SVR Nandgi e

20
Notices and General Information RULES FOR BUILDING AND CLASSING STEEL VESSELS 2013 NOTICES AND GENERAL INFORMATION American Bureau of Shipping Incorporated by Act of Legislature of the State of New York 1862 Copyright 2012 American Bureau of Shipping ABS Plaza 16855 Northchase Drive Houston, TX 77060 USA

Transcript of SVR Nandgi e

Page 1: SVR Nandgi e

N o t i c e s a n d G e n e r a l I n f o r m a t i o n

RULES FOR BUILDING AND CLASSING

STEEL VESSELS 2013

NOTICES AND GENERAL INFORMATION

American Bureau of Shipping Incorporated by Act of Legislature of the State of New York 1862

Copyright 2012 American Bureau of Shipping ABS Plaza 16855 Northchase Drive Houston, TX 77060 USA

Page 2: SVR Nandgi e

ii ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013

T a b l e o f C o n t e n t s

part Notices and General Information

CONTENTS Introduction ..................................................................................................................... 1

TABLE 1 Applicable Editions of Booklets Comprising 2013 Rules .......... 4 TABLE 2 Division and Numbering of Rules .............................................. 4

Rule Change Notice (2013) ............................................................................................. 5 TABLE 3 Summary of Changes from the 2012 Rules .............................. 5

Page 3: SVR Nandgi e

ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013 1

Notices and General Information

Introduction 1. The year 2013 edition of the Rules for Building and Classing Steel Vessels consists of the eleven

(11) booklets as shown in Table 1. In this regard, we would bring the following to the user’s attention:

a) The purpose of the generic title ABS Rules for Conditions of Classification (Part 1) is to reflect the expanded contents of PART 1, as a result of including consolidated requirements for “Classification” applicable to all types of and sizes of vessels, barges and specific shipboard arrangements/systems, etc., except for those in offshore service, as specified in the Foreword to Part 1.

b) The purpose of the generic title ABS Rules for Materials and Welding (Part 2) of PART 2 is to emphasize the common applicability of the requirements to ABS-classed vessels, other marine structures and their associated machinery, and thereby make PART 2 more readily a common “PART” of various ABS Rules and Guides, as appropriate.

c) The purpose of the generic title ABS Rules for Survey After Construction (Part 7) is to reflect the expanded contents of PART 7, as a result of including consolidated requirements for “Surveys After Construction” applicable to all types and sizes of vessels, barges and specific shipboard arrangements/systems, etc., as specified in Part 7, Chapter 1, Section 1.

2. The numbering system applied in the Rules is shown in Table 2.

3. The primary changes from the 2012 edition of the Rules are identified and listed in Table 3. The effective date of the indicated Rule Changes is 1 January 2013, unless specifically indicated otherwise.

4. The effective date of each technical change since 1993 is shown in parenthesis at the end of the subsection/paragraph titles within the text of each Part. Unless a particular date and month are shown, the years in parentheses refer to the following effective dates:

(2000) and after 1 January 2000 (and subsequent years) (1996) 9 May 1996 (1999) 12 May 1999 (1995) 15 May 1995 (1998) 13 May 1998 (1994) 9 May 1994 (1997) 19 May 1997 (1993) 11 May 1993

5. Until the next edition of the Rules for Building and Classing Steel Vessels is published, Rule Change Notices and/or Corrigenda, as necessary, will be published on the ABS website – www. eagle.org – only, and will be available free for downloading. It is not intended to publish hard copies of future Rule Change Notices and/or Corrigenda to existing Rules or Guides. The consolidated edition of the Rules for Building and Classing Steel Vessels, which includes Rule Change Notices and/or Corrigenda using different colors for easy recognition, will be published on the ABS website only when Rule Change Notices and/or Corrigenda are issued.

6. The listing of CLASSIFICATION SYMBOLS AND NOTATIONS is available from the ABS website http://www.eagle.org/absdownloads/index.cfm for download.

7. In association with the introduction of the Common Structural Rules for Double Hull Oil Tankers and Bulk Carriers, respectively, on 1 April 2006, Part 5 of the Rules for Building and Classing Steel Vessels was divided into three Sub-parts, 5A, 5B and 5C. The contents and application of each Part are as follows:

Page 4: SVR Nandgi e

Notices and General Information

2 ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013

Contents

Part 5A: Common Structural Rules for Double Hull Oil Tankers (*See note below)

Part 5B: Common Structural Rules for Bulk Carriers (*See note below)

Part 5C: This Part is divided into two separate booklets as follows:

Chapters 1 to 6: Tankers not covered by Part 5A, Bulk Carriers not covered by Part 5B and Container Carriers

Chapters 7 to 10: Passenger Vessels, Liquefied Gas Carriers, Chemical Carriers and Vessels Intended to Carry Vehicles.

* Note: In view of the effective date (1 July of each year) of the updated Common Structural Rules, the 2013 editions of Part 5A and Part 5B will be published in July 2013. Until the effective date of the 2013 editions, the following 2012 editions are applicable:

Part 5A Specific Vessel Types (Chapter 1), 2012 Common Structural Rules for Double Hull Oil Tankers [including Rule Change Notice No. 1 (1 July 2012)]

Part 5B Specific Vessel Types (Chapters 3 and 4), 2012 Common Structural Rules for Bulk Carriers [including Rule Change Notice No. 1 (1 July 2012) and Corrigenda No. 1 (1 July 2012)]

Application – Oil Tankers

The structural requirements in Part 5A of the Rules are applicable for double hull oil tankers of 150 m in length and upward, with structural arrangements as specified in Part 5A, Section 2.

For oil tankers with structural arrangements not covered by Part 5A, the requirements in Part 5C, Chapters 1 or 2, are to be complied with.

Application – Bulk Carriers

The structural requirements in Part 5B of the Rules are applicable for single side skin and double side skin bulk carriers of 90m in length and upward, with structural arrangements as specified in Part 5B, Chapter 1, Section 1.

For vessels intended to carry ore or bulk cargoes, other than the single side skin or double side skin bulk carriers of 90 m in length and upward with structural arrangements as specified in Part 5B, Chapter 1, Section 1, the requirements in Part 5C Chapters 3 or 4 are to be complied with.

Application – ABS Construction Monitoring Program

These compulsory requirements for CSR notation are specified in Part 5C, Appendix 2.

Application – Onboard Systems for Oil Tankers and Bulk Carriers

The onboard systems for all tankers are to comply with the requirements of Part 5C, Chapter 1, Section 7, and for all bulk carriers are to comply with the requirements of Part 5C, Chapter 3, Section 7 of the Rules.

The following flow chart indicates the application of the Rules and typical Class Notations for tanker and bulk carrier vessels, of which arrangements and scantlings are in full compliance with the Rules:

Page 5: SVR Nandgi e

ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013 3

Vessels Intended to Carry Oil in Bulk Vessels Intended to Carry Ore or Bulk Cargoes

L ≥ 150 m?

Arrangement andlayout comply with

5A-1-2/3.1.2 and5A-1-2/Fig 2.3.1?

Part 5A, Chapter 1:Common Structural Rules for

Double Hull Oil Tankers,and

Part 5C, Appendix 2Part 5C, Chapter 1, Section 7

À A1 Oil Carrier, CSR, AB-CMplus

appropriate notations for oil carriers

Part 5C, Chapter 1,Appendix 1 to Part 5C

(L ≥ 150 m)

À A1 Oil Carrier, SH, SHCMplus

appropriate notations for oil carriers

Part 5C, Chapter 2(L < 150 m)

À A1 Oil Carrierplus

appropriate notations for oil carriers

L ≥ 90 m?

Arrangement andlayout comply with

5B-1-1/1.1.2?

Part 5B, Chapters 1 through 13:Common Structural Rules for

Bulk Carriers,and

Part 5C, Appendix 2Part 5C, Chapter 3, Section 7

Part 5C, Chapter 3,Appendix 1 to Part 5C

(L ≥ 150 m)

Part 5C, Chapter 4(L < 150 m)

À A1 Bulk Carrier, CSR, AB-CMplus

appropriate notations for bulk carriers

À A1 Bulk Carrier, SH, SHCMplus

appropriate notations for bulk carriers

À A1 Bulk Carrierplus

appropriate notations for bulk carriers

Yes

Yes

Yes

Yes

No No

Or

Page 6: SVR Nandgi e

4 ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013

TABLE 1 Applicable Editions of Booklets Comprising 2013 Rules

Notices and General Information 2013 Part 1: Rules for Conditions of Classification 2013 Part 2: Rules for Materials and Welding

Rules for Testing and Certification of Materials Rules for Welding and Fabrication

2013

Part 3: Hull Construction and Equipment 2013 Part 4: Vessel Systems and Machinery 2013 Part 5A: (Booklet 1)

Specific Vessel Types Chapter 1 Common Structural Rules for Double

Hull Oil Tankers

2012 (on and after 1 July 2012)

Part 5B: (Booklet 2)

Specific Vessel Types Chapter 3 & 4 Common Structural Rules for Bulk

Carriers

2012 (on and after 1 July 2012)

Part 5C: (Booklet 3)

Specific Vessel Types Chapter 1 & 2 Oil Carrier Chapter 3 & 4 Bulk Carrier Chapter 5 & 6 Container Carrier

2013

Part 5C: (Booklet 4)

Specific Vessel Types Chapter 7 Passenger Carrier Chapter 8 Liquefied Gas Carrier Chapter 9 Chemical Carrier Chapter 10 Vehicle Carrier

2013

Part 6: Optional Items and Systems Chapter 1 Strengthening for Navigation in Ice Chapter 2 Refrigerated Cargo Vessels

2013

Part 7: Rules for Surveys After Construction 2013

TABLE 2 Division and Numbering of Rules

Division Number Part Part 1 Chapter Part 1, Chapter 1 Section Section 1-1-1 Subsection (see Note 1) 1-1-1/1 Paragraph (see Note 1) 1-1-1/1.1 Subparagraph 1-1-1/1.1.1 Item 1-1-1/1.1.1(a) Subitem 1-1-1/1.1.1(a)i) Appendix Appendix 1-1-A1 or Appendix 1-A1-1

Note: 1 An odd number (1, 3, 5, etc.) numbering system is used for the Rules. The purpose is to permit future insertions of

even-numbered paragraphs (2, 4, 6, etc.) of text and to avoid the necessity of having to renumber the existing text and associated cross-references, as applicable, within the Rules and associated process instructions, check sheets, etc.

Page 7: SVR Nandgi e

Notices and General Information

ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013 5

Rule Change Notice (2013)

TABLE 3 Summary of Changes from the 2012 Rules

EFFECTIVE DATE 1 November 2011 – shown as (1 November 2011)

Part/Para. No. Title/Subject Status/Remarks 1-1-5/11 (New)

ABS Surveyor’s Safety and ABS Safety Manual

To include wording for rules regarding application of ABS safety policies. (Incorporates Notice No. 1)

EFFECTIVE DATE 1 February 2012 – shown as (1 February 2012)

Part/Para. No. Title/Subject Status/Remarks 1-1-8/5 Notification of Port State Detention To remove the requirement for Owners to notify ABS of Port State

interventions. (Incorporates Notice No. 2)

EFFECTIVE DATE 1 May 2012 – shown as (1 May 2012)

Part/Para. No. Title/Subject Status/Remarks 1-1-5/11 ABS Surveyor’s Safety and ABS

Safety Manual To clarify the requirements. (Incorporates Notice No. 3)

EFFECTIVE DATE 1 July 2012 – shown as (1 July 2012)

Part/Para. No. Title/Subject Status/Remarks 1-1-4/7.6 Application of Common Structural

Rules for Tankers and Bulk Carriers To specify that CSR vessels accepted under the provision of 1-1-4/7.6 are exempted from AB-CM notation unless otherwise the notation is specially requested and the relevant requirements are fully complied with. (Incorporates Notice No. 4)

EFFECTIVE DATE 1 September 2012 – shown as (1 September 2012)

Part/Para. No. Title/Subject Status/Remarks 1-1-7/3 Machinery Plans To support the VIM population initiative to ensure that shipyards

submit machinery equipment list for VIM population. (Incorporates Notice No. 5)

EFFECTIVE DATE 1 January 2013 – shown as (2013) (based on the date of purchase order of the materials)

Part/Para. No. Title/Subject Status/Remarks 2-1-1/11.11 Impact Test Specimens To meet the ASTM A370 standard requirements.

2-1-1/17 Steel Plates and Wide Flats with Specified Minimum Through Thickness Properties (“Z” Quality)

To delete reference to ASTM A770. In Z-quality plates, ASTM A770 covers only 1 in. (25 mm) and greater in thickness whereas ABS Rules do not have any minimum thickness limit. Also, the minimum percentage of reduction in area requirements are different between ABS Rules and ASTM A770.

Page 8: SVR Nandgi e

Notices and General Information

6 ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013

Part/Para. No. Title/Subject Status/Remarks 2-1-1/17.15 Certification To specify that for certification, UT results are to be reported.

2-1-5/13.7 Welded Repair To highlight that all welds are to be done to approved procedures and that weld procedures for castings should be qualified with cast material per IACS UR W28.

2-1-6/11.9 Rectification of Defective Forgings To highlight that all welds are to be done to approved procedures and that weld procedures for castings should be qualified with cast material per IACS UR W28.

2-3-7/1.15 Rectification of Defective Forgings To highlight that all welds are to be done to approved procedures and that weld procedures for castings should be qualified with cast material per IACS UR W28.

2-3-7Table 1 Chemical Composition Requirements for Carbon Steel Machinery Forgings, in percent

To match with the IACS requirements, the maximum limit of manganese is increased to 1.50%.

2-3-7Table 2 Tensile Property Requirements for Carbon-steel Machinery Forgings

To specify the size limits for grades 4, 4C.

2-3-8/1 Hot-rolled Steel Bars To clarify that hot rolled bars can be used where permitted in lieu of forgings, and should therefore be subject to the same manufacturing approval requirement.

2-3-9/15.7 Welded Repair To highlight that all welds are to be done to approved procedures and that weld procedures for castings should be qualified with cast material per IACS UR W28.

2-3-13/3 Designation ASTM A333 Grade 4 does not have a Nickel (Ni) 2.5%. ASTM A350 Grade LF4 is not available in the standard.

2-4-1/1.3 Plans and Specifications To clarify that in the case of plans and specifications of the welding, the drawing needs to indicate the full/partial penetration weld.

2-4-1/3.13 Forming To match with the qualification test requirements specified in 2-A4-2/Table 1.

2-4-1/5.17 Inspection of Welds To reference the cooling time requirements specified in the ABS Guide for Nondestructive Inspection of Hull Welds.

2-4-3/3.1 General To clarify that Appendix 3 should be cited because it indicates filler metal applications.

2-4-3/Figure 13 Orientation and Location of Charpy V-notch Specimens for Weld and Heat Affected Zone Properties

To clarify that CVN test temperature of the weld and base metal may not be the same, and PQR testing should be based on the weld test temperature.

2-4-3/Table 2 (New)

Minimum Weld Metal and HAZ CVN Impact Values for ABS Grade Steels

To clarify that CVN test temperature of the weld and base metal may not be the same, and PQR testing should be based on the weld test temperature and to completely cover PQR CVN test temperatures and impact values for ABS grade steels.

2-4-4/15.3 Hot Forming To clarify that many ASME Section IX P-4 steels are 1.25Cr-0.5 Mo.

2-A1 List of Destructive and Nondestructive Tests Required for Materials and Responsibility for Verifying

To include the list of test and test data for seamless copper tube, condenser and heat exchanger tube, copper nickel tube and pipe, and Monel pipe.

EFFECTIVE DATE 1 July 2012 – shown as (1 July 2012) (based on the contract date for new construction between builder and Owner)

Part/Para. No. Title/Subject Status/Remarks PART 3 Hull Construction and Equipment 3-2-15/3.3 Vertical Design Pressures To align the Rules with IACS S21A “Evaluations and Scantlings of

Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/Figure 1 (New)

Positions 1 and 2 To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

Page 9: SVR Nandgi e

Notices and General Information

ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013 7

Part/Para. No. Title/Subject Status/Remarks 3-2-15/Figure 2 (New)

Positions 1 and 2 for an Increased Freeboard

To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/3.5 (New)

Horizontal Design Pressures To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/Table 1 (New)

Minimum Design Load pHmin To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/9 Hatchways Closed by Covers of Steel Fitted with Gaskets and Clamping Devices

To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/Figure 3 (New)

Determination of Normal Stress of the Hatch Cover Plating

To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/Figure 4 (New)

Forces due to Container Loads To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/Figure 5 (New)

Partial Loading of a Container Hatch Cover

To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/Table 2 (New)

Effective Breadth em of Plating of Primary Supporting Members

To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/Figure 6 (New)

General Arrangement of Panel To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/Table 3 (New)

Correction Factor F1 To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/Table 4 (New)

Coefficients e1, e2, e3 and Factor B To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/Table 5 (New)

Buckling and Reduction Factors for Plane Elementary Plate Panels

To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/Figure 7 (New)

Stiffening Parallel to Web of Primary Supporting Member

To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/Figure 8 (New)

Stiffening Perpendicular to Web of Primary Supporting Member

To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/Figure 9 (New)

Dimensions of Stiffeners To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/Table 6 (New)

Moments of Inertia To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/Figure 10 (New)

Example for Arrangement of Coaming Plates

To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/Figure 11 (New)

Lifting Forces at a Hatch Cover To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

Page 10: SVR Nandgi e

Notices and General Information

8 ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013

Part/Para. No. Title/Subject Status/Remarks 3-2-15/Table 7 (New)

Permissible Nominal Surface Pressure pn

To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/Table 8 (New)

Corrosion Additions tS for Hatch Covers and Hatch Coamings

To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

3-2-15/21.5 Escape Openings To align the requirements for escape openings with IACS UI SC 247, “Emergency Exit Hatches to Open Deck”. (Incorporates Notice No. 1)

3-2-15/21.11 Chain Pipe Opening To align the Rules with recent revisions to IACS UR L4 Rev 3 Corr 1, revised August 2011, that provides examples of acceptable arrangements of closing chain pipe openings. (Incorporates Notice No. 1)

3-2-18/5 Corrosion Protection of Steel To remove requirements pertaining to corrosion protection of "Salt Water Ballast Tanks and Double-side Skin Spaces" (section 5.3), "Cargo Oil Tanks of Crude Oil Tankers" (section 5.5) and "Void Spaces" (section 5.9) which are addressed by specific and more detailed SOLAS regulations (SOLAS II-1/3-2 & SOLAS II-1/3-11), so as to avoid confusion and conflict with respect to the application of the SOLAS regulations. (Incorporates Notice No. 1)

3-3-A3/11.1 Conditions of Approval of the Onboard Software for Stability Calculations

To ensure the stability software is available if the primary computer crashes. (Incorporates Notice No. 1)

PART 4 Vessel Systems and Machinery 4-3-4/21.7 Sea Trials To establish alternative steering gear trial conditions for vessels which

cannot be tested at their deepest seagoing draught, as required by SOLAS Regulations II-1/29.3.2 and 29.4.2, in line with IACS UR M42 Rev 4, Steering Gear. (Incorporates Notice No. 1)

4-6-2/7.3.4 Pneumatic Tests in Lieu of Hydrostatic Tests

To remove the responsibility of accepting pneumatic tests in lieu of hydrostatic tests from a Surveyor and place it on the Divisional Survey Department, to properly assess risk of conducting such test. (Incorporates Notice No. 1)

4-6-4/5.5.13 (New)

Cargo Spaces With Non-watertight Hatches Intended to Carry Containers

To align the Rules with IACS S21A “Evaluations and Scantlings of Hatch Covers and Hatch Coamings and Closing Arrangements of Cargo Holds of Ships”. (Incorporates Notice No. 1)

4-6-4/5.7.3 Sludge Tank To align the Rules with UI 15.1.5 in MARPOL, as shown in Annex 28 to MEPC 58/23, eliminating the provision that allowed for a reduction in the minimum required Sludge Tank capacity where a vessel was fitted with an incinerator or similar equipment (Incorporates Notice No. 1)

4-6-4/7.7 (New)

Ballast Water Treatment Systems To ensure that users are aware of the mandatory requirements identified in the ABS Guide for Ballast Water Treatment. (Incorporates Notice No. 1)

PART 5C Specific Vessel Types 5C-A2/3 Application “AB-CM” notation is unique to ABS, while CSR is the common

Rules among IACS. The CSR vessel accepted under the provision of 1-1-4/7.6 is exempted from “AB-CM” notation unless otherwise the notation is specially requested and the relevant requirements are fully complied with. (Incorporates Notice No. 1)

5C-8-1/3.2 <No Title> To align the Rules with Annex 6, Resolution MSC.220(82) (adopted on 8 December 2006) Adoption of Amendments to the International Code for the Construction and Equipment of Ships Carrying Liquidized Gases in Bulk. (Incorporates Notice No. 1)

5C-8-1/3.34 <No Title> To align the Rules with Annex 6, Resolution MSC.220(82) (adopted on 8 December 2006) Adoption of Amendments to the International Code for the Construction and Equipment of Ships Carrying Liquidized Gases in Bulk. (Incorporates Notice No. 1)

Page 11: SVR Nandgi e

Notices and General Information

ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013 9

Part/Para. No. Title/Subject Status/Remarks 5C-8-3/3.1.1 <No Title> To align the Rules with Annex 6, Resolution MSC.220(82) (adopted

on 8 December 2006) Adoption of Amendments to the International Code for the Construction and Equipment of Ships Carrying Liquidized Gases in Bulk. (Incorporates Notice No. 1)

5C-8-5/3.2.3 (IACS)

Cargo Pumps To align the Rules with IACS UR G3.6.3 Rev. 4, which provides revised guidance on the prototype testing and unit production testing of cargo pumps. (Incorporates Notice No. 1)

5C-8-11/1.1 <No Title> To align the Rules with Annex 6, Resolution MSC.220(82) (adopted on 8 December 2006) Adoption of Amendments to the International Code for the Construction and Equipment of Ships Carrying Liquidized Gases in Bulk. (Incorporates Notice No. 1)

5C-8-11/2.1 <No Title> To align the Rules with Annex 6, Resolution MSC.220(82) (adopted on 8 December 2006) Adoption of Amendments to the International Code for the Construction and Equipment of Ships Carrying Liquidized Gases in Bulk. (Incorporates Notice No. 1)

5C-8-11/5.1 <No Title> To align the Rules with Annex 6, Resolution MSC.220(82) (adopted on 8 December 2006) Adoption of Amendments to the International Code for the Construction and Equipment of Ships Carrying Liquidized Gases in Bulk. (Incorporates Notice No. 1)

5C-8-11/6 <No Title> To align the Rules with Annex 6, Resolution MSC.220(82) (adopted on 8 December 2006) Adoption of Amendments to the International Code for the Construction and Equipment of Ships Carrying Liquidized Gases in Bulk. (Incorporates Notice No. 1)

5C-8-12/Note <No Title> To align the Rules with Annex 6, Resolution MSC.220(82) (adopted on 8 December 2006) Adoption of Amendments to the International Code for the Construction and Equipment of Ships Carrying Liquidized Gases in Bulk. (Incorporates Notice No. 1)

5C-9-15/11.2 (IACS)

Interpretation of 5C-9-15/11.2 To align the Rules with IACS UI CC6 (April 2011) “Lining approved for the use with acids IBC Code item 15.11.2, which clarifies that spray-on corrosion protection systems are not acceptable linings for the protection of steel tank and pipe materials required by IBC Code item 15.11.2 when carrying acids (Incorporates Notice No. 1)

5C-10-4/3.5.4 Control of the Ventilation System To implement IACS UI SC 243 (Mar 2011) Access to controls for closing of ventilation of vehicle, special category and ro-ro spaces (SOLAS II-2/20.3.1.4.1). (Incorporates Notice No. 1)

EFFECTIVE DATE 1 January 2013 – shown as (2013) (based on the contract date for new construction between builder and Owner)

Part/Para. No. Title/Subject Status/Remarks PART 3 Hull Construction and Equipment 3-1-2/5.3 Reduced Scantlings with Protective

Coatings The incorporation of Performance Standards for Protective Coatings (PSPC) requirements in modern shipbuilding has removed the need for special consideration of protective coatings.

3-2-11/3.1 General To clarify that requirements for openings and closing appliances in deckhouses are the same as those for superstructures.

3-2-11/5 Enclosed Superstructures and Deckhouses

To clarify that requirements for openings and closing appliances in deckhouses are the same as those for superstructures.

3-3-A2/1.3 Applicability To align the requirements with IMO Resolution MSC.170 (79), which adds information about Double Side Skin Bulk carriers.

PART 4 Vessel Systems and Machinery 4-1-1/Table 3 Certification Details – Electrical and

Control Equipment To align the table with other parts of the Rules.

4-1-1/Table 6 Certification Details – Piping System Components

To align the table with other parts of the Rules.

Page 12: SVR Nandgi e

Notices and General Information

10 ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013

Part/Para. No. Title/Subject Status/Remarks 4-2-2/1.5.1 Turbocharger Construction To clarify the intent of the requirements and to be consistent with the

requirements in 4-3-4/1.11.

4-2-2/5.3.3 Type Test Data To align the requirements with the current practice for speed and temperature of burst tests and containment tests.

4-3-1A1/13 Load Sharing Factor, Kγ To align the Rules with SO 10300-2, Calculation of load capacity of bevel gears – Part 2: Calculation of surface durability (pitting).

4-3-2/7.1 General To clarify the requirements. To add relative misalignment criteria for the slope between the shaft and tail shaft bearing and shafting arrangements without a forward stern tube bearing to the list of items for which the shaft alignment analysis must verify compliance. To add requirements to consider hull deflection as well as the actions that will be required if hull deflection is not considered. To add provisions to require validation of the calculation results as well as the calculation methodology used in the submitted calculations. To specify details of what is to be addressed in the Shaft Alignment Procedures.

4-3-2/7.3 Shaft Alignment To clarify the requirements. To add relative misalignment criteria for the slope between the shaft and tail shaft bearing and shafting arrangements without a forward stern tube bearing to the list of items for which the shaft alignment analysis must verify compliance. To add requirements to consider hull deflection as well as the actions that will be required if hull deflection is not considered. To add provisions to require validation of the calculation results as well as the calculation methodology used in the submitted calculations. To specify details of what is to be addressed in the Shaft Alignment Procedures.

4-3-2/7.9 Whirling Vibrations To include a calculation check that the shafting system’s critical speeds are not close to the operating speeds of the vessel.

4-3-2/11.1 Shaft Alignment To identify the shaft alignment efforts for which the Surveyor should attend along with specific acceptance criteria that should be applied.

4-3-2/11.3.2 Axial and Whirling Vibrations To allow for requiring additional measurements where the whirling vibration analysis indicates potentially harmful resonance within operating range of the propulsion installation.

4-3-2/Table 4 Allowable Torsional Vibratory Stress To clarify the intent of the special consideration requirement.

4-3-6 Propulsion Redundancy To remove the sentence in 4-3-6/11 related to service oil pump, since it is considered not to be directly related to a redundancy.

4-6-1/Table 1 Classes of Piping Systems To relocate the requirements in 4-6-7/7.5.1(a) to a more appropriate location.

4-6-4/Figure 3 Acceptable Fuel Oil Tanks Arrangements Inside Category A Machinery Spaces

To provide consistency between the plan and elevation views.

4-6-4/13.5.3(a) Required Valves To align the requirements with the IACS Common Structural Rules, which allow connecting the valve to the tank using a short piece of pipe between the tank and valve so the valve clears the insulation.

4-6-4/13.5.6(f) Additional Level Alarms To clarify that if an adequate overflow is installed for the operation of the purifier, the high level alarm in the service tank is meaningless since the fuel oil level will never reach the high level.

4-6-4/17.3.2(c) (New)

Main Engine Lubricating Oil Drain Tanks

To clarify that the arrangement of the lubricating oil sump tank shall comply with the requirement in SOLAS, as amended by MSC.194(80), annex 2, Regulation 9.3.

4-6-4/17.5 Class Notation – POT To clarify that the arrangement of the lubricating oil sump tank shall comply with the requirement in SOLAS, as amended by MSC.194(80), annex 2, Regulation 9.3.

4-6-5/5.1.2 Basic Requirement To define the term “other measures” as machinery shutdown.

Page 13: SVR Nandgi e

Notices and General Information

ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013 11

Part/Para. No. Title/Subject Status/Remarks 4-6-5/5.3.4 Diesel Engines and Associated

Reduction Gears To clarify that where diesel engines are driving reduction gears, shutdown of diesel is required, regardless of a propulsion train configuration, in order to protect the gear.

4-6-5/Table 2 Lubrication Oil System Basic Alarms and Safety Shutdown

To align the table with revisions to the requirements to 4-6-5/5.1.2 and 4-6-5/5.3.4.

4-6-7/3.5.5(f) (New)

Exemptions To clarify the exemption of compliance with the Rule requirements when the fluid power cylinders are not within the scope of classification.

4-6-7/7.5.1(a) General To provide references to the appropriate requirements in Sections 4-6-1 and 4-6-2.

4-6-7/9.5.2 Drainage To clarify that the requirements are intended only for the coaming around the fuel storage tank, but not for the pumping unit coaming when they are separate, as indicated in 4-6-7/9.5.1.

4-7-1/9 Fire Control Plan To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-1/11.21 Control Stations To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-1/11.25 Dangerous Goods To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-2/1.1.1 Fixed Fire Extinguishing Systems To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-2/1.1.3 Portable Fire Extinguishers To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-2/1.11.2 Fixed Local Application Fire-fighting Systems

To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-2/1.13.1 Fire Detection and Alarm Systems To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-2/1.13.1(b) Alarms To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-2/1.13.1(c) (Deleted)

Testing To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-2/3.4 (New)

Locations Requiring Manually Operated Call Points

To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-2/5.3.1 Application To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-2/5.3.2 Provisions for Helicopter Deck To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-2/7.1.3 Vessels Carrying Low Fire Risk Cargoes

To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-2/7.3.1(b) Quantity of Water To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-2/7.3.6 Personnel Protection To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-2/Table 4 Application of the Requirements in 4-7-2/7.3 to Different Classes of Dangerous Goods Except Solid Dangerous Goods in Bulk

To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-3/1.5.3vii) <No Title> To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-3/3.1.9ii) <No Title> To clarify the requirement for location of the fire extinguishing media storage room and controls to release the media.

4-7-3/3.7 Steam Systems To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

Page 14: SVR Nandgi e

Notices and General Information

12 ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013

Part/Para. No. Title/Subject Status/Remarks 4-7-3/3.9 Systems Using Gaseous Products of

Fuel Combustion To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-3/3.11 Equivalent Fixed Gas Fire-Extinguishing Systems for Machinery Spaces and Cargo Pump Rooms

To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-3/3.13 (New)

Clean Agent Fire Extinguishing Systems

To introduce a new subsection for clean agent fire extinguishing systems which are being used onboard vessels and MODUs as a substitute for Halon systems (new installations now prohibited) and as an alternative to CO2 systems.

4-7-3/5.1 Fixed High-expansion Foam Fire Extinguishing Systems in Machinery Spaces

To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-3/5.3 Fixed Low-expansion Foam Fire Extinguishing System in Machinery Spaces

To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-3/9 Automatic Sprinkler, Fire Detection and Fire Alarm Systems

To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-7-3/11 Fixed Fire Detection and Fire Alarm Systems

To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

4-8-2/5.15.2 Number of Starts To clarify the requirements and align with SOLAS II-1/Reg. 44 Starting arrangements for emergency generating sets.

4-8-2/11.5.4v) <No Title> To clarify that the power supply requirement is to comply with 4-8-2/11.7.1(b) and 4-8-2/11.7.1(c).

4-8-2/11.9.1 Ventilation Systems To allow the one control position which is outside of the space to be chosen wisely. To separate ventilation for spaces for: 1, propulsion machinery, 2, other machinery, and 3, other spaces.

4-8-3/Table 6 Maximum Current Carrying Capacity for Cables

To align the requirements with the latest IEC 60092-351/352/353 Standard and current shipyard practices.

4-8-4/11.5 Lighting Distribution Boards To allow the main and the emergency lighting distribution boards to both be placed on the navigation bridge.

4-8-4/13 Heating Equipment To remove repetition of the requirements in the Rules.

4-8-4/19 Power Receptacles To align the requirements with IEC 60092-306.

4-8-4/21.17 Installation of Cables and Apparatus for Emergency and Essential Services

To reference the specific requirements for the Emergency Fire Pump in 4-8-4/21.17.3.

4-8-5/5.17.13 (New)

Reduction Gear Safety – Lubrication To protect reduction gears for electric propulsion installations in the case of lubrication failure.

4-9-1/13i) <No Title> To align with the revision in 4-6-5/5.1.2.

4-9-1/13v) <No Title> To require shutdown of diesel where diesel engines are driving reduction gears, regardless of a propulsion train configuration, in order to protect the gear.

4-9-4/Table 3B Instrumentation and Safety System Functions in Centralized Control Station – Medium and High Speed (Trunk Piston) Diesel Engines

To clarify that the lube oil monitoring temperature is related to oil outlet.

4-9-4/Table 5 Instrumentation and Safety System Functions in Centralized Control Station – Propulsion Gas Turbines

To align with the instrumentation and control list for Auxiliary Gas Turbine.

4-9-4/Table 6B Instrumentation and Safety System Functions in Centralized Control Station – Generator Prime Mover for Electric Propulsion

To clarify that the lube oil monitoring temperature is related to oil outlet.

Page 15: SVR Nandgi e

Notices and General Information

ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013 13

Part/Para. No. Title/Subject Status/Remarks PART 5C Specific Vessel Types 5C-1-A1 Fatigue Strength Assessment of

Tankers To completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.

5C-1-A5 Hull Girder Ultimate Strength Assessment of Oil Carriers

To completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.

5C-2-A1 Hull Girder Shear Strength for Tankers

To completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.

5C-3-7/3.3 Vessels Carrying Low Fire Risk Cargoes

To update the Rules in accordance with IMO MSC/Circ.1395.

5C-3-7/3.9 Vessels Intended to Carry Materials Hazardous Only in Bulk

To update the Rules in accordance with IMO Resolution MSC.268(85).

5C-3-A1 Fatigue Strength Assessment of Bulk Carriers

To completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.

5C-3-A5 Hull Girder Ultimate Strength Assessment of Bulk Carriers

To completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.

5C-5-2/Figure 1 Nominal Design Corrosion Values (NDCV)

To align the Rules with the revision of MARPOL 73/78, ANNEX I, Reg. 12A, which requires fuel oil tanks of 600 m3 and over for ships delivered on or after August 1, 2010 to be located at a specified minimum distance inboard of the outer shell of the ship's hull.

5C-5-2/Table 1 Nominal Design Corrosion Values (NDCV) for Container Carriers

To align the Rules with the revision of MARPOL 73/78, ANNEX I, Reg. 12A, which requires fuel oil tanks of 600 m3 and over for ships delivered on or after August 1, 2010 to be located at a specified minimum distance inboard of the outer shell of the ship's hull.

5C-5-3/Figure 3B (New)

Loading Pattern of Container Carrier Fuel Oil Tank Located Between Cargo Hold Transverse Bulkheads

To align the Rules with the revision of MARPOL 73/78, ANNEX I, Reg. 12A, which requires fuel oil tanks of 600 m3 and over for ships delivered on or after August 1, 2010 to be located at a specified minimum distance inboard of the outer shell of the ship's hull.

5C-5-3/Figure 3C (New)

Loading Pattern of Container Carrier Fuel Oil Tank Located within Cargo Holds

To align the Rules with the revision of MARPOL 73/78, ANNEX I, Reg. 12A, which requires fuel oil tanks of 600 m3 and over for ships delivered on or after August 1, 2010 to be located at a specified minimum distance inboard of the outer shell of the ship's hull.

5C-5-3/Table 1A Combined Load Cases for Yielding and Buckling Strength Formulation

To align the Rules with the revision of MARPOL 73/78, ANNEX I, Reg. 12A, which requires fuel oil tanks of 600 m3 and over for ships delivered on or after August 1, 2010 to be located at a specified minimum distance inboard of the outer shell of the ship's hull.

5C-5-3/Table 1B Combined Load Cases for Fatigue Strength Formulation

To align the Rules with the revision of MARPOL 73/78, ANNEX I, Reg. 12A, which requires fuel oil tanks of 600 m3 and over for ships delivered on or after August 1, 2010 to be located at a specified minimum distance inboard of the outer shell of the ship's hull.

5C-5-3/Table 2 Design Pressure for Local and Supporting Members

To align the Rules with the revision of MARPOL 73/78, ANNEX I, Reg. 12A, which requires fuel oil tanks of 600 m3 and over for ships delivered on or after August 1, 2010 to be located at a specified minimum distance inboard of the outer shell of the ship's hull.

5C-5-4/Figure 1 Scantling Requirement Reference by Subsection

To align the Rules with the revision of MARPOL 73/78, ANNEX I, Reg. 12A, which requires fuel oil tanks of 600 m3 and over for ships delivered on or after August 1, 2010 to be located at a specified minimum distance inboard of the outer shell of the ship's hull.

Page 16: SVR Nandgi e

Notices and General Information

14 ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013

Part/Para. No. Title/Subject Status/Remarks 5C-5-4/21.13 (New)

Tank Bulkhead Between Fuel Oil Tanks

To align the Rules with the revision of MARPOL 73/78, ANNEX I, Reg. 12A, which requires fuel oil tanks of 600 m3 and over for ships delivered on or after August 1, 2010 to be located at a specified minimum distance inboard of the outer shell of the ship's hull.

5C-5-4/25.5 (New)

Main Supporting Members on Boundaries of Fuel Oil Tank

To align the Rules with the revision of MARPOL 73/78, ANNEX I, Reg. 12A, which requires fuel oil tanks of 600 m3 and over for ships delivered on or after August 1, 2010 to be located at a specified minimum distance inboard of the outer shell of the ship's hull.

5C-5-4/Figure 14 (New)

Transverse Tank Bulkhead Definition of Spans for Bulkhead with Fuel Oil Tank in The Cargo Hold or Under the Deckhouse

To align the Rules with the revision of MARPOL 73/78, ANNEX I, Reg. 12A, which requires fuel oil tanks of 600 m3 and over for ships delivered on or after August 1, 2010 to be located at a specified minimum distance inboard of the outer shell of the ship's hull.

5C-5-4/Figure 15 (New)

Longitudinal Tank Bulkhead Definitions of Spans for Bulkhead with Fuel Oil Tank in the Cargo Hold or Under the Deckhouse

To align the Rules with the revision of MARPOL 73/78, ANNEX I, Reg. 12A, which requires fuel oil tanks of 600 m3 and over for ships delivered on or after August 1, 2010 to be located at a specified minimum distance inboard of the outer shell of the ship's hull.

5C-5-4/27 (New)

Fuel Oil Tank Tops To align the Rules with the revision of MARPOL 73/78, ANNEX I, Reg. 12A, which requires fuel oil tanks of 600 m3 and over for ships delivered on or after August 1, 2010 to be located at a specified minimum distance inboard of the outer shell of the ship's hull.

5C-5-A1 Fatigue Strength Assessment of Container Carriers

To completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.

5C-5-A1/Table 3A Combined Load Cases for Container Carriers

To align the Rules with the revision of MARPOL 73/78, ANNEX I, Reg. 12A, which requires fuel oil tanks of 600 m3 and over for ships delivered on or after August 1, 2010 to be located at a specified minimum distance inboard of the outer shell of the ship's hull.

5C-5-A1/Table 3B (New)

Combined Load Cases for Container Carriers with Fuel Oil Tank in between Transverse Bulkheads

To align the Rules with the revision of MARPOL 73/78, ANNEX I, Reg. 12A, which requires fuel oil tanks of 600 m3 and over for ships delivered on or after August 1, 2010 to be located at a specified minimum distance inboard of the outer shell of the ship's hull.

5C-5-A1/Table 3C (New)

Combined Load Cases for Container Carriers with Fuel Oil Tank in Cargo Holds

To align the Rules with the revision of MARPOL 73/78, ANNEX I, Reg. 12A, which requires fuel oil tanks of 600 m3 and over for ships delivered on or after August 1, 2010 to be located at a specified minimum distance inboard of the outer shell of the ship's hull.

5C-5-A4 Hull Girder Ultimate Strength Assessment of Container Carriers

To completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.

5C-6-A1 Strength Assessment of Container Carriers – Vessels Under 130 meters (427 feet) in Length

To completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.

5C-A1 SafeHull Construction Monitoring Program

To completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.

5C-A2 ABS Construction Monitoring Program

To completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.

5C-7 Vessel Intended to Carry Passengers To reintroduces the requirements from the Guide for Building and Classing Passenger Vessels back into Part 5C of the Steel Vessel Rules and to completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.

Page 17: SVR Nandgi e

Notices and General Information

ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013 15

Part/Para. No. Title/Subject Status/Remarks 5C-8-11/3.5 (ABS) (New)

Interpretation of 5C-8-11/3.5 To restrict the application of 304 and 304L, and highlight that 316 and 316L can also pit if the conditions are unfavorable and the Molybdenum content is less than 2.5%.

5C-8-19 Summary of Minimum Requirements To update the listed products.

5C-10-4/Table 3 Application of the Requirements in 4-7-2/7.3 to Different Classes of Dangerous Goods Except Solid Dangerous Goods in Bulk

To align relevant requirements and references with 2009 consolidated edition of SOLAS as amended and 2007 edition of the Fire Safety Code.

Page 18: SVR Nandgi e

Notices and General Information

16 ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013

Part 7 “Rules for Survey After Construction”

The reference date which is indicated in the parentheses following the title of the requirement in this Part is the date that the requirement becomes effective [e.g., 7-1-1/7.5 “Prompt and Thorough Repairs” (1 July 2012) is to apply for vessels undergoing survey on or after 1 July 2012].

EFFECTIVE DATE 1 July 2012 – shown as (1 July 2012)

Part/Para. No. Title/Subject Status/Remarks PART 7 Rules for Survey After Construction 7-1-1/1.1 Chapters 1 through 9 Part 7 applies to the High Speed Naval Craft Guide and the OSV

Guide. The Guide for the Class Notation Environmental Safety (ES) has been superseded by the Guide for the Environmental Protection Notation for Vessels and the Guide for the Environmental Protection Notation for Offshore Units, Floating Installations, and Liftboats. (Incorporates Notice No. 1)

7-1-1/1.7.1(a) Oil Carrier To align the requirements with IACS UR Z11, rev. 4, which notes ESP vessels (Oil Tanker, ORE/OIL carrier, OIL/BULK/ORE carrier) may be subject to regulations requiring phase out. (Incorporates Notice No. 1)

7-1-1/1.7.1(d) Combination Carrier To align the requirements with IACS UR Z11, rev. 4, which notes ESP vessels (Oil Tanker, ORE/OIL carrier, OIL/BULK/ORE carrier) may be subject to regulations requiring phase out. (Incorporates Notice No. 1)

7-1-1/3.33 General Dry Cargo Vessel (ESDC) To align the requirements with IACS UR Z7.1 Rev. 8, which excludes double-skin general dry cargo ships, with double skin extending over the entire length and height (to the upper deck) of the cargo carrying area from the requirements of Z7.1. (Incorporates Notice No. 1)

7-1-1/7.1.3 (New)

<No Title> To Provide reference for ABS requirements on hull testing, when required. (Incorporates Notice No. 1)

7-1-1/7.5 Prompt and Thorough Repairs To align the requirements with IACS UR Z7 Rev. 19 which gives guidance on course of action when isolated damage is found, which does not affect structural integrity. (Incorporates Notice No. 1)

7-3-1/1 General To align the requirements with IACS UR Z7 Rev. 17 which requires examination of coating condition behind insulation of refrigerated cargo spaces at representative locations. (Incorporates Notice No. 1)

7-3-2/1.7.3 Vessels Subject to SOLAS XII/9.1 and 9.2

To align the requirements with IACS UR Z1 rev. 4 that refers to IMO Resolution A.997(25) as amended by IMO Resolution A.1020(26), that requires testing of bilge well alarms. (Incorporates Notice No. 1)

7-3-2/5.11.1(i)i) <No Title> To align the requirements with IACS UR Z16, rev. 3 corr. 1 2011, which clarifies that nondestructive testing for type C tanks for Liquefied Gas Carriers may not be totally dispensed. (Incorporates Notice No. 1)

7-3-2/5.21.4(c) Special Periodical Survey No. 3 (10 < Age ≤ 15 years)

To align the requirements with IACS UR Z10.3 requirements, which require that all transverse bulkheads in all ballast tanks are subject to Close-Up Survey during Special Survey No. 3 and No. 4 and subsequent. (Incorporates Notice No. 1)

7-3-2/5.21.4(d) Special Periodical Survey No. 4 and Subsequent Special Periodical Surveys (Age > 15 years)

To align the requirements with IACS UR Z10.3 requirements, which require that all transverse bulkheads in all ballast tanks are subject to Close-Up Survey during Special Survey No. 3 and No. 4 and subsequent. (Incorporates Notice No. 1)

7-6-2/1.1.1(e) Fuel Oil and Lubricating Oil Pumps To provide Surveyor verification during Annual Machinery Surveys for requirements outlined in 4-6-5/3.3.1, 4-6-5/5.3.1, 4-6-5/7.7.1. (Incorporates Notice No. 1)

Page 19: SVR Nandgi e

Notices and General Information

ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013 17

Part/Para. No. Title/Subject Status/Remarks 7-6-2/1.1.1(f) Circulating Water Pumps To provide Surveyor verification during Annual Machinery Surveys

for requirements outlined in 4-6-5/3.3.1, 4-6-5/5.3.1, 4-6-5/7.7.1. (Incorporates Notice No. 1)

7-6-2/1.5 (Deleted)

Vessels Carrying Vehicles To remove duplicate requirements. Requirements already included in Annual Hull (7-3-2/1.17) and Machinery (7-6-2/1.1). (Incorporates Notice No. 1)

7-A-14 Guide for Surveys Based on Preventative Maintenance Techniques

To ensure that all the existing Guides embedded in the current Rules are completely integrated into the Rules. To clarify multiple misunderstandings. To create a notation that will trigger an AS-PM survey, as well as give additional credit to those owners with more than 50% of their equipment enrolled into the PMP program. To create additional awareness of the RCM Program, and how it operates. To update guide to reflect changes in technology. To include a section for bearing wear monitor systems. To introduce the concept of Condition Based Maintenance (CBM). (Incorporates Notice No. 1)

EFFECTIVE DATE 1 January 2013 – shown as (2013)

Part/Para. No. Title/Subject Status/Remarks PART 7 Rules for Survey After Construction 7-1-1/1.1 Chapters 1 through 9 To update references. The High-Speed Craft Guide and Offshore

Support Vessel Guide are upgraded to Rules.

7-1-1/1.5 Appendix To completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.

7-9-11/1 Oil Spill Recovery – Standby Class 1 and 2 Notation

To specify the oil carrier survey requirements which are applicable for Class 1 and Class 2. To introduce hydro test requirements for piping in recovered oil tanks and recovered oil piping in other tanks during the Special Survey.

7-9-11/3 (New)

Oil Spill Recovery – Capability Class 1 and 2 Notation

To introduce survey requirements for the Oil Spill Recovery – Capability Class 1 and 2 notations

7-A-1 Underwater Inspections in Lieu of Drydocking Surveys

To completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.

7-A-2 Surveys of Voyage Repairs to Hull Structures

To completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.

7-A-3 Vessel Lay-up and Reactivation To completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.

7-A-4 Additional Information for Hull Thickness Measurement

To clarify that many of the recommendations embedded in this Guide are not meant to be requirements.

7-A-10 Bronze and Stainless Steel Propeller Castings

To completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.

7-A-10/1.5.1 New Propeller Inspection To require surface NDT (PT) of weld repair areas on new Bronze propellers over 2 m (78 in.) in diameter.

7-A-10/1.5.5(b) Severity Zones To clarify that all welding procedures for bronze and stainless steel propellers are to be reviewed by ABS Materials department irrespective of the zone of repair.

Page 20: SVR Nandgi e

Notices and General Information

18 ABS RULES FOR BUILDING AND CLASSING STEEL VESSELS . 2013

Part/Para. No. Title/Subject Status/Remarks 7-A-10/3.7.1 General To clarify that all welding procedures for bronze and stainless steel

propellers are to be reviewed by ABS Materials department irrespective of the zone of repair.

7-A-11 Repair and Cladding of Shafts To completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.

7-A-12 Ultrasonic Examination of Carbon Steel Forgings for Tail Shafts

To completely integrate all the existing Guides embedded in the current Rules into the Rules by dropping the word “Guide” from the title, changing embedded recommendations to requirements, and by sending all embedded Guides through the Committee review process.