![Page 1: SURVEY ON HEAVY RAIL CONTRACTS A comparison between the different public services contracts for heavy rail administered by the EMTA Authorities EMTA Budapest.](https://reader036.fdocuments.in/reader036/viewer/2022072011/56649e3b5503460f94b2e101/html5/thumbnails/1.jpg)
SURVEY ON HEAVY RAIL CONTRACTSSURVEY ON HEAVY RAIL CONTRACTS
A comparison between the different public services contracts for heavy rail administered by the EMTA Authorities
EMTA Budapest Meeting 15 -16 April 2010
![Page 2: SURVEY ON HEAVY RAIL CONTRACTS A comparison between the different public services contracts for heavy rail administered by the EMTA Authorities EMTA Budapest.](https://reader036.fdocuments.in/reader036/viewer/2022072011/56649e3b5503460f94b2e101/html5/thumbnails/2.jpg)
2
FOREWORD
Heavy rail is one of the most relevant public transport services in metropolitan areas. It involves huge investments in infrastructure building and maintenance and higher cost of operation if compared to the other PT modes (metro, tramway, buses).
The aim of this document is to highlight the different contract structures and the average level of public subsidy where financial data is not a confidential information.
The information received from the Members can be useful for all the other EMTA members to add more strength to the contract management.
Our objective is to verify how the unit cost of our rail service is aligned with the average cost in the other European metropolitan areas, in order to quantify the right amount for the tender offers.
![Page 3: SURVEY ON HEAVY RAIL CONTRACTS A comparison between the different public services contracts for heavy rail administered by the EMTA Authorities EMTA Budapest.](https://reader036.fdocuments.in/reader036/viewer/2022072011/56649e3b5503460f94b2e101/html5/thumbnails/3.jpg)
3
AUTHORITIES THAT FILLED OUR QUESTIONNAIRE
Our initiative was launched in September 2009 with a 2 pages questionnaire that was circulated among the EMTA Members.As of now we have received contributions from:- Stuttgart Region- RMV Frankfurt- ATM Barcelona- SYPTE Sheffield- ZTM Warsaw- AMT MontréalIn addition to this we examined the Contract 2008 – 2011 between STIF and SNCF for the rail service in Ile-de-France (available on paper).
![Page 4: SURVEY ON HEAVY RAIL CONTRACTS A comparison between the different public services contracts for heavy rail administered by the EMTA Authorities EMTA Budapest.](https://reader036.fdocuments.in/reader036/viewer/2022072011/56649e3b5503460f94b2e101/html5/thumbnails/4.jpg)
4
THE RAIL SERVICES OFFER
The table shows the offer in Train*Km per year.The amount of service offered varies between the 57 million train*km of Région Ile-de-France to the 2,8 M Km of Barcelona. However it must be underlined that in the case of Barcelona only the service surveyed is light rail and not heavy rail. Financial data concerning the AMT contracts are not available due to pending negotiations.
Authority Offer (in train km per year)
AMMT Torino 2,5 M train Km (Trenitalia)1,0 M train Km (GTT)
Stuttgart Region 9,8 M train km
RVM Frankfurt 38 M train Km
ATM Barcelona 2,8 M train Km
SYPTE Sheffield 3,4 M train Km
ZTM Warsaw 2010 about 5 M vehicle Km2011 about 11 M vehicle Km2012 about 16 M vehicle Km (start of 2 new airport lines), trains with different number of cars
STIF Ile-de-France 57,5 M
AMT Montréal Canadien National : 613138 Train kmChemin de fer Canadien Pacifique : 705474 Train km
![Page 5: SURVEY ON HEAVY RAIL CONTRACTS A comparison between the different public services contracts for heavy rail administered by the EMTA Authorities EMTA Budapest.](https://reader036.fdocuments.in/reader036/viewer/2022072011/56649e3b5503460f94b2e101/html5/thumbnails/5.jpg)
5
OPERATORS AND TYPE OF CONTRACT
The table shows the type of contract adopted by each authority.
The Net cost contract is more frequently used (5 cases out of 7).
Authority Name of the heavy rail operator
Type of Contract
AMMT Torino Trenitalia S.p.A.GTT S.p.A.
Net cost
Stuttgart Region DB Regio AG (S-Bahn) Net cost
RVM Frankfurt Deutsche Bahn AG, Hessische Landesbahn GmbH, VIAS and more (8)
Gross cost
ATM Barcelona Light rail: Tramvia Metropolità
Net cost
SYPTE Sheffield Northern Rail Net cost
ZTM Warsaw Szybka Kolej Miejska Sp. z o.o. (Urban Rapid Rail Ltd.)
Gross cost
STIF Ile-de-France SNCF Net cost
![Page 6: SURVEY ON HEAVY RAIL CONTRACTS A comparison between the different public services contracts for heavy rail administered by the EMTA Authorities EMTA Budapest.](https://reader036.fdocuments.in/reader036/viewer/2022072011/56649e3b5503460f94b2e101/html5/thumbnails/6.jpg)
6
THE AMOUNT OF SUBSIDIES
The table shows the amount of subsidy for each contract. Some contracts include also a subsidy for the infrastructure charge. In some cases data were confidential and not publicly available. None of the Authorities’ contracts calculated the unit amount on a different basis (i.e. per train hour instead of train km)
2. AMOUNT OF PUBLIC SUBSIDIES / YEAR
for operations for infrastructure access
Unit price in € per train km
AMMT Torino Rail Operator “Trenitalia” 22,9 M€ (+ VAT)Rail operator “GTT” 20,0 M€ (+ VAT)* *: GTT subsidy includes the infrastructure maintenance charge
9,16 € (Trenitalia)6,80 € (GTT)
Stuttgart Region 58,7 M€, (for operation and infrastructure access for rail, stations and transmission of electricity), no VAT to pay for these services
6,01€ (= 58,7 m€ / 9,8 m train km)
RVM Frankfurt No specifications No specifications No specifications
ATM Barcelona 26,14 M€ (+VAT), total cost of operation16,50M€ (+VAT), total subsidy for operation
28,3 M€ (+VAT) 9,31 €
SYPTE Sheffield 34,015 M€ (at April 2010 conversion rates) for total cost of the operation
The contract is for the agreed level of service (capacity, timetable, rolling stock class).
ZTM Warsaw operator has not enabled ZTM to fill in the exact financial data
STIF Ile-de-France 1.211 M€ for operations, investments and other specific arrangements
21,09 €
![Page 7: SURVEY ON HEAVY RAIL CONTRACTS A comparison between the different public services contracts for heavy rail administered by the EMTA Authorities EMTA Budapest.](https://reader036.fdocuments.in/reader036/viewer/2022072011/56649e3b5503460f94b2e101/html5/thumbnails/7.jpg)
7
INVESTMENTSThis table show the different investment policies set up by the Authorities. In some cases investments are included in the contract subsidies.
Are investments included in the contract?
New rolling stock
Building of new infrastructure
Other....
AMMT Torino No No No
Stuttgart Region Yes, operator buys 83 new trains, worth 450 m€; no extra costs for the region, they are included in 6,01€/train-km
No No
RVM Frankfurt Yes No Yes
ATM Barcelona No No No
SYPTE Sheffield No No No
ZTM Warsaw Yes (17 new trains till 30.06.2011)
No No
STIF Ile-de-France Yes (Quadrennial investments plan) PQI
? (Confidential information)
Renewal of stations, accessibility for people with reduced mobility, information to travellers
AMT Montréal No No No
![Page 8: SURVEY ON HEAVY RAIL CONTRACTS A comparison between the different public services contracts for heavy rail administered by the EMTA Authorities EMTA Budapest.](https://reader036.fdocuments.in/reader036/viewer/2022072011/56649e3b5503460f94b2e101/html5/thumbnails/8.jpg)
8
ADDITIONAL SERVICES4. ADDITIONAL SERVICES
Train announcements with loudspeaker in stations/stops
Ticket office availability
Customer service counter (timetable info, disabled passengers assistance, groups)
Is there an additional charge in case a newer or higher quality rolling stock is used?
AMMT Torino No No No No
Stuttgart Region Real time information at each platform in the S-Bahn network, loudspeaker information is not necessary.
Ticket offices only at larger stations, included
No
RVM Frankfurt Yes Yes Yes No
ATM Barcelona No No No No
SYPTE Sheffield Yes (automated with manual over-ride)
7 stations (out of 27) TimetablesDisabled assistanceCycles carried
No
ZTM Warsaw No No No average unit price and max total payment per year put into the contract – prices may vary depending on vehicle type
STIF Ile-de-France
AMT Montréal Provide directly by AMT Provide directly by AMT
Provide directly by AMT
No
![Page 9: SURVEY ON HEAVY RAIL CONTRACTS A comparison between the different public services contracts for heavy rail administered by the EMTA Authorities EMTA Budapest.](https://reader036.fdocuments.in/reader036/viewer/2022072011/56649e3b5503460f94b2e101/html5/thumbnails/9.jpg)
9
ADDITIONAL SERVICES
4. ADDITIONAL SERVICES
Is there an additional charge for off-peak or Sundays / holidays service?
Is there an additional charge for low demand services
Other, specify....
AMMT Torino No No No
Stuttgart Region No No
RVM Frankfurt No Yes No
ATM Barcelona No No No
SYPTE Sheffield No No SYPTE are able to buy-in enhancements. Northern Rail funded separately for station upgrade works, above maintenance of the station asset which is part of the contract.
ZTM Warsaw No No (it’s a gross contract) No
STIF Ile-de-France
AMT Montréal No No No
![Page 10: SURVEY ON HEAVY RAIL CONTRACTS A comparison between the different public services contracts for heavy rail administered by the EMTA Authorities EMTA Budapest.](https://reader036.fdocuments.in/reader036/viewer/2022072011/56649e3b5503460f94b2e101/html5/thumbnails/10.jpg)
10
CONCLUSIONS
The European regulations impose specific Public Service Obligations to the operators
The Service contract is a strategic tool for the Authorities to promote improvements in the quality of service
Our proposal is to set up an Observatory of the Public Services Contracts inside EMTA with the following tasks:
• Compare the main indicators that influence the cost of operation and therefore the amount of subsidy needed to run the service (i.e. cost of personnel, infrastructure access charge, traction charge)
• All the results of this activity can be included in a periodic report to be circulated among Members.