© 2016 Pegasystems 1
Surviving in a Hybrid Agile-Waterfall World
Steven Martin, PMI-ACP, CSPO, CSM
Senior Program Manager – Methodology & Governance
Pegasystems Project Office
October 25th, 2016

© 2016 Pegasystems 2
Workshop Objectives
• Gain insights into practices for “smoother” hybrid
Agile – Waterfall environments
• Provide some inspirations for next steps to try at your agency

© 2016 Pegasystems 3
Agenda
• Simple “demographics” of attendees in our session today
• What’s our problem?
• Tips and Tricks
• Q&A

© 2016 Pegasystems 4
Let’s set some expectations…
• This will not be an introductory talk on Agile or
scaling Agile frameworks, such as SAFe or LeSS
– This is intended for those with foundational
knowledge assumptions of Agile and Scrum
– Chances are, you are experiences issues with
Agile and Waterfall together
• We have 40 mins today
– Spar some thought processes of next steps
– But, will likely not solve your lingering
organizational circumstances
Expectation
is the root of
all heartache.
William Shakespeare

© 2016 Pegasystems 5
So…How you doin’?

© 2016 Pegasystems 6
Please Stand and Remain Standing if…
You are using
a Waterfall approach
at your agency
right now

© 2016 Pegasystems 7
Please Stand and Remain Standing if…
You are using both
Agile and Waterfall approaches
at your agency
right now

© 2016 Pegasystems 8
Please Stand and Remain Standing if…
You are have been using Agile at
you agency for…
• More than 1 year
• More than 2 years…
• More than …

© 2016 Pegasystems 9
Raise your hand if…
At your agency, you are using…
• Scrum
• Kanban
• Lean or Lean Startup
• Other Agile approaches?

© 2016 Pegasystems 10
How well are your projects going at your Agency?
Things are great!
Gimme a high 5!
Not bad, but could
use improvement.
I’m so on fire I’m
literally going to
combust right now.

© 2016 Pegasystems 11
Small Group Exercise
• Brainstorm at your tables:
“What are your largest challenges
with hybrid Agile – Waterfall approaches
at your organization?”
• 1 idea per card/sticky note
• Keep at “headline” (3-5 words)
• Start by writing one or two ideas as an individual
• Then share around the table
• As a table, pick one or two highest challenges
• Time box: 4 mins

© 2016 Pegasystems 12
You just experienced the first tip…
• Establish a small “task force” (7 +/- 2) to float between teams
– Note: did not say sit “above” teams
– Cross-functional team empowered to make decisions and try things
• Internal, Partner, Pega
– Relentless focus on enabling hybrid environment to work better
• Establish and prioritize a backlog of blockers,
impediments, risks, issues, etc. of working
together as a hybrid environment
• Limit Work In Process (WIP) to focus and resolve
– Pilot with a team
– Learn
– Expand reasonably and responsibly

© 2016 Pegasystems 13
Some foundational concepts reminders…

© 2016 Pegasystems 15
Scrum is an Empirical Process
• Scrum is based upon applying an empirical process control mindset
• An empirical process embraces change versus discouraging it
– Knowledge comes from experience
– Make decisions based on what is known
• The 3 components of any empirical process are:
– Inspection
– Adaptation
– Transparency
Source: Sutherland, Schwaber, “The Scrum Guide”, 2016

© 2016 Pegasystems 16
How does this impact hybrid Agile – Waterfall environments?
• Transitioning from focus on individual efficiency to organizational effectiveness
– An agile-waterfall hybrid approach impacts the organization, not just IT
– Go from “command and control” to creating environment for accountable
progress to solving highest value problems
• Working in hybrid environments does not favor one approach over the other
– Don’t force one to work with another
– Take the “best” from both, go from there
• Yes, you will have to do something different from today
– Change involves feelings of loss
– Good change management / communication essential

© 2016 Pegasystems 17
Considerations for adopting practices
Some considerations we may talk about today
• Syncing up teams
• Dividing your product releases into “independent” chunks
• Keeping stakeholders up to date
Use caution in using practices discussed here directly
Empower your “task force” to evaluate, adjust, experiment
for your agency

© 2016 Pegasystems 18
Some tips & approaches to consider…

© 2016 Pegasystems 19
Keeping Teams In Sync

© 2016 Pegasystems 20
Let’s pull inspiration from scaling models
• We are not advocating one scaling model
over another
• Consider the models with respect to your
organization
–Where does it make sense to adopt
Scaling Agile approaches?

© 2016 Pegasystems 21
Large Scale Scrum Framework (LeSS)
Source: http://less.works/

© 2016 Pegasystems 22
Scaled Agile Framework (SAFe) – 4 Level
Source: www.scaledagileframework.com

© 2016 Pegasystems 23
Next Release Sprint 0
Team 1
Team 2
Team 3
Team 4
Team 5
Case Study: Mixing Scrum and Waterfall Teams in 1 ProgramW
FS
cru
m
Current Release Hardening
Wks 1-2 Wks 3-4 Wks 5-6 Wks 7-8 Wks 9-12

© 2016 Pegasystems 24
Example Calendar for a 2 Week IterationMonday Tuesday Wednesday Thursday Friday
Sprint Planning
Sprint Planning
(Next Sprint)
Sprint Retro
Sprint Review
Daily Scrum Daily ScrumDaily Scrum
Daily Scrum Daily ScrumDaily ScrumDaily Scrum Daily Scrum
Daily Scrum
SoS
SoSSoS
SoS
I
I
SM CoE
SM CoE
I

© 2016 Pegasystems 25
Some things that helped this program be successful
• Within each location, Teams were together (not split across multiple sites)
– All roles needed to get their increment of working product to “Done”
• All 3 Scrum teams had the same:
– Cadence for a sprint (2 weeks)
– Start and end date
• “Expert” resources at each physical site
– Product, Technology, Quality, Agile Coach/Lead, etc.
• Integration team (“task force”) floated across entire 5-team program
– Not directly working on features, but ensuring well oiled machine
• Technical environments available
– Dev, QA, Staging then Prod

© 2016 Pegasystems 26
Keeping Product In Sync

© 2016 Pegasystems 27
Release Roadmaps
• Release Roadmaps help set “scope” over a series of deployments
• Some reasons for Release Roadmaps:
– Gains consensus around the direction/vision,
especially if multiple partners involved
– Helps to establish reasonable architecture runway
– Avoids the “last/loudest” priority problem
– Prevents “too large” releases early in program
(everything plus the kitchen sink…)
– Becomes a filter for user story creation and
backlog prioritization
• Caution: A roadmap is not a contract…it will likely change over time

© 2016 Pegasystems 28
GUI
Business Logic / Rules
Database
Rel 1 Rel 2
Releases as Vertical Slices

© 2016 Pegasystems 29
Name of Release /
Version (to where)
Release date
Key Features:
1. Feature A
2. Feature B
3. Feature C
Theme: Prove “?”
For <stakeholder X>,
this release provides
<what value>
Roadmap: Example Template
• Release date, driven by:
– An event or specific dates/schedule
– Level of functionality needed
• Name of Release / Version
– Make name meaningful
– Indicate where release will happen:
• Internal delivery to a platform, other team,
or release train
• Distribution to Production
• Theme
– Compelling reason to use by whom?
– Significant business value to the organization
• Planned feature set
– High-level descriptions of system services
that delivers value to the user/customer

© 2016 Pegasystems 30
Full CC exp’n/Mobile POC
R4 (to PROD)
1. Monitor performance
2. Run mobile POC
with client subset
(TBD)
3. Revise forms with
critical/moderate
improvements as
needed
• For remaining client
subgroups, submit
claim request for autos
via call center
• Pilot POC for mobile
with subgroup #1
June August October
1. Update/expand 2
forms with feedback
2. Auto validate
processing
confirmation
3. Auto send email
confirmation
4. Validate/revise
training materials
• For client subgroups 2-
4, submit claim request
for autos via call center
1. Revise forms with
critical/moderate
improvements and
bug fixes
2. Validate
performance
3. Establish POC for
mobile (customer
driven) claim
submission
• For client subgroups
5-10, submit claim
request for autos via
call center
• Create POC for mobile
app
First CC expansion
R2 (to PROD)Second CC expansion
R3 (to PROD)
April
1. Simple 2 forms (data
entry, data validation)
2. Send data to sub
system to initiate
processing
3. Validate manually in
sub system
4. Manually send email
confirmation
• For client subgroup #1,
submit claim request for
autos via call center
Pilot CC
R1 (to PROD)
Roadmap: Example Template

© 2016 Pegasystems 31
Release Planning Approach Overview
Show N Tell
Refresh Strategy
Story Identification
& Sizing
Sequence Epics,
Start Story ID
Reconcile &
Tweak
Lunch Lunch
Day 1 Day 2
Mo
rnin
gA
ftern
oo
n
Exec Readout Exec Readout

© 2016 Pegasystems 32
Day 1 Afternoon / Day 2 Morning – In Action…
• Epics are printed from system for all items in release
for all teams (both Agile and WF)
• Business and Technology force-rank prioritize
– Items at top of table are highest priority
• Estimate / confirm size of epic(s)
– Teams given preset # of stickies, representing
available time
– Color-coded by team
– Teams put stickies on stories
• Understand dependencies between teams
– Orange stickies represent critical dependencies

© 2016 Pegasystems 33
Sprint 1 Sprint 3Sprint 2
Theme T1S1 Theme T1S2 Theme T1S3
Theme T2S1 Theme T2S2 Theme T2S3
Theme T3S1 Theme T3S2 Theme T3S3
PO Team 1
Chief
Product
Owner
(CPO)
PO Team 2
PO Team 3
Day 9: Next Sprint
Look Ahead
Day 4: 3 to 5 Sprint
Look Ahead
The Product Owner Forum

© 2016 Pegasystems 34
Sprint 1 Sprint 3Sprint 2
Theme T1S1 Theme T1S2 Theme T1S3
Theme T2S1 Theme T2S2 Theme T2S3
Theme T3S1 Theme T3S2 Theme T3S3
PO Team 1
Chief
Product
Owner
(CPO)
PO Team 2
PO Team 3
Day 9: Next Sprint
Look Ahead
Sprint 4
Theme T1S4
Theme T2S4
Theme T3S4
D4:
3-5 D9:
Next
Day 4: 3 to 5 Sprint
Look Ahead
The Product Owner Forum

© 2016 Pegasystems 35
Sprint 1 Sprint 3Sprint 2
Theme T1S1 Theme T1S2 Theme T1S3
Theme T2S1 Theme T2S2 Theme T2S3
Theme T3S1 Theme T3S2 Theme T3S3
PO Team 1
Chief
Product
Owner
(CPO)
PO Team 2
PO Team 3
Day 9: Next Sprint
Look Ahead
Sprint 4
Theme T1S4
Theme T2S4
Theme T3S4
D4:
3-5
D4:
3-5D4:
3-5D9:
Next
D9:
NextD9:
Next
Day 4: 3 to 5 Sprint
Look Ahead
The Product Owner Forum

© 2016 Pegasystems 36
Enabled “the business” to see
the forest and the trees
at the same time
The Product Owner Forum

© 2016 Pegasystems 37
Example Calendar for a 2 Week IterationMonday Tuesday Wednesday Thursday Friday
Sprint Planning
Backlog
Sync-up
Sprint Planning
(Next Sprint)
Sprint Retro
Sprint Review
Daily Scrum Daily ScrumDaily Scrum
Daily Scrum Daily ScrumDaily ScrumDaily Scrum Daily Scrum
Daily Scrum
Refine
(Next Sprints)
Refine
(Next Sprints)
Refine
(Next Sprints)
Refine
(Next Sprints)
Refine
(Next Sprints)
Refine
(Next Sprints)
Refine
(Next Sprints)
Refine
(Next Sprints)
PO Forum
PO Forum
SoS
SoSSoS
SoS
I
I
SM CoE
SM CoE
I

© 2016 Pegasystems 38
Keeping Stakeholders Informed

© 2016 Pegasystems 39
Example Calendar for a 2 Week IterationMonday Tuesday Wednesday Thursday Friday
Sprint Planning
Backlog
Sync-up
Sprint Planning
(Next Sprint)
Sprint Retro
Sprint Review
Daily Scrum Daily ScrumDaily Scrum
Daily Scrum Daily ScrumDaily ScrumDaily Scrum Daily Scrum
Daily Scrum
Refine
(Next Sprints)
Refine
(Next Sprints)
Refine
(Next Sprints)
Refine
(Next Sprints)
Refine
(Next Sprints)
Refine
(Next Sprints)
Refine
(Next Sprints)
Refine
(Next Sprints)
PO Forum
PO Forum
SoS
SoSSoS
SoS
Enablement Team
Enablement Team
I
I
SM CoE
SM CoE
I
Status
Status
Release Planning*
*not every 2 wks…
Exec Review

© 2016 Pegasystems 40
Metrics…
Backward-looking, inactionable,
vanity metrics
Forward-looking, actionable,
enable decision-making
• % Complete (if not using
working software as measure
of progress, such as Reqts,
Des, Testing, etc.)
• # Teams using Agile
• # People trained on Agile
• Release burn-ups of working
software
• Effectiveness of teams (star
charts)
• Actionable scorecards

© 2016 Pegasystems 41
Example Release Burn-Up
41
Image Source: http://agilewhys.blogspot.com/2015/03/how-to-create-release-burn-up-chart.html

© 2016 Pegasystems 42
Example Radar Chart (1 Team)
0.0
1.0
2.0
3.0
4.0
5.0Ownership
Scrumability
Accountability
Quality focused
Collaboration
Resilience
Team Average
Combo Coach/SM Rating
0.0
1.0
2.0
3.0
4.0
5.0Ownership
Scrumability
Accountability
Quality focused
Collaboration
Resilience
Team Average
Coach Rating
After 5 Sprints (1 Team) After 10 Sprints (1 Team)

© 2016 Pegasystems 43
Example Post-Release Scorecard
Business Expectations:
• % User Story Definition Before
Coding Begins (%)
• Did Release meet release
expectations (1-5, user)
Quality:
• % Code Coverage for Unit Testing (%)
• % Code Coverage for Functional
Testing (%)
• # Runs/Day for Unit Tests (#)
• # Runs/Day for Functional Tests (#)
Communication:
• % Items in Communication Plan
Completed (%)
• Effectiveness of Communications
(1-5, user)
Planning:
• # Story Points/Day (#)
• Velocity Variance (%)

© 2016 Pegasystems 44
Governance…
• Status Reporting
• Tactical
• Not fun (blame and shame)
• Advisory & alternatives discussions
• Strategic
• More fun (possibilities and how
we solve problems)
• Every other week Executive reviews
• Approx. 2 days after traditional Sprint Reviews
• Key working software functionality (wrt problems we’re solving)
• Where we were going next
• Where we needed help
• What did they need to know so they wouldn’t be caught off-guard

© 2016 Pegasystems 45
Implications of Change
• Benefits to using Agile approach is to
harness information to help drive
greater value and reduce risk
― Change is unpredictable, but
expected
― How to acknowledge change when
we see it, but not panic
Hey,
Change.
Hey.

© 2016 Pegasystems 46
Benefits Obtained from Implementing Agile
Source: 10th Annual State of Agile Survey, VersionOne, 2016.

© 2016 Pegasystems 47
Role of Change in Scrum: Exploit feedback to maximize business value
• Change requests can be added to the backlog as a new (revised)
user story at anytime
― Still need to go through prioritization, like any backlog item.
― The new (revised) user story may be prioritized as the highest
value backlog item
― If high enough priority, then start to estimate (size)

© 2016 Pegasystems 48
Roles & Responsibilities
• Your Product Owner should be
empowered to make these prioritization
decision
― If your PO must get approval before
proceeding, then this is a sign your PO
is not empowered…

© 2016 Pegasystems 49
Do I still need a Change Control Board?
• Actually, it is recommended
― Not all your projects in your organization may be “Agile” or “Scrum”
• Agile doesn’t mean “free reign for everybody.” There needs to be
reasonable guardrails. Reasonable…
• Need to have clear threshold / intake criteria, such as:
― Does it impact teams outside of your project or program?
― Is there a financial limit (e.g. do as long as its 1 sprint or less of
work, with a certain burn rate per sprint)?
― Do you impact overall release timeframe?
― Does this impact core vision of company? Product?

© 2016 Pegasystems 50
Tips for Change Management in Agile
• Make sure understanding of embracing change is expected from
project inception
― Project Charter / Kickoff
― Clear roles & responsibilities
― PO, Stakeholders in Reviews, Teams, etc.
― Guardrails for a change management board
― Expected behaviors for change
• Hold those involved to expected behaviors during product builds
― Especially for management and customers/stakeholders
― Takes greater discipline to be self-organized
― With great power comes greater responsibility…

© 2016 Pegasystems 51
Q&A

© 2016 Pegasystems 52
Closeout

© 2016 Pegasystems 53
Key Nuggets to Take Away…
• Establish your agile-waterfall “working together” task force
• Create prioritized backlog of issues specific to your agency
• Will impact beyond IT
• Don’t force one way to work with the other
• Use practices from others as inspiration
• Use critical thinking to determine hypothesis for next step
• Experiment with pilot team
• Learn and adapt as needed
• Expand responsibly

© 2016 Pegasystems 54
twitter.com/pega
linkedin.com/company/pegasystems

© 2016 Pegasystems 55
Coming soon – Next in Agile Webinar Series
Lalig Musserian
Senior Program Manager,
Methodology and Governance
Pegasystems Project Office
Topic: Defining Agile Change Control
Date: Wednesday, October 26, 2016
Time: 10:00 AM Eastern Daylight Time
Info/Register: www.pega.com/agile

© 2016 Pegasystems 56