1 2G Swapping Sites delivery & implementation schedule Manado 20 Sept IBSC delivery & installation 2008 26 Sept 1st 2nd Cluster sites installation & debugging B class sites installation & debugging C class sites installation & debugging 15 Oct. 25 Aug 30 Aug IBSC2 installation & debugging, 3 Ref. Sites Installation & Pre- debugging 15 Sept 3 Sept 8 Oct. 1 st Cluster Sites Swapping 2 nd Cluster Sites swapping 30 Sept. D class sites installation & debugging 3 rd Cluster Sites Swapping 4th,5th,6th Clu Sites Swapping

description

Swapping Plan.ppt

Transcript of Swapping Plan.ppt

Page 1: Swapping Plan.ppt

1

2G Swapping Sites delivery & implementation schedule Manado

20 Sept

IBSC delivery & installation

2008

26 Sept

1st 2nd Cluster sites installation & debugging

B class sites installation & debugging

C class sites installation & debugging

15 Oct.

25 Aug 30 Aug

IBSC2 installation & debugging,

3 Ref. Sites Installation & Pre-debugging

15 Sept3 Sept 8 Oct.

1st Cluster Sites Swapping

2nd Cluster Sites swapping

30 Sept.

D class sites installation & debugging

3rd Cluster Sites Swapping

4th,5th,6th Cluster Sites Swapping

Page 2: Swapping Plan.ppt

2

Manado 1st & 2nd Cluster Swapping Sites

BSC PAT will start on 3rd Sept.The sites of 1st & 2nd Cluster will be swapped during 7th ---14th Sept.

Page 3: Swapping Plan.ppt

3

Manado 3rd Cluster Swapping Sites

3rd Cluster will be installed during 14th --- 21th Sept.3rd Cluster will be swapped on 22th Sept

Page 4: Swapping Plan.ppt

4

Manado 4th Cluster Swapping Sites

Page 5: Swapping Plan.ppt

5

Manado 5th Cluster Swapping Sites

Page 6: Swapping Plan.ppt

6

Manado 6th Cluster Swapping Sites

4th,5th,6th Cluster will be swapped during 30th Sept. --- 15th Oct.

Page 7: Swapping Plan.ppt

7

A Interface Replacement Plan for Manado MSC2

The requirement of A interface E1 between ZTE BSC2 with Manado MSC2 is 300 E1.Currently, only 50 A interface E1 in MSC2 are available.

The strategy of A interface E1 replacement is to following the swapping scheme to release the A interface E1 of existing BSC one by one.The sequence as following diagram:

Page 8: Swapping Plan.ppt

8

2G Swapping Sites delivery & implementation schedule Gorontalo

18 Sept

IBSC delivery & installation

2008

21 Sept

c class sites installation & debugging

d class sites installation & debugging

15 Oct.

29 Aug

IBSC3 installation & debugging,

1 Ref. Sites Installation & Pre-debugging

8 Oct.30 Sept.

11 Sept

1ndCluster Sites Swapping2nd,3rd,4th Cluster Sites Swapping

7 Sept 9Sept

Page 9: Swapping Plan.ppt

9

Gorontalo 1st,2nd Cluster Swapping Sites

The 1st Ref. Sites will be swapped on 21th Sept.

Page 10: Swapping Plan.ppt

10

Gorontalo 3rd,4th Cluster Swapping Sites

The 2nd, 3rd & 4th Cluster Swapping sites will be swapped on 2 nights within 30th Sept. --- 15th Oct.

Page 11: Swapping Plan.ppt

11

Swapping Project Brief Scheme

Page 12: Swapping Plan.ppt

12

Site Swapping Workflow – Step 1

Page 13: Swapping Plan.ppt

13

Site Swapping Workflow – Step 2

Page 14: Swapping Plan.ppt

14

Site Swapping Workflow – Step 3