Stephanie Jones Stebbins, PESeaport Environmental Programs

Page 2: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Outline

• Port of Seattle overview

• Sustainable Asset Management

• Resource Conservation during Operations

• Cost Recovery

2

Page 3: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Port of Seattle Overview

• 3 operating divisions

• Airport (15th busiest in US)

• Seaport (container port, bulk cargo,

cruise, fishing fleet, grain)

• Real Estate

3

Page 4: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

• Seaport Terminals map to be inserted

here

4

Page 5: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Seaport Asset Portfolio

Current replacement value > $2.0 billion

Terminal 5

Pier 2

Terminal 91

Terminal 86

Pier 69

Pier 66

Pier 48

Terminal 10

Terminal 18

Pier 16/17

Terminal 30

Terminal 25

Terminal 37/46

5

Page 6: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Seattle Seaport Business model

• Primary:

– Port builds facilities

– Tenant leases facilities – long - term

– Tenant responsible for maintenance

• Secondary:

– Port builds facilities

– Tenants rent facilities/pay dock moorage

– Port responsible for maintenance

6

Page 7: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Seaport capital assets

• Docks & piers

• Pavement

• Rail

• Buildings

• Cranes

• Utility infrastructure

• Roads & bridges

7

Page 8: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Our Challenge

• What do we own?

• What is the age, condition, and cost to

replace?

• How long will they last based on

appropriated maintenance funding?

• How long do we want it to last?

• Who is responsible for maintaining?

• How do we prioritize?

8

Page 9: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Sustainable Asset Management

Policy adopted 2007

• Focus on total cost of facility ownership to link capital investments & ongoing operating costs

• Benchmarking – industry best practices to maximize efficient use of funds & conserve natural resources

• Integrate environmental & financial performance – reduce total ownership costs AND reduce environmental impacts

9

Page 10: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Environmental asset management

• CEO goal – be the cleanest, greenest, most energy efficient Port in the US

• Our approach:

1. Achieve real environmental benefits

2. Make business sense• Cost effective

• Enhance customer value

• Enhance long term competitiveness

10

Page 11: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Total cost of ownership

• Present value of:

– Initial capital cost

– Ongoing operations & maintenance

– Renewal at end of useful life

• Adjust for:

– Business model

– Changes in needs over useful life

– Levels of service

11

Page 12: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Changing the model to total cost of

ownership

• Much of total ownership costs occur after design and construction

• Decisions driving these costs occur before detailed design is completed

• Change long standing approach - lowest initial cost

• Change internal/external expectations

– Design, engineering, project management

– Maintenance

12

Page 13: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Detailed facility assessments at the

Seattle Seaport

• In-house facility condition assessments of 80-100 year old facilities

• Detailed - to building & utility system level

• Determine useful life, ongoing maintenance costs, renewal/replacement costs

• Combine with business planning for facility long term use

14

Page 14: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Maintenance Goals

• Where Port responsible

– Focus on preventive maintenance

• Where tenant responsible

– Developing & documenting joint expectations

– Documenting asset condition

– Auditing tenant maintenance performance

15

Page 15: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Resource Conservation

16

Page 16: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Resource Use and Conservation

• Sustainable Facility Management

• Energy Conservation Efforts:

– Port of Seattle Headquarters: 43% reduction

in energy use: $126K annual savings

– Pier 66: 58% reduction in energy use: $156K

annual savings

17

Page 17: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Installed VFDs

Replaced all exit lights

with LED

Turned off unneeded lighting

Conservation Initiatives

18

Page 18: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Energy Savings Strategies

• New HVAC contract

• Repaired deferred maintenance items

• Negotiated a long-term contract w/ Seattle

Steam

• Changed the way we operate equipment

19

Page 19: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Worked w/ Mechanical Contr. to modify HVAC equipment operation

Scheduled larger spaces off

20

Page 20: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

21

Chiller Plant

–Put the chillers on a schedule

–Raised chilled water set point

Page 21: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Electricity Savings

–2002 usage 4,115,704 kwh

–2006 usage 1,710,903 kwh

2,404,801 kwh

58.4% less electricity used

$163,000 2006 savings

$200,000 2009 savings22

Page 22: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Cost Recovery

23

Page 23: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Past Cost Summary: $102 Million

Footnote: Excludes environmental cleanup costs for: T5 Southwest Harbor Project RA1, RA-2, RA3, RA5; T30 cleanup costs between 1984 and 2000.

24

Lower Duwamish, $25,409 , 25%

T91, $7,163 , 7%

T5 PSR, $20,893 , 21%

East Waterway, $26,768 , 27%

HI Uplands, $6,299 , 6%

T117 Uplands , $4,021 , 4%

T117 Sediments, $3,597 , 4% T30, $2,031 , 2%

Other, $3,836 , 4%

Figure 1a. Total Environmental Cleanup Cost "Gross" 1991 to 2009 $102 Million

Page 24: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Cost Recovery by Site: $65 Million

25

Lower Duwamish, $(21,117), -33%

T5 PSR, $(17,654), -27%

T117 Uplands , $(10,860), -17%

East Waterway, $(5,229), -8%

HI Uplands, $(5,423), -8%

T91, $(1,733), -3%T117 Sediments,

$(1,510), -2%

Other, $(1,417), -2%

Page 25: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Cost Recovery by Source ($65 Million)1991 to 2009

26

LITIGATION Future Liability, ($11,155,000), -

17%

GRANT, ($13,677,182), -21%

INSURANCE, (7,309,662), -11%LITIGATION, (5,670,682),

-9%

REIMB, (18,798,691), -29%

TRUST, (8,304,504), -13%

Page 26: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Cost Recovery by Year and Source

$0

$5

$10

$15

$20

$25

$30

1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009

Mill

ion

s

Cost Recovery by Year and Source ($ Millions)

TRUST

REIMB

LITIGATION

INSURANCE

GRANTS

LITIGATION - Future Liability

Footnote: only includes cost recovery through 2009 6/30/2009

27

Page 27: Sustainable Asset Management and Managing Environmental costsaapa.files.cms-plus.com/SeminarPresentations... · Stephanie Jones Stebbins 206-787-3818 jonesstebbins.j@portseattle.org

Stephanie Jones Stebbins

206-787-3818

[email protected]