ramagundam-Nagarjuna Sagar-II during tripping of Vijaywada TPS. 41

Figure 5-39 : Frequency during the tripping of Vijaywada TPS 41

Figure 5-40 : SLD of 765 kV Bus at Ballia. 42

Figure 5-41 : SLD of 400 kV Bus at Ballia. 42

Figure 5-42 : 400 kV Bus voltage of Ballia station in northern region from PMU during multiple tripping. 43

Figure 5-43 : 400 kV Bus voltage of Ballia station in northern region while charging 125 Mvar Bus Reactor. 43

Figure 5-44 : PMU plot of phase Voltages of Ballia sub-station during restoration sequence. 44

Figure 5-45 : PMU plot of phase Voltages of Ballia sub-station while charging 240 Mvar Bus Reactor at 765 kV level. 44

Figure 5-46 : PMU plot of phase Voltages of Ballia sub-station during repetative attempts to charge 765 kV Ballia-Lucknow Line. 44

Figure 5-47 : PMU plot of phase Voltages of Ballia sub-station after succesful charging of 765 kV Ballia-Lucknow Line. 44

Figure 5-48 : Schematic Diagram of Bhadrawati and Near By area. 45

Figure 5-49 : Frequency and WR Demand from SCADA during multiple tripping. 45

Figure 5-50 : Zero sequence Voltage plot of Bhadrawati from Bhadrawati PMU 46

Figure 5-51 : Voltage plot of Bhadrawati from PMU along with the sequence of event during the occurrence 46

Figure 5-52 : Current plot of Bhadrawati-Raipur II Circuit from Bhadrawati PMU with the sequence of event during 47

the occurrence

Figure 5-53 : Current plot of Bhadrawati-Raipur III Circuit from Bhadrawati PMU with the sequence of event during 47

the occurrence.

Figure 5-54 : Frequency and df/dt plot from PMU describing the sequence of events during the occurrence. 47

Figure 5-55 : Bongaigaon Positive sequence voltage and positive sequence current of 400 kV Bongaigaon-Balipara-I & II Ckts. 48

Figure 5-56 : Connectivity diagram of Srisailam Hydro power station and its interconnection. 50

Figure 5-57 : Rate of change of frequency observed from various PMUs during high impedance fault. 50

Figure 5-58 : 400 kV Vijayawada bus voltage during high impedance fault. 51

Figure 5-59 : Negative and zero sequence current of 400 kV Vijaywada-VTPS-I from PMU during high impedance fault. 51

Figure 5-60 : PMU Plot of phase voltages of different station during 13:24 – 13:33 Hrs on 9-4-2013 53

Figure 5-61 : PMU Plot of phase voltages of different station during the fault at 13:26 Hrs 54

Figure 5-62 : Schematic Diagram of Omkareshwar and Near By area. 54

Figure 5-63 : Phase Voltages from Itarsi PMU during the fault at 13:47 Hrs. 55

Figure 5-64 : Positive sequence voltage from various PMUs during the fault at 13:47 Hrs 55

Figure 5-65 : DR of 220 kV Itarsi - Barwaha from Barwaha end which shows that fault was in R phase initially. 56

Figure 5-66 : Continuation of Figure 5-64 DR indicating the phase to phase fault appeared after 1 second resulting 56

in tripping of line in zone 1.

Figure 5-67 : Frequency observed at various nodes during the fault on 220 kV Itarsi Barwaha at 13:47 Hrs 56

Figure 5-68 : Phase Voltages from Itarsi PMU during the fault at 14:06 Hrs and tripping of Units on over frequency. 57

Figure 5-69 : Positive sequence Voltages from various PMUs during the fault at 14:06 Hrs and tripping of Units on over frequency. 57

Figure 5-70 : DR of 220 kV Itarsi - Barwaha from Barwaha end while charging of line from Barwaha which shows that fault 57

star ted in R phase initially.

Figure 5-71 : Continuation of Figure 5-70 DR indicating the phase to phase fault appeared after 1 second resulting 58

in tripping of line of zone 1.

Figure 5-72 : Frequency observed by various PMU during the fault on 220 kV Itarsi Barwaha at 14:06 Hrs. 58

Figure 5-73 : Connectivity Diagram of Udipi power station 59

Figure 5-74 : 400 kV Narendra bus voltage 59

Figure 5-75 : SLD of 400/220kV Bihar Sharif S/S 61

Figure 5-76 : 400kV Farakka Bus voltage 61

Figure 5-77 : DR of HV side of 315MVA ICT-II at Bihar Sharif overcurrent relay 62

Figure 5-78 : Line Current of 400 kV Farakka-Durgapur-I from Farakka PMU 62

Figure 5-79 : Frequency observed from Farakka PMU during ICTs tripping at Biharsharif 63

Figure 5-80 : Schematic diagram of the affected portion. (Islanded portin is shown with dotted lines). 70

Figure 5-81 : Frequency and ROCOF observed during the Incidence from Raipur PMU. 70

Figure 5-82 : Oscillation in Frequency from various PMUs in the NEW Grid. 71

Figure 5-83 : Mode Shape of 0.53 Hz. 71

(vii)

DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 5-84 : Voltage and Frequency plot of Farakka PMU along with the OMS result 72

Figure 5-85 : Oscillation as observed from the SCADA data in Voltage of DVC 72

Figure 5-86 : Frequency from PMU from Western, Northern and Eastern region of Indian Grid. 73

Figure 5-87 : Mode shape of 0.49 Hz Frequency from the analysis of various PMU 73

Figure 5-88 : Voltage, Real power and Reactive power observed from Gajuwaka PMU 73

Figure 5-89 : Oscillation observed in frequency at different location in WR. 74

Figure 5-90 : 1.03 Hz Mode shapeof the oscillation observed. 74

Figure 5-91 : Low Frequency oscillations in Dadri Frequency 75

Figure 5-92 : Zoomed view of Frequency Plots 76

Figure 5-93 : PMU plot of Dadri phase voltages 76

Figure 5-94 : Grid connectivity diagram of Paricha thermal power plant 77

Figure 5-95 : Frequency and ROCOF observed during the event from different PMU in NR. 77

Figure 5-96 : Phase Voltage observed during the event showing oscillation. 77

Figure 5-97 : Oscillation observed in the frequency and ROCOF. 78

Figure 5-98 : Modal Analysis of Oscillation performed by the OMS Engine. 78

Figure 5-99 : Connectivity Diagram of 400 kV Chabra station 79

Figure 5-100 : PMU plot of frequency and modal analysis. 79

Figure 5-101 : Zoom view of PMU plot of frequency and modal analysis. 79

Figure 5-102 : Single Line Diagram of NER Grid during the time of incidence. 80

Figure 5-103 : Oscillation in Frequency observed from NER PMUs. 80

Figure 5-104 : FFT Analysis on Frequency at different nodes of NER 81

Figure 5-105 : FFT of 400 kV Bongaigaon phase voltage. 81

Figure 5-106 : FFT of current of 132 kV Badarpur – Khleihriat S/C. 81

Figure 5-107 : 0.96 Hz with damping of 0.77 %. 82

Figure 5-108 : 0.94 Hz with damping of -0.35 %. 82

Figure 5-109 : 1.95 Hz with damping of 5.65 %. 82

Figure 5-110 : NER Grid view prior to the LFO observation i.e. 23:34 Hrs. 83

Figure 5-111 : R-phase currents of few Lines of NER Grid. 83

Figure 5-112 : R-phase voltages (in p.u.) of few nodes of NER Grid. 83

Figure 5-113 : During 12-128 seconds data window considered for analysis 84

Figure 5-114 : Mode shape of 1.0058 Hz. 84

Figure 5-115 : During 137-200 seconds data window considered for analysis 84

Figure 5-116 : Mode shape of 1.0074 Hz. 84

Figure 5-117 : During 213-241 seconds data window considered for analysis 85

Figure 5-118 : Mode shape of 0.9958 Hz 85

Figure 5-119 : During 253-280 seconds data window considered for analysis 85

Figure 5-120 : Mode shape of 0.9627Hz. 85

Figure 5-121 : AGTPP unit-wise MVAR from SCADA. 86

Figure 5-122 : Loktak unit-wise MVAR from SCADA 86

Figure 5-123 : Doyang unit-wise MVAR from SCADA 86

Figure 5-124 : Frequency plots during bus fault at 400 kV Parli Substation illustrating the antiphase swinging of Western region 89

machines with Northern Region.

Figure 5-125 : Frequency plots during bus fault at 400 kV Parli Substation illustrating the antiphase swinging of Western 89

region machines with Northern Region.

Figure 5-126 : Frequency plots during bus fault at 400 kV Parli Substation illustrating the antiphase swinging of Western region 90

machines with Northern Region.

Figure 5-127 : Phase angle difference during the islanding of NR from rest of the NEW grid on 30th July 2012. 91

Figure 5-128 : Phase angle difference during the islanding of NR, ER & NER from rest of NEW grid on 31th July 2012. 91

Figure 5-129 : Connectivity diagram of North-Eastern Regional Grid with NEW grid prior to islanding 92

Figure 5-130 : Angular Separation between Positive Sequence Voltages of NER PMUs w.r.t. Bhadrawati PMU (in WR) 93

along with NER Grid

Figure 5-131 : Positive Sequence voltages at Bongaigaon, Balipara, Agartala (When NER Grid Islanded) 93

(viii)

DECEMBER - 2013 POSOCO

Synchrophasors - Initiative in India

Figure 5-132 : Voltages at Bongaigaon showing significant dip in R-phase voltage at Bongaigaon 94

(Voltage input to PMU at Bongaigaon was from line CVT of 400 kV Balipara – Bongaigaon II).

Figure 5-133 : Angular Separation between Positive Sequence Voltages of NER PMUs w.r.t. 94

Bhadrawati PMU along with NER Grid Frequency (At time of resynchronization with NEW Grid).

Figure 5-134 : Positive Sequence Voltage at Bongaigaon, Balipara, Agartala (At time of resynchronization with NEW Grid) 95

Figure 5-135 : Frequency of NER and NEW grid (At time of resynchronisation with NEW Grid) 96

Figure 5-136 : HVDC Talcher-Kolar schematic Diagram 98

Figure 5-137 : HVDC Current reduction charecteristics 98

Figure 5-138 : Frequency profile of SR grid during the event 99

Figure 5-139 : NEW Grid frequency for the incident 99

Figure 5-140 : Schematic Diagram of WR and SR Grid Connectivity via HVDC Bhadrawati and PMU Location. 100

Figure 5-141 : SR frequency, WR frequency and HVDC power flow during 14:21 to 14:47 hrs. 101

Figure 5-142 : SR frequency, WR frequency and HVDC power flow during 14:49 to 15:19 hrs. 102

Figure 5-143 : SR frequency, WR frequency and HVDC power flow during 15:25 to 15:44 hrs. 102

Figure 5-144 : SR frequency, WR frequency and HVDC power flow during 16:04 to 16:25 hrs. 102

Figure 5-145 : EMS estimated and PMU measured angular difference between Korba and Kalwa over a day 103

Figure 5-146 : Korba Bus Voltage during Y phase to earth fault on 400 kV Korba -Batapara line. 104

Figure 5-147 : 400 kV Korba-Batapara Circuit Real and Reactive power during Y phase to ear th fault on400 kV Korba -Batapara line. 104

Figure 5-148 : Korba-Bhatapara Circuit Current during Y phase to earth fault on 400 kV Korba -Batapara line. 104

Figure 5-149 : Korba Unit 6 Current from PMU at Korba during Y phase to earth fault on 400 kV Korba -Batapara line. 104

Figure 5-150 : Korba Unit 6 Real and Reactive Power during Y phase to ear th fault on 400 kV Korba -Batapara line. 104

Figure 5-151 : Frequency observed from different PMU during Y phase to ear th fault on 400 kV Korba -Batapara line. 104

Figure 5-152 : Voltage from DR of Korba-Bhatapara Circuit from Korba end during Y phase to earth fault on 400 kV Korba -Batapara line. 105

Figure 5-153 : Current from DR of Korba-Bhatapra Circuit from Korba end during Y phase to earth fault on 400 kV Korba -Batapara line. 105

Figure 5-154 : Korba Bus Voltage during Y phase to earth fault on 400 kV Korba -Batapara line. 106

Figure 5-155 : Korba-Batapara Circuit Real and Reactive power during Y phase to earth fault on 400 kV Korba -Batapara line. 106

Figure 5-156 : Korba-Batapara Circuit Current during Y phase to earth fault on 400 kV Korba -Batapara line. 106

Figure 5-157 : Korba Unit 6 Current during Y phase to earth fault on 400 kV Korba -Batapara line. 106

Figure 5-158 : Korba Unit 6 Real and Reactive Power during Y phase to ear th fault on 400 kV Korba -Batapara line. 106

Figure 5-159 : Korba Unit 6 Real and Reactive Power during Y phase to ear th fault on 400 kV Korba -Batapara line. 106

Figure 5-160 : Voltage plot from DR of Korba-Bhatapara Circuit from Korba end during Y phase to earth fault on 400 kV Korba -Batapara line. 107

Figure 5-161 : Current plot from DR of Korba-Bhatapara Circuit from Korba end during Y phase to earth fault on 400 kV Korba -Batapara line. 107

Figure 5-162 : P & Q of Korba-Unit-VI using offline study. 108

Figure 5-163 : Screenshot of PMU data display at NRLDC on 23-August 2012 at 19:02 hrs 109

Figure 5-164 : R phase to Neutral voltage of Wangtoo 400 kV Bus 110

Figure 5-165 : Odhisha Demand met during 03-Oct 2013 to 17-Oct-2013. 111

Figure 5-166 : Talcher PMUPositive sequence voltage, frequency & df/dt plots (17:00 to 18:00 hrs) 111

Figure 5-167 : Positive sequence voltage, frequency plots of Talcher PMU (18:00 to 19:00 hrs) 112

Figure 5-168 : Positive sequence voltage, frequency & df/dt plots of Talcher PMU (19:00 to 20:00 hrs) 112

Figure 5-169 : Positive sequence voltage, frequency & df/dt plots of Talcher PMU (22:00 to 23:00 hrs) 112

Figure 5-170 : Positive sequence voltage, frequency & df/dt plots of Talcher PMU (23:00 to 00:00 hrs) 113

Figure 5-171 : Positive sequence voltage, frequency & df/dt plots of Talcher PMU (00:00 to 01:00 hrs) 113

Figure 5-172 : Positive sequence voltage, frequency & df/dt plots of Talcher PMU (01:00 to 02:00 hrs) 113

Figure 5-173 : Positive Sequence Voltage plots of Meerut and Hissar PMU (20:50-21:50 hrs) 115

Figure 5-174 : Positive Sequence Voltage plots of Meerut and Hissar PMU (01:00-02:00 hrs) 115

Figure 5-175 : Positive Sequence Voltage plots of Meerut and Hissar PMU (02:15-03:15 hrs) 116

Figure 5-176 : Positive Sequence Voltage plots of Meerut and Bassi PMU (Failed Autoreclose attempts of 400 kV Meerut-Muzaffarnagar) 116

Figure 5-177 : Positive Sequence Voltage plots of Moga and Bassi PMU (successful Autoreclose attempts of 765 kVMoga-Bhiwani) 117

Figure 6-1 : Frequency Controller testing on Bhadrawati HVDC monitored using the Synchrophasor 120

Figure 6-2 : Current and MW plots of 400 kV Meerut-Muzaffarnagar line during sudden reduction in power at Tehri Unit-III 121

Figure 6-3 : Current and MW plots of 400 kV Ramagundam-N’Sagar line during sudden reduction in power at Ramagundam Unit-IV 121

(ix)

DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 6-4 : Oscillation observed in Farakka PMU on 20-11-2013 at 1244 hrs 121

Figure 6-5 : Oscillation and coherent group of generators observed from various PMU in Western Grid on 28-11-2013 122

Figure 6-6 : Voltage, Current, frequency & rate of change of frequency plots 122

Figure 6-7 : 400 kV bus voltage of Bina substation 123

Figure 6-8 : 400 kV Satna bus voltage. 123

Figure 6-9 : Voltage of 132 kV and 400 kV Bus on actual scale 124

Figure 6-10 : Voltage of 132 kV and 400 kV Buses on p.u. scale. 124

Figure 6-11 : Visualization of measured currents for three different voltage level lines. 125

Figure 6-12 : Visualization of measured currents for three different lines in per unit. 125

Figure 6-13 : Visualization of measured currents for three different circuits on a logarithmic scale. 126

Figure 6-14 : Angular visualization available at operator console 126

Figure 6-15 : Angular variation of NR with respect to ER 127

Figure 6-16 : Contour visualization of WR MAP using PMU and SCADA data 129

Figure 6-17 : Contour visualization of All India with angular differences 129

Figure 7-1 : ROCOF from three different PMU vendors located in Western Regional Grid for tripping in Eastern Regional Grid 132

Figure 7-2 : Time Quality Flags in C37.118 Data Frame showing an unlocked clock status 133

Figure 7-3 : Time Quality Flags in C37.118 configuration frame showing normal, locked clock 133

Figure 7-4 : Fraction of Second (FOS) drift 134

Figure 7-5 : Korba and Bhadrawati Reported Angle as per C37.118 Standard 137

Figure 7-6 : Angle difference between Korba and Bhadrawati 138

Figure 7-7 : Reported Angles plot for missing Bhadrawati PMU data 138

Figure 7-8 : Angular difference between Bhadrawati and KSTPS in case of Missing Bhadrawati PMU data 138

Figure 7-9 : Reported Angles plot for missing KSTPS PMU data 139

Figure 7-10 : Angular difference between Bhadrawati and KSTPS in case of Missing KSTPS PMU data 139

Figure C-1 : Geographical locations of PMUs and Communication status 155

Figure C-2 : Visualization of Frequency at WRLDC 156

Figure C-3 : Visualization of Voltage magnitudes at WRLDC 156

Figure C-4 : Visualization of Current magnitudes at WRLDC 157

Figure C-5 : Visualization of low frequency dominant modes 157

Figure C-6 : Geographical location of PMUs and communication status 158

Figure C-7 : Visualization of phase angle differences 158

Figure C-8 : Visualization of system frequency from all PMUs 159

Figure C-9 : Visualization of voltage magnitudes 159

Figure C-10 : Visualization of low frequency modes 160

Figure C-11 : Visualization of Phase angle differences 161

Figure C-12 : Visualization of frequency plot 161

Figure C-13 : Visualization of df/dt trend 162

Figure C-14 : MW flow of Sasaram-Biharsharif-II 162

Figure C-15 : Geographical location of PMUs and Communication status 163

Figure C-16 : Visualization of Angular differences 163

Figure C-17 : Visualization of frequency 164

Figure C-18 : Visualization of df/dt 164

Figure C-19 : Visualization of positive sequence voltage 165

Figure C-20 : Visualization of positive sequence currents 165

Figure C-21 : Visualization of MW flows 166

Figure C-22 : Visualization of MVAR flows 166

Figure C-23 : Visualization of low frequency modes 167

Figure C-24 : Visualization of Angular differences 167

Figure C-25 : Visualization of df/dt 168

Figure C-26 : Visualization of Frequency 168

Figure D-1 : Eastern Region pilot project distribution of costs 169

Figure D-2 : North Eastern Region pilot project distribution of costs 169

Figure D-3 : Southern Region pilot project distribution of costs 170

Figure D-4 : Western Region pilot project distribution of costs 170

(x)

DECEMBER - 2013 POSOCO

Synchrophasors - Initiative in India

AGC Automatic Generation Control

API Application Program Interface

ATC Available Transmission Capability

AVR Automatic Voltage Regulator

CAPEX Capital Expenditure

CEA Central Electricity Authority

CERC Central Electricity Regulatory Commission

COI Centre of Inertia

CT Current Transformer

CTU Central Transmission Utility

CVT Capacitor Voltage Transformer

DR Disturbance Recorder

DSA Dynamic Security Assessment

DT Direct Trip

EHC Electro Hydraulic Control

EMS Energy Management System

ERLDC Eastern Region Load Dispatch Centre

FOS Fraction of Second

FRC Frequency Response Characteristic

GD Grid Disturbance

GI Grid Incidence

GIS Gas Insulated Substation

GPS Global Positioning System

GT Generator Transformer

HEP Hydro Electric Plant

HIF High Impedance Fault

HTLS Hankel Total Least Squares method

HVDC High Voltage Direct Current transmission

ICCP Inter Control Centre Protocol

ICT Interconnecting Transformer

IDMT Inverse Definite Minimum Time

IEC International Electrotechnical Commission

IEEE Institute of Electrical and Electronics Engineers

LDC Load Dispatch Centre

LFO Low Frequency Oscillations

LG Line-Ground

LL Line-Line

LLG Line-Line-Ground

LLL Line-Line-Line (3-phase)

NERLDC North-Eastern Region Load Dispatch Centre

NLDC National Load Dispatch Centre

NRLDC Northern Region Load Dispatch Centre

OMS Oscillation Monitoring System

PDC Phasor Data Concentrator

PDH Plesiochronous Digital Hierarch

PMU Phasor Measurement Unit

POSOCO Power System Operation Corporation Ltd

PSS Power System Stabilizer

PT Potential Transformer

RLDC Regional Load Dispatch Centre

ROCOF Rate of Change of Frequency

RTU Remote Terminal Unit

SCADA Supervisory Control and Data Acquisition

SLD Single Line Diagram

SOE Sequence of Events

SPS Special Protection Schemes

SRLDC Southern Region Load Dispatch Centre

ST Station Transformer

STFT Short Time Fourier Transform

SVC Static VAR Compensator

TCSC Thyristor Controlled Series Capacitor

TPS Thermal Power Station

TTC Total Transmission Capability

TVE Total Vector Error

UDP User Datagram Protocol

UHV Ultra High Voltage

UI Unscheduled Interchange

ULDC Unified Load Dispatch and Communication

UMPP Ultra Mega Power Plant

URTDSM Unified Real Time Dynamic State Measurement

WAMS Wide Area Measurement System

WRLDC Western Region Load Dispatch Centre

ABBREVIATIONS

(xi)

DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

(xii)

Synchrophasors - Initiative in India

DECEMBER - 2013 POSOCO1

Introduction

State, Regional and National Load Despatch Centers as mandated by the Electricity Act 2003 carry out the

supervision and control of Indian electricity grid. The grid operators at Load Despatch Centres monitor and supervise

system parameters and tie line flows with neighboring control areas and ensure integrated operation of the power

grid within their jurisdiction.

The complexity of Indian power system is increasing rapidly due to factors like demand growth, increasing

machine size, long distance power haulage, integration of renewable energy sources, increased competition in

electricity market and Large seasonal load variations. The skewed availability of energy resources vis-à-vis the

load pockets over large geographical regions in the country results in transmission of power over long distances.

The power grids are expected to operate closer to their limits in order to maximize utilization of the network. In

such a scenario, the role of the system operator has become very critical and a judiciary balance has to be struck

between the market and margins towards security of the interconnected system.

The decision of system operator in SLDCs, RLDCs and NLDC greatly depends on the data or information available

to them in real time. The existing SCADA or EMS systems acquire analog and digital information such as voltage,

frequency, active and reactive power flows and circuit breaker status through RTUs/SAS spread throughout the

system. This information is updated once every 4-10 seconds at respective LDCs. This information is not presently

time synchronized. Lack of a coordinated accurate time stamp for recorded data makes any reconstruction of a

timeline difficult and is time consuming. In addition, the lack of coordinated time stamping of data may cause the

recorded data to be suspect when it is used to reconstruct a timeline of events among Disturbance Recorders

(DR) and Event Loggers (EL) records.

The stress on the grid due to power flows is reflected by the angular separation between the nodes. SCADA/EMS

calculates these angles through state estimation methods which is not instantaneous and may not be accurate

due to time skewed data. The low resolution data acquisition also limits the transient analysis of events. In order

to overcome these limitations, an emerging new technology known as synchrophasor technology is increasingly

being used all over the world. Synchrophasors technology enhances the visibility and situational awareness and

is popularly known as Wide Area Measurements System (WAMS) in Power Systems. Wide area monitoring

through high speed communication helps in securing the system in minimum amount of time.

Synchrophasor technology comprise of Phasor Measurement Units (PMUs), Phasor Data Concentrators (PDCs),

Historian, communication network, real time visualization and offline toolboxes with following distinct features:-

� Phasor measurement units report the power system data 25 to 50 times in a second with synchronized

time stamp. This is much faster as compared to existing conventional technology.

� Phasor data concentrator collects the time synchronized data from PMUs and time aligns this data. Apart

from time aligning the data, PDC also checks data and time sync quality feed this data to Historian.

EXECUTIVE SUMMARY

Synchrophasors - Initiative in India

2 DECEMBER - 2013POSOCO

� Historian archives the PMU data for a period of few years depending on the storage capacity. The data can

be retrieved in user readable format and can be used for post-disturbance and forensic analysis. This data

can also be exported or imported to required standard format.

� Communication networks consist of high speed wide band communication infrastructure (optical fibres)

from substation to control centres.

� Real time visualizations include trend graphs of voltages, currents, frequency, angular separation between

nodes, MWs, MVARs and rate of change of frequency. Based on these trends, alarms can be raised for

decision making.

� Offline toolboxes consist of Signal Analysis Methods, Oscillation Monitoring Systems and Voltage Stability

Analysis etc.

Being the new evolving technology, Synchrophasors initiative in India was taken up by Power System Operation

Corporation Ltd. (POSOCO) in pilot manner in the year 2010 by installing 4 PMUs in Northern Region. Since then,

many other pilot projects have been taken up and implemented in other Regions also. Subsequently all these pilot

projects have been integrated and formed into a national level synchrophasors project which is under operation

with data availability from about 60 PMUs.

Overview of Synchrophasor pilot projects in India

As stated above, PMUs were installed on pilot basis in order to gain experience in Synchrophasor technology and

identify the challenges that may result prior to large scale deployment of PMUs in India. The PMUs installed in all

the five regions of the Indian grid were at strategically selected locations like generating stations, load centre

substation and interconnecting substations and as stated above a total of sixty PMUs have been installed in India.

All PMUs are ultimately integrated through respective Regional PDCs installed at Regional Load Dispatch Centres

to Central PDC installed at National Load Dispatch Centre, New Delhi.

Apart from the Pilot projects some PMUs are also installed as a demo project by different vendors and are also

reporting to National Load Despatch Centre through Regional PDCs. Futher MSETCL has also installed few PMUs

in Maharashtra under a separate project.

As regards to PDCs, it is stated that under the regional pilot schemes one Central PDC at NLDC, 5 Regional PDC

at respective RLDCs, 4 Local PDCs in Eastern Region and one Lab PDC at WRLDC are installed in India. At present

total 11 PDCs are functional and this is expected to grow with further concentration of PMUs in All India Grid.

Application of Synchrophasor data available through pilot project

The availability of Synchrophasors has considerably enhanced the wide area visualization and situational awareness

of power system behaviour under steady state as well in transient/dynamic conditions. The availability of

Synchrophasor data at control center has become first-hand information for grid operator to view and analyze any

transient phenomenon occurring in the grid. Various events that went un-noticed with present SCADA system can

now be detected and analyzed, opening up a completely new era in power system monitoring and control. There

is a paradigm shift in monitoring the grid after the commissioning of Synchrophasor pilot projects. Now-a-days

control centre operator first observes the signature of events through PMUs data and then refers to SCADA

system for the details of the events. Since the commissioning of Synchrophasor pilot projects in India, the

Synchrophasors - Initiative in India

DECEMBER - 2013 POSOCO3

synchrophasor data available at the Regional & National Load Despatch Centre has been utilized for real time

visualization and also for post-dispatch analysis in offline mode.

Grid event analysis at the Load Dispatch Centres in India hitherto was conventionally carried out with the help of

protection relay flags, Disturbance Records (DR) / Event Logger Records (EL) forwarded by the respective

transmission substations as well as the analogue data and SCADA Sequence of Events (SoE) Records, from wide

area SCADA/EMS and operator log book records. However challenges are posed in grid event analysis on

account of issues such as non-availability / healthiness / failure of recording instruments, human inhibitions in

data sharing, jurisdiction of the control centre over the station, time synchronization, portability/compatibility of

station DR/EL records with visualization software at the control centre, latency and skewedness in SCADA data,

and the challenges in the enforcement of regulations provided for grid event recording and data sharing. The

availability of synchrophasors has become an effective tool for analysis of grid events and facilitated preparation

of an accurate ‘first information report’ of an event occurring in the grid.

Apart from post fault analysis, synchrophasor data has been utilized for monitoring & analysis of oscillations,

computation of Frequency Response Characteristic, validation of correct operation of protection system, island

detection & re-synchronization of grid, dynamic model validation, visualization of special events such as HVDC

Frequency Controller Testing, Power System Stabilizer Testing, Turbine Valving and monitoring of cyclones. An

overview of the application of synchrophasors data in real-time and offline arrived on the basis of a number of

case studies captured in different RLDCs/NLDC since July 2012 is presented in the table below:

Application Description Reference No.ofin Present CaseDocument Studies

� Fault detection, classification and analysis

- Faults in Transmission Line,

power station/grid substation

- Tripping due to lack of protection Section 5.1 15

co-ordination/Instrument error.

- Faults involving high impedance

- Faults cleared by back up protections

� Low frequency Oscillation

- Inter Area Oscillation

- Inter Plant Oscillation Section 5.2 9

- Inter & Intra Plant Oscillation

� Detection of coherent group of generators Section 5.3 1

� Island Detection & Resynchronization to Grid Section 5.4 3

� Dynamic Model Validation Section 5.5 4

� PSS testing of hydro power station Section 5.6 1

� Monitoring during National disaster Section 5.7 2

Analysis of

faults / Grid

incidents

Detection and

analysis of

oscillations in the

power system

Post-dispatch

analysis of grid

operation

Enhancing

situational

awareness

Synchrophasors - Initiative in India

4 DECEMBER - 2013POSOCO

Challenges

Synchrophasor technology has many advantages, however implementing it on a large scale also poses many

challenges. In India, the project was first started on a pilot basis to obtain initial experience of the technology and

now it is being scaled up in the upcoming scheme known as Unified Real Time Dynamic State Measurement

Scheme (URTDSM Scheme). During the execution of pilot projects many challenges were faced, which include:

� Selecting locations for PMU placements

� Type of architecture required

� Setting up of standards and compliances

� Ensuring interoperability of PMUs

� Availability and setting up of communication infrastructure

� Developing tools for in-depth post facto analysis

� Event Detection

� Developing lucid visualizations for system operators

� Integration of Synchrophasor technology with SCADA

� Cyber Security Management & Compliance

Way-forward

Initial experience with Synchrophasor pilot project has been extremely beneficial and the analysis carried out

using Synchrophasor data is highly rewarding. It will be more beneficial to install PMUs throughout the country on

all EHV and UHV substations.

Currently, the PMUs are installed on the pilot/ demo basis. The pilot/demo projects have been extremely beneficial

in obtaining the knowledge of difficulties involved in installation and communication of PMUs. With this platform,

India is now fairly ready for large scale deployment of PMUs across the country. Under URTDSM scheme being

implemented by POWERGRID, it is envisaged to deploy around 1700 PMUs throughout All India Grid with aim of

enhanced visibility to the operator. Along-with advanced applications are also under development and efforts are

going on at a fast pace to attain maximum benefits using synchrophasor data.

Synchrophasors - Initiative in India

DECEMBER - 2013 POSOCO5

ACKNOWLEDGEMENT

The motivation, encouragement and support provided by Ministry of Power, Government of India, in deployment of

synchrophasors technology in India are gratefully acknowledged.

POSOCO is grateful to the Central Electricity Regulatory Commission for its pioneering role in recognizing the need

for synchrophasor and being considerate in approvingand providing funds for the synchrophasor pilot project in

India.

The technical assistance and guidance provided by the Central Electricity Authority and Power Grid Corporation of

India Limited, particularly during finalization of the technical specifications of the synchrophasor pilot project, are

duly acknowledged. POSOCO is thankful to the management and operating personnel of the concerned grid sub-

stations in the different regions for coordinating the commissioning of PMUs at their substations. Availability of

the wide band communication is very important in making any synchrophasor project operational. Availability of

communication channels at the desired nodes was one of the deciding factors for PMU placement in India. With

the concerted efforts and support of the Regional Transmission Groups and Telecommunication Department of

POWERGRID, the communication channels between some of the critical nodes could be arranged and these

efforts and support are also duly acknowledged.

Cooperation and support extended by all the esteemed members of the Regional Power Committees and other

stakeholders is also gratefully acknowledged.

POSOCO would like to thank researchers, scientists, engineers and institutions working on Synchrophasors/

Smar t Grid across the globe. The technical literature developed by them provided a solid foundation for the

initiatives taken in India. Special thanks to Prof. Arun Phadke (Virginia Tech University), Dr. Ken Mar tin,

Mr. Mahendra Patel (PJM), Prof. Anjan Bose (Washington State University), Dr. Vahid Madani (PGE, USA), Dr.

Prabha Kundur (KPSS, USA), Prof Venkatasubramanian (Washington State University), Dr N. D. R. Sarma (ERCOT

Texas), Prof A.M. Kulkarni (IIT-Bombay), Prof S. Soman (IIT-Bombay), Prof S.C. Srivastav (IIT-Kanpur), and Dr.

Nilanjan Senroy (IIT-Delhi) for sharing their knowledge and experience during various interactions with system

operators.

The herculean effor ts put in by all the persons/engineers,vendors and application developers involved in

conceptualizing, commissioning, designing applications and utilizing the synchrophasor technology as well as in

documenting the experience in different phases is acknowledged.

This report is a culmination of collective efforts and contribution of a large number of engineers within POSOCO/

POWERGRID. The valuable contribution by each and every one of them is highly appreciated and acknowledged.

Synchrophasors - Initiative in India

6 DECEMBER - 2013POSOCO

Precautions have been taken by Power System Operation Corporation (POSOCO) to ensure the accuracy of data/

information and the data/information in this repor t is believed to be accurate, reliable and complete. However,

before relying on the information material from this report, users are advised to ensure its accuracy, currency,

completeness and relevance for their purposes, and, in this respect, POSOCO shall not be responsible for any

errors or omissions. All information is provided without warranty of any kind.

POSOCO disclaims all express, implied, and statutory warranties of any kind to user and/or any third par ty,

including warranties as to accuracy, timeliness, completeness, merchantability, or fitness for any par ticular

purpose. POSOCO have no liability in tor t, contract, or otherwise to user and/or third party. Further, POSOCO shall,

under no circumstances, be liable to user, and/or any third party, for any lost profits or lost opportunity, indirect,

special, consequential, incidental, or punitive damages whatsoever, even if POSOCO has been advised of the

possibility of such damages.

By reading this repor t, the users/reader confirm about their awareness and agreement to this disclaimer and

associated terms referred elsewhere.

Copyright Information

This report has been compiled by POSOCO and is a result of contribution in some or other form of many experts, engineers, power

system professionals. Hence, this report is being published for the benefit of power system fraternity. Information in this report can

be used without obtaining the permission of Power System Operation Corporation. However, the material used from this report

should be duly acknowledged by way of citing the name of report, publishing month and name of Power System Operation

Corporation.

DISCLAIMER

Synchrophasors - Initiative in India

DECEMBER - 2013 POSOCO7

1.1. Introduction

The Indian electricity grid is among one of the largest power grids in the world. It has installed capacity of 229 GW

as on Oct. 2013 and comprises of five regional grids namely Nor thern, Eastern, North Eastern, Western and

Southern grids. Among these the first four are operating synchronously as N-E-W grid while southern grid is

connected asynchronously with the N-E-W grid through HVDC system. Southern grid is also likely to be synchronized

with N-E-W grid in first quarter of year 2014.

Operation of the Indian power grid is monitored and coordinated through the National Load Dispatch Centre

(NLDC) and five regional load dispatch centres (RLDCs), thir ty-three state load dispatch centres (SLDCs) and

several sub-load dispatch centres. Each control center has been provided with SCADA/EMS system which provides

necessary data visualization to the grid operators.

To complement visualization and to enhance situational awareness to the grid operators in control center,

synchrophasors projects have recently been deployed. The endeavor star ted with a pilot project in Northern

Region in the year of 2010 with four Phasor Measurement Units (PMUs) and one Phasor Data Concentrator

(PDC). Subsequently more pilot projects were taken up in all the regions and consequently the number of PMUs

has now increased to sixty and the Regional projects were further integrated at NLDC. Thus within a span of two-

three years the synchrophasors initiatives resulted in a national level project and have helped in understanding

and harnessing the benefits of this technology.

With the help of Synchrophasor technology, system operators are now able monitor the magnitude and angle of

each phase of the three phase voltage/current, frequency, rate of change of frequency and angular separation at

every few millisecond interval (say 40 milliseconds) in the Load Despatch Centre. Thus the transient / dynamic

behavior of the power system can be observed in near real-time at the control centre which hitherto was possible

only in offline mode in the form of substation Disturbance Records or through offline dynamic simulations performed

on network models.

With the interconnection of regional grids, the angular separations over a wide area are one of the key indicators

to assess the stress in the power system. The larger the phase angle difference between the source and sink,

greater is the power flow between those points. Hence greater phase angle differences imply larger stress across

that interface and larger stress could move the grid closer to instability. Angular separation could provide valuable

insights into the health of the synchronous interconnection. Relative phase angles across the system at the

BACKGROUND

1

Synchrophasors - Initiative in India

8 DECEMBER - 2013POSOCO

starting time of the disturbance can provide information about initial system loading conditions. They also provide

a very important indicator of how the system reacted to the disturbance. In case of oscillations, relative phase

angles can be analyzed to understand the nature and shape of the oscillations, and to provide knowledge of how

different parts of the system oscillate relative to each other. This information allows an assessment of what parts

of the system swinging coherently, and in what parts of the system would out-of-step conditions be more likely

to occur.

The initial experience in India with Synchrophasors was documented in the report titled “SYNCHROPHASORS

INITIATIVE IN INDIA” published in June 2012.

Previous edition of the report has covered following aspects in detail:

� Features of Pilot and demo projects in different regions

� Availability of online and offline applications

� Various case studies for each application

� Further analytics to be done

� Road map and suggestions for the future

1.2. Objective of this Report

Since the publishing of first edition of report on “Synchrophasors Initiatives in India”, in June-2012, the implementation

and experiences of Synchrophasor technology in India has progressed to a level of confidence. Since then, new

pilot projects have been implemented, integration at national level has been carried out, many availability of

synchrophasors data during grid incidences and events have enhanced the confidence of the grid operators.

In order to document further experiences and to benefit the power system fraternity world-wide, a working group

was formed by Power System Operation Corporation Ltd, India for compilation of the experience with Synchrophasors

technology in India in the form of second report. The working group is comprised of members from Regional/

National Load Despatch Centres of India to enumerate the experience and challenges in implementing the various

pilots and challenges experienced during execution.

This report attempts to compile the experience of the pilot/demo/complementary projects undertaken in Northern,

Eastern, North Eastern, Western and Southern Regional power system in India. This report covers the following

aspects:

� To comprehensively present the features available in the present pilot projects installed in all regions.

� Pilot projects Implementation and integration experience at POSOCO.

� Document the case studies for each application using Synchrophasors.

� To discuss the applications available and used in real time as well as offline analysis

� Way Forward for the Synchrophasor assisted grid operations

This report describes the currently available features in Synchrophasor pilot projects in India, associated benefits

achieved, use of Synchrophasor data in grid operation and POSOCO experience and challenges faced during

integration.

Document the case studies for each application using Synchrophasors.

Synchrophasors - Initiative in India

DECEMBER - 2013 POSOCO9

Further the project data and costs mentioned in the report are indicative and only approximate and not necessarily

the actual cost implication to the POSOCO/POWERGRID. Challenges mentioned in this report are based on the

experience and not necessarily the compulsory challenges for every utility around the world and including India.

1.3. Chapter-wise overview

Chapter-1iIntroduces the Indian Electricity Grid with its structure and the objective of the report. It also gives a brief

glimpse of the previous edition of the report. The literature survey carried out before and during the implementation

of the projects is documented in this chapter.

Chapter-2 gives the project details in all the five regions of Indian power system. Details of PMU, PDC, Historian

and Real time Dashboard are listed in tabular form to give a one shot view of the project across all five regions of

the Indian Power System.

Chapter-3 describes the architecture of the synchrophasor project in all the regions.

Chapter-4 details the national level integration of the synchrophasor project in India. The location of PMUs across

the country is depicted in this chapter. It also includes the architecture of the project at national level.

Chapter-5 illustrates an compendious list of case studies of grid incidences/events wherein PMU data was found

helpful. Variety of case studies such as fault detection and classification, Low frequency oscillation, detection of

coherent groups, island detection and resynchronization, Dynamic model validation and visualization of PSS

testing are discussed in this chapter.

Chapter-6 describes the experience with the utilization of the PMU data both in offline and online mode is discussed

in this chapter.

Chapter-7 describes the challenges faced during the installation and commissioning in multivendor system. It also

describes the challenges faced in analysing the data obtained from PMUs.

Chapter-8 gives the introduction to way forward in Synchrophasor technology for POSOCO/POWERGRID.

1.4. Literature survey

Though the Synchrophasor technology in India has not achieved deep penetration, the rate at which it is gaining

momentum is really promising. In the coming years there will be wide spread increase in number of PMUs

installed all across the country. The first-hand experience of the Synchrophasor technology was really enriching

and effor ts are going on to attain maximum benefits from PMUs. It is expected that, once the reliability and

confidence in utilization of the PMU data is attained it will slowly replace the conventional SCADA systems. Indian

Power System scenario is very complex mainly due to geographical reasons. The concentration of generators and

loads in the country dictates the construction of the transmission network. Ever since the invention of PMUs, it

has become a key research topic for improving the power system operation. India, in the quest of attaining

maximum availability and reliability, has taken the Synchrophasor technology very seriously and the experiences

in its implementation are very well documented in this second Synchrophasor report.

Synchrophasors - Initiative in India

10 DECEMBER - 2013POSOCO

It is well known fact that, Proof of Concept (PoC) validation and pilot/demonstration is very much required to be

carried out before implementing the Synchrophasor technology on large scale. The pilot projects are being carried

out on the basis of many research results and utility experiences on Synchrophasor technology all across the

world. This report includes some of the results which were also presented in some of the conferences. It includes

the benefits derived from the data obtained from PMUs in the Indian Power Grid. Many interesting case studies

were observed which are presented in references.

1.4.1. Fundamental understanding of Synchrophasor technology

Before star ting the project it was extremely necessary to understand the fundamentals of the Synchrophasor

technology. The preliminary understanding regarding PMUs and few of its applications is explained very

comprehensively in. [B1-B2]. Since the tolerable frequency band in Indian grid is from 49.7 Hz to 50.2 Hz, it is

extremely necessary to determine the correct value of phasor at off nominal frequencies, where small deviation in

frequency may cause large errors in measurements.

1.4.2. Initial experiences from around the world

The pre-execution experiences regarding the PMU installation and its use across the world were deliberated in

[B3] were very useful in understanding the challenges and preparedness required. Due to high resolution data of

PMU of around 25 samples per second as followed in India and the ability to measure additional quantities like

angles, ROCOF and sequence components, the amount of data required to be transmitted by the PMUs to the

PDCs is huge. As the number of PMU increases this data size also increases exponentially. The overheads added

from each PMU further increases the size. One method to address this problem as mentioned in [B3] is to have

intermediate PDC installed transmitting data to main PDC which will at least reduce the overheads to be transmitted.

Diverse requirements from the stakeholders, hinders the customization of the technology.

Before installation on a large scale, pilot projects were carried out and the locations were to be decided. Optimal

placement techniques are explored in many research papers in order to increase the observability of the system.

The [B4] discusses various possible locations where PMU should be placed. It describes the selection of PMU

locations based on three selection criteria viz. Criteria based selection, selection by topology analysis and selection

by dynamic analysis. In order to attain varied experiences and to attain at least partial observability, PMUs were

installed in India on the basis of certain thumb rules mentioned in the previous report and other literature. Currently,

the PMUs are installed at generating stations, load centers, HVDC links, interregional lines stations and critical

intermediate substations.

1.4.3. Communication

In order to make effective use of PMUs, the communication required between PMUs and the PDCs to which they

report must be reliable. The IEEE standards C37.118 [B42], introduces the concept of frames for transmitting data

from PMU to PDC. The bandwidth of the communication channel should be decided from the communication

traffic in the utility environment. [B5] shares the experience of PMUs communication in Utility environment. A free

version of PMU connection tester available from Grid Protection Alliance (GPA) was really helpful for testing the

PMU configuration on sites.

Synchrophasors - Initiative in India

DECEMBER - 2013 POSOCO11

1.4.4. Offline applications

The process of application development from the Synchrophasor data is also needed to be developed simultaneously

along with the installation. Due to the time stamping of the data, the analysis based on PMU data is fairly

accurate. Various possible offline applications are listed in [B6]. Effor ts are going on to achieve each of the

application in Indian power systems. The experiences of Synchrophasor technology in case of faults were discussed

in the earlier edition of this report also. PMU helps in identifying the type of faults. The behavior of the voltage and

currents for LG, LL, LLG and three phase faults are different. The nature of faults can be identified from the PMU

measurements easily. The applicability of PMUs in identifying the location of faults is also explored. The number

of PMUs installed in the Indian power system at present are very less. The effective use of the information derived

from such less number of PMUs needs to be explored. [B7] throws some light on how useful information can be

derived from such a small percentage of PMUs in the system. The same reference also explains the detection of

line outage using Phasor angle measurements. Although the methods are not implemented yet, but possibilities

for including them in the system is high. Some case studies depicting the detection of approximate location of

faults are discussed in this report.

The most important benefit of WAMS is that it gives real time angle difference between the nodes. Conventionally,

the angle difference is calculated using state estimation techniques or offline power flow techniques. The angle

difference gives the indication of stresses on the system. The measurement of node angles faced the problem of

angle wrapping. This introduced erroneous result in calculation of angular difference. This problem was addressed

in [B8]. The previous edition of the report focused on stability assessment based on angular difference between

the nodes.

The increasing stresses on the power system have witnessed the problem of low frequency oscillations in the

power systems. Low frequency oscillations may occur due to small changes in the system or can be due to a

fault in the remote location. These oscillations which were difficult to monitor earlier can be very well monitored

using the PMU measurements. Numerous mathematical techniques for analysis of low frequency oscillations are

discussed in the literature. The simple frequency domain technique such as Fourier transform in the form of FFT

can be used for initial analysis of the signals. Techniques such as STFT and wavelet transform which give the

instant of the fault or any ambient change were used in [B9-B10]. PMUs helped in analyzing low frequency

oscillations in Indian Grid also. The references [R5-R6] describes the experiences of low frequency oscillations in

Indian grid and their analysis. These LFOs were confirmed by multiple mathematical techniques such as Matrix

Pencil, Prony analysis and HTLS. [B18] explores the possibility of performing Matrix Pencil, HTLS and Prony

analysis on real time basis. This paper also explores the modulation scheme for HVDC to damp out interarea

oscillations when the OMS detect poorly damped oscillation.

The PMUs were also helpful in detecting islanding conditions in the system. Detection of island formation is one

of the most critical case in Indian power system since the Indian power system is largely interconnected. [B13-

B14] discusses few methods of islanding detection. [B13] Mentions the passive methods based on voltage,

frequency and rate of change of frequency and the active methods based on forced frequency shifting, reactive

power fluctuation etc. for islanding detection. Generally as of now, the passive methods have helped in detection

of islands. Few of the case studies are presented in this report related to islanding detection are offline in nature.

Synchrophasors - Initiative in India

12 DECEMBER - 2013POSOCO

1.4.5. Real time applications

The application of PMU during real time is the desired goal of the project. The PMUs must be able to create

situational awareness of the system in real time in order to make the operator to take preventive actions. In [B15],

it is clearly deducible that most of the blackout events occur due to lack of situational awareness. Legible

visualizations need to be developed in order to make the operator aware of the situations. The [B26] discuss

different types of visualizations which help the operator to understand the data. The common types of visualization

are the trend graph, polar plots etc. In order to depict small signal analysis output data on the visualizations, online

oscillation monitoring tools are essential. Effor ts are still going on to provide better easily understandable

visualizations for the operators regarding the condition of the power system.

Synchrophasor technology is a step towards smart grid in transmission system. It is required to be implemented

on a large scale to increase the observability of the system. The variety of case studies analyzed using PMU data

provide a platform for research and understanding more about power system. With new applications continuously

being identified and researched upon, Synchrophasor prove to be a promising technology for improving the reliability

in the power system.

Synchrophasors - Initiative in India

DECEMBER - 2013 POSOCO13

The Synchrophasor initiatives in India star ted with the implementation of a very simple project consisting of 4

PMUs and 1 PDC along with data historian and operator console in May 2010 in Northern Region. Subsequently,

other pilot projects were taken up in different regions. Later on these all projects were integrated at National level

by providing a PDC at National level in National Load Despatch Center located at Delhi. Details of the projects are

given below in Table 2-1.

Table 2-1 : Project Details

Sl. No. Description Details Pertaining to

ER NER NR SR WR NLDC

1 Project Type Pilot Pilot Pilot Pilot Pilot Pilot

2 Number ofPMUs 8 6 8 6 11 18

Installed

ERLDC,Kolkata

BinaguriS/s

3 PDC Biharshariff NERLDC, NRLDC, SRLDC, WRLDC, NLDC, Locations S/s Shillong New Delhi Bengaluru Mumbai New Delhi

RourkelaS/s

Sasaram

S/s

2.1. Phasor Measurement Units (PMU)

PMUs installed under these projects provide time stamped synchronized measurements to Phasor Data

Concentrators (PDCs) installed at Control Center at a reporting rate of 10, 25 and 50 frames/second. Most of the

PMUs installed at EHV substations are reporting in IEEE C37.118-2005 protocol combination of either One/Two

sets of Voltage or one/two sets of Current signals. The major features of Phasor measurement units installed in

different regions are given in Appendix-A, Table A-1.

OVERVIEW OF SYNCHROPHASOR PROJECTS

2

Synchrophasors - Initiative in India

14 DECEMBER - 2013POSOCO

2.2. Phasor Data Concentrators (PDC)

The Phasor Data Concentrators receives data from various PMUs, aligns the received data and forwards the

aggregated data to real time applications. The major features of Phasor Data Concentrators installed at different

Control Centers are given in Appendix-A, Table A-2.

2.3. Data Historians

The data historian systems have been provided to archive the Synchrophasor data for later retrieval and analysis.

Since all projects have been taken independently, all have separate data historians. The features available in the

historian installed at different control centers are tabulated in Appendix-A, Table A-3.

2.4. Data Visualisation

Visualization is used for showing data to the control room operators in a comprehensible way and has been

extended to Control Rooms of the respective control center. This is used for real time monitoring through

Synchrophasor data. Features of operator dashboard available in different control centers are given in Appendix-A,

Table A-4.

Synchrophasors - Initiative in India

DECEMBER - 2013 POSOCO15

3.1. Eastern Region

The WAMS pilot project of ERLDC consists of installation of PMUs with GPS system initially at eight substations

of Eastern Region. The Phasor data from these locations will be monitored at ERLDC. The critical PMUs are also

integrated with the station PDC. The PDC at ERLDC shall forward PMU data to PDC installed at NLDC and also to

the visualization unit and data archival server. The schematic architecture of the Project is shown Figure 3-1 and

PMU geographical locations are shown in Figure 3-2.

Figure 3-1 : Architecture of PMU pilot project in Eastern region

ARCHITECTURE OF SYNCHROPHASOR PROJECT

3

Synchrophasors - Initiative in India

16 DECEMBER - 2013POSOCO

3.2. North Eastern Region

M/s SEL has installed PMUs at selected eight locations in North Eastern Region. SEL 700G PMU model has been

installed at all locations. The installed PMUs are being used as measurement class, reporting 12 phasors and 4

analogs with reporting rate of 25 frames/sec. The most of communication links are having a bandwidth of 2Mbps,

offering good speed for transfer of data between PMUs and PDC. The architecture of PMU pilot project in NER is

shown in Figure 3-3. Synchrophasor data is being transferred from PMUs to PDC through various routers, firewall and

LAN switches. The received data from PMUs are not only presented to NERLDC Control room, visualization is

extended to RPC, SLDCs and NLDC.

Figure 3-2 : Location of PMUs in Eastern region

Synchrophasors - Initiative in India

DECEMBER - 2013 POSOCO17

Figure 3-3 : Architecture of PMU project in North Eastern region

The Geographical locations of PMUs in North Eastern region are shown in Figure 3-4.

Figure 3-4 : Geographical locations of PMUs in North Eastern Region

Synchrophasors - Initiative in India

18 DECEMBER - 2013POSOCO

3.3. Northern Region

PMU pilot project implemented in Northern region has fourteen PMUs. The locations of PMUs were selected in view

of observability of dynamics of NR and availability of communication links. Through existing wideband communication

links the PMUs are reporting to PDC placed in NRLDC. The synchrophasor application consists of historian,

visualization of events, alarm alerts and visualizations in real time. It also consists of visualization of low frequency

dominant modes existing in the system. Architecture of PMU pilot project in Northern region is shown in Figure 3-

5 and PMU Geographical locations are shown in Figure 3-6.

Figure 3-5 : Architecture of PMU pilot project in Northern region

Figure 3-6 : Geographical Locations of PMU pilot project in Northern region

Synchrophasors - Initiative in India

DECEMBER - 2013 POSOCO19

3.4. Southern Region

PMU pilot project in southern Region involves installation of six PMUs and the associated application software.

The PMUs are installed by M/s SEL and this project has been successfully completed by 31st March 2013. An

additional four PMUs were also installed by M/s SEL under the Northern region PMU project (NLDC project). The

communication link from PMUs to PDC is fiber optic, other than PMU in Narendra which is using VSAT link of

KPTCL. PMUs were spread all over southern region communicating with PDC at SRLDC. The schematic architecture

of the Project is shown Figure 3-7.

Figure 3-7 : Architecture of PMU pilot project in Southern region

The geographical locations of PMUs in southern region is shown in Figure 3-8.

Figure 3-8 : Geographical locations of PMU

Synchrophasors - Initiative in India

20 DECEMBER - 2013POSOCO

3.5. Western Region

The architecture of pilot project in western region is shown in Figure 3-9. M/s Kalkitech in collaboration with

National Instruments (NI), USA has installed PMUs (NI -cRIO-9024) in selected eleven locations under WR PMU/

PDC Interim Pilot Project. M/s. SEL has installed four PMUs under NLDC project, One PMU (Siprotec 6MD85) is

installed by Independent Power Producer(IPP). SYNC 4000 PDC is installed to align and aggregate the all fifteen

PMUs data. eDna (M/s. Instep) Visualization and historian software is installed at WRLDC to store data as well as

operator console visualization. The communication link connecting PMUs and PDC is mostly provided by

POWERGRID. These communications links are having a bandwidth ranging from 64Kbps to 2Mbps depending

upon location and feasibility. All the PMUs transfer the Synchrophasor data to PDC in IEEE C37.118-2011 standard.

Figure 3-9 : Architecture of PMU project in Western region

The Geographical locations of PMUs in western region are shown in Figure 3-10.

Figure 3-10 : Geographical locations of PMUs in Western region

Rajkumar
Typewritten Text

Synchrophasors - Initiative in India

DECEMBER - 2013 POSOCO21

4.1. National WAMS Project Architecture

At the National level one central PDC is installed at National Load Despatch Centre (NLDC), Delhi. This Central

PDC is integrated with the PDCs installed at five regional control centres through dedicated 2 Mbps optical fiber

communication links. The architecture of pilot project taken up at National Load Dispatch Center for all India

Synchrophasor data integration is shown in Fig 4-1. In addition to above 6 numbers of PDCs, one at National and

five at regional control Centres, 4 nos of local PDCs are also installed in Eastern Region and one Lab PDC also

installed at Western Region control Centre. Hence at present total 11 numbers of PDCs are functional in India

(details of PDCs and locations are given in Appendix B, Table B-6).

Figure 4-1 : National WAMS Project Architecture in India

There are Fifty seven PMUs installed by RLDCs / NLDC under different Pilot Projects, apart from these, three more

PMUs are installed by IPPs. PMUs installed in a region are reporting to PDC (Phasor Data Concentrator) of that

region. At NLDC PMUs data are available through regional PDCs. PMU measures the Voltage Phasors, Current

Phasors, Frequency, Rate of change of frequency etc The inputs given to the PMUs are 110 Volt from the secondary

side of PT/CVT of 400 KV/220 KV/132 KV buses and 1 ampere three phase current inputs from CTs of the selected

feeders (list of the PMUs and feeders in given in Appendix-B) PMUs are GPS clock synchronized and reporting to

NATIONAL LEVEL INTEGRATION OF SYNCHROPHASORS

4

Synchrophasors - Initiative in India

22 DECEMBER - 2013POSOCO

respective Regional PDCs at 25 Frames/Second i.e. every control center is updating Phasor data every 40 milli

seconds, with the integration of Regional PDC to National PDC has facilitated all India level monitoring.

Apart from the Pilot projects some of the PMUs are also installed by the vendors as a demo project. These demo

project PMUs are also integrated with the Regional PDCs alongside the PMUs of Pilot projects. MSETCL also

installed few PMUs in Maharashtra EHV network. Geographical locations of PMUs are shown in Figure 4-2.

Figure 4-2 : Geographical Locations of PMUs in India

Synchrophasors - Initiative in India

DECEMBER - 2013 POSOCO23

Before the integration and up-scaling of regional projects to National level it was not possible to analyse the

impact of an event occurred in one region on the far situated substations located in other regions. After the

availability of all regional PMUs data at National Control Center it became possible to visualise the grid wide

impact of any grid event.

4.2. WAMS Infrastructure at NLDC

Under the project one PDC, one Historian along-with SAN storage (installed at NLDC) and eighteen nos. of PMU

was envisaged, which are installed at selected locations all over the India. Details of the SEL supplied PDC and

Historian are attached as appendix-A. Currently all five regional PDCs are integrated with Central PDC at NLDC.

NLDC PDC (SEL - 5073) is receiving data at 25 frames per second from all regional PDCs. The communication

links between Regional PDCs and NLDC PDC are 2 Mbps each.

Historian installed at NLDC is expected to handle large volume of time stamped measurement data and typically

used for saving and retrieving phasor data. Historian is connected with the SAN storage (9 TB) to store the

historical data. Data from historian can be retrived in csv or COMTRADE (ASCII & Binary) formats.

The visualizations for system operators are custom made and these consoles are made in historian. Historian

quickly translates Synchrophasor data into visual information through trend and dial displays. SEL-5078-2 performs

modal analysis on received event data from PDC and the results are stored. The data from historian not only

improvises system operator decision also helps system planners to improve system models.

4.3. ERLDC PDC Integration

At present Jamshedpur, Ranchi, Farakka and Talcher PMUs (Under NRLDC phase-II PMU project) are reporting to

NLDC PDC directly. A dedicated 2Mbps communication link has been provided by POWERTEL from ERLDC, Kolkata

to NLDC, New Delhi. As per future plan all these PMUs will be reporting to ERLDC PDC and subsequently all PMUs

data including 8 PMUs under ERLDC WAMS Pilot project will report to NLDC PDC through ERLDC PDC.

4.4. NERLDC PDC Integration

All Eight PMUs installed in NER have integrated to NLDC PDC through NER PDC in C37.118 protocol, these two

PDCs are connected through a 2 Mbps Communication Channel.

4.5. NRLDC PDC Integration

At present all the Fourteen (14) PMUs installed in Northern Region are integrated to NLDC PDC through NRLDC

PDC in C37.118 protocol.

4.6. SRLDC PDC Integration

Presently Ten (10) PMUs are installed in Southern Region under the Pilot project and are repor ting to PDC at

SRLDC which have been integrated with PDC at NLDC. The communication link is a dedicated 2 Mbps link from

SRLDC to NLDC.

Some PMUs under demo project are also installed in Southern Region and are integrated with PDC installed at

SRLDC. These PMU are also reporting to NLDC.

Synchrophasors - Initiative in India

24 DECEMBER - 2013POSOCO

4.7. WRLDC PDC Integration

All PMUs reporting at WRLDC are reporting to NLDC PDC through a dedicated 2 mbps communication link in

C37.118 protocol. Currently Sixteen WR PMUs are integrated with NLDC PDC through WRLDC PDC. During initial

stage of integration, data with WRLDC to NLDC used to be frequently interrupted. The inherent peculiarity of WR

Synchrophasor project is the varying nature of communication channels from bandwidth range starting from

64kbps to 2 Mbps in between PMU locations to WRLDC PDC, in addition the initial memory allocation for input

buffer was only 100MB, due to low buffer size and slow communication channels, few data frames were discarded

at PDC level. After rigorous exercises, by increasing the input buffer size at WRLDC PDC to 500MB, the data

interruption problem has been solved since then.

Some PMUs under demo project are also installed in Western Region and are integrated with PDC installed at

WRLDC. All these PMUs are also reporting to NLDC.

DECEMBER - 2013 POSOCO25

Synchrophasors - Initiative in India

One of the greatest advantages of synchrophasor measurement is availability of time synchronized data obtained

from various grid stations spread across a wide geographical area covering thousands of square kilometers. The

synchrophasor data is being extensively used for real time and post event analysis.This chapter envisages the use of

the synchrophasor data for event detection and event analysis for the purpose of development of analytics and tools

to monitor the event. The whole chapter has been divided into various categories of analysis for which the data was

used. This was followed by the collective knowledge from all the NLDC/RLDCs kept in form of inferences derived, key

points and statistics.

Various grid events have been analyzed using the synchrophasor data along with other data like Station Disturbance

recorder (DR), Event logger (EL), SCADA Sequence of Event (SOE) etc. These events can be broadly classified in

the following categories:

1. Fault detection, classification and analysis

2. Low Frequency Oscillation

3. Detection of Coherent Group of Generators

4. Islanding Detection and their resynchronization with the grid

5. Dynamic Model Validation Using Synchrophasor data

6. Visualization of PSS testing.

7. Monitoring of Natural disasters.

These are the major categories of various types of events in the Indian grid which are analyzed with the help of

Synchrophasor data. Each category consists of various case studies from different regions which are discussed in

section ahead. These case studies have helped in identifying the protection system/controller issues present in system

and accordingly taking corrective measures.

5.1. Fault Detection, Classification and Analysis

Fault detection, localization, recovery and its analysis is the focal point of research in field of power systems since the

establishment of electricity transmission and distribution systems. Main objectives of any fault analysis are to provide

information to understand the reasons that has led to the interruption, performance of protective equipments and

remedial actions taken to avoid its occurrence in future. There are two methods to analyze any fault in power

system which are as follows:

USE OF SYNCHROPHASOR DATA -CASE STUDIES

5

26 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

1. Field measurement based fault Analysis: Any disturbance is associated with abnormal changes in current,

voltage, power and power angle. These perturbations in the electrical parameters can be captured by recording

devices with high sampling rate. These measurement help in finding the type of faults, elements affected by

the fault, fault current and its characteristic, protections operated, mal-operation or failure of protection

system, fault clearing time, fault location and distance etc.

2. Offline simulation based fault analysis: Fault analysis from this approach is cumbersome activity and

time consuming. This type of fault analysis is performed to visualize the large event like grid disturbance

and blackout. It helps in finding the large scale shor tcomings in the system and give insight to the

planners to plan the course of action to safeguard the system. This type of analysis first requires a very

reliable sequence of event from the various measurements.

Field measurements for any fault are available in basically three forms:

1. Disturbance recorder (DR): Disturbance recorders or Numerical Relay outputs give insight into the measurement

aspect of the fault along with the protection. It allows the user to look into the measured electrical parameters

and electrical protection with progress of time. DRs are basically meant to analyse the response of individual

elements of power system.

2. Event logger (EL): Event logger (ELs) is basically a logging device for any sub-station or set of equipment

which aligns the different operation from the set list of devices (Relay, CB, Isolator, CT, and PT) and aligns the

signal with time synchronization. This will create a sequence of event (SOE) for any fault /trippings in the sub-

station.

3. Data Acquisition System (DAS): This is a fixed time interval data of the field measurement like current,

voltage, power etc. for operator visualization.

In recent years Phasor measurement Unit (PMU) has evolved as a very important tool for power system engineer to

analyze any disturbance/event in the grid. A combination of PMU data along with SOE from SCADA and EL & DR from

Sub-station has given a good insight into the fault analysis in the power system. It has considerably reduced the time

consumed for analysis and helped in characterizing the event.

This section describes various fault analysis case studies observed in Indian Power system and their analysis based

on PMU data along with DR/EL/SOE. From the Voltage and current magnitude, angular difference, sequence voltage

and current magnitude, frequency and rate of change of frequency 40 ms data plots, it is possible to find out the type

of fault, fault duration, successful/ un-successful auto-reclosure and operation/ mis-operation of protection system

The cases in this section have been categorized as:

1. Faults in Transmission line, Power station / Grid sub-station

2. Tripping due to lack of Protection co-ordination / Instrument Error.

3. Fault involving High Impedance

4. Faults cleared by back up protection

DECEMBER - 2013 POSOCO27

Synchrophasors - Initiative in India

5.1.1. Transmission Line Fault

Transmission line faults consist of 85-87% of the total number of faults occurring in power system. Transmission line

faults are classified as single line-to-ground faults, Line-to-line faults, Double line-to-ground faults and three phase

faults. Following case studies discuss the various type of faults occurring in transmission lines and their characterisation

using synchrophasor data :

5.1.1.1. LG Fault on 400 kV Sami Dehgam circuit-1 and Unsuccessful Auto reclosure

Date and Time : 03-05-2013 16:21

Data Used for Event Analysis : Dehgam, Sugen, Boisar, Sugen PMU

Overview: This case study discusses a single phase to earth fault on a transmission line, detection of unsuccessful

auto-reclosure and fault location based on frequency and rate of change of frequency.

Event Description: B-phase to earth fault had occurred on 400 kV Sami- Dehgam Circuit-1. Auto reclosure was not

successful due to persistent fault which led to tripping of line. Figure 5-1 shows the fault location and the connectivity

of the various sub-stations along one of the path whose PMU data was used for analysis.

Analysis: As observed from the Figure 5-1 and Figure 5-2, the frequency and rate of change of frequency vary

depending on the electrical location of fault. The electrical location is the impedance path between the fault location

and various sub-stations. More is the electrical distance between the fault location and PMU installed, lesser is the

variation in frequency and ROCOF. It can be observed that the change in frequency and ROCOF during the fault is

highest at Dehgam which is the nearest PMU and it decreases with increase in electrical distance of the PMU location

[B46].

Figure 5-1: Connectivity diagram showing PMUs at Dehgam, Sugen, Boisar and Bhadrawati Sub-stations.

28 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 5-2: Frequency and ROCOF from Various PMUs in Western Region

Figure 5-3: Voltages from the PMU at Dehgam end

Figure 5-4: Zero Sequence voltage from the PMU at Dehgam end

DECEMBER - 2013 POSOCO29

Synchrophasors - Initiative in India

From Figure 5-3 it can be observed that the voltage drop is highest in B-phase indicating fault in B-phase. The

duration of fault clearance was calculated from the zero sequence voltage shown at Figure 5-4. Two faults are

observed within a time gap of one second as the line auto reclosed for a persistent fault.

Figure 5-5: Current plot of 400 kV Dehgam-Gandhar II circuit from the PMU at Dehgam end

In the Current plot from PMU for 400 kV Dehgam-Gandhar II as shown in Figure 5-5, current in the faulty phase has

increased while in the remaining two phases there is an increment in Y phase, while small dip is ovserved in R phase.

As discussed in respect to Figure 5-2, fault can be localized based on excursion in frequency and ROCOF. The fault

was simulated in the PSS/E using dynamic simulation and the frequency variation during the fault was plotted which

is shown at figure 5.6. Hence it can be observed that similar results were obtained from Offline simulation studies

which were observed with synchrophasor data. The frequency change is maximum near to the fault and gradually

decreases with increase in electrical distance from the fault. Such type of characteristic will help in locating the source

of the fault in the grid.

Figure 5-6: Frequency plot obtained from the PSS/E Simulation for L-G fault on 400 kV Sami Dehgam 1

30 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

5.1.1.2. LL Fault on 400 kV Ranchi Sipat 1 circuit

Date and Time : 09-06-2013 19:07

Data Used for Event Analysis : Bhadrawati PMU

Overview: This case study discusses a phase to phase fault on a transmission line.

Event Description: R-phase to Y-phase to phase fault had occurred on 400 kV Ranchi-Sipat circuit 1.

Analysis: Voltage plot from Bhadrawati (Figure 5-7) shows that dip was observed in R and Y phase indicating phase

to phase fault while the zero sequence voltage (Figure 5-8) has decreased by marginal amount indicating no ground

was involved.

Figure 5-7: Bhadrawati Phase voltage during the fault on 400 kV

Ranchi-Sipat-I

Figure 5-8: Bhadrawati Zero sequence voltage during the fault on

400 kV Ranchi-Sipat-I

Figure 5-9: Bhadrawati Raipur II Current plot during the fault on 400 kV Ranchi-Sipat-I

DECEMBER - 2013 POSOCO31

Synchrophasors - Initiative in India

Figure 5-10: DR of 400 kV Ranchi Sipat 1 from Sipat end during the fault

From the current plot of 400 kV Raipur Bhadrawati 2 circuit from Bhadrawati shown in Figure 5-9 it can be observed

that the current in one of the faulty phase has decreased while in other increased. The increment is not substantial as

fault was being monitored by PMU installed at a bus which was far from location of fault. DR of 400 kV Ranchi-Sipat

circuit 1 shown at Figure 5-10 indicates occurrence of a phase to phase fault.

This case study helped in fault characterisation of LL fault on transmission line using synchrophasor data.

5.1.1.3. Three Phase Fault on 400 kV Dadri-Muradnagar Ckt

Date and Time : 24-09-2013 02:32 Hrs

Data Used for Event Analysis : Dadri PMU

Overview:This case study discusses an unbalanced three phase fault.

Event Description: Complete outage of Dadri Thermal station occurred due to failure of a 11 kV Distribution transformer

which was located underneath 400 kV Dadri – Muradnagar line, just 4 kilometers outside the powerstation The failure

of distribution transformer in turn caused a 3 phase fault in 400 kV Dadri-Muradnagar line. The line tripped on

operation of distance protection Zone-1 with 3-phase fault indication.

Analysis: Voltage of 400 kV Dadri bus obtained from Synchrophasor at Dadri is shown at Figure 5-11 and Current in

HVDC Dadri interconnector is shown at Figure 5-12. It can be observed that the voltage has dipped to a very low value

and recovered after the tripping of the faulty line. From DR shown at figure 5-13, it can be observed that fault was

initially involving Y & B phases which got converted to three phase fault. From DR it was observed that the fault

clearing time was 160 ms, and the fault current was of the order of 37 kA peak (26 kA rms).While the fault should

ideally have been cleared within 100 milliseconds, the adjacent section viz, 400 kV Muradnagar-Panki has a Fixed

Series Capacitor (FSC) at Muradnagar end which necessitated a delay in Zone-I timings at Dadri end.

32 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 5-11: Phase voltage of Dadri bus from PMU during three phase fault

Figure 5-12: Current of HVDC Dadri I/C from PMU during three phase fault

Figure 5-13: DR of 400 kV Dadri –Muradnagar Ckt from Dadri end during three phase fault

DECEMBER - 2013 POSOCO33

Synchrophasors - Initiative in India

Three phase faults are a rare event and that too close to a large generating substation. This incident brings out the

need for PMUs to be located at generator terminals to identify the dynamic behavior of generators under a

condition of fault in the power system.

5.1.2. Faults occurring at Power station & Grid Sub-station

Fault at or near a power station or a grid sub-station is always of high severity as it involves tripping of several

elements. Such faults occur mainly due failure of switchyard equipment’s or due to failure of jumpers. Faults which

involve complete station outage or multiple tripping are analyzed in detail using available measurements and remedial

actions are taken to avoid reoccurrence.

5.1.2.1. Multiple tripping of 400 kV lines due to failure of current transformer at Hassan substation

Date and Time : 10-03-2013 15:04 Hrs

Data Used for Event Analysis : Somanhalli PMU, DR,EL of Hassan substation & Udupi power station

Event Description: Current transformer installed in the tie bay of 400 kV Hassan-Mysore line-2 failed which in turn led

to tripping of four 400 kV transmission lines i.e., 400 kV Mysore-Hassan line-1 & 2 and 400 kV Udupi-Hassan line-1

& 2. Tripping of evacuating lines from Udupi power station led to generation loss of 800 MW. The loss of generation

led to over-loading 400 kV Hiryur-Neelmangla, 400 kV Gooty-Somanahalli and 400 kV Gooty-Neelamangala lines.

Figure 5-14 and Figure 5-15 shows the schematic diagram of area and the SLD of the Hassan 400 kV Sub-station

respectively.

Analysis: Figure 5-16 shows the 400 kV bus voltage recorded by synchrophasor installed at 400 kV Somanhalli sub-

station. The voltage plot indicates occurrence of two successive faults in Y phase with a time gap of nearly 1 second

between the two faults.

Figure 5-14: Schematic Diagram of Affected Area during

CT failure at Hassan S/sFigure 5-15: SLD of Hassan sub-station

The voltage drop was prominent in Y-Phase in both the cases which indicated a Y-Phase to earth fault. This in-turn

indicated failure of Y – phase current transformer at Hassan substation. From the negative sequence and zero sequence

current plot of 400 kV line Somanhalli-Salem line shown at Figure 5-17, it was inferred that the first and second fault were

cleared in 240 ms and 320 ms respectively i.e., there was delayed clearance of fault. A time gap of nearly 1 second was

observed between occurrences of the two faults.

34 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 5-16: 400 kV Somanhalli bus voltage from PMU during CT failure at Hassan S/s

Figure 5-17: Negative and Zero sequence current for 400 kV Somanhalli-Salem Line from Somanhalli PMU

Table 5-1: Sequence of events during the multiple tripping due to CT failure at Hassan S/s

DECEMBER - 2013 POSOCO35

Synchrophasors - Initiative in India

From the sequence of events (Table 5-1) it was observed that all the Main breakers connected to 400 kV Bus-2

had opened within 50 ms of occurrence of the fault due to operation of busbar protection for Bus-2. This was a

desired operation as the faulty CT comes in the zone of busbar protection of 400 kV bus-2.

Figure 5-18: DR of 400kV Hassan-Mysore line-2 (Hassan end) Figure 5-19: Fault time line

It can be observed from disturbance recorder data of 400 kV Hassan-Mysore line-2 shown at Figure 5-18, that the

voltage dip in Y-Phase occurred at 15:04:24.080 hrs and the rise in current at 15:04:23.889 hrs i.e., there is a 240 ms

delay in operation of distance relay. Direct trip command was sent from Hassan end to 400 kV Udipi and 400 kV

Mysore which resulted in tripping of breakers of 400 kV Hassan-Mysore line-1 & 2 and 400 kV Hassan-Udipi line

from remote ends. This was not a desired protection operation and needed further analysis.

In both the cases it was observed that there was delayed operation of distance protection of 400kV Hassan-Mysore

line-2 which had led to delayed clearance of fault. The delayed operation of distance protection relay has been taken

up with the relay manufacturer. The wrong configuration in Bus-bar protection scheme had led to the initiation of direct

trip command to the other ends which was later rectified.

It can be observed that this was a case of high resistance fault so the zero sequence Current will be low. Here PMU

data helps in knowing about delayed clearance of fault & multiple faults in Y-Phase and Un-successful auto re-close of

breaker.

5.1.2.2. LG and LLG Fault at LANCO Sub-Station

Date and Time : 02-04-2013 20:20 and 20:23 Hrs

Data Used for Event Analysis : Raipur PMU, DR from LANCO S/s, EL and SOE from LANCO S/s

Overview: This case study describes the Single phase to ground and Double phase to ground fault which occurred at

the same sub-station.

Event Description: Heavy wind condition had caused a tin cladding sheet to fall on the B Phase of GT bay and ST bay

which resulted in earth fault. Due to this Unit#1 at LANCO thermal power station tripped on operation of differential

protection of GT-1. During the incidence ST-2 had tripped on REF protection. Generation loss of 268 MW was observed

due to tripping of Unit 1 of LANCO. The connectivity diagram of the affected area is shown at figure 5-20.

36 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 5-20: Schematic Diagram of LANCO S/s and its connectivity

with nearby system

Figure 5-21: Frequency Measured from Sugen and

Raipur during fault at LANCO

Analysis: From the PMU data (Figure 5-21) it was observed that the two faults had occured at LANCO sub-station:

1. At 20:20 Hrs : B Phase to Ground fault

2. At 20:23 Hrs: Y-B phase to ground fault

It can be observed from the DR of 400kV LANCO-Sipat line (LANCO end) that voltage of B phase was nearly zero

during the fault (Figure 5-23 ). Heavy voltage dip was also observed in 400 kV bus voltage obtained from Raipur PMU

which was nearest to LANCO station shown in Figure 5-22. The current plot from Raipur PMU shown at Figure 5-24

indicates that the current had increased in B-phase while the current in one healthy phase had increased i.e. in R phase

and had decreased in the other healthy phase i.e. Y phase . This is also reflected in the DR of LANCO-Sipat Line which

is shown at Figure 5-25. From DR the fault clearing time was observed to be 82 ms while from PMU it was 120 ms.

In case of second fault which is LL-G fault , DR of 400 kV LANCO-Korba line(Figure 5-26) shows that voltage of faulty

phase has decreased which is also observed from the Raipur PMU shown in Figure 5-27. While the current has

shown a very unique charactristic as observed from PMU i.e. current of one faulty phase has increased while the other

has decreased as shown at Figure 5-28. From D.R shown at figure 5.29, it can be observed that current of faulty

phases are in phase opposition by 180o i.e. IY= - I

B . The fault got cleared in 79 ms as observed fom DR while PMU it

was observed to be cleared in 80 ms.

Figure 5-22: Voltage plot from the Raipur PMU during B phase to

ground fault at LANCO

Figure 5-23: Voltage from DR of 400 kV LANCO - Sipat

line from LANCO

DECEMBER - 2013 POSOCO37

Synchrophasors - Initiative in India

Figure 5-24: Current from the PMU at Raipur for Raipur-Bhadrawati 1

Ckt during B phase to ground fault at LANCO

Figure 5-25: Current from DR of 400 kV LANCO -Sipat line

from LANCO

Figure 5-26: PMU Voltage from the Raipur end during Y-B phase to

ground fault at LANCO

Figure 5-27: Voltage from DR of 400 kV LANCO-Korba

from LANCO

Figure 5-28: Current in Raipur-Bhadrawati 1 (Raipur end) during

Y-B phase to groung fault at LANCOFigure 5-29: Current in 400 kV LANCO -Korba line from LANCO

38 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

This case study also explained the validation of PMU data with the help of Disturbance recorder files.

5.1.2.3. Multiple tripping at 400/220 kV Mamidapalli substation

Date and Time : 03-08-2013 05:26 hrs

Data Used for Event Analysis : PMU data, D.R, E.L of all station involved in the incident

Overview: This event led to complete outage of a vital 400 kV grid station in Andhra Pradesh. There was load loss in

grid due to tripping of ICTs at Mamidapalli sub-station.

Event Description: All connected lines and ICTs tripped at 400/220 kV Mamidapalli (Hyderabad) sub-station of

APTRANSCO. The triggering incident was failure of R-phase current transformer in 400 kV Khammam line-1 Main bay

and failure of B-phase bus post insulator in Srisailam-2 Main bay at Mamidapalli substation. Blocking of Bus-bar

protection had occurred due to improper time delay setting of CT supervision relay. This had led to delayed clearance

of fault during the 2nd fault and led to complete station outage. The schematic network diagram and single line diagram

of 400 kV Mamidapalli sub-station is shown in Figure 5-30 and 5-31 respectively.

Figure 5-30: Schematic Diagram of the Area affected during multiple

tripping at Mamidapalli

Figure 5-31: SLD of 400/220kV Mamidapalli s/s

Analysis: From Figure 5-32 it can be observed that a fault had occurred in R-Phase at 5:26:58.640 hrs. This fault

got timely cleared in 120 milli seconds (approx). Now 840ms after occurrence of 1st fault in R-phase, a second

fault is observed in B-Phase and there was a delayed clearance of fault i.e., in 920 ms (approx). The R-phase fault

was sensed by distance protection relays at Mamidapalli and Khammam end and the R-Pole breaker (Main and

Tie breakers) were tripped at both ends through operation of distance protection at 5:26:58.789 hrs and this in turn

cleared the fault. The fault in R phase CT in Khammam-1 bay resulted in a 2nd fault in B-Phase bus post insulator

of 400 kV Srisailam Line-2 bay.

DECEMBER - 2013 POSOCO39

Synchrophasors - Initiative in India

Figure 5-32: 400 kV Ramagundam bus voltage during fault at

Mamidapalli S/s

Figure 5-33: Negative and Zero sequence current at 400 kV Gooty -

Neelamangla from PMU

Figure 5-34: Frequency change due to ICTs tripping at Mamidapalli resulting in Load loss

On further analysis of SOE/DR/EL it was found that there was operation of bus bar CT supervision relay which in

turn blocked the bus bar protection of 400 kV Bus-1 at Mamidapalli. Due to blocking of bus bar protection, the fault

could not be isolated and the connected lines and ICTs continued to feed the fault. The fault was sensed at remote

ends (Srisailam, Ghanapur, Khammam) by Zone-2 of distance protection and this resulted in tripping of all the

connected 400 kV lines to Mamidapalli sub-station from remote ends after zone-2 time delay i.e. 500 milli

seconds. The backup over current and earth fault protections at LV side of ICTs which have an IDMT characteristics

operated and tripped the ICTs after 1000 milli seconds after of occurrence of the 2nd fault. The fault got cleared

after tripping of all the connected elements at 400/220 kV Mamidapalli sub-station. The time delay setting of Bus

bar CT supervision relay at 400 kV Mamidapalli sub-station was reviewed and corrected. ICTs tripping resulted in

load loss leading to rise in frequency as displayed in Figure 5-34.

In this case validation of protection settings was done with synchrophasor data. The delayed clearance of fault was

due to blocking of bus-bar protection which had occurred due to incorrect setting of CT supervision relay.

40 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

5.1.2.4. Tripping of running units at Vijayawada TPS

Date and Time : 04-10-2013 14:55 Hrs

Data Used for Event Analysis : Ramagundam PMU

Overview: Running units-2, 3, 4, 5 & 6 at Vijayawada TPS (connected at 220kV) tripped at 14:55 hrs on 4-10-2013

(Unit-1 was under shutdown).The generation loss was 900MW and change in frequency was 0.25 Hz.

Event Description:Both the 220 kV buses at Vijayawada TPS had tripped due to failure of equipment connected to 220

kV Bus-1 & 220 kV Bus-2. This in turn had led to complete tripping of all elements. The schematic network diagram

and single line diagram of 220 kV Vijaywada sub-station is shown in Figure 5-35 and 5-36 respectively.

Figure 5-35 : SCADA diagram displaying the Area affected

Figure 5-36: SLD of Vijayawada TPS

DECEMBER - 2013 POSOCO41

Synchrophasors - Initiative in India

Figure 5-37: 400 kV Ramagundam bus voltage during tripping at

Vijayawada TPS

Figure 5-38: Negative & zero sequence current of 400 kV

Ramagundam-Nagarjuna Sagar-II during tripping of Vijayawada TPS

Figure 5-39: Frequency during the tripping of Vijaywada TPS

From synchrophasor data of Ramagundam shown in Figure 5-37 and 5-38, it can be observed that two faults had

occurred, 1st in B-Phase which was immediately followed by a fault in R-Phase. Both the faults were timely cleared.

The triggering incident was failure of B phase CT in 220 kV VTPS-Narsaraopeta line at VTPS end. It was informed by

sub-station representative that CT failure had also occurred in 220 kV VTPS-Podili line at VTPS end. The 220 kV

Nasaraopeta line is connected to 220 kV bus-2 and 220 kV Podili line to 220 kV Bus-1 at VTPS. Bus-bar protection of

both the buses acted due to failure of above CTs. This in turn led to outage of complete Vijayawada thermal station.

The frequency dip due to generation loss is shown in Figure 5-39.

In this case it can be observed that how PMU data helped in multiple faults detection. Detection of first fault in B-phase

and second in R-phase helped in validating the multiple failure of equipment at Vijayawada Thermal station.

42 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

5.1.3. Tripping due to lack of protection co-ordination/Instrument Error

In electrical grid, several times tripping may occur due to mis-operation of protection system which could be due to

incorrect or inadvertent settings in protection relay, lack of protection co-ordination/Instrument error in measuring

equipment, inherent relay characteristics & due to human error while carrying out protection testing. Few case studies

based on the above are discussed in the following section.

5.1.3.1. Multiple tripping of 400 kV lines at 400kV Ballia Station

Date and Time : 20-05-2013 18:01 Hrs

Data Used for Event Analysis : Ballia PMU, DR/EL from Ballia ,SOE from SCADA

Overview: All connected 400 kV lines at Ballia sub-station tripped on operation of overvoltage protection. The event of

multiple tripping was analyzed using the PMU data from Ballia sub-station. The results were also compared with the

station DR, EL and SCADA SOE.

Event Description:, During charging of 765kV Ballia-Lucknow line, multiple tripping of 400 kV lines occurred at 400

kV Ballia station on operation of overvoltage stage-1 and due to direct trip command received from remote end. Figure

5-40 and 5-41 shows the 765 kV and 400 kV Single line diagram of Ballia Sub-station. Table 5-2 shows the SOE for

the event and table 5-3 shows the implemented Over-voltage stage-1 protection setting at Ballia sub-station.

Figure 5-40: SLD of 765 kV Bus at Ballia Figure 5-41: SLD of 400 kV Bus at Ballia

Table 5-2: SOE from Ballia Sub-station

DECEMBER - 2013 POSOCO43

Synchrophasors - Initiative in India

Table 5-3: O/V Setting of 400 kV lines from Ballia S/s

Analysis: The preliminary tripping analysis was carried out with SCADA SOE and Synchrophasor data.

Figure 5-42: 400 kV Bus voltage of Ballia station in northern region from

PMU during multiple tripping.

Figure 5-43: 400 kV Bus voltage of Ballia station in northern region

while charging 125 Mvar Bus reactor

Figure 5-42 shows Ballia Bus voltage from which different events occurring during the incident can be observed.

Figure 5-43 shows the voltage variation while charging of Bus reactor. The charging of different elements to restore the

system can be observed from Figure 5-44. Figure 5-45 shows the voltage of Ballia 400 kV bus while charging of 240

MVAR Bus Reactor on 765 kV Bus. Repeated attempt to charge 765 kV Ballia-Lucknow circuit can be observed from

Figure 5-46. The rise in voltage of 400 kV Balia bus after successful charging of 765 kV Ballia-Lucknow can be

observed from Figure 5-47.

44 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 5-44: PMU plot of phase Voltages of Ballia S/s during

restoration sequence

Figure 5-45: PMU plot of phase Voltages of Ballia S/s while charging

240 Mvar Bus reactor at 765 kV Level

Figure 5-46: PMU plot of phase Voltages of Ballia sub-station during

repetitive attempts to charge 765 kV Ballia-Lucknow line

Figure 5-47: PMU plot of phase Voltages of Ballia sub-station after

successfull charging of 765 kV Ballia-Lucknow line

This case study has given an insight into the event in the sub-station where PMU is located. The crux of this

event is how the synchrophasor data helps in monitoring of real time restoration. It can be observed that event

detection can be accelerated during grid operation. Also it helped in rapid analysis of the event which usually

takes a lot of time.

5.1.3.2. Multiple tripping of Lines from Bhadrawati and nearby Sub-station on Overvoltage.

Date and Time : 19-07-2013 16:55 Hrs

Data Used for Event Analysis : Bhadrawati, Satna, Boisar, Dehgam, Sugen PMU; SOE from SCADA

Overview: This case study is similar to previous case study as here also all the lines tripped on overvoltage

according to their O/V setting. The uniqueness lies in the fact that overvoltage appeared due to tripping of HVDC

DECEMBER - 2013 POSOCO45

Synchrophasors - Initiative in India

pole. The associated filter bank tripped after 1.5 seconds during which voltage shot up to a high value. The event

of multiple tripping was analyzed using the PMU data from the Bhadrawati sub-station only. Then later the same

was confirmed using the DR/EL.

Figure 5-48: Schematic Diagram of Bhadrawati and Near By area

Event Description:

At 16:55 Hrs, due to fluctuation in auxiliary supply, valve cooling system main pump of HVDC Bhadrawati Pole 1

failed and resulted in HVDC Bhadrawati Pole-1 tripping on “VCC full flow very low alarm”. This has led to high

voltage at Bhadrawati beyond 440 kV and consequently lines from Bhadrawati tripped as per their O/V Stage 1

setting. Simultaneously, over voltage also appeared at Chandrapur and Parli (MSETCL) sub-station leading to

tripping of lines from these sub-stations. During this incident 400 kV Bhadrawati - EMCO I & II lines also tripped on

O/V from Bhadrawati end leading to tripping of EMCO Unit 1. Tripping of HVDC Pole 1 resulted into 480 MW load

loss while EMCO Unit 1 tripping led to generation loss of 182 MW. Figure 5-48 shows the schematic diagram for

the area affected during the tripping and Figure 5-49 shows the WR demand and frequency as observed from

SCADA.

Analysis: As observed from the Zero sequence voltage of Bhadrawati (Figure 5-50), no fault was present in the

system. Then from the voltage plot of Bhadrawati (Figure 5-41) it was observed that voltage went beyond 1.1 p.u.

which is the setting for over-voltage pickup for the relays. The tripping was sequenced using the SOE, O/V setting

of the various transmission lines and the voltage, current, Frequency and ROCOF from PMU at Bhadrawati. The

ease with which the event was analyzed using preliminary information, relay setting and the SOE can be observed.

All trippings have been shown in the Bhadrawati PMU voltage plot in Figure 5-51. It can be observed that with

each line tripping (reduction in MVAR), voltage has improved at Bhadrawati yet trippings continued due to reset

value of the relay being 98- 95% (1.078 -1. 045 p.u.) which has been discussed in the protection meeting for

corrective action.

Figure 5-49: Frequency and WR Demand from SCADA during

multiple tripping

46 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Table 5-4: Overvoltage Stage 1 Protection of various lines from Bhadrawati and Chandrapur S/s

Figure 5-50: Zero sequence Voltage plot of Bhadrawati from Bhadrawati PMU

Figure 5-51: Voltage plot of Bhadrawati from PMU along with the sequence of event during the occurrence

Circuit O/V Setting S-1 Status Tripping issue

400 kV Bhadrawati-Parli(PG) 1 1.1 p.u. 5 Sec Tripped No

400 kV Bhadrawati-Parli(PG) 2 1.1 p.u. 7 Sec Out No

400 kV Bhadrawati- EMCO I 1.1 p.u. 5 Sec Tripped No

400 kV Bhadrawati- EMCO II 1.1 p.u. 7 Sec Tripped No

400 kV Bhadrawati- Chandrapur 1 1.1 p.u. 5 Sec No tripping No

400 kV Bhadrawati- Chandrapur 2 1.1 p.u. 6 Sec Out to Control H/V No

400 kV Bhadrawati- Chandrapur 3 1.1 p.u. 7 Sec No tripping No

400 kV Bhadrawati- Chandrapur 4 1.1 p.u. 8 Sec Out to Control H/V No

400 kV Bhadrawati- Raipur 1 1.1 p.u. 6 Sec No Tripping No

400 kV Bhadrawati- Raipur 2 1.1 p.u. 7 Sec No tripping No

400 kV Bhadrawati- Raipur 3 1.1 p.u. 5 Sec Tripped Tripped 8 sec later

400 kV Bhadrawati- Bhilai 1.1 p.u. 5 Sec No tripping Not in Order

400 kV Chandrapur-Parli 1 1.1 p.u. 5 Sec Tripped No

400 kV Chandrapur-Parli 2 1.1 p.u. 6 Sec Out No

400 kV Chandrapur-Parli 3 1.1 p.u. 7 Sec Tripped No

400 kV Chandrapur-Khaparkheda 1.1 p.u. 5 Sec Tripped No

DECEMBER - 2013 POSOCO47

Synchrophasors - Initiative in India

Figure 5-52: Current plot of Bhadrawati-Raipur II Circuit from Bhadrawati PMU with the sequence of event during the occurrence.

Figure 5-53: Current plot of Bhadrawati-Raipur III Circuit from Bhadrawati PMU with the sequence of event during the occurrence

Figure 5-54: Frequency and df/dt plot from PMU describing the sequence of events during the occurrence

48 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

The event was then analysed using the current plots from PMU shown in Figure 5-52 and based on the tripping

sequence the current waveform in Raipur-Bhadrawati II circuit was in order. The similar current sensitivity was

observed in PSS/E simulation of the event which also confirmed the analysis. Fig 5-53 is shows the current

waveform of 400 kV Bhadrwati Raipur III which tripped at the end after the voltage shoot up at start of event which

was not in order with time setting of 5 second. Figure 5-54 shows the frequency and rate of change of frequency

plot from PMU. In the frequency it can be observed that for any tripping maximum change in frequency is observed

at Bhadrawati then at Boisar while no significant change is observed at other location like Sugen,Satna and

Dehgam. In this case synchrophasor data has helped in detecting abnormality in protection and accordingly taking

corrective action. During over-voltage tripping the PMU helps in giving operator the information that whether the

tripping is due to fault or not. With low value of Zero sequence voltage and uniform dip in three phase voltage

during the tripping with no sudden dip in any of the phases indicate that the tripping was not due to fault.

5.1.3.3. Tripping of 400 kV Balipara-Ranganadi circuit-2

Date and Time : 02-11-2013 16:46 Hrs

Data Used for Event Analysis : PMU data from Bongaigaon ; SOE available at NERLDC ; SCADA data ;

Disturbance Recorder data from Balipara

Event Description: One circuit of 400 kV Balipara – Ranganadi D/C was kept in open condition due to high voltage

problem at Ranganadi. NER Demand met was 1675 MW prior to the event. At 16:09 Hrs, Unit-1 of Ranganadi was

synchronized when voltage of 400 kV Balipara was 406 kV. Following this, at 16:15 Hrs, Unit-2 of Ranganadi was

synchronized when voltage of 400 kV Balipara was 404 kV. At 16:34 Hrs, charging instruction for 400 kV Balipara

– Ranganadi I was issued from NERLDC, when voltage at 400 kV Balipara was 402 kV. At 16:44 Hrs, Unit-3 of

Ranganadi got synchronized to NER Grid. At that time 400 kV Balipara bus voltage was around 399 kV. At 16:46:09:267

Hrs, 400 kV Balipara – Ranganadi II tripped on Transient earth fault protection which was followed by tripping of all

units of Ranganadi HEP.

Analysis

Figure 5-55: Bongaigaon positive sequence voltage and positive sequence current of 400 kV Bongaigaon-Balipara-I & II Ckts

DECEMBER - 2013 POSOCO49

Synchrophasors - Initiative in India

From the PMU data, it can be seen that possible fault got cleared in around 2.3 seconds. The positive sequence

voltage shows that voltage dip is very low which was indicating towards a high resistive nature fault (Figure 5-55).

But the current signature did not suggest any fault in system. After further investigation it was found that there

was no physical fault in the system. It was instead a snag in CT core used as input to Main 2 relay on 400 kV

Balipara – Ranganadi II line that caused disproportionate current flow from CT secondary and pickup of residual

earth fault element of numerical distance protection relay.

This relay has IDMT characteristic and picks-up only after imbalance current exceeds 200 A. The disproportionate

current flow was sensed as similar to High-impedance earth fault and hence TEF operated. It was observed from DR

prints from relay that there was imbalance in currents (>200 A) among 3 phases of 400 kV Balipara – Ranganadi II (R

phase – 186 A, Y and B phase – 392 A). However, the secondary input as sensed in other relay was only 65 A, as it

was from a different core of the CT and so it did not operate.

It is clear that this event is very unique in nature where Main-II relay at Balipara end picked-up due to imbalance in CT

secondary input and not due to physical fault. The same was later informed to the sub-station for correction.

So it can be observed how PMU helped in determining the instrument failure and taking fast corrective action. There

have been several cases where tripping on overvoltage occurred even the voltage was within threshold. In those cases

PMU helped in finding such issues and CVTs were replaced. Also various cases of non auto reclosure action have

been corrected during single phase fault.

5.1.4. High Impedance Fault

High impedance faults (HIF) represent one of the most difficult protection problems in power system. By definition

high impedance fault does not draw enough current to cause the conventional protective device to operate as it fails to

establish a permanent return path. High impedance faults produce current levels in the 0 to 50 ampere range. In

general they involve either small change in current (Resulting impedance is high) or small change in voltage while

large change in current (impedance value is still high as voltage has not changed significantly). This section describes

various case studies involving such faults.

5.1.4.1. Multiple tripping of 400 kV lines, ICT’s and generating units in southern grid.

Date and Time : 29-03-2013 13:48 hrs

Data Used for Event Analysis : Somanhalli PMU, DR,EL

Overview: This incident led to tripping of fifteen 400 kV lines, ten Inter connecting transformers and two generating

units in southern region which started with high resistance fault. Tripping of 400 kV lines weakend the transmission

system and tripping of ICTs had led to load loss and over voltage condition in certain area of southern grid. The

affected area is shown in the Figure 5-55 schematic diagram.

Event Description: Fault had occurred in Srisailam hydro station which is a Gas insulated station. The high resistance

fault could not be detected by distance protection relays. Due to absence of backup earth fault protection at remote

ends the fault could not be cleared by line protection and this led to operation of ICT back up protection at few grid

stations. During this event few mis-operation of protections were also observed which had led to tripping of Units at

Vijayawada & Kothagudam Thermal station. The fault was cleared when 400 kV Kurnool-Srisailam line got tripped.

50 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 5-56: Connectivity diagram of Srisailam Hydro power station and its Interconnection

Analysis: The df/dt plots, voltage plots for drop at respective buses, zero & negative sequence current data plots

were observed for determining the possible nearest location of fault. From Figure 5-57, it can be observed that

highest df/dt was recorded at 400 kV Vijaywada. It can be inferred from Figure 5-58 and 5-59 that the fault

persisted for 21 seconds.

In this event it was found that distance protection zone-2/zone-3 did not sense the gradually developing a high

resistance fault. Further the fault could not be cleared due to non-availability of directional earth fault protection

provided in 400 kV lines for sensing of any un-cleared faults beyond reach of zone-3 of distance relays. The

backup over current and earth fault protection of interconnecting transformers (ICT) at different grid sub-stations

sensed the fault and started tripping ICTs. The tripping of ICTs in turn led to Overvoltage condition in grid. This led

to tripping of 400kV lines at 400 kV Hyderabad and 400 kV Srisailam on over voltage protection. The 400 kV

Srisailam – Kurnool line tripped from both ends due to over voltage. This finally stopped the fault feed from other

buses in the grid and finally led to clearance of fault.

Figure 5-57: Rate of change of frequency observed from various PMUs during high impedance fault

DECEMBER - 2013 POSOCO51

Synchrophasors - Initiative in India

Figure 5-58: 400 kV Vijayawada bus voltage during high impedance fault

Figure 5-59: Negative and zero sequence current of 400 kV Vijayawada-VTPS-I from PMU during high impedance fault

52 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Table 5-5: Sequence of events during high impedance fault in SR grid

From sequence of events shown in Table 5-5, it was observed that fault got cleared after lines connected to Srisailam

opened. This increased the possibility of occurrence of fault at Srisailam bus. Srisailam Hydro station had also informed

occurrence of fault in the 400 kV Kurnool section inside the Gas Insulated Substation at srisailam.

The remedial actions taken to avoid re-occurrence of the event was enabling of directional earth fault protection for all 400 kV

lines, provision of sensitive bus bar protection at Gas Insulated Substation (GIS) to detect any slow developing and high

resistance fault in GIS bus. Incorrect relay settings and mis-operation of relay which had led to tripping of Units at two

generating stations were reviewed and rectified.

This case study shows that how PMU helps in analyzing the slowly developing high resistance fault was observed

from the voltage, negative and zero sequence current plots. The rate of change of frequency plot helped to identify the

possible nearest location of fault.

5.1.4.2. Tripping at Narora Atomic Power Station

Date and Time : 09-04-2013 13:32 hrs

Data Used for Event Analysis : Agra, Dadri, Ballia, Hissar, Merrut PMU, DR,EL

Overview: This case study is to show how synchrophasor has helped in analyzing the event which involved tripping

of nuclear power plant due to high impedance fault in the system. This has helped in sensitizing the issue that how a

small event can result into the cascaded tripping due to lack of electrical clearance.

DECEMBER - 2013 POSOCO53

Synchrophasors - Initiative in India

Event Description: All the evacuating lines from NAPS tripped resulting into poisoning out of nuclear station of

Narora. Total generation loss during the event was around 335 MW. Prior to incident 220 kV NAPS- Simbholi line

was under shut down at NAPS end and all other power evacuation lines were in service. The sequence of events

which led to tripping of NAPS Unit-1 & 2 at 13:32 hours on 9th April 2013 is shown in Table 5-6

Table 5-6: Sequence of Event during tripping of NAPS units

Analysis: It can be observed from the PMU Voltage and Current plots in Figure 5-60 and Figure 5-61 respectively

that this is a case of high impedance fault. From the patrolling of site it was found that due to lack of electrical

clearance tree branches were in contact with conductor resulting in flashover creating a high impedance fault.

The fault persisted for longer duration of time. As these faults were not sensed by the Zone 1/Zone 2 protection

from both the ends resulted in circulation of negative phase sequence (NPS) current in 6.6 KV auxiliary equipment

leading to tripping of motors and in turn outage of units. As observed when the voltage dip increased, lines tripped

as the fault was cleared when it entered in zone 1 protection. It can be observed from the SOE that one of the lines

tripped on zone 5 which is reverse protection operation after 2.5 second.

Figure 5-60: PMU Plot of phase voltages of different station during 13:24 – 13:33 Hrs on 09-04-2013

54 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 5-61: PMU Plot of phase voltages of different station during the fault at 13:26 Hrs

5.1.4.3. Tripping Omkareshwar HPS

Date and Time : 02-09-2013 13:47 and 14:06 Hrs

Data Used for Event Analysis : Itarsi,Satna,Dehgam,Raipur,Bhadrawati,Sugen PMU, DR/EL/SOE

Overview: This case study is unique in the sense that it involves the high impedance arcing type fault, delayed fault

clearance, oscillation observed in the grid and finally tripping of all the running unit of a generating plant. Here the fault

characteristic is different from previous studied cases as voltage drop is insignificant while current was gradually

increasing.

Event Description: All the eight units at Omkareshwar HPS were running prior to the event. At 13:47 Hrs, R phase fault

appeared in the 220 kV Itarsi-Barwaha ckt. But the line did not trip immediately as the fault was of resistive nature. This

line tripped when the fault also appeared in Y phase after 1 second from Barwaha and Itarsi end in Zone 1.During this

fault, 220 kV Omkareshwar-Barwaha which sensed the fault and tripped the line in earth fault protection from OSP

end. This line remained out and Omkareshwar was left with 220 kV Omkareshwar-Chhegaon and 220 kV Omkareshwar-

Nimrani circuit for 390 MW power evacuation. Figure 5-62 shows the affected portion of the grid.

Figure 5-62: Schematic Diagram of Omkareshwar and Near By area

DECEMBER - 2013 POSOCO55

Synchrophasors - Initiative in India

After this first trial charging attempt of 220 kV Itarsi-Barwaha line from Barwaha end at 14:06 Hrs was taken and

similar phenomenon was observed again. This time 220 kV Omkareshwar-Nimrani Line (tapped at Barwaha)

tripped from Omkareshwar on earth fault trip as the fault was being observed by the Omkareshwar end relay. After

tripping of this line whole 390 MW power was being evacuated by the 220 kV Omkareshwar-Chhegaon line. At

14:07 Hrs, 220 kV Omkareshwar- Chhegaon line tripped from Cheggaon end. With this all outgoing feeder from

Omkareshwar were out leading to tripping of all eight units on over frequency.

Analysis: From Figure 5-63 it can be observed that during the fault voltage of faulty R phase of Itarsi PMU dipped

initially by 4 kV only. After 1 second duration it dipped again by 4 kV along with 6 kV dip in Y phase. The similar

characteristic was observed in the DR of 220 kV Barwaha–Itarsi from Barwaha end indicating similar characteristic

as observed in PMU voltage displaced in Figure 5-64. The current as observed from DR was high but due to small

dip in voltage the fault impedance did not enter the zone 1 of the relay. Later as the fault appeared in Y phase also,

then the line tripped on phase to phase indication in zone 1 and the same is shown at Figure 5-65. The sub-

stations were informed for revising the resistive reach of zone 1. During this only 220 kV OSP-Barwaha line tripped

from OSP after sensing the fault as transient earth fault. It can also be observed from the Figure 5-64 that the

voltage drop during fault is higher at a location which is closer to the fault and decreases as we move away from

the fault.

Figure 5-63: Phase Voltages from Itarsi PMU during the fault at 13:47 Hrs

Figure 5-64: Positive sequence voltage from various PMUs during the fault at 13:47 Hrs

56 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 5-65: DR of 220 kV Itarsi - Barwaha from Barwaha end which shows that fault was in R phase initially

Figure 5-66: Continuation of Figure 5-65 DR indicating the phase to phase fault appeared after 1 sec. resulting in tripping of linein zone 1

Figure 5-67: Frequency observed at various nodes during the fault on 220 kV Itarsi-Barwaha at 13:47 Hrs

DECEMBER - 2013 POSOCO57

Synchrophasors - Initiative in India

Figure 5-68: Phase voltages from Itarsi PMU during the fault at 14:06 Hrs and tripping of Units on over frequency

Figure 5-69: Positive sequence voltages from various PMUs during the fault at 14:06 Hrs and tripping of Units on over frequency

Figure 5-70: DR of 220 kV Itarsi - Barwaha from Barwaha end while charging of line from Barwaha which shows

that fault started in R phase initially

58 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 5-71: Continuation of Figure 5-70 DR indicating the phase to phase fault appeared after 1 sec. resulting in tripping of line in zone 1

Figure 5-72: Frequency observed by various PMUs during the fault on 220 kV Itarsi Barwaha at 14:06 Hrs

While trial charging this line from Barwaha end, again the similar phenomenon was observed. From Figure 5-68 it

can be observed that the voltage of Faulty R phase of Itarsi PMU dipped initially by 3 kV only. After 1 second

duration it dipped again by 3 kV along with 5 kV dip in Y phase. The similar characteristic was observed in the DR

of 220 kV Barwaha–Itarsi from Barwaha end shown in Figure 5-70. The current as observed from DR was high but

due to small dip in voltage the fault impedance did not enter the zone 1 of the relay. Later as the fault appeared in

Y phase also then the line tripped on Phase to phase indication in zone 1 displayed in Figure 5-71. At the same

time 220 kV OSP-Nimrani line which was sensing the fault tripped on Transient earth fault protection operation.

With this the Omkareshwar hydel power plant was left with only one 220 kV feeder which got overloaded and

DECEMBER - 2013 POSOCO59

Synchrophasors - Initiative in India

oscillations were observed in the WR grid. (Figure 5-72) The resistive reach in zone- 1 for this line was suggested

for revision to avoid re-occurrence of the problem.

5.1.4.4. Disturbance in Karnataka system due to Resistive nature of fault

Date and Time : 18-09-2013 15:59 Hrs

Data Used for Event Analysis : Narendra PMU, KPTCL report

Overview: This case study involves resistive fault which persisted for 5 second before getting cleared.

Event Description: Tripping of transmission lines and generation loss had occurred in Karnataka’s 220 kV system.

The triggering incident was reported to be fault in 220 kV Kemar- Varahi line-3. 220 kV Kemar-Varahi line-3, 220 kV

UPCL-Kemar line-1 & 2, 400kV Hassan-UPCL line-1 & 2, running unit-2 at Udipi power station tripped during the

incident. The generation loss at Udupi power station was 350 MW. The network connectivity of affected portion is

shown in Figure 5-73.

Figure 5-73: Connectivity Diagram of Udipi Power Station

Analysis: From PMU voltage plot in Figure 5-74, it can be observed that a high resistance fault had star ted at

15:59:50.400 hrs. After nearly 5 seconds, dip in voltages of all the phases was observed i.e. at 15:59:55.800 hrs.

Figure 5-74: 400 kV Narendra bus voltage

60 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

There was snapping of Y-Phase jumper of 220 kV Kemar-Varahi line-3. 220 kV Kemar-Varahi line-3 tripped at

Varahi end on operation of distance protection, zone-2. It tripped in zone-2 time as there is no provision of carrier

aided protection. The line tripped at Kemar end on operation of directional earth fault relay. At UPCL 220 kV UPCL-

Kemar line-2 tripped on operation of directional earth fault relay. The Unit 2 at Udupi Power station tripped on

operation of back up earth fault protection (51N) of generator transformer. 220 kV UPCL-Kemar line-2 had sensed

the fault and had tripped on earth fault protection. 400 kV Hassan-UPCL line-2 sensed fault in zone-1 and auto

reclosed from Hassan end. This line tripped 400 ms after auto reclose due to Zone-2 operation. 400 kV Hassan-

UPCL line-1 tripped on operation of Zone-2 protection. With this the fault was isolated from the system.

Various remedial actions have been performed based on the combined analysis of PMU data, SCADA data, DR/EL and

SOE which include:

1. Running Unit-2 tripped at Udupi power station on operation of back up earth fault protection of Generator

transformer. It was observed that the relay was having definite time instead of IDMT characteristics which has

been rectified.

2. 400 kV Hassan-UPCL line-1 & 2 tripped from Hassan end on operation of distance protection Zone-1 and

Zone-2 protections respectively for a fault in 220 kV Kemar-Varahi line-3. The resistive reach of relay was

reduced to prevent over-reach.

3. Review of protection co-ordination will be done at UPCL as 220 kV lines from UPCL tripped for a fault in 220

kV Kemar-Varahi line-3

This section explains how PMU has helped in identification of High Impedance fault analysis in the system. It also

helped in finding the duration of the faults which persist for larger duration. Earlier such analysis used to take a

significant amount of time and it was difficult to deduce the exact SOE. With PMU such analysis becomes very fast

facilitating corrective actions to be taken in minimum possible time.

5.1.5. Detection of faults cleared by back up protections

5.1.5.1. Tripping of all three 315 MVA ICTs at Biharsharif Substation

Date and Time : 25-06-2013 at 12:13 hrs

Data Used for Event Analysis : Farakka PMU

Overview:

This case study presents the tripping analysis of all three 315MVA ICTs at Bihar sharif S/S.

Event description: At 12:13 hrs, 220 kV Fatuah-Patna (PG) ckt tripped on Y phase to ground fault at a distance of

9.6 km from Patna (PG) end. Also, all the three 315 MVA, 400/220 kV ICTs at Bihar Sharif (PG) tripped on operation

of back up HV side Over Current protection. Around 240 MW of load loss occurred in areas adjoining Biharsharif

due to outage of all 220 kV & 132 kV lines from Bihar Sharif sub-station. The schematic diagram of Biharsharif sub-

station is shown in Figure 5-75.

DECEMBER - 2013 POSOCO61

Synchrophasors - Initiative in India

Figure 5-75: SLD of 400/220 kV Biharsharif S/s

Analysis: The sequence of events was initiated due to Y phase to ground fault (as reported) in 220 kV Patna-

Fatuha S/C (Zone-II from Fatuah; 9.6 km from Patna). However, the single phase to ground fault can be corroborated

only from sequence plots. From the PMU plot of 3-phase Farakka voltages (Figure 5-76) it can be observed that

the highest initial voltage dip was observed in Y-phase indicating the presence of Y phase fault.

Figure 5-76: 400 kV Farakka Bus voltage

The fault was isolated properly at Patna (PG) end, but there was a delayed clearance/non-clearance at Fatuah

end. It is also evident that the fault was not cleared from Biharsharif (BSEB) end. Consequently, HV side over-

current protection got triggered for all the three 400/220 kV ICTs at Biharsharif (PG) end which isolated the fault.

The fault persistence time of 700 to 750 ms was observed in DR of Biharsharif ICT II shown in Figure 5-77 which

tripped at the end. It can inferred that Biharsharif (BSEB) end of 220kV Biharsharif-Fatuha D/C did not clear the

fault from Biharsharif(BSEB) end which is possibly due to the fact that fault was in Zone-III from Biharsharif(BSEB)

62 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

end while the ICTs isolated the fault in about 700ms to 750 ms. However, Distance protection relays at Biharsharif

(BSEB) end may have picked up(Zone-III timer started) which needs to be confirmed.From PMU plots of voltage

and current shown in Figure 5-76 and Figure 5-78, fault clearance time appears to be of the order of 680 ms to 760

ms. Persistence of the fault for such a high duration confirms delayed operation/non-operation of Distance protection

at Fatuah (BSEB) end along with non-clearance of the fault from Biharsharif end.

Figure 5-77: DR of HV side of 315 MVA ICT-II at Biharsharif overcurrent relay

Figure 5-78: Line Current of 400 kV Farakka-Durgapur-I from Farakka PMU

DECEMBER - 2013 POSOCO63

Synchrophasors - Initiative in India

From the DR outputs as shown in Figure 5-77, it was observed that ICT-II took the longest time to trip i.e. around

700 ms. Hence, considering a further delay of 2 cycles associated with complete isolation(opening of main & tie

bays), from the DR outputs it can be concluded that the fault was cleared in about 750 ms. Hence the fault

clearance from DR plots corroborates that obtained from PMU plots.Frequency plot as shown in figure 5-79 starts

increasing after the tripping which indicates that load was lost due to ICT tripping.

Figure 5-79: Frequency observed from Farakka PMU during ICT tripping at Bihar Sharif

On the basis of case studies discussed and experience gained over the fault analysis and detection, the section

can be summarized in various aspects of case studies like location of fault, type of fault, clearing time and

characterization.

Fault location: Any fault occurring in the system will have its effect at all the locations and the effect will decrease with

distance from the location of the fault. Bus frequencies will be different at different location following a disturbance

however this will happen only during the first stage of dynamics lasting only a few seconds or milliseconds and after

that the frequency will be uniform in the system. Furthermore, the differences between individual bus frequencies will

not be a function of local power imbalance but they will be a function of the electrical distance from the disturbance.

During transient state the frequency of the bus which is nearest to the fault will have more variation compared to other

locations. Similarly the rate of change of frequency (ROCOF) will also be following the same trend. The Frequency

deviation and ROCOF near to fault will be quite high during the initial stages while low for other locations. [B46]

Classification of Fault: Based on the observation from various case studies in this section, characteristic for

various type of faults have been identified based on user experience. This will help in the event detection formulation

and will speed up the event analysis.

A. Single Phase to Ground Fault (L-G fault):

1. Maximum Voltage dip in faulty Phase can be observed in the nearby PMU data.

2. Increase in current of faulty phase is observed in the nearby PMU. (Observed in most of the

cases)

3. Zero sequence voltage will be high during the fault.

64 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

4. In one of the healthy phases,current increases while in other it decreases as observed from

nearest PMU. (Observed in most of the cases)

B. Phase to Phase Fault (L-L fault)

1. Maximum Voltage dips are observed in faulty phases in PMU data.

2. Currents in the faulty phases will be almost equal and opposite to each other. (Based on user

experience, may vary)

3. The current in the healthy phase will be almost zero.

4. Zero sequence voltage and current will not be significant.

C. Double Phase to Ground Fault (L-L-G fault)

1. Maximum Voltage dips are observed in faulty phases in PMU data.

2. Zero sequence voltage and current will be significant in such fault.

D. Three phase fault (Symmetrical fault)

1. All the three phase voltages will have dip which is near to zero.

2. The fault current will be very high in all the three phases.

E. Resistive Nature of Fault

1. Phase voltages and positive sequence voltage will have small dip as observed in PMU data will

be low( 3-6 kV)

2. The zero sequence and negative sequence current will also be low. They will gradually rise to

higher values till the fault is cleared.

3. In some cases, even the current was high but voltage dip may be very low which depends on the type

of path and its varying nature with arcing.

Fault Recovery Time: PMU data helps in knowing about the total fault recovery time. The minimum value during fault

indicates the time after which fault start recovering due to tripping of source feeding the fault.It helps user in knowing

about how much time the fault was present in the system.

The limitation in determining the actual fault clearing time using the synchrophasor measurement can be explained in

terms of the philosophy adopted by PSS/E [B47] in respect of Dynamic Voltage violations for a typical fault which is

reproduced below:

“The voltage recovery may have primary voltage criteria (i.e., voltage to recover above threshold V1 faster than t

1

seconds after fault clearing) and secondary voltage criteria (i.e., voltage to recover above threshold V2 faster than t

2

seconds after fault clearing). The voltage dip check will be based on voltage threshold V3 and time t

3 (seconds). Once

voltage has recovered above threshold V3, it should not dip below that value for longer than t

3.”

So, Let us consider

DECEMBER - 2013 POSOCO65

Synchrophasors - Initiative in India

t- :

at the time of fault,

t0: after clearing fault

If we consider the fault is sensed at Point A and cleared at Point B, then Fault clearance time would be B-A ,Fault

clearing time may be computed as :

1. Case 1: B-A=(t0-t

-)+t

1+t

2

2. Case 2: B-A=(t0-t

-)+t

1

3. Case 3: B-A=(t0-t

-)

Here question may arise which case is better for proper fault clearance time calculation? If correlation is done between

the voltage dip and rise phenomenon observed in PMUs:

1. Just after the fault, voltage dip is having negative (- ve) slope against sudden dip.

2. For time (t0-t

-), PMUs capture this duration moderately in sustained faults.

3. After clearing fault, time t1, is a straight line with positive slope, it also different for different types of

faults (balanced and unbalanced faults.)

4. Time t2, most of the time is neglected in computation.

Normally, Case 2 methodology is adopted to calculate the fault clearing time. As we have 40ms (at 25 frames/

second) interval measurements on interpolated plots, it is difficult to calculate fault clearance time for less than

100 ms with three intervals. Factors effecting errors includes inherent delays associated with PMU measurement,

location of PMU and phasor (V, I, f,angle) used and unbalanced operating conditions between two successive

Source: Siemens PTI, PSS / E user Manual

66 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

measurements, however, it would be appropriate to consider computed time moderately for faults cleared say for

more than 150-200 ms or more.

So there is need to maintain number of case studies where PMU data and DR data has been used for fault clearing

time measurement, till that time, PMU based fault clearance time calculation can be used only for interpretation

of whether fault is sustained or cleared immediately; of course other A/R operation can be validated. Table 5-7

shows the fault clearance time using the DR and PMU data.

Table 5-7: Summary of PMU Typical Delays and typical ranges [B42]

In such direction, an attempt is made to baseline fault clearance time using the DR and PMU data, details are

given in Table 5-8.

Table 5-8: Fault clearance time based on DR and PMU

As observed from the Table 5.8 that fault clearing time observed from DR and PMU shows that , for a 100 ms fault

clearance time the PMU shows the recovery in voltage/current after either 80 ms or 120 ms . This is completely valid

till the fault is on transmission line , as the source feeding to fault will be both ends of the line.

While in case of a fault which involves multiple elements (like bus fault) voltage recovery starts even with the first

element tripping which is feeding the fault. So in such cases fault recovery time should be used after which last

recovery of voltage has occurred.

Sl.No Cause of Delay Typical Range of Delay

1 Sampling window (delay ½ of window) 17 ms to100 ms

2 Measurement filtering 8 ms to 100 ms

3 PMU processing 0.005 ms to 30 ms

4 PDC processing & alignment 2 ms to 2+ s

5 Serializing output 0.05 ms to 20 ms

6 Communication system I/O 0.05 ms to 30 ms

7 Communication distance 3.4 μs/km to 6 μs/km

8 Communication system buffering and error correction 0.05 ms to 8 s

9 Application input 0.05 ms to 5 ms

Fault clearing Time taken for Maximum Time taken for full

Event Time from DR voltage dip after which recovery of voltage

(millisecond) voltage starts recovering from PMU Data (ms)

from PMU Data (ms)

Case study 5.1.2.2 (L-G) 82 120 160

Case study 5.1.2.2 (LL-G) 79 80 120

Case study 5.1.1.1 (L-G) 75 80 120

Case study 5.1.1.1 (A/R) 84 80 120

Case study 5.1.1.3 (LLL) 167 80 240

Case study 5.1.1.2 (LL) 147 40 200

DECEMBER - 2013 POSOCO67

Synchrophasors - Initiative in India

So to know the operational time of protection: During line tripping if both ends relay operated in 100 ms then PMU

should show us 80 ms-120 ms (for sampling rate of 25 sample/sec). While beyond this we need to check for the

relay operation. In case of fault with multiple source feed, the last recovery point in voltage/current could be taken

as recovery time while the first recovery assures that protection action has initiated.

During the last 8 months i.e. (April’13-Nov’13) the total GD (as per CEA grid standard 2010) analyzed in different

region with the help of synchrophasor data are listed in table 5-9.

Table 5-9: Cases analyzed using Synchrophasor (April’13 – Nov’13)

It can be observed that how extensively the PMUs were used in analyzing various events in the electrical grid and

how WAMS helped in resolving various issues observed in the system in an accelerated manner.

5.2. Low Frequency Oscillation

Power system is a typical case of a large nonlinear system with lots of oscillation modes. These include electro-

mechanical oscillations, Control modes and Sub Synchronous Resonance (SSR) etc.In this paper only the electro-

mechanical oscillations have been considered. The root cause of electrical power oscillations is the unbalance

between power demand and available power at a particular operating point. The change in the electromechanical

torque of a synchronous machine following a perturbation can be split into two components as shown in eq. (1).

The component Ks .Δδ is called the synchronizing torque T

s and determines the torque change in phase with rotor

angle perturbation Δδ. The component Kd.Δω is called damping torque T

d and determines the torque change in

phase with speed variation. Ks and K

d are called synchronizing torque coefficient and damping torque coefficient

respectively. Rotor angle stability depends on both components of torque. Lack of synchronizing torque causes

non-oscillatory instability or monotonic instability in the system and lack of damping torque result in oscillatory

instability in the system.

Rotor angle stability is of two types which are small signal stability (small disturbance in the power system) and

transient stability (large disturbance in the power system). Small signal stability is the ability of power system to

be in steady state after a small disturbance. The instability due to this is mainly attributed to insufficient damping

torque. While transient stability is associated with the ability of power system to maintain synchronism when

subjected to large disturbances like line fault, bus fault, generator outage etc. The instability arising due to this is

result of insufficient synchronizing torque.

Small signal instability is due to insufficient damping torque leading to low frequency electromechanical oscillations

in system which is oscillatory in nature. If there are N generators in a system, then total number of such LFO

modes would be N-1. During Low Frequency oscillations, mechanical kinetic energy is exchanged between

synchronous generators of the inter-connected system through tie lines. Most of these oscillatory modes in

normal power system state are well damped. However, they get excited during any small disturbance in the

ΔTe = K

s .Δδ + K

d.Δω = T

s + T

d ..................................... (1)

NR NER WR SR ER

75 24 36 15 88

68 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

system and lead to oscillation in power system parameters like rotor velocity, rotor angle, voltage, currents power

flow etc. Due to oscillation in parameters, protection equipment may undesirably operate leading to cascade

tripping in power system. Therefore, it is necessary to detect such modes and initiate corrective actions to ensure

system reliability and security. Among these parameters the rotor velocity of the generators and the power flow in

the network are most important. The rotor velocity variation causes fatigue to the mechanical parts of turbine-

generator system. The power flow oscillations may amount to the entire rating of a power line, when they are

superimposed on the stationary line flow and would limit the transfer capability by requiring increased safety

margins.

The low frequency oscillation classification is in general dependent on the power system for which it has to be

used based on Eigenvalue analysis based on the system model. This helps in monitoring the variables which will

be participating globally or alone. The participation factor of each variable in one of the oscillatory modes helps in

deciding the classification of modes. In general low frequency oscillation can be basically of four different types

as given below:

1. Inter-Area Mode (0.1 Hz-0.7 Hz): Inter-area modes are associated with swinging of a group of generators

in one part of the system with group of generators in other parts due to weak interconnecting lines

between two power systems. There are also referred as global mode.

2. Local mode (0.7 Hz -2.5 Hz): It is either due to oscillation of one generator against the remaining of the

system (very similar to the one-machine infinite-bus system) or oscillation of one generator against

another, both located close to each other (two generators in the same power plant).

3. Control Mode: These are in system due to poor design of controllers of AVR, HVDC, SVC, AGC etc. These

are also referred as regulating mode.

4. Torsional Mode (10 Hz-40 Hz): These modes are associated with the turbine-generator shaft system and

associated rotational components.

The ranges define may overlap on other depending of power system but in general this is accepted in power

system fraternity.

5.2.1. Detection of Low Frequency Oscillations using Synchrophasor Measurements

With the current SCADA system, power system operators are not able to identify LFOs in the system due to inherent

slow updating rates i.e. once in every 4 -15 Seconds (analog values). The oscillation at generator level i.e. intra-plant

or local mode was assumed as it appeared as hunting in the generators while the inter-area modes were not visible to

system operators by any means apart from simulation studies. The SCADA data reporting rate is comparatively slow

which are not useful in detecting the oscillation or the changes going in the system in sub-seconds.

With advent in the technology, faster data processing and time synchronized phasor measurements availability at

a reporting rate of 25-50 frames/second from Phasor measurement unit (PMU), now operator is able to visualize

such oscillations in the system. Tools and techniques are also in development to detect the source of such

oscillation and to analyze them in real time and take corrective action before they create fur ther complexities in

the system. The detection of LFOs and their history is of great help in planning and implementation of damping

DECEMBER - 2013 POSOCO69

Synchrophasors - Initiative in India

controllers of HVDC, TCSC etc. At present PMUs have enabled the operator to visualize such LFOs whose source

can be tracked with placement of optimum number of PMUs giving complete observability of system.

In this section various case study on low frequency oscillations is being discussed in detail. Along with that a

statistical table is included at the end of the section which summarizes these oscillations and their characteristic.

5.2.2. Analysis of Low frequency oscillation

Low frequency oscillation detection as a stability aspect comes under the Small signal stability. Basically there are two

methods to analyze such stability which are linear analysis of system using eigenvalue approach on system model

and measurement based analysis. There are various software available for small signal stability on power system

model. Analysis based on Eigenvalue Analysis technique is carried out through linearization of the nonlinear differential

equations that represent the power system around an operating point. This approach is very comprehensive and is

based on complete modeling of the Power System elements and gives all the modes in the system.

While the measurement based techniques (Response based) is based on spectral analysis of measured data from the

field directly gives the low frequency oscillation modes existing in the system. This is fur ther classified as frequency

domain and time domain analysis on the measured data. The frequency domain techniques have an advantage of

indicating the margin of stability and details of damping and its measure. The frequency domain techniques are based

on eigenvalues of the system for determination of the margin of stability. The time domain techniques determine

whether the system is stable or unstable, but not the degree of stability. Therefore, for power system planners and

system operators dealing with pre-dispatch issues (before real time operation), knowledge of the degree of stability,

possible low frequency modes and the extent of damping of each of these modes is required so that the operators can

prepare operational and contingency plans. There are several methods out of which Fast Fourier Transform, Matrix

Pencil method, Wavelet Transform method, Henkel’s Total Least Square (HTLS), ERA method are prominent [B

17].

In linear analysis methods, mode shape is very important as it gives the relative activity of state variables in each

mode. They are obtained from the right eigenvectors and the larger the magnitude of the element, more is the

observabilty of state variable. The generator having the largest magnitude of mode shape has the largest activity in the

mode of interest. The mode shape indicates which generators are active and how they swing against each other.

Moreover, mode shapes also helpto determine the optimum location for installing power oscillation dampers(PODs).

It is expected that by installing a PSS at the generator having the largest magnitude in the modeshape (at the mode of

interest), a more signicant damping than installingat the other generators can be established.

5.2.3. Inter-Area Oscillation Observed in the Grid

5.2.3.1. 0.5 Hz Oscillation in the NEW Grid due to Tripping at Buddhipadar, Sterlite and IBTPS

Date and Time : 13-04-13 22:02 Hrs

Data Used for Event Analysis : Raipur and Sugen PMU, DR and EL of the Sterlite, Korba (E) and

Buddhipadar S/s

Overview: Low frequency oscillation with mode frequency of 0.5 Hz (0.45 Hz-0.55 Hz) was observed during the

disturbance at Buddhipadar, Sterlite and IBTPS. .

70 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Event Description: Weather was stormy with heavy rain in Chhattisgarh & Orissa states in the N-E-W grid. Figure

5-80 shows the system that was affected during this incident. In the beginning 220 kV Buddhipadar-Tarkera line 1

tripped on fault followed by tripping of 220 kV Buddhipadar-Tarkera line 2 on over current protection. This led to the

par t of Orissa system comprising generation of IBTPS power station (2*230 MW), 600 MW unit of Sterlite,

Vedanta CPP (9*135 MW) and Bhusan steel CPP (2*120 MW) getting connected to Western grid. After this at

22:01:49 Hrs 220 kV Raigarh –Buddhipadar circuit tripped. This has resulted in overloading of 220 kV Korba(E) –

Buddhipadar 2 & 3 circuits. At 22:02:38 Hrs oscillation started in the system which was observed at various

locations in the NEW grid. This may be due to the connection of an islanded part of system (Generation Rich

Island) with the rest of the system through only two lines i.e. 220 kV Buddhipadar-Korba (E) 2 & 3. At 22:04:39 Hrs

220 kV Korba (E)-Buddhipadar 2 & 3 tripped resulting in complete islanding of Buddhipadar, IBTPS and Sterlite Area

which further collapsed. The event is shown with the help of PMU data from Raipur in Figure 5-81.

Figure 5-80: Schematic diagram of the affected portion.(Islanded portion is shown with dotted lines)

Figure 5-81: Frequency and ROCOF observed during the Incidence from Raipur PMU. The circle marked

in plot indicate the oscillations in the grid

DECEMBER - 2013 POSOCO71

Synchrophasors - Initiative in India

Analysis: Severe oscillations were observed in all the parameters from the PMU at Raipur, Sugen, Bassi, Agra and

Karcham for 60 seconds. Frequency plot of all the five locations as described above is shown in Figure 5-82. These

oscillations were analyzed using various nonlinear techniques to find the various modes of oscillation. It was found

that 0.51 Hz mode was dominant present in system at all the location as shown by Figure 5-83. The mode shape can

be described as the Machines near Sugen oscillated in 90o phase shift with Machines near Raipur. While NR

machines near Agra, Bassi oscillated with an angle 42o while Karcham wangtoo at 20o w.r.t Raipur.

Figure 5-82: Oscillation in Frequency from various PMUs

in the NEW Grid

Figure 5-83: Mode Shape of 0.53 Hz

Table 5-10: Low frequency oscillation observed during tripping at Budhipadar, sterlite and IBTPS

Cause: Prior to oscillation WR-ER inter-regional lines have tripped and generators-load (later formed island and

collapsed) at the boundary of WR-ER got disconnected from ER and were connected to WR only through only two

220 kV Lines (Korba (E) - Buddhipadar 2 & 3). The overloading of these lines and their inability to transfer MVAR

may have resulted in limit hitting of AVR of the generators in the weakly connected system resulting in Inter-area

oscillation.

5.2.3.2. 0.5 Hz Oscillation in the NEW Grid due to DSTPS (DVC) Unit forced outage.

Date and Time : 23-09-13 14:34 Hrs

Data Used for Event Analysis : PMU at Farakka, Talcher ,Sugen, APL Mundra, Karcham Wangtoo, Dadri

Overview: Low frequency oscillation with mode frequency of 0.49 Hz (0.45-0.55 Hz) was observed in the NEW

grid during the forced outage of DSTPS Unit 2.

Event Description: On 23.09.13, at 14:34 hrs, while taking DSTPS Unit-I (500 MW) out of service due to low

demand, low frequency oscillations were observed in PMUs of NEW Grid. The Unit was generating approx. 310

MW at the time of incident.

Method Frequency Damping Ratio (%) Energy

Matrix Pencil 0.5137 0.5394 0.2640

ERA 0.5137 0.5451 0.2684

HTLS 0.5138 0.5346 0.2653

72 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Analysis: The PMU plot of frequency in Figure 5-84 shows that oscillation persisted for 110 seconds. Since

oscillations persisted for more than a minute, so these were also captured in the SCADA Data from DSTPS as

shown in Figure 5-85. Initially it was found that oscillation is of 0.49 Hz which is Inter-Area in nature from the OMS

engine. So the data from various NEW Grid PMUs were analyzed. Figure 5-86 shows the oscillation observed from

different region’s PMUs. While Figure 5-87 shows that the mode shape of 0.49 Hz which was dominant during the

oscillation with a damping of less than 3 % (Table 5-11).

Figure 5-84: Voltage and Frequency plot of Farakka PMU along with the OMS result

Figure 5-85: Oscillation as observed from the SCADA data in Voltage of DVC

DECEMBER - 2013 POSOCO73

Synchrophasors - Initiative in India

Figure 5-86: Frequency from PMU from Western, Northern and

Eastern region of Indian Grid

Figure 5-87: Mode shape of 0.49 Hz Frequency from the analysis of

various PMU

Table 5-11 : Mode observed during the oscillation

5.2.3.3. 0.2 Hz Oscillation in the SR Grid while taking Simhadri Unit 2 in service

Date and Time : 22-10-13 19:29 Hrs

Data Used for Event Analysis : Gajuwaka, Vijaywada

Overview: Low frequency oscillation is also observed in the SR grid. This case presents a situation when LFO

appeared while synchronizing a generating unit in the grid.

Event Description: On 22.10.13, at 19:29 hrs, while taking Simhadri Unit-2 (500 MW) in service, low frequency

oscillations were observed in PMUs of SR Grid.

Analysis: The PMU plot of frequency in figure 5-88 shows that oscillations were observed in voltage, real and

reactive power from Gajuwaka PMU. Along with that it was also observed in Vijayawada PMU.

Figure 5-88: Voltage, Real power and Reactive power observed from Gajuwaka PMU

Frequency Damping Ratio (%) Energy

0.4925 0.6431 0.4105

74 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

The voltage signal was analysed using multiple signal Prony analysis with singular value decomposition so as to

remove the errors due to singularity. Thus it helps in identifying the major mode and removing the modes with low

contribution near to major modes. In the analysis it was found that major mode is 0.2 Hz which is an inter-area mode.

5.2.4. Inter-Plant Oscillation Observed in the Grid

5.2.4.1. Inter-Plant oscillation at Omkareshwar Hydel Power station

Date and Time : 02-09-2013 14:06 Hrs

Data Used for Event Analysis : Itarsi, Satna, APL Mundra, Bhadrawati PMU

Overview: Low frequency oscillation with mode frequency of 1.02-1.03 Hz was observed in the WR grid when 350

MW Omkareshwar Hydel power station evacuating through by only one 220 kV circuit during contingency.

Event Description: This case is the continuation of the Omkareshwar case study discussed in Fault Analysis

section. When the Omkareshwar (OSP) hydel power evacuations was through a single feeder i.e. 220 kV OSP-

Chhegaon, this line got overloaded due to 350 MW power transfer. With this oscillations were observed in WR grid

for duration of 15 second and got damped out.

Figure 5-89: Oscillation observed in frequency at different location in WR Figure 5-90 : 03 Hz Mode shape of the oscillation observed

Table 5-12: Mode observed during the oscillation

Method Frequency Damping Ratio (%) Energy

Prony 1.0301 1.8611 0.09655

Matrix Pencil 1.0255 1.6494 0.0969

HTLS 1.0266 1.5044 0.0743

DECEMBER - 2013 POSOCO75

Synchrophasors - Initiative in India

Analysis:

It can be observed that Low frequency oscillation of 1.02- 1.03 Hz was observed at various locations in WR grid

during the event. From mode shape it can be inferred that this mode is localized near Itarsi only. The damping of

the oscillation is less than 3 % which is of concern. The tuning of PSS at Omkareshwar HPS may be required and

NHDC has been requested to kindly look into the matter.

5.2.5. Inter and Intra-Plant Oscillation Observed in the Grid

5.2.5.1. Oscillation at Dadri Thermal Power station

Date and Time : 01-01-2013 18:37 Hrs

Data Used for Event Analysis : NEW Grid PMUs

Overview: Low Frequency oscillation has been observed in Indian system on several occasions. This case study

present low frequency oscillation observed at only one location. No oscillation was observed in rest of the system

as observed in the PMU installed across the different region of NEW grid. This indicated that this is a case of local

mode of oscillation.

Event Description: Low frequency oscillations were observed in Dadri frequency at 18:37:30 hrs to 18:37:49 hrs

on 1st January 2013. Persistence oscillations were observed for more than 18 seconds.

Analysis: Figure 5-91 shows the frequency plot and it can be seen that low frequency oscillations were observed

only at Dadri PMU. The mode that was observed is 1.67 Hz which is in the range of Intra-plant oscillation which

was present only in Dadri Frequency signal. Figure 5-92 shows the zoomed view of the oscillation which is of

growing nature. Figure 5-93 shows the voltage variation at Dadri during the event.

During this case all over India data was collected for oscillation and once again it was found that it was localized

only to Dadri as no oscillations were reported from any other generators. During investigation, it was learnt that

there was an event of malfunctioning of EHC governor of 490 MW Unit-5 at Dadri TPS stage-2. It was further

clarified that low frequency oscillation was on account of testing of the valve control system on 490MW Unit-5 at

Dadri TPS and same unit was hunting from 350 MW to 470MW. The oscillation frequency was 1.66 Hz.

Figure 5-91: Low Frequency oscillations in Dadri Frequency

76 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 5-92: Zoomed view of Frequency Plots

Figure 5-93: PMU plot of Dadri phase voltages

5.2.5.2. Blackout at Paricha Thermal Power Station

Date and Time : 11-04-2013 01:45 Hrs

Data Used for Event Analysis : Bassi, Kanpur, Hisar, Balia, Agra, Meerut, Karcham PMU

Overview: This case study presents how bottleneck in transmission and overloading in transmission line results

in oscillation at generating plant and further their tripping.

Event Description: Paricha Stage-I, II & III (2× 110 + 2× 210 + 2×250 = 1140 MW) has been commissioned

and evacuated through existing network of Stage-I & II. At the time of event Paricha thermal power station was

being evacuating through five 220 kV circuits i.e. 220 kV Paricha-Orai T/C, 220 kV Paricha-Bharthana S/C and 220

kV Paricha-Banda S/C as shown in Figure 5-89. 220 kV Orai-Kanpur circuit was out which resulted in transmission

bottleneck as now four 220 kV circuits (220 kV Paricha-Orai T/C and 220 kV Paricha-Bharthana) were connected

to Mainpuri. Now in this scenario, any tripping at 220 kV Mainpuri will affect all these four circuits. At 01:45 hrs,

DECEMBER - 2013 POSOCO77

Synchrophasors - Initiative in India

B-phase CT at Manipuri (UP) of 220 kV Mainpuri-Harduaganj line bursted and during this 220 kV Orai-Mainpuri line

also tripped. With this the 220 kV Paricha-Orai T/C of no use and it resulted in power evacuation of Stage II and

Stage III (810 MW Generation) through two circuits i.e. 220 kV Paricha-Bharthna-Safai-Mainpuri and 220 kV

Paricha-Banda ckt. Oscillations were observed in system and Units tripped resulting in blackout of Paricha.

Figure 5-94: Grid connectivity diagram of Paricha thermal power plant

Analysis :

Figure 5-95: Frequency and ROCOF observed during the event from different PMUs in NR

Figure 5-96: Phase Voltage observed during the event showing oscillation

78 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

As observed from the Figure 5-95 and 5-96 oscillations were observed in Frequency as well as Voltage in various

PMUs across Northern region. Maximum oscillations was observed at Agra followed by Bassi, Dadri, Bawana and

Meerut as observed from Figure 5-97. Modal analysis is shown in Figure 5-98 shows that the oscillation is in the

range of 1.54 Hz to 2.58 Hz which are Intra-plant mode. The participation factor for this mode was maximum for

Agra PMU (Near to the Parichha) followed by Bassi, Dadri, Bawana and Meerut.

Figure 5-97: Oscillation observed in the frequency and ROCOF

Figure 5-98: Modal Analysis of Oscillation performed by the OMS Engine

5.2.5.3. Severe Oscillation observed in NR System

Date and Time : 06-06-2013 16:33 Hrs

Data Used for Event Analysis : PMUs at Bassi, Kanpur, Hisar, Balia, Ara, Merut, Karcham

Overview: This case study shows low frequency oscillation of Intra-plant range due to separation of Bus 1 and Bus 2

at 400 kV Chabra Sub-station.

DECEMBER - 2013 POSOCO79

Synchrophasors - Initiative in India

Event Description: At 16:33 hrs 400 kV Chabra-Bhilwara line reportedly tripped and due to only one tie breaker

availabilitybetween 400 kV Bus 1 & 2 at Chabra S/s, both buses got separated. The bus configuration during the

event is shown in Figure 5-99. Large fluctuations in MW output of Kawai machine were observed and reported by

shift personal at Kawai (From 800 MW to 350 MW).

Figure 5-99: Connectivity Diagram of 400 kV Chabra station

Analysis: These oscillations were captured in the synchrophasor data as shown in Figure 5-100. The oscillations

were of growing magnitude and lasted for 22 seconds. The probable reason of oscillation is the wheeling of power

through longer route. The total line length of 400 kV Kawai-Chabra-Hindaun-Heerapura ckt is 513 km. through

which power was wheeling. It can be observed from PMU that frequency measured at Bassi was oscillating

against rest of the PMU frequency in NR as shown in Figure 5-101.

Figure 5-100: PMU plot of frequency and modal analysis Figure 5-101: Zoom view of PMU plot of frequency and modal

analysis

80 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

The OMS shows that oscillations were in the range of intra plant oscillation (1.9 Hz - 2.4 Hz). This may be due to

limit hitting of generators near Bassi.

5.2.5.4. Oscillations in NER Grid

Date and Time : 03-08-2013 at 22:31 Hrs

Data Used for Event Analysis : PMU data from Bongaigaon, Balipara, Sarusajai, Agartala, Imphal,

SOE available at NERLDC

Event Description: From 22:31:50 Hrs to 22:34:04 Hrs on 03-August-2013, Low Frequency Oscillations were

observed in NER Grid in all the PMUs of NER. The duration of this low frequency oscillation is around 3 minutes.

Figure 5-102: Single Line Diagram of NER Grid during the time of incidence

Figure 5-103: Oscillation in Frequency observed from NER PMUs

DECEMBER - 2013 POSOCO81

Synchrophasors - Initiative in India

Analysis: The Synchrophasor data was analyzed using Fast Fourier transform and Matrix pencil method to find

the Individual mode, damping and mode shape.

1. FFT Analysis : From the PMU data, oscillations could be observed in the PMU in NER. To ascertain the probable

source of this persistent oscillation, fast fourier transform (FFT) analaysis was done on frequency, phase voltages and

currents measured from the PMU. From the FFT plots of frequency in Figure 5-104, it can be seen that the relative

amplitude (or energy) is maximum at Imphal and Agartala. The maximum energy is at 0.96 Hz, which is indicative of

Inter-Plant oscillation.

Figure 5-104: FFT Analysis on Frequency at different nodes of NER

Further analysis was performed on phase voltages of all PMUs of NER and line currents of 132kV Badarpur-

Khleihriat S/C, 132 kV Badapur-Kumarghat S/C, 132 kV Dimapur – Imphal S/C, which indicate two modes of

oscillation at 0.96 Hz and 1.91 Hz, with 0.96 Hz being the dominant mode as shown in Figure 5-105 & 5-106.

Figure 5-105: FFT of 400 kV Bongaigaon phase voltage Figure 5-106: FFT of current of 132 kV Badarpur – Khleihriat S/C

82 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

2. Matrix Pencil Analysis:

Figure 5-107: 0.96 Hz with damping of 0.77 % Figure 5-108: 0.94 Hz with damping of -

0.35 %

Figure 5-109: 1.95 Hz with damping of

5.65 %

The matrix pencil was used for modal analysis on frequency and it was found that two Inter-plant modes with

frequency 0.96 and 0.94 Hz and one Intra-plant mode of 1.95 Hz was observed. Out of these 0.96 Hz was having

positive damping while 0.94 Hz is having negative damping. Such nearness of modes occurs due to modal

resonance. From the Figure 5-107 & 5-108 it can be observed that generators near to Agartala, Sarusujai and

Imphal participate in the oscillation. 1.95 Hz oscillation was observed only at Imphal as shown in Figure 5-109

which indicate source of oscillation is located there.

5.2.5.5. Oscillations in NER Grid Resulting in tripping of Generating units and lines

Date and Time : 11-08-2013 at 23:35 Hrs

Data Used for Event Analysis : PMU data from Misa, Badarpur, NEHU, Imphal, Agartala ; SOE available at

NERLDC ; SCADA data

Overview: This event showcases how a small perturbation like switching of reactor can result in small signal

instability in the grid. It also emphasizes the importance of PSS tuning of generator’s AVR.

Event Description: Oscillation started in NER grid at 23:33:10 Hrs which was having low magnitude. At 23:35:07

Hrs, 63 Mvar Bus-Reactor II at 400 kV Silchar(PG) was taken into service to improve voltage profile following

which low frequency oscillations started growing as observed in PMU data of all available nodes of NER upto

23:37:47 Hrs. The total duration of LFO observed in the grid was 268 seconds. It was informed that heavy

oscillations were observed in Doyang HEP of NEEPCO with generation and flow of outgoing feeders from Doyang

varying rapidly. Due to severe oscillations at Doyang HEP, Unit-2 of Doyang HEP (Generation = 23 MW) tripped at

23:36 Hrs along with 132 kV Doyang – Dimapur II line. Oscillations were also observed at Loktak HEP of NHPC,

with variation of generation and rapid variation in outgoing feeders from Loktak. After observing these oscillations,

Manipur manually reduced its drawal to around 50 MW (reduction by15 MW) and Loktak also reduced its generation

to prevent overloading of lines from Loktak.

DECEMBER - 2013 POSOCO83

Synchrophasors - Initiative in India

Figure 5-110: NER Grid view prior to the LFO observation i.e. 23:34 Hrs

In the Figure 5-110 shows the schematic diagram of NER grid where yellow circle indicates the generation

participation in the oscillation as per the preliminary investigation while red square indicates the PMU location in

the NER grid. Blue circle in the figure indicate the place where the 63 Mvar Bus reactor was switched on which

excited the LFOs.

Figure 5-111: R-phase currents of few Lines of NER Grid Figure 5-112: R-phase voltages (in p.u.) of few nodes of NER Grid

The PMU plots ( Figure 5-111 & 5-112) indicate that three events had occurred during the events which are as:

1. At 23:33:10:740: Either a reactor is switched off / Capacitor bank switching / Line charged

2. At 23:35:07.920: 63 MVAR Bus Reactor at Silchar was switched on.

3. At 23:37:09.440: Doyang Unit 2 tripped along with 132 kV Doyang Dimapur II.

Analysis: From the PMU data, oscillations could be observed in all 4 PMUs of NER at that time. As it was

observed that the oscillations initiated due to change in reactive power, so best signal to analyze such oscillation

84 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

would be voltage. From Different PMUs of NER voltage data was first converted to p.u. based on base voltage and

then analyzed. The data was analysed for the sequence of events as above and is presented below :

Figure 5-113: During 12-128 Seconds data window

considered for analysisFigure 5-114: Mode shape of 1.0058 Hz

From the analysis of first 12-128 seconds as shown in Figure 5-113 it was found that 1.0058 Hz which is Inter-

plant mode is present in the system. The damping of this Inter-plant mode was almost zero during the period.

Imphal was having the highest energy followed by Badarpur, Balipara and Misa. Generators in the vicinity of

Imphal (Loktak HEP, Doyang HEP) were oscillating.

Figure 5-115: During 137-200 Seconds data window considered

for analysis

Figure 5- 116: Mode shape of 1.0074 Hz

During the analysis of period after 63 Mvar reactors switching it was found that 1.0074 Hz mode which is Inter-

plant (or Local mode) mode was having the highest energy and its damping is negative. The 2nd harmonic of this

mode i.e. 2.0156 Hz was also present with low energy content negative damping. This mode is Intra-plant

nature. From the mode shape shown in Figure 5-116, it is observed that Generators near Balipara and Imphal

were oscillating at 126 deg apart.

DECEMBER - 2013 POSOCO85

Synchrophasors - Initiative in India

Figure 5-117: During 213-241 Seconds data window considered for

analysis

Figure 5-118: Mode shape of 0.9958 Hz

Table 5-13: Dominant Modes observed during the 213-241 Seconds

When the oscillation started growing up as shown in Figure 5-117, two Intra-plant modes (1.9740 Hz and 1.9774

Hz) and two Inter-plant modes (0.9958 Hz and 0.9979 Hz) are being observed in the system as given in Table 5-

13 . Their frequencies are very nearby suggesting the strong resonance /mode coupling phenomenon. Modal

resonance has resulted in increase in damping of one mode while other mode becomes unstable with negative

damping. Similar behavior is true for the 2nd harmonics of these modes. With the switching of reactor, LFOs in the

system got excited resulting in growing nature of oscillations. At some point of time, the modes which are very

near to each other move closer and has shown a strong resonance leading to unstablising of one mode while

stabilizing other mode. This has resulted in unstable system leading to growing oscillation.

Figure 5-119: During 253-280 Seconds data window considered for

analysis

Figure 5-120: Mode shape of 0.9627 Hz

Frequency Damping (%) Energy

0.9958 1.4589 0.6203

0.9729 -0.1670 0.2851

1.9774 0.4950 0.2826

1.9470 -0.1909 0.0685

86 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Table 5-14: Dominant Modes observed during the 253-280 Seconds

In the final stage shown in Figure 5-119, the damping of modes has improved and with this oscillations has

damped out in the system. The damping resulted from the change in system condition which has resulted in

moving the modes away from the resonance.

Figure 5-121: AGTPP unit-wise Mvar from SCADA Figure 5-122: Loktak unit-wise Mvar from SCADA

Figure 5-123: Doyang unit-wise Mvar from SCADA

Based on above analysis, it is certain that LFO got excited at 23:33:10:740 which may be due to either reactor/

capacitor switching or line charging. At this moment Inter-plant modes in the range 0.9 Hz-1.1 Hz got excited and

Frequency Damping (%) Energy

0.9627 0.9109 0.6157

0.9964 -0.1357 0.0373

1.9164 0.9092 1.0167

1.9637 0.1785 0.1578

DECEMBER - 2013 POSOCO87

Synchrophasors - Initiative in India

persisted in the system. This may be due to the sudden change in reactive power which has resulted in voltage

rise/dip at different location in the system and several generators were trying to modulate their AVRs to adjust the

change in their terminal voltages. But due to their improper/absence of PSS tuned exciter or manual control mode

of AVRs, the LFOs did not damp out and persisted in the system.

The rise in amplitude as observed is sudden which indicate that a system can collapse very fast when the PSS of

generators are not tuned properly or their AVRs are in manual control mode. The Inter-plant modes in the range 0.9 Hz-

1.1 Hz and intra-plant mode in the range 1.8 Hz-2 Hz were observed in the system. Interestingly it can be observed

that modes and their harmonic are having similar nature of magnitude increment with time as observed from Table 5-

13 and 5-14.

From Figures 5-121, 5-122 & 5-123, it can be observed that even within the same plant, some generators were

absorbing MVARs while some were generating near to Imphal. After the switching of reactor, wide variation in

Mvar can be seen at Loktak, AGTPP and Doyang. With tripping of generators and lines, the oscillations subsided.

This case study signifies the importance of small signal stability studies and Model updation of small generators

for study and planning purposes. Model validation of turbine and governor of such generators is very much

required for offline and real time dynamic assessment.

In the Table 5-15, Low frequency oscillation observed in the NEW grid and SR grid has been tabulated.

Table 5-15 Low frequency Oscillations observed in Indian grid

88 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

5.3. Detection of Coherent Group of Generators

Generator Coherency is a phenomenon in power system where certain generators tend to swing together after a

disturbance. These generators are collectively referred to as a group of coherent generators. A coherent group of

generators can be aggregated to form a single equivalent generator model that has the same effect on system

dynamic modes as the original generator set. The process of aggregation removes the high frequency, inter-

generator modes from the aggregated model and the generator [R2]. Transient stability or large disturbance rotor

angle stability is concerned with the ability of the power system to maintain synchronism when subjected to a

severe disturbance, such as a short circuit on a transmission line. Instability that occurs in the form of increasing

angular swings of some generators leading to their loss of synchronism with respect to others. The rotor angles

of all the generators swing together in a synchronous frame of reference prior to the occurrence of disturbance.

This means the angular difference between any two generators is approximately constant over a period of time.

The disturbance on the system causes drift in the rotor angle of some generators and hence these generators

move away from the rest of the generators in the system and form different groups. Generators belonging to a

cer tain coherent group are to have similar response curves with each other after a system disturbance. The

generators in each group are known as coherent generators. After the removal of the disturbance, the affected

generators will again swing back to synchronism with the rest of the generators.

Multi-machine equations can be written similar to the one-machine system connected to the infinite bus. Following

any disturbance the difference of rotor angles of the coherent machines remains constant in time and if they have

equal velocity and acceleration as described by the following equations:

During disturbances weak tie lines interconnecting two systems may lead to formation of group of generators

oscillating against each other. Generators among each group may have similar rotor angle waveforms. These

generators are considered to be coherent. To avoid an impending disturbance, certain out of step relays have to be

set to accomplish system separation or adaptive islanding and as such these groups must be identified.

5.3.1. Coherency observed in NEW grid during Bus fault at Parli S/s on 03-03-2013.

As shown in Figure 5-124 during a bus fault at 400 kV Parli substation in Western Region, generators in western

part of the Western grid were in anti-phase with generators in Northern region. This anti-phase swinging was in

system for three seconds after which they again reached to the equilibrium point. The mode which was the found

during the analysis was 0.5 Hz and it can be observed from Figure 5-125 that the Northern Region and Western

Region generators were swinging in phase opposition.

DECEMBER - 2013 POSOCO89

Synchrophasors - Initiative in India

Figure 5-124: Frequency plots during bus fault at 400 kV Parli Substation illustrating the antiphase swinging of Western region machines

with Northern Region

Figure 5-125: Frequency plots during bus fault at 400 kV Parli Substation illustrating the antiphase swinging of Western region machines

with Northern Region

5.4. Island Detection and Resynchronization in the Grid

Islanding detection and its re-synchronization with the grid is an important event that can be monitored and

detected using wide area measurement system. During a synchronous operation the phase angle difference

measured from the PMUs between different nodes will be constant and will vary according to power transfer

between source and sync and other parameter like load generation balance, voltage etc. During islanded condition

the phase angle difference between nodes in two different islands will vary and their variation will depend on the

differential frequency of the two islands.

90 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

From the experience it has been observed that phase angle difference between PMU in two different islands will

be the saw tooth and the saw tooth wave frequency would be the differential frequency. If the frequency difference

is quite large then the sawtooth frequency will depend on the reporting rate of PMU. In case both the grid are

running at same frequency then the phase angle difference will be same and will not be having any sawtooth.

For example Figure 5-126 shows the islanding of one portion from the other. Frequency of the two islands (Island

1 with Bhadrwati and island 2 with Balipara and Agar tala) were different from each other after the loss of

synchronization. The angle between the positive sequence voltage between the two islands shows that prior to

loss of synchronization angle was constant. But as the synchronization is lost the angle start increasing. After

360o the angle was continuously increasing which was again wrapped in (0o-360o) for convenience. This resulted

in sawtooth waveform of the angle.

PD = 1/ (Time difference between peak adjacent peak points of saw tooth)

FD = frequency difference in between the two islands during the adjacent peak

Figure 5-126: Frequency plots during bus fault at 400 kV Parli Substation illustrating the antiphase swinging of Western region machines

with Northern Region

It can be observed from the Figure 5-126 that the frequency of the sawtooth for the angle difference between two

islands is equal to the frequency difference between two islands.

5.4.1. Islanding of NR Grid from Rest of the NEW Grid on 30-07-2012

Date and Time : 30-07-2012 02:33 Hrs

Data Used for Event Analysis : PMU at Kanpur and Jabalpur

DECEMBER - 2013 POSOCO91

Synchrophasors - Initiative in India

Figure 5-127: Phase angle difference during the islanding of NR from rest of the NEW grid on 30th July 2012

Figure 5-127 shows that the NR grid got islanded from the rest of the system on 30th July’12. The ambular

difference plot is made in offline mode during post dispatch analysis. As observed in the Figure 5-127, first phase

angle difference has increased between Kanpur and Jabalpur and sawtooth wave form represents that two

systems has islanded.

5.4.2. Islanding of NR, ER and NER Grid from Rest of the NEW Grid on 31-07-2012

Date and Time : 31-07-2012 13:00 Hrs

Data Used for Event Analysis : PMU at Kanpur and Jabalpur

Figure 5-128: Phase angle difference during the islanding of NR, ER and NER from rest of NEW grid on 31th July 2012

Figure 5-128 shows that the NR, ER and NER grid got islanded from the rest of the NEW grid on 31st July’12 The

ambular difference plot is made in offline mode during post dispatch analysis. As observed in the Figure 5-128,

first phase angle difference has increased between Kanpur and Jabalpur and sawtooth wave form represents that

two systems has islanded.

92 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

5.4.3. Islanding of NER Grid from Rest of the NEW Grid on 29-09-2013

Date and Time : 29-09-2013 16:25

Data Used for Event Analysis : PMU data from Bongaigaon, Balipara, Agartala, Bhadrawati, Raipur,

Jabalpur ; SOE available at NERLDC ; SCADA data ; Disturbance Recorder

data from Bonagaigaon

Overview: This case study is unique in the sense that after the deployment of the Pilot project in the all the regions,

this being the first event of islanding that has been analyzed using synchrophasor data.

Event Description: 220 kV BTPS-Salakati D/C lines were under planned shutdown. NER Grid was connected to rest

of NEW Grid through 400 kV Balipara – Bongaigaon D/C lines and was exporting around 240 MW to NEW Grid as

shown in Figure 5-129. Demand met of NER prior at that time was 1057 MW.

Figure 5-129: Connectivity diagram of North-Eastern Regional grid with NEW grid prior to islanding

At 16:25:08:360 Hrs, 400kV Balipara – Bongaigaon I tripped and at 16:25:09:440 Hrs 400 kV Balipara – Bongaigaon

II tripped, which led to isolation of NER Grid from rest of NEW Grid.The schematic diagram of NER grid is shown in

figure 5.129. With the isolation from NEW grid, NER grid formed a generation rich island. To stabilize the frequency

which was increasing, Unit-1 of Ranganadi HEP (Gen: 110 MW) was tripped as per NERLDC instruction at

16:32:39:370 Hrs while Palatana GTG-I got tripped at 16:26 Hrs (Gen: 59 MW) and while AGTPP generation

reduced from 75 MW to 57 MW. This has resulted in load generation balance and frequency was stabilized.

Separation of NER Grid from rest of NEW Grid, as well as fault clearing can be clearly observed from PMU plots of

NER w.r.t. WR Grid (Connected to NEW Grid) in Figure 5-130 , 5-131 & 5-132.

DECEMBER - 2013 POSOCO93

Synchrophasors - Initiative in India

Figure 5-130: Angular Separation between Positive Sequence Voltages of NER PMUs w.r.t. Bhadrawati PMU (in WR) along with

NER Grid Frequency

Figure 5-131: Positive Sequence voltages at Bongaigaon, Balipara, Agartala (When NER Grid Islanded)

94 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 5-132: Voltages at Bongaigaon showing significant dip in R-phase voltage at Bongaigaon (Voltage input to PMU at Bongaigaon was

from line CVT of 400kV Balipara – Bongaigaon II)

The synchronization at 16:34:48 Hrs appears to be rough synchronization where frequency difference between

NER Grid and rest of NEW Grid was around 0.344 Hz as shown in Figure 5-133. This resulted in heavy power

inrush to NER Grid (around 160 MW). Also this synchronization resulted in vibrations (hunting) of machines, and

also wide changes in MVAR absorption/injection of units resulting in tripping of several units. The swing in voltage

in NER PMUs can be seem in Figure 5-134. All units of AGTPP at 16:34:49.162 Hrs tripped following synchroniza-

tion and Generation of STG-I of Palatana came down by around 25 MW which later tripped at 16:39 Hrs. Tripping

of generators were also reported in Tripura system (Gen Loss: 42 MW) and Assam system (Gen Loss: 53 MW).

Net loss of generation was 380 MW in NER Grid

Figure 5-133: Angular Separation between Positive Sequence Voltages of NER PMUs w.r.t. Bhadrawati PMU along with NER Grid

Frequency (at the time of resynchronization with NEW Grid)

DECEMBER - 2013 POSOCO95

Synchrophasors - Initiative in India

Figure 5-134: Positive Sequence Voltage at Bongaigaon, Balipara, Agartala (at the time of resynchronization with NEW Grid)

Analysis: From the PMU data, it was possible to uniquely identify the event, the fault clearing times (may not be

exactly accurate as PMU data are available at every 40 ms whereas stipulated fault clearing time on 400 kV is 100

ms) and the oscillations that developed in the system as a result of this rough synchronisation process. The PMU

data was analysed further which showed that the synchronisation resulted in Inter-area oscillations of around

0.53 Hz in the system and hence is very dangerous in nature.The R phase voltage of bongaigaon was low for

considerable amount of time as the PMU voltage input is taken from the line CVT.

From the relay indication of 400 kV Balipara-Bongaigaon II, R Phase fault was observed at both Bongaigaon and

Balipara ends. Auto-reclosure was successful on this circuit at Balipara end. It appears that while 1 phase (R-phase)

may have tripped at Bongaigaon end, other 2-phases (Y and B) were still connected. From the phase voltage plots at

Bongaigaon, significant sag in voltage of R-phase is found for a long duration. This seems to be a case of persistent

earth-fault on R-phase but is yet to be confirmed as the magnitude of voltage on R-phase was quite low (around 0.1

– 0.2 p.u.) Another reason could be due to the induced voltage on this phase from other two charged phases even

after the fault was cleared. Since voltage inputs to PMU at Bongaigaon were from line CVT of 400kV Bongaigaon

– Balipara II, it could not be confirmed from PMU measurements. Also data of this line from Balipara end was not

available at the time of event which could have given a clearer picture.

Frequency of Agartala, Balipara, Bongaigaon, Bhadrawati, Sugen and Mundra was analyzed for LFO observed during

synchronization as shown in Figure 5-135. It was confirmed that 0.53 Hz mode (Inter-area mode) was present with

high energy content as given in Table 5-16.

96 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 5-135: Frequency of NER and NEW grid (at the time of resynchronisation with NEW Grid)

Table 5-16: Major Mode observed after the combined analysis of several PMU of NEW grid

This being the first case study when islanding at regional level occurred and survived after the pilot project of

synchrophasor has been commissioned in all the regions. The synchrophasor has given lots of insight into the

islanding of the grid which are as following:

1. All the constituents and all Control room operators must be well informed about any planned outage prior

to that, and must also be aware of the grid conditions and connectivity so that they do not undertake any

rough operation which could be dangerous. In this particular case, NER Grid was exporting (as is usually

the case for most of the year) and if the demand of NER have been on higher side, it might have resulted

in collapse of entire grid of NER.

2. Proper care to be taken while synchronization of two islands, one with low and other with high inertia.

3. The rough synchronization was as a result of some snag in the synchroscope at Bongaigaon. Thiswas a

serious issue as NER Grid was connected to rest of the NEW Grid through only one in feed point (Bongaigaon)

Method Frequency Damping Ratio (%) Energy

Matrix Pencil 0.5374 10.264 6.4912

DECEMBER - 2013 POSOCO97

Synchrophasors - Initiative in India

and hence any such issues could be very harmful to the entire grid. The snag was rectified later; however

the incident highlights the need for healthiness of equipment at important substations to avert any mishap.

4. The PMU inputs at site should be as per stipulated and not be modified due to site constraints. Had the

voltage input at Bongaigoan PMU been from Bus PT of 400kV Bus at Bongaigaon, it could have given a

better understanding of the event. It is learnt that due to some constraints at site this input was taken from

line CVT.

5. It would be helpful for all the RLDC to at least have one PMU data from other Region. This will help in any such

cases resulting in separation.

6. Exciter / PSS tuning of generators in NER, especially in Southern Part of NER Grid is required as frequently

LFO are being observed.

5.5. Dynamic Model Validation Using Synchrophasor data

In power system, dynamic Modelling and its validation are very important tasks. The first question that is being

raised by the utility is “Why there is a need to validate the dynamic modelling validation of various elements in the

power system?”. The answer to the question is that these models form the foundation of all the power system

simulation studies for contingency planning during pre-dispatching, in real time system operation and future

planning for grid strengthening. So, periodic system model validation in actual operation is a need for planners and

operators. It is required to ensure that the power system models are accurate and up to date from time to time.

These tasks need to be performed regularly in order to keep up with ongoing changes and additions in the grid.

These models are also being used in the Control Centre for state estimator. If the model is not updated the output

of state estimator will be having a large error.

One of the efficient ways to validate the model is during the disturbances. Disturbances present great opportunities

for model verification and identification of necessary model improvements. As during these condition the control

variable associated with the model will function which affect the response of the equipment in respect to the

disturbance.

This section presents the case studies involving the model validation of Electrode Current limiting characteristic of

HVDC bipole, SPS associated with HVDC, Frequency controller of HVDC, data validation from PMU/DR/Offline

simulation for a fault.

5.5.1. Validation of Electrode Current limitation characteristics of HVDC Talcher-Kolar.

Date and Time : 09-05-2013 04:11

Data Used for Event Analysis : Somanahalli, Bhadrawati, Raipur, Dehgam, Itarsi PMU

Overview: Southern Grid in Indian power system is asynchronously connected with the rest of the Indian grid

through two back to HVDC and one Bipolar HVDC Line. The Talcher-Kolar bipolar HVDC connect Talcher Sub-

station (Converter) in Orissa to Kolar Sub-station (Kolar) in Karnataka. This case study validates the electrode

current limitation characteristic as well as the SPS action. Connectivity of the bipolar HVDC links is shown in

Figure 5-136.

98 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 5-136: HVDC Talcher-Kolar schematic Diagram

Event Description: HVDC Talcher-Kolar Pole -1 blocked due to External feeder Protection due to bus fault due to

failure of 400 kV Bus-1 sectionalizer CT and tripping of Bus 1A, IIb and IIa at Kolar. Pole-2 came on Metallic return

mode and then to Ground return mode. Power flow came down from 1857 MW to 1040 MW then to 153 MW.

Frequency increased to 49.80 Hz from 49.93 Hz then came down to 49.43 Hz.

The behavior of southern region frequency NEW grid frequency was compared with the current reduction

characteristics of HVDC bipole after tripping of one HVDC pole without changing over to metallic return. The

current characteristic of HVDC link is shown in Figure 5-137.

Figure 5-137: HVDC Current reduction charecteristics

DECEMBER - 2013 POSOCO99

Synchrophasors - Initiative in India

Figure 5-138 shows the current reduction after tripping of one HVDC pole without changing over to metallic return

in SR grid. As per the current reduction characteristics, the power flow on HVDC pole-2 slowly reduced for 1745

MW to 1230 MW at the rate of 7.35 MW/Sec i.e.14.7 Amps/Sec in 70 seconds. Before going into ground return

mode the power flow on pole-2 reduced from 1230 MW to 153 MW at the rate of 56.66 MW/Sec i.e. 13.33 Amps/

sec in 19 seconds.

Figure 5-138: Frequency profile of SR grid during the event

Figure 5-138 shows the Southern region frequency profile recorded at 400kV Somanhalli substation during tripping

of HVDC Talcher-Kolar Pole-1.

Figure 5-139: NEW Grid frequency for the incident

100 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 5-139 shows the NEW grid frequency for the above mentioned incident. It can be observed that the frequency

increased after blocking of pole-1. This is due to the power which was being send to SR grid from Talcher TPS

through HVDC Pole was now available as the excess power in NEW grid. This resulted in increasing of NEW grid

frequency from 50 Hz to 50.2 Hz in the first 70 seconds. After that frequency ramped up to 50.43 Hz in next 19

seconds. After that SPS action resulted in units tripping which led to fall in frequency of NEW grid. The frequency

characteristic is in accordance with the HVDC action which validates the current characteristic of the electrode.

5.5.2. Model Validation of Frequency Control of HVDC

Date and Time : 22-11-2013 14:22-16:20 Hrs

Data Used for Event Analysis : Somanahalli, Bhadrawati, Raipur, Dehgam, Itarsi PMU

Overview: This case study is the model validation of frequency control and frequency limit function of HVDC

.Frequency control in HVDC can be used during the synchronization of two grids. Keeping in view the synchronization

of SR grid with NEW grid, a test for confirming the functioning of frequency control in HVDC Bhadrawati back to

back link was performed on 22nd Nov 2013. This HVDC connects SR grid with WR grid of NEW grid. Here Bhadrawati

West side is in converter mode while the south side in inverter mode. From South Bus of Bhadrawati 400 kV

Bhadawati-Ramagundam D/C are for importing the power to Ramagundam from where it is sent to the Southern

grid.

Background: Frequency control is superimposed on power control. The power flow through the DC link is therefore

guided by the combination of two types of controller. Frequency controller can further be of two types: Target frequency

controller and frequency limit function controller.

In target frequency controller, the target frequency is set as reference and the HVDC link tries to achieve the target

frequency by regulating the flow. In frequency limit function controller, the frequency is made to remain within a

band. When the frequency is within the band, the HVDC is in power controller mode and the power flow through

the link is constant. When the frequency tries to violate the band limits, the HVDC frequency limit function

controller tries to bring it within the band by regulating the flow on the DC link. Various tests have been performed

to validate the action of HVDC controller. Figure 5-140 shows the network connectivity of HVDC bhadrawati.

Figure 5-140: Schematic Diagram of WR and SR Grid Connectivity via HVDC Bhadrawati and PMU Location

DECEMBER - 2013 POSOCO101

Synchrophasors - Initiative in India

HVDC Performance under Various Test its validation: The case study is an example of model validation application

of the PMU. The frequency controllers were set for changing the frequency of the SR grid. PMUs are available at

Bhadrawati (WR Grid) and Ramagundam (SR Grid) end. At Ramagundam end the PMU is connected at Ramagundam

- Bhadrawati 1 circuit. So the power measured at Ramagundam end of this line is equivalent to half of the power

that is coming from Bhadrawati HVDC. The tests at frequency control and frequency limit at HVDC were performed

in four stages.

Test 1: This test was performed to achieve the target frequency at a frequency target higher than nominal frequency

(50 Hz) in Southern Grid. The target frequency for the SR grid was set as 50.16 Hz. Prior to the test the frequency

of SR grid was 49.95 Hz.

Figure 5-141: SR frequency, WR frequency and HVDC power flow during 14:21 to 14:47 hrs

As can be seen from Figure 5-141, as soon as the test star ted, the power flow through the HVDC link pole 1

deviated from its scheduled power of 300MW. Power flowed from Bhadrawati to Ramagundum and measurement

is from Ramagundam end in SR region. This action was due to the controller which tried to bring the frequency of

SR grid to the target frequency. Once the target frequency was reached, the SR system was tending to further

increase the frequency, but the HVDC link reduced the inflow of power so as to reduce the frequency and bring it

back to 50.16 Hz.

Test 2: This test was performed to achieve the target frequency at a frequency target lower than nominal frequency

(50 Hz) in Southern Grid. The target frequency for the SR grid was set as 49.96 Hz. Prior to the test the frequency

of SR grid was around 50.15 Hz. From Figure 5-142 it can be observed that the HVDC power is in accordance to

keep the SR grid frequency at target frequency.

Test 3: This test was to perform the frequency limit control in which the controller will act if the frequency of the

SR grid goes out of the band. The band of frequency was set at 49.9 Hz -50.1 Hz. While conducting the test, pole

2 tripped at 15:26 Hrs as observed in Figure 5-143. The other pole could not take the total power so the power

102 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

reduced to half. Further when the frequency remained within the band the frequency limit function controller did

not respond and the flow through the HVDC link remained constant.

Figure 5-142: SR frequency, WR frequency and HVDC power flow during 14:49 to 15:19 hrs

Figure 5-143: SR frequency, WR frequency and HVDC power flow during 15:25 to 15:44 hrs

Test 4: The band of frequency within which the frequency was to be maintained was 49.7 Hz – 49.9 Hz. The test

started at 16:04 hrs. During the test frequency in southern grid higher than the band selected for frequency control.

The HVDC controller acted to bring the frequency back within the range as observed from the Figure 5-144.

Figure 5-144: SR frequency, WR frequency and HVDC power flow during 16:04 to 16:25 hrs

DECEMBER - 2013 POSOCO103

Synchrophasors - Initiative in India

So, the frequency control function of HVDC was tested and analyzed in real time using the synchrophasor data. It

can be observed how synchophasor has given an insight into the functioning of controller whose action is within

second and its impact of frequency and power.

5.5.3. Validation of Angular Separation calculated from EMS and measured from PMU

Synchrophasor data gives the real time angular difference between the two nodes in the grid while the EMS gives the

angular difference based on state estimation. State estimation is yet to be perfected due to constraint related to

topology and communication issues. At present State estimation is performed based on the available data to the

SCADA and the angular difference between two nodes were calculated and compared with PMU data as shown in

Figure 5-145.

Figure 5-145: EMS estimated and PMU measured angular difference between Korba and Kalwa in a day

As observed from the figure the duration for which most of the data were available, the EMS estimated angle is

well in coherence with the synchrophasor measured angle. This has helped in further improving the state estimator.

5.5.4. Cross validation of DR, Offline simulation and Synchrophasor measurements

This case study presents the model validation of synchrophasor measurement, disturbance recorder for a single

phase to earth fault on transmission line. The line selected here is 400 kV Korba-Bhatapara whose Korba end CT

is connected with PMU along with the Unit 6 GT H/V side. Two events are analyzed here on the same circuit for

single phase to earth fault. Along with that Unit 6 response was also analysed using Synchrophasor data and

offline study for the fault.

Event 1: Y phase to earth fault on 400 kV Korba-Bhatapara ckt on 03-10-2013 (A/R was blocked by the Main 2

Relay due to logic problem)

104 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

PMU PLOTS:

Figure 5-146: Korba Bus Voltage during Y phase to earth fault on

400 kV Korba -Batapara line

Figure 5-147: 400 kV Korba-Batapara Circuit Real and Reactive

power during Y phase to earth fault on 400 kV Korba -Batapara line

Figure 5-148: Korba-Bhatpara Circuit Current during Y phase to

earth fault on 400 kV Korba -Batapara line

Figure 5-149: Korba Unit 6 Current from PMU at Korba during Y

phase to earth fault on 400 kV Korba -Batapara line.

Figure 5-150: Korba Unit 6 Real and Reactive Power during Y phase

to earth fault on 400 kV Korba -Batapara line

Figure 5-151: Frequency observed from different PMU during Y

phase to earth fault on 400 kV Korba -Batapara line

DECEMBER - 2013 POSOCO105

Synchrophasors - Initiative in India

DR PLOTS:

Figure 5-152: Voltage from DR of Korba-Bhatapara Circuit from Korba end during Y phase to earth fault on 400 kV Korba -Batapara line

Figure 5-153: Current from DR of Korba-Bhatapara Circuit from Korba end during Y phase to earth fault on 400 kV Korba -Batapara line

106 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Event 2: R phase to earth fault on 400 kV Korba-Bhatpara ckt (A/R was blocked by the Main 2 Relay due to logic

problem)

PMU PLOTS :

Figure 5-154: Korba Bus Voltage during Y phase to earth fault on

400 kV Korba -Batapara line

Figure 5-155: Korba-Batapara Circuit Real and Reactive power

during Y phase to earth fault on 400 kV Korba -Batapara line

Figure 5-156: Korba-Batapara Circuit Current during Y phase to

earth fault on 400 kV Korba -Batapara line

Figure 5-157: Korba Unit 6 Current during Y phase to earth fault on

400 kV Korba -Batapara line

Figure 5-158: Korba Unit 6 Real and Reactive Power during Y

phase to earth fault on 400 kV Korba -Batapara line

Figure 5-159: Korba Unit 6 Real and Reactive Power during Y

phase to earth fault on 400 kV Korba -Batapara line

DECEMBER - 2013 POSOCO107

Synchrophasors - Initiative in India

DR PLOTS :

Figure 5-160: Voltage plot from DR of Korba-Bhatapara Circuit from Korba end during Y phase to earth fault on 400 kV Korba -Batapara line

Figure 5-161: Current plot from DR of Korba-Bhatapara Circuit from Korba end during Y phase to earth fault on 400 kV Korba -Batapara

line

108 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Offline Study Result from PSS/E for Unit -6 Response:

Figure 5-162: P & Q of Korba-Unit-VI using offline study

Analysis: Based on the synchrophasor data (Figure 5-146 to 5-151 & 5-154 to 5-159), DR data (Figure 5-152,

5-153, 5-160 & 5-161) and offline study (Figure 5-162), validation was done through three different sources,

details are given below:

From above table the Fault current is validated using PMU and DR of the same line. Along with that the fault

clearance time is also validated. The generator 6 response on which PMU is connected at HV side is also similar

to what has been observed from the offline model for the fault study in PSS/E. The auto-reclosure for this line was

not observed as seen from PMU/DR.

5.6. Visualization of PSS testing.

5.6.1 PSS tuning at Karcham Wangtoo HEP on 11-12 April 2013

This section describe a case study where PMU has helped in detecting the oscillation in real time and giving a

clue that the PSS requiresto be tuned,subsequently the PMU helped in visualizing the online performance test of

PSS at archam Wangtoo HEP.

DECEMBER - 2013 POSOCO109

Synchrophasors - Initiative in India

Figure 5-163: Screenshot of PMU data display at NRLDC on 23-August 2012 at 19:02 hrs

Oscillations were observed on 23rd August 2012 (at 19:02 hrs) and 24th August 2012 (04:08 hrs) in the NEW grid.

The oscillations on 23rd August 2012 coincided with the forced outage of 400 kV Wangtoo-Abdullapur – ckt-1 & 2

(carrying 2x500 MW) and 400 kV Panchkula-Abdullapur- ckt-2 (carrying 392 MW). The antecedent generation in

the Jhakri-Baspa-Wangtoo complex was 3000 MW (Jhakri: 1600 MW, Wangtoo: 1100 MW and Baspa: 300 MW).

The screen shot of the oscillations observed on the PMU data display at NRLDC is shown in figure 5.163. The

oscillations subsided after manual reduction of generation in the complex.

Testing of PSS of generator at Karcham: The performance of PSS on the generating units of Wangtoo HEP was

tested in time domain using the following two methods:

1. Performance of unit running with and without PSS in service was monitored for a voltage step change of ~

3% to the AVR.

2. Performance of the running units with and without PSS in service was monitored for a perturbation created

by switching of one of the evacuating lines from Wangtoo HEP. The PLCC on the line being switched was kept

off during the test so that the line is opened only from one end and it remains connected from the remote end.

Line switching test recorded in real time:The generation at Baspa HEP and Wangtoo HEP is evacuated through 400

kV Wangtoo-Jhakri D/C and 400 kV Wangtoo-Abdullapur D/C lines. Critical operating conditions were created by

opening both circuits of 400 kV Wangtoo - Jhakri D/C resulting in Karcham Wangtoo HEP being connected radially

only through Karcham Wangtoo – Abdullapur 400kV D/c (quad) line.

Since at the time of testing Baspa HEP generation was Nil, the running Units # 2 & # 4 at Wangtoo HEP were

loaded to 275 MW each (limited availability of water inflows). Thus in the antecedent conditions 400 kV Wangtoo

– Abdullapur D/C (quad) line was carrying 550 MW. Under this condition, the system was perturbed by manual

tripping of one circuit of 400 kV Karcham Wangtoo – Abdullapur D/C lines (from 400 kV Wangtoo end) such that

110 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

the entire 550 MW being generated by the running units is evacuated through the remaining line. The tests were

carried with and without PSS on the running units. PSS response both at the time of tripping of the line and at the

time of reclosing of the line was monitored.

The plot of R phase voltage-neutral voltage of 400 kV Wangtoo bus (with and without PSS in service on both the

running units) immediately after the tripping of 400 kV Wangtoo Abdullapur-I as recorded through the PMU at Wangtoo

is shown in below Figure 5-164.

Figure 5-164: R phase to Neutral voltage of Wangtoo 400 kV Bus

The PSS performance test results prima facie indicate that the damping of oscillations is better when PSS is in

service.

5.7. Monitoring of Natural disasters

5.7.1 Monitoring during Phailin Cyclone in Odisha

Date and Time : 12.10.2013, 21:26 Hrs

Data Used for Event Analysis : Talcher PMU

Overview: During this event PMU data helped in observing important tripping in Eastern region and southern

region which enabled the operator to have better situational awareness.

Event Description: At 21:26 hrs, very severe Cyclone Phailin categorized as very very severe cyclone had landfall

near Gopalpur in Odisha on 12.10.2013 night with a wind speed of 200 km / hr. causing severe damage to the

distribution network of SOUTHCO & CESU as well as transmission network of OPTCL in the southern & central region

of the State. Distribution network of NESCO had also been affected due to heavy rainfall and flood. Twenty six (26)

sub-stations and fourty five (45) EHT lines had gone out of service.

DECEMBER - 2013 POSOCO111

Synchrophasors - Initiative in India

Due to drastic load reduction in the State (Figure 5-165), major transmission lines & transformers tripped on over

voltage / over fluxing and could not be charged due to persisting high voltage since 05:50 Hrs.

Due to cyclonic effect demand of Odisha state reduced drastically with demand touching as low as 500MW at

around 18:30 hrs (at around the time of impact). Several 220 / 132 kV substations such as Berhampore, Chatrapur,

Narendrapur, Ganjam, Dighapahandi, Mohna, Aska, Bhanjanagar, Phulbani, Paralkhemundi, Akhusing, Kesura,

Nimapara, Khurda, Puri,nayagarh, Jaleshwar, Choudwar, Basta,dhenkanak, Bargarh, Rairakhol, Balugaon,

Purushottampur mostly along and near the odisha coast line suffered total outages. However, the cyclone did not

impact deeper into Odisha, but caused sgnificant damages to EHV and distribution system along and near Odisha

Coast. Many of the Grid substations were not muchimpacted and could be restored shor tly after the cyclonic

impact.

Odisha Demand met

Figure 5-165: Odisha Demand met during 03-Oct 2013 to 17-Oct-2013

Figure 5-166: Talcher PMU Positive sequence voltage, frequency & df/dt plots (17:00 to 18:00 hrs)

112 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 5-167: Positive sequence voltage, frequency plots of Talcher PMU (18:00 to 19:00 hrs)

Figure 5-168: Positive sequence voltage, frequency & df/dt plots of Talcher PMU (19:00 to 20:00 hrs)

Figure 5-169: Positive sequence voltage, frequency & df/dt plots of Talcher PMU (22:00 to 23:00 hrs)

DECEMBER - 2013 POSOCO113

Synchrophasors - Initiative in India

Figure 5-170: Positive sequence voltage, frequency & df/dt plots of Talcher PMU (23:00 to 00:00 hrs)

Figure 5-171: Positive sequence voltage, frequency & df/dt plots of Talcher PMU (00:00 to 01:00 hrs)

Figure 5-172: Positive sequence voltage, frequency & df/dt plots of Talcher PMU (01:00 to 02:00 hrs)

114 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Analysis: Talcher PMU plots were taken on hourly basis. These plots are stamped with various tripping mentioned

with the screen shots which improved situational awareness of the power system. Fig. 5-171 & Fig. 5-172 depicting

tripping of HVDC Talcher-Kolar pole II & Talcher-Kolar Pole I respectively. Fig. 5-172 Talcher PMU plot shows an

increase of frequency from 50.25 HZ to 50.41 HZ and further reduced to 49.57 HZ which depicted an SPS operation

due to tripping of Talcher-Kolar HVDC poles. In fig. 5-172 HVDC Talcher-Kolar Pole II & Pole I charging attempt taken

at 01:09 hrs & 01:16 hrs respectively on 13.10.2013. Finally HVDC Talcher-Kolar bipole got tripped at 01:19 hrs.

Immediately after the tripping of HVDC Talcher-Kolar Bipole, in order to avoid further fall in frequency, SR constituents

were advised to regulate the generation/Load.

5.7.2 Monitoring during fog condition in Northern Region

Date and Time : 17.12.2013, 18.12.2013 (Early Morning hours)

Data Used for Event Analysis : Meerut & Hissar PMU

Overview: During this event PMU data helped in observing important trippings in Northern Region which enabled the

operator to have better situational awareness.

Event Description: Northern Region power system has witnessed several incidents of multiple transmission lines

outage due to transient faults caused by line insulator flashover under dense fog conditions in the region during past

several years. This phenomenon has aggravated in recent years and can be attributed to all around increase in

pollution level. These trippings have the potential to cause blackout / brownout in large parts of the grid for several

hours.

It has been observed that such trippings mostly occur during mid-night and early morning hours (from 03:00 hrs to

08:00 hrs) when the atmospheric temperature is minimum and relative humidity is very high and conditions are

favourable for fog formation. Detailed investigation of the flashovers indicate that under dense foggy atmospheric

conditions, break down strength of the surface of the porcelain insulator reduces due to deposit of pollutant (soil dust,

fertilizer deposits, industrial emissions, fly ash and construction activities, etc) over it. Depending on the proximity to

highways and traffic, the wear of vehicles tyres also produces a slick, tar-like carbon deposit on the insulator surface.

Exhaust from the diesel vehicles also contribute in this phenomenon. In this event 18 lines (of 765 kV, 400 kV & 220

kV) tripped in Northern Region on transient fault due to dense fog conditions. The tripping of lines in midnight raised

an alarming situation and posed a serious threat to Grid Security. These trippings were mainly concentrated in areas

of Punjab, Haryana & western U.P.

DECEMBER - 2013 POSOCO115

Synchrophasors - Initiative in India

Figure 5-173 : Positive Sequence Voltage plots of Meerut and Hissar PMU (20:50-21:50 hrs)

Figure 5-174: Positive Sequence Voltage plots of Meerut and Hissar PMU (01:00-02:00 hrs)

116 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 5-175 : Positive Sequence Voltage plots of Meerut and Hissar PMU (02:15-03:15 hrs)

Figure 5-176: Positive Sequence Voltage plots of Meerut and Bassi PMU (Failed Autoreclose attempts of 400 kV Meerut-Muzaffarnagar)

DECEMBER - 2013 POSOCO117

Synchrophasors - Initiative in India

Figure 5-177: Positive Sequence Voltage plots of Moga and Bassi PMU (successful Autoreclose attempts of 765 kV Moga-Bhiwani)

Analysis: Meerut and Hissar PMU plots were taken on hourly basis. These plots are stamped with various tripping

mentioned with the screen shots which improved situational awareness of the power system. Figure 5-173, Figure 5-

176 depicting tripping.Trippings occurred at Meerut, Muzaffarnagar, Muradnagar, Roorkee, Kaithal and

Pankisubstations.Tripping of lines was being monitored closely and efforts were being made to gradually restore the

system. Several instances of Auto Recloses were also captured in the event. Northern Region constituents were

advised to regulate the generation/Load.

118 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

DECEMBER - 2013 POSOCO119

Synchrophasors - Initiative in India

EXPERIENCE ON UTILIZATION OF SYNCHROPHASOR TECHNOLOGY

Synchrophasor data has come out as an effective tool both for monitoring the grid in real time and for post event

analysis in offline mode. Synchrophasor Pilot projects taken up at all five RLDC’s and NLDC have raised visualization

and the level of understanding of the power system at the control centers within few months of its commissioning. It

has also enhanced situational awareness in real-time.

A number of real time events that have been detected using Synchrophasors would have gone un-noticed due to non-

availability of high resolution data in the conventional SCADA system. It has enabled the system operator to take

actions and mitigate the effects in real time. These monitoring are based on the standard visualization provided to the

system operator. The visualizations include voltage and current magnitude, angular difference, oscillation monitoring

engine, frequency and rate of change of frequency. Post event analysis has become effective as synchrophasor data

has given a new dimension to the analyst in finding more about the sequence of event and taking future preventive

action so that such event should be avoided. Currently various analytics module using synchrophasor data are being

developed based on the operator experience such as event detection and classification engine.

This section is on the collective information the user experience on the utilization of the synchrophasor data in

real time as well as offline mode.

6.1. Utilization of Synchrophasor data in real-time

The availability of Synchrophasor data at control center has become first-hand information for a grid operator to

view and analyze any transient phenomenon occurring in the grid. The system operator could also visualize the

cause of the disturbance from the typical ‘signature’ from trending of various power system parameters.The data

from the PMUs is very extensive and effective tools are required to use these data in real time grid operation. At

present there is a large difference in the extent of utilization of synchrophasor in real time when compared with its

offline utilization. The visualization of synchrophasor data at load dispatch center at regional and national level has

helped the operator in finding various issues related to system operation in real time. Some of the events were

monitored based on the following:

1. Excursion in Voltage and Current

2. Voltage and Current pattern

3. Angular separation

4. Oscillation observed in various power system parameters

5. Rate of change of frequency.

6

120 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

6.1.1. Events detected in real time:

PMUs have helped in real time monitoring of grid and visualization of events and helped operator in taking real time

action to improve the reliability of the grid.

6.1.1.1. Testing of damping controller at Bhadrawati HVDC B/B station

Figure 6-1 shows the synchrophasor voltage, current and frequency trend recorded during testing of damping

controller at HVDC Bhadrawati sub-station. The event was being monitored at Western region load dispatch center

by observing the synchrophasor units installed in AC bus at HVDC Bhadravati substation. The detailed analysis of

the event is discussed in section 5.5.2. The changes in voltage, current, frequency were being monitored in real

time. The voltage being monitored is of 400 kV Bhadravati Bus and currents are for 400 kV Bhadravati-Raipur #

2&3 respectively. A sudden drop in the current was observed due to tripping of one of the HVDC pole which was

immediately confirmed from the sub-station.

Figure 6-1 : Frequency Controller testing on Bhadrawati HVDC monitored using the Synchrophasor

6.1.1.2. Sudden reduction of generation

Figure 6-2 & 6-3 shows the sudden reduction in generation which were observed for 2 minutes at Unit#3 at Tehri

hydro station in Northern region and for 1 minute in unit#4 at Ramagundam Thermal station in Southern region.

DECEMBER - 2013 POSOCO121

Synchrophasors - Initiative in India

Figure 6-2: Current and MW plots of 400 kV Meerut-Muzaffarnagar

line during sudden reduction in power at Tehri Unit-III

Figure 6-3 : Current and MW plots of 400 kV RamagundamN’Sagar line during sudden reduction in power

at Ramagundam Unit-IV

6.1.1.3. Observation of Low frequency oscillations & Coherent group of generators

Synchrophasor have made it possible to visualize Low frequency oscillations occurring in the system in real time.

Low frequency oscillation gives an insight regarding the coherency of generators in the system. Figure 6-4 shows

the oscillation observed in Farakka PMU which got triggered due to tripping of generators in eastern region. The

values displayed are for Farakka Bus voltage, Farakka – Durgapur#1 real power and Farakka bus frequency.

Figure 6-4 : Oscillation observed in Farakka PMU on 20-11-2013 at 1244 hrs

122 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 6-5 : Oscillation and coherent group of generators observed from various PMU in Western Grid on 28-11-2013

Figure-6-5 shows the coherent group of generators located in eastern and western part of Western Grid. The event

which triggered the swinging of generators in these two areas is yet to be identified but for the system operator

having such a plot in real time gives enough warning that the system is being exposed to inherent stress. This

helps avoiding any nasty ‘surprises’. This plot reflects the stressed condition of lines connecting the eastern and

western part of the western grid.

6.1.1.4. Detection of fault

Figure 6.6 shows the detection of R-phase to earth fault in 220 kV Damoh-Tiamagarh transmission.

Figure 6-6 : Voltage, Current, frequency & rate of change of frequency plots

DECEMBER - 2013 POSOCO123

Synchrophasors - Initiative in India

6.1.1.5. Detection of non-operation of auto reclose in a transmission line

Figure 6-7 and 6.8 shows the 400 kV bus voltage of Bina and Satna substations respectively. It can be observed

that a transient fault had occurred in B-phase of 400 kV Indore-Indore (PG) line-1. The line did not auto-reclose

after 1 sec which is the dead time of auto reclose cycle. The transient fault was followed by tripping of 765 kV

Seoni-Bina on operation of over voltage protection.

Figure 6-7 : 400 kV bus voltage of Bina substation Figure 6-8 : 400 kV Satna bus voltage

6.2. Suggestions for Improved Visualization and Situational Awareness in real time

Synchrophasor Technology has facilitated the system operators in better situational awareness in real time grid

operation and offline post facto analysis. Although low lying fruits of Synchrophasor technology have been extracted

in different ways, still there is a big scope for improvements in the field of visualization and situational awareness.

At present some basic challenges are being faced by system operators are base lining of the system parameters,

automatic event triggering based on the set parameters and alarming etc. In this section a broad overview of all

the challenges being faced is presented.

6.2.1. Base lining of Voltage and Current plots for different voltage levels

Presently the Synchrophasors units have been installed mostly at 400kV buses at various EHV grid stations and

two units at 765 kV & 132 kV voltage level. The simultaneous visualization of all voltage levels in the same trend

chart may not be able to visualize the event properly. At present visualization of voltage magnitudes of different

voltage levels may not be more useful due to large difference in voltage levels. These voltage level on same plot

will not reflect any disturbances at lower kV voltage.

124 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 6-9 : Voltage of 132 kV and 400 kV Bus on actual scale

Figure 6-10 : Voltage of 132 kV and 400 kV Buses on p.u. scale.

Figure 6-9 & 6-10 depict the need for normalized voltage based visualization. The dynamics or switching events

observed in the lower voltage level will not be clear as the amplitude will not be reflected due to linear scaling as

shown in Figure 6-9. However when plotted on per unit (p.u.) scale as shown in Figure 6-10, the dynamics in 132

kV level can also be observed with same severity as observed at 400kV level. This helps in finding out the

sensitivity of any change in the system.

With rapidly upgrading Indian power system where in the near future a huge backbone of 765 kV network is

expected and with the planned addition of many more PMUs, with few on 765 kV level, accurate and prompt

visualization of all these different voltage level PMUs need to addressed.

DECEMBER - 2013 POSOCO125

Synchrophasors - Initiative in India

Similar to voltage visualization, a similar problem is expected with the current visualization scales wherein a high

value of current of any one monitored feeder may cause the scale to become quite high resulting in hiding the

sensitivity on lines having lower current level. The same can be solved by either selecting different MVA base for

different voltage level or having logarithmic plots.

Figure 6-11 : Visualization of measured currents for three different voltage level lines.

Figure 6-11 depicts a case where three circuits currents which are on three different voltage level. It can be easily

observed that the effect of any event can be visualized only on the feeder having a higher value of current. To

resolve this, current need to be represented in per unit equivalent. In order to address the issue, there is a need to

establish a base MVA value for all the voltage levels. Figure-6-12 shows the currents in per unit (p.u.), where

Base MVA for 400 kV is assumed as 500 MVA and for 132 kV as 20 MVA.

Figure 6-12 : Visualization of measured currents for three different lines in p.u.

126 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Another way may be visualizing the measured current on logarithmic scale. Figure 6-13 shows the plots of current

in logarithmic scale.

Figure 6-13 : Visualization of measured currents for three different circuits on a logarithmic scale.

6.2.2. Base lining of Angular difference between two distinct nodes

The essence of PMU measurement is the simultaneous angular difference between distinct nodes in the grid.

Angle measurements are relatively new in practice, the larger the phase angle difference between the source and

sink, the greater the power flow between those points. Greater phase angle differences imply larger static stress

across that interface; larger stress could move the grid closer to instability.Currently Real time Angle difference is

calculated at PDC and being displayed to real time operator.

Figure 6-14 : Angular visualization available at operator console

DECEMBER - 2013 POSOCO127

Synchrophasors - Initiative in India

Figure 6-14 shows the angular difference plot which is available at operator console. There is a need for base

lining of angular information so as to identify the alert state of operation based on angular separation. The angular

difference between various corridors varies based on the different events occurring in the system. PMUs pairs

need to be base lined which will help in defining the upper and lower limit for monitoring of these angles during

normal operation. This will act as a real tool for system operator to monitor the system stress.

By looking at the angular variation for three NR buses (Agra, Meerut & Moga) with respect to an ER bus (Farakka)

on a typical day, a trend is seen emerging. As is seen in Fig 6-15, during off-peak hours a high angular separation

is seen and during the morning and evening peak the angular separation reduces due to more hydro generation

availablity in NR.

Figure 6-15 : Angular variation of NR with respect to ER

This implies that in the cases of Inter regional flows (and flow across critical flow gates), it is possible to set limits

for the angles under different contingencies beyond which the system can be treated as ALERT mode and suitable

action can be initiated by the system operator.

6.2.3. Alarms based on event detection in real time

Synchrophasor has given ability to system operator to look into the event with information having milli-second accuracy.

For analyzing this fast rate data, better visualization is necessary for the system operator to sense any transient

phenomenon occurring in the system. For instance, the reaction time required for an operator to see changes in

phasor measurements and to take action may be too long. Additionally, the change may be so slight that it may be

unnoticeable to the naked eye. For these reasons, it is more efficient to automatically detect system events and

disturbances using synchronized phasor measurements.

128 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

The main challenge in feasibility of real-time automatic analytics and detection of power system disturbances is

interpreting huge chunk of synchronized data. Data mining tools to detect and classify events is the need of the

hour and research in this area is in progress throughout the globe. Automation in terms of developing simple

analysis tools would minimize the effor t put in manual tasks. Various alarms need to be integrated with the

visualization for the operator based on real time signal processing of the synchrophasor data. These alarms

should be based on the threshold provided by the operator for event detection. At present only the alarms have

been developed which get triggered when the parameters crosses the set threshold values.

The alarms can be based either on the set limit violation of any parameter or based on event detection. There is a

need to define certain threshold based on empirical observation of actual system events and evaluation of the

characteristics which a signal would exhibit before or during a disturbance. At the end of section 5.1 several type

of event have been characterized and based on this event detection algorithm and tools are under development to

identify different types of event.Few criteria which have been used for event detection application are as follows:

1. Voltage angle deviation: Voltage Angle deviation of ± 2-10o change over 1 second (25 samples)

will capture any tripping in the system or any changes in the load – generation balance. Voltage

angle is one of the main signal which helps in visualizing the stress on the grid. The analysis of

such angular deviation will provide insight into stability or alert signal for the operator.

2. Change in instantaneous voltage magnitude: If the voltage magnitude changes by 4-10 kV in

adjacent sample (4-10 kV in 1 sample) then this indicate transient conditions like faults, tripping,

etc.

3. Change in Voltage Magnitude for larger duration: This is to capture the faults which are present

for more than 200 ms. So a voltage change of 4-10 kV for 10 samples indicate clearing of fault by

back up protections.

4. Instantaneous Frequency: It is one of the best indicators to locate fault in the system. If frequency

varies by more than 0.4 Hz in adjacent sample then this could give an indication of the transient

condition like tripping or fault in the system.

5. Frequency change: If the frequency change in one second is around 0.1 Hz then this could give

an indication of load – generation imbalance in system.

6. Rate of change of frequency: A sudden change in ROCOF i.e. 0.02 Hz/sec in either direction

indicates an event in the system.

6.3. Visualization Improvement for faster event detection

It is essential to have good situational awareness through advance visualisation techniques. In such direction a

contour map for depicting the voltage profile throughout the Western Region is being developed in offline is shown

at Figure 6-16.

DECEMBER - 2013 POSOCO129

Synchrophasors - Initiative in India

Figure 6-16 : Contour visualization of WR MAP using PMU and SCADA data

A similar map is available at NLDC/NRLDC too which displays Voltage contour throughout the country with angular

difference between key nodes is shown in Figure-6-17. With the gradual increase in number of PMUs the contour

shall be fine-tuned with more data being made available giving a system operator an overview of the voltages and

angular difference across the country.

Figure 6-17 : Contour visualization of all India with angular differences

130 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

6.4. Utilization of Synchrophasor data in offline mode

Synchrophasor data has given a lot of insight into the system dynamics as discussed in the chapter 5. The

utilization of synchrophasor data in offline mode can be summarized in following points:

1. Fault classification

2. Fault recovery time and delayed clearance of fault

3. Characterization of fault nature based on DR and Synchrophasor data

4. Fault location

5. Low frequency oscillation and its analysis

6. Coherent group formation in the Indian grid

7. Benchmarking, validation and fine-tuning of dynamic models in system.

8. Validation of offline and EMS results with Synchrophasor measurements and EMS.

Along with the above availability of synchrophasor data has helped in faster analysis of the events. Synchrophasor

has helped in characterization of event as the time synchronized data can be aligned to find the root cause of the

event.

DECEMBER - 2013 POSOCO131

Synchrophasors - Initiative in India

The experience with Synchrophasors projects execution has been a roller coaster ride full of exhilaration and

excitement. Though the Synchrophasors data is presently available only from a few locations in the Indian grid,

yet it has dramatically raised visualization and the level of understanding of the power system at the control centre

within few months of its commissioning. It has now become an indispensable part of the data resource available

at the load dispatch centre. The three years of experience has revealed several challenges that need to be

addressed during the full-fledged project. These challenges and difficulties have been discussed below:

7.1. Implementation Experience in a Multi-vendor System

The Synchrophasor technology around the globe has moved from its nascent stage to the next level where it is

experimented with different protocols, is being discussed for a better Phasor estimation and communication. Thus

it can be said that synchrophasor technology is still evolving. Further, advanced applications based on Phasors at

a central level vis-à-vis a distributed architecture is also being discussed aggressively.

The C37.118 standard has upgraded from 2005 version to 2011 and the guide for PDC has been published i.e.

IEEEC37.244-2013 during the last couple of years. Equivalent IEC standard i.e, IEC 61850-90-5, is also picking up the

market and with most of the Substation Automation systems moving in this direction, this standard is expected to gain

more momentum. It is under these situations the Integration with Multi-Vendor system supporting different protocols

becomes a challenge. Typical vendor distribution in pilot projects is given in Table 7-1.

Table 7-1 Vendor Distribution

7.1.1 Multi-vendor PMU integration

A major challenge in using PMU data for application development is IEEE C37.118 data formats, supporting both

integer and floating point. Different vendors are using different algorithms for phasor estimation and reporting with

SI. No. PMU Vendor Quantity Installed

1 National Instruments 11

2 Siemens 10

3 SEL 39

IMPLEMENTATION EXPERIENCE & INTEGRATION CHALLENGES

7

132 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

in the IEEE C37.118 standards provision. In turn precision in number of digits after decimal points used by different

vendors for df/dt is in the range of three to ten. POSOCO has installed PMUs from multiple vendors. An analysis of

the rate of change of frequency (ROCOF), as observed, from three different vendors is illustrated in Fig 7-1. It can

be observed that all three have different level of accuracy and making alarms based on such different behaviour is

difficult, unless these values are normalized to a common scale.

Figure 7-1 : ROCOF from three different PMU vendors located in Western Regional Grid for tripping in Eastern Regional Grid

With multiple utilities installing PMUs for a large scale system (1800 PMUs as envisaged in proposed Unified Real

Time Dynamic System Monitoring in India), it is evident that implementer would have to source products from different

vendors/suppliers. Unlike with protective relays, where different relay products with different operating characteristics

and performance are sometimes preferred to avoid the same-mode failure, a PMU system requires a consistent

performance from all installed PMU units to meet its application requirements. For example, measured power

angles from different units must be within allowed error tolerance. Otherwise, the performance of the system will

be affected.

7.1.2. PMU Sync Errors and Troubleshooting

It has been observed that a good number of PMUs are out of synchronization for various reasons like GPS Antenna

position misalignment, non-visibility of satellites and problems in GPS receivers.

When the PMU has lost synchronization lock with GPS time source, it is required to detect a loss of time synchronization

that would cause the TVE to exceed the allowable limit, or within 1 min of an actual loss of synchronization, whichever

is less (IEEE Std C37.118.2-2011[B42], 4.5). In this case a flag in the PMU data output (STAT word Bit 13) should be

asser ted until the data acquisition is resynchronized to the required accuracy level. When the PDC detects a

synchronization error in the incoming PMU input, then the PDC reads bit 13 of status word of incoming PMU Data

frame, if it is set to 1, PDC displays incoming PMU as Sync Error.

DECEMBER - 2013 POSOCO133

Synchrophasors - Initiative in India

In addition to the STAT word Bit 13, IEEE Std C37.118.1-2011[B41] specifies further signals intended to describe

the time quality of the synchronization source. Each of the PMU output messages defined (Configurations 1, 2,

and 3, Header, and Data) have a time quality field of 4 bits. This field allows the PMU to state the quality of the

time source from clock locked, 1 ns to 10s uncertainty (estimated worst-case error), or clock failure. Figure 7-2

illustrates theclock unlocked with four time quality bits.

Figure 7-2 : Time Quality Flags in C37.118 Data Frame showing an unlocked clock status

Also, the Data message STAT word has two bits to indicate the length of time the clock has been unlocked. This

varies from locked to unlocked for more than 10s, 100s, or more than 1000s.

Even though a clock may be unlocked for over 1000s, a quality oscillator is able to maintain better that 1 μs accuracy

over this period. This field indicates the uncertainty in the measurement time at the time of measurement and

indicates time quality at all times, both when locked and unlocked, and unknown when the clock is starting up.

Further, In below Figure 7-3 , Time Synchronization status word bit is set 1, indicating the synchronisation is lost,

however the unlocked time is best quality, and the time quality flags also showing clock is locked. This may be

due to improper time stamping in the PMU or GPS problem.

Figure 7-3 : Time Quality Flags in C37.118 Configuration frame showing normal, locked clock

134 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

7.1.3. Sync Error due to Fraction of Second Drift

An interesting case found in one of the PMUs is a constant drift in the Fraction of Second (FOS), due to which the

quality of data was getting invalid. The time base in this PMU was noted to be 1000000 (as per relevant standards).

If a PMU is configured to report at 25 samples per second, then the FOS in C37.118 data frame is expected to

arrive as 0, 40000, 80000,….., 920000, 960000 (25 values for 1 second). But the time that was coming from the

PMU were 30, 40030, 80030, 920030, 960030 that was having a constant drift of 30 microseconds.

The PDC installed at WRLDC works in data sorting based on absolute time and expects an accuracy of 1 microsecond

or better in the PMU time stamps. If the accuracy in time stamp is less that 1 microsecond, the corresponding PMU

data will be flagged as “Data sort on arrival” instead of “Data sort on time stamp”, as per IEEE C37.118 standard. This

might be what has led to tagging the quality of the data arrived to be flagged as Unreliable.

Figure 7-4 : Fraction of Second (FOS) drift

7.2. Communication Challenges in Integrating PMU

It is an established fact that success of any WAMS implementation is primarily dependent on availability of a

dedicated and reliable communication system. The problem is compounded due the fact that PMUs are required

to be installed at generating stations & sub stations at remote locations and geographically spread over large

area. During the execution of pilot PMU projects in India at RLDCs/NLDC, establishing communication links/

channels between geographically remote substations having PMUs and regional control centers has been the

biggest challenge. Due to this, location of some of the PMUs either have to be re-located to different substation

having communication feasibility or use of corporate Wide Area Network where communication path is shared

with other applications thus compromising data reliability/latency. Data update rate adopted for all the projects is

25 samples per second (40 msec per sample). For such high rate of reporting, in general, dedicated fibre channel

are required for reliability of real time data. However, at some locations, implementation of fibre optic network is

still going on. Hence, PMUs at such locations have to be relocated to the sub stations where fibre optic

communication is already available or third party leased lines have been taken to integrate PMUs.

DECEMBER - 2013 POSOCO135

Synchrophasors - Initiative in India

However, major part of Synchrophasor data is being received at Regional Control Centers is through communication

system installed under ULDC scheme in year 2000. At that time, PDH technology was used for communication

equipment. In PDH, channels are separated by using hardware which uses G.703 and V.35 interface. But present

equipment used for networking system uses Ethernet interface. To solve this mismatch in interfaces, converters from

G.703 to Ethernet and V.35 to Ethernet converters were used. These converters require external power supply. Due to

this, though the converters could solve the issue of different interfaces but became a weak point due to need of

external power supply. In most of EHV substations Reliable Auxiliary power supply is available at 220V DC level, but

most of media converters are available at 230V AC or 48V DC Supply, in order to use reliable power supply to

interfacing equipment small universal supply adapters were used in most of the locations. Typically Universal Power

Supply modules having a capability to take inputs voltage range of 24VDC to 350VDC and 100 to 240V AC.

In some locations Optical to Ethernet converters are used, wherever the third party leased lines only the feasible

option.

Table 7-2 : Average Latency observed with different communication channels and PMUs

Each PMU Vendor is having different number of signals to be transmitted to PDC, an average latency of 600-700

ms latency is observed over 64 kbps channel, minimum of 512 kbps channels are recommended for PMU data

transmission.

Vendor 5 is has 1.5-1.6 times of latency over same communication channel due to latest version of Protocol

implementation for almost same number of signals.

Adequacy of communication infrastructure is one of the biggest challenges in executing the Synchrophasors

projects. In India, the availability of communication between the EHV substation and the Regional Load Despatch

Centre was one of the deciding factors for identifying the location of PMUs. Wherever Fiber optic links are available,

they have been used to transfer PMU’s data from respective station to control centre. Optical Fibre is being laid on

existing transmission lines all over the India to facilitate communication from EHV substations to Control centers

for Synchrophasors, Special protection schemes implementation, Grid Security Exper t System (GSES)

implementation, RTU data and voice connectivity etc.

1. Vendor 1 12 8 2 22 625 350 300

2. Vendor 2 6 32 2 40 - - 50

3. Vendor 3 12 - 2 14 - - 50

4. Vendor 4 18 4 2 24 - - 160

5. Vendor 5 13 3 2 18 - - 150

Phasor Analog Frequency Total 64 kbps 512 kbps 2 Mbps

Composition of Signals

Average Latency on

Communication Bandwidth

(in ms)SI. No. PMU Make

136 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

7.3. Synchrophasor data in Multi Cast

In existing projects, Synchrophasor streams are being transmitted using unicast packets to pre-defined receivers,

i.e Control Center PDCs as in these cases PMUs are reporting to only one PDC. However, in cases where PMU

measurement data is also required to transmitted to multiple PDCs simultaneously, unicast may over load

communication channels with multiple packets of same data. For such scenarios, multicasting is more suitable

method of data transmission.

Hence, it is preferable that PMUs also support multicasting. However, multicasting may also be implemented

through networking devices described in [B19] or Synchrophasors stream splitter given in [W6] in case PMUs are

not able to send data in multicast mode.

7.4. Challenges in handling of Synchrophasor data

Microsoft excel is used for plotting and analysing of Synchrophasor data. The versatility of XLS/XLSX would allow

it to continue to be the end applications for management presentation / analysis for some time. There is a

limitation with excel that only 35000 data points can be plotted. There is a need for data normalization to reduce

the data content over raw data extracted from Historians to screen the interested event data, robust algorithms are

needed to screen event data, after that, plotting of data to describe the event for analysis purpose.

7.4.1. Reliability of Synchrophasor data

Even with a healthy PMU in place, there had been instances of data losses due to communication link issues

between PMU and control center and synchronization loss at PMU, due to communication loss there is complete

loss of data from one or more location or sometimes intermittent data loss for shorter period, for example, an

application running all repor ted Synchrophasor data like OMS and Angle monitoring applications need to detect

such scenario, and have the capability to either discard un reliable data or handle these situations to avoid wrong

interpretations from results.

Sometimes data from PMU is being reported even after synchronization loss and time stamp error drift is more

than 1 minute, in such cases Application need to have intelligence to handle such type of situations

There are also some PMUs that don’t report any data to control center if its GPS synchronization is lost. The

common practice adopted at the PDC is to re-transmit the last received data, rather than making the measurement

null, to Historian and Visualisation. But then, the data needs to be read along with its quality information (13 Bit

STAT word) for its validity.

The invalid data handling is also tricky in case of applications like OMS, where this is treated as a discontinuous

signal and in turn making the solution not converging for an entire window length. Again, this is also posing a

challenge in Angle unwrapping calculations where if the invalid data is not handled would give rise to a wrapped

signal, giving an impression of Oscillation or Grid event.

7.4.2. Computation Challenges at Historian within 20ms

It is expected that, historian shall be able to do calculation on incoming data stream from PDC(phasor, analog

measurements), currently PMU to PDC reporting rate is 25 frames/seconds, so every 40 msec, there is a new

measurement available at PDC or historian , hence before arrival of next measurement, calculation output should

DECEMBER - 2013 POSOCO137

Synchrophasors - Initiative in India

be available to visualization or other application. So it is recommended to have execution speed better than 20

msec or better for 25 frames/second and for 50 frames/second system execution speed should be 10 msec or

better.

7.4.3. Calculation of Sequence Components at PDC level

Some of PMUs are reporting only three phase voltages and currents and some of the PMUS are reporting three

phases as well as positive sequence quantities but not reporting other sequence components to PDC. One of the

option is to calculate sequence components of voltages and currents at PDC. As long as number of PMUs are not

more, this option is acceptable but with deployment of large number of PMUs calculating components at PMUs

will be preferable option.

7.4.4. Synchrophasor Angle Measurement Unwrapping

In order to assess stress on grid, anglular difference between two distinct nodes is used. In similar lines angle

measurements from PMUs is used for monitoring grid condition. Synchrophasor supporting IEEE C37.118 standards

are reported over a range of ±π radians or ±180 degrees, hence they “wrap” at the end of the range limits which

is a discontinuous signal and need to be addressed properly. These discontinuities result in faulty analysis of grid

instabilities, especially when considering the angle difference between two separate locations on the grid.

Subtraction of two discontinuous angles results in a discontinuous signal.

If weare dealing with 4-5 PMUs Calculation of Angle difference using commonly available unwrapping algorithms

can solve the problem, but the problem becomes significant while dealing with missing data frames and handling

few thousands of PMUs. To illustrate the issue two distinct nodes are selected, and their reported absolute angles

are shown in Figure 7-5, and their angular difference is shown in Figure 7-6. Here the angle is converted in

between 0-360 degrees, still it need to be unwrapped using commonly available unwrapping algorithms.

Figure 7-5 : Korba and Bhadrawati reported Angles as per C37.118 Standard

138 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure 7-6 : Angle difference between Korba and Bhadrawati

Figure 7-7 : Reported Angles plot for missing

Bhadrawati PMU data

Figure 7-8 : Angular difference between Bhadrawati and KSTPS

in case of Missing Bhadrwati PMU data

It happens quite often that, sometime PDC may not receive some frames for various reasons, during this time

angle difference between two distinct nodes is illustrated below:

DECEMBER - 2013 POSOCO139

Synchrophasors - Initiative in India

Figure 7-9 : Reported Angles plot for missing

KSTPS PMU data

Figure 7-10 : Angular difference between Bhadrawati and KSTPS in

case of Missing KSTPS PMU data

Figure 7-7 and Figure 7-9 shows the reported angles from Bhadrawati and KSPTS (Korba) PMUs, and it can also

be seen that a few samples are missed in Bhadrawati PMU in first case and in later case, few samples are

missed in KSTPS PMU. Figure 7-8 and Figure 7-10 shows the Bhadrawati and KSPTS (Korba) PMUs angular

difference for the both cases. In both cases the error in angle difference is observed around 7.6º. Even though

there is no event, the angular difference plot shows an angle dip, it can create a wrong interpretation.

There were quite few attempts to solve the issue. The algorithms suggested in [B8] takes advantage of sequentially

measured data;it adds the difference from previous sample in the present unwrapped angle to create a smooth

angle stream which continuously increases or decreases depending upon frequency.

Solving the wrapping problem opens a wide scope for real time PMU applications while being helpful in offline

analysis as well as it is expected that, unwrapping algorithms should run in real time.

Further, selecting reference angle for calculation of relative angles is a complex issue; however following approaches

can be deployed based on operator experience:

1) Calculate Center of Inertia (COI), take nearby PMU as reference Angle.

2) Check df/dt for typical event; take nearby PMU Angle having highest df/dt PMU as reference.

3) Take generation rich area PMU angle as reference and calculate other load rich area relative angles.

7.4.5. Availability of APIs for Custom Application Development

The interfaces used by executable application modules to activate and interact with functions in the other executable

application modules are commonly referred as Application Program Interface (API), APIs to Historians and PDC are

required to develop custom availability reports for typical PMUs and stastical analysis on PMU Synchronization

loss and PMU communication availability etc.

140 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Currently C #, C++, .Net and Java API are very much required to develop applications related to event detection,

event analysis, Detection of cascading events and other third party applications.

PDC and Historian vendors needs to provide stable API so that external will have the freedom to change the

internals of the application without effecting interfaces to external applications.

7.5. Phasor Data recording and Exchange in COMTRADE Format

Nowadays it is widely accepted by many utilities all over world to exchange the synchrophasor data in COMTRADE

format for typical events. Schema for using the COMTRADE format for recorded phasor data is already released

its second edition by IEEE standards in association with IEC called as IEC 60255-24/IEEE C37.111 -2013[B43].

It still a question faced by utilities , whether PDC should generate recorded phasor data for power system events

or Historian should provide retrieval data for typical event from Historian.

However, it is advised have capability at both historian and PDC, to have run time event detection and localisation

algorithms.

7.6. Phasor Event Data Exchange in COMFEDE Standard.

IEEE Std C37.239-2010[B40] COMFEDE standard in India is not yet popularly adopted in Substation Automation

Systems, extension of this standard to Phasor domain is very much essential. This standard defines a common

format for the data files needed for the exchange of various types of power network events in order to facilitate

event data integration and analysis from multiple data sources and from different vendor devices. Since each

source of data may use a different proprietary format, a common data format is necessary to facilitate the

exchange of such data between applications. This will facilitate the use of proprietary data in diverse applications

and allow users of one proprietary system to use digital data from other systems. COMFEDE format is able to, at

least, hold the information related to:

1) Sequence of events (SOE) reports.

2) Fault summary reports.

3) IEC 61850 Logs.

Information from these reports can be stored natively in the COMFEDE format or be translated via a tool into

COMFEDE format.

Synchrophasors data are being widely reported in IEEE C37.118 standard, it is very much essential to combine

phasor data along with SOE and Fault summary reports and IEC 61850 logs to reconstruct timeline following a

disturbance event. Many PDCs and historians need to have a capability to either to export are retrive the phasor

data in COMFEDE format to facilitate event data integration and analysis from multiple data sources.

7.7. Compliance to IEEE C37.244 PDC Guide

IEEE Std C37.244.2013 [B45] guide has defined PDC functions to applied on Synchrophasor streams. Although all

functions are not mandatory and are voluntary in nature, it is advised to have following minimum functions to be

made compulsory for the national wide consistency implementation of WAMS technology.

1) Data aggregation

DECEMBER - 2013 POSOCO141

Synchrophasors - Initiative in India

2) Data forwarding

3) Data transfer protocol support and conversion

4) Data format and coordinate conversion

5) Data latency calculation

6) Reporting rate conversion (downsizing)

7) Output data buffering

8) Configuration

9) Phase and magnitude adjustment

10) Performance monitoring

11) Redundant and duplicate data handling

12) Data re-transmission request

13) Cyber security

7.8. Synchrophasor Data Storage related Experience and Challenges

Huge volume of synchrophasor data gets accumulated at the control center over a period of time. Presently installed

historian storage capacity is in the range of 4Tb to 10 Tb at control center level. With more number of PMUs being

planned to be installed, the capacity of historian needs to be increased and proper mechanisms need to be devised for

storage of data. Big data and data centre type technologies may need further feasibility studies are required. However

event based data storage is still a considerable option till permanent discontinuation of Existing SCADA.

Synchrophasor technology is dealing with time series data with high reporting rate. The amounts of data pushed

into database every second and to be retrieved are high. Historian software provides an algorithm for compressed

storage and quick retrieval of stored past values. One of the main challenges is on the resolution needed for the

retrieved data. For a data window of 5 mins, millisecond resolution of data would be desirable. For a data window

more than an hour, the data resolution may be in seconds and zooming in would require a resolution to be changed

to millisecond range.

7.9. Integration with SCADA State Estimator/EMS challenges

Some of the important characters of WAMS compared with SCADA are:

� High precision

� Synchronized measurements

� Fast rates of data communications;

� New metering types including bus voltage angle measurements and branch current angle

measurements.

In order to get the advantages of WAMS data for good visualization and State Estimation in SCADA, it is necessary

to integrate the same. Possibly till the complete SCADA is migrated to PMU measurements, these two technologies

will mutually co-exist. There are various ways to integrate WAMS data to SCADA and some are as under:

� ICCP

142 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

� IEC 690870-5-104

� FTP of Text/COMTRADE file

� Integration at Database level

Integration at ICCP level and IEC 104 level would fall under standards whereas FTP and DB integration are crude

method non-standards compromising security considerations. Also integration through latter method can be

considered for temporary period. For integration of WAMS with SCADA at ICCP or IEC 104 level. Modified IEC 104

integration through site adaption can be done with IEC 104 to IEC 101 conversion where SCADA supports only IEC

101.

Some of the important considerations related to Integration over IEC 60870-5-101/104 with SCADA:

1) Down sampling of phasor data to a level compatible to SCADA, i.e. Two (2) to ten (10) seconds

(Indian conditions – as per the present specifications).

2) Normally Analog measured are reported without time tag, but it can also report with time tag supported

in new gateways, if PDC supports Analog points with Time tag output, Time stamp mismatch problem

can be addressed.

3) Angle measurements from PMU are reported in -180 degrees to +180 degrees, need careful addressing

while down sampling in PDC and using in SCADA based applications.

4) The SCADA applications like State Estimation should be capable for phasor measurement input as

initial condition during solution

7.10. Challenges in Usage of Synchrophasor event Analysis

The availability of Synchrophasor data improves the ability to perform root cause analysis and enables thorough

and accelerate after-the-fact analysis following the various events that require reporting or operational analysis.

The resolution of the synchrophasor data is sufficient to reveal the details of dynamic system response and the

synchronized time stamps enable the easy determination of the true sequence of events.

Zero sequence, and negative sequence voltages and currents, phase angle differences between different nodes

etc. can be made available. But visualization of the available data is of key importance here, since to the real-time

operator only the necessary data must be made available. Remaining data may be useful for post-event analysis.

For example, in case of North-Eastern region, where PMUs are located at nodes at different voltage levels (400kV,

220kV, 132 kV), it is felt necessary to view the voltage data as L-L voltage on p.u. so that in case of any event or

in general it is possible to superimpose voltages of all the nodes which enhance visibility in real-time as also

enable faster post-event analysis. Choosing to view the voltage data as Line-Line instead of phase voltage is

preferred since in the Grid Code, the limiting voltages are specified in terms of L-L voltages and operators are more

accustomed to seeing voltages in those terms. Again limits are specified in p.u. of voltages based on different

voltage levels.

DECEMBER - 2013 POSOCO143

Synchrophasors - Initiative in India

With sixty numbers of PMUs installed throughout the country, the visibility of the power system state at sub-

seconds level has enhanced to a fair level. As discussed throughout this report in the case studies of using data

form the PMUs, it is evident that PMUs are extremely helpful in understanding the system to a greater detail

especially during transient and stressed conditions. During the implementation of these pilot projects, in a number

of cases the availability of communication has remained a constraint in locating the PMUs at desirable locations.

PMUs located at following strategic locations might have given more inner view of grid behavior:-

1. Wind energy generation complex.

2. At generating stations.

In view of the likely synchronisation of SR Grid with NEW grid forming it to be a synchronously operated system

of 125GW at present level, it is extremely necessary to develop high amount of confidence in synchrophasor

technology. Some of the immediate area of applications could be as under

� Real time monitoring of Frequency Response Characteristics (FRC) of control area

� Control Area load and Generation Dynamics for effective modelling in offline simulations

� Net Drawls/injections calculations of Control area using PMU data

� Enhancing State estimation with PMU input as initial condition

� Oscillation Monitoring

� Load angle gradient across the entire country

As more synchrophasor measurements are available, the applications can also be extended to the area of Operational

Planning and to have a realistic assessment of the transfer capability of the network.

For ensuring safety, security of Indian power system and steps towards intelligent and self-healing grid deployment

of WAMS technology has been envisaged in report of working group of power for 11th plan.

Power Grid Corporation of India Ltd. is coming up with a full fledge project named”Unified Real Time Dynamic

State Measurement” (URTDSM), for deployment of WAMS technology over wide scale in Indian EHV Grid, which

WAY FORWARD

8

144 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

involves installation of PMUs, PDCs and fibre optic communication infrastructure. Project aims for installing about

1700 nos Phasor Measurement Units and 30 Phasor Data Concentrators in Indian power system. It is envisaged

to develop following analytics under URTDSM in association with IIT, Mumbai:-

1. Line Parameter Estimation

2. Online vulnerability Analysis of Distance relays

3. Linear/Dynamic State Estimator

4. CT/CVT Calibration

5. Supervision of Zone-3 distance protection

6. Control Schemes for improving system security

DECEMBER - 2013 POSOCO145

Synchrophasors - Initiative in India

Published Papers

R1. S.K. Soonee, S.R. Narasimhan, R.K. Porwal, S. Kumar, R.Kumar, V. Pandey, “Application of phase anglemeasurement for real time security monitoring of Indian Electric Power System- An Experience”, SC C2-107, CIGRE Session 2008, August 2008

R2. V. K. Agrawal, P. K. Agarwal, R. K. Porwal, R. Kumar, Vivek Pandey T. Muthukumar, Suruchi Jain "OperationalExperience of the First Synchrophasor Pilot Project in Northern India" CBIP- 5th International Conference onPower System Protection and Automation, 6-9 Dec 2010.

R3. P. Pentayya, Abhimanyu Gartia, Samit Kurmar Saha, Rajkumar A, Chandan Kumar, “Synchrophasor basedApplication Development in Western India”, In IEEE PES ISGT Asia Conference, Bangalore, 10-13 November2013.

R4. T. Muthu Kumar, P. R. Raghuram, S.P. Kumar, “Operational experience of synchrophasor pilot project inSouthern India”, IEEE PES ISGT Asia 2013, Bangalore, India 10-13 November 2013

R5. P. Pentayya, Abhimanyu Gar tia, Rajkumar A, Chandan Kumar, “Comparative Analysis of Low FrequencyOscillations Using PMU and CPR-D Relay- A Case Study”, In 5th International Conference of Power andEnergy System Conference, Kathmandu, 28-30 October 2013.

R6. P. Pentayya, Abhimanyu Gartia, Pushpa Seshadri, Rajkumar A, Chandan Kumar, “Low Frequency Oscillationsin Indian Grid”, In 5th International Conference of Power and Energy System Conference, Kathmandu, 28-30October 2013.

R7. R. K. Pandey, P. Pentayya, Abhimanyu Gar tia, Rajkumar A, Chandan Kumar, “Operational ReliabilityEnhancement with PMUs in Indian Power Network”, In IEEE CATCON Conference, Kolkata, 6-8 December2013.

R8. P. Pentayya, P. Mukhophadhaya, S. Banerjee, M K Thakur, “A simple and efficient approach for optimalplacement of PMU” in NPSC 2010

R9. Rajiv Kumar Porwal, V. V. Sharma, Vivek Pandey, T. Muthukumar "Application of Synchrophasors in GridEvent Analysis" CIGRE Symposium, Lisbon, April 2013.

R10. V.K. Agrawal, P.K. Agarwal and Harish Rathour “Application of PMU Based Information in Improving thePerformance of Indian Electricity Grid” 17th NATIONAL POWER SYSTEMS CONFERENCE, 12th-14th December,2012, Department of Electrical Engineering, Indian Institute of Technology (BHU), Varanasi – 221005 UttarPradesh, INDIA.

R11. V.K. Agrawal, P.K. Agarwal and Rajesh Kumar “Experience of Commissioning of PMUs Pilot Project in theNorthern Region of India” 16th NATIONAL POWER SYSTEMS CONFERENCE, 15th-17th DECEMBER, 2010,Department of Electrical Engineering, University., College of Engineering., Osmania University, Hyderabad,A.P, INDIA.

R12. V.K. Agrawal and P.K. Agarwal “Challenges faced and Lessons Learnt in Implementation of firstSynchrophasors Project in the Northern India”, GRIDTECH 2011, 19-20 April 2011, New Delhi, India.

R13. V.K. Agrawal and P.K. Agarwal “Synchrophasors Measurements A Paradigm Shift in Power System SCADA”IEEE SPONSORED NATIONAL CONFERENCE ON ELECTRICAL POWER & ENERGY SYSTEMS, 20/21-Sep-2013, Ghaziabad, India

REFERENCES

146 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

R14. V.K. Agrawal, P.K. Agarwal and Harish Rathour “Experience of Up-scaling and Integration of Regional LevelSynchrophasors Pilot Projects to a National Level Project” GIGRE SC D2 Colloquium, 13-15 November2013Mysore, Karnataka, INDIA.

Bibliography

B1. A. G. Phadke, J. S.Thorpe, “Synchronized phasor measurements and their applications”, Springer 2008.

B2. A.G. Phadke, “Synchronized phasor measurement in power system”, Computer Applications in Power,IEEE, vol. 6, no. 2, pp. 10,15, April 1993.

B3. Y Hu, D.Novosel,”Challenges in Implementing a Large Scale PMU System”, International conference onPower System Technology, 2006.

B4. Midwest ISO, “Midwest ISO PMU Placement Approach Whitepaper”, Version 1, 18 August 2010

B5. K. Narendra, T. Weekes, “Phasor Measurement Unit Communication Experience in a Utility Environment”,Conference on Power Systems Winnipeg, Cigre, Oct 19-21, 2008.

B6. Midwest ISO, “Synchrophasor Integration into Planning and operational reliability processes”, Version 1, 12March 2010.

B7. Tate J. E., Overbye T. J., “Line outage detection using phasor angle”, IEEE transactions on power systems,2007.

B8. OSIsoft, LLC (San Leandro, CA), “Unwrapping Angles from Phasor Measurement Units”, US Patent:US8497512B1 June 2013.

B9. J. C-H. Peng, N. C. Nair, “Effects of sampling in monitoring Power System Oscillations using Online PronyAnalysis”, Australasian Universities Power Engineering Conference, 2008.

B10. M. Balabin, K. Gorner, Y. Li, I. Naumkin and C. Rehtanz, “Evaluation of PMU performance during transients”.Power System Technology (POWERCON), 2010

B11. Khatib A. R., Nuqui R.F, Ingram M.R, Phadke A. G, “Real time estimation of security of voltage collapseusing synchronized phasor measurements”, IEEE Power Engineering Society General Meeting, 2004 vol.,no., pp 582-588

B12. Chenine M, Vanfretti L, Bengtsso S, Nordstroum L, “Implementation of an experimental wide-area monitoringplatform for development of synchronized phasor measurement applications,” Power and Energy SocietyGeneral Meeting, 2011 IEEE , vol., no., pp.1,8, 24-29 July 2011

B13. N. Strath, “Islanding Detection in Power Systems”, Dissertation, Lund University, Sweden

B14. A. Mazloomzadeh, M. Cintuglu, O. Mohammed, “Islanding detection using synchronized measurements insmart micro grids”, IEEE 2013.

B15. US-Canada Power system outage task force, final report on August 14 2003 black out in USA and Canada,pp -104-107, April 2004.

B16. Gardner R, “A wide area perspective on power system operation and dynamics,” PhD dissertation, VirginiaPolytechnic Institute, 28 March 2008.

B17. Venkatasubramanian Mani, Liu Xing, Liu Guoping, Zhang Qiang and Sherwood Michael, “Overview ofwide area stability monitoring algorithms in power systems using Synchrophasors”, 2011 American controlconference, San Fransisco, June 29-July 01, 2011.

B18. G. Liu, J. Quintero, Venkatsubramanian M.V, “Oscillation monitoring system based on wide areasynchrophasors in Power systems”, Bulk Power System Dynamics and Control – VII. Revitalizing OperationalReliability, 2007 iREP Symposium, pp. 1,13 ,19-24 Aug. 2007.

DECEMBER - 2013 POSOCO147

Synchrophasors - Initiative in India

B19. Cisco, “PMU networking in IP multicast”, 2012 [Available at www.cisco.com/en/US/prod/collateral/routers/ps10967/ps10977/whitepaper_c11-697665.pdf]

B20. Jaime De La Ree, Virgilio Centono, James S. Thorp, A. G. Phadke, “Synchronized Phasor MeasurementApplications in Power Systems”, IEEE Transactions on Smart Grid, vol 1, no. 1 pp. 20-27, June 2010.

B21. D. Novosel, Khoi V., “Benefits of PMU technology for various applications”, International council on LargeElectric Systems – Cigre 7th symposium on Power System Management 2006.

B22. T. Hashiguchi, H. Ukai, Y. Mitani, M. Watanabe, O. Saeki and M. Hojo, “Power System Dynamic Performancemeasured by Phasor Measurement Unit”, IEEE PowerTech 2007.

B23. I. Kamwa, R. Grondin, “PMU configuration for system dynamic performance measurement in large multiareapower systems”, Power Systems, IEEE transactions, vol 17, no. 2, pp. 385,394, May 2002.

B24. Verma S.C, Nakachi Y, Wazawa Y, Kosaka Y, Kobayashi T, Omata K, Takabayashi Y, “Short circuit currentestimation using PMU measurements during normal load variation,” Innovative Smart Grid Technologies(ISGT Europe), 2012 3rd IEEE PES International Conference and Exhibition, vol. 1, no. 5, pp 14-17, Oct. 2012.

B25. Q Jiang, X Li, B Wong, “PMU based fault location using voltage measurements in large transmissionnetworks,” Power Delivery, IEEE Transactions, vol. 27, no. 3, pp 1644,1652, July 2012.

B26. T. Overbye, C. DeMarco, M Venkatasubramanian, “Using PMU data to increase situational awareness”,PSERC Publication, Sept. 2010.

B27. Powalko M, Komarnicki P, Rudion K, Styczynski Z, “Improving power system observability with PMUs”,Science and Technology, 2011 EPU-CRIS International Conference, Vol. 1, no. 6, pp. 16, Nov 2011.

B28. Adamiak Mark, Premerlani William and Kasztenny Dr. Bogdan “Synchrophasors: Definition, Measurement,and Application”, retrived on December 11,2013 [Avaliable at www.gedigitalenergy.com/SmartGrid/Sep06/Synchrophasors_Paper.pdf]

B29. California ISO Five Year Synchrophasor Plan - 2011, retrieved on December,11,2013, [Available atwww.caiso.com/Documents/FiveYearSynchrophasorPlan.pf]

B30. K. Seethalekshmi, Singh S.N. and Srivastava S.C. Wide-Area Protection and Control: Present Status andKey Challenges , National Power Systems Conference (NPSC), 2008.

B31. Lawrence Berkeley National Laboratory, Real Time Grid Reliability Management, California EnergyCommission, 2008, retrived on December 11, 2013 [Avaliable at www.energy.ca.gov/2008publications/CEC-500-2008-049/CEC-500-2008-049.PDF]

B32. Mills-Price Michael and Flerchinger Bill, Smart Anti-Islanding Using Synchrophasor Measurements, successstory, NASPI, retrived on December 11, 2013 [Avaliable at www.naspi.org/File.aspx?fileID=572]

B33. NASPI Guidelines for Siting Phasor Measurement Units. NASPI, June- 2011, retrived on December 11,2013.[Avaliable at www.diva- portal.org/smash/get/diva2:482602/FULLTEXT01.pdf]

B34. NERC Real-Time Application of Synchrophasors for Improving Reliability - 2010, retrived on December11,2013 [www.nerc.com/docs/oc/rapirtf/RAPIR%20final%20101710.pdf].

B35. Parashar Manu, Dyer Jim and Bilke Terry, “EIPP Real-Time Dynamics Monitoring System”, retrived onDecember 11,2013 [Avaliable at www.certs.lbl.gov/pdf/eipp-r t.pdf]

B36. Prasertwong K, Mithulananthan N. and Thakur D, “Understanding low frequency oscillation in powersystems”, IJEEE, UK, June 2009

148 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

B37. David G. Hart, David Uy, Vasudev Gharpure, Damir Novosel, Daniel Karlsson, Mehmet Kaba, “PMUs – Anew approach to power network monitoring”, [White paper] retrived on December 11,2013 [Avaliable atwww.05.abb.com]

B38. IEEE Std C37.118™-2005, IEEE Standard for Synchrophasors for Power Systems.

B39. IEEE Std C37.242™-2013, Guide for Synchronization, Calibration, Testing, and Installation of PhasorMeasurement Units (PMU) for Power System Protection and Control.

B40. IEEE Std C37.239™-2010, IEEE Standard for Common Format for Event Data Exchange (COMFEDE) forPower Systems.

B41. IEEE Std C37.118.1™-2011, IEEE Standard for Synchrophasor Measurements for Power Systems.

B42. IEEE Std C37.118.2™-2011, IEEE Standard for Synchrophasor Data Transfer for Power Systems.

B43. IEC 60255-24/IEEE C37.111 -2013, IEEE/IEC Measuring relays and protection equipment Part 24: Commonformat for transient data exchange (COMTRADE) for power systems.

B44. IEEE Std C37.238™-2011, IEEE Standard Profile for Use of IEEE 1588™ Precision Time Protocol in PowerSystem Applications

B45. IEEE Std C37.244™-2013, IEEE Guide for Phasor Data Concentrator Requirements for Power SystemProtection, Control, and Monitoring.

B46. J. Machowski, J.W. Bialek, J.R. Bumby, “Power system dynamics-stability and control”, October, 2008,second edition, wiley publication.

B47. Siemens, PSS/E user manual, version 32.0

B48. P. Kundur, “Power system stability and control”, McGraw Hill Inc., New York, 1994.

Websites

1. “Tennessee Valley Authority (TVA) free PMU connection Tester Program”,www.phasors.pnl.gov

2. www.naspi.org

3. “Washington State University GridStat”, www.gridstat.net/trac

4. “Electricity Infrastructure Operations Center (EIOC)”, www.eioc.pnnl.gov/research/synchrophasor.stm

5. “Bonneville Power Administration Transmission, Services”, www.transmission.bpa.gov/orgs/opi/system_news/index.shtm

6. “Grid Protection Alliance”, www.gridprotectionalliance.org

7. www.selinc.com/synchrophasors

8. www.gedigitalenergy.com/multilin/index.htm

9. http://www.macrodyneusa.com

10. LinkedIn Group: Synchrophasors and WAMS

11. Yahoo Group: group.yahoo.com/group/RLDCs_SystemOperation_India

DECEMBER - 2013 POSOCO149

Synchrophasors - Initiative in India

S.No. Description Details pertaining to

ERLDC NERLDC NRLDC SRLDC WRLDC NLDC

1 Make/Model Siemens Phase-I: SEL-700G NI cRIO SEL-700GSyprotec SEL-700G SEL 451, -90246MD85 SEL-487B

Phase-II:SEL-700G

2 AC current input 1A 1A 1A 1A 1A 1A

3 AC Voltage input 110V 110V 110V 110V 110V 110V

4 Measurement Voltage & Voltage & Voltage & Voltage & Voltage & Voltage &Current Current Current Current Current Current

phasors, phasors, phasors, phasors, phasors, phasors,MW,MVAR, MW,MVAR, MW,MVAR, MW,MVAR, MW,MVAR, MW,MVAR,Frequency Frequency Frequency Frequency Frequency Frequencyand df/dt and df/dt and df/dt and df/dt and df/dt and df/dt

5 Sequence Positive Positive Positive Positive, Positive, Positivevoltages and sequence sequence sequence negative negative sequencecurrents of voltage of voltage of voltage and zero and zero of voltage

and current and current and current sequence sequence and currentof voltage of voltages,

and current positivesequenceof current

6 Number of 8 8 8 8 8 8digital inputs

7 No. of Analog 1 set of 1 set of 2 set of 1 set of 1 set of 2 set ofinputs 3 Ph 3 Ph 3 Ph 3 Ph 3 Ph 3 Ph

Voltages & Voltages Voltages Voltages Voltages Voltages2 sets of & 2 sets of & 2 sets of & 2 sets of & 2 sets & 2 sets

3 Ph 3 Ph 3 Ph 3 Ph of 3 Ph of 3 PhCurrents Currents Currents Currents Currents Currents

8 Communication C37.118- C37.118- C37.118- C37.118- C37.118- C37.118-Protocol 2005 2005 2005 2005 2011 2005

9 Data repor ting 10/25/50 10/25/50 10/25/50 10/25/50 10/25/50 10/25/50rate (Frames/Sec)

10 Time reference IRIG-B IRIG-B IRIG-B IRIG-B MCX IRIG-Bsource interface

of GPS

11 GPS accuracy ±1 μs ±100 ns ±100 ns ±100 ns ±100ns ±100 ns

12 Local data storage No No No No No No

Appendix-ATable A-1: Phasor Measurement Unit Details

150 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Table A-2: Phasor Data Concentrator System

Sl.No Description ERLDC NERLDC NRLDC SRLDC WRLDC NLDC

1 Make/Model Siguard- SEL-5073 SEL-3378 SEL-5073 Kalkitech SEL-5073PDP ver3.0 SYNC 4000

2 No. of PMUs that 100 200 20 200 100 200can be integratedto PDC

3 Data Transmission TCP&UDP TCP&UDP TCP&UDP TCP&UDP TCP&UDP TCP&UDP(TCP or UDP)

4 Protocol C37.118- C37.118- C37.118- C37.118- C37.118- C37.118-Suppor ted 2005 and 2005 2005 2005 2005 and 2005

2011 2011

5 Other Protocols ICCP,OPC IEC-60870- IEC-60870- IEC-60870- IEC-60870- IEC-60870-Suppor ted 5-104,OPC 5-104 5-104 5-104,OPC 5-104,OPC

6 Facility to Monitor Yes Yes Yes Yes Yes YesInput and outputTraffic

7 Support of dual No Yes Yes Yes No Yescommunicationchannels forindividual PMU

Table A-3: Historian Details

Sr.No Description ERLDC NERLDC NRLDC SRLDC WRLDC NLDC

1 Make/Model Siemens SEL-5078-2 SEL-5078-2 SEL-5078-2 eDna, SEL-Sigurad Instep 5078-2

PDP

2 Web services No Yes Yes Yes Yes Yessupport

3 Data storage 1.8 TB 2 TB 2TB 1.6 TB 4 TB 9 TBCapacity

4 History Data Yes Yes Yes Yes Yes Yesvisualization

5 Availability of APIs No No No No C, .NET & NoVB

6 Data protocol IEEE IEEE IEEE IEEE IEEE IEEEfrom PDC C37.118 C37.118 C37.118 C37.118 C37.118 C37.118

7 Alarms Yes Yes Yes Yes Yes Yes

8 Play back feature Yes No No No Yes No

DECEMBER - 2013 POSOCO151

Synchrophasors - Initiative in India

Table A-4: Visualization Features

Sl. No. Description ERLDC NERLDC NRLDC SRLDC WRLDC NLDC

1 Frequency Yes Yes Yes Yes Yes Yes

2 Rate of change Yes Yes Yes Yes Yes Yesof frequency

3 Delta Frequency Yes Yes Yes Yes Yes Yes

4 Phasor magnitude Yes Yes Yes Yes Yes Yes

5 Phasor angle Yes Yes Yes Yes Yes Yes

6 Sequence Yes Yes Yes Yes Yes Yescomponents

7 Angular separation Yes Yes Yes Yes Yes Yes

8 MW Yes Yes Yes Yes Yes Yes

9 MVAR Yes Yes Yes Yes Yes Yes

10 Digital Yes Yes Yes Yes Yes Yes

11 Modal analysis information Yes Yes Yes Yes Yes Yes

12 Screen Refresh rate 1sec 1sec 1sec 1sec 1sec 1sec

13 Historical/Real Time Trend Yes Yes Yes Yes Yes Yes

14 Trend period 10 sec to 1 sec to 1 sec to 1 sec to 1 sec to 1 sec to1 month 1 year 1 year 1 year 1 year 1 year

15 Contour plots Yes Yes Yes Yes No Yes

16 LFO modes trending Yes Yes Yes Yes Yes Yes

17 Event/Alarm Display Yes Yes Yes Yes Yes Yes

18 Polar Chart Yes Yes Yes Yes Yes Yes

Visualizationof parameter

152 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Appendix-BTable B-1: Location of PMUs in Eastern region

SEL

S.No. PMU Location PMU Make Current Feeders Voltage Measuredconnected to PMU by PMU

1 Binaguri Purnea-3, Tala-3 Bus Selection PT

2 Biharshariff Balia-1, Kahalgaon-1 Bus Selection PT

3 Patna Balia-1, Barh -1 Bus Selection PT

4 Rourkela Raigarh-2 , Talcher-1 Bus Selection PT

5 Jeypore Bolangir, Indravati Bus Selection PT

6 Durgapur Maithon-2, Jamshedpur Bus Selection PT

7 Rengali Talcher-2, Baripada Bus Selection PT

8 Sasaram Biharsharif-2 , Allahabad Bus Selection PT

9 Farakka Durgapur-1, Kahalgaon-1 400 kV Bus 1, 2

10 Talcher Rengali-2, Meramundalli-1 400 kV Bus 1, 2

11 Ranchi Sipat-1, Maithon-1 400 kV Bus 1, 2

12 Jamshedpur Rourkela-1, Maithon-1 400 kV Bus 1, 2

Siemens

Table B-2: Location of PMUs in North Eastern Region

S.No. PMU Location PMU Make Current Feeders Voltage Measuredconnected to PMU by PMU

1 Balipara Misa-1, Bongaigaon-1 400 kV Bus-1

2 Sarusajai Samaguri-2, Agia-2 220 kV Bus-1

3 Badarpur Kumarghat , Khleirihat 132 kV Kumarghat,Khleirihat CVT

4 Imphal Dimapur, Loktak-2 132 kV Main Bus PT

5 Agar tala B J Nagar-1, RCNagar-1 132 kV Main Bus PT

6 NEHU Sumer, Khlerihat 132 kV Main Bus PT

7 Bongaigaon Balipara-1, Balipara-2 400 kV Balipara-2 Line CVT

8 Misa Dimapur-2, Kopili-2 220 kV Dimapur-2 &Kopili-2 CVT

SEL

DECEMBER - 2013 POSOCO153

Synchrophasors - Initiative in India

Table B-3: Location of PMUs in Northern region

S.No. PMU Location PMU Make Current Feeders Voltage Measuredconnected to PMU by PMU

1 DADRI Inter-connecting lines Dadri 400 kV Bus 1AC and HVDC S/s

2 KANPUR Ballabgarh-1 400 kV Bus 1

3 MOGA Bhiwadi-1 400 kV Bus 1

4 AGRA - 400 kV Bus-1, 2

5 VINDHYACHAL Singrauli-1 400 kV Bus 1

6 HISSAR Bawana 400 kV Bus-1, 2

7 BASSI Agra-1, Agra-2 400 kV Bus-1, 2

8 K'WANGTOO Abdullapur 1, Abdullapur2 400 kV Bus-1, 2

9 KISHENPUR Moga-1, Moga-2 400 kV Bus-1, 2

10 MEERUT Muzaffarnagar, Koteshwar 400 kV Bus-1, 2

11 BALIA HVDC interconnector(AC) I,II 400 kV Bus-1, 2

12 RIHAND HVDC interconnector(AC) I,II 400 kV Bus-1, 2

13 BAWANA Mandola, Mahendragarh 400 kV Bus-1, 2

14 MOHINDERGARH Dhanonda 1, Bhiwani 1 400 kV Bus-1, 2

SEL

Table B-4: Location of PMUs in Southern region

S.No. PMU Location PMU Make Current Feeders Voltage Measuredconnected to PMU by PMU

1 Ramagundam Nagarjunsagar-2, Chandrapur-1 400 kV Bus-1

2 Somanhalli Salem, Gooty 400 kV Bus-1

3 Narendra Guttur-1,Kaiga-1 400 kV Bus-1

4 Vijaywada Nellore-1,VTPS-1 400 kV Bus-1

5 Sriperumbadur Chitoor, Kolar 400 kV Bus-1

6 Trichur Palakkad-1,Bus-1 extension CT 400 kV Bus-1

7 Gazuwaka Vijaywada,Shimhadri-1 400 kV Bus-1, 2(South Bus)

8 Gooty Raichur-1,Nelmangala 400 kV Bus-1, 2

9 Tirunlelveli Trivendrum-1,Udumalpet-2 400 kV Bus-1, 2

10 Kolar Hoody-1,Sriperumbdur 400 kV Bus-1, 2

SEL

SIEMENS

154 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Table B-5: Location of PMUs in Western region

S.No. PMU Location PMU Make Current Feeders Voltage Measuredconnected to PMU by PMU

1 Boisar Phadge, Tarapur-2 400 kV Bus-1

2 Dehgam Gandhar-2, Pirana-2 400 kV Bus-1

3 Bhadravathi Raipur-2, Raipur-3 400 kV Bus-1

4 Solapur Kolhaur-1, Parli-1 400 kV Bus-1

5 Itarsi jabalpur-2, Indore-2 400 kV Bus-1

6 Satna National Bina-3, Vindyachal-3 400 kV Bus 1Instruments

7 Raipur SEL Korba-3, Raigarh-1 400 kV Bus-1,2

8 Jabalpur SEL Itarsi-2, Vindyachal-4 400 kVBus-1,2

9 Mundra Dehgam-2, Hadala 400 kV Bus-1

10 Bina MP Bina(PG)-1, Bhopal-1 400 kV Bus-1

11 Korba Bhatapara, GT-6 400 kV Bus-2

12 Vindyachal Jabalpur-1, Korba-1 400 kV Bus-1

13 CGPL Mundra Limbdi-2, GT-4 400 kV Bus 2

14 Lab PMU,WRLDC Lighting Feeder WRLDC 3-Phase Supply 400V

15 Kalwa Phadge-II, Kharghar 400 kV Bus-1,2

16 Asoj Indore-1 400 kV Bus-1

Table B-6: Location of PDCs all over India

S.No. Northern Southern Western Eastern North Eastern CentralRegion Region Region Region Region PDC

1 NRLDC SRLDC WRLDC ERLDC NERLDC NLDC(New Delhi) (Banglore) (Mumbai) (Kolkata) (Shillong) (New Delhi)

2 WRLDC BinaguriMumbai)(Lab PDC)

3 Biharshariff

4 Rourkela

5 Sasaram

NationalInstruments

SEL

Siemens

NationalInstruments

DECEMBER - 2013 POSOCO155

Synchrophasors - Initiative in India

Appendix-C

C.1 Operator Console Displays

Various customized displays have been made for providing situational awareness on the grid at each

control center. These displays include frequency, df/dt, sequence voltages, sequence currents, phase

voltages, phase currents and low frequency modes existing in the system.

C.1.1 Western Region

The displays for system operator were developed in eDna Historian visualization software. Customized

displays such as trend displays and dial displays are developed for system operators. The Figures (C1-C5)

shown below are used as visualizations for system operators. Visualization has the option to check the

reliability of the data received from PMUs. Below the visualization trend there is an option to retrieve the

current and historical data immediately. The retrieved data can be expor ted to excel sheet for fur ther

analysis. In visualizations positive sequence, negative sequence and zero sequences of voltages and

currents can be seen to detect what type of fault has been happened. There is also a trend in visualizations

displaying individual signals measured by individual PMU. In OMS visualization the dominant low frequency

mode can be seen. The dominant modes frequency and damping ratios are displayed in this window. The

df/dt trend and frequency trend helps in detecting events happened in the system.

Figure C-1 : Geographical locations of PMUs and Communication status

156 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure C-2 : Visualization of Frequency at WRLDC

Figure C-3 : Visualization of Voltage magnitudes at WRLDC

DECEMBER - 2013 POSOCO157

Synchrophasors - Initiative in India

Figure C-4 : Visualization of Current magnitudes at WRLDC

Figure C-5 : Visualization of low frequency dominant modes

158 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

C.1.2 North Eastern Region

Situational awareness can be improvised by viewing synchronized measurements in real-time. Visualizations

for operator console helps in analyzing data and location of events either in real time or offline. These

visualizations are user configurable and can be exploited for optimized power system analysis. All the

displays are made in historian SEL-5073.

Figure C-6 : Geographical location of PMUs and communication status

Figure C-7 : Visualization of phase angle differences

DECEMBER - 2013 POSOCO159

Synchrophasors - Initiative in India

Figure C-8 : Visualization of system frequency from all PMUs

Figure C-9 : Visualization of voltage magnitudes

160 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure C-10 : Visualization of low frequency modes

C.1.3 Eastern Region

The offline/online status of PMUs and PDCs can be seen in Communication UI. In SIGUARD PDP UI, which

is used for observation and analysis, there are following components:

PSS Curve: A curve which shows the status of entire power system being monitored. Siemens has got their

own formula for calculation of this PSS factor, which is mainly based upon the limits defined for measuring

channels like V, I, f.

It is here one can see older time period data, can select a particular time slice and save it to permanent

archives, can simulate changed limiting values, can play the older real time data.

All the other elements like alarm/event, maps, chart, phasors will get displayed according to the time range

selected in PSS curve.

Alarm/Event list: This list shows the alarms/events about limit violations, PMU communication, time sync

error, application events like Islanding, etc.

Map: The map shows an overview of entire power system graphically. The limits violations are displayed as

change of colours, Power swing recognitions or Islanding detection are also displayed as change of colours

(application not yet verified by ERLDC).

Chart: In this area, one can plot any analog/Phasor measurands as well as calculated values. There is a list

DECEMBER - 2013 POSOCO161

Synchrophasors - Initiative in India

of predefined formulas for calculations, which can be used temporarily or can be used permanently (even

for archiving).

Phasor Chart: Here it shows rotating phasors which gives an idea about the frequency at one shot. The

direction of rotation of Phasors indicates the frequency above or below 50 Hz. One can compare the phase

angle of a Phasor in reference to another.

Power Swing Analysis: There is an application for this power swing analysis.

Figure C-11 : Visualization of Phase angle differences

Figure C-12 : Visualization of frequency plot

162 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure C-13 : Visualization of df/dt trend

Figure C-14 : MW flow of Sasaram-Biharsharif-II

DECEMBER - 2013 POSOCO163

Synchrophasors - Initiative in India

C.1.4 Southern Region

Figure C-15 : Geographical location of PMUs and Communication status

Figure C-16 : Visualization of Angular differences

164 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure C-17 : Visualization of frequency

Figure C -18 : Visualization of df/dt

DECEMBER - 2013 POSOCO165

Synchrophasors - Initiative in India

Figure C -19 : Visualization of positive sequence voltage

Figure C-20: Visualization of positive sequence currents

166 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure C-21: Visualization of MW flows

Figure C-22: Visualization of MVAR flows

DECEMBER - 2013 POSOCO167

Synchrophasors - Initiative in India

Figure C-23: Visualization of low frequency modes

C.1.5 Northern Region

For ensuring security and reliability of the system angular difference calculations in real time play a vital

role. PMUs can measure phasor angles which can be exploited for calculations of angular differences. The

figures shown below are variety of displays have been used for visualization of system behavior in real

time.

Figure C-24: Visualization of Angular differences

168 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure C-25: Visualization of df/dt

Figure C-26: Visualization of Frequency

DECEMBER - 2013 POSOCO169

Synchrophasors - Initiative in India

Appendix-D

D.1 Cost analysis of Synchrophasor Project

The total cost of the pilot projects in all the regions is approximately around 5 to 6 Crores. However, cost ofeach pilot project differs due to the varying quantity of PDC and PMUs. Approximate cost of project in eachregion is given in Table D-1.

Table D-1: Project cost implication for each region

Sr. No. Details pertaining to Project cost in Rs.(Approx.)

1 WRLDC 72 Lakhs

2 ERLDC 120 Lakhs

3 SRLDC 68 Lakhs

4 NERLDC 101 Lakhs

5 NRLDC 95 Lakhs

6 NLDC 115 Lakhs

The major portion of the project cost is attributed to PMUs. Incremental PMU (per PMU unit) cost is in therange of around 3-8 % of the individual pilot project is due to variations in Voltage and Current channels. Thecost of communication and other logistics costs are excluded in the calculation. For all the pilot projects theportion of cost towards PMUs (excluding other logistics) is approximately 42% of total projects cost.

Per unit cost of PDC, in general, is in the range of 3-10% of the total cost in individual pilot project. As thenumber of PDCs is less, the PDC cost is around 11% of the total project cost. The absolute cost mayremain more or less constant as the number of PDCs is not likely to increase. Historian and the Visualization(H&V) cost is around 3-22 % of the total cost in individual pilot project. Percentage costwise distribution ofvarious regional pilot projects is given below :

Figure D-1: Eastern Region pilot projectDistribution of costs

Figure D-2: North Eastern Region pilot projectDistribution of costs

170 DECEMBER - 2013POSOCO

Synchrophasors - Initiative in India

Figure D-3: Southern Region pilot project Distribution of CostsFigure D-4: Western Region pilot project Distribution of Costs