Surveying RTP MOD
-
Upload
prakash-kumar-kumar -
Category
Documents
-
view
8 -
download
2
description
Transcript of Surveying RTP MOD
-
i
Module 2.5: Survey & Investigation Contents 1.0 Introduction.............................................................1 2.0 Types of Survey & Investigation.........................................................1
2.1 Socio-Economic Survey ......................................................................1
2.1.1 Level of Presentation ...................................................................2
2.2 Engineering Survey and Investigations .................................................7
2.2.1 Use of Satellite Images and Remote Sensing Technology ..................8
2.2.2 Online Satellite Images .............................................................. 12
2.2.3 Total Station Survey .................................................................. 13
2.2.4 Codes and Manuals and Guidelines for Survey & Investigation ......... 18 3.0 Survey and Investigation related to Urban Road Project..................23
3.1 Introduction ................................................................................... 23
3.2 Scope............................................................................................ 24
3.3 Stages in Project Preparation ............................................................ 25
3.3.1 Pre-feasibility study ................................................................... 26
3.3.2 Feasibility Study/Preliminary Project Report Preparation.................. 26
3.3.3 Detailed Engineering and Plan of Construction ............................... 26
3.3.4 Land Acquisition........................................................................ 27
3.3.4 Land Acquisition........................................................................ 28
3.4 Guiding Principles of Route Selection and alignment Improvement ......... 28
3.5 Traffic Surveys and Analysis ............................................................. 29
3.6 Reconnaissance Survey.................................................................... 34
3.6.1 Purpose ................................................................................... 34
3.6.2 Survey Method.......................................................................... 34
3.6.3 Study of Survey Sheets, Maps etc................................................ 34
3.7 Preliminary Survey .......................................................................... 35
3.7.1 Purpose ................................................................................... 35
3.7.2 Survey Procedure ...................................................................... 36
3.7.3 Modern Trends in Surveying........................................................ 38
2.7.4 Survey Instruments ................................................................... 38
3.7.5 Map Preparation........................................................................ 44
3.8 Feasibility Report ............................................................................ 44
3.9 Final Location Survey....................................................................... 46
3.9.1 Purpose ................................................................................... 46
3.9.2 Bench Marks............................................................................. 46
3.9.3 Longitudinal Sections and Cross-Sections...................................... 46
3.9.4 Proper Protection of Points of Reference ....................................... 48
3.10 Soil and Material Surveys ............................................................... 48
3.10.1 Composition of Soil .................................................................. 48
3.10.2 Soil Texture Classification ......................................................... 49
-
ii
3.10.3 Soil Investigation..................................................................... 50
3.10.4 Degree of Expansion of Fine Grades Soils .................................... 50
3.11 Road Drainage Studies ................................................................... 55
3.11.1 General .................................................................................. 55
3.11.2 High Flood Level ...................................................................... 55
3.11.3 Depth of Water-Table ............................................................... 56
3.11.4 Ponded Water Level ................................................................. 56
3.11.5 Surface Run-off ....................................................................... 56
3.12 Cross- Drainage Structures ............................................................. 57
4.0 Water Supply Project.....................................................................57
4.1 Desk Studies .................................................................................. 57
4.2 Pre-design Stage............................................................................. 57
4.2.1 After Field Survey...................................................................... 58
4.3 Design Development Stage............................................................... 60
4.4 Prior Studies & Choice of Location Water Resources.............................. 60
4.5 Route Alignment of Transmission Line ................................................ 61
4.6 Ground Investigation ....................................................................... 61
5.0 Sewerage Project. ...................................................................62
5.1 Basic Information ............................................................................ 63
5.1 Basic Information ............................................................................ 64
5.1.1 Physical Aspects........................................................................ 64
5.1.2 Developmental Aspects .............................................................. 64
5.2 Project Surveys............................................................................... 65
5.2.1 Preliminary Project Surveys ........................................................ 65
5.2.2 Detailed Project Surveys ............................................................ 65
6.0 Solid Waste Management .................................................................66
6.1 Functional Elements of Solid Waste Management ................................. 66
6.2 Composition, Characterization and Quantification of Solid Waste ............ 69
6.3 Field Investigations ......................................................................... 71
6.3.1 Sample Survey ......................................................................... 71
6.3.2 Quantification ........................................................................... 72
6.3.4 Chemical Characterisation .......................................................... 72
6.3.5 Solid Waste Collection Routing .................................................... 76
6.4 Surveys for Identification of Disposal Sites....................................... 78
6.4.1 Preliminary Boreholes and Geophysical Investigation ...................... 79
6.4.2 Site Investigation and Site Characterization .................................. 80
6.4.3 Subsoil Investigation.................................................................. 81
6.4.4 Ground Water/Hydrogeological Investigation ................................. 81
6.4.5 Topographical Investigation ........................................................ 82
6.4.6 Hydrological Investigation........................................................... 82
6.4.7 Geological Investigation and Seismic Investigation ......................... 82
-
iii
6.4.8 Waste Characterisation .............................................................. 83
6.4.9 Leachate Investigation ............................................................... 83
List of Annex
Annex I: Guiding Principles Covering Route Selection
Annex II: Checklist of major operations involved in the Survey and Investigation
Annex III: List of Laboratory Test to be Conducted for Road Embankments
Annex IV: Seismic Zones of India
Annex V: Sample Road Sections
Annex VI: Satelitte Data Order Form
Annex VII: Sample TOR for Surveying
-
1
1.0 Introduction The process of urbanization has created a huge gap between demand and supply
of urban infrastructure services such as roads, water supply, sewerage,
sanitation, solid waste management etc. To fulfil the gap between demand and
supply, a most important step is probably to get a clear idea about the existing
situation. Proper survey and investigation is therefore very important to assess
the qualitative and quantitative demand.
Lack of adequate, investigations has been one of the major factors in many urban
infrastructure project, resulting into inaccurate assessment of costs, necessitating
substantial revision during the course of execution. Many times the actual project
implementation may get delayed due to inaccurate survey and investigation. Thus
the extent and quality of investigations have a strong influence on selection of the
most cost-effective alternatives, and execution of the job itself.
Survey and investigation not only includes technical surveys but may also include
social-economic surveys based on the objective of the project. This Module is
therefore structured to discuss the most commonly used survey and investigation
methods during planning and project preparation of many of the urban
infrastructure projects like, water supply, sewerage, solid waste management of
road projects.
2.0 Types of Survey & Investigation Survey and investigation required for any urban infrastructure project can be
categorized in two broad categories as below:
Socio-economic Survey Engineering Survey
2.1 Socio-Economic Survey
Population data is the most important information required for any kind of
infrastructure project, as it is the base for demand assessment for a particular
infrastructure for present as well as for future demand.
As far as population data is concerned, the Indian Census is the largest single
source of statistics on the people of India. With a history of more than 125 years,
this reliable, time tested exercise has been bringing out a veritable wealth of
statistics every 10 years beginning from 1872 when the first census was
conducted non-synchronously in different parts of India.
Office of the Registrar General and Census Commissioner, India, New Delhi, is
responsible for conducting the decennial population census.
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 2
2.1.1 Level of Presentation The All India Series presents Census statistics, all in one volume, at the following
administrative levels:
India level (for Rural and Urban residences separately State and Union Territory level (for Rural and Urban residences separately) District level (for Rural and Urban residences separately) Urban Agglomerations or City level (for Urban residences only)
The State Series presents Census statistics, in separate volumes for each state or
union territory, at the following administrative levels:
State or Union Territory level (for Rural and Urban residences separately) District level (for Rural and Urban residences separately) Tahsil level (for Rural and Urban residences separately) Urban Agglomerations, City or Town level (for Urban residences only)
2.1.2 List of Tables available with Census Department A Series: Population Tables
This series provides basic population tables of the 1991 Census at different levels
of presentation. There are in all 16 Tables in this series.
B Series: Economic Tables
The data on main workers, marginal workers, non workers and non workers
seeking work are presented in this series of tables. Data on classification of main
and marginal workers by industrial classification of work, occupation, age and
educational level, non workers by main activity, age and educational level, and
those seeking work by age, educational level and whether they have worked
before are available. There are in all 31 Tables in this series.
C Series: Socio - Cultural Tables
This series of tables give the data on age, marital status, educational level, school
attendance, mother tongue, bilingual, trilingual and religion. Data on marital
status, educational level and school attendance are available cross classified by
age groups while data on school attendance in the age group 5-19 years has also
been classified by work participation. There are in all 16 Tables in this series.
D Series: Migration Tables:
Data on migration characteristics like place of birth, place of last residence,
reason for migration and duration of residence at the place of enumeration are
available through these tables. Data on educational level, economic activity and
age distribution of the migrants are also available in these tables. There are in all
17 Tables in this series.
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 3
F Series: Fertility Tables
This series of tables provide data on female age at marriage, number of children
ever born and number of children surviving to ever married women and birth to
currently married women during the last year. Data on age at marriage have
been classified by duration of marriage while all other data are classified by age
of the woman. At state level data are also available by religion, educational level
and work status of the woman. There are in all 32 Tables in this series.
H Series: Housing and Household Amenities
These tables give information on housing and household amenities, viz., the type
of material used for construction; tenure status, number of rooms and household
size; availability of electricity, drinking water supply (by source) and toilet
facilities to the household and type of fuel used for cooking. There are in all 17
Tables in this series.
SC ST Series: Tables on Scheduled Castes and Scheduled Tribes
These tables give information on the Scheduled Castes and Scheduled Tribes
population of the country. Most of the tables are generated at
State/District level. The tables provide population, demographic and
socio- cultural characteristics of the group on individual Scheduled
Castes and Scheduled Tribes
2.1.3 List of State Publications The State publications are brought out separately for each state and union
territory as listed on the right.
These cover the following subjects:
Population Totals Part I: Administration Report Part II: A Series - Population Tables Part III : B Series - Economic Tables Part IV-A : C Series - Socio - Cultural Tables Part IV-B : Language and Religion Part V : D Series - Migration Tables Part VI : F Series - Fertility Tables Part VII : H Series - Housing Tables Part VIII : Tables on Scheduled Castes and Scheduled Tribes Part IX : Town Directory PART X: Special Studies PART XI: Census Atlas PART XII: District Census Handbook
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 4
Part IX: Town Directory
T - 1: All India Town Directory
T - 2: Civic and other amenities in the Notified Slums of Class I & II Towns
2.1.4 Soft Data All data available with census department is now a days available in CD form with
user friendly software. The following abbreviations of civic status of cities or
towns are commonly used while presenting the data in the Table on Final
Population Totals in CD
C.B. - Cantonment Board/Cantonment
C.M.C. - City Municipal Council
E.O - Estate Office
G.P. - Gram Panchayat
I.N.A. - Industrial Notified Area
I.T.S. - Industrial Township
M - Municipality
M.B. - Municipal Board
M.C. - Municipal Committee
M.Cl. - Municipal Council
M.Corp. - Municipal Corporation/Corporation
N.A. - Notified Area
N.A.C. - Notified Area Committee/Notified Area
Council
N.P. - Nagar Panchayat
N.T. - Notified Town
N.T.A. - Notified Town Area
S.T.C. - Small Town Committee
T.C. - Town Committee/Town Area Committee
T.M.C. - Town Municipal Council
T.P. - Town Panchayat
T.S. - Township
C.T. - Census Town
O.T. - Out Growth
Sample Input window and output data sheet of a user-friendly Census CD has
been given below.
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 5
Sample Input Window
Sample Output Datasheet
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 6
Maps showing different demographic indicators can be prepared very easily Based
on the census. Some sample demographic maps prepared from census data has
been given below.
Map showing Temporal Change in Population and Density
Map showing Temporal Demographic Indicators
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 7
2.2 Engineering Survey and Investigations Frequently it is understood that surveying is the science and art of measuring
distances, both horizontal and vertical and angles on or near the surface of the
earth. It is also said that survey and investigation is an orderly process of
acquiring data relating to the physical characteristics of the earth and in particular
the relative position of points and the magnitude of areas. Some of the common
survey types has been listed below.
1. Land surveys, which fix property lines, calculate land areas and assist with the transfer of real property from one owner to another.
2. Engineering surveys, which collect the data needed to plan and design engineering projects. The information ensures the necessary position and
dimension control on the site so that the structure is built in the proper
place and as designed.
3. Informational surveys obtain data concerning topography, drainage and man-made features of a large area. This data is portrayed as maps and
charts.
Another way to make a simple classification is:
1. Geodetic surveys are precise and over large areas require the curvature of the earth to be considered. Distances and angle measurements must be
very, very accurate. A wide variety of techniques are used including
triangulation, traversing, trilateration, levelling and astronomical direction
fixing.
2. Plane surveys, which consider the surface of the earth to be a plane. Curvature is ignored and calculations are performed using the formulas of
plane trigonometry and the properties of plane geometry. These may be
considered accurate for limited areas.
Sub-categories of the major classes provide more insight into the various fields of
surveying as follows:
Property surveys determine boundary lines, property corners; rights-of-way provide data necessary for the preparation of land sub-divisions.
Cadastral surveys are executed by the Federal Government in connection with the disposal of vast areas of land known as the public
domain.
Route surveys are necessary for the design and construction of various engineering projects such as roads, railways, pipelines, canals and power
lines.
Industrial surveys, or optical metrology, are used in the aircraft and other industries where very accurate dimensional layouts are required.
Topographic surveys are performed to gather data necessary to prepare topographic maps. These are multicolour contour maps portraying the
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 8
terrain; and rivers; highways, railways, bridges and other man-made
features.
Hydrographic surveys map the shorelines of bodies of water; chart the bottom of streams, lakes, harbours and coastal waters; measure the flow
of rivers; and assess other factors affecting navigation and water
resources. The sounding of depths by radar is involved in this type of
survey.
Mine surveys determine the position of underground works such as tunnels and shafts, the position of surface structures and the surface
boundaries.
Aerial surveys use photogrammetry to produce a mosaic of matched vertical photographs, oblique views of landscape and topographic maps
drawn from the photographs.
Construction surveys fix elevations, horizontal positions and dimensions for construction projects.
Control surveys provide basic horizontal and vertical position data. These are called datum. For most surveying work the vertical position of points in
terms of height above a curved reference surface is mean sea level. The
Australian Geodetic Datum (AGD) is the surface that passes through mean
sea level at thirty tide gauges. Heights obtained from the GPS satellite
system do not refer to the AGD, but to the mathematical reference surface
(the ellipsoid). The difference between these two surfaces is known as the
geoid ellipsoid separation.
2.2.1 Use of Satellite Images and Remote Sensing Technology This technique is used with the help of satellites. At present it gives a resolution
of the order of 6 meters. Photographic products of imagery are available from
National Remote Sensing Agency, Hyderabad on scales of 1:12,500, 1:25,000
and 1:50,000. digital products are also available in floppy cartridge and tapes.
The cartridge/tape can be digitally processed in the computer and the image on
the monitor can be interpreted with the possibility of enhancement of quality
through manipulation of image processing software.
Major advantages of satellite imagery is its repeatability as orbiting satellites visit
the same spot on earth every few weeks. Thus, the latest information regarding
the physical features (like, the extent of a town or urban area, etc.) can be
obtained to update on available map. The information on natural resources
namely, geology, geomorphology, land use, soil status (water logging, erosion,
etc.), drainage, forest extent, etc. as available may be most useful input for the
planners of road alignment.
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 9
Satellite remote sensing for urban and land development can be used to gather
strategic planning information pertaining to a district or an entire city. High
resolution satellite imagery from satellite sensors such as GeoEye-1, Quick Bird,
IKONOS, SPOT-5 aerial photography and LIDAR incorporated into a GIS
(Geographic Information Systems) and CAD (Computer Aided Drafting) has
gained popularity among Planners, Developers and Engineers for large scale
mapping of any region for most urban and land development applications.
Information from satellite images or aerial photography when combined with GIS
mapping is used for analysis in evaluating construction costs as well as
environmental impacts of alternative routes for utility and transport corridors;
land cover and land use classification; identifying population groups at risk where
human intervention is most needed to limit and prevent hazards during
development stages.
Satellite image data is highly useful for creating or updating base maps and
detecting major changes in urban land cover and land use from imagery such as
LANDSAT and ASTER satellite sensors due to their multi-spectral band
combinations, which allows for frequent coverage and overlaying of different time
sequences to classify soil and vegetation areas for the proposed development
area(s). Other applications include:
Updating information on road networks and other urban infrastructure Collection and analysis of data on population density, distribution and
growth
Preparation of housing typologies Analysis of watersheds
Geodetic and mapping experts create two-dimensional interactive mapping
projects by overlaying third-party data, such as land cadastre ownership
information, census data, and labels of geographic features.
Mapping: Image Maps
In most areas of the world,
medium- and small-scale maps
either have not yet been produced,
or are outdated and inaccurate.
The ability to extract a wide variety
of information, and to locate
features at 1:25,000 scale without
ground control, provides an
unprecedented opportunity to
produce accurate, relatively
inexpensive maps of entire
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 10
countries, including areas previously inaccessible due to terrain. Frequent satellite
coverage offered by Digital Globe can make such areas easily accessible and
inexpensive to update.
60-centimeter panchromatic imagery will provide an alternative for costly
updating of inaccurate medium- and small-scale maps. The value of satellite
imagery is based on the comparison of map and imagery. Infrastructure changes
can be quickly detected and updated on maps.
Mapping: Feature Extraction
Digital Globe 60-centimeter imagery
can be used to identify and locate a
variety of features, such as street
centrelines, building footprints,
parking lots, and elevation contours to
within a few meters horizontal and
vertical accuracy.
60-centimeter pan-chromatic imagery.
with extracted features: red lines
indicate buildings, yellow lines
delineate contour lines, blue lines
depict transportation boundaries.
Mapping: Infrastructure Monitoring
City, regional, and national
governments, as well as public and
private utilities worldwide, can use
high spatial resolution satellite
imagery to identify, inventory,
monitor, and plan for a wide variety of
urban and residential infrastructure
projects. Streets, highways, bridges,
railroads, canals, buildings of all sizes,
and other infrastructure can be
accurately identified and located within
a few meters of their true horizontal
position.
2.4-meter multi-spectral imagery, sharpened with 60-centimeter panchromatic, is
an excellent tool for identifying and monitoring various types of infrastructure.
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 11
Mapping: Utilities & Boundaries
Planning, construction, permitting, and
service activities are more efficient
when 60-centimeter imagery is
combined with vectors and point data
to identify parcel boundaries and utility
location.
60-centimeter panchromatic imagery,
combined with point data, will
accurately identify parcel boundaries
and utility locations.
Environmental: Storm Water Runoff
60-centimetre pan-sharpened multi-spectral imagery can be used to measure
impervious surfaces, such as roofs, streets, and parking lots. Pervious surfaces,
such as tree- and grass-covered areas can also be measured. Applying runoff
coefficients to the area of each surface type can provide the best available
estimates for non-point source water pollution. By adding parcel boundaries, it is
possible to provide estimates of runoff per parcel in order to assess storm sewer
fees.
Original near-infrared image
Color-classified by surface type
Parcel boundaries
2.4-metre multispectral imagery, sharpened with 60-centimetre panchromatic
imagery, will clearly illustrate different surface types.
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 12
2.2.2 Online Satellite Images Now a days some websites are available, which gives satellite images at a very
good zoom level, e.g., www.googleearth.com, www.wikimapia.com.
Source: wikimapia.com
Source: wikimapia.com
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 13
These images are useful to get an idea about the existing land use of any study
area, however these images should not be used for preparing detailed project
report or detail designing as many times accuracy of the images are questionable.
Some such images has been given below which gives a clear idea of exiting land
use.
Small Format Aerial Photography (SFAP)
In case of large projects with mapping as one of the main objectives conventional
aerial photography in traditional format (23 cm X 23 cm) may also be useful.
There are at least three known agencies in India for such aerial photography,
namely, the National Remote Sensing Agency (NRSA), Hyderabad, Air Survey
Company, Calcutta and the Indian Air Force
All aerial photography work requires clearance from the Ministry of Defence.
The major advantages of SFAP are
Very large scale true colour photo enlargements can be done in scales upto 1:1,000 to 1:2,000 (upto scales of 1:10,000). Acquisition plans along
side roads can be suitably made in scale 1:4,000
Monitoring of urban areas, villages and environment along the corridor are possible at comparatively lower cost than ground surveys.
2.2.3 Total Station Survey Total station survey can be very useful for any new urban infrastructure project
like water supply, sewerage, roads etc, in an area, which is having very low
settlement or existing structures. As in case of urban fringe areas, where new
development is expected to come.
A total station is an optical instrument used in modern surveying. It is a
combination of an electronic theodolite (transit), an electronic distance measuring
device (EDM) and software running on an external computer.
With a total station one may determine angles and distances from the instrument
to points to be surveyed. With the aid of trigonometry, the angles and distances
may be used to calculate the coordinates of actual positions (X, Y, and Z or
northing, easting and elevation) of surveyed points, or the position of the
instrument from known points, in absolute terms.
The data may be downloaded from the theodolite to a computer and application
software will generate a map of the surveyed area. Some total stations also have
a GPS interface which combines these two technologies to make use of the
advantages of both (GPS - line of sight not required between measured points;
Traditional Total Station - high precision measurement especially in the vertical
axis compared with GPS) and reduce the consequences of each technology's
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 14
disadvantages (GPS - poor accuracy in the vertical axis and lower accuracy
without long occupation periods; Total Station - requires line of sight observations
and must be setup over a known point or within line of sight of 2 or more known
points).
Measurement of distance is accomplished with a modulated microwave or infrared
carrier signal, generated by a small solid-state emitter within the instrument's
optical path, and bounced off of the object to be measured. The modulation
pattern in the returning signal is read and interpreted by the onboard computer in
the total station, and the speed-of-light lag between the outbound and return
signal is translated into distance. Most total stations use a purpose-built glass
prism as the reflector for the EDM signal, and can measure distances out to a few
kilometres, but some instruments are "reflectorless", and can measure distances
to any object that is reasonably light in colour, out to a few hundred meters. The
typical Total Station EDM can measure distances accurate to about 0.1 millimetre
or 1/1000-foot, but most land surveying applications only take distance
measurements to 1.0 mm or 1/100-foot.
Box Sample Terms and condition for tender for Total Station Survey
1. Chief Engineer, _______Corporation invites sealed quotation from appropriate and
eligible Firms/Consultancy Firm dealing with surveying work for the following project:
(i) XYZ Land .measuring approximately 18 hects.
(ii) Camping land at , at .measuring approximately 15 hects.
1.1 Time allowed for completion - 10 Days from the date of issue of work order for
.Project & 15 days for Project.
2. Description of work
The work involves
2.1 Surveying of .. land at .. measuring approximately 18 hects. and
Camping resort land at , at . measuring approximately 15 hects.
Using total station incorporating all existing features.
2.2 Establishment of bench mark (Horizontal control points) on the ground at Strategic
locations to carry our details surveys in future if required.
2.3 Supplying of Site Plan to proper scale with proper Horizontal control points duly
existing features with dimensions and offsets. The Boundary shall be properly established
with proper dimensions / angles etc. in order to facilitate of features with ease.
2.4 Supplying of Contour Maps with Contour interval of 1mtr drawn to a proper scale.
2.5 Supplying of sectional details along strategic points.
2.6 All drawing shall be generated through computers with appropriate software
2.7 Original tracing shall be handed over to the corporation which shall be the property of
XYZ corporation
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 15
2.8 An overall site plan to a scale of 1:500 or to a suitable scale in single sheet shall be
submitted.
2.9 Detailed Sheets to 1:200 scales or to any convenient scale with all internal details shall
be submitted.
2.10 Indicating 50 meters, 200 mtrs. and 500 mtrs. line from HTL.
2.11 Indicating location of naturally grown trees, Creek, wells, electric transmission lines,
telephone lines, pipelines, nallah, adjoining roads etc.
3. Eligibility criteria:
Only those firms /consultants which fulfill the following the following minimum criteria are
eligible to tenders.
3.1 The tenderer should have satisfactorily completed at least one similar nature of work.
Proof of having executed similar works shall be enclosed.
3.2 The firm should have well-qualified and experienced Surveyors associated with them.
They shall submit proof of qualifications/ experience of the persons associated with the
project.
3.3 The firms shall possess modern survey instruments viz. Total Station and appropriate
Computer Software and facilities for plotting etc.
4. Final decision making authority
The ..corporation reserves the right to accept or reject any application and to
annul the qualification process and reject all applications at any time, without there by
incurring any liability to the affected applicants or specifying the grounds for the
. action.
Rate & Payment
The rate includes for the following items of work per Ha. of land area.
5.1 All field works related with the Survey
5.2 Supplying of Drawing as mentioned in Para-4 of Press Notice (8 copies each)
5.3 Supplying of original tracing to the Department
5.4 Payment towards all service charges, tax if any.
5.5 All unforeseen works required for completing the work.
5.6 Expenditure to visit the site from Chennai including air fare and ship fare.
5.7 The payment shall be made after successful completion of work to the satisfaction of
the Engineer- In-charge and handing over of the drawing to .corporation.
5.8 ..corporation shall arrange accommodation for the staff visiting for the
survey.
5.9 The payment will be made in the single bill on first and final bill and no part payment
will be made during execution of the work.
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 16
6. Other Conditions
6.1 EMD amounting to Rs. 12500/- in the form of call deposit from any scheduled bank
issued in favor payable at ..should be enclosed. The tender
document without EMD will be rejected.
6.2 The last date for submission of tender is 3.00 pm on 25th June 2007 at
. and it will be opened at 3.30 pm on the same day.
Output of Total Station Survey
The major outputs of a total station survey are listed below.
Site Plan to proper scale with proper Horizontal control points duly existing features with dimensions and offsets.
Site Contour Maps with Contour interval of 1mtr, 5mtr etc. Sectional details along strategic points Drawing generated through computers with appropriate software An overall site plan to a scale of 1:500 or to a suitable scale Detailed Sheets to 1:200 scales or to any convenient scale with all internal
details indicating 50 meters, 200 mtrs. and 500 mtrs. line from HTL, and
indicating location of naturally grown trees, Creek, wells, electric
transmission lines, telephone lines, pipelines, nallah, adjoining roads and
some output maps of total station survey is given below.
Contour Map of Project Area
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 17
Land Use Map
Three Dimensional Terrain Modeling
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 18
2.2.4 Codes and Manuals and Guidelines for Survey & Investigation The development of various infrastructures in the urban need to carry out
different activities of survey and investigation as follows:
List of IRC & IS Codes
1. IRC: SP: 13 2004 Guidelines for Design for Small Bridges and Culverts 2. IRC: SP: 19 2001 Manual for Survey, Investigation & Preparation of
Road Project (1st Revision)
3. IRC: SP: 42 1994 Guidelines for Drainage 4. IRC: 69 1977 Space Standards for Roads in Urban Areas 5. IRC: 70 1977 Guidelines on regulation and Control of Mixed Traffic in
Urban Areas
6. IRC: SP: 50 1999 Guidelines for Urban Drainage 7. IRC: 52 1981 Recommendations about alignment Survey & Geometric
Design of Hill Roads
8. IRC: SP: 48 1998 Hill Road Manual 9. IRC: 102 1988 Traffic Studies for Planning Bypasses around Towns 10. IS:7537- 1974 Road Traffic Signals 11. IRC: 106 1990 Guidelines for capacity of Urban Road in Plain Areas 12. IS:1498 -1970 Classification & Identification of Soil for General
Engineering Purpose (Reaffirmed 1997)
13. IS: 1892 1979 Code of Practice for Sub-surface Investigation for Foundation (Reaffirmed 1997)
14. IS:2132 - 1986 Code of Practice for Thin Wall Rube Sampling of Soil (Second Revision) (Reaffirmed 1997)
15. IS: 2720 Part 1 to Part 41 Method of Test for Soil 16. IS: 6403 1981 Code of Practice foe Determination of Breezing Capacity
of Shallow Foundation
17. IS:8763 1978 Guide for undisturbed Sampling of Sand and Sandy Soil (Reaffirmed 1997)
18. IS:9640 1980 Split Spoon Sampler (Amendment 2) (Reaffirmed 1997)
19. IS:10042 1981 Code of Practice for Site Investigation for Foundation in Gravel Boundary Deposit (Reaffirmed 1997)
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 19
List of Manuals of Central Pubic Health and Environmental Engineering Organization (CPHEEO)
1. CPHEEO Manual on Water Supply & Treatment, May 1999 2. CPHEEO Manual on Sewerage & Sewage Treatment, Dec 1993 3. CPHEEO Manual on Solid Waste Management, 2000
Survey Activities to be performed for Infrastructure Development Project
1. Study of topographical survey sheets 2. Study of agricultural soil 3. Study of Geological & meteorology cal maps 4. Aerial Reconnaissance 5. Ground Reconnaissance with Compass, abney level, Alti-meter, Pedometer
etc. instruments
6. Locality map 7. Longitudinal sections/cross section 8. Establishment of Bench Mark 9. Soil information 10. Construction material information 11. Locating Physical features such as buildings, burial grounds, cremation
grounds, places of worship
12. Crossing of pipelines, railway, stream/river 13. Map preparation 14. Environmental Impact Study 15. Viable, technical soundness, alternative final selection 16. Socio-economic profile 17. Traffic survey 18. Soil investigation in detail for Foundation Soil, Borrow area etc. 19. Drainage studies 20. HFL & ponded water level 21. Depth of subsoil water table 22. Surface runoff 23. Site Selection for Cross drainage structure 24. Collection of hydraulic and foundation data 25. Detailed maps preparation
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 20
Table 2.1: Survey & Investigation for Urban Works
Sr.
No. Types of Project
IS/IRC/CPHEEO
Vol. (As per
clause 1.2.1)
Survey
Activities To be
Done (As per
clause 1.2.2)
Road related Infrastructure
Development Projects
1 Stone paving in Local Streets 1-4, 10-12 5-8,10,16,19,22
2 Road up-gradation in local streets Do 5-11,19,22
3 Cement concrete work in local & collector
streets
Do 5-11,18,22
4 Asphalt road resurfacing work in collector.
Sub arterial & Arterial road
1-19 1 - 25
5 New construction of road in local,
collector & arterial streets.
1-19 1 - 25
6 New Road construction work for rapid
transmission work.
1-19 1 - 25
7 Integrated Street development in urban
area
2,3,12,13 5-8,10,16,17,22
Water supply & Sewerage related
Infrastructure Development Projects:
1 Enhancing the existing water
supply/sewerage systems
20,21 1,5-
8,10,12,13,20-
22,26
2 Rehabilitation & reinstatement of the
existing water supply/ Sewerage systems
20,21 1,5-
8,10,12,13,20-22
3 Construction of new water/sewerage
treatment plant
12-19 1 - 25
4 Development of water supply / sewerage
system in new township
New laying of water/sewerage pipelines
in collector, sub arterial and arterial
streets
20,21 1 - 25
5 New laying of water/sewerage pipelines
in collector, sub arterial and arterial
streets
20,21 1,5-8,10-13,20-
23,26
6 New construction work of ESR/UGR in
local area of the city
20,21 1 25 except 2 &
17
7 Retrofitting & strengthening work of ESR
& UGR
20,21 6,9,10,18-22,26
8 Augmentation of supply network in the
new merged area of the urban sprawl in
existing limit
20,21 1 25 except 2 &
17
Solid Waste Management related
Works
1 Development of new land fill site in the
urban area
22 1-6,9,11-16,18-
22,24,25
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 21
Sr.
No. Types of Project
IS/IRC/CPHEEO
Vol. (As per
clause 1.2.1)
Survey
Activities To be
Done (As per
clause 1.2.2)
2 Procurement of new trucks, tractors,
hand Lorries, tricycles for augmentation
of transportation work
22 Nil
3 Procurement of containers & dustbins in
the urban area
22 Nil
4 Construction of new solid waste
composting plant in the urban area
22 1,3-6,9-15,18-
22,25
5 Procurement of mechanical equipments
for segregation of SW
22 Nil
Housing related Works:
1 Integrated Housing Development Scheme
in Urban area
1-25 except
17,23,24
2 Slum development project in the urban 1-25 except
17,23,24
3 Rehabilitation of slums within the urban
area
1-25 except
17,23,24
4 Construction of low-cost sanitation in the
slum area within the urban
-do-
5 Construction of community center, health
centers in urban area
-do-
Measures of Length 12 inches = 1 foot
3 feet = 1 yard
5.5 yards = 1 rod, pole or perch
220 yards = 1 furlong
8 furlongs = 1 mile=1760yards
5000 feet = 1 canal mile
Metric Units of Length 1 megametre = 1,000,000 metres 1 hectokilometre = 100,000 metres 1 myriametre = 10,000 metres 1 kilometre (km) = 1,000 metres 1 hectometre (hm) = 100 metres 1 dekametre (dkm) = 10 metres 1 metre (m) = 10 dm 1 decimetre (dm) = 1/10 metres = 10 cm 1 centimetre (cm) = 1/100 metres = 10 mm 1 millimetre (mm) = 1/1000 metres 1 micron or micrometre = 1/1000 millimetre = 0.00039 inch 1 millimicron = One millionth of a millimetre
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 22
The metre is used in ordinary measurements, the centimetre or millimetre in
reckoning very small distances or measurements, and the kilometre for roads or
great distances.
Conversion Factors 1/25 inch = 1 millimetre
1 inch = 25.4 millimetre or 2.54 cm
1 foot = 30.48 cm or 0.3048 metres
1 yard = 0.9144 metres or 91.44 cm
1 rod = 5.029 metres
1 furlong = 0.201 km or 201.168 metres
1 mile = 1.609 km or 1609 metres
1 millimetres = 0.03937 inch
1 centimetre = 0.3937 or 2/5 inch
1 decimeter = 3.937 inches
= 0.328 feet
1 metre = 39.37 inches
= 3.281 feet
1 decametre = 32.81 feet
= 1.094 yards
1 hectometre = 328 ft 1 in.
1 kilometre = 3280 ft 10 ins.
= 1093.63 yards
= 4.97 furlongs
= 5/8 or 0.621 mile
Square Measures or Measures of Surface 144 sq. inches = 1 sq. foot
9 sq. feet = 1 sq. yard
1 Hectare = 2.471 acre
484 sq. yards = 1 sq. chain
43,560 sq. ft. = 1 acre
640 acres = 1 sq. mile
An acre is the area of a square whose side is 208.71 ft. long Metrix Units 1 sq. kilometre (km2) = 1,000,000 sq. metres = 100 ha
1 sq. hectometre = 10,000 sq. metres = 100 ares = 1 ha
1 sq. dekametre = 100 sq. metres = 1 ares
1 sq. metre (m2) = 1 sq. metres = 100 sq. dm
1 sq. decimeter (dm2) = 1/100 sq. metres = 100 sq. cm
1 sq. centimetre (cm2) = 1/10,000 sq. metres = 100 sq. mm
Sq. metre = centare or centiare; hetare = sq. Hectometre
are= sq. Dekametre
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 23
The sq. metre is the primary unit of ordinary surfaces or small areas. The are or
sq. dekametre, hectare or sq. hectometer are the units of land measures. Conversion Factors 1 sq. inch = 6.45 sq. centimetre
= 645.2 sq. millimetre
1 sq. foot = 929.0 sq. centimetre
= 0.093 sq. metres
1 sq. yard = 0.836 sq. metres
= 0.836 centares
1 acre = 4046.86 sq. metres
= 40.47 ares
= 0.4047 hectare
1 sq. mile = 2.590 sq. kms
= 259 hectares
= 640 acres
1 sq. millimetre = 0.00155 sq. ins.
1 sq. centimetre = 0.155 sq. ins.
1 sq. decimetre = 15.50 sq. ins.
1 sq. metre or a centare = 10.76 sq. ft. or 1.196 sq. yards
1 sq. dekametre or 1 are = 11,959.85 sq. yards = 2.471 acres
1 sq. hectometer or 1 hectare = 247.10 acres
1 sq. kilometre = 0.3861 sq. miles
3.0 Survey and Investigation related to Urban Road Project 3.1 Introduction Preparation of Infrastructure project involves a chain of activities, such as, field
surveys and investigations, selection of road alignment, carrying out various
designs, preparation of drawings and estimates etc. to be compatible with
technical requirement, consistent with economy, it is essential that every project
should be prepared after thorough investigations and collecting all relevant
information and evaluating all possible alternatives.
The extent and quality of investigations have a strong influence on selection of
the most cost-effective design, estimation of quantities, cost and execution of the
job itself. As such, accuracy and completeness of surveys deserves very special
attention in project preparation. The objective can be achieved by carrying out
the project preparation work either departmentally or with the help of
consultants. In any case, it should be ensured that experts having the required
knowledge are deployed on the work. Use of modern instruments and survey
techniques ensure high degree of accuracy and can speed up the work. Quality
Assurance Plan is required to be drawn before the start of field investigations.
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 24
Adequate funds should be earmarked for the work of survey, investigation and
project preparation. Estimation of realistic fund and time requirement needed for
project preparation will go a long way in making the project preparation a
success. It will be found that in the long run, such investment pays more than for
itself in the form of well prepared and cost effective projects, orderly schedule of
work and timely completion.
Systematic presentation of project details is no less important. The project
document is the very basis of technical, administrative and financial sanction of a
project. It is also crucial for accurate execution of work in the field. The project
should, therefore, be comprehensive enough for proper appreciation of the
proposals as well as easy understanding of the details. This Manual lays down
guidelines both for survey and investigations and presentations of the project
details.
Surveying methods and instruments used at the beginning of the twentieth
century new light weight metals and more advanced calibration techniques
resulted in development of lighter and more accurate instruments needed for the
precise layout requirements of high speed railroads and roads.
Use of aerial photography for mapping began in the 1920s, and advanced rapidly
during the following decades. By 1950 photogrammetric methods had
revolutionized survey procedures, especially in route surveying and site selection.
3.2 Scope
It should be understood clearly that the extent of operations involved in surveys
and investigations including the detailing of the individual aspects, would depend
very much on the size and scope of each project. Depending on needs of the
situation, one or more phases of investigations might be curtailed, telescoped or
made more extensive than prescribed in the manual.
The order in which various surveys are discussed in the manual should not be
taken to mean that such work must strictly follow the same pattern or sequence.
Some of the surveys could easily be initiated in advance and carried out
simultaneously overlapping each other. For example, some results of soil and
materials survey and study of cross-drainage structures would be needed as an
essential input to the Feasibility Report. But more detailed investigations on these
aspects may be continued in the detailed engineering phase. It should be upto
the Engineer-in-charge to exercise his discretion and adopt a flexible approach.
The requirements of the funding agencies or the authority according
administrative approval may also result in rescheduling the sequence of work and
in redefining the extent of coverage of each work.
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 25
3.3 Stages in Project Preparation Broadly, the stages involved in the preparation and sanction of project are:
1. Pre-feasibility study 2. Feasibility study/Detailed project report preparation 3. Detailed engineering and plan of construction
However it should be noted that JnNURM project cycle is having two major stages
namely Preparation of CDP and Preparation of DPR
Chart 3.1 Main survey required for Urban Road Project
Planning
Reconnaissance Survey: Map Study, Aerial Reco., Ground Reco., General Soil Study
Detail Study Final Route: Centre line marking, Existing properties, Long/Cross section, Detailed Drainage Study, HFL and ponded level, CD Works, EIA
Pavement Design Sub grade base course
Bituminous: Soil Investigation & Material Survey
Feasibility Study 1. Primary Survey: Traffic Survey,
Establishment of BMS, Topographical survey with instruments, Socio-economic, H/H Survey
2. Secondary Survey: Land Acquisition, Revenue map/ City Map, Census data, Facility accommodation survey, Geo-tech. i.e. Soil Investigation
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 26
3.3.1 Pre-feasibility study In some cases, specially for externally funded and BOT projects, it may be
necessary to prepare a pre-feasibility report to enable a funding agency or private
financier to appreciate the broad features of the project, the levels of financial
involvement and probable returns. This may be done on the basis of
reconnaissance survey by collecting information on the present status of the road,
deficiency/distress identification, development potential, environmental impact,
traffic data (present and future), approximate estimation of cost and an economic
analysis. The economic analysis may involve traffic allocation studies, assessment
of resource generation potential, funding pattern and risk. Location of toll plaza
sites may also need to be identified.
3.3.2 Feasibility Study/Preliminary Project Report Preparation The feasibility study is intended to establish whether the proposal is acceptable in
terms of soundness of engineering design and expected benefits from the project
for the investments involved. The feasibility report enables the funding agency to
appraise the project for financial variability and accord approval. This approval is
commonly known as Administrative Approval (AA) in the Road departments/Public
Works Departments in the country. When international funding is involved, the
Feasibility study forms a basis for an investment decision.
3.3.3 Detailed Engineering and Plan of Construction The detailed engineering covers detailed alignment surveys, soil and materials
surveys, pavement design studies, drainage studies, environment management
plan based on environment impact assessment studies, detailed drawings,
estimates and implementation schedules and documents. On the basis of such
work, Technical Approval and Financial Sanction (TA and FS) are accorded to the
project, enabling it to be executed.
Basically detailed study is done to cover technical feasibility, economic analysis,
financing viability, social and economic acceptability and legal validity.
The following figure gives a flow chart of the operations involved in project
preparation.
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 27
Stages in Project Preparation
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 28
3.3.4 Land Acquisition
The process of land acquisition needs to be started immediately after finalizing
the alignment.
Provision of the appropriate Land Acquisition Act will govern the various steps to
be followed in the process of land acquisition. Depending on the quantum of land
acquisition, creation of separate land acquisition authority may also be sometimes
necessary. Acquisition of Government land, Private Land, Forest Land and land
falling under Costal Regulation Zone, etc. will attract different acts/regulations.
The various steps in land acquisition, namely, appointment of exclusive
competent authority, if required declaring intention of acquisition, issuing notices
and giving hearing to the affected parties, joint measurements, final notices and
acquisition of the land, etc. require considerable time and need to be closely
monitored to acquire the land within the desired time limit.
Temporary and permanent structures coming in the alignment, tress need to be
cut, including those in the forest lands, need specific attention for obtaining
permission/valuation from the Competent Authority. Similarly, obtaining
permission of the ministry of Forest and Environment for the Forest land and the
land coming in the coastal regulation zone need to be processed in time.
Innovative acquisition such as that adopted by Ahmedabad Urban and
Development Authority may provide faster ways for acquisition.
Identifications and acquisition of land for borrow areas, quarries etc. also need to
be started in advance in case of large projects, such as, national highway project
and expressway projects.
3.4 Guiding Principles of Route Selection and alignment Improvement The fundamental principle of route selection and alignment improvement is to
achieve the least overall cost on transportation, having regard to the costs of
initial construction of the road facility, its maintenance and road user cost, while
at the same time, satisfying the social and environmental requirements. To
achieve this objective, it will be necessary to make a detailed investigation before
the alignment is finally decided. Factors that should be in view in the process are
listed in Appendix-1. It should be understood that all these factors may not be
applicable to each and every road project and some of them even if applicable,
may not be feasible in many circumstances. For each case, the Engineer-in-
charge has to exercise his own judgment to reach an optimum compromise
solution in the light of the fundamental principle of minimum transportation cost
enunciated earlier.
Where the project involves improvements to an existing road, every effort should
be directed towards removing the inherent deficiencies with respect to
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 29
Plan and profile Sight distance/visibility in horizontal as well as vertical plan Curve implements Carriageway, shoulder and roadway width Cross-drainage structures Road side drainage provisions as well as area drainage considerations Safety features
Any disregard of these aspects may well lead to unnecessary expenditure, since
at a later date the alignment may again have to be improved at considerable
extra cost. It is, therefore, imperative that the final centre line of the road with
respect to which, the improvements are designed and are to be carried out is
fixed with great care in the light of ultimate geometric requirements and
economy. The other important point is removal of structural deficiencies with an
eye on future needs with respect to pavement, culverts, road and area drainage
requirements, etc.
Proper location and orientations of cross-drainage structures is an important
factor in the selection of the road alignment. Their importance increases with
their length and cost. In general for bridges having length between 60 to 300 m,
siting of the bridges as well as alignment of the approaches will have equal
priority and should be well co-ordinated. For bridges of length more than 300 m,
siting for the bridges will be primary guiding factor in route selection.
Apart from engineering factors, like social and environmental impact of the
proposal should be fully kept in view in terms of such aspects as air pollution,
damage to life systems, soil erosion, drainage pattern, landscaping, disruption of
local communities, etc.
3.5 Traffic Surveys and Analysis Information about traffic is indispensable for any road project since it would form
the basis for the design of the pavement, fixing the number of traffic lanes,
design of intersections and economic appraisal of the project, etc.
Traffic surveys required to be conducted in connection with the preparation of
road project are as under:
a) Classified Traffic Volume Counts b) Origin Destination Surveys c) Speed and delay studies d) Traffic Surveys for the Design of Road junction e) Traffic Surveys for Replacing Level Crossings with over
Bridges/Subways
f) Axle Load surveys
g) Accident Records
In urban area traffic volume surveys must include bicycle traffic as one of traffic
category. If need require separate bicycle tracked may be planed.
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 30
Table 3.1: Proforma 1: Classified Traffic Volume Count Survey (IRC: SP:19-2001)
Road Name: Section: From ____________to_____________ Location Km.: Direction Towards: Road No.: Station No.: Date & Day: Hour: Additional Information: Weather:
Fast Moving Vehicles
Bus Truck Agri. Tractor
Slow Moving Vehicles
Time Two
Wheeler
Three
Wheeler/
Auto
Rickshaw
Car/
Jeep/
Van/
Taxi Mini Full 2-
Axle
Multi
Axle
Artic/
semi
Artic
With
Trailer
Without
Trailer cycle
Cycle
Rickshaw
Bullock
Cart Hoarse
Others (Pl. Specify Drawn)
00-15
15-30
30-45
45-60
Total
Source: IRC: SP 19, 2001 Name & Signature of Enumerators: ________________________
Name & Signature of Supervisor: __________________________
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 31
Table 3.2: Proforma 2(a): Origin & Destination (O-D) Survey (Freight Traffic). (IRC: SP:19-2001)
Name of Road: Road No.: Location at Km: Weather: Towards: Date: Day: Time: Sr. No. Particulars
Registration No.
Type of Vehicles & Axle Configuration
Make & Model Vehicles Particulars
RLW/ULW
Commodity Type
Quantity (Tonnes/Litre)
Origin (Name of place & District/State/Country)
Commodity/ O-D Particulars
Destination (Name of place & District/State/Country)
Trip Length (km)
Number of Trips
Average km driven/day no. of hours per day Vehicle Utilization
no. of working days per month
adopted Route Particulars
Preference for Proposed Superior Road Source: IRC: SP 19, 2001 Name & Signature of Enumerators: ________________________ Name & Signature of Supervisor: __________________________
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 32
Table 3.3: Proforma 2(b): Origin & Destination (O-D) Survey (Car/Bus). (IRC: SP:19-2001)
Name of Road: Road No.: Location at Km: Weather: Towards: Date: Day: Time: Sr. No. Particulars
Registration No.
Type of Vehicles No. of Passengers
Origin (Name of Place & District/State/Country)
Destination (Name of place & District/State/Country)
Quantity (Tonnes/Litre)
Origin (Name of place & District/State/Country)
Vehicles Particulars
Destination (Name of place & District/State/Country)
Trip Length (km)
Number of Trips
Average km driven/day no. of hours per day Vehicle Utilization
no. of working days per month
adopted Route Particulars
Preference for Proposed Superior Road Source: IRC: SP 19, 2001 Name & Signature of Enumerators: ________________________ Name & Signature of Supervisor: __________________________
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 33
Chart 3.3 Sample Chart Showing Origin Destination MAV
Chart 3.4 Sample Chart Showing Traffic Flow Pattern
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 34
3.6 Reconnaissance Survey 3.6.1 Purpose The main objective of reconnaissance survey is to examine the general character
of the area for the purpose of determining the most feasible route, or routes for
further more detailed investigations. Data collected should be adequate to
examine the feasibility of all the different routes in question, as also to furnish the
Engineer-in-charge with approximate estimates of quantities and costs, so as to
enable him to decide on the most suitable alternative or alternatives. The survey
should also help in determining any deviations necessary in the basic geometric
standards to be adopted for the road facility.
3.6.2 Survey Method The reconnaissance survey may be conducted in the following sequence
a) Study of topographical survey sheets, agricultural, soil, geological and meteorological maps, and aerial photographs, if available
b) Aerial reconnaissance (when necessary and feasible)
c) Ground reconnaissance (including another round of aerial reconnaissance for inaccessible and difficult stretches, where called for)
3.6.3 Study of Survey Sheets, Maps etc. Reconnaissance begins with a study of all the available maps. The types of useful
map information which are currently available in the country are as below:
(a) Survey of India (SOI) Maps
(i) The most useful maps are the topographical sheets available in the scale 1:25,000, 1:50,000 and 1:250,000. Maps coverage on 1:50,000 and
1:250,000 scales are available for the whole of India but map coverage
in the scale 1:25,000 is most preferred and at present is available only
for about 30 percent of the country.
(ii) State maps on scale 1:1,000,000 These are useful as index maps or to indicate an overview of the project location and are available for most of
the states.
(iii) Plastic Relief Maps on scale 1:15,000,000 One may be lucky to have these maps for certain regions. For very difficult areas road location
planning may be very much helped if these three dimensional maps
delineating ridges, valleys, peaks, etc. with contour information are
available.
(b) Apart from the above mentioned SOI maps there are special purpose maps,
like, Forest, Survey of India, Vegetation Maps on scale 1:25,000,000 showing
incidence of orchards, reserve forests, clusters of social forestry areas, etc. which
may be helpful in special cases in selection of alignment.
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 35
Earthquake possibility should also be studied from earthquake maps & relevant
IS. Type and design of structure should be planned accordingly.
Also, maps prepared by National Bureau of Soil Survey and Land Use Planning
(NBSS & LUP) indicating information on Soil, Wasteland, etc. and Geological
Survey of India Maps (on scale 1:250,000 or smaller) with information on
geology, geomorphology and changes in drainage, river courses, etc. are
available for many areas. These maps are fruitfully used when considered
necessary.
After study of the topographical features on the maps, a number of alignments
feasible in a general way are selected.
The present status of Aerial Photography (AP) in India is that AP on scale
1:50,000 is available for the whole of India. Depending on their quality the
negatives of these photographs, when necessary, can be enlarged easily by about
five times without losing clarity and thus obtain AP enlargements on scale of
1:5,000 to 1:20,000.
3.7 Preliminary Survey 3.7.1 Purpose The preliminary survey is a relatively large scale instrument survey conducted for
the purpose of collecting all the physical information which affects the proposed
location of a new urban road or improvements to an existing urban road. In case
of the new roads an accurate traverse line along the route previously selected on
the basis of the reconnaissance survey. In the case of existing roads where only
improvements are proposed, the survey line is run along the existing alignment.
During this phase of the survey, topographic features and other features like,
houses, monuments, places of worship, cremation or burial grounds, utility lines,
existing road and railway lines, stream, river, canal crossings, cross-drainage
structures etc. are tied to the traverse line. Longitudinal-sections and cross-
sections are taken and bench marks established. The data collected at this stage
will form the basis for the determination of the final centre line of the road. For
this reason, it is essential that every precaution should be taken to maintain a
high degree of accuracy.
Besides the above, general information which may be useful in fixing design
features within close limits is collected during this phase. The information may
concern traffic soil, construction materials, drainage, etc. and may be collected
from existing records as through intelligent inspection/simple measurements. It
may be found convenient to divide the road into homogeneous sections from
traffic consideration and prepare a typical estimate for one km stretch as
representative of each homogeneous section. With the data collected, it should be
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 36
possible to prepare rough cost estimates within reasonably close limits for
obtaining administrative approval, if not already accorded and for planning
further detailed survey and investigations.
In particular, information may be collected regarding:
(i) The highest sub-soil and floor water levels, the variation between the maximum and minimum and the nature and extent of inundation, if
any, gathered from local enquires or other records. These should be
correlated to data about the maximum and minimum rainfall and its
duration and spacing, etc. by appropriate hydrological analysis.
(ii) The character of embankment foundations including the presence of any unstable strata likes micaceous schists, poor drainage or marshy
areas; etc. this is particularly necessary in areas having deep cuts to
achieve the grade.
(iii) Any particular construction problem of the area, like, sub-terranean flow, high level water storage resulting in steep hydraulic gradient
across the alignment canal crossings and their closure periods.
Information regarding earlier failures in the area of slides or
settlements of slopes, embankments and foundations, together with
causes thereto may also be gathered from records and enquiry where
feasible.
(iv) In cut sections, the nature of rock i.e. hard, soft etc. should be determined by trial pits or boreholes. This is essential to make realistic
cost estimates.
3.7.2 Survey Procedure 1. The preliminary survey starts with running of a traverse along the selected
route, adhering as far as possible to the probable final centre line of the
road. In difficult situations, a secondary traverse connected to the primary
one at either end may also be run. In hilly area, a trace cut 1.0 to 1.2 m
wide, if required may be made during the preliminary survey. For details
in this regard, reference may be made to IRC: 52 Recommendations
about the Alignment Survey and Geometric Design of Hill Roads.
2. The traverse consists of a series of straight lines with their lengths and intermediate angles measured very carefully. In difficult terrain the
alignment may have to be negotiated through a series of short chords,
preferably, the traverse should be done with a theodolite with Electronic
Distance Measurement (EDM) and all angles measured with double
reversal method. Global Positioning System (GPS) is also very useful and
appropriate for preliminary survey. The GPS will give locations in co-
ordinates all the necessary points on the traverse. The GPS is very fast
reasonably accurate for preliminary system and computer friendly for data
transfer. Control pillars in cement concrete should be fixed at suitable
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 37
interval (ranging from 500 m to 2 kms) to have control on accuracy. It
also helps in repeating the survey, if required, within the control pillars.
3. Distances along the traverse line should be measured with EDM or total station. An accuracy of at least 1 in 10000 should be aimed at in all
distance measurement.
4. No hard and fast rule can be laid down as regards distance between two consecutive transit stations. In practice, the interval will be dictated by
directional changes in the alignment, terrain conditions and visibility. The
transit stations should be marked by means of stakes and numbered in
sequence. These should be protected and preserved till the final location
survey.
5. Physical features, such as buildings, monuments, burial grounds, cremation grounds, places of worship, posts, pipelines, existing roads and
railway lines, stream/river/canal crossings, cross-drainage structures, etc.
that are likely to affect the project proposals should be located by means
of offsets measured from the traverse line. Where the survey is for
improving or upgrading an existing road, measurements should also be
made for existing carriageway, roadway and location and radii of
horizontal curves. In case of roads in rolling and hilly terrain the nature
and extent of grades, ridges and valleys and vertical curves should
necessarily be covered. The width of land to be surveyed will depend on
the category of road, purpose of the project, terrain and other related
factors. Generally, the survey should cover the entire right-of-way of the
road, with adequate allowance for possible shifting of the centre line from
the traverse line.
6. Levelling work during a preliminary survey is usually kept to the minimum. Generally, fly levels are taken along the traverse line at 50 metre intervals
and at all intermediate breaks in ground. To draw contours of the strip of
land surveyed, cross-sections should be taken at suitable intervals,
generally 100 to 250 m in plain terrain, upto 50 m in rolling terrain, and
upto 20 m in hilly terrain. To facilitate the levelling work, bench marks,
either temporary or permanent, should be established at intervals of 250
to 500 metres. The levels should be connected to GTS datum.
7. Field notes of the survey should be clear and concise, yet comprehensive enough for easy and accurate plotting.
8. Apart from traverse survey, general information about traffic, soil, drainage should be collected while the traverse is being run, as mentioned
in Para 7.1.
9. Check list on preliminary survey is available in Appendix 2.
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 38
3.7.3 Modern Trends in Surveying Recent developments in photogrammetric and surveying equipment have been
closely associated with advances in electronic and computer technology.
Electronic distance measuring instruments for ground surveying now are capable
of printing output data in machine-readable language for computer input and/or
combining distance and angle measurements for direct readout of horizontal and
vertical distances to the nearest 0.001 of a centimetre. The incorporation of data
collectors and electronic field books with interfaces to computer, printer, and
plotter devices has resulted in the era of total station surveying.
The recent refinement in Global Positioning Systems (GPS) and techniques
developed for military navigation had led to yet another dramatic change in
surveying instrumentation. Inertial surveying, with its miniaturized packaging of
accelerometers and gyroscopes and satellite radio surveying, with its miniaturized
packaging of accelerometers and gyroscopes and satellite radio surveying have
already revolutionized geodetic control surveying and promises to impact all
phases of the surveying process.
The principal change in levelling instruments has been widespread adoption of the
automatic level, in which the main level bubble has been replaced with a levels
the line of sight. Lasers are being used for acquisition of vertical control data in
photogrammetry and for providing line and grade in construction related
surveying.
As a result of the technological breakthroughs in surveying and mapping the
survey engineer of 1990s must be better trained in a much broader field of
science than the surveyor of even a decade ago. A background in higher
mathematics, computer technology, photogrametry, geodetic science and
electronics is necessary for todays survey engineer to compete in this rapidly
expanding discipline.
2.7.4 Survey Instruments Tapes: Taping is frequently used. Most surveyors' tapes are made of steel ribbon
with a favoured length being 100m. Metal tapes suffer from kinks and are easily
broken. Non-metallic tapes are woven from synthetic yarns with or without
metallic threads. These tapes are strong and wear well but can be subject to
errors due to temperature and moisture changes. Many modern tapes are made
of durable 'plastic' or fibreglass and these will probably be the type available for
use in your school. All tapes need to be handled with care. Stadia: A stadia is a graduated measuring rod that is held vertically at a location
whose distance is required to be known. The rod is sighted through the optical
equipment (transit, theodolite, alidade, telescope) and the distance read on the
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 39
stadia rod is in proportion to the distance from the equipment to the rod. A
simple demonstration of the stadia method of measuring distance is included in
the Practical activities section of this topic - the activity is called In the distance.
This method was demonstrated by Bob Christopherson as a very effective means
of helping students understand the principles of measurement with surveying
equipment, in particular the dumpy level. Electronic Distance Measuring (EDM): EDM equipment is of various types
relying on the reflection of electromagnetic radiation such as microwaves, infra-
red, and laser radiation waves from a reflector at the distant station. Chain: Chaining is an older means of measuring distances. The chain is made of
metal and has 100 links. Each link is 7.92 inches long, and each chain is 66 feet
long 7.92 100 = 792 inches 792 12 = 66 feet. The Surveyors Museum located in the Land Centre at Woolloongabba has examples of these chains that
were used in early surveying work in Queensland. I believe only a few remain
although many were in existence. Trundle wheel or perambulator: For early surveying work the perambulator
was used to measure distances. It was pushed along and the number of
revolutions of the wheel counted either manually (room for lots of error) or by an
odometer attached to the frame. Depending on the radius of the wheel distance
could then be determined by calculating circumference number of revolutions.
A perambulator is on display at the Surveyor's Museum located in the Land
Centre at Woolloongabba. Trundle wheels, which work in the same manner,
should be available in schools. They measure a standard one metre per
revolution.
Compass: Measurement of Horizontal Angel
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 40
Swiss Origin Theodolite GXI Digital Theodolite
Level: to know elevation of the ground
Theodolite
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 41
Modern Precise Theodolite Optical Theodolite
Optical Theodolite: An optical theodolite being used on Montserrat in 1996 to
measure the growth of the lava dome (in distance, partially covered in meteoric
and ash clouds). A theodolite measures horizontal and vertical angles extremely
accurately, and is a common surveying tool. By siting on points on the dome from
at least two locations, they can be accurately located in 3 dimensions. Repeated
measurements then can define the movement of the dome.
Distometer Broad range of measurement (from 0.2m to 200m) easy to use accurate measurements that are simple to read Made of lightweight materials, making it easy to manipulate. 5 second readout instrument. This instrument is ideal for
small building companies.
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 42
Ultrasonic Distometer with Lacer Indicator
Tracheometer The electronic tacheometer 4Ta5 is designed for
measuring of slant distances, horizontal and
vertical angles and elevations in topographic
and geodetic works, tacheometric surveys, as
well as for solution of application geodetic tasks.
The measurement results can be recorded into
the internal memory and transferred to a
personal computer via RS-232C interface.
Global Positioning System The Global Positioning System (GPS) is an
important technology, which provides
unequalled accuracy and flexibility of
positioning during movement, surveying
and GIS data capture. The GPS is a
satellite-based navigation, timing and
positioning system. There are 24
satellites, known as GPS satellites that
orbit at 11,000 nautical miles above the
Earth. They are continuously monitored
by ground stations located worldwide. The
satellites transmit signals that can be
-
Module 2.5: Survey and Investigation
JnNURM - Rapid Training Programme
Preparation of DPRs
CEPT, Ahmedabad 43
detected by anyone with a GPS receiver. GPS satellites circle the earth twice a
day and transmit signal information to earth.
GPS receivers take this information and calculate the user's exact location. The
GPS provides continuous three-dimensional positioning 24 hrs a day throughout
the world. The basic GPS service provides commercial users with an accuracy of
10-15 meters, 95% of the time anywhere on the earth. The GPS technology has
tremendous amount of applications in GIS data collection, surveying, and
mapping.
Advantages of GPS
1. More time efficient than using the toposheets and recording information by hand