SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Surface Maintenance
Engineering Planning Program
Update
FMMS Port Engineer Symposium
Mark Leary, John Murphy, Mark Darwin
01 September 2015
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Agenda
Background & Review: SURFMEPP Mission and Products
New/Recent CMP tasks & revisions
Recent Process Changes
Time-Directed Maintenance Strategy (Mark Darwin)
Third Party Planning (John Murphy)
Class Standard Work Templates & Master Spec Catalog
Mandatory Safety Alterations & SURFMEPP role in modernization
Routines and Services standardization effort
Issues and Concerns
2
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
SURFMEPP Mission and Key References
3
SURFMEPP Mission: Provide centralized surface ship life cycle maintenance
engineering, class maintenance and modernization planning, and management of
maintenance strategies
• Standard Organization and Regulations of the U.S. Navy (SORM) (OPNAVINST 3120.32D)
• OPNAVINST 4700.7L (Maintenance Policy for U.S. Navy Ships)
• Ships’ Maintenance and Material Management (3-M) Manual (NAVSEAINST 4790.8C)
• Joint Fleet Maintenance Manual (JFMM) (COMFLTFORCOMINST 4790.3)
• Surface Force 3-M Assessment & Certification Program
(COMNAVSURFPAC/LANTINST 4790.2 change 1)
Joint Fleet Maintenance Manual
SURFMEPP has an ENDURING focus on the maintenance requirements
SURFACE Force Assessment
and Certification Program OPNAVINST 4700.7L SORM Ship’s 3M Manual
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Evolution of SURFMEPP
2008 Pre – Surface Ship Life Cycle
Management Activity (SSLCM)
• 14 people for entire surface Navy
• No Technical Foundation Papers (TFP)
• No Baseline Availability Work Packages
• Ship Sheets at the Class level
• Budgets based on averages of historical
costs (MRS)
SSLCM – May 2009
• 36 total staff in May 2009
• Class Maintenance Plan
• TFP for DDG 51 class only
• BAWP
• Deferral tracking
• Ship Sheets based on deferrals
SURFMEPP – Est. Nov 2010
• 83 total staff in Nov 2010
• 226 total staff today
• Class Maintenance Plans
• TFP for all major ship classes
• BAWPs for all CNO availabilities
• Deferral tracking by hull
• Monthly status reports for all Mandatory
Technical Requirements (MTR)
• Ship Sheets for every CNO availability
• Long Range Maintenance Schedules by
hull
• Corrosion Control (CCIMS, TPRs,
LRTPRs)
4
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
SURFMEPP Global Footprint
5
PACNW DETACHMENT
SAN DIEGO DETACHMENT
PEARL HARBOR DETACHMENT
MAYPORT DETACHMENT
NORFOLK DETACHMENT
ROTA DETACHMENT
BAHRAIN DETACHMENT
SASEBO DETACHMENT
Lead: Don Kultti (428) 304-4579
Lead: George McVey (619) 556-5243
Lead: Jen Valle (904) 270-5126 ext. 3383
Lead: Jim Batchelor 011-81-46-816-9441
Lead: Russ Fitzwater 011-81-956-50-6601
Lead: Dan Hengerer 011-34-956-82-2714
Lead: Dennis Reinhardt
011-973-3838-4673
Lead: Ed McIntyre (757) 443-2650 ext. 1137
Lead: Al Owczarek (904) 270-5126 ext. 3380
SURFMEPP HQ Portsmouth, VA
YOKOSUKA DETACHMENT
THE SUN NEVER SETS ON SURFMEPP
PRODUCT AREAS
• Availability Analysis Study
• Baseline Availability Work Package
• Change Management Documentation
• Class Maintenance Plans
• Class Standard Work Templates
• Contracting Strategies
• Corrosion Program Management
• Deferral tracking by hull
• Integrated maintenance & modernization
work packages
• Master Specification Catalog
• POM Ship Sheets by hull
• Robust Metrics
• Ship Sheets
• Technical Foundation Papers
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
SURFMEPP Product Value Stream
Assessment Results
Ship CSMP
Modernization
Availability Work Package (AWP)
Execute Availability
Avail Close Out
(Technical & Financial)
Class Maintenance Plan (CMP)
Technical Foundation
Paper
Ship Sheets
(Ship specific LRMS)
Baseline Availability Work Package (BAWP)
Integrate, Execute, Document and Feedback
Plan Long Range Requirements into Availabilities
Technical Reqts Class Reqts ($) Specific Ship Reqts ($, Schedule)
Plan FRP Cycle
Execute (A-0 through C+0)
Document & Feedback (C+100)
Integrate Package (A-360 through A-35)
Plan Availability (A-540 through A-360)
POM & DON Submission
Deferred Life Cycle Maintenance
(C+150)
6
Work Item Level
Enhanced tracking during AWP planning process
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Agenda
Background & Review: SURFMEPP Mission and Products
New/Recent CMP tasks & revisions
Recent Process Changes
Time-Directed Maintenance Strategy (Mark Darwin)
Third Party Planning (John Murphy)
Class Standard Work Templates & Master Spec Catalog
Mandatory Safety Alterations & SURFMEPP role in modernization
Routines and Services standardization effort
Issues and Concerns
7
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
FY15 CMP Task Additions
LSD Stern Gate Hydraulic Cylinder
Overhaul
LSD Stern Gate Transom Gasket
LSD, LHD Sea Valves and Waster
Sleeves
LPD Caley Davit Overhaul
LPD Sea Valves
LPD, DDG VCHT Chemical Cleaning
LHD, LCC Ventilation Steam Heaters
NSWC Below Waterline Space
Assessments
LPD Bulwark Overhaul
LCC, LHD Condenser Sea Water
Rubber Expansion Joints
8
Additional Info in Backup Section
LSD, LPD, MCM Laundry and
Galley Ventilation
Steam Propulsion ISEA
Assessment support
DDG, LSD, CG, LHA6, LCS1 Lube
Oil Purifier Heater Cleaning and
Calibration
LHD, LSD, LPD lower vehicle
G1N6
G1N6 bilge area breakout (All
classes)
DDG and CG CPP and Lube Oil
Settling Tank Heater one-time
assess
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
FY15 CMP Changes / Updates
IR SURVEY: 12 Month IR survey now 36 months
SPS-67: Modified pedestals now 48 month vice 30 or 36 month periodicity
DDG: VLS strikedown crane task inactivated for all DDGs with torpedo
strikedown ALT completed
DDG and CG: CSAV and Collimation validated and all LMA/NDD aligned with PHD
MCM MP Air Flask now 180M vs 120M
PC Parasense refrigerant monitor
DDG lube oil cooler tube bundle replacement
Underwater hull preservation
LSD fuel oil purifiers
DDG SVTT assessment
9
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
What Happened to the Requirement?
CMP “SWEEP”
• Total Assessment and Repair Tasks
– Pre SWEEP: 6,644 tasks: 604 Mandatory A1
– Post SWEEP: 2,704 tasks: 316 Mandatory A1
• Assessment tasks:
– Pre SWEEP: ~2,800 tasks
– Post SWEEP: ~1,800 tasks
• Overall:
– 1,546 task modifications
– 5,259 task inactivations
– 323 new tasks with technical underpinning
• IMPACT:
– Right task at the right time in the FRP to maximize investment
10
Results: Defendable, Accurate, Executable Maintenance Requirements
Right Sizing the CMP
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Pre-/Post-SWEEP Mandatory
(A1) Maintenance Actions
11
• Non-pedigreed requirements removed.
• Technically valid maintenance actions remain.
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Pre-/Post-SWEEP Non-Mandatory
(B9) Maintenance Actions
12
• Non-pedigreed requirements removed.
• Technically valid maintenance actions remain.
• Fully supports TSRA / CAP processes.
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Agenda
Background & Review: SURFMEPP Mission and Products
New/Recent CMP tasks & revisions
Recent Process Changes
Time-Directed Maintenance Strategy (Mark Darwin)
Third Party Planning (John Murphy)
Class Standard Work Templates & Master Spec Catalog
Mandatory Safety Alterations & SURFMEPP role in modernization
Routines and Services standardization effort
Issues and Concerns
13
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Recent Process Changes
Shift from MSMO Cost plus Incentive Fee contract vehicles to Firm Fixed
Price contracts in all AORs.
• Package lock date moves from A-99/A-75 to A-170.
Single deferral letter required at A-220 ISO Firm Fixed Price availabilities
and earlier package lock.
• Previous requirement was one deferral letter at A-240, another at A-120, in
support of A-99/A-75 package lock.
• New requirement is only one letter at A-220. Response from Ship Design
Manager should be back to MT prior to A-170 package lock.
• This cuts the admin burden of deferral letters in half.
• As before, Type Commander MAY write additional deferral requests any time,
as needed.
14
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Recent Process Changes
Branding Review (“AR” Category of Work) from A-150 to A-250
• First SURFMEPP review of CSMP will still be at A-440, ISO A-410 Mid-Cycle
Review.
• Second SURFMEPP review of CSMP will be at A-250. This will give MT time to
put “AR” branded items into work package OR into A-220 Deferral Request.
• No new jobs are pushed to the CSMP – this is a review of existing CSMP jobs
for SSEOC impact items. We will notify MT before changing Category of Work.
CMP Situational Periodicity Code change from A-150 to A-360
• All CMP tasks with SPC of A-150 will now be due at A-360. Goal is earlier
completion of assessments and earlier work identification ISO earlier package
lock.
• No additional assessments, requirements or workload. Just changing WHEN.
15
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Recent Process Changes
Non-Mandatory TSRA tasks Closure Method = MA COMPLETE
• 811 (A1), 816 (A6), 832 (AR), 833 (AH), and now 849 (B9) Type Sequence
Number are all changed to “MA COMPLETE” via VSB script.
• Port Engineer should not have to Customer Close these jobs when MA
executes and closes these jobs in TAAS, AIM or NMD.
Removal of CDNS – Per PE requests, SEA05 has also concurred
• First step: All CDNS notifications will be EXEMPT (no auto-generated emails). Deferrals of
MTRs will all be via letter process (AWPM/TDCA can assist).
• You will get the pop-up window as a notification but it won’t stop you from screening
• 2nd step: remove from VSB altogether
16
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Recent Process Changes
Additional Details In Following Slides:
• Time-Directed Tank and Void Maintenance Strategy
• Third Party Planning
• Master Spec Catalog & Class Standard Work Templates with Front Load
• Mandatory Safety Alterations
17
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Agenda
Background & Review: SURFMEPP Mission, SURFMEPP Products
New/Recent CMP tasks / revisions
Recent Process Changes
Time-Directed Tank Maintenance Strategy (Mark Darwin)
Third Party Planning (John Murphy)
Class Standard Work Templates & Master Spec Catalog
Mandatory Safety Alterations & SURFMEPP role in modernization
Routines and Services standardization effort
Issues and Concerns
18
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Place Holder
Time-Directed Tank Maintenance Strategy (Mark Darwin)
PE Symposium Briefing TDMS.pdf
19
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Agenda
Background & Review: SURFMEPP Mission and Products
New/Recent CMP tasks & revisions
Recent Process Changes
Time-Directed Tank Maintenance Strategy (Mark Darwin)
Third Party Planning (John Murphy)
Class Standard Work Templates & Master Spec Catalog
Mandatory Safety Alterations & SURFMEPP role in modernization
Routines and Services standardization effort
Issues and Concerns
20
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Place Holder
• Third Party Planning (John Murphy)
• PE Symposium 3PP slides 20150820.ppt
21
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Agenda
Background & Review: SURFMEPP Mission and Products
New/Recent CMP tasks & revisions
Recent Process Changes
Time-Directed Tank Maintenance Strategy (Mark Darwin)
Third Party Planning (John Murphy)
Class Standard Work Templates & Master Spec Catalog
• Mandatory Safety Alterations & SURFMEPP role in modernization
• Routines and Services standardization effort
• Issues and Concerns
22
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Class Standard Work Templates with
“Front Load”
Method:
Obtain relevant historic maintenance data from NMD. We
started with the SWLINS with the most growth in CNO avails.
Review current CSWT to identify functional area coverage
Look for repeated /recurring maintenance actions
Compare maintenance actions to the current CSWT:
• If maintenance actions are covered adequately by CSWT, no
modification needed
• If maintenance actions are not covered, generate recommendation
based on average/median of data
• If an existing reservation is not required, it will be removed
23
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Top Growth for all Surface
Ships
24
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Example: CG Gas Turbine
Exhaust Repair
Developed Two CSWTs - One for 1A and 1B and One for 2A and 2B - to
include the following reservations:
• 10 linear feet of Vee-out and weld repair
• 10 manhole cover studs replaced
• 10 manhole cover bolting ring holes repaired
• 450 ft2 of interior insulation replacement
• 100 ft2 of perforated sheathing panel replacement
• The following CSWTs have been modified to include the reservations:
• CSWT 259-008 1A and 1B Gas Turbine Exhaust; repair
• CSWT 259-002 2A and 2B Gas Turbine Exhaust; repair
25
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Agenda
Background & Review: SURFMEPP Mission and Products
New/Recent CMP tasks & revisions
Recent Process Changes
Time-Directed Tank Maintenance Strategy (Mark Darwin)
Third Party Planning (John Murphy)
Class Standard Work Templates & Master Spec Catalog
Mandatory Safety Alterations & SURFMEPP role in modernization
Routines and Services standardization effort
Issues and Concerns
26
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
MSA Definition
Created and codified via the NMPT in NDE
MSA ALTS identified in NDE by selection of the “Mandatory
Safety Alteration” field
Safety risk assessment provided by ALT sponsor
Currently SURFMEPP uses a list of MSAs provided by
SEA21 (vetted by SEA05)
27
Official Definition of “MSA” Approved - NDE Being Populated
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
MSA ID, Tracking and Deferral
SURFMEPP reviews LOA and IDs MSA
Pushes MSA JSN to MT and brands “AS”
• “AS” in JFMM as “Mandatory Safety Maintenance”
- Volume II, Part I, Chapter 3
- Being added to Appendix “AN” at next JFMM BoD
• Set Due Date to end of CNO avail and notifies stakeholders
Reviewed at E2E meetings (LCPC, A-410, IPTD, and C+70)
Tracked in A-360, Deferral and Closeout letters
Stakeholders notified if LOA change removes MSA
Deferral through LOA change process vice JFMM
28
Deferral from FRP to FRP may be an SSEOC reportable requirement
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Agenda
Background & Review: SURFMEPP Mission and Products
New/Recent CMP tasks & revisions
Recent Process Changes
Time-Directed Tank Maintenance Strategy (Mark Darwin)
Third Party Planning (John Murphy)
Class Standard Work Templates & Master Spec Catalog
Mandatory Safety Alterations & SURFMEPP role in modernization
Routines and Services standardization effort
Issues and Concerns
29
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
CNO Availability Services and
Routines
In an effort to standardize Services and Routines and the associated
processes need to ensure jobs are on the CSMP, SURFMEPP
conducted an analysis to identify tasks needed to support the
planning and execution of CNO availabilities
Tasks were divided into two categories, Core and Optional by AOR
Task review is complete in Norfolk
Task review is ongoing in San Diego
30
CNO Services & Routines Under Review For Standardization By AOR
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Core Services and Routines
Core Services and Routines are tasks deemed required to support
the planning and execution of the CNO availability
The AOR specific Core Services and Routines were developed by
SURFMEPP and concurred upon by the TYCOM and RMC
Core Services and Routines will be discussed at LCPC
Core Services and Routines will be pushed with the BAWP but will
not be branded mandatory
31
Core Services & Routines are Pushed with the BAWP
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Optional Services and
Routines
Optional Services and Routines are unique package relevant tasks
deemed needed to support the planning and execution of the CNO
availability
The AOR specific Optional Services and Routines were developed
by SURFMEPP and concurred upon by the TYCOM and RMC
Optional Services and Routines will be discussed at LCPC and the
A-410 meeting
Optional Services and Routines will be pushed to the CSMP when
requested by the Maintenance Team
32
Optional Services & Routines Pushed at Maintenance Team Request
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Agenda
Background / Review: SURFMEPP Mission and Products
New/Recent CMP tasks & revisions
Recent Process Changes
Time Directed Tank Maintenance Strategy (Mark Darwin)
Third Party Planning (John Murphy)
Class Standard Work Templates & Master Spec Catalog
Mandatory Safety Alterations &SURFMEPP role in modernization
Routines and Services standardization effort
Issues and Concerns
33
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Issues and Concerns
CSMP Management
• Tasks must be completely closed out in VSB – Last Accomplished Date does not update until the
JCN is closed out. Job will continue to appear on “overdue CMP task” list until closed.
• Jobs that are NOT complete must stay on the CSMP – If the job is still valid, leave it open so we
can put on Ship Sheets and ensure you have the budget for it in the next cycle.
• All DFS need a JCN – A DFS can’t be screened and brokered…only a JCN can be screened and
brokered. Without a JCN there is no mechanism to actually get it fixed.
CMP Task Ownership
• If it is in the CSMP with an “A” Category of Work it is PE responsibility to Screen and Broker (or
get deferred by SDM).
• When it is assigned to the RMC it is their responsibility to get it accomplished.
• “Upon completion of a mandatory assessment, the assessment team is responsible for creating
CSMP-ready repair AWRs”
• BAWP report is distributed every 30 month. Full listing of all “A” Category of Work items in the
CSMP with a due date in the current cycle, WITH current status (Avail plus authorized, assigned,
rejected, on hold, etc)
34
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Issues and Concerns
CMP Task Feedback / TFBR
• If a CMP task is not right (not executable as written, wrong periodicity,
mismatch with tech manual, etc.), don’t just “live with it” - give us that
feedback so we can fix it.
• If no task exists for a piece of gear, but it should – we can help with that too.
We can work with ISEA / TWH.
• You can write your own TFBR in PMSMIS, or you can talk to / email / call your
local SURFMEPP detachment. We can either show you how to do a TFBR or we
can do it on your behalf.
Deferral Process
• Not being fully utilized. We still see items not accomplished but never
adjudicated on almost every closeout letter. If you know it can’t / won’t be
done, request deferral. Call your AWPM / TDCA.
• Deferral letters can be submitted at any time. RMC Chief Engineer can also
adjudicate tasks during execution, per JFMM.
35
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Summary
36
TYCOM and SURFMEPP: One TEAM/One FIGHT
• “It’s all about the ships”
SURFMEPP is fully engaged in the Surface Maintenance and
Modernization E2E process
• Defining and Defending the requirement
Working with you to improve Surface Maintenance
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Questions/Backup
37
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Team Ships Organization
38
COMBATANTS
OFFICE
Ms. Bilyana Anderson (SES) EXECUTIVE DIRECTOR
PMS 400D
DDG51
PM: CAPT Vandroff
Ships Acquisition
Management Office
DIRECTOR: B. Budd
DEPUTY
DIRECTOR
C. Teichert
PMS 500
DDG 1000
PM:
RDML (Sel) J. Downey
DPM
L. Radocha
PMS 377
LHA(R) / SSC / LCAC /
AADS / LCU / SC(X)
PM: CAPT Mercer
PMS 317
LPD 17/ LX(R)
PM: CAPT Plath
PMS 325
Auxiliary Ships /
Small Boats & Craft
PM: M. Kosar
Team Ships Staff Chief of Staff
P. Murphy
PROGRAM EXECUTIVE
OFFICER SHIPS
RADM David Gale
DEPUTY COMMANDER
FOR SURFACE WARFARE
RDML Larry Creevy
DPM
M. Sermon
PMS 385
Strategic & Theater
Sealift
PM: CAPT Stevens
DPM
T. Rivers
DPM
M. Lyons
DPM
T. Roberts
(acting)
DPM
C. Mitchell
SURFACE WARFARE
DIRECTORATE
Ms. E. Anne Sandel (SES) EXECUTIVE DIRECTOR
SEA 21I
Inactive Ships
DIRECTOR:
W. Boozer (acting)
PMS 443
Surface Ship Readiness
and Sustainment
PM: CAPT Crone
PMS 326
International Fleet
Support
PM: CAPT Dick
PMS 407
Surface Ship
Modernization
PM: CAPT Zobel
DPM
E. Littig
SURFMEPP
CO: CAPT Bauer
DPM
B. Smith
DEPUTY
DIRECTOR
T. White (acting)
PMS 320
Electric Ships Office
DIRECTOR: S. Markle
DEPUTY
DIRECTOR
P. Grabowski
AMPHIBIOUS, AUXILIARY
& SEALIFT OFFICE
Mr. Jay Stefany (SES) EXECUTIVE DIRECTOR
DPM
F. Thompson
DPM
T. Conlon
DEPUTY
DIRECTOR
T. Gallagher SEA 21P
Chief Financial Office
M. Scott
PMS 339
Surface Training
Systems
PM: CAPT Sinclair
SEA 21D
Director, Contract
Mgmt
M. Reese
As of July 2015
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Class Maintenance Plans
Class Maintenance Plans (CMP) are the “maintenance manual” of the ship class. Specifically included are:
– Maintenance Delivery Plan including required dry-docking intervals
– Engineered maintenance requirements such as equipment overhauls, shaft replacements, and corrosion protection
– System certification requirements
CMPs are continuously updated based on class maintenance history
CMP = “Automobile’s Maintenance Manual”
39
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Purpose
Identify maintenance required to meet the
expected service life (ESL) for CMAV and CNO
avails
“Class-level” notional long range maintenance
schedule for a well designed and maintained
ship. TFP Includes:
- Man-days
- Availability periodicity
- Availability duration for depot level maintenance
Technical Foundation Paper
Building Blocks M
ain
tena
nce R
equ
iremen
ts b
y Ava
ilab
ility
Techn
ical Fo
un
da
tion
Pa
per
(Sum
ma
ry)
Technical Foundation Paper (Owner’s Manual)
Time
Directed
Services
Corrective
(CMP)
Corrective
(CSMP)
Fleet Alts
To
tal N
oti
on
al
Re
qu
ire
me
nt
C+90
Deferral
40
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Ship Sheets
Ship Sheets support the annual requirements and
budgeting process “at the hull level”
– Dollars and schedule
– Technical Foundation Paper is the baseline
– Material condition is used to develop ship-specific
requirements
– Assessments are critical to document material condition
Two year old process for Surface Navy - improved upon
Sub and Carrier model
Deferred maintenance is tracked via MMWP and Ship
Sheets
41
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
42
BAWP
A collection of all Mandatory Technical
Requirements ISO CNO Availability
Work Package, and includes:
• Mandatory Safety Alterations
• Integrated/approved Mod sked & avail
duration risk assessment
• CMP Assessment and Repair Tasks
• Mandatory DFS / CLAD items
• Routines and Services
LCPC held/BAWP items
reviewed at C+140
BAWP items pushed to
CSMP 10 days later
MOD items to CSMP ISO
Letters of Authorization
at A-360
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
• End to End Maintenance Process / CNO Availability Milestones
• Baseline Availability Work Package (BAWP) Status
– Mandatory work deferred from last cycle
– Tank Assessments (G1N5), Preservation and Repairs
– Corrosion Assessments (G1N6)
– Infrared Surveys (T1B6)
– Additional Items to be pushed
– Docking Items / Routines and Services
• Class Advisories (CLAD) / DFS
• Maintenance Events Remaining (TSRA / CMAV) / Establish Milestones
• BAWP Summary
43
SURFMEPP Life Cycle Planning Conference
C+140 Start of the cycle - get everyone on the same page right from the start
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
• Baseline Availability Work Package (BAWP) Status
• Tank Assessments (G1N5), Preservation and Repairs
• Corrosion Assessments (G1N6)
• Intake / Uptake Assessments (G1E8), Infrared Surveys (T1B6)
• Docking Items / Routines and Services
• Class Advisories (CLAD) / Departures from Specifications (DFS) status
• CSMP review for Lifecycle Critical JSNs (AR Branding)
• Modernization Items / Availability Duration Scorecard
44
SURFMEPP Mid-Cycle Review
A-410 MCR - a key input to the Maintenance and Modernization Work Package
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
SURFMEPP Closeout Process
• Review Status of Mandatory Technical Requirements (MTR)
• Review MTRs to Re-Program
• Establish notional milestone dates for the next FRP maintenance cycle
• Review the status of Departures From Specification (DFS)
• Review recommendations for SURFMEPP process improvement and possible LEAN initiatives
• SURFMEPP also reviews actual expenditures vs budget and controls (W=X=Y=Z)
45
C+70 Closeout meeting, formal audit report issued C+100
Future state: will also include a review of planned modernization
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
SSEOC Life Cycle Critical Systems
100 Structure
U/W Hull
Superstructure / Mast
Sonar Dome
Decking, Structure
Bilges
Tanks / Voids
Bulkheads, Structure
Corrosion, General
200 Propulsion
Steam Turbines
Boilers
MPDE
MRG
Shafts
Struts
Hubs / Propulsors
Intakes / Uptakes
Forced Draft Blowers
Main Feed Pumps
Main Steam Valves (>4”)
Gas Turbine Module Mounts
Piping:
Fuel
Main / Aux
Steam
300 Electrical
SSDG
EDG
SSTG
GTG Module Mounts
Cabling Distribution
Switch Boards
400 Command/Surveillance
SPY Array
PCMS
MK 82
SPG 62
500 Auxiliary
Ventilation System - Structure
Ballast Systems
Steering
Hangar Doors
Rudders
Aux Blr /WHB
Elevators -Aircraft
Boat Davits
Stern Gate
Piping:
CHT
Firemain
CMWD
Main / Aux SW
600 Outfits/Furnishings
ICCP System
Corrosion, General
U/W Hull Paint Systems
700 Armament
VLS
Magazines
Elevators - Weapons
JSNs are branded and tracked throughout the E2E process
46
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Impact of Non-compliant Deferral Process
47
USS IWO JIMA:
AVAILS CANX TO INCREASE OPERATIONAL
SCHEDULE.
RESULTED IN :
• TANKS NOT ASSESSED SINCE
COMMISSIONING
• 115 TANKS IN UNKNOWN STATUS
• 25 TANKS REQUIRING 100% RECOAT
• POSSIBILITY OF AVAIL EXTENSION AND LOST
Ao
POSSIBILITY OF INCREASED AVAIL COSTS
DUE TO MANDATORY DOCKING WORK
USS ASHLAND:
ASSESSMENTS & MAINTENANCE
DEFERRED OVER MULTIPLE FRP
CYCLES
RESULTED IN :
• MULTIPLE AVAIL EXTENSIONS DUE TO
GROWTH/NEW WORK (AVAIL NOW 18+
MONTHS)
• INCREMENTAL DISCOVERY AVAIL
(1,600+ RCCs)
• INCREASED AVAIL COSTS (219%
G/NW)
• LOSS OF OPERATIONAL AVAILABILITY
USS STOUT: BMD SHIP
TANKS COND 3 and COND 4 REPAIRS
DEFERRED.
RESULTED IN :
• INCREASE TANK INTERNAL DEGRADATION
• FUTURE AVAIL CHANGED TO DOCKING
REPAIRS
• INCREASED FUTURE AVAIL COST TO
SUPPORT DOCKING REQUIREMENTS
PLACE
HOLDER
IWO TANK PICTURE ; COND 3 TANK
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
FY14 CMP tasks / revisions
Radiation Hazard Certification
Pointing and Firing Cutouts Certification
LPD 17 SWAN Fail-over Test
MCM Rudderstock Seals Replacement
LHD Laundry and Galley Ventilation
LPD 17 Fiber Optic Cables
LHD Stern Gate Transom Gasket
Stern Gate Cylinder Rebuilds
DDG Collective Protection System
Silicon Aluminum Bronze Union Nuts
• NSWC Below Waterline Space Assessments
48
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
Executing the Requirement Developing & Tracking CMP / CSWT Tasks
49
• Standardizes recurring repair
planning – reduces planning costs
• Reduces variance of work scope
between ports/contractors
• Provides contract vehicle for
detailed technical instructions
• Standardizes cost estimating
• Improves cost return analysis for
feedback into the requirement
process
• Incorporates best
practices/lessons learned
CMP / CSWT
(Technical. Req.) BAWP
(Est. $, Scope)
AWP (Gov. Est.)
Execution (Track growth vs. Est.)
Avail Close Out (Variation Analysis)
Analysis
• Review CMP, SWTs,
CSWTs, and LWTs
• Technical Doc.
• Configuration Data
• Failure Analysis
• Return Cost Data
Develop Strategy
• Identify Gaps
• Engage with ISEA
• Identify tasks to be
inactivated, modified or
created
• Draft Maintenance Strategy
Approval /
Develop Task • TWH Approval
• AP cards
• SWTs or CSWTs and IGEs
• Fielding Plan
• Resource Plan
• CMP task in M&SWP
Implementation
• Socialize with the
Waterfront
• Master Spec Catalog
• M&SWP – Go Live
• TWH Follow-up
Class Standard Work Template (CSWT)
Currently 5500 templates in the Master Spec Catalog
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
50
The Good News about…
Stern Gate Cylinder Rebuilds
ICMP Task Number: Q-58420-A01 MRID: 106245 Periodicity: 72M
Short Description: Overhaul Stern Gate Mechanical System
Cost Estimate: Man-days: 54 Material: $210,910 Associated CSWT: 584-024
Class Applicability: LSD 41/49 First Hull: USS ASHLAND (LSD 48)
CMP
Task at a
Glance:
Background: Stern gate hydraulics and operating equipment are high usage items that are
operated in a harsh exposed environment which can lead to increased corrosion.
System downtime can impact amphibious operations and the ship’s ability to
meet mission tasking.
Strategy: Preserve Stern Gate Foundation and Cylinder to include rebuilding of the Port
and Starboard Hydraulic Cylinders (and associated components).
Benefit: Time directing the maintenance in the CMP will improve the overall maintenance
strategy for the stern gate equipment, provide a budget for better and lower cost of
continuous maintenance, while minimizing the excessive costs of growth and new
work; all of which will increase reliability and support the primary mission of the
ship.
Questions concerning this CMP Task should be addressed to: [email protected]
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
51
The Good News about…
Stern Gate Transom Gasket
ICMP Task Number: Q-58420-A02 MRID: 106265 Periodicity/Situational Requirement: 36M
Short Description: Replace Stern Gate Lower Transom Gasket
Cost Estimate: Man-days: 89 Material: $10,500 Associated CSWT: 584-001 (41)/ 584-023 (49)
Class Applicability: LSD 41/49 First Hull: USS GERMNANTOWN LSD 42
CMP
Task at a
Glance:
Background: Stern gate gaskets are damaged during normal operation and require
maintenance every FRP avail.
Strategy: Replace stern gate transom gasket every 36M IAW LSD 41 and LSD 49 CSWTs.
Benefit: Time directing the maintenance in the CMP will improve the overall maintenance
strategy for the stern gate equipment, provide a budget for better and lower cost of
continuous maintenance, while minimizing the excessive costs of growth and new
work; all of which will increase reliability and support the primary mission of the
ship.
Questions concerning this CMP Task should be addressed to: [email protected]
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
52
The Good News about…
LSD 41 Sea Valves and Waster Sleeves
ICMP Task Number: Q-52010-A0A /Q-16310-A01 MRID: 93049 /93106
Periodicity/Situational Requirement: Every normal docking interval
Short Description: SEA VALVES REQUIRE REPAIR OR REPLACEMENT/ WASTER SLEEVES REQUIRE
REPLACEMENT.
Cost Estimate: Man-days: 474 / 209 Material: $61,455/8,738 Associated SWT/CSWT/AP: 520-052/163-013
Class Applicability: LSD 41 First Hull: LSD 42 USS GERMANTOWN
CMP
Task at a
Glance:
Background: Routine work performed on ships in dry dock normally consists of inspect and repair, sea
valves and sea chests. Waster sleeves are installed in sea chests to prevent galvanic
corrosion of sea chest valves and piping components. Waster sleeve removal facilitates
proper inspection of sea chests. Standard waster sleeve configurations require the sea
valve to be removed, most times damaging the waster sleeve in the process. Sea valve
inspections are preformed to accurately assess the extent of damage requiring repair.
Repairs vary in cost, smaller valves often exceeds 50% of the cost of a new valve.
Strategy: Replace sea valves 2 ½ inches and below, overhaul sea valves greater than 2 ½ inches
within every normal docking interval. Replace waster sleeves in conjunction with the sea
valve task.
Benefit: Additional costs to remove sea valves for repair is eliminated, the cost of valve removal is
rolled into the cost of the waster sleeve repair. Catastrophic failure to sea valves that are
exposed to harsh environments are reduced. Decrease need for costly diving services that
pose logistical challenges affecting ships operational requirements.
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
53
The Good News about…
CALEY DAVIT OVERHAUL
ICMP Task Number: Q-58311-A21 MRID: 105373 Periodicity/Situational Requirement: 72 CNO Avail
Short Description: CALEY DAVIT OVERHAUL
Cost Estimate: 154 Mandays Material: $93,657 (Including OEM Cost) Associated CSWT: 583-003
Class Applicability: LPD-17 First Hull: LPD-2 USS NEW YORK
CMP
Task at a
Glance:
Background: Currently there are no tasks for overhaul
the Caley Boat Davits for LPD 17 class ships. The davit
suffers from maintainability and reliability issues.
Strategy: Scheduled CMP task to overhaul the Boat Davit
and Tow Boom every 72 months.
Benefit: A time directed overhaul strategy will improve
equipment lifecycle and readiness requirements while
minimizing growth and new work
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
54
The Good News about…
LPD 17 Sea Valves
ICMP Task Number: Q-52010-A0A MRID: 93049
Periodicity/Situational Requirement: Every normal docking interval
Short Description: SEA VALVES REQUIRE REPAIR OR REPLACEMENT
Cost Estimate: Man-days: 1,119 Material: $53,374 Associated SWT/CSWT/AP: 520-001
Class Applicability: LPD 17 First Hull/: LPD 18 USS GREEN BAY
CMP
Task at a
Glance:
Background: Routine work performed on ships in dry dock normally consists of inspect and repair, sea
valves and sea chests. Sea valve inspections are performed to accurately assess the extent
of damage requiring repair. Repairs vary in cost, smaller valves often exceeds 50% of the
cost of a new valve.
Strategy: Replace sea valves 2 ½ inches and below, overhaul sea valves greater than 2 ½ inches
within every normal docking interval.
Benefit: Catastrophic failure to sea valves that are exposed to harsh environments are reduced.
Decrease need for costly diving services that pose logistical challenges affecting ships
operational requirements.
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
55
The Good News about…
LPD VCHT Chemical Cleaning
ICMP Task Number: Q-59310-A01 MRID: 105989 Periodicity/Situational Requirement: CNO Availability
Short Description: VACUUM, COLLECTION, HOLDING, AND TRANSFER PIPING REQUIRES CHEMICAL CLEANING
Cost Estimate: Man-days: 141 Material: $75,600.00 Associated CSWT: CSWT 593-008
Class Applicability: LPD 17 First Hull: USS ANCHORAGE (LPD 23)
CMP
Task at a
Glance:
Background: VCHT piping is highly susceptible to
corrosion and clogging due to build-up. This can lead to
failure of the system and greatly affect ship’s habitability.
Waterfront best practice determined chemically cleaning
to be necessary on a time/availability directed basis.
Strategy: Accomplish a chemical cleaning of Vacuum
Collection, Holding, and Transfer piping every FRP to
ensure system operational integrity.
Benefit: Supports Waterfront Best Practices to avoid
failure and effective maintenance planning. Reduces
growth and new work during CNO availabilities.
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
56
The Good News about…
Ventilation Steam Heaters
ICMP Task Number: I-51200-A05 MRID: 113222 Periodicity: 72 Months (AVAIL PRE-270)
Short Description: ASSESS VENTILATION SERVICE STEAM HEATER SYSTEM
Cost Estimate: Man-days: 50 Estimate provided by NSWCCD-SSES Code 922.
Class Applicability: LHD-1, LCC-19 First Hull/Date: TBD
CMP
Task at a
Glance:
Background: Ventilation system service steam heaters have become severely
degraded are in various states of inoperability, presenting safety
hazards to Ship’s Force personnel and other ship equipment.
Strategy: Establish mandatory tasking for ISEA to inspect service steam
heaters and piping components, assess operability and
configuration, assist Ship’s Force in 2K generation, and provide a
written report with a Risk Matrix and ILS recommendations.
Benefit: Increase safety to personnel and equipment, improve system
readiness and operability, reduce overall repair costs
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
57
The Good News about…
NSWC Below Waterline Space Assessments
MRID: 108096 Periodicity/Situational Requirement: Dry Dock FRP cycle
Short Description: CONDUCT STRUCTURAL ASSESSMENT OF ALL COMPARTMENTS BELOW WATERLINE
Cost Estimate: Man-days: 220 (COMB), 265 (AMPH) Material: N/A Associated CSWT: N/A
Class Applicability: All Classes (MCM, PC excluded) First Hull/Date: CURRENTLY BEING FIELDED
CMP
Task
at a
Glance:
Background:
Unidentified structural and corrosion related deficiencies would often
lead to growth and new work during docking availabilities. Correction
of the deficiencies would often result in availability duration
extensions and impact total costs.
Strategy: NSWC-CD will conduct a “below the waterline” structure and corrosion
assessment prior to each scheduled docking. The assessment will be
scheduled for completion at A-720 during the DSRA FRP cycle. Credit will be
given for any G1N6 technical requirement to prevent duplication of effort.
Benefit: Early and consistent identification of structural and corrosion required repairs.
Detailed report to include risk matrix, technically valid JSNs and DFS direction.
Reduction of growth and new work. Reduction in assessment costs by non-
duplication of efforts by multiple activities. Provides early input to the POM
budget submission process.
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
58
The Good News about…
LPD-17 Bulwarks
MRID: 107951 Periodicity/Situational Requirement: DRYDOCK
Short Description: REPAIR & PRESERVE WITHIN THE BULWARK
Cost Estimate: Man-days: 644 Material: $50,020 Associated CSWT: 150-001
Class Applicability: LPD-17 First Hull: LPD-18 USS NEW ORLEANS
CMP
Task
at a
Glance:
Background: Due to the bulwark design, applied coatings and location, the bulwarks on LPD-
17 class have experienced recurring premature coating system failure and
subsequent structural degradation. These structural failures have frequently
resulted in water penetration to adjacent compartments and running rust on the
ship exterior requiring additional repairs and coating application.
Strategy: Every docking availability, bulwarks will receive a directive task with a
supporting Class Standard Work Template (CSWT) to repair any structural
degradation and preserve the deck plating and structural members utilizing
Ultra High Solids (UHS) coatings.
Benefit: The new repair task will maintain the structural integrity of the bulwarks,
improve ship appearance by reducing running rust, and result in cost
avoidance through reduced growth work and new work.
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
59
The Good News about…
LCC Condenser
Sea Water Rubber Expansion Joints
ICMP Task Number: Q-25600-A05 MRID: 112700 Periodicity/Situational Requirement: Docking Availability
Short Description: Replace Main condenser expansion joints.
Cost Estimate: Man-days: 61 Material: $22,331.58 Associated CSWT: CSWT 256-006
Class Applicability: LCC 19 First Hull: BLUE RIDGE (LCC 19)
CMP
Task at a
Glance:
Background: Main condenser rubber expansion joints
accommodate thermal growth and shock motion of the
sea water circulating piping system. In compliance of
NSTM requirement 505-3.37.1, “Replace rubber
expansion joints in manned spaces at least every 10-12
years”. This supports the O-FRP 36/9 construct.
Strategy: Replace main condenser expansion joints
each scheduled docking availability.
Benefit: Avoid catastrophic failures and costly
emergent repairs that will affect Operational Availability
and Expected Service Life.
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
60
The Good News about…
LSD Laundry and Galley Ventilation
ICMP Task Number: Q-51200-A01/ Q-51200-A02 MRID: 88927/97386 Periodicity/Situational Requirement: Every FRP
Short Description: GALLEY AND LAUNDRY VENTILATION REQUIRES INTERNAL CLEANING
Cost Estimate: Man-days: 129 (LSD 41), 131 (LSD 49) Material: $18,070 Associated CSWT: 512-020 (LSD 41), 512-021 (LSD 49)
Class Applicability: LSD 41 and 49 First Hull: USS RUSHMORE (LSD 47)
CMP
Task at a
Glance:
Background: Ventilation systems associated with shipboard laundries and galleys that are
poorly maintained cause a buildup of dirt, grease, and oil in ventilation ducts;
restricts airflow, reduces air flow capabilities, exceeds design pressure and
results in elevated temperatures, hazardous environments, loss of ships
efficiency and increased operational costs. Most ventilation components are
located in constrained spaces, making maintenance difficult for ships force;
resulting in repairs and cleaning being accomplished on a fix-when-fail basis.
Strategy: Cleaning of galley and laundry ductwork and associated components with
NAVSEA approved methods within every FRP cycle.
Benefit: Clean ventilation protects personnel and sensitive equipment from potentially
hazardous airborne contaminants, fires, explosions, and excessive heat;
reduces ships emissions, ship operates more efficiently and lowers operational
costs.
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
61
MRID: 112358 Periodicity/Situational Requirement: “R”: Scheduled at A-270 each FRP cycle
Short Description: Steam Propulsion ISEA Assessment
Cost Estimate: Man-days: 220 Material: N/A Associated CSWT: N/A
Class Applicability: LHD 1-7 /LCC-19 (8 ships/15 propulsion plants) First Hull: USS ESSEX
CMP
Tasks
at a
Glance:
Background: Errors in assessments/repair planning/execution, lack of critical spare parts, and failure to implement
lessons learned have led to CNO Availability propulsion plant growth work, schedule extensions and
significant cost increases.
Strategy: Provide ISEA engineering and inspector involvement in critical steam propulsion plant equipment baseline
assessments, work package development, onsite technical support during critical repairs, inspections and
tests, and participation in post availability IPTDs. This approach applies the proven Boiler Strength and
Integrity Inspection process model (PSAI/SAI/ISVs/CAI/IPTD) to critical steam propulsion components and
systems. Includes: main propulsion and auxiliary steam turbines, SSTGs, forced draft blowers, heat
exchangers, condensers, distilling plants, pumps, piping & valves, all associated automation/controls, etc…
Benefit: Early and accurate identification of deficiencies and associated critical LLTM, technical input and OQE for
repair planning, critical QA inspections for complex work packages, proactive onsite assistance with immediate
engineering reach back to all NAVSSES Subject Matter Experts and application of lessons learned between
repair activities. Result is reduction in growth work, schedule disruption and total costs.
Steam Propulsion Plant Readiness
Enhanced CNO Maintenance Availability ISEA Support
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
62
The Good News about…
Radiation Hazard Certification
ICMP Task Number: I-86113-A03 MRID: 104896 Periodicity/Situational Requirement: 60M
Short Description: Certify Radiation Hazard (RADHAZ) Control Measures
Associated SWT/CSWT/AP: NAVSEAINST 9700.2, NAVSEA S9040-AA-GTP-010/SSCR
Class Applicability: All Surface Ships First Hull/Date: Ongoing Last Hull/Date: Ongoing
CMP
Task at a
Glance:
Background: NAVSEAINST 9700.2 Integrated Topside Safety and Certification
Program for Surface Ships and S9040-AA-GTP-010/SSCR Surface Ships
Certification Requirements, Rev 5, Chapter 1, require: “RADHAZ Cert. issued upon confirmation of proper placement of required control
measures and is effective for 5 yrs.”
Strategy: NSWC Dahlgren Division Q52 and NSWC PHD A33 requested
SURFMEPP CHENG convert existing Routine into a 60M Scheduled
Assessment that can be pushed and tracked within the CMP.
Benefit: This Certification, with safety impacts, will be formally tracked and
managed by NAVSEA 21 via SURFMEPP.
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
63
The Good News about…
Pointing and Firing Cutouts Certification
ICMP Task Number: I-86113-A02 MRID: 104554 Periodicity/Situational Requirement: 36M
Short Description: CERTIFY POINTING AND FIRING CUTOUTS.
Associated SWT/CSWT/AP: NAVSEAINST 9700.2, NAVSEA S9040-AA-GTP-010/SSCR
Class Applicability: All Surface Ships First Hull/Date: Ongoing Last Hull/Date: Ongoing
CMP
Task at a
Glance:
Background: NAVSEAINST 9700.2 Integrated Topside Safety and Certification Program for Surface Ships,
Encl (1), Para 1.g.(1) requires: “safe, correct and interference free installation of weapon systems pointing and firing cutout (P&FCO) zones
whenever a SHIPALT has been accomplished which affects the P&FCO or if it has been more than three
years since the last certification.”
Strategy: NSWC Dahlgren Division G73 requested SURFMEPP
CHENG convert existing Routine into a 36M Scheduled
Assessment that can be pushed and tracked within the CMP.
Benefit: This Certification, with safety impacts, will be formally
Tracked and managed by NAVSEA 21 via SURFMEPP.
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
64
The Good News about…
LPD 17 SWAN Fail-over Test
ICMP Task Number: I-4A040-A04 MRID: 97426
Periodicity/Situational Requirement: DEPLOY PRE - 180
Short Description: SWAN Fail-over Test.
Cost Estimate: 24 M/H Director/Rover; 156 M/H SF Operators. Associated SWT/CSWT/AP: Drawings (see above)
Class Applicability: LPD 17 First Hull/Date: LPD 20 USS GREEN BAY
CMP
Task at a
Glance:
Background: • INSURV Technical Issue Paper 12-003 of 13 Jun 12 cited OPNAVINST 9070,
2009 NVR and DOD Directive 8500.2 in requiring formal demonstration of SWAN
redundancy and survivability.
• PEO Ships 317 contracted Raytheon to develop test procedures to meet the
requirements and TWH NAVSEA 05WH approved the resulting drawings and
mandatory requirement.
Strategy: Implement the 3 drawings, by WAN architecture and hull series, in a scheduled pre-
deploy CMP Task with execution funded by PEO Ships 317.
• 9002134 Rev B - LPD 17/18
• 9003644 Rev D - LPD 22 - 25
• 9003734 Rev A - LPD 19 - 21
Benefit: Demonstrate ability to sustain combat ops, mission critical networks and
contingency plans required in cited documents.
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
65
The Good News about…
Rudderstock Seals Replacement
ICMP Task Number: Q-56211-A07 MRID: 97726 Periodicity/Situational Requirement: Dry-dock
Short Description: Rudderstock Seal Assemblies Require Replacement
Cost Estimate: Man-days: 28 Material: $46,700.00 Associated CSWT: MCM-1 562-006
Class Applicability: MCM -1 First Hull/Date: USS CHIEF (MCM 14)
CMP
Task at a
Glance:
Background:
A number of US Navy surface ships have recently experienced
severe damage to rudder spherical roller bearings (SRB). CG 47,
DDG-51, FFG 7, LHD 1-7, LHA 1, LPD-4, LPD-17, MCM and LSD41/49
class ships are susceptible to sea water intrusion into the lower
rudder bearing.
Strategy:
Create mandatory CMP task and supporting CSWTs to replace
Rudderstock Inflatable Seal, Hull Seal, Upper & Lower Bearing Seals,
and Sand Excluder Seals every CNO Dry-Docking Availability.
Benefit:
Prevent premature bearing failure, cost savings through effective
planned maintenance.
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
66
The Good News about…
LHD Laundry and Galley Ventilation
ICMP Task Number: Q-51200-A01/ Q-51200-A02 MRID: 88927/97386 Periodicity/Situational Requirement: Every FRP
Short Description: GALLEY AND LAUNDRY VENTILATION REQUIRES INTERNAL CLEANING
Cost Estimate: Man-days: 112 Material: $18255 Associated CSWT: LHD 512-003
Class Applicability: LHD First Hull/Date: USS IWO JIMA (LHD 7)
CMP
Task at a
Glance:
Background: Ventilation systems associated with shipboard laundries and galleys that are
poorly maintained cause a buildup of dirt, grease, and oil in ventilation ducts;
restricts airflow, reduces air flow capabilities, exceeds design pressure and
results in elevated temperatures, hazardous environments, loss of ships
efficiency and increased operational costs. Most ventilation components are
located in constrained spaces, making maintenance difficult for ships force;
resulting in repairs and cleaning being accomplished on a fix-when-fail basis.
Strategy: Cleaning of galley and laundry ductwork and associated components with
NAVSEA approved methods within every FRP cycle.
Benefit: Clean ventilation protects personnel and sensitive equipment from potentially
hazardous airborne contaminants, fires, explosions, and excessive heat;
reduces ships emissions, ship operates more efficiently and lowers operational
costs.
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
67
The Good News about…
LPD 17 Fiber Optic Cable Plants
ICMP Task Numbers: I-4A040-A01, 3 & 2 MRIDs: 93145, 96907, 96905
Periodicity/Situational Requirement: DEPLOY PRE – 60 (A6G4) , CNO AVAIL (A6G5, A5G6)
Short Description: FOCP Repair Readiness, Growth Tube and Material Condition Assessments.
Cost Estimate: 16, 384 & 80 Man-Hours each. Associated SWT/CSWT/AP: A6G4, A6G5, A6G6
Class Applicability: LPD 17 First Hull: USS SAN DIEGO (LPD 22)
CMP
Task at a
Glance:
Background: ISEA NSWC Dahlgren Division W64 Proposed and TWH NAVSEA 05W Approved
creating AP-MRC-based scheduled 60-days-pre-deployment tasks to ensure
LPD 17 FOCP material, crew, tools readiness and to assess growth capacity.
Strategy: Implement the following AP Cards as Scheduled CMP Tasks, Funded by PMS 470
A6G4 - Fiber Repair Readiness Assessment
A6G5 - FOCP Growth Tube Assessment
A6G6 - FOCP Material Condition Assessment
Benefit: Greatly improved Operational Availability. Crew over-the-shoulder
training. Improved information for fiber capacity growth planning.
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
68
The Good News about…
Stern Gate Transom Gasket
System Photo
ICMP Task Number: Q-58420-A02 MRID: 106265 Periodicity/Situational Requirement: 27M
Short Description: Replace Stern Gate Lower Transom Gasket
Cost Estimate: Man-days: 83 Material: $4,680 Associated SWT/CSWT/AP: 584-002
Class Applicability: LHD-1 First Hull: USS BATAAN (LHD 5)
CMP
Task at a
Glance:
Background: PREPRL and SSEOC noted a need to create Stern Gate CMP tasks.
There is a clear shortage of CMP stern gate time directed repair and assessment
tasks. The number of A1 branded repair tasks is currently zero.
Strategy: Replace Stern Gate Transom Gasket (Lower Section) every 27M. Please see CSWT
584-002.
Benefit: Time directing the maintenance in the CMP will improve the overall maintenance
strategy for the stern gate equipment, provide a budget for better and lower cost of
continuous maintenance, while minimizing the excessive costs of growth and new
work; all of which will increase reliability and support the primary mission of the
ship.
Questions concerning this CMP Task should be addressed to: [email protected]
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
69
The Good News about…
Stern Gate Cylinder Rebuilds
System Photo
ICMP Task Number: Q-58420-A01 MRID: 106245 Periodicity/Situational Requirement: 54M
Short Description: Overhaul Stern Gate Mechanical System
Cost Estimate: Man-days: 140 Material: $163,905 Associated SWT/CSWT/AP: 584-003
Class Applicability: LHD-1 First Hull: USS BATAAN (LHD 5)
CMP
Task at a
Glance:
Background: PREPRL and SSEOC noted a need to create Stern Gate CMP tasks.
There is a clear shortage of CMP stern gate time directed repair and assessment
tasks. The number of A1 branded repair tasks is currently zero.
Strategy: Preserve Upper and Lower Stern Gate Foundation and Cylinder to include
rebuilding of the Upper and Lower Hydraulic Cylinders (and associated
components). Please see CSWT 584-003
Benefit: Time directing the maintenance in the CMP will improve the overall maintenance
strategy for the stern gate equipment, provide a budget for better and lower cost of
continuous maintenance, while minimizing the excessive costs of growth and new
work; all of which will increase reliability and support the primary mission of the
ship.
Questions concerning this CMP Task should be addressed to: [email protected]
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
70
The Good News about…
DDG’s Collective Protection System
ICMP Task Number: Q-51200-A04 MRID: 105999 Periodicity/Situational Requirement: One-Time
Short Description: CPS CLEAN SIDE PLENUM ACCESS OPENING REQUIRES REMOVAL
Cost Estimate: Man-days: 7 Material: $115 Associated SWT/CSWT/AP: DDG: 512-029
Class Applicability: DDG 51- 92 First Hull/Date: USS HIGGINS (DDG 76)
CMP
Task at a
Glance:
Background: During CPS filter change outs, chemical/biological/radiological (CBR)
filters are leak tested to verify the filters, housings, and
plenums do not leak. During leak testing of CBR filters serving
CPS Zone 1 on DDG51 class hulls, leak failures are often identified
through a plenum access plate in Zone 1 bulkhead separating the
clean side plenum from the dirty side plenum in CPS fan room 01-
110-3-Q. ISEA Advisory 031-13 Rev 1. DTG 121130Z NOV 13.
Strategy: Remove Collective Protection System (CPS) clean side access opening and
replace with a new welded plate.
Benefit: CPS integrity, protecting personnel from hazardous CBR environments.
SURFMEPP Achieving Expected Service Life…One Ship at a Time
DISTRIBUTION STATEMENT C. Distribution authorized to U.S. Government Agencies and Naval Sea Systems Command (NAVSEA) contractors involved with ship construction and repair. Other requests for this document shall be referred to SURFMEPP.
71
The Good News about…
DDG Silicon Aluminum Bronze Union Nuts
ICMP Task Number: I-50500-A02 MRID: 101627 Periodicity/Situational Requirement: One-time
Short Description: PIPING SYSTEMS REQUIRE INSPECTION FOR SAB MATERIAL
Cost Estimate: Man-days: 942 Material: $60,854 Associated SWT/CSWT/AP: CSWT 505-007
Class Applicability: DDG (51-92) First Hull/Date: USS JOHN PAUL JONES (DDG-53)
CMP
Task at a
Glance:
Background: Silicon Aluminum Bronze (SAB) unions have been known to have failed on high pressure air
systems. This was first discovered at the beginning of 2000 on DDG 51 class ships, and
again in October 2010 on LPD 17 class ships. A series of laboratory tests was conducted
and identified specific conditions, stress levels, and defined the limitations of SAB nuts
making them susceptible to failure. As a result, Naval Sea Systems Command (NAVSEA)
issued Surface Fleet Advisory No. 11-01 Silicon Aluminum Bronze Union Failure, directing
the Surface Fleet to conduct ship-wide inspections of systems greater than 300 psi, to
identify unions with SAB material, and immediately replace them. This shall be adjudicated
by DFS, for later repair.
Strategy: Accomplish a one-time, ship-wide inspection of all union-ended valves and takedown joints
for the presence of SAB material in piping systems with a design pressure of greater than
300 psi, and replace indentified SAB unions.
Benefit: Prevents risk of union failure and potential of endangering personnel and equipment .