Switchgear Installation Precomissioning Inspection.PPT
-
Upload
abdullah-al-dushaishi -
Category
Documents
-
view
329 -
download
2
Transcript of Switchgear Installation Precomissioning Inspection.PPT
![Page 1: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/1.jpg)
Metal-Clad SwitchgearMetal-Clad Switchgear Installation & Precommissioning InspectionInstallation & Precommissioning Inspection
April 15, 2007Abdullah M Al-Dushaishi
![Page 2: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/2.jpg)
2
OUTLINEOUTLINE
EQUIPMENT INSTALLATION INSPECTION BUSBAR INSTALLATION INSPECTION CABLE CONNECTION INSPECTION GROUNDING CONNECTION INSPECTION SOME DESIGN CONCERNS PRE-COMMISSIONING REFERENCES
![Page 3: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/3.jpg)
3
EQUIPMENT INSTALLATION EQUIPMENT INSTALLATION INSPECTIONINSPECTION
Ensure that adequate protection is provided when installing switchgear
Switchgear shall only be installed in an indoor, air-conditioned environment
Switchgear shall have an unobstructed horizontal space of:a) Not less than 2 meters in front
b) Not less than 1 meter in back and sides
Spacing requirement between equipment shall be based upon the largest dimension for either
![Page 4: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/4.jpg)
4
EQUIPMENT INSTALLATION EQUIPMENT INSTALLATION INSPECTIONINSPECTION
Lifting/handling devices shall be provided within a room containing switchgear to mechanically assist in removing to floor level, any withdrawable component (e.g., circuit breaker, contactor, potential transformer, etc.) weighing over 20 kg
Switchgear shall be free of any physical damage after installation
Switchgear should be properly anchored to its foundation
![Page 5: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/5.jpg)
5
EQUIPMENT INSTALLATION EQUIPMENT INSTALLATION INSPECTIONINSPECTION
Switches, circuit breakers, and other operating mechanisms shall be manually exercised to make sure that they are properly aligned and operate freely
Grounding connections shall be made properly
Debris, scrap wires and surplus shall be removed from the switchgear interior before closing the enclosure
![Page 6: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/6.jpg)
6
EQUIPMENT INSTALLATION EQUIPMENT INSTALLATION INSPECTIONINSPECTION
Covers, doors & enclosure parts shall be properly tightened
The switchgear shall be vertically & horizontally aligned before anchoring
Check components for proper identification as per IFC drawings and specifications
Nameplate on equipment shall conform to single line diagrams and schematics
![Page 7: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/7.jpg)
7
EQUIPMENT INSTALLATION EQUIPMENT INSTALLATION INSPECTIONINSPECTION
Concrete floor in front of switchgear shall be flush with the roller level of lower breaker carriage rack and have a smooth surface to facilitate removal and rolling of breaker
The bay spacing of transformers and the location of the incoming circuit breakers on switchgear lineups shall be positioned to minimize metal enclosed bus or cable bus length and/or eliminate bends
Preferably, incomer circuit breakers shall be located at ends of switchgear lineup
Unavoidable bends in cable bus or metal enclosed bus shall be inside the substation building
![Page 8: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/8.jpg)
8
BUSBAR INSTALLATIONBUSBAR INSTALLATIONINSPECTIONINSPECTION
Neutral buses shall not be used within switchgear
Cable shall not be used to extend the main bus of switchgear
![Page 9: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/9.jpg)
9
BUSBAR INSTALLATIONBUSBAR INSTALLATIONINSPECTIONINSPECTION
Contact surfaces for the main bus connections shall be clean
Tightness of bolted bus joints are correct as per manufacturer's instruction for the proper torque (foot-pound) levels
![Page 10: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/10.jpg)
10
CABLE CONNECTION CABLE CONNECTION INSPECTIONINSPECTION
Cable phasing shall be in accordance with connection diagram
Proper cable tags shall be provided
Cables termination shall be in accordance with cable manufacturer's instruction
Cable connections are clean and securely bolted.
Bolt torque values shall be as per manufacturer's specifications
![Page 11: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/11.jpg)
11
GROUNDING CONNECTION GROUNDING CONNECTION INSPECTIONINSPECTION
Sections of ground bus previously disconnected at shipping sections shall be reconnected when units are installed
Secondary wirings are connected to switchgear ground bus as indicated on IFC drawings
Ground bus shall be connected direct to grounding grid and shall not run in metal conduit unless conduit is adequately bonded to the circuit
![Page 12: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/12.jpg)
12
SOME DESIGN CONCERNSSOME DESIGN CONCERNS
Switchgear shall not be used to control: low voltage motors and high voltage motors rated less than 5kV
In industrial facilities, 480V switchgear shall not be fed from 4160V systems
A separate 120 VAC branch circuit shall be provided for the space heater
![Page 13: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/13.jpg)
13
PRE-COMMISSIONINGPRE-COMMISSIONINGCheck electrical relays, meters, or instruments to determine connections are made properly and devices function properly
Check settings of the adjustable current and voltage trip mechanisms to confirm that they are at proper values.
Check control, power transformer and PT fuses for size, type, and circuit location
Check PT and CT ratios
![Page 14: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/14.jpg)
14
PRE-COMMISSIONINGPRE-COMMISSIONINGCheck wiring connections for tightness at instrument transformers and terminal blocks
Protective devices’ setting for current, voltage, or other relays shall be done on-site in accordance with manufacturer’s recommendation
Ground-fault protection system shall be tested in accordance with manufacturer's instruction
![Page 15: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/15.jpg)
15
PRE-COMMISSIONINGPRE-COMMISSIONING
Protective relays, overcurrent trip devices, and breakers shall be tested for correct connections and operation at factory
Factory test results shall be referenced during Precommissioning
![Page 16: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/16.jpg)
16
PRE-COMMISSIONINGPRE-COMMISSIONINGInsulation resistance test shall be performed to make sure switchgear is free from short circuits and grounds. This test shall be done both phase to ground and phase to phase and with the switches and breakers both opened and closed
Switchgear busbar shall be tested for insulation resistance with a 1-minute test (phase to phase and phase to ground) with 1kV megohmmeter
Instrument transformers shall be tested for insulation resistance with a 1-minute test with 1 kV megohmmeter
![Page 17: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/17.jpg)
17
PRE-COMMISSIONINGPRE-COMMISSIONING
Each circuit breaker protective relay device shall be calibrated and tested with final settings in accordance with relay setting summary or coordination study
With CT disconnected, CT secondary circuit shall be tested for continuity and operation of applicable relays and meters by applying current to the CT secondary winding
PT secondary circuit shall be tested by applying voltage to the PT secondary, with PT disconnected, verifying operation of all applicable relays and meters
![Page 18: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/18.jpg)
18
PRE-COMMISSIONINGPRE-COMMISSIONING
Space heaters, switching and indicating devices shall be tested for operation
Auxiliary devices interlocks shall be tested for operation
Local and remote control devices/circuits shall be tested according to engineering specification
![Page 19: Switchgear Installation Precomissioning Inspection.PPT](https://reader035.fdocuments.in/reader035/viewer/2022062522/5875b3c71a28ab8b618b6a31/html5/thumbnails/19.jpg)
19
REFERENCESREFERENCES
NFPA 70 --National Electrical Code, 2005
NETA ATS -- Acceptance Testing Specification for Electrical Power Distribution Equipment and Systems, 1999
SAES-P-116 -- Switchgear and Control Equipment, 28 February 2005
SAES-P-119 -- Onshore Substations, 30 march 2005