SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA …€¦ · 13:15 Lunch Monday 25th January 2016...
Transcript of SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA …€¦ · 13:15 Lunch Monday 25th January 2016...
1
SUPPORT TO WATER RESOURCES
MANAGEMENT IN THE
DRINA RIVER BASIN
Brief Status on Project Progress
David HeywoodBELGRADE 25-26 January 2016
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
2
1. Review of Agenda
2. Progress on Tasks
3. Progress on Deliverables
4. Inputs
5. Financials
6. Constraints
ITEMS
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
3
Date Time Venue Details
DAY ONE
Monday 25th January 2016Morning session
9:30
Hotel Park (TBC)
Registration of ParticipantsCoffee available
10:30Welcome and Introduction by Chairman of Coordination Committee (B Kenjic)
10:45 Brief status on Project Progress (KE1 David Heywood)
11:10Summary of Water Resources Management issues associated with three country reports (KE1 David Heywood)
11:30Summary of Environmental issues associated with three country reports (KE2 Stephanie Andre)
11:50 Coffee Break
12:20Summary of Hydropower issues associated with three country reports (KE3 Bernard Joos)
12:40Summary of Legal and Institutional issues associated with three country reports (KE4 Dragoljub Todic)
13:15 Lunch
Monday 25th January 2016Afternoon session
14:15
Hotel Park (TBC)
Question/Comments on BiH CR from BiH SH
14:45 Questions/Comments on Montenegro CR from MNE SH
15:15 Questions/Comments on Serbia CR from SER SH
15:45 Coffee Break
16:15Prioritisation of Recommendations - IWRM Basin Level ReportKE1 David Heywood
17:00 TentativeSteering Committee Meeting (Three country focal points, World Bank and Consultant)
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
4
Date Time Venue Details
DAY TWO
Tuesday 26th
January 2016
Morning Session
9:30
Hotel Park (TBC)
Presentation of hydrological model and outputs (Cerni)
9:50Presentation of draft climate change model and outputs
(Faculty)
10:10 Presentation of conceptual WEAP model (Faculty)
10:30Introduction of development scenarios for Investment
Prioritisation Framework (KE 1 David Heywood)
11:00 Coffee Break
11:20 Introduction of Green Growth Scenario (KE1 David Heywood)
11:50 Introduction of Full HPP scenario (KE3 Bernard Joos)
12:20 Any other Business
12:45 Wrap up by Coordination Committee Chairman (B Kenjic)
13:00 Lunch
SH disperse
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
5
TASKS• Task 0 – Project Management• Task 1 – Inception• Task 2 – River Basin Assessment• Task 3 – Institutional + Legal Assessment• Task 4 – Hydrological Simulation Model• Task 5 – Scenario Development• Task 6 - Inventory of Changes• Task 7 – Multi Criteria Analysis• Task 8 – River Basin Data Management• Task 9 – Capacity Building• Task 10 – Stakeholder Consultation and Organisation
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
6
Pro
jec
t M
an
ag
em
en
t a
nd
Co
ord
inati
on
›M
ob
ilis
ati
on
Acti
vit
ies
›M
an
ag
em
en
t A
cti
vit
ies
›B
acksto
pp
ing
Acti
vit
ies
Review and Analysis Phase
KEY ACTIVITIES:› Data Analysis and Review
› Hydrological Modelling› Multi Criteria Analysis
Final Reporting Phase
KEY ACTIVITIES:› Finalise country level RBMPs into one single RBMP
› On the Job Training
MAIN DELIVERABLES:› River Basin Assessment (Baseline) › Integrated Water Resources Management Study and Plan
› Institutional and Legal Assessment› Hydrological Model› Future Development Scenarios
› Investment Priority Framework
MAIN DELIVERABLES:› Roof Report for the Drina River Basin› Training Materials
› Training Workshops
KEY ACTIVITIES:› Inception Report and Updated Work Plan
MAIN DELIVERABLES:› Draft Inception Report
› Draft and Final Inception Report
Inception Phase
Sta
ke
ho
lde
rC
on
su
ltatio
n a
nd
Org
an
isa
tion
›S
take
ho
lde
r Ide
ntific
atio
n›
Pu
blic
Co
nsu
ltatio
n P
lan
›C
on
su
ltativ
eW
ork
sh
op
s (c
ou
ntry a
nd
basin
lev
el)
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
7
Task 0 – Project Management - Ongoing throughout Project
Task 1 - Inception - Completed
Task 2 – River Basin Assessment - Completed
Task 3 – Institutional and Legal Assessment – Completed
Task 4 - Modelling – In Progress
Task 5 – Scenario Development - In Progress
Task 6 - Inventory of Changes – Not Started
Task 7 – Multi Criteria Analysis – Not Started
Task 8 – River Basin Data Management – Not Started
Task 9 – Capacity Building – Not Started
Task 10 – Stakeholder Consultation and Organisation - Ongoing throughout Project
TASK STATUS
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
8
Oct. 14 Oct.-16TIMELINE
INCEPTION
IWRM COUNTRYREPORT
IIWRM BASINREPORT
INVESTMENTPRIORITIZATION
FRAMEWORKCOUNTRY REPORT
DRINA ROOF(BASIN) REPORT
DELIVERABLES
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
9
ITEMBOSNIA AND HERZEGOVINA
MONTENEGRO SERBIA RS FBIH
Inception (English) Feb 15 Feb 15 Feb 15 Feb 15
Inception (Local Language) May 15 May 15 May 15 May 15
Country Report (English) Nov 15 Nov 15 Aug 15 Sep 15
Country Report (Local Language) Dec 15 Dec 15 Oct 15 Dec 15
IWRM Basin Report (English) Mar 15 Mar 15 Mar 15 Mar 15
IWRM Basin Report (Local Language) Apr16 Apr16 Apr16 Apr16
IPF Country Report (English) Jun 16 Jun 16 Jun 16 Jun 16
IPF Country Report (Local Language) Jul 16 Jul 16 Jul 16 Jul 16
Roof Report (English) Oct 16 Oct 16 Oct 16 Oct 16
Roof Report (Local Language) Nov 16 Nov 16 Nov 16 Nov 16
Public Consultation Report (Eng + Local) Nov 16 Nov 16 Nov 16 Nov 16
Denotes Submitted
REPORT DELIVERABLES
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
10
PrefixCodex Task Ref # Title of Report Deliverable
PR# Task 0 Monthly Progress Report (electronic form only) Continuous Activity
IAR Tasks 0-5 Intermediate (Annual) Report RPC Task 10 Report on Preliminary ConsultationsDFR Tasks 5-10 Draft Final ReportFR Tasks 5-10 Final Report including report on Final consultation WorkshopDIR Task 1 Draft Inception Report and Revised Work PlanFIR Task 1 Final Inception Report and Revised Work Plan
DBP BiH Tasks 2-5 Draft IWRM Study and Plan – Background Paper – BiH (FBiH+RS)DBP Ser Tasks 2-5 Draft IWRM Study and Plan – Background Paper – Serbia
DBP MNE Tasks 2-5 Draft IWRM Study and Plan – Background Paper – MontenegroFBP BiH Tasks 2-5 Final IWRM Study and Plan – Background Paper – BiH (FBiH+RS) To be completed after 25/26 Workshop
Then needs public consultation process to discuss them
FBP Ser Tasks 2-5 Final IWRM Study and Plan – Background Paper – SerbiaFBP MNE Tasks 2-5 Final IWRM Study and Plan – Background Paper – MontenegroDIWRMP Tasks 2-5 Draft IWRM Study and Plan at Basin LevelFIWRMP Tasks 2-5 Final IWRM Study and Plan at Basin Level
DIPF - BiH Tasks 6-8 Draft Investment Prioritization Framework – BiH (FBiH + RS)DIPF - Ser Tasks 6-8 Draft Investment Prioritization Framework – SerbiaDIPF MNE Tasks 6-8 Draft Investment Prioritization Framework – MontenegroFIPF - BiH Tasks 6-8 Final Investment Prioritization Framework – BiH (FBiH + RS)FIPF - Ser Tasks 6-8 Final Investment Prioritization Framework – SerbiaFIPF MNE Tasks 6-8 Final Investment Prioritization Framework – Montenegro
DDBRR Tasks 6-8 Draft Drina Basin Roof ReportFDBRR Tasks 6-8 Final Drina Basin Roof Report
DPCR Task 7 Public Consultation Report - Draft
FPCR Task 7 Public Consultation Report – Final Denotes Completed
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
11
WORKSHOP DELIVERABLES
No Task Ref # Title/Reason for the Workshop (WS) No of
Days Timing
1 Task 0 Kick Off Meeting/Workshop 1 Start Month 1
2 Task 1 Inception Workshop to discuss DIR 1 End of Month 2
3 Tasks 2-5 Present IWRM DBP for BiH (FBiH + RS), Serbia + MNE 3 Month 11 16
4 Tasks 2-5 Broad scale WS for IWRM DBP - BiH (FBiH + RS) 1 Month 12 18
5 Tasks 2-5 Broad scale WS for IWRM DBP - Serbia 1 Month 12 18
6 Tasks 2-5 Broad scale WS for IWRM DBP - MNE 1 Month 12 18
7 Tasks 2-5 Finalise IWRM FBP – at Basin Level 1.5 Month 17 20
8 Tasks 6-8 WS for D IPF for BiH (FBiH + RS), Serbia + MNE 3 Month19
9 Tasks 6-8 Broad scale WS for DIPF - BiH (FBiH + RS) 1 Month 22
10 Tasks 6-8 Broad scale WS for DIPF - Serbia 1 Month 21
11 Tasks 6-8 Broad scale WS for DIPF - MNE 1 Month 21
12 Tasks 6-8 Finalise F IPF – at Basin Level 1.5 Month23
13 Task 9 Training workshop for Modelling 1 Month24
14 Task 9 Training workshop for Economic evaluation/risk 1 Month24
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
12
OTHER DELIVERABLES
Task Ref # Title of Deliverable Month Due
Task 6 Scope of Work for Additional Investigations Month 22
Task 7 Multi Criteria Analysis Model Month 14 20
Task 8 Updated Data Records for Drina River Basin Month 24
Task 9 Training Manual for Hydrological Model Month 24
Task 9 Hydrologic Model Month 19
Task 9 Training Materials for Modelling Month 22
Task 9 Training Materials for Economic Evaluation and Risk Assessment Month 22
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
13
1. Oct 14 start – 16 months into project
2. Initially 16 months operation
3. Now 24 months
4. VO1 Processed
5. VO2 in progress – should be completed in February 16
PROJECT MANAGEMENT
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
14
• Now available in English and Local Language
• Calendar operation to show key dates
• Stakeholder links and social media links now available
PROJECT WEB SITE
1. Europe 1,642 91.58%
2. North America 78 4.35%
3. Asia 35 1.95%
4. South America 25 1.39%
5. Africa 12 0.67%
6. Oceania 1 0.06%
1. Serbia 1,011 56.32%
2. Montenegro 203 11.31%
3. Bosnia and Herzegovina 176 9.81%
4. United Kingdom 83 4.62%
5. United States 72 4.01%
6. Switzerland 22 1.23%
7. Brazil 21 1.17%
8. Germany 20 1.11%
9. Italy 19 1.06%
10. Croatia 19 1.06%
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
15
1. Oct 14 start – 16 months into project
2. Initially 16 months operation
3. Timeframe now 24 months
4. VO1 Processed
5. VO2 in progress – should be completed in February 16
6. Even 24 months timeframe looks difficult!!!!
OVERALL CONTRACT STATUS
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
16
1. Contract signed 2nd October 2014.
2. Project in operation for 15 months.
3. Modification A – 23/3/15 – covering VO#1 extra costs translation Workshops.
4. Modification B – 28/5/15 – revise terms and conditions of payment.
5. Modification C – Jan/Feb 2016 VO#2 extend timing to 24 months with fees + reimbursable costs – currently in progress.
CONTRACT & MODIFICATIONS
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
17
• Input amounts to 1,478 days – 350 key and 1128 key
• With VO2 this amount will rise to about 1,500
• More than 90% of input has been consumed but less than 50% of the project has been completed!
• Fixed price lump sum contract however
INPUTS
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
18
1. Stakeholder meetings taking too long to organise (last one >2 months)
2. Obtaining key data not good enough
3. Coordination not good enough
CONSTRAINTS
WORLD BANK - SUPPORT TO WATER RESOURCES MANAGEMENT IN THE DRINA RIVER BASIN
19
Thank You!