SUPPLY OF PIG LAUNCHER / RECEIVER FOR...

81
SUPPLY OF PIG LAUNCHER / RECEIVER FOR HARIDWAR - RISHIKESH - DEHRADUN PIPELINE (HRDPL) PROJECT Project No. P.013313 Document No. P.013313 D11031 003 E - Tender No. 8000014799 GAIL (India) Limited Noida | INDIA PUBLIC 23 April 2019 TECHNICAL DOCUMENTATION Technical, Vol II of II, Rev. 0

Transcript of SUPPLY OF PIG LAUNCHER / RECEIVER FOR...

SUPPLY OF PIG LAUNCHER / RECEIVERFOR HARIDWAR - RISHIKESH -DEHRADUN PIPELINE (HRDPL) PROJECT Project No. P.013313Document No. P.013313 D11031 003E - Tender No. 8000014799

GAIL (India) LimitedNoida | INDIA

PUBLIC

23 April 2019

TECHNICAL DOCUMENTATIONTechnical, Vol II of II, Rev. 0

S.No. Document/ Drawing No. Rev. No. Pages Page No.

I VOLUME I OF II

1 P.013313 D 11033 003 0

2 P.013313 D 11033 003 0

3 P.013313 D 11033 003 0

4 P.013313 D 11034 003 0

5 P.013313 D 11035 003 0

6 P.013313 D 11037 003 0

7 P.013313 D 11038 003 0

II VOLUME II OF II

1 P.013313 D 11031 003 0 3 1

2 MR P.013313 D 11071 104 0 9 4

3 DATA SHEET P.013313 D 11088 105 0 2 13

4 DATA SHEET P.013313 D 11088 106 0 3 15

5 DATA SHEET P.013313 D 11090 107 0 1 18

6 DATA SHEET P.013313 D 11090 108 0 1 19

7 PTS P.013313 D 11077 109 0 10 20

8 PTS P.013313 D 11077 117 0 21 30

9 P.013313 D 11000 101 0 4 51

10 PMS P.013313 D 11076 101 0 6 55

11 PMS P.013313 D 11076 102 0 6 61

12 PTS P.013313 D 11077 111 0 5 67

13 QCT P.013313 D 11013 110 0 1 72

14 QCT P.013313 D 11013 140 0 3 73

15 QCT P.013313 D 11013 141 0 3 76

P.013313

D 11031

003

COMMERCIAL

Description

Section - I - Invitation for Bid (IFB)

Section - V - Special Conditions of Contract (SCC)

PROJECT-HARIDWAR RISHIKESH DEHRADUN PIPELINE.

160 Page 1 to 160

Section - III - Instructions to Bidders (ITB) including Attachments ( Annexures I, II ,III & IV)

Section - VII - Price schedule / Schedule of Rates (SOR)

Fittings

TABLE OF CONTENTS

PIG LAUNCHER / RECEIVER

Piping Specifications - Piping Classes (1C1)

Section - II - Bid Evaluation Criteria & Evaluation Methodology (BEC)

Material Requisition

Piping Specifications - Piping Classes (6C1)

TECHNICAL

Section - IV - General Conditions of Contract (GCC)

Piping Classes

Introduction

Quick Opening End Closure.

Pig Launcher

Section - VI- Forms and Formats

Flange

Non Intrusive type PIG Signaller

Pressure Safety Valve

Painting System and Colour Code for Final Layer

Pig Launcher

Pig Launcher/Receiver

Fittings & Flanges

Rev. 0 Supply of Pig Launcher / Receiver Page 1 of 1

INTRODUCTION

P.013313

D 11031

003

HARIDWAR-RISHIKESH-DEHRADUN PIPELINE

(HRDPL) PROJECT

TRACTEBEL ENGINEERING PVT. LTD.

INTRODUCTION

0 23.04.2019 Issued for Procurement VNG NC AR

Rev. Date Description Prepared By Checked By Approved By

Page 1 of 78

INTRODUCTION

P.013313

D 11031

003

Rev. 0 Supply of Pig Launcher / Receiver

Page 1 of 1

TABLE OF CONTENTS

1.0 INTRODUCTION ................................................................................................................. 1

2.0 TECHNICAL SPECIFICATIONS ............................................................................................ 1

3.0 DEFINITIONS ..................................................................................................................... 1

Page 2 of 78

INTRODUCTION

P.013313

D 11031

003

Rev. 0 Supply of Pig Launcher / Receiver

Page 1 of 1

1.0 INTRODUCTION

Gas Authority of India Limited (GAIL) is planning to lay a 50.000 kms (approx.) Natural Gas Pipeline, with

Dispatch Station (DT) at Jwalapur, in the Haridwar District of Uttarakhand State and Receipt Station (RT)

in the Dehradun District of Uttarakhand State. This proposed pipeline is hereinafter referred to as Haridwar-

Rishikesh-Dehradun Pipeline (HRDPL).

The Pipeline Size has been finalized as 8” NB, with a Flow capacity of 1.2 MMSCMD.

In addition to DT and RT, the proposed Natural Gas Pipeline shall have Six (6) nos. of Sectionalizing Valve

(SV) Stations between the dispatch terminal and receipt terminal and one (1) no. Tap-Off Station for

Rishikesh Spur Line.

The proposed pipeline is traversing within the vicinity of either existing GAIL’s pipeline or proposed ROU

of NH-58, NH-72 and other PWD roads of Haridwar and Dehradun and will cross though areas falling

under Location Class 1, 2, 3 and 4. However, Location Class 1 & 2 pipe thickness have not been used in the

entire pipeline route, only Location Class 3 & 4 pipe thickness have been used in the entire pipeline route.

The proposed natural gas pipeline route runs cross-country, between dispatch station and receiving station.

The route of the pipeline crosses through Rajaji National Park Wildlife Sanctuary, Reserve Forest, Major

River Crossings, Canal/Channel Crossing, Fault Line Crossing, Major District Roads Crossing including

National Highways and Railway Lines etc.

TE-India is now inviting tenders on Limited Domestic Competitive Bidding basis for procurement of Pig

Launcher/Receiver for this project.

The present document covers the technical specifications for this procurement enquiry. It forms an integral

part and is to be read in conjunction with ‘Volume I of II: Commercial.

2.0 TECHNICAL SPECIFICATIONS

The technical specifications for this present tender enquiry are as listed in Material Requisition (No.

P.013313 D 11071 104).

3.0 DEFINITIONS

Owner/Purchaser Shall mean GAIL (India) Ltd;

Engineer/Owner’s Representative Designate the individual or legal entity to which the

Owner has entrusted various tasks in relations with

the carrying-out of his project. This also includes

PMC (Project Management Consultant) of the

Project;

Manufacturer Means the Manufacturer of the Pig Launchers /

Receivers as well as its sub-contractor(s) including

the supplier(s) of Pig Signallers...etc.

Third Party Inspection Agency (TPIA) Means the Inspection Agency to be appointed by

Manufacturer

Control Authority Owner / Engineer or their Authorised Inspection

Agency

Σ Σ Σ

Page 3 of 78

MATERIAL REQUISITION FOR PIG

LAUNCHER.

P.013313

D 11071

104

HARIDWAR RISHIKESH DEHRADUN PIPELINE PROJECT

TRACTEBEL ENGINEERING PVT. LTD.

MATERIAL REQUISITION FOR PIG LAUNCHER

0 23.04.2019 Issued for Procurement VNG NC AR

Rev. Date Description Prepared by Checked by Approved by

Page 4 of 78

MATERIAL REQUISITION FOR PIG

LAUNCHER.

P.013313

D 11071

104

Rev. 0 Supply of Pig Launcher / Receiver

Page 1 of 1

TABLE OF CONTENTS

1. INTRODUCTION ................................................................................................................ 1

2. LIST OF ABBREVIATIONS ................................................................................................. 1

3. REFERENCE DOCUMENT.................................................................................................... 1

4. DESCRIPTION OF GOODS ADD/OR SERVICES AND OTHER DOCUMENTS REQUIRED

FOR PIG LAUNCHER / RECEIVER ...................................................................................... 1

A. REMARKS / COMMENTS .................................................................................................... 2

1.0 GENERAL NOTES ............................................................................................................... 2

2.0 COMPLIANCE WITH SPECIFICATION ............................................................................... 2

3.0 VENDOR's SCOPE .............................................................................................................. 2

4.0 INSPECTION ..................................................................................................................... 2

5.0 APPLICABLE DOCUMENTS ................................................................................................ 2

6.0 VENDOR's DOCUMENTS .................................................................................................... 2

7.0 DOCUMENTS NUMBERING AND FORMAT ......................................................................... 2

B. LIST OF ATTACHMENTS .................................................................................................... 3

C. DOCUMENTS & DATA REQUIREMENTS ............................................................................. 4

Page 5 of 78

MATERIAL REQUISITION FOR PIG

LAUNCHER.

P.013313

D 11071

104

Rev. 0 Supply of Pig Launcher / Receiver Page 1 of 7

1. INTRODUCTION

Gas Authority of India Limited (GAIL) is planning to lay a 50.000 kms (approx.) Natural Gas Pipeline, with

Dispatch Station (DT) at Jwalapur, in the Haridwar District of Uttarakhand State and Receipt Station (RT) in the

Dehradun District of Uttarakhand State. This proposed pipeline is hereinafter referred to as Haridwar-Rishikesh-

Dehradun Pipeline (HRDPL).

Present document is prepared to inviting enquiry for procurement of Pig Launcher /Receiver for 8” pipeline for

this project.

This document covers the technical specification for the enquiry.

2. LIST OF ABBREVIATIONS

GAIL GAIL India limited

TE Tractebel Engineering Pvt. Ltd.

TPIA Third Party Inspection Agency

3. REFERENCE DOCUMENT

Piping Class P.013313 D 11000 101

Piping Material Specification P.013313 D 11097 101 & P.013313 D 11097 102

4. DESCRIPTION OF GOODS ADD/OR SERVICES AND OTHER DOCUMENTS REQUIRED FOR

PIG LAUNCHER / RECEIVER

Item

Sr. No.

Total Qty Description

1. 1 Nos of

Launcher

Y-0201

Pig Launcher (Bi-directional type), 8" x 14", #600, along with internal tray, pig

handling device. - Removable type, Quick Opening Closure including all

applicable accessories as specified in tender datasheet & specification)

2 1 Nos of

Receiver

Y-1001

Pig Receiver (Bi-directional type) ,8" x 14", #600 , along with internal tray, pig

handling device, Quick Opening Closure including all applicable accessories as

specified in tender datasheet & specification

3 6 Nos Pig Signaller (Non-intrusive type) complying to tender datasheet and

specification.

4 2 Nos Pressure safety valve complying to tender data sheet and specification.

5 6 Nos ‘O’ Ring Gasket For Launcher / Receiver complying to tender data sheet and

specifications

Page 6 of 78

MATERIAL REQUISITION FOR PIG

LAUNCHER

P.013313

M 11050

104

Rev. 0 Supply of Pig Launcher / Receiver

Page 2 of 7

A. REMARKS / COMMENTS

1.0 GENERAL NOTES

VENDOR's compliance

Vendor shall submit his bid in full compliance with the requirements of this MR and attachments.

Vendor must include the following statement in his bid:

We certify that our bid is fully complying with your enquiry dated……………, and referenced…………………

Compliance with this material requisition in any instance shall not relieve the Vendor of his responsibility to

meet the specified performance.

2.0 COMPLIANCE WITH SPECIFICATION

The Vendor shall be completely responsible for the design, materials, fabrication, testing, inspection,

preparation for shipment and transport of the above equipment strictly in accordance with the Material

Requisition and all attachments thereto.

All items shall be provided with 3.2 certificates.

3.0 VENDOR's scope

Vendor scope of work includes the equipment with all internals and accessories shown on the data sheets,

specifications and all unmentioned parts necessary for a satisfactory operation and testing except those which

are indicated to be out of the Vendor's supply.

4.0 INSPECTION

Vender shall appoint anyone of the following TPIA for inspection purpose. Vender has to propose

minimum 2 no of below listed agencies to be approved by Owner/Owner’s Representative and /or Tractebel

Engineering.

a) Lloyd Register of Industrial Services

b) Technische Ulierwachungs Verein (TUV)

c) DNV-GL

d) AIB-Vincotte

e) Bureau Veritas

f) SGS

g) American Bureau Services (ABS).

5.0 APPLICABLE DOCUMENTS

General descriptions, requirements and information are listed in annex C of this Material Requisition.

6.0 VENDOR's DOCUMENTS

Vendor shall submit the documents as listed under point D of this Material Requisition.

All documents shall be submitted in English language only.

7.0 DOCUMENTS NUMBERING AND FORMAT

Vendor shall strictly follow the document numbering procedure in their document as per client’s instruction.

Page 7 of 78

MATERIAL REQUISITION FOR PIG

LAUNCHER

P.013313

M 11050

104

Rev. 0 Supply of Pig Launcher / Receiver

Page 3 of 7

B. LIST OF ATTACHMENTS

The table here below lists the documents which are integral part of

this Material Requisition. The applicable revision index of each

document is mentioned in the column below the current Material

Requisition revision index.

Material Requisition revision

0

Documents Revision of documents

Data Sheet - Pig Launcher

Doc No: P.013313 D 11088 105

0

Data sheet – QOEC

Doc No: P.013313 D 11088 106

0

Data sheet – Non intrusive type Pig Signaller

Doc No: P.013313 D 11090 107

0

Data sheet – Pressure safety valve

Doc No: P.013313 D 11090 108

0

Particular Technical Specification - Pig Launcher

Doc. No: P.013313 D 11077 109

0

Particular Technical Specification - Painting

Doc No : P.013313 D 11077 111

0

Particular Technical Specification - Fitting & Flange

Doc No : P.013313 D 11077 117

0

QCT – Pig Launcher

Doc No: P.013313 D 11013 110

0

QCT – Fitting

Doc No: P.013313 D 11013 140

0

QCT – Flange

Doc No: P.013313 D 11013 141

0

Page 8 of 78

MATERIAL REQUISITION FOR PIG

LAUNCHER

P.013313

M 11050

104

Rev. 0 Supply of Pig Launcher / Receiver

Page 4 of 7

C. DOCUMENTS & DATA REQUIREMENTS

The table hereunder specifies the quantities and the nature of the documents to be submitted by the

CONTRACTOR/ VENDOR to the ENGINEER.

The documents required at the inquiry stage and to be included in the bid are listed under column A.

The documents required after award of the AGREEMENT and subject to the written approval of the

ENGINEER are listed under column B.

The final and certified documents are listed under column C.

Any document, even when preliminary, shall be binding and therefore duly identified and signed by the

CONTRACTOR. It shall bear the ENGINEER's Project reference, the Material Requisition number and the

identification number.

THE DOCUMENTS ARE FULLY PART OF THE SUPPLY WHICH SHALL BE COMPLETE ONLY IF

AND WHEN THE DOCUMENTS COMPLYING FULLY WITH THE MATERIAL REQUISITION

REQUIREMENTS ARE RECEIVED BY THE ENGINEER.

Item Documents and Data

Document

Index No.

A B C

Number

of copies

Number

of copies Required

date

Number

of copies Required date

1 ISO Certification latest CDS 1 3 2 weeks 3

2 weeks

before

despatch

with final

techn. file

2 Completed data sheet for pig

launcher/receiver CDS 1

3

2 weeks

3 2 weeks

before

despatch

with final

techn. file

3

Recommended arrangement of Pig

Launcher/Receiver along with

internal tray, pig handling device

RAP 1

3

2 weeks

3

2 weeks

4 Drawing/data submittal

list/schedule DLS -

3 2 weeks +

monthly

3 2 weeks

5 Fabrication, test and delivery

schedule (per item) FTD -

3 2 weeks +

monthly

3 2 weeks

6 Progress report PRT - 3 2 weeks +

monthly

3 2 weeks

7 Catalogues / References CRS 1 3

- 3 With final

techn. file

8

Outline drawing + material

specification + unit weight

OMS -

3

2Weeks

3 With final

techn. file

9 Packing/shipping list with weights

and dimensions PLD -

3

2 weeks

before

shipping

3 2 weeks

before

despatch

with final

techn. file

Page 9 of 78

MATERIAL REQUISITION FOR PIG

LAUNCHER

P.013313

M 11050

104

Rev. 0 Supply of Pig Launcher / Receiver

Page 5 of 7

Item Documents and Data

Document

Index No.

A B C

Number

of copies

Number

of copies Required

date

Number

of copies Required date

10

Detail drawing + material

specification + unit weight +

calculations + Welding details

DMU -

3 2 weeks 3

2 weeks

before

despatch

with final

techn. file

11 Code compliance certificate

CCC -

3 2 weeks 3

2 weeks

before

despatch

with final

techn. file

12 Bill of materials (on drawings)

BOM -

3 2 weeks 3

2 weeks

before

despatch

with final

techn. file

13 Recommended spare parts list

(for erection and commissioning)

RSE -

3 2 weeks 3

2 weeks

before

despatch

with final

techn. file

14

Recommended spare parts list

(for 2 years operation)

( Not applicable)

RSO -

3 2 weeks 3

2 weeks

before

despatch

with final

techn. file

15 Welding procedure specification

and records WPS/PQR

WPS -

3 2 weeks 3

2 weeks

before

despatch

with final

techn. file

16 QA/QC program*

QAP -

3 2 weeks 3

2 weeks

before

despatch

with final

techn. file

17 Inspection and test procedures

ITP -

3 2 weeks 3

2 weeks

before

despatch

with final

techn. file

18 List of fabrication and control

operations (LOFC)

LOF -

3 2 weeks 3

2 weeks

before

despatch

with final

techn. file

Page 10 of 78

MATERIAL REQUISITION FOR PIG

LAUNCHER

P.013313

M 11050

104

Rev. 0 Supply of Pig Launcher / Receiver

Page 6 of 7

Item Documents and Data

Document

Index No.

A B C

Number

of copies

Number

of copies Required

date

Number

of copies Required date

19 Test reports TRS - 3 1 week

after test 3

2 weeks

before

despatch

with final

techn. file

20 NDE reports NDR - 3 1 week

after test 3

2 weeks

before

despatch

with final

techn. file

21 Heat treatment reports HTT - 3 1 week

after test 3

2 weeks

before

despatch

with final

techn. file

22 Hydro test and air test report HTR - 3 1 week

after test 3

2 weeks

before

despatch

with final

techn. file

23 Maintenance and operating

manuals MOM - 3

2 weeks

before

shipping

3

2 weeks

before

despatch

with final

techn. file

24 Installation instructions

Site inspection procedure ITS - 3

2 weeks

before

shipping

3

2 weeks

before

despatch

with final

techn. file

25 Material certificate MCT - 3 1 week

after test 3

2 weeks

before

despatch

with final

techn. file

26 Painting system description PSD - 3 2 weeks 3

2 weeks

before

despatch

with final

techn. file

27 List of subcontractors with their

scope LSS - 3 2 weeks 3

2 weeks

before

despatch

with final

techn. file

Page 11 of 78

MATERIAL REQUISITION FOR PIG

LAUNCHER

P.013313

M 11050

104

Rev. 0 Supply of Pig Launcher / Receiver

Page 7 of 7

Item Documents and Data

Document

Index No.

A B C

Number

of copies

Number

of copies Required

date

Number

of copies Required date

28 Instrument data sheets IDS - 3 2 weeks 3

2 weeks

before

despatch

with final

techn. file

29 Wiring diagrams WDG - 3 2 weeks 3

2 weeks

before

despatch

with final

techn. file

30

CENELEC certificates for

electrical instruments in hazardous

locations

CCE - 3 2 weeks 3

2 weeks

before

despatch

with final

techn. file

31

Final technical file, preliminary

copy for approval (In Soft & Hard

copy)

FTP - 3 2 weeks

before

shipping

3 -

32 Final technical file (In Soft & Hard

copy) FTF - - - 3

Before

shipping

* QA/QC Program shall comprise of In-House testing facilities, Resources and Quality Procedure being followed by

the vendor to ensure Quality of Product in line with tender requirement.

Page 12 of 78

DATA SHEET NO.

P.013313 D 11088 105

Page 1 of 2

1 FOR : UNIT :

2 PROJECT SITE : SIZE :

3 TYPE : NO. REQUIRED :

4 APPLICABLE SPECIFICATION : MANUFACTURER :

5 TAG NOS.

OPERATING DESIGN CONDITIONS WEIGHTS

6 CODE : ASME B 31.8 / ASME SEC. VIII Div 1 DESIGN FACTOR : 0.4 EMPTY (SHIPPING - ERECTION) : *

7 WIND VELOCITY : - 50 m/s (To be finalized during detail engineering) TOTAL OPERATING : *

8 EARTHQUAKE ZONE - Zone III (To be finalized during detail engineering) FULL OF WATER (SITE TEST) : *

INTERNALS : *

INSULATION/ FIRE PROOFING : NA

ACCESSORIES : * (SEE SR. NO.: 50)

CAPACITIES

NOMINAL : * m3

9 MATERIAL CERTIFICATE : EFFECTIVE : * m3

10 INSPECTION BY : FULL : * m3

DESIGN DATA SHELL JACKET

16 OPER. TEMP. : Min.- Max. °C

17 DESIGN TEMP. : Min.- Max. °C

18 OPER. PRESSURE : Min.- Max. barg

19 DESIGN PRESSURE : Min.- Max. barg -

20 HYDROSTATIC TEST PRESSURE : barg

21 PNEUMATIC TEST PRESSURE : barg NA

22 CORROSION ALLOWANCE=CA : mm

23 MIN. THK (CA INCLUDED) OF CONNECTING PIPE mm

25 LINING : mm

26 FLUID NATURE/ PHASE

27 FILLING : %

28 SPECIFIC GRAVITY : kg/m3

29

FABRICATION - TESTING DATA

30 SHELL / HEAD JOINT EFFICIENCY

31 SHELL / HEAD ALLOWABLE STRESS EFFICIENCY

32 SHELL / HEAD X-RAY

SHELL / HEAD ADDITIONAL TESTS (Impact Test)

34 HEAT TREATMENT : PWHT/ SPECIAL

35 HEAD SHAPE

36

SPECIFIED PROPOSED SPECIFIED PROPOSED

37

38

39

40 HEADS

41 VESSEL FLANGE (FORGED )

42 NOZZLE NECK (PIPE )

43 NOZZLE FLANGE (FORGED)

44 EXT. GASKET

45 EXT. BOLTS

46 EXT. NUTS

47 EXT. ATTACHMENT LUGS

48 SUPPORT :

49 SHOP PAINTING - COATING

50

DATE REV PREPARED CHECKED APPROVED

33

E

X

T

E

R

N

A

L

DESCRIPTION

EN 10204 3.2

SPIRAL WOUND AISI 304, Filling Pure

Graphite, Centering Ring CS

Issued for Procurement0

As per PMS

NATURAL GAS

*

For LTCS : at -20 0C Energy Absorbed Min. 28J & Avg. 35J

and at temperature specified in Material Spec. or -45 0C, whichever is

lower. Energy Absorbed as per Material Spec.

-20

3.0

2 Nos PIG Launcher/Receiver

65

AR

98

AS PER ASME SECTION VIII DIV. I

ASTM A320 GR. L7

SADDLES / SKIRT/RING / LEG / BRACKET

AS PER QOEC

IS 2062 GR.A OR EQ.

ASTM A333 GR.6 or equv. With Charpy

Impact Test

ASTM A194 GR. 4 / 7

QUICK OPENING CLOSURE

23.04.2019

MATERIAL CS (PIPING CLASS 6 C1)

100 %

BAND LOCK TYPE 'O' ring with ASME U stamp (NOTE 8)

ASTM A 516 Gr. 70 or equv. With Charpy

Impact Test

CONCENTRIC REDUCER

NCVNG

ASTM A350 LF2

For CS : at -20 0C Energy Absorbed Min. 28J & Avg. 35J

ASTM A 516 Gr. 70 or equv. With Charpy

Impact Test

AUTHORISED INSPECTION AGENCY

AS PER ASME SECTION VIII DIV. I

ASTM A 516 Gr. 70 or equv. With Charpy

Impact Test

LARGER BARREL

ASTM A 350 LF2 CL1 or equv. With

Charpy Impact Test

SMALLER BARREL

N.A.

1

Pig launcher shall be provided with suitable handling system for retraction, insertion & launching of pigs including

instrumented pigs (such as basket / tray; retracting rod/ mechanism etc.) from it.

The Pig launcher shall be equipped with a half internal removable filtering basket consisting of a punched plate with at least

five rows of drain holes. The filtering basket shall slide on guides/rails or wheels and in all cases the material of the parts being

in contact with each other shall be of anti-spark type. The filtering basket shall be provided with suitable stops. Lock bracket

shall be provided to such that the basket does not slide within the trap. Rear end of the basket shall be provided with suitable

lug to enable retrieval of the basket by hooks. The handling system (for inserting and retracting the pigs from the Pig launcher

) shall be complete with handling devices. In case any rails are required for sliding of the handling system, the same shall be

provided by the Pig launcher manufacturer.

ACCESSORIES

SANDBLASTING + PRIMER + FINISH COAT , TOTAL DRY FILM THICKNESS 320 µ MINIMUM as per Painting spec.

P.013313 M 11097 111

DATA SHEET FOR PIG LAUNCHER/RECEIVER

8"x 14"

GAIL (INDIA) LIMITED

HARIDWAR RISHIKESH DEHRADUN PIPELINE PROJECT

HORIZONTAL

PIG LAUNCHER - Y -0201, PIG RECEIVER - Y-1001

Rev.0 Supply of Pig Launcher / Receiver Page 1 of 2

Page 13 of 78

DATA SHEET No

P.013313 D 11088 105

Page 2 of 2

NOZZLE SCHEDULE

1 ITEM Nos NOZZLE NECK FLANGE SERVICE REMARKS

2 DIA SCH RATING FACING TYPE

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

38

39

40

41

42

43

44

45

46

47 NOTES :

48 1. All nozzles reinforcements & clips to be same material quality as shell plate.

49 2. Nozzles necks 6" & larger may be fabricated from rolled plate.

50 3. Nozzles standouts are from T.L. or C.L. of vessels to flange gasket seating face.

51 4. Nozzle positions are from reference lines unless otherwise stated.

52 5. Nozzle orientation will be Finalised during detail engineering.

53 6. Bolt holes to straddle centre lines except as noted.

54 7. Thicknesses must be checked by Vendor at bidding time.

55

56

57 10. If the minor barrel is fabricated from plates, dimensional tolerance of the barrel shall be same as pipes manufactured as per API 5L, Latest Edition.

58 11. This data sheet shall be read in conjunction with Specification for Pig Launcher and PMS.

59 12. * Vendor to indicate

60 13. All the permissible forces on nozzles to be furnished by vendor.

61 14. Foundation details of Pig launcher / Receiver to be furnished by vendor.

DATE REV PREPARED CHECKED APPROVED

8. ASME U Stamp applicable only for Quick opening closure only. Quick-opening closure shall include a safety device to prevent opening before depressurizing in compliance with ASME section VIII, Div, UG. 35 (b).

WN * Utility Connection B16.5N11 1 2" 160 RF

600 # RF WN *

600 #

STANDOUT

N10 1 B16.5Secondary Connection (Kicker

connection)

*

*

*

1 2" 160 600 # RF

8"

*

1

To match I.D. of

major barrelNote 8

4"

1 2" 160

*N5

By Vendor RF

N2 & N6 2 2"

600 #N1

600 #

RF

Note 814"

160 600 #

N8

N4

2"

DESCRIPTION

9. ID of minor barrel should match with Connecting pipe ID and bore of Flange .

N7 1

23.04.2019

4"

AR Issued for Procurement

Secondary Connection (Kicker

connection)

Quick-opening closure

NC

600 #

Note - All Dimensions are tentative and in mm only. Vendor to indicate final dimensions in drawings submitted for approval.

FIELD INSTALLATION LAYOUT

B16.5

Drain Connection

B16.5WN

WN

WN

B16.5

600 # RF

Vent Connection

PSV Connection

Pressure Indicator

WN B16.5

B16.5

RF

WN *N9

80 WN

1

0

160

600 #

1 RF

*

B16.5

VNG

Connection to 8" main pipeline

80

DATA SHEET FOR PIG LAUNCHER

N11

Rev.0 Supply of Pig Launcher / Receiver Page 2 of 2

Page 14 of 78

QUICK OPENING END

CLOSURE

P.013313

D 11088

106

HARIDWAR RISHIKESH DEHRADUN PIPELINE

PROJECT

TRACTEBEL ENGINEERING PVT. LTD.

DATA SHEET

QUICK OPENING END CLOSURE (QOEC)

0 23.04.2019 Issued for Procurement VNG MS AR

Rev. Date Description Prepared By Checked By Approved By

Page 15 of 78

QUICK OPENING END

CLOSURE

P.013313

D 11088

106

Rev. 0 Supply of Pig Launcher / Receiver

Page 1 of 2

GENERAL

Design Standard :

ASME BPVC SEC VIII Div 1 (Latest edition), ASME B31.8

(Latest edition)

Type of QOEC : Band lock type having 'O' ring with ASME U stamp.

Size

:

::

:

As per P&ID

Orientation :

::

:

Horizontal

End Connection : Butt Joint, ASME B 31.8, Appendix I, Fig. I-4.

Design Standard :

ASME SEC VIII Div 1 (Latest edition), ASME B31.8 (Latest

edition)

ANSI Rating : 600#

DESIGN CONDITION :

Corrosion Allowance, mm : 3.0

Service : Natural Gas – Non Sour

Pressure in Bar(g) : 98

Temperature in 0C : (-)20 to (+)65

Design Factor : 0.4

Thickness of closure hub, mm :

Installation : Above ground

Connecting Pipe : As per P&ID

MATERIAL SPECIFICATION

(Equivalent or Superior)

Description

QOEC ASTM A 350 LF2 CL1

Seal Viton

Name Plate AISI 304, min 2mm

TESTING REQUIREMENTS

Charpy Impact Test Required (Note 4)

Hydrostatic test pressure (with vessel) ASME SEC VIII Div 1

Pneumatic Test (with vessel) To be same as mentioned in Pig Launcher /Receiver

Cyclic test Atleast 10 closing and opening cycles

Radiography 100% (Full)

PAINTING :

Surface Preparation SA 2 1/2

External Surface *

Internal Surface *

Legend: * to be filled by Vendor

Page 16 of 78

QUICK OPENING END

CLOSURE

P.013313

D 11088

106

Rev. 0 Supply of Pig Launcher / Receiver

Page 2 of 2

Notes:

1. This data sheet shall be read in conjunction with Specification for Pig Launcher and PMS.

2. Quick opening closures shall be equipped with safety locking devices in compliance with Section VIII,

Division I, UG-35.2 of the BPV Code.

3. For the welding end, the out of roundness (i.e. difference between maximum and minimum ID at pipe end)

tolerance shall be OD > 6” - 3 mm (max.)

4. The Charpy V-notch test shall be conducted at -20°C. Test procedure shall conform to ASTM A 370. The

average absorbed energy value of three full sized specimens shall be 35 J. The minimum impact energy

value of any of the specimen analyzed as above shall not be less than 28 J. If LTCS material used for

construction, Impact test shall be carried out as per material Standard impact test requirements temperature

or (-) 450C whichever is lower.

5. Lifting Eye shall be provided for hinged closure.

6. Correct operation of QOEC & system shall be established and furnished to purchaser for as built condition

of piping system.

7. All Inspection and tests shall be carried out as per approved QAP. Unless otherwise specified, all tests shall

be witnessed by the purchase / control authority.

8. Material compliance as per EN 10204 3.2 certification.

9. The painting shall be carried out as per Pipeline Design basis (P.013313 D 11062 001 latest revision) and

Painting specification no. P.013313 D 11077 111

10. Minimum Marking: Manufacturer Name, Nominal Diameter, Heat number, Tag number, Material, Design

Pressure, and Hydro test Pressure, Year of Manufacturing.

11. Quick Opening Closure shall be ASME "U" stamped.

Σ Σ Σ

Page 17 of 78

1 Manufacturer Name *

2 Qty 6 Nos.

3 Design Standard ASME BPVC SEC VIII Div 1 (Latest edition), ASME B31.8 (Latest edition)

4 Electrical Area Classification IEC zone-1 / zone-2, Gas Group IIA/IIB, Temp. Class T3

5 Pig Detection At passage

6 Service Natural Gas – Non Sour

7 Pressure in Bar(g) 98

8 Temperature in 0C (-)20 to (+)60

9 Density, (Kg/m3) As per Gas composition of Process design basis

10 Installation Above ground

11 Multiphase Product (Yes / No) No

12 Type Non-Intrusive (Bi-directional)

13 Sensing Element Piezo Electrical crystal

14 Sensor Repeatability 1% Minimum

15 Detection Passive acoustic based (Ultrasonic type)

16 Signal Output

17 Particle & Pig Detection Required (Note-4)

18 Spectrum analysis using associated software Required

19 Body Material AISI SS316L

20

21 Degree of Protection EEx ‘d’, IP- 65

22 Power Supply 24V,DC + 10%

23 Signal Interface Local Control Panel / RTU

24 Electrical Entry ½”NPTF (Note - 3)

25 Pipeline Outside Diameter & Wall thickness 219.1 ODmm, thickness 7.1mm

26 Pipeline Material API 5L Gr. X 70

27 Pipeline Coating (Internal) Epoxy Paint (DFT 110 + 10 microns)

28 as per P&ID / Horizontal

29 Pipeline Coating (External) 3 Layer Polyethylene (3.1 mm Min)

30 Pig Material Carbon Steel/ Poly urethane

31 Pig Length 600mm ~ 3000mm (indicative refer Note-13)

32 Pig Diameter 95% ~ 100% of Pipeline ID

33 Pig Velocity (Max. / Normal) 5 m/s (indicative refer Note -14)

34 Local Indicator Red LED based, EExe, IIB, T5, IP65 (visible from min. 5 meters)

35 Local Reset Button Black colour, Eexd, IP65 (visible from min. 5 meters)

36 Inbuilt Battery Required (Note-2)

37 Termination Junction Box Required (Note-6)

38 Bolting & Nut Material ASTM A 320 L7 & ASTM A194 Gr.4/ Gr.7

39 Data Storage Capacity Up to 60 days of measurement data

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

DEVIATION NO DEVIATION CONTRACTOR'S SIGNATURE WITH SEAL

AR

REV. DATE PREP CHKD APPD

CONTRACTOR: 0 23.04.2019 MA SHD

PROJECT: HRDPL

CLIENT: GAIL (I) Limited

The painting shall be carried out as per Specification

Minimum Marking: Manufacturer Name, Nominal Diameter, Heat number, Tag number, Material, Design Pressure, and Hydro test Pressure,

Year of Manufacturing.

Sheet No. 1 of 1 Document No. P.013313 D 11090 107

Pig Velocity shall be as per prevalent industrial practices for Oil & Gas pipelines.

Terminal junction box shall be provided. JB shall be AISI SS316L material. Termination box of EExe / EEx’d’ type shall be suitable for

hazardous area classification for connecting the sensor cables , power and signal cables, the light indication and reset switch as applicable.

Junction box shall be Weather proof to IP 65.

Area Classification: IEC Zone-1/Zone-2, IIA/IIB, T3 or Better.

Local indicator shall be Eexd type. 

Material compliance as per EN 10204 3.2 certification.

Minimum Dry film thickness of painting shall be 400 microns.

Location / Orientation (Horizontal/ Vertical)

PIG

DETAILS

OTHERS

NOTES: All fields electronic shall be sealed in an epoxy resin for Protection.

Max length shall be considered as per the max. length of intelligent pig for respective pipe dia.

All Pig Signaller shall have two (2) nos. of inbuilt batteries (1 working + 1 spare), with a minimum lifespan of 1 year.

All cable glands supplied by the Vendor shall be EExe/ EExd certified double compression type with PVC shrouds.

Pig Signaller shall be capable of detecting all type of pigging devices (permanent magnet type and transmitter equipped intelligent pigs).

The Pig Signaller / detectors sensor is mounted in hermetically sealed AISI SS316L housing and to be clamped to the external surface of the

pipe through which the pig is passing.

Quantity distribution is : 1 no. at Major barrel, 1 no. at Minor barrel & 1 no. at 8"mainline, for each Pig launcher & Receiver.

SCRAPER

TRAP

/PIPEPING

SPECIFICA

TION

TECHNICAL DATASHEET FOR NON INTRUSIVE PIG SIGNALLAR

GENERAL

DESIGN

CONDITIO

N

SENSING

ELEMENT1 no. potential free contact (DPDT), 1 no serial communication interface (Modbus over RS-

485 / Ethernet)

ENCLOSU

RE

Rev.0 Supply of Pig Launcher / Receiver Page 1 of 1Page 18 of 78

1 Tag No. PSV-1001, PSV-0201 Quantity 2 * *

2 Line No. Schedule * *

3 Vessel No. *

4 Safety / Relief Safety relief

5 Full Nozzle Full Lift/Mod. Nozzle Full nozzle full lift

6 Bonnet type Closed

7 Conv./Bellows/Pilot Operated Conventional

8 Inlet Conn. Size & Rating *

9 Facing & Finish *

10 Outlet Conn. Size & Rating *

11 Facing & Finish *

12 Cap Over Adj. Bolt Yes

13 Screwed / Bolted Bolted

14 Lifting Gear - Type

15 Test Gag Yes

16

17

18 Body and Bonnet A351 CF8M

19 Nozzle and Disc SS316

20 Spring SS304

21 Bellows --

22

23

24 Resilient Seat Seal --

25

26

27 Code API

28

29

30 Fluid State Natural Gas Gas

31 Corrosive Constituent

32 Required Flow Capacity

33 Mol.Wt. S.G. at Rel. Temp

34 Oper. Pressure Normal

35 Oper. Temp. Rel. Temp.

36 Valve Discharges to Atmosphere

37 Back Press. Const. Or Variable Variable

38 Set Pressure

39 Cold Bend Test Pressure

40 % Over Pressure % Blow Down 21%

41 Cp/Cv Compressibility Factor

42 Viscosity @ Rel. Temp. mPas(cP)

43 Vess. Wall Temp. Surf.Area-m2

44

45 Calculated Area cm2 *

46 Sel. Area cm2 Orifice Design * *

47 No. of Valves Reqd. for capacity *

48 Tota Area - cm2 *

49 Actual Flow Capacity *

50

51 Model No. *

52 IBR Certification No

53

54

NOTES:

'*' : Vendor to furnish

Note 1 Please refer Pig launcher PTS (P.013313 D 11077 109) also for more details.

DEVIATION NO DEVIATION VENDOR'S SIGNATURE WITH SEAL

AR

VENDOR: REV. DATE PREP CHKD APPD

0 23.04.2019 VNG NC

PROJECT: HRDPL

P.013313 D 11090 108

CLIENT: GAIL (I) Limited

PRESSURE RELIEF VALVE

UNITS: Flow<-> Liquid- m*3/hr Gas- Sm*3/hr Steam- kg/hr Pressure-> kg/cm*2 G Temperature<-> oC Level/Length<-> mm

General

Valve

Material

Options

Basis

Service

conditions

Orifice

APPENDIX 3

Rev.0 Supply of Pig Launcher / Receiver Page 1 of 1Page 19 of 78

PTS- SCRAPER BARRELS

(PIG LAUNCHER )

P.013313

D 11077

109

HARIDWAR RISHIKESH DEHRADUN PIPELINE

PROJECT

TRACTEBEL ENGINEERING PVT. LTD.

PTS – SCRAPPER BARREL

(PIG LAUNCHER)

RERT

0 23.04.2019 Issued for Procurement VNG MS AR

Rev. Date Description Prepared by Checked by Approved by

Page 20 of 78

PTS- SCRAPER BARRELS

(PIG LAUNCHER )

P.013313

D 11077

109

Rev. 0 Supply of Pig Launcher / Receiver

Page 1 of 1

TABLE OF CONTENTS

1.0 SCOPE ...................................................................................................................................... 1

2.0 GENERAL REQUIREMENTS ...................................................................................................... 1

3.0 DESIGN DATA .......................................................................................................................... 1

4.0 MATERIALS .............................................................................................................................. 1

5.0 REFERENCE DOCUMENTS ........................................................................................................ 1

6.0 TECHNICAL REQUIREMENT ..................................................................................................... 2

7.0 WELDING ................................................................................................................................. 3

8.0 INSPECTION AND TESTING ..................................................................................................... 4

9.0 STANDARD OF ACCEPTABILITY ............................................................................................... 5

10.0 CLEANING, PAINTING & PROTECTIVE COATING .................................................................... 5

11.0 TRANSPORTATION .................................................................................................................. 6

12.0 MARKING ................................................................................................................................. 6

13.0 DOCUMENTATION .................................................................................................................... 7

14.0 CERTIFIED DRAWINGS ........................................................................................................... 7

15.0 VENDOR’s OBLIGATIONS ........................................................................................................ 8

16.0 BID CONDITIONS .................................................................................................................... 8

17.0 DELIVERY ................................................................................................................................ 8

18.0 WORKING SCHEDULE .............................................................................................................. 8

Page 21 of 78

PTS- SCRAPER BARRELS

(PIG LAUNCHER )

P.013313

D 11077

109

Rev.0 Supply of Pig Launcher / Receiver

Page 1 of 8

1.0 SCOPE

This specification covers the requirements for design, material procurement fabrication, inspection testing

and supply of launchers/ receivers installed at various stations in the pipe line Project.

Scope of supply include Pig Launcher/Receiver along with internal tray, pig handling device -

Removable type, Quick Opening End Closure (QOEC).

2.0 GENERAL REQUIREMENTS

All the equipment to be supplied must comply with the requirements of the latest edition of ASME B

31.8/ ASME Sec VIII Div.1 for the gas pig launcher and pig receiver.

The Launcher and Receiver shall be provided with pig tray, lifting devices and handling trolleys for pigs.

Following order of procedure shall be followed for any conflict in technical requirement.

1. Data sheet

2. This specification

3. Codes and standards

3.0 DESIGN DATA

As per pipeline pig launcher and pig receiver data sheets. Document no. P.013313 D 11088 105

4.0 MATERIALS

Material of Pig Launcher & Receiver shall be as per Data sheet document no. P.013313 D 11088 105

The Pig Launcher and Pig Receiver will be installed on saddle support only.

Notes:

1. Alternative equivalent materials may be used when approved by the OWNER OR OWNER’S

REPRESENTATIVE / Consultant.

2. The steel plates used in the construction of the Pig Launcher and Pig Receiver must be certified

materials as per specification.

3. All materials used in the manufacturing of Pig Launcher and Receiver assemblies shall be subject

to approval by the OWNER OR OWNER’S REPRESENTATIVE / Consultant. All pressure

containing components NPS 2 and larger shall have proven notch toughness meeting the

requirements of ASME Section VIII, paragraph UG-84, in the final heat treated condition Charpy

V- notch impact tests shall be performed as per the requirement of the Oil and line pipe data

sheets.

4. All branch outlets larger than NPDS 3 shall be extruded or reinforced saddle as per ASME B 31.8

Code.

5. The OWNER OR OWNER’S REPRESENTATIVE / Consultant has the right to request all the

necessary destructive and non – destructive material tests in order to verify that all the components

comply with the required specifications.

6. The costs of the above mentioned tests, materials, equipment, and personnel to be borne by the

SUPPLIER.

5.0 REFERENCE DOCUMENTS

5.1 Project Specifications and Data Sheets

1 P&ID

2 Pig Traps Data Sheets, Codes and Standards

Page 22 of 78

PTS- SCRAPER BARRELS

(PIG LAUNCHER )

P.013313

D 11077

109

Rev.0 Supply of Pig Launcher / Receiver

Page 2 of 8

Pig launchers and receivers specified herein shall be designed, manufactured and tested in accordance

with the latest edition of the following codes and standards and / or others as applicable. These Codes and

Standards are the minimum requirements, and manufactured design shall meet or exceed them.

API5L API Specification for Line pipe

ASTM A350 LF2 Carbon and Low-Alloy Steel Forgings, Requiring Notch Toughness

Testing for Piping Components

ASTM A694F65/F56 Forging, High Strength Carbon Steel for Piping Components

ASTM A 105 Forging Carbon Steel for Piping Components

ASTM A 234 Piping Fitting of Wrought Carbon Steel and Alloy Steel for Moderated

and Elevated Temperatures

ASTM A516 GR 70 Pressure Vessel Plates, Carbon Steel, for Moderate and Lower-

Temperature Service

ASME Sec II Boiler and Pressure Vessel Code- Materials

ASME Sec V Boiler and Pressure Vessel Code- Non Destructive Testing

ASME Sec VIII Boiler and Pressure Vessel Code Div I- Pressure Vessels

ASME Sec IX Boiler and Pressure Vessel Code- Code Welding and Brazing

Qualifications

ASME B1.1 Unified Screw Threads

ASME B 16.5 Steel Pipe Flanges and Flanged Fittings

SME B16.9 Factory made Wrought Steel Butt Welding Fittings.

ASME B.16.11 Forges Steel Fittings, Socket Welding and Threaded

ASME B 31.4 Pipeline Transportation System for liquid and Hydrocarbons and other

Liquids

ASME B 31.8 Gas Transmission and Distribution Pipeline System

ASTM A20 General Requirements for steel plate for pressure vessels

ASTM A516 Carbon steel pressure vessel plates for moderate and low Temperature

service.

ASTM A106 Carbon steel seamless pipe for high temperature service

ASTM A193 Alloy steel and stainless steel bolting materials for high temperatures

ASTM A194 Carbon and alloy steel nuts for bolts for high pressure or temperature

services or both.

MSS-SP-75 High test wrought butt welding fittings

MSS-SP-44 Steel pipeline flanges

MSS-SP-97 Integrally Reinforced forged branch outlet fittings

IS 875 Part 3 Codes of practice for design loads ( other than earthquake ) for buildings

and structures

IS 1892 Codes for earth quake resistance design of structures

6.0 TECHNICAL REQUIREMENT

• The pig launcher and pig receiver shall be suitable for launching and receiving pigs /

intelligent pigs.

• Mechanical design of each pig launcher and pig receiver for shall be as per ASME B31.8. All

the launcher/ receiver shall be horizontal type and shall be supported on 2 no. saddles suitably

spaced and designed to withstand the maximum dead load including pipeline reaction on

barrel flange.

• The launching and receiving barrels shall be bidirectional. Bidirectional Scraper

Launcher/Receiver shall be suitable for intelligent pigging.

• Orientation of all the nozzles is indicative only and same shall be confirmed during Detailed

Engineering.

• Each pig launcher and pig receiver assembly shall be equipped with a quick opening closure

with a davit so designed as to permit one man to load or remove pig from the assembly. The

closure hinge pin shall be vertical with the closure opening in a horizontal plane.

Page 23 of 78

PTS- SCRAPER BARRELS

(PIG LAUNCHER )

P.013313

D 11077

109

Rev.0 Supply of Pig Launcher / Receiver

Page 3 of 8

• The quick closure shall be manufactured with a safety system as per ASME Sec VII Div.1,

UG35 (b) which grants the opening only when the pig launcher and pig receiver is not under

pressure. It shall be manually operated. The design shall allow opening or closing by one man

in a period of one (1) minute or less without the use of additional equipment.

• Quick opening closure shall be Bank lock / Clamp ring type. Pig traps shall be designed in

accordance ASME Section VIII Div.1 with corrosion allowance of 3mm. Material of QOEC

shall be similar to that of major barrel. QOEC shall be band lock type having 'O' ring with

ASME U stamp. The Scrapper Trap manufacturer shall have “U” stamping of fabrication yard.

• Quick Opening Closure shall be ASME "U" stamped.

• Scraper trap shall be provided with suitable handling system for retraction, insertion &

launching of pigs including instrumented pigs (such as basket / tray; retracting rod/ mechanism

etc.) from the trap. Price of scraper trap shall be inclusive of pig handling system.

• The pig receiving traps shall be equipped with a half internal removable filtering basket

consisting of a punched plate with at least five rows of drain holes. The filtering basket shall

slide on guides/rails or wheels and in all cases the material of the parts being in contact with

each other shall be of anti-spark type. The filtering basket shall be provided with suitable

stops. Lock bracket shall be provided to such that the basket does not slide within the trap.

Rear end of the basket shall be provided with suitable lug to enable retrieval of the basket by

hooks. The handling system (for inserting and retracting the scraper and instrumented pigs

from the trap) shall be complete with handling devices. In case any rails are required for

sliding of the handling system, the same shall be provided by the scraper trap manufacturer

• The internal diameter of the pig launcher and pig receiver assembly shall have a smooth

continuous level surface and shall have the same diameter as the export pipeline.

• The pig launcher and pig receiver shall have saddle mounting to create a fall towards the trap

door to a minimum 1:100. Vendor to provide suitable cleats for installation

7.0 WELDING

• All nozzle attachment welds including added reinforcement shall be full penetration nozzle

less than or equal to 2” shall be attached with the barrel using weldolet.

• All fillet welds shall be continuous.

• The welders and the welding procedures shall be qualified and performed according to the

requirements of the ASME code, section IX. This shall be verified by the authorized Inspector.

• Welding procedure specifications (WPS’s) together with the supporting procedure

qualifications records (PQR’s) shall be submitted INSPECTOR for review and acceptability

before commencement of fabrication.

• Each WPS submitted should closely relate to the production weld it represents. The actual

joint preparation, fit up and weld consumables to be used shall be described.

• When the ambient temperature is 00C and below, the base metal shall be preheated to 150C

minimum before welding unless a higher preheat temperature is dictated by the code.

• All butt weld joints shall be welded with full penetration full fusion and double sides. All

nozzles to shell / head welds shall also be full penetration.

• There is no opening to permit access for internal welding of the final closure scam, Gas

Tungsten Are Welding or other techniques, shall be used that will assure a quality root pass as

specified in code.

• Electro slag or single pass Electro-gas process shall not be used to weld any components of

vessels.

• All internal and external attachments shall be continuously welded, unless specified otherwise.

Page 24 of 78

PTS- SCRAPER BARRELS

(PIG LAUNCHER )

P.013313

D 11077

109

Rev.0 Supply of Pig Launcher / Receiver

Page 4 of 8

• The maximum weld deposit per pass shall not exceed 6.5mm except root run.

• All welding including tack welding and non-pressure parts welding shall be performed by a

welder qualified as per code.

• No welding or weld repair is permitted on pressure parts after Post Weld Heat Treatment

(PWHT), unless specifically approved.

8.0 INSPECTION AND TESTING

• All inspections shall be carried out by OWNER OR OWNER’S REPRESENTATIVE /

Consultant or approved third party inspection agency.

• SUPPLIER shall advise the OWNER OR OWNER’S REPRESENTATIVE / Consultant with

two weeks advance notice, from the date of the test required on the traps in order to allow one

of the OWNER OR OWNER’S REPRESENTATIVE, representatives to witness the test.

• SUPPLIER shall submit Inspection and Test Plant for OWNER OR OWNER’S

REPRESENTATIVE / Consultant, approval.

• The following minimum inspections are required and shall be performed at the SUPPLIER’S

shop.

• Visual inspection.

• Dimensional check

• Air testing of reinforcement pads prior to hydro testing.

• Hydrostatic test at a pressure 1.5 times the design pressure for a period of at 4 (four) hours.

• 100% inspection of all longitudinal and circumferential weld scams for their entire length by

radiography.

• 100% UT of all main weld (longitudinal and circumferential) of the vessel body.

• 100% UT for vessel plate for lamination.

• Magnetic Particle Inspection of all other welds.

• All forgings shall be Wet Magnetic Particle Examined on 100% of the forged surfaces.

Method and acceptance shall comply with MSS-SP-53.

• Inspection of weld ends intended for field welding over their entire length with Ultrasonic

testing.

• Review of the material test certificates.

• Operation of the quick release closure.

The Inspectors must witness all tests to certify the validity of the procedures.

The designated Inspectors have the authority to reject or make objections to any procedure, material,

or equipment that is not complying with the specified codes and practices.

8.1 Non destructive Examination

• All non-destructive examination shall be performed by personnel qualified in accordance with

ASNT Recommended Practice SNT-TC-1A or equivalent. Personnel interpreting results of any non-

destructive testing method shall be qualified in accordance with Level II requirements of SNT-TC-

IA or equivalent.

• The longitudinal scam will be nondestructively tested for final acceptance only after hydrostatic

testing except for weld repairs.

• One (1) inch of each pipe end shall be examined around the periphery by an approved ultrasonic

method to check for lamination, pipe containing laminations greater then ¼ inch circumferentially

Page 25 of 78

PTS- SCRAPER BARRELS

(PIG LAUNCHER )

P.013313

D 11077

109

Rev.0 Supply of Pig Launcher / Receiver

Page 5 of 8

shall be rejected. All non-destructive examination shall be carried out in accordance with ASME

Section V and ASME Section VIII. All acceptance criteria shall be based on ASME Section VIII.

9.0 STANDARD OF ACCEPTABILITY

9.1 Dimensions

Internal Diameter and Out of Roundness.

9.2 Visual Inspection

All surfaces shall be free of nicks, dents, gauges, taps, are burns and other defects.

9.3 Non Destructive Inspections

Pig Launcher and pig receiver traps will not be accepted if any of the following defects are detected by

the ultrasonic or radiographic methods.

• Cracks

• Insufficient penetration or fusion

• Laminations

• Continuous occurrence, regardless of dimensions of undercuts, porosity gas pockets or slag

inclusions.

• Undercuts exceeding 0.35 mm in depth and 25 mm in length.

• Individual gas pockets exceeding 1.6 mm in diameter and/or concentrations of gas pockets with a

maximum diameter of 1 mm exceeding 6 per 4 cm2. Adjacent groups of two or more gas pockets,

which exceed 1 mm in diameter, shall be separated by at least 100 of sound material.

• Slag inclusions that exceed 3 mm in width or 1.6 mm in depth and length.

• VENDOR shall employ Non-destructive Test operators, qualified as required by code. VENDOR

shall also certify that each operator, engaged in NDT, is qualified to meet the code requirement.

• The extent of radiography shall be in accordance with the most stringent requirements of relevant

code or vessel data sheet and this specification.

• For vessels where butt weld seams are 100% radiographed, all other pressure containing welds and

all attachment welds to pressure containing parts shall be examined as follows (a) All

circumferential and longitudinal butt welds and butt welds joining heads, shells and nozzles shall

be fully radiographed (b) Nozzle to shell welds and pressure containing welds other than butt

welds shall be examined by the ultrasonic method, after PHWT (c) All root runs of longitudinal

and circumferential seams shall be examined by magnetic particle method or liquid penetrant

inspection method (d) All nozzle-to-shell welds, hold root runs and final nuts shall be examined

by magnetic particle method or liquid penetrant inspection method in addition to ultrasonic

method.

• Are strikes on the pressure parts shall be avoided. When they occur, the surfaces shall be properly

conditioned to eliminate surface stress raisers and such surfaces, shall be examined by, either

magnetic particle or liquid penetrant method of examination.

• Air and soapy water tests shall be performed on nozzle reinforcement pads by applying 1.05 kg/

cm2 (g) air for 5 minutes, subsequently reduce to 0.2 kg/cm2 g before applying soap solution.

• Irrespective of code requirements, welds shall be free from all surface breaking defects.

10.0 CLEANING, PAINTING & PROTECTIVE COATING

• All exterior surfaces in contact with the atmosphere under operating conditions must be cleaned

and painted according to the paint manufacturer’s standards suitable for the site conditions.

Page 26 of 78

PTS- SCRAPER BARRELS

(PIG LAUNCHER )

P.013313

D 11077

109

Rev.0 Supply of Pig Launcher / Receiver

Page 6 of 8

Cleaning and painting procedures is required to be approved by OWNER OR OWNER’S

REPRESENTATIVE.

• The pig launcher/receiver shall be shot blasted and primed as follows.

• Blast clean to ISO 8501-1, Grade Sa 2-1/2.

• Painting shall be as per Design Basis of Pipeline of this project. (Document no. P.013313 D 11062

001, latest revision) and PTS Painting System and Color code for final layer (Document no.

P.013313 D 11077 111, latest revision)

• The inner surfaces must be free of loose particles lamination flakes, welding splatter, etc. They

also must be free of sharp edges or any protruding element that interferes with the free circulation

of the scrapper.

• Unless otherwise specified, the VENDOR shall include the following for painting.

• All internal and external surfaces of vessel shall be thoroughly cleaned to remove all loose mill

scales, rust, grease, dirt, weld spatters etc.

• Internal coating, if specified in vessel data sheet shall be carried out as per the requirements of

internal coating material specification and the complete procedure shall be approved by OWNER

OR OWNER’S REPRESENTATIVE / Consultant before start of any work.

• All machined and bright finish surfaces shall be coated with an easily removable corrosion

preventive.

• The painting, as specified in vessel data sheets, shall be carried out as per the painting material

specification requirements and painting specification.

• No painting or internal coating shall be applied before weld inspection leak test or hydrostatic test.

11.0 TRANSPORTATION

• Care shall be taken to ensure that mechanical damage is not caused during handling and

transportation. Weld bevels shall be suitably protected against damage during handling and

transportation. All open ends shall be blind with wooden or plastic discs to prevent the ingress of

dirt or moisture.

• Care shall be taken to ensure that wire ropes, chains or other handling devices do not come into

metallic contact with the launcher/ receiver. It is recommended that broad band, non-metallic

slings to be used to load/ unload and support the tee when in transit.

• The protection, packing and shipping shall be subject to the approval of the OWNER OR

OWNER’S REPRESENTATIVE / Consultant.

12.0 MARKING

Each trap shall have a name plate clearly marked by the minimum following details:

• Manufacturer name

• Job number

• Specification number

• Year of production

• Nominal diameter ( at flanged or welding end)

• Maximum, design, operating and allowable pressures/ temperatures

• Test pressure

• Inspector stamp

• Project Name- HRDPL Pipeline Project

Page 27 of 78

PTS- SCRAPER BARRELS

(PIG LAUNCHER )

P.013313

D 11077

109

Rev.0 Supply of Pig Launcher / Receiver

Page 7 of 8

• CLIENT’s Name

Vendor to furnish name plate/ bracket Drawing. For OWNER OR OWNER’S REPRESENTATIVE /

Consultant approval

Transportation marking shall be painted with synthetic resin paint.

13.0 DOCUMENTATION

SUPPLIER shall provide a Manufacturer’s data report in compliance with their Supplier Document

requirement List (SDRL) for pig launchers and Receiver.

• Complete material specification, including certificates of mechanical and chemical test.

• Forming process with the indication of temperature at which the forming process has been

performed.

• Detailed description of welding process including type, size and grade of filler material and flux,

welding speed, electrical characteristics, number of weld passes, specific energy input ( in J/cm),

hardness test covering critical sections of welds.

• Heat treatment after forming and welding.

• Test reports on radiographic and ultrasonic inspections as well as on the hydrostatic test complete

with all diagrams.

• Protection coating.

• Quality control forms (Certified by SUPPLIER’s third party).

- Check of dimensions

- Verification of materials

- NDT Inspection

- Hydrostatic test

- Painting/ Coating

- Inspection Release Note (Released for Shipment) etc.

• Quality Assurance Plan and Procedures.

• Operation and maintenance instructions.

14.0 CERTIFIED DRAWINGS

SUPPLIER shall furnish drawings and /or specifications to the OWNER OR OWNER’S

REPRESENTATIVE for comments/ approval

It is understood that the suggestion, recommendations for design, variations and fabrication changes

issued by the OWNER OR OWNER’S REPRESENTATIVE / Consultant do not relieve the

CONTRACTOR from any responsibilities concerning the compliance with all requirements of this

Specification and/or from the fulfillment guaranties.

The drawings shall at least contain the following information

• Material (chemical composition, mechanical strength properties).

• Maximum, design, operating and allowable pressures/ temperatures.

• Maximum test pressure.

• Dimensions

• Welding procedure for each type of weld, including weld joint factor.

Page 28 of 78

PTS- SCRAPER BARRELS

(PIG LAUNCHER )

P.013313

D 11077

109

Rev.0 Supply of Pig Launcher / Receiver

Page 8 of 8

15.0 VENDOR’s OBLIGATIONS

Submit construction drawings to be approved by the OWNER OR OWNER’S REPRESENTATIVE /

Consultant. Perform all the tests necessary and submit the results for the OWNER OR OWNER’S

REPRESENTATIVE / Consultant’s approval to assure the quality.

Submit for the OWNER OR OWNER’S REPRESENTATIVE / Consultant approval the welding

procedures and welders qualifications. Communicate to the OWNER OR OWNER’S

REPRESENTATIVE / Consultant the performance of any test 10 days in advance to permit the

presence of the authorized OWNER OR OWNER’S REPRESENTATIVE / Consultant Inspector.

16.0 BID CONDITIONS

For the supply of each of the equipment items indicated in this specification and supporting Data sheets/

purchase requisition including supply of all materials.

17.0 DELIVERY

At the place indicated in the OWNER OR OWNER’S REPRESENTATIVE / Consultant’s Purchase

Order.

18.0 WORKING SCHEDULE

VENDOR shall submit to the OWNER OR OWNER’S REPRESENTATIVE / Consultant, a detailed

“working schedule” that will include the engineering fabrication, purchasing, testing and delivery.

Page 29 of 78

FITTINGS & FLANGES P.013313

D 11077

117

HARIDWAR-RISHIKESH-DEHRADUN PIPELINE

(HRDPL) PROJECT

TRACTEBEL ENGINEERING PVT. LTD.

PTS - FITTINGS & FLANGES

(Up to 12” Size)

0 23.04.2019 Issued for Procurement MK MS AR

Rev. Date Subject of Revision Prepared By Checked By Approved By

Page 30 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 1 of 1

TABLE OF CONTENTS

1.0 GENERAL ............................................................................................................................ 1

2.0 DESIGN AND CONSTRUCTION ........................................................................................... 3

3.0 MATERIALS ........................................................................................................................ 6

4.0 FABRICATION AND TEST ................................................................................................... 7

5.0 UPGRADING FROM 3.1 TO 3.2 CERTIFICATE .................................................................... 9

6.0 INSPECTION .................................................................................................................... 13

7.0 CORROSION PROTECTION............................................................................................... 14

Σ Σ Σ

Page 31 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 1 of 19

1.0 GENERAL

This specification describes the requirements of fittings and flanges to be installed on Barmer Pali Pipeline

and particularly in the despatch stations, intermediate pigging stations and tap off, receiving stations and

sectionalizing valve stations.

This specification also describes the examinations and upgrading tests to be performed for obtaining a 3.2

certificate on the standard new fittings and flanges or taken out of stock with a 3.1 certificate.

The fittings have to be delivered in accordance to the particular specification:

Codes, Norms and standards (latest revision); but not limited to:

ANSI B16.5 Pipe flanges and flanged fittings

ANSI B16.9 Factory - made wrought steel butt welding fittings.

ANSI B 16.11 Forged steel fittings

ANSI B16.28 Wrought steel butt welding short radius elbows and returns

ASME B31.3 ASME code for process piping.

ASME B31.4 Pipeline transportation system for Liquid hydrocarbons

ASME B31.8 Gas transmission and distribution piping systems.

ANSI B36.10 Welded and seamless wrought steel pipe

ASTM A 105/

A 105 M

Forging, carbon steel, for piping components.

ASTM A 203 Pressure vessel plates, alloy steel, nickels

ASTM A 234/

A 234 M

Piping, fittings of wrought carbon steel and alloy steel for moderate and elevated

temperatures

ASTM A 333 Seamless and welded steel pipe for low temperature

ASTM A 350/

A 350 M

Forging, carbon and low alloy steel, requiring notch toughness testing for piping

components.

ASTM A 370 Mechanical testing of steel products.

ASTM A 420/

A 420 M

Piping fittings of wrought carbon steel and alloy steel for low temperature service.

ASTM E 112 Standard methods for determining the average grain size.

MSS SP 25 Standard marking system for valves, fittings, flanges and unions.

MSS SP 55 Quality standard for steel castings for valves, flanges and fittings and other piping

components (visual method).

MSS SP 75 Specification for high test wrought butt welding fittings.

ASME Boiler and Pressure Vessel code.

DIN 2413 Design of Steel Pressure Pipes

EN 10204 Type of Inspection documents

ISO 148 Metallic Material - Charpy Pendulum impact test

ISO 9001 Quality management standard

Page 32 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 2 of 19

The present specification can confirm, complete or alter certain characteristics or tolerances of existing

laws or specifications.

In his offer, the manufacturer or vendor shall specify all proposed modifications or alternatives to the

present specification. In all cases, each modification has to be submitted to the pipe laying contractor and

the Client/Consultant. The complete upgrading cycle shall be supervised by a pipe laying contractor. All

consequences after eventual order for non respect of this obligation are at the manufacturer's charge and

responsibility.

A valid copy of the ISO 9001 certificate shall be included in the offer.

Before the order is placed, a technical audit will take place with pipe laying contractor/ Client.

The manufacturer's specification of the steel, the manufacturing procedure itself and the laboratories in

which testing takes place, shall be approved and registered by the pipe laying contractor. Valid approval

certificates must be available.

The pipe laying contractor shall verify the control equipment of the manufacturer, its calibration and the

points at which it is located. If during the control of the fittings certain problems arise the pipe laying

contractor agent may demand supplementary tests at the cost of the manufacturer.

At all times while work on the contract of the Client is being performed, the inspector representing the

Client shall have free entry to all parts of the manufacturer's facilities and those of all subcontractors, who

are involved in the manufacturing of the fittings. All reasonable facilities shall be afforded to the inspector

to satisfy him that the product is being furnished in accordance with these specifications. All tests and

inspections called for by these specifications will be made in the manufacturer's plant prior to shipment and

at the manufacturer's expense, unless otherwise, and shall be conducted as not to interfere unnecessarily

with the operations of the manufacturer's plant. The manufacturer shall notify the Client prior to

completion or shipment of all fittings requiring such inspection.

Eventual interpretations and deviations to this specification by the Manufacturer shall be requested by

writing in his offer with detailed justification and approved by the Client/Consultant and the Authorised

pipe laying contractor before eventual order to the Manufacturer. The latter is responsible and shall

indemnify the Client/Consultant for any damage resulting from the non-respect of this obligation.

An approval of documents can never be considered as an acceptance of deviations or relaxations to

requirements. A deviation is only possible after specific request to the Client.

1.1. Glossary

Client shall mean GAIL (I) Limited

Manufacturer means the Manufacturer of the Fittings &

Flanges as well as its sub-contractor(s)

PTS means the present «Particular Technical Specification P.013313

D 11077 117 » and all its appendices, if any.

Pipe Laying Contractor/Contractor party which carries out all or part of Engineering, Procurement,

Construction, Pre-commissioning & Commissioning of the project.

It shall mean Pipe Laying Contractor in the present context.

Third Party

Inspection Agency (TPIA) means the Inspection Agency to be appointed by the Vendor

Consultant /Owner Shall means TRACTEBEL Engineering Pvt. Limited /

Representative The entity of the Client or the company nominated by the Client to

design the natural gas transport or distribution system and to specify

the equipment

Page 33 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 3 of 19

2.0 DESIGN AND CONSTRUCTION

2.1 The pressure temperature ratings for tee, weldolets, elbows and flanges shall be calculated respectively in

accordance with ANSI B31.8, DIN2413 and ANSI B16.5. For all other types of fittings (caps, reducers,

nipple) ASME section VIII shall apply.

The standard dimension shall be in accordance

� Flanges such as weld neck flanges and blind flanges shall conform to the requirements as follows :

- ASME B16.5 upto sizes DN 600 mm (24") excluding DN 550 mm (22"),

- MSS-SP-44 for sizes DN 550 mm (22").

� With ANSI B16.9 for the tees, reducers and elbows (except for short radius elbows which should be in

accordance with ANSI B16.28)

� With ANSI B 16.9 for the caps,

� With ANSI B 36.10 for the nipples,

� And with ANSI B16.5 / MSS SP 44 for the flanges.

2.2 The temperature range as follows:

• For above ground Services (CS) : -20°C to +65°C

• For above ground Services (LTCS) : -45°C to +65°C

• For Underground Services : -20°C to +60°C

The Design pressure is 98 barg.

2.3 The wall thickness shall meet the following requirements:

2.3.1 The maximum allowable stress in the base material and in the weld shall be equal to fifty per cent (50%) of

the minimum yield strength guaranteed by the specification of the steel used.

2.3.2 The minimum wall thickness must be greater than the following:

a. Thickness calculated in line with requirements given in ASME B 16.9 Para 2.2

b. Nominal Thickness of pipe

Thickness calculation is to be submitted to Owner/Owner’s Representative for prior approval before

manufacturing.

2.3.3 If the fitting has yield strength lower than the yield strength of the pipe to which it is intended to be

welded, the wall thickness in each zone of the fitting is at least equal to the largest value "tr" of either.

� The specified pipe wall thickness times the ratio of the minimum yield strength guaranteed by the

standard of the steel of the pipe and the minimum yield strength guaranteed by the standard of the steel

of the fitting;

� The absolute minimum thickness required by the applicable code(s).

2.3.4 The specified pipe wall thickness and grade (with reference to the equivalent grade in ASTM spec. or API

5L spec.) with which the fitting and flange is intended to be used is specified in the piping material

specification.

Fittings such as tees, elbows, reducers, etc. shall be either welded or seamless type. All welded fittings

shall be subjected to heat treatment. All fittings (except weldolets) shall comply with

The requirements of MSS-SP-75. Fittings such as weldolets etc. shall be manufactured in accordance with

MSS-SP-97.

Welded pipes used for fittings shall be LSAW type only.

Page 34 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 4 of 19

2.3.5 The thickness at the welding end shall not exceed 1.5 times the nominal wall thickness of the pipe to be

matched.

2.3.6 All the above requirements also apply to the welding ends of the flanges.

2.4 The manufacturer shall submit for approval to the Pipe Laying contractor and to the Client the dimensional

drawings, calculations, and the material part lists for all the types of fittings and flanges. All the documents

must be identified with the Client's order number.

2.5 The design shall take into consideration performance requirements prescribed in paragraph 2.6.

2.6 The design of tees, reducers or elbows must be established, by proof testing, in accordance with par. 2.7.

The design of the other fittings must be established by mathematical analysis according to ASME code.

2.7 All fittings under this specification shall be designed to withstand a field hydrostatic test pressure with non

corrosive water, after installation, during 24 hours at a following pressure level:

Minimum: P = 1.5 MOP

Where:

P = hydrostatic test pressure, bar

MOP = maximum operating pressure = 91barg.

The pressure level will however not exceed 1.9 MOP for the fittings and 1.5 times the 38°C pressure

rating for the flanges.

2.8 Design Proof Test

This applies to fitting only and not to flanges.

2.8.1 In addition to the requirements of par. 2.3.1 to 2.3.4 proof tests shall be made as evidence of the adequacy

to the design references. Records of design or successful proof tests shall be available at the facility for

inspection by the Client and copy shall be added to the Certified Material Test Report (CMTR, par. 6.3.).

2.8.2 Unless otherwise agreed upon between manufacturer and Client, the only required proof test is a bursting

strength test.

2.8.2.1 Prototype fittings, representatives of production, selected for test shall be identified as to material, grade,

and lot, including heat treatment. They shall be inspected for dimensional compliance to this standard.

2.8.2.2 Straight seamless or welded pipe sections, whose calculated bursting strength is at least as great as that

calculated for the fittings, shall be welded to each end of the fitting to be tested. Any internal misalignment

greater than 0.06 inch (1.6 mm) shall be reduced by taper boring at a slope not over 1:3. Length of pipe

sections for closures shall be at least twice the pipe O.D. Shorter lengths may be used as follows:

� The assembly must withstand at least 110 % of the pressure computed in 2.7.2.3.

� Minimum length of pipe shall be one pipe O.D. for sizes NPS 8" and smaller.

Test fluid shall be water or other liquid used for hydrostatic testing.

2.8.2.3 Hydrostatic pressure shall be applied until the fitting ruptures. The actual test

pressure prior to rupture must at least be equal to the adjusted proof test pressure

defined as follows:

P (adj.) = P x S act

s

( .)

where

P (adj.) = the adjusted proof test pressure, bar

P = the computed proof test pressure at burst of any part of the assembly, bar

S = minimum specified tensile strength of the pipe for which the fitting is intended to be

used, N/mm2

Page 35 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 5 of 19

S (act.) = the actual tensile strength of the material of the test fitting (determined on specimen

representative of the test fitting), N/mm2

The computed proof test pressure shall be determined as follows:

which refers to the pipe which the fitting's marking identifies and, where

P = 20S t

D

. where,

P = Computed bursting pressure of the pipe, bar

S = Minimum specified tensile strength of the pipe, N/mm2

t = Nominal pipe wall thickness, mm

D = Specified outside diameter of pipe, mm

2.8.2.4 As an alternate, if the pipe ruptures, or if sufficient pressure to rupture any part of the assembly cannot be

attained, the test pressure is acceptable if a final test pressure is at least 105 % of the adjusted proof test

pressure.

2.8.3 A successful proof test on a prototype fitting, selected as required in subsection 2.7.2.1., may be used to

qualify other fittings to the extent described herein.

2.8.3.1 One test fitting may be used to qualify similar designs which shall not be smaller than one-half nor larger

than two times the size of the test fitting.

2.8.3.2 The test on a non-reducing fitting qualifies reducing fittings of the same pattern.

2.8.3.3 The untested fitting must have a t/D ratio neither less than one-half nor more than three times the t/D of the

test fitting.

2.8.3.4 The pressure retaining capacity of a fitting, made of various grades of steel, will be essentially directly

proportional to the tensile properties of the various grades. Hence, it is necessary to test a prototype in only

a single grade to prove the geometric design of the fitting.

2.8.3.5 A test on a prototype elbow qualifies elbows having longer radii than the test fitting providing they qualify

under 2.7.3.1 and 2.7.3.3.

2.8.3.6 A change in design from seamless fitting to fitting containing (a) seam weld(s) require(s) an appropriate

prototype test. A change of location of the seam weld requires a separate prototype test. Any deviation

must be submitted for approval to the pipe laying contractor.

2.8.4 If the manufacturer cannot give the certificate of prototype bursting test, the design of fittings shall be

verified as follows. A prototype must withstand during 24 hours 1.4 times the maximum operating

pressure (M.O.P). The prototype is considered to be agreed upon if the deformations measured during the

test at 1.4 X M.O.P. shows that the stress does not exceed 70 % of the minimum guaranteed yield strength

of the fitting.

The certificate of this prototype qualifies in the same limits than par. 2.7.3.

2.9 Fitting dimensions

One of the principles of this standard is the maintenance of a fixed position for the welding ends with

reference to the centreline of the fittings or the overall dimensions, as the case may be.

Dimensional standards will be in accordance with §2.1.

2.10 Fitting and Flanges Tolerances

2.10.1 Tolerances for welding ends, out-of-roundness at the welding ends and inside diameter at the bevel are

shown hereafter. Other tolerances wall thickness are as per corresponding codes: ANSI B16.9 standard

and for short radius elbows ANSI B16.28 standard.

2.10.2 Welding ends

Page 36 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 6 of 19

The welding end and bevel shall be in accordance with Figure 1 for wall thickness up to 20.0 mm ; for

thicker walls, refer to Figure 2. The welding end land of the fitting & flanges shall be machined flat and

shall not vary from the plane by more than 0.03 in (0.8 mm) at any point. If a fitting & flange has a

thickness unequal to the pipe with which it is intended to be used, the welding end preparation at the joint

has to conform with Figure 3.

2.10.3 Out-of-roundness at the welding ends

The out-of-roundness, defined as the difference between the maximum and the minimum inside diameter at

the welding ends shall not exceed 1 % of the specified inside diameter for sizes NPS 4 and smaller.

Fittings & flanges NPS 4 and larger shall be machined true round.

2.11 Inside Diameter

The inside diameter at any place at end (bevel) shall be the following:

NPS Tolerance of inside Ø at end (mm)

1/2" – 24” + 1.6 - 0.4

(1) The tolerance refers to variation from nominal I.D. calculating by (O.D. nom. - 2 t nom.).

(2) Flange Bore to match with I.D. of the pipe.

3.0 MATERIALS

3.1 The steel used in the manufacture of fittings & flanges shall be selected by the manufacturer and submitted

for approval to the Client and the pipe laying contractor at the time of the offer. The manufacturer shall fill

in the data sheet.

3.2 The chemical composition of the steel meets the requirements of Table 1.

3.3 The steel used has tensile properties conforming to the requirements prescribed in the ASTM standards.

3.4 The ratio of yield strength to tensile strength shall not exceed 0.90.

3.5 The material for fittings shall consist of blooms, billets, slabs, forging quality bar, plate, seamless or fusion

welded tubular products with filler metal added.

3.6 The steel shall be fully killed, fine grain practice.

3.7 The steel used shall be suitable for field welding to other fittings, pipes, flanges, or valves manufactured

under ASTM specifications A333, A350, A352, A381, A420, A694, A707 or API standards specifications

5L, 6D, 605 or MSS standards SP-44, SP-72, SP-75, EN 10208-2 in line with Piping Specification 6C1

attached with the tender document.

3.8 If preheating of the material is required to ensure proper weldability under normal field conditions, the

manufacturer shall state so in the offer, specifying preheat requirements and if accepted by the Client this

shall be permanently indicated on the fitting & flanges.

3.9 The Manufacturer must deliver a certificate EN 10204 (3.1 for upgrade fitting & flange; 3.2 if new), stating

the quality, the mechanical properties (yield strength, tensile strength, percent elongation, impact test,

chemical analysis, the process of manufacture and the marking (for example the heat number of material)

of the steel.

Page 37 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 7 of 19

3.10 Chemical Composition

3.10.1 For each heat the manufacturer shall check a chemical analysis of the steel (see Table 1).

3.10.2 Check analysis

Carbon equivalent shall be computed by the following equation:

C.E. = C + Mn

6 +

5

VMoCr ++ +

Ni Cu+

15

And shall not exceed 0.43

4.0 FABRICATION AND TEST

For all forging materials, the specimen shall be taken from the integral part of the forging.

The par.4.1 to 4.2 are only applicable on welded fittings.

4.1 Welding Fabrication

4.1.1 All welds and repair welds shall be performed according to written procedures. The welding procedure

must be submitted for approval to the pipe laying contractor before any fabrication.

Only qualified & approved welders and welding operators shall be used in production.

4.1.2 The joints shall be furnished in accordance with the requirements of Section VIII of ASME Boiler and

Pressure Vessel Code.

4.1.3 Machine welding shall be done by an electric process, preferably by submerged arc.

4.1.4 All butt welds shall have full penetration. Submerged arc machine welding shall be done with at least one

pass from the inside, except when accessibility makes this impossible, then a manual or machine root bead

may be employed provided that a visual inspection of the root bead is possible. Backing rings shall be not

used.

4.1.5 Repair, chipping or grinding of welds shall be done in such a manner as not to gouge, groove, or reduce the

original metal thickness by more than 6 1/2 % of nominal specified wall.

4.1.6 Except for bar in the tees, fillet welds shall not be permitted.

4.1.7 Welded-on braces, if used, should be removed before heat treatment and the weld spot shall be repaired and

ground flush and smooth. However, when braces are required for heat treatment, they shall be cut out and

the surface shall be ground flush and smooth after heat treatment. Except for bar in the tees, welding shall

not be permitted after heat treatment. The ground areas shall be inspected by magnetic particle or liquid

penetrant testing.

4.2 Welding Procedures

4.2.1 All welds, repair welds and repair by welding shall be performed according to written procedures. These

welding procedures shall be qualified according to the requirements of the ASME Boiler and Pressure

Vessel Code, Section IX.

The welding procedure tests are required on material which is on the high side of the chemistry

specification.

The manufacturer shall maintain a weld record of the procedure and performance test results. The test

coupons shall be submitted to the same fabrication and heat treatment as the actual fittings.

The welding procedure qualification must include an impact test set in the weld and in the HAZ with

requirements of paragraph 5.1.2 and a macrographic examination described in paragraph 4.2.2. These tests

shall be performed after eventual final heat treatment.

4.2.2 Macrographic examination: the etched surface of the macro test specimen viewed macroscopically must

display the image of a well performed welded joint with sufficient penetration, free from linear defects and

important inclusions. In case of doubt, the etched surface must be examined microscopically and

additional macroscopical examinations of other areas may be required.

Page 38 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 8 of 19

The macrographic examination will include hardness measurements in the weld and the HAZ. The hardness

will not exceed the values measured on the parent metal by more than 80 points for the welds and 100 point

for HAZ, with an absolute maximum of 350HV10.

The acceptance of inclusions can be decided upon with the NDE of the welded plates (see paragraph 5.3).

4.2.3 Transverse guided bend test

4.2.3.1 Test method

Transverse weld test specimens shall be subjected to face and root guided bend tests. The specimens shall

be approximately 1.5 in (38 mm) wide, at least 6 in (152 mm) long with the weld at the centre, and shall be

machined in accordance with Figure 4. The face bend specimen shall be bent with the inside surface of the

pipe against the plunger, and the root bend specimen with the outside surface against the plunger. The

dimensions of the plunger for the bending jig shall be in accordance with Figure 5 and the other dimensions

shall be substantially as shown in Figure 5.

The manufacturer shall use a "jig" based on this dimension or a smaller dimension at this option.

4.2.3.2 Test specimen

The weld bend test specimens, as described hereabove shall be cut from the coupon. The specimens may be

taken from a fitting or from sample plates as described in par. 4.2.3.1.

4.2.3.3 Acceptance criteria

The bend test shall be acceptable if no cracks or other defects exceeding 0.12 in (3.2 mm) in any direction

are present in the weld metal or between the weld metal and the fitting metal after the bending. Cracks

which originate along the edges of the specimen during testing and which are less than 0.25 in (6.4 mm)

measured in any direction, shall not be considered unless obvious defects are observed.

4.2.3.4 Retest

If either test fails to conform to specified requirements, the manufacturer may elect to make retests on two

additional specimens from the same lot, each of which shall conform to the requirements specified

hereabove. If any of these specimens fail to conform to the requirements, the welding procedure

qualification test is not accepted.

(*) A lot consists of all fittings/flanges from one heat of steel with same initial wall thickness, from the

same furnace charge for final normalizing heat treatment, from the same shape and the same main pipe

dimension.

4.2.4 Number of tests

The nature and number of tests are specified in the Table below and only one retest is allowed.

Specification test Number

Non destructive test par. 5.3. par. 5.3

X-ray and U.S. testing par. 5.3 par.5.3.

Destructive test All specimens shall be taken transverse to the weld

Tensile par. 5.1.1. 2

Bend test Face par. 4.2.3. 2

Root par. 4.2.3 2

Impact Weld par. 5.1.2. 1 set of 3 specimens

HAZ par. 5.1.2. 1 set of 3 specimens

Macrographic examination par. 4.2.2 1

Page 39 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 9 of 19

4.3 Normalising Heat Treatment

Start & stop temperature chart shall be signed by TPIA, also power failure log shall be maintained.

4.3.1 After forming and welding, all fittings & flanges shall be heat treated by normalising. Normalising shall be

carried out in such a way that the base material acquires a fine grained perlitic structure. If the

manufacturer can give proof by qualified manufacturing procedure that after forming, the steel of the

fitting & flanges has a homogeneous fine grained perlitic structure, he can ask for a derogation supported

by technical file to the Client and to the pipe laying contractor.

The normalizing procedure requires the approval of the pipe laying contractor. Good care shall be taken to

avoid direct contact of the flames with the material to be heated.

During the normalizing period, the temperature of the heat treatment lot shall be automatically recorded by

a sufficient number of thermocouples attached to the material surface. The thermocouples shall be

adequately protected against the influence of heat radiation. Temperature variations shall be within ±

20°C. The manufacturer shall furnish time temperature charts of each heat treatment lot. The fittings &

flanges belonging to each treatment lot shall be specified on the charts. Temperature measurements by

other means are permitted only if approved by the pipe laying contractor.

4.3.2 The fine grained perlitic structure of the steel shall be verified by at least one micrographic examination per

lot (definition in §4.2.4), according to ASTM E 112. The grain size shall be in the range of 8 to 12.

4.3.3 The manufacturer shall include in the CMTR data of this treatment.

5.0 UPGRADING FROM 3.1 TO 3.2 CERTIFICATE

5.1 Mechanical Tests

The following mechanical tests shall be performed by the vendor under the supervision of the PIPE

LAYING contractor and the certificates shall be added to the CMTR.

Test specimens may only be cut after a marking transfer by the Authorised PIPE LAYING contractor. All

the tests shall be performed after final heat treatment.

Certification requirements to comply with EN 10204 – 3.2 certificates shall issued by TPIA

5.1.1 Tension test

5.1.1.1 Requirements

The material shall be in conformance with the ASTM standards and the ratio of yield stress to tensile stress

shall not exceed 0.90.

For fittings containing welds, the fracture must be outside of the weld. If there is a fracture in weld or

HAZ, the tensile strength shall at least meet the requirements for tensile properties as per ASTM standards.

5.1.1.2 Test specimen

The test specimen shall represent all forgings from the same lot. Test specimens shall be taken from the

fitting after final heat treatment or from a piece of pipe or plate of the same nominal thickness, same heat

of steel from which the fitting is made and which has been heat treated in a lot with any of the fitting(s) it

represents. For welded fittings, this coupon (piece of pipe or plate) shall contain a weld in prolongation of

the weld of the fitting.

5.1.1.3 Number of tests

For fittings NPS 2 and greater the following number of test shall be performed:

� Base material : one tension test

� Weld : one tension test

5.1.1.4 Test locations and orientations

For welds, the test specimen shall be orientated transversally to the weld. For base material, test specimens

shall be orientated transversally and if this orientation is not feasible, it shall be orientated longitudinally.

Page 40 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 10 of 19

For flanges, the test location shall be in accordance with ASTM A350§6.1.3.

5.1.1.5 Test method

Testing shall be performed in accordance with ASTM A 370 standard rectangular plate type 1-1/2" wide

(Fig. 4-A370) or standard round (Fig. 5 or Fig. 6-A370). Yield strength shall be determined either by the

0.2 % offset or the 0.5 % extension under load (EUL) method.

5.1.1.6 Retest

If the tension test specimen from any lot fails to conform to the requirements of the particular grade

ordered, the manufacturer may elect to make retests on two additional pieces from the same lot. If one or

both of the retests fail to conform to the requirements, the whole lot of that specimen will be rejected.

5.1.2 Impact test

5.1.2.1 Requirements

For product, the Charpy V- Notch test shall be conducted as per following requirements:

Material Impact Test Temperature Energy Absorption Value

(Minimum)

Carbon Steel Material -20 Deg. C Individual 28J

Average 35J

Low Temperature

Carbon Steel Material

-20 Deg. C Individual 28J

Average 35J

Material Standard’ impact test

requirements temperature or

- 45 Deg. C whichever is lower

Material Standard’s impact test

requirement

5.1.2.2 Test specimen

The test specimen shall be machined from material obtained as in paragraph Test specimen for Tension test

(par. 5.1.1.2.).

Flattening of test specimens are not allowed.

5.1.2.3 Number of tests and orientation

Three test specimens shall constitute one test set.

For fittings NPS 2 and greater, the following number of tests shall be performed :

� Base material : 2 test sets, one set shall be orientated longitudinally and another one transversally.

� Weld : 1 test shall be orientated transversally.

� HAZ : 1 test shall be orientated transversally.

5.1.2.4 Test method

The notched bar impact test shall be made in accordance with ISO 148 - Charpy V - Notch.

If the wall thickness of the fitting or the coupon does not enable machining of full size specimens, the

largest possible size must be used but not less than (10 x 5 mm). The axis of the notch shall be orientated

through the wall thickness of the fitting.

5.1.3 Flattening test

This is not applicable to the flanges.

5.1.3.1 Requirements

Page 41 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 11 of 19

Flatten to 1/3 original O.D. without cracks or breaks in the fitting, continue flattening until meeting

opposite walls of the fitting.

No evidence of lamination of burnt metal may develop during entire test.

5.1.3.2 Test specimen

The test specimen represents all the fittings from the same heat of steel of the same shape and of the same

main pipe dimension of the fittings.

5.1.3.3 Number of tests

For fittings size lower than 2” one flattening test shall be made per test specimen.

5.1.4 Retreatment

If the result of the mechanical tests does not conform to the requirements specified in par. 5.1.3.1., the

manufacturer, with the acceptance of the Client and the pipe laying contractor, may reheat treat the fittings

as applicable and repeat all the tests specified.

5.2 Chemical Analysis

For each lot/item a new chemical analysis of the steel shall be done.

The chemical analysis shall conform to the ASTM requirements specified in the specification.

The carbon equivalent shall be computed by "check analysis": see par. 3.10.2 with C.E. ≤ 0.43.

The reports shall be added to the CMTR reports and approved by the pipe laying contractor.

5.3 Non Destructive Examinations (NDE)

The following mechanical tests shall be performed by the vendor under the supervision of the pipe laying

contractor and the certificates shall be added to the CMTR.

5.3.1 Radiography

All butt and repair welds shall be 100% radiographed in accordance with ASME section V - non

destructive examination - article 2 - using fine grain film and lead screens. Acceptance criteria shall be as

be ASME B 31.4 or ASME B 31.8 as applicable and API 1104. Radiography shall be performed after the

final heat treatment.

5.3.2 U.S., Magnetic, Visual and Dimensional examination

5.3.2.1 Non destructive examinations

In the presence of the TPIA, the manufacturer shall perform the following non destructive examinations on

the fittings after the mechanical tests and according to an inspection procedure to be submitted for

approval.

� For fitting with wall thickness larger than or equal to 6 mm, ultrasonic inspection on the whole surface

(with angle probe and straight probe) to the maximum extent possible.

� All finished wrought weld ends shall be 100% tested for lamination type defects by ultrasonic test. Any

lamination larger then 6.35 mm shall not be acceptable.

� When elbows of size > DN 300 mm (12") are manufactured, the first elbow of each radius, diameter

and wall thickness shall be ultrasonically checked for sufficient wall thickness in areas where a

minimum wall thickness is to be expected. This shall be followed by random inspection of one out of

every three elbows of the same radius, diameter and wall thickness.

� Magnetic Particle or Liquid Penetrant Examination shall be performed on cold formed.

� Butt welding tees with extruded outlets as per applicable material standard.

� Welds, which cannot be inspected by radiographic methods, shall be checked by Ultrasonic or

Magnetic particle methods. Acceptance criteria shall be as per ASME section VIII Appendix U and

Appendix VI respectively.

Page 42 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 12 of 19

� Magnetic particle inspection on the whole external surface and the accessible internal surface.

5.3.2.2 Ultrasonic inspection

Ultrasonic inspection of all welds and 25 mm of base material at each side of the weld shall be done.

5.3.2.3 Visual examination

All fitting & flanges shall be visually examined.

5.3.2.4 Test after machining

After machining, all the finished bevels shall be submitted to the following tests:

� Magnetic particle or liquid penetrant

� For fitting and flanges with wall thickness larger than or equal to 6 mm, ultrasonic inspection on 25

mm of base material.

5.3.2.5 Dimensional examination

� For fittings up to NPS 6, the TPIA shall choose 10 % with a minimum of one piece per item of the

order and these pieces shall be submitted to a dimensional examination.

� For fittings larger than NPS 6, all pieces shall be submitted to a dimensional examination

� All flanges shall be submitted to a dimensional examination.

5.3.3 Acceptance criteria of the different NDE

5.3.3.1 Visual examination

The following defects are unacceptable:

� Undercuts exceeding 1 mm in depth and 25 mm in length.

� Undercuts of the outside weld which overlap undercuts of the inside weld.

� Lack of penetration.

� Continuous occurrence of under-cutting.

5.3.3.2 Magnetic particle inspection

Magnetic particle inspection on the external surface. ASME code, section VIII, division 1, appendix VI.

5.3.3.3 Ultrasonic inspection

� For the longitudinal welds: ASME code, section VIII, division 1, appendix 12.

� For welding ends, see § 5.3.3.5.

� For base material :

� Procedure: ASME code, section V, art. 23, SA-388.

� Criteria: ASME code, section VIII, division 1, UF-55 (angle probe will be used).

5.3.3.4 Radiographic examination

� For longitudinal seam welds :

� Criteria : ASME code, section VIII, division 1, UW 51

� For girth welds :

� Criteria: API standards 1104, section 6.0.

5.3.3.5 Magnetic particle or liquid penetrant on the finished bevel

The following defects are unacceptable:

Page 43 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 13 of 19

� Defects extending into the bevel provided the lamination is parallel to the surface and has a transverse

dimension exceeding 6.35 mm.

� All defects not parallel to the surface extending into the bevel.

5.4 Fitting & Flange Testing

Hydrostatic testing by the manufacturer is not required, but welding fittings shall be capable to withstand a

field hydrostatic testing in accordance with par. 2.6.

5.5 Workmanship and Finish

5.5.1 Fittings & Flanges shall be free of injurious defects and shall have workmanlike finish.

5.5.2 Injurious defects are defined as those having a depth in excess of 6-1/2 % of specified nominal wall.

5.5.3 Machining and grinding of surface defects shall be treated as follows: sharp defects such as notches,

scratches, scraps, seams, laps, tears, or slivers not deeper than 6-1/2 % of nominal wall thickness

shall be removed by grinding. Repair of injurious defects by welding shall be permitted only after

agreement by the Client and the pipe laying contractor, except that welding of injurious defects shall not be

permitted when the depth of defects exceeds 33-1/3 % of the nominal wall thickness, or the length of repair

exceeds 25 % of the specified diameter. Defects must be completely removed and welding performed by a

welder qualified specifically for repair welding, as per par. 4.2.1. Such repair welding shall be ground

flush with the surface and all welding shall be done before final heat treatment. Repair welding shall be

done with low hydrogen electrodes in shielded metal arc welding, gas metal arc process or submerged arc

process. In no case, repair welding or cracks nor repair or repairs is allowed. Repair welding will not be

permitted for flanges.

5.5.4 Repair welding shall be done before the last heat treatment. Adjusting weld preparations, intended for field

welding, by means of welding is not allowed. For "standard fitting" repair by welding is not permitted.

5.5.5 Repair welding on the welds & in the body shall be 100 % radiographed and U.S tested.

5.5.6 At the discretion of the TPIA, finished fittings & flanges shall be subject to rejection if surface

imperfections acceptable under par. 5.5.2 are not scattered but appear over an area in excess of what is

considered as a workmanlike finish.

5.6 Marking

5.6.1 All fittings and flanges furnished under this specification shall be clearly identified on the O.D. with the

following information marked with low stress die stamps or interrupted dot stamps as noted (refer to MS

SP25):

� Manufacturer's name or trademark.

� Heat code identity.

� Fitting or flange number: the fitting or flange number shall be made up of six figures specified as

follows: the item and his number specified in the purchase order.

� The monogram of the pipe laying contractor. This marking shall only be applied after complete

approval of the Certified Material Test Report (see par. 6.4.).

5.6.2 In addition to the above, for NPS 2" and larger, it shall also include the following information:

� Grade symbol: the grade symbol must designate the material of the fitting or flange.

5.6.3 Marking must be done prior to final inspection.

6.0 INSPECTION

6.1 Information

The manufacturer shall inform the Pipe Laying contractor MIN. 5 working days (15 in case of foreign

supplier) in advance of any intervention required by this specification and shall send a copy (fax) of it to

the Client/Consultant.

Page 44 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 14 of 19

6.2 Documentation

Before starting any control, the manufacturer shall submit for approval to the pipe laying contractor and the

Client/Consultant the following documents:

� Detailed fabrication drawing and calculations.

� Fabrication and control procedure (if new -not if upgraded).

� List of Operations of Control (LOC) in accordance with annex 1(if new -not if upgraded).

� Material list.

� Qualified welding procedures (if new -not if upgraded).

� Welder’s performances qualifications (if new -not if upgraded).

� Heat treatment procedure-(if new -not if upgraded).

� Non destructive testing procedures.

Each company dealing in the order by fabrication and/or control shall implement a LOC for all operations

and interventions performed in its organization. They shall also be responsible for the implementation of

the same by their subcontractors.

6.3 CERTIFIED MATERIAL TEST REPORT

A Certified Material Test Report (CMTR) shall be furnished listing as built drawing and calculations, the

LOC (see paragraph 6.2.), the proof test certificate, the base material certificate, the chemical check

analysis. The certificate of the heat treatment, the mechanical tests, the non-destructive examination, the

mechanical properties, the quality release note (see paragraph 6.4.) and any special test required by the

purchase order the fitting or flange individual number (see paragraph 5.6.1.) must be indicated in the

CMTR to permit the correct traceability of each piece. The manufacturer shall furnish one copy of the

CMTR to the pipe laying contractor and one original and one copy to the Client/Engineer.

6.4 IRN

After final approval of fittings/flanges and the acceptance of the CMTR, the PIPE LAYING contractor

shall furnish to the Client/Consultant and to the manufacturer an Inspection Release Note (IRN). The

manufacturer shall deliver one copy of the IRN with the fittings/flanges and one copy shall be included in

the CMTR (see paragraph 6.3.).

6.5 REJECTION

Each fitting or flange in which injurious defects are found during inspection and after delivery shall be

rejected. The manufacturer shall be notified. In this case, the fitting shall be replaced immediately. All

the costs involved, including wages and travel expenses of the pipe laying contractor/Client/ Consultant

shall be borne by the manufacturer.

7.0 CORROSION PROTECTION

The corrosion protection will be applied by the manufacturer after final inspection by the pipe laying

contractor.

The product shall meet the following criteria:

� Guarantee a corrosion protection for a storage period in open air for at least 6 months.

� Shall be easily removable by wire brushing or by grinding.

� It shall not produce toxic vapour or smoke when heated by blow torches or during welding.

Page 45 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 15 of 19

TABLE 1

CHEMICAL COMPOSITION FOR FITTINGS

Maximum limit of chemical elements which may be used in material under this standard.

% MAXIMUM

C 0.230

Mn 1.60

Si 0.50

P 0.030

S 0.025

Nb 0.080

V 0.120

Mo 0.250

Nt 0.0150

Alternate alloy elements may be used but they shall be discussed with the user prior to delivery of the material. This

table is not intended to represent the composition of any heat of steel, but merely to record the maximum permissible

amounts of one element. The combination of elements of any heat must conform to the carbon equivalent, subsection

3.10.2.

For each heat the manufacturer shall analyse the following elements:

C, Mn, Si, P, S, Nb, V, Cr, Mo, Ni and Cu.

The intentional addition of elements other than those specified is not permitted unless agreed upon by the Client.

In any case, for unintentional additions, the following limitations shall be respected:

Cr ≤ 0.15 % Mo ≤ 0.05 % Cu ≤ 0.20 %

Ni ≤ 0.30 % Co ≤ 0.01 % Al ≤ 0.07 %

The content of N total (Nt) may be up to 0.0150 % and must be guaranteed by the manufacturer. If the manufacturer

cannot give any guaranty of N content, he shall analyse this element.

The total content for Nb + V will be limited to 0.150 %.

For each reduction of 0.01 % below the maximum carbon content, an increase of 0.05 % manganese above the specified

maximum is permissible, up to a maximum of 1.70 %.

Page 46 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 16 of 19

FIG. 1

Fitting size 24" and smaller may be furnished with 37° ½ bevel at manufacturer's option.

Recommended bevel for wall thickness (t) at end of fitting: 20 mm or less.

FIG. 2

Recommended bevel for wall thickness (t) at end of fitting, greater than 20 mm

L ≤

20m

m

Page 47 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 17 of 19

FIG. 3

Note

1. No min. when materials

joined have equal yield

strength.

2. t2 must be limited to the

minimum

ACCEPTABLE DESIGN FOR UNEQUAL WALL THICKNESS

FIG. 4

TRANSVERSE FACE AND ROOT BEND TEST SPECIMENS

PIPE FITTING

Page 48 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 18 of 19

FIG 5

GUIDED-BEND TEST JIG DIMENSIONS

CLASS OF STEEL

Y52 and low-grade Y56 Y60 Y70

Radius of male member R A ½ A ½ A ½ A ½ A

Radius of female member R B ½ B ½ B ½ B ½ B

Width of male member, A 4 t 5 t 6 t 8 t

Width of groove in female member, B A + 2t + 3.2 mm A + 2t + 3.2 mm A + 2t + 3.2 mm A + 2t + 3.2 mm

t = specimen thickness

The manufacturer shall use a jig based on this dimension, or a smaller dimension at his option.

Page 49 of 78

FITTINGS & FLANGES P.013313

D 11077

117

Rev. 0 Supply of Pig Launcher / Receiver Page 19 of 19

FIG. 6

SPECTACLE FLANGE

Σ Σ Σ

Page 50 of 78

PIPING CLASSES

P.013313

D 11000

101

GAIL (INDIA) LIMITED

HARIDWAR-RISHIKESH-DEHRADUN PIPELINE (HRDPL) PROJECT

TRACTEBEL ENGINEERING PVT. LTD.

PIPING CLASSES

REPORT

NATURAL GAS PIPELINE FROM HARIDWAR TO DEHRADUN

0 23.04.2019 Issued for Procurement VNG NC RB

Rev Date Description Prepared By Checked By Approved By

Page 51 of 78

PIPING CLASSES

P.013313

D 11000

101

Rev. 0 Supply of Pig Launcher / Receiver Page 1 of 1

TABLE OF CONTENTS

1. SCOPE ................................................................................................................................... 1

1.1. CODING OF PIPING CLASSES............................................................................................... 1

1.2. WALL THICKNESS................................................................................................................. 1

1.3. CORROSION ALLOWANCE .................................................................................................... 2

1.4. WALL THICKNESS CALCULATION......................................................................................... 2

Page 52 of 78

PIPING CLASSES

P.013313

D 11000

101

Rev. 0 Supply of Pig Launcher / Receiver Page 1 of 2

1. SCOPE

Piping classes are established taking into account the following criteria:

The medium to be handled.

The surrounding.

The referenced codes.

The temperature-pressure rating.

1.1. Coding of Piping Classes

Each class is named by a code consisting of four parts:

First part

A figure designating the rating and the code:

1 = 150 lbs ANSI

3 = 300 lbs ANSI

6 = 600 lbs ANSI

9 = 900 lbs ANSI

Second part

A letter designating the material:

A = Alloy steel

C = Carbon steel

F = Fiberglass reinforced plastic/epoxy (FRP)

G = Galvanized

P = Plastic (PEHD, ...)

S = Stainless steel

V = PVC

Third part

A sequential number to differentiate two or more piping classes of the same rating and same material but

presenting some differences related to the handled fluid.

Fourth part

A letter designating the underground:

U = Underground

1.2. Wall Thickness

The wall thickness of pipe shall be as follows:

Wall thickness of pipe shall be calculated as specified in the applicable sections of:

Page 53 of 78

PIPING CLASSES

P.013313

D 11000

101

Rev. 0 Supply of Pig Launcher / Receiver Page 2 of 2

ANSI B 31.8 for classes covering the main process and auxiliary gas lines.

ANSI B 31.3 for classes covering utilities lines.

1.3. Corrosion Allowance

The minimum corrosion allowance used to calculate wall thickness as follows:

Carbon steel and ferritic alloys in classes calculated following ANSI B 31.8 : 1.0 mm

Carbon steel and ferritic alloys in classes calculated following ANSI B 31.3 : 1.0 mm

Stainless steel : 0 mm

Plastic and FRP pipes: 0 mm.

1.4. Wall Thickness Calculation

a) Pipes for gas application have to comply with ASME/ANSI B 31.8 code. Pipe wall thickness will be

calculated as follows :

cTEFS

PDt

2 (1)

t = nominal wall thickness (mm)

P = design pressure (MPa)

S = minimum yield strength (MPa)

D = nominal outside diameter (mm)

F = design factor (As per Table no. 841.114B of ASME B 31 .8)

E = longitudinal joint factor

= 1.0 for ASTM A 333 (seamless or electric resistance welded)

= 1.0 for API 5L X 60 (seamless or EFW or SAW)

T = temperature derating factor = 1.0

C = corrosion allowance (mm)

b) Pipes for utilities lines have a wall thickness complying with ASME/ANSI B 31.3 code :

)1()(2

acPYSE

PDt

t = nominal wall thickness (mm)

S = allowable stress (MPa)

P = design pressure (MPa)

E = longitudinal joint factor

Y = coefficient as per table 304.1.1

C = corrosion allowance (mm)

a = negative fabrication tolerance (%)

Page 54 of 78

PIPING SPECIFICATION

6C1

DOC. NO :

P.013313 D 11076 101

SHEET 1 OF 6

ASME B 31.8 Carbon Steel - 20 to 65 Carbon Steel 98.00

600#-RF LTCS - 45 to 65 LTCS 98.00

(BARE PIPE - TO BE

PAINTED AT SITE)

LTCS (See Note 3)

CARBON STEELTemperature

(Deg.C)

Pressure

bar (g)

° C bar (g)

CORROSION ALLOWANCE -29 102.04

CARBON STEEL 2.0 mm 0 102.04

2.0 mm 38 102.04

100% 93 93.08

PIPE SIZE RANGE 1/2"- 8"

0 23.04.2019 MK NC AR

REV DATE PREAPARED CHECKED APPROVED

8" NB Pipeline from Haridwar to Dehradun

PRESSURE bar(g)

FLUIDS

1/2" to 12"

8"

NG : NATURAL GAS

DESCRIPTION

Issued for Procurement

2. ALL ABOVE GROUND (A/G) STATION PIPES SHALL BE BARE PIPES. THE PIPES SHALL BE PAINTED AT SITE, AS PER PROJECT

SPECIFICATIONS FOR PAINTING OF ABOVE GROUND STATION PIPING.

BASIC PIPING SPECIFICATION DATASTEMPERATURE °C

6 C1 - PMS for PIPELINE AND STATION PIPING

Temperature & Pressure Rating

LTCS

DESIGN CODE

MAXIMUM PIPELINE DESIGN CONDITIONS

3. MATERIAL FOR 1/2" TO 12" STATION PIPING SHALL BE ASTM A 333, GRADE 6 (LTCS). LTCS MATERIAL SHALL BE CHARPY

IMPACT TESTED AT (-45 °C).

X-RAYS

BASIC MATERIAL

PRIMARY FLANGE RATING

Note :

1. '6C1' INDICATES - 600# PIPING AND PIPELINE

AG : ACTUATING GAS

Rev. 0 Supply of Pig Launcher / Receiver 1 of 6Page 55 of 78

PIPING SPECIFICATION

6C1

DOC. NO :

P.013313 D 11076 101

SHEET 2 OF 6

REV. 0

ITEM SHORT SIZE END RATING DIMENSION MATERIAL REMARKS

CODE FROM- CONNECTION AND/OR STANDARD

THRU SCH/THK

MAIN LINE

PIPES P 8'' BE-ANSI B16-25 6.4 mm Thk API 5L API5L X 60 8" - CLASS 3 (MAINLINE)

PIPES P 8'' BE-ANSI B16-25 7.1 mm Thk API 5L API5L X 60 8" - CLASS 4 (MAINLINE)

PIPES P 8'' BE-ANSI B16-25 7.1 mm Thk API 5L API5L X 60 8" HOT INDUCTION BENDS - IN CLASS 3

PIPES P 8'' BE-ANSI B16-25 7.9 mm Thk API 5L API5L X 60 8" HOT INDUCTION BENDS - IN CLASS 4

STATION PIPING

PIPES P 1/2" - 1 1/2" PE-ANSI B16-25 160 ANSI B 36-10 ASTM A333 GR 6 SEAMLESS (LTCS)

PIPES P 2" BE-ANSI B16-25 160 ANSI B 36-10 ASTM A333 GR 6 SEAMLESS (LTCS)

PIPES P 3" - 12" BE-ANSI B16-25 80 ANSI B 36-10 ASTM A333 GR 6 SEAMLESS (LTCS)

PIPES P 8'' BE-ANSI B16-25 7.1 mm Thk API 5L API5L X 60 STATION PIPING (MAINLINE AG & UG)

PIPES P 8'' BE-ANSI B16-25 7.9 mm Thk API 5L API5L X 608" HOT INDUCTION BENDS AT STATIONS

(CLASS 4 THICKNESS)

ELBOWS 90 LR E 1/2"- 1 1/2" BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 ASTM A 350 LF2, CL1 SMLS

ELBOWS 90 LR E 2"- 12" BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 ASTM A420 WPL 6 SMLS

ELBOWS 90 LR E 8'' BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 API5L X60 or A860 WPHY 60 (MAINLINE)

ELBOWS 45 LR note 1 E45 1/2"- 1 1/2" BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 ASTM A 350 LF2, CL1 SMLS

ELBOWS 45 LR note 1 E45 2"- 12" BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 ASTM A420 WPL 6 SMLS

ELBOWS 45 LR note 1 E45 8'' BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 API5L X60 or A860 WPHY 60 (MAINLINE)

REDUCERS CONC RC 1/2"- 1 1/2" BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 ASTM A 350 LF2, CL1 SMLS

REDUCERS CONC RC 2"- 12" BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 ASTM A420 WPL 6 SMLS

REDUCERS CONC RC 8'' BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 API5L X60 or A860 WPHY 60 (MAINLINE)

REDUCERS ECC RE 1/2"- 1 1/2" BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 ASTM A 350 LF2, CL1 SMLS

REDUCERS ECC RE 2"- 12" BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 ASTM A420 WPL 6 SMLS

REDUCERS ECC RE 8'' BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 API5L X60 or A860 WPHY 60 (MAINLINE)

TEES EQUAL T 1/2"- 1 1/2" BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 ASTM A 350 LF2, CL1 SMLS

TEES EQUAL T 2"- 12" BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 ASTM A420 WPL 6 SMLS

TEES EQUAL T 8'' BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 API5L X60 or A860 WPHY 60 (MAINLINE)

TEES RED

(See Note 1)

TR3"- 8"

BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 ASTM A420 WPL 6

SMLS

The size inicated in this table refers to Mainline

size of Tee Connection. For Branch Size, Please

refer to the Chart given in Sheet 6 of this

Document.

TEES RED

(See Note 1)

8''

(Mainline Size)BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 API5L X60 or A860 WPHY 60

SMLS

The size inicated in this table refers to Mainline

size of Tee Connection. For Branch Size, Please

refer to the Chart given in Sheet 6 of this

Document.

FLOW TEE EQUAL

(See Note 1) T2

8''

(Mainline Size)BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 API5L X60 or A860 WPHY 60 SMLS

FLOW TEE RED

(See Note 1) TR2

8''

(Mainline Size)BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 API5L X60 or A860 WPHY 60

The size inicated in this table refers to Mainline

size of Tee Connection. For Branch Size, Please

refer to the Chart given in Sheet 6 of this

Document.

WELDOLETS WEL1 1/2"-6''

BW - ANSI B16-25 SEE PIPE & note 1 MSS-SP-97 ASTM A 350 LF2, CL1

The size inicated in this table refers to Mainline

size. For Branch Size of Weldolet, Please refer to

the Chart given in Sheet 6 of this Document

WELDOLETS WEL8''

(Mainline Size)30.03.2019 SEE PIPE & note 1 MSS-SP-97

ASTM A694 F60 OR

EQUIVALENT

The size inicated in this table refers to Mainline

size. For Branch Size of Weldolet, Please refer to

the Chart given in Sheet 6 of this Document

CAPS C 1/2"- 6" BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 ASTM A420 WPL 6

CAPS C 8'' BW - ANSI B16-25 SEE PIPE & note 1 ANSI B16-9 API5L X60 or A860 WPHY 60 (MAINLINE)

NIPPLES NBEP 1/2" - 1 1/2" BOTH ENDS PLAIN 160 ANSI B36-10 ASTM A333 GR 6 SEAMLESS-LG=100mm

NIPPLES NOET 1/2" - 1 1/2" ONE END THRD-MNPT 160 ANSI B36-10 ASTM A333 GR 6 SEAMLESS-LG=100mm

NIPPLES NBET 1/2" - 1 1/2"BOTH ENDS THRD-

MNPT160 ANSI B36-10 ASTM A333 GR 6 SEAMLESS-LG=100mm

FULL COUPLINGS CF 1/2" - 1 1/2" FNPT ANSI B1-20-1 3000# ANSI B16-11 ASTM A 350 LF2, CL1 THREADED

CAPS THRD C2 1/2" - 1 1/2" FNPT ANSI B1-20-1 3000# ANSI B16-11 ASTM A 350 LF2, CL1

PLUGS THRD PL 1/2" - 1 1/2" MNPT ANSI B1-20-1 3000# ANSI B16-11 ASTM A 350 LF2, CL1

8" NB Pipeline from Haridwar to Dehradun

6 C1 - PMS for Piping

NOTE 1 :

WALL THICKNESS FOR TEES, ELBOWS, REDUCERS AND CAPS SHALL BE DETERMINED BY VENDOR AS PER THE REQUIREMENTS OF ASME B 16.9 § 2.3. MINIMUM THICKNESS OF

TEE SHALL ALSO MEET THE REQUIREMENTS OF ASME B 31.8, APPENDIX -F FOR BRANCH OPENING. FURTHER, MINIMUM THICKNESS OF TEES, ELBOWS, REDUCERS AND CAPS

SHALL NOT BE LESS THAN THAT OF MATING PIPE. ALL WALL THICKNESS CALCULATIONS SHALL BE APPROVED BY OWNER. THE MATING PIPE DETAILS SHALL BE TAKEN AS

MENTIONED IN THE PIPE SECTION OF THIS PMS.

Rev. 0 Supply of Pig Launcher / Receiver 2 of 6Page 56 of 78

PIPING SPECIFICATION

6C1

DOC. NO :

P.013313 D 11076 101

SHEET 3 OF 6

REV. 0

ITEM SHORT SIZE END RATING DIMENSION MATERIAL REMARKS

CODE FROM- CONNECTION AND/OR STANDARD

THRU SCHED.

WN FLANGES

note 2F 1/2"- 2" BW - ANSI B16-25 600# WNRF, SCH 160 ANSI B16-5 ASTM A350 LF2, CL1 Note 2

WN FLANGES

note 2F 3"- 12" BW - ANSI B16-25 600# WNRF, SCH 80 ANSI B16-5 ASTM A350 LF2, CL1 Note 2

WN FLANGES

note 2F 8'' BW - ANSI B16-25 600# WNRF, SEE PIPE

ANSI B16-5 /

MSS SP-44ASTM A694 F60 OR EQUIVALENT Note 2 (MAINLINE)

ORIFICE FO 1" - 6" For 600 # WNRF ANSI B16-36 ASTM A350 LF2, CL1

BLIND FB 1/2"- 12" For 600 # WNRF ANSI B16-5 ASTM A350 LF2, CL1

SPECTACLE SB 1" - 6" For 600 # WNRF ANSI B16.48 ASTM A350 LF2, CL1

SPECTACLE SB 8'' For 600 # WNRF ANSI B16.48 ASTM A350 LF2, CL1 Note 2 (MAINLINE)

SPECTACLE SB 12'' For 600 # WNRF ANSI B16.48 ASTM A350 LF2, CL1

RESTRICTION

ORIFICERO 1" - 6" For 600 # WNRF ANSI B16-5 ASTM A240 GR 304

MONOLITHIC

INSULATION

JOINT

IJ 2"-6" BW - ANSI B16-25 600# MANUF STD.ASTM A350 LF2 CL1,

or A420 WPL 6Note 2

MONOLITHIC

INSULATION

JOINT

IJ 8'' BW - ANSI B16-25 600# MANUF STD. ASTM A694 F60 Note 2 (MAINLINE)

STUD BOLTS B All Sizes For 600 # WNRF

ASME B 18.2.1 &

ASME B 18.2.2STUD BOLTS: ASTM A320 GR. L7,

HEXAGONAL NUTS : ASTM A194

GR 4

GASKETS

SPIRAL

WOUND G All Sizes For 600 # WNRF ASME B 16.20

WINDING AISI 304, FILLING PURE

GRAPHITE. CENTERING RING CS 4.5 mm THK

NOTE 2 :

BORE OF FLANGE SHALL MATCH INSIDE DIA OF MATING PIPE. THE MATING PIPE DETAILS SHALL BE TAKEN AS MENTIONED IN THE PIPE SECTION OF THIS PMS.

8" NB Pipeline from Haridwar to Dehradun

6 C1 - PMS for Piping

Rev. 0 Supply of Pig Launcher / Receiver 3 of 6Page 57 of 78

PIPING SPECIFICATION

6C1

DOC. NO :

P.013313 D 11076 101

SHEET 4 OF 6

REV. 0

ITEM SHORT SIZE END RATING DIMENSION MATERIAL REMARKS

CODE FROM- CONNECTION AND/OR STANDARD

THRU SCHED.

BALL VALVES

(See Note 3)VBA 1/2" - 1 1/2" FLGD RF:ANSI B16-5 600# ANSI B16-10

BODY : ASTM A350 LF2, CL1 /

ASTM A 352 Gr. LCB

BALL : ASTM A 182 Gr. F316 OR

ASTM A 351 GR. CF8M OR

(ASTM A350 LF2, CL1 / ASTM A

352 Gr. LCB) + ENP

FULL BORE

FIRE SAFE

WRENCH OPERATED.

BALL VALVES

(See Note 3)VBA 2" - 4"

FLGD RF:ANSI B16-5

or BW: ANSI B16-25600# ANSI B16-10

BODY : ASTM A350 LF2, CL1 /

ASTM A 352 Gr. LCB

BALL : ASTM A 182 Gr. F316 OR

ASTM A 351 GR. CF8M OR

(ASTM A350 LF2, CL1 / ASTM A

352 Gr. LCB) + ENP

DOUBLE BLOCK AND BLEED

FULL BORE

FIRE SAFE

WRENCH OPERATED

BALL VALVES

(See Note 3)VBA 8''

FLGD RF:ANSI B16-5

or BW: ANSI B16-25600# ANSI B16-10

BODY : ASTM A350 LF2, CL1 /

ASTM A 352 Gr. LCB

BALL : ASTM A 182 Gr. F316 OR

ASTM A 351 GR. CF8M OR

(ASTM A350 LF2, CL1 / ASTM A

352 Gr. LCB) + ENP

DOUBLE BLOCK AND BLEED

FULL BORE

FIRE SAFE

GEAR OPERATED :

MANUAL / ACTUATED - AS

INDICATED IN DATA SHEET

GLOBE VALVES

VGL 1/2"-1 1/2" FLGD RF:ANSI B16-5 600# ANSI B16-10

BODY : ASTM A350 LF2, CL1 /

ASTM A 352 Gr. LCB

DISC / RING : (ASTM A350 LF2,

CL1 / ASTM A 352 Gr. LCB) + 13%

CR. STEEL FACING

STEM : 13% CR. STEEL (NO

CASTING)

HANDWHEEL FIRE SAFE

VGL 2" - 4" FLGD RF:ANSI B16-5 600# ANSI B16-10

BODY : ASTM A350 LF2, CL1 /

ASTM A 352 Gr. LCB

DISC / RING : (ASTM A350 LF2,

CL1 / ASTM A 352 Gr. LCB) + 13%

CR. STEEL FACING

STEM : 13% CR. STEEL (NO

CASTING)

HANDWHEEL FIRE SAFE

VGL 8" FLGD RF:ANSI B16-5 600# ANSI B16-10

BODY : ASTM A350 LF2, CL1 /

ASTM A 352 Gr. LCB

DISC / RING : (ASTM A350 LF2,

CL1 / ASTM A 352 Gr. LCB) + 13%

CR. STEEL FACING

STEM : 13% CR. STEEL (NO

CASTING)

GEAR OPERATED FIRE SAFE

SWING CHECK VCH 2"- 8'' FLGD RF:ANSI B16-5 600# ANSI B16-10

BODY : ASTM A350 LF2, CL1 /

ASTM A 352 Gr. LCB

HINGE PIN : 13% CR. STEEL (NO

CASTING)

DISC / RING : ASTM A350 LF2,

CL1 / ASTM A 352 Gr. LCB)

+ 13% CR. STEEL FACING

HORIZONTAL INSTALLATION

VERTICAL INSTALLATION FLOW

UPWARDS

NOTE 3 :

PUP PIECES SHALL BE PROVIDED FOR BUTT WELDED VALVES AS PER THE DATASHEET. MINIMUM THICKNESS OF PUP PIPECE SHALL BE DETERMINED

BY VENDOR AS PER THE REQUIREMENTS OF ASME B 31.8, FIG I-5 FOR WELDING TO VALVE DESIGNED AS PER ASME B 16.34. THE THICKNESS

CALCULATIONS SHALL BE APPROVED BY CLIENT. THE PIPE END OF THE PUP PIECE SHALL MATCH THE THE MATING PIPE.THE MATING PIPE DETAILS

SHALL BE TAKEN AS MENTIONED IN THE PIPE SECTION OF THIS PMS.

8" NB Pipeline from Haridwar to Dehradun

6 C1 - PMS for Piping

Rev. 0 Supply of Pig Launcher / Receiver 4 of 6Page 58 of 78

PIPING SPECIFICATION

6C1

DOC. NO :

P.013313 D 11076 101

SHEET 5 OF 6

REV. 0

SMALL SIZE

1/2"3/4" 1" 1.1/2" 2" 3" 4" 6" 8" 10" 12" 14" 16" 18" 20"

1/2"

3/4" X

1" X X

L 1.1/2" X X X

A 2" X X X

R 3" X X

G 4" X X X

E 6" X X

8" X X

S 10" X X X

I 12" X X X

z 14" X X X X

E 16" X X X X

18" X X X X

20" X X X X

24" X X X

LEGEND

X : CONCENTRIC AND ECCENTRIC REDUCERS- BW

REDUCERS CHART

8" NB Pipeline from Haridwar to Dehradun

6 C1 - PMS for Piping

Rev. 0 Supply of Pig Launcher / Receiver 5 of 6Page 59 of 78

BRANCH SIZE

1/2" 3/4" 1" 1.1/2" 2" 3" 4" 6" 8" 10" 12" 14" 16" 18" 20" 24"

1/2" T

3/4" TR T

1" TR TR T

H 1.1/2" W TR TR T

E 2" W W TR TR T

A 3" W W W TR TR T

D 4" W W W W TR TR T

E 6" W W W W W TR TR T

R 8" W W W W W BW* TR TR T

10" W W W W W BW* BW* TR TR T

S 12" W W W W W BW* BW* BW* TR TR T

I 14" W W W W W BW* BW* BW* BW* TR TR T

Z 16" W W W W W BW* BW* BW* BW* BW* TR TR T

E 18" W W W W W BW* BW* BW* BW* BW* BW* TR TR T

20" W W W W W BW* BW* BW* BW* BW* BW* BW* TR TR T

24" W W W W W BW* BW* BW* BW* BW* BW* BW* BW* TR TR T

LEGEND

T : TEE EQUAL-BW

TR : REDUCING TEE-BW (FLOW TEE WHEREVER INDICATED SHALL BE PROVIDED)

W : WELDOLET- BW

BW : BRANCH WELD-CHECK IF REINFORCING PLATE IS NECESSARY ACCORDING ANSI B 31.8 (See Note)

6C1

DOC. NO :

P.013313 D 11076 101

SHEET 6 OF 6

REV. 0

BRANCH CHART

*NOTE : IN PLACE OF BRANCH -WELD, EXTRUDED TEE, CONFORMING TO ASME B 16.9 SPECIFICATION,

MAY BE USED, SUBJECT TO AVAILABILITY

8" NB Pipeline from Haridwar to Dehradun

6 C1 - PMS for Piping

PIPING SPECIFICATION

Rev. 0 Supply of Pig Launcher / Receiver 6 of 6Page 60 of 78

PIPING SPECIFICATION

1C1

DOC. NO :

P.013313 D 11076 102

SHEET 1 OF 6

PRIMARY FLANGE RATING 150#-RF LTCS - 45 to 65 LTCS 19.00

BASIC MATERIALLTCS (See Note A)

CORROSION ALLOWANCE 2.0 mm

Temperature

(Deg.C)

Pressure

bar (g)

° C bar (g)

X-RAYS 100% -29 19.65

0 19.65

PIPE SIZE RANGE 1/2"- 8" 38 19.65

93 17.93

CODE ASME B 31.8

0 23.04.2019 MK NC AR

REV DATE PREPARED CHECKED APPROVEDDESCRIPTION

Issued for Procurement

Note :

A. Material for 1/2" to 8" Station Piping shall be ASTM A 333, Grade 6 (LTCS). LTCS Material shall be Charpy Impact Tested at (-45 °C).

8" NB Pipeline from Haridwar to Dehradun

BASIC PIPING SPECIFICATION DATASPRESSURE bar g

Temperature & Pressure

Rating

MAXIMUM DESIGN CONDITIONS

TEMPERATURE ° C

FLUIDS

AG : ACTUATING GAS

NG : NATURAL GAS

Rev. 0 Supply of Pig Launcher / Receiver 1 of 6Page 61 of 78

PIPING SPECIFICATION

1C1

DOC. NO :

P.013313 D 11076 102

SHEET 2 OF 6

REV. 0

ITEM SHORT SIZE END RATING DIMENSION MATERIAL REMARKS

CODE FROM- CONNECTION AND/OR STANDARD

THRU SCH/THK

PIPES P 1/2" - 1 1/2" PE-ANSI B16-25 160 ANSI B 36-10 ASTM A333 GR 6 SEAMLESS (LTCS)

2" BE-ANSI B16-25 160 ANSI B 36-10 ASTM A333 GR 6 SEAMLESS (LTCS)

3" - 8" BE-ANSI B16-25 40 ANSI B 36-10 ASTM A333 GR 6 SEAMLESS (LTCS)

ELBOWS 90 LR E 1/2"- 1 1/2" BW - ANSI B16-25 SEE PIPE ANSI B16-9 ASTM A350 LF2 CL1 SMLS

(See Note 1) 2"- 8" BW - ANSI B16-25 SEE PIPE ANSI B16-9 ASTM A420 WPL 6 SMLS

ELBOWS 45 LR E45 1/2"- 1 1/2" BW - ANSI B16-25 SEE PIPE ANSI B16-9 ASTM A350 LF2 CL1 SMLS

(See Note 1) 2"- 8" BW - ANSI B16-25 SEE PIPE ANSI B16-9 ASTM A420 WPL 6 SMLS

REDUCERS RC 1/2"- 1 1/2" BW - ANSI B16-25 SEE PIPE ANSI B16-9 ASTM A350 LF2 CL1 SMLS

CONCENTRIC

(See Note 1)2"- 8" BW - ANSI B16-25 SEE PIPE ANSI B16-9 ASTM A420 WPL 6 SMLS

REDUCERS RE 1/2"- 1 1/2" BW - ANSI B16-25 SEE PIPE ANSI B16-9 ASTM A350 LF2 CL1 SMLS

ECCENTRIC

(See Note 1)2"- 8" BW - ANSI B16-25 SEE PIPE ANSI B16-9 ASTM A420 WPL 6 SMLS

TEES EQUAL T 1/2"- 1 1/2" BW - ANSI B16-25 SEE PIPE ANSI B16-9 ASTM A350 LF2 CL1 SMLS

(See Note 1) 2"- 8" BW - ANSI B16-25 SEE PIPE ANSI B16-9 ASTM A420 WPL 6 SMLS

TEES RED TR1/2"- 1 1/2"

BW - ANSI B16-25 SEE PIPE ANSI B16-9 ASTM A350 LF2 CL1

(See Note 1)2"- 8"

BW - ANSI B16-25 SEE PIPE ANSI B16-9 ASTM A420 WPL 6

WELDOLETS

(See Note 1)WEL

1 1/2"- 8''BW - ANSI B16-25 SEE PIPE MSS-SP-97 ASTM A350 LF2 CL1

For Branch Size of Weldolet, Please

refer to the Chart given in Sheet 6 of this

Document.

CAPS

(See Note 1) C 1/2"- 8" BW - ANSI B16-25 SEE PIPE ANSI B16-9 ASTM A420 WPL 6

NBEP 1/2" - 1 1/2" BOTH ENDS PLAIN 160 ANSI B36-10 ASTM A333 GR 6 SEAMLESS-LG=100mm

NOET 1/2" - 1 1/2" ONE END THRD-MNPT 160 ANSI B36-10 ASTM A333 GR 6 SEAMLESS-LG=100mm

NBET 1/2" - 1 1/2"BOTH ENDS THRD-

MNPT160 ANSI B36-10 ASTM A333 GR 6 SEAMLESS-LG=100mm

FULL CF 1/2" - 1 1/2" FNPT 3000# ANSI B16-11 ASTM A350 LF2 CL1

COUPLINGS ANSI B1-20-1

THRD

CAPS C2 1/2" - 1 1/2" FNPT 3000# ANSI B16-11 ASTM A350 LF2 CL1

THRD ANSI B1-20-1

PLUGS PL 1/2" - 1 1/2" MNPT 3000# ANSI B16-11 ASTM A350 LF2 CL1

THRD ANSI B1-20-1

SMLS

For Branch Size, Please refer to the

Chart given in Sheet 6 of this Document.

NOTE 1 :

WALL THICKNESS FOR TEES, ELBOWS, REDUCERS AND CAPS SHALL BE DETERMINED BY VENDOR AS PER THE REQUIREMENTS OF ASME B 16.9 § 2.3.

MINIMUM THICKNESS OF TEE SHALL ALSO MEET THE REQUIREMENTS OF ASME B 31.8, APPENDIX -F FOR BRANCH OPENING. FURTHER, MINIMUM

THICKNESS OF TEES, ELBOWS, REDUCERS AND CAPS SHALL NOT BE LESS THAN THAT OF MATING PIPE. ALL WALL THICKNESS CALCULATIONS

SHALL BE APPROVED BY OWNER. THE MATING PIPE DETAILS SHALL BE TAKEN AS MENTIONED IN THE PIPE SECTION OF THIS PMS.

NIPPLES

8" NB Pipeline from Haridwar to Dehradun

Rev. 0 Supply of Pig Launcher / Receiver 2 of 6Page 62 of 78

PIPING SPECIFICATION

1C1DOC. NO :

P.013313 D 11076 102

SHEET 3 OF 6

REV. 0

ITEM SHORT SIZE END RATING DIMENSION MATERIAL REMARKS

CODE FROM- CONNECTION AND/OR STANDARD

THRU SCHED.

F 1/2"- 2" BW - ANSI B16-25150# WNRF, TO MATCH

SCH 160 PIPEANSI B16-5 ASTM A350 LF2 CL1

3"- 8" BW - ANSI B16-25150# WNRF, TO MATCH SCH 40 PIPEANSI B16-5 ASTM A350 LF2 CL1

ORIFICE COMPLETE WITH GASKET

FLANGES STUD BOLTS, NUTS

BLIND COMPLETE WITH GASKET

FLANGES STUD BOLTS, NUTS

SPECTACLE

BLINDS

(See Note 2)

RESTRICTION

ORIFICES

STUD BOLTS: ASTM

A320 GR. L7

HEXAGONAL NUTS :

ASTM A194 GR 4

GASKETS G All Sizes WINDING

SPIRAL AISI 304,

WOUND FILLING

PURE GRAPHITE.

CENTERING RING

cs

ASTM A240 GR 304

1/2"- 8"

1" - 8" 150# RF ANSI B16.48

ANSI B16-36 ASTM A350 LF2 CL1

ASTM A350 LF2 CL1ANSI B16-5150# RF

NOTE 2 :

BORE OF FLANGE SHALL MATCH INSIDE DIA OF MATING PIPE. THE MATING PIPE DETAILS SHALL BE TAKEN AS MENTIONED IN THE PIPE SECTION OF THIS

PMS.

8" NB Pipeline from Haridwar to Dehradun

ALWAYS TO BE WELDED ON 1C1

PIPE

ASME B 18.2.1 &

ASME B 18.2.2

1" - 8"

ASTM A350 LF2 CL1

WN FLANGES

See Note 2

STUD BOLTS B All Sizes 150 # RF

FO 150# RF

1" - 8"

150# RF ASME B 16.20

SB

RO

FB

150# RF ANSI B16-5

Rev. 0 Supply of Pig Launcher / Receiver 3 of 6Page 63 of 78

PIPING SPECIFICATION

1C1

DOC. NO :

P.013313 D 11076 102

SHEET 4 OF 6

REV. 0

ITEM SHORT SIZE END RATING DIMENSION MATERIAL REMARKS

CODE FROM- CONNECTION AND/OR STANDARD

THRU SCHED.

BALL VBA 1/2" - 1 1/2" FLGD RF:ANSI B16-5 150# ANSI B16-10

VALVES

(See Note 3)WRENCH OPERATED.

2" - 4" FLGD RF:ANSI B16-5 150 # ANSI B16-10

or BW: ANSI B16-25

WRENCH OPERATED.

6"- 8'' FLGD RF:ANSI B16-5 150# ANSI B16-10DOUBLE BLOCK AND BLEED

FULL BORE

or BW :ANSI B16.25 FIRE SAFE

GEAR OPERATED -

MANUAL / ACTUATED - AS

INDICATED IN DATA SHEET

GLOBE VGL 1/2"-1 1/2" FLGD RF:ANSI B16-5 150# ANSI B16-10

BODY : ASTM A350 LF 2 /

ASTM A 352 Gr. LCBHANDWHEEL

VALVES FIRE SAFE

STEM : 13% CR. STEEL (NO

CASTING)

2" - 4" FLGD RF:ANSI B16-5 150# ANSI B16-10

BODY : ASTM A350 LF 2 /

ASTM A 352 Gr. LCB HANDWHEEL

FIRE SAFE

STEM : 13% CR. STEEL (NO

CASTING)

6" - 8" FLGD RF:ANSI B16-5 150# ANSI B16-10

BODY : ASTM A350 LF 2 /

ASTM A 352 Gr. LCB GEAR OPERATED

FIRE SAFE

STEM : 13% CR. STEEL (NO

CASTING)

SWING CHECK VCH 1/2" - 1 1/2" FLGD RF:ANSI B16-5 150# ANSI B16-10

BODY : ASTM A350 LF 2 /

ASTM A 352 Gr. LCB HORIZONTAL INSTALLATION

VALVES

HINGE PIN : 13% CR. STEEL

(NO CASTING)

2"- 8'' FLGD RF:ANSI B16-5 150# ANSI B16-10

BODY : ASTM A350 LF 2 /

ASTM A 352 Gr. LCBHORIZONTAL INSTALLATION

HINGE PIN : 13% CR. STEEL

(NO CASTING)

8" NB Pipeline from Haridwar to Dehradun

BALL : (ASTM A350 LF 2 /

ASTM A 352 Gr. LCB ) + ENP

OR ASTM A182 Gr. F316

BODY : ASTM A350 LF 2 /

ASTM A 352 Gr. LCB

BALL : (ASTM A350 LF 2 /

ASTM A 352 Gr. LCB ) + ENP

OR ASTM A182 Gr. F316

BODY : ASTM A350 LF 2 /

ASTM A 352 Gr. LCB

BALL : (ASTM A350 LF 2 /

ASTM A 352 Gr. LCB ) + ENP

OR ASTM A182 Gr. F316

NOTE 3 :

PUP PIECES SHALL BE PROVIDED FOR BUTT WELDED VALVES AS PER THE DATASHEET. MINIMUM THICKNESS OF PUP PIPECE SHALL BE DETERMINED

BY VENDOR AS PER THE REQUIREMENTS OF ASME B 31.8, FIG I-5 FOR WELDING TO VALVE DESIGNED AS PER ASME B 16.34. THE THICKNESS

CALCULATIONS SHALL BE APPROVED BY CLIENT. THE PIPE END OF THE PUP PIECE SHALL MATCH THE THE MATING PIPE.THE MATING PIPE DETAILS

SHALL BE TAKEN AS MENTIONED IN THE PIPE SECTION OF THIS PMS.

DISC / RING : (ASTM A350 LF

2 / ASTM A 352 Gr. LCB) + 13%

CR. STEEL FACING

DISC / RING : (ASTM A350 LF

2 / ASTM A 352 Gr. LCB) + 13%

CR. STEEL FACING

BODY : ASTM A350 LF 2 /

ASTM A 352 Gr. LCB

DISC / RING : (ASTM A350 LF

2 / ASTM A 352 Gr. LCB)

+ 13% CR. STEEL FACING

DISC / RING : (ASTM A350 LF

2 / ASTM A 352 Gr. LCB) + 13%

CR. STEEL FACING

VERTICAL INSTALLATION FLOW

UPWARDS

VERTICAL INSTALLATION FLOW

UPWARDS

DISC / RING : (ASTM A350 LF

2 / ASTM A 352 Gr. LCB)

+ 13% CR. STEEL FACING

Rev. 0 Supply of Pig Launcher / Receiver 4 of 6Page 64 of 78

PIPING SPECIFICATION

1C1

DOC. NO :

P.013313 D 11076 102

SHEET 5 OF 6

REV. 0

SMALL SIZE

1/2"3/4" 1" 1.1/2" 2" 3" 4" 6" 8" 10" 12" 14" 16" 18" 20"

1/2"

3/4" X

1" X X

L 1.1/2" X X X

A 2" X X X

R 3" X X

G 4" X X X

E 6" X X

8" X X

S 10" X X X

I 12" X X X

z 14" X X X X

E 16" X X X X

18" X X X X

20" X X X X

24" X X X

LEGEND

X : CONCENTRIC AND ECCENTRIC REDUCERS- BW

REDUCERS CHART

8" NB Pipeline from Haridwar to Dehradun

Rev. 0 Supply of Pig Launcher / Receiver 5 of 6Page 65 of 78

PIPING SPECIFICATION

1C1

DOC. NO :

P.013313 D 11076 102

SHEET 6 OF 6

REV. 0

BRANCH SIZE

1/2" 3/4" 1" 1.1/2" 2" 3" 4" 6" 8" 10" 12" 14" 16" 18" 20" 24"

1/2" T

3/4" TR T

1" TR TR T

H 1.1/2" W TR TR T

E 2" W W TR TR T

A 3" W W W TR TR T

D 4" W W W W TR TR T

E 6" W W W W W TR TR T

R 8" W W W W W BW TR TR T

10" W W W W W BW BW TR TR T

S 12" W W W W W BW BW BW TR TR T

I 14" W W W W W BW BW BW BW TR TR T

Z 16" W W W W W BW BW BW BW BW TR TR T

E 18" W W W W W BW BW BW BW BW BW TR TR T

20" W W W W W BW BW BW BW BW BW BW TR TR T

24" W W W W W BW BW BW BW BW BW BW BW TR TR T

LEGEND

T : TEE EQUAL-BW

TR : REDUCING TEE-BW (BARRED TEE WHEREVER INDICATED SHALL BE PROVIDED)

W : WELDOLET- BW

BW : BRANCH WELD-CHECK IF REINFORCING PLATE IS NECESSARY ACCORDING ANSI B 31.8

NOTE : IN PLACE OF BRANCH -WELD, EXTRUDED TEE, CONFORMING TO ASME B 16.9 SPECIFICATION,

MAY BE USED, SUBJECT TO AVAILABILITY

BRANCH CHART

8" NB Pipeline from Haridwar to Dehradun

Rev. 0 Supply of Pig Launcher / Receiver 6 of 6Page 66 of 78

PAINTING P.013313

D 11077

111

HARIDWAR-RISHIKESH-DEHRADUN PIPELINE

(HRDPL) PROJECT

TRACTEBEL ENGINEERING PVT. LTD.

PTS - PAINTING

0 23.04.02019 Issued for Procurement MK MS AR

Rev. Date Subject of Revision Prepared By Checked By Approved By

Page 67 of 78

PAINTING P.013313

D 11077

111

Rev. 0 Supply of Pig Launcher / Receiver Page 1 of 1

TABLE OF CONTENTS

1.0 INTRODUCTION ................................................................................................................... 1

2.0 DEFINITIONS ....................................................................................................................... 1

3.0 COLOUR CODE SYSTEM ........................................................................................................ 1

Page 68 of 78

PAINTING P.013313

D 11077

111

Rev. 0 Supply of Pig Launcher / Receiver Page 1 of 3

1.0 INTRODUCTION

This Document (PTS - Particular Technical Specification for Painting) lists the Specification for the

project.

This present document covers the technical specification for the procurement of Painting used in high

pressure natural gas transmission systems. It describes the general requirements, controls, tests,

QA/QC examination and final acceptance criteria which need to be fulfilled.

In case of any conflict of Specification, PTS will supersede General Technical specification (GTS)

and Data sheet will supersede PTS.

2.0 DEFINITIONS

Client / Owner Shall mean GAIL (I) Limited

Manufacturer Means the Manufacturer of the Insulating Joint.

Contractor The party which carries out all or part of Engineering, Procurement,

Construction, Pre-commissioning & Commissioning of the project.

It shall mean Pipe laying contractor in the present context.

Third Party Inspection

Agency (TPIA)

Means the Inspection Agency to be appointed by the Pipe laying

contractor

Consultant / Owner

Representative

Shall means TRACTEBEL Engineering Pvt. Limited / The entity of

the purchaser or the company nominated by the purchaser to design

the natural gas transport or distribution system and to specify the

equipment

PTS Means the present <<Particular Technical Specification P.013313 D

11077 111>>and its entire appendix, if any.

3.0 COLOUR CODE SYSTEM

The colour codes for final layer of Station Pipe Work & Metering Shed shall be as under:

S. No. DESCRIPTION FINAL LAYER

COLOUR SHADE

RAL CODE

1 Pipe Work Yellow RAL 1004

2 Piping Support Grey RAL 7043

3 Hand Rail Grey RAL 7043

4 Gas O/L Actuator Blue RAL 5015

5 Valve Handle/Wheel Black RAL 9005

6 All Valves Grey RAL 7038

7 IJ Grey RAL 7038

Page 69 of 78

PAINTING P.013313

D 11077

111

Rev. 0 Supply of Pig Launcher / Receiver Page 2 of 3

S. No. DESCRIPTION FINAL LAYER

COLOUR SHADE

RAL CODE

8 Filter Grey RAL 7038

9 Pig launcher &

Receiver Grey RAL 7038

10 Bolts & Nuts Grey RAL 7038

11 Grating Hot Galvanized

12 Metering Station Shed

12.1 Steel Frame Beige RAL 1018

12.2 Roof / Vertical Shed Grey RAL 7030

12.3 Control Panel Grey RAL 7032

The recommended painting system should be of Category C5 – I Very high (Industrial) as specified in the Standard ISO

12944 Part 1 to 8. The proposed Painting system shall conform to Table A5 of ISO 12944 – 5 Standard.

Page 70 of 78

PAINTING P.013313

D 11077

111

Rev. 0 Supply of Pig Launcher / Receiver Page 3 of 3

∑ ∑ ∑

Page 71 of 78

Rev.: 0

Prepared : MK

ManufacturerThird Party Inspection

Agency(by EPC)Control Authority

3 ASME Section IX ASME Section IX Cert. 3.2 P 100%W 100%R

4 ASME V Art. 7ASME Section VIII Div. I,

APP. VICert. 3.2 P 100%W W/R

5 ASME V Art. 6ASME Section VIII Div. I,

APP. VIIICert. 3.2 P 100%W W/R

6 ASME V Art. 6ASME Section VIII Div. I,

APP. VIIICert. 3.2 P 100%W 100%R

10 Data Sheet Data Sheet Cert. 3.2 P 100%W 100%W

11As per Pipeline Design Basis

( P.008776 M61 0151)Cl. No. 7.1 Cert. 3.2 P 100%W 100%W

13 Data Sheet Data Sheet P 100%R 100%R

LEGEND:

RT:Radiographic test PT:Liquid penetrant test MT:Magnetic particle test

P:Performed R:Review W:Witness

TPIA: Third Party Inspection Agency ; Control Authority : Owner/Engineer or their Authorised Inspection Agency.

Note:

2 The supplier shall submit their own detailed QAP prepared on the basis of the above for approval of Owner/Owner's representative and TPIA.

4

5

6

7

8

9

10

11

API 5L /ASTM A 370

100%

Acceptance Criteria Document Type

ASME V, Art. 2

ASTM A-370 Cert. 3.2

API 5L/ASTM E350

API 5L/ASTM A 3701 per heat on samples taken from

millAPI 5L/ASTM A 370

Cert. 3.2

Cert. 3.2

1 per heat API 5L/ASTM E350

All bought out items including Quick opening closure shall be provided with EN 10204 3.2 certificates.

QAP No: P.013313 D 11013 110

Date: 23.04.2019

Approved : NC

100%W

100%R

100%R

Supplier shall submit Calibration certificates of all Instruments/Equipment to be used for Inspection and Testing to TPIA with relavant procedures and updated standards for TPIA reveiew/Approval.

QUALITY ASSURANCE PLAN

PIG LAUNCHER

Applicable

Standard/Document

100%R

100%

Sn Activity Extent of Check

1. Chemical analysis P

Scope of Inspection

W/R

7 X - Ray Exam. All butt joints P 100%W

100%

2 Mechanical properties P 100%W

ASME VIII-UW 51

9

Heat Treatment (Start & Stop temp. Chart

shall be signed by TPIA, also Power

failure log shall be maintained).

P 100%W

Hydrostatic test

8 Low temperature certificate(Impact test) P 100%WASME B 31.3/323

12 Dimensional & Visual Check P 100%W

HT: Heat Treatment VT: Visual Test

WPS: Welding Procedure Specification PQR: Procedure qualification Record WQT: Welder Qualification Test

Cert. 3.2API 5L/ ASME B 31.3

TPIA along with Owner/Owner's representative shall review/approve all the documents related to QAP/Quality manuals/Drawings etc.submitted by supplier.

Supplier in coordination with Sub vendor shall issue detailed Production and Inspection schedule indicating the dates and the locations to facilitate Owner/Owner's representative and TPIA to organise Inspection.

100%W

Drawing & Calculation approval

1 The Above Testing and acceptance critera are minimum requirements, however, equipment supplier shall ensure that the product also comply to the additional requirements as per Technical specifications and data sheets.

3

100% ASME V, Art. 9

1 per heat

1 per furnace charge

100%

TPIA will have Right to Inspect minimum 10% of all manufacturing activities on each day or as specified above.

W/R

Painting 100%

Cert. 3.2

Cert. 3.2ASTM A-370

For All Forging Materials, The Specimen Shall Be Taken From The Integral Part of The Forging.

In case of conflict between purchase specification, contract documents and QAP, more stringent conditions shall be applicable.

Certification requirements shall comply with European Standard EN 10204:3.2(latest edition)

Checked : RP

Quick Opening Closure shall be ASME "U" stamped.

100%

Qualified Welding Procedures (WPS,

PQR,WQT)

UT/Magnetic Test on weld and Butt

welding ends/bevels

UT of shell area under RF pass

PT on fillet welds (Pressure parts and

barrel supports)

Rev. 0 Supply of Pig Launcher / Receiver Page 1 of 1

Page 72 of 78

Date: 23.043.2019 Revision: 0

Prepared : GG

Checked : RP

Approved : AR

PTS

Clause No. ManufacturerTPIA

(By Manufacturer / Contractor)Control Authority

0

- list of operation in manufacturing and control 9.1 specification procedures Perform review point review point

- Fabrication and Control procedure 9.1 specification procedures Perform review point review point

2.7 specification procedures Perform review point review point

9.1; 2 and 3 specification procedures Perform review point review point

9.2 ; 2 specification procedures Perform review point review point

2, 4, 5, 6 & 7 specification procedures Perform review point review point

6 specification procedures Perform review point review point

As per Appl PTS specification procedures Perform review point review point

1 BASE MATERIAL

1.1 MATERIALS

5.1.1 1 per heat PTS certif. 3.2 Perform hold point review report

5.1.2 1 per heat Mat. Spec. certif. 3.2 Perform hold point review report

1.2 CHEMICAL COMPOSITION review report

3.10 1 per heat PTS-Table1+ ASTM & Mat. Spec. Lab certificate Perform review report review report

2 FABRICATION & TESTS 4

- report Perform hold point review report

- Review of welders records report Perform hold point review report

- Cosumable Verification ASME SEC IX / SEC IIC PTS & ASME Sec-IX & Sec-II report Perform review point

2.2 4.3 all fittings T/T Graph PTS certif. 3.2 PerformWitness Point

(Loading & Unloading)review report

- time temperature chart 4.3.1 1 per furnace charge report Perform review report review report

- micrographic examination 4.3.2 1 per lot* ASTM E 112 Grain size : range 8 to 12 certif. 3.2 Perform hold point review report

ACTIVITY

CONTROL BEFORE MANUFACTURING

- material part list

PTS & ASME Sec-IX

- painting procedure

Tensile tests (YS, UTS, YS/UTS, %EL, RA, Bend etc. as applicable)

(remark : marking transfer by TPIA)

Charpy-test at as per Mat. Spec. (Impact Energy & Shear Area)

(remark : marking transfer by TPIA)

- Design Proof test

Check chemical analysis & Carbon Equivalent

ASME SEC IX

Welding

Review of WPS (If New WPS has established, same to be

witnessed by TPIA) 4.1 & 4.2

2.1

Applicable standard &

ProcedureAcceptance criteria

Heat treatment (Loading & Unloading shall be witnessed by TPIA,

Power failure log shall be maintained)

S NO.

- heat treatment procedure

- non destructive testing procedures

- dimensional drawings

QUALITY CONTROL TABLE

FITTINGS

Scope of Inspection

QCT No. : P.013313 D 11013 140

Frequency Document type

Rev.0 Supply of Pig Launcher / Receiver Page 1 of 3

Page 73 of 78

Date: 23.043.2019 Revision: 0

Prepared : GG

Checked : RP

Approved : AR

PTS

Clause No. ManufacturerTPIA

(By Manufacturer / Contractor)Control Authority

ACTIVITYApplicable standard &

ProcedureAcceptance criteriaS NO.

QUALITY CONTROL TABLE

FITTINGS

Scope of Inspection

QCT No. : P.013313 D 11013 140

Frequency Document type

2.3

-

- base material 1 per lot PTS + E/R <= 0.85 & Mat. Spec.

- weld 1 per lot PTS & Mat. Spec.

-

- base material (Longitudinal & Transverse)2 sets of 3 specimens per

lot

- weld (Transverse)1 sets of 3 specimens per

lot

- HAZ (Transverse)1 sets of 3 specimens per

lot

- Flattening test for fitting < 2" 5.1.3 1 per group (*) PTS PTS & Mat. Spec.

2.4 5.2 For each lot ASTM & PTS Cl 3.10.1 & 3.10. 2 PTS & Mat. Spec. certif. 3.2 Perform review report review report

3 NON DESTRUCTIVE EXAMINATIONS (NDE) 5.3

Longitudinal welds : ASME section

VIII division 1 UW 51

Girth welds : API 1104 section 6.0

3.2 Ultrasonic inspection

- base material thickness ≥ 6 mm6.1.2.1, 6.1.2.2,

6.1.2.4 & 6.1.3.3100% ASME section V art 23, SA-388 ASME section VIII division1 UF-55

- weld6.1.2.1, 6.1.2.2 &

6.1.3.3100% ASME V

ASME section VIII division1,

appendix 12

3.3 - Magnetic particle inspection6.1.2.1, 6.1.2.4,

6.1.3.2 & 6.1.3.5100% ASME V

ASME section VIII division1,

appendix 6certif. 3.2 Perform witness point review report

3.4 - After machining

- Magnetic particle or liquid penetrant of the bevels 6.1.2.4 & 6.1.3.5 wall thickness ≥ 6 mm all

finished bevelsASME V PTS & Mat. Spec.

- Ultrasonic inspection of 25 mm of base material (if t ≥ 6 mm)6.1.2.1, 6.1.2.2,

6.1.2.4 & 6.1.3.3All finished bevels ASME V PTS & Mat. Spec.

3.5 - Visual examination 6.1.2.3 & 6.1.3.1 100% PTS & Mat. Spec. certif. 3.2 Perform hold point review report

10% NPS ≤ 6"

100% NPS > 6"

Impact test for fitting ≥ 2"

ASTM A 370

3.1 6.1.1 and 6.1.3.4 All butt welds ASME section V witness point review reportPerform

Mechanical testing

(remark : marking transfer by TPIA)

- For CS at -20°C Energy is

35J/cm²(Avg.), 28J/cm²(Ind.)

- For LTCS at -20°C Energy is

35J/cm²(Avg.), 28J/cm²(Ind.)

and Material Standard’s impact test

temperature requirements or -450C,

Whichever is lower.

4.2.4 & 5.1.2

4.2.4 & 5.1.1

hold point review reportcertif. 3.2 Perform

- Dimensionnal examination Perform

certif. 3.2 witness point review report

3.6 certif. 3.2

Chemical analysis & Carbon Equivalent

Radiographic examination certif. 3.2

Perform

Perform

Tension test for fitting ≥ 2" (YS, UTS, YS/UTS, %EL, RA, Bend

etc. as applicable)

review report

ISO 148 - Charpy V - Notch

certif. 3.2 witness point

PTS & Mat. Spec.6.1.2.5 witness point review report

Rev.0 Supply of Pig Launcher / Receiver Page 2 of 3

Page 74 of 78

Date: 23.043.2019 Revision: 0

Prepared : GG

Checked : RP

Approved : AR

PTS

Clause No. ManufacturerTPIA

(By Manufacturer / Contractor)Control Authority

ACTIVITYApplicable standard &

ProcedureAcceptance criteriaS NO.

QUALITY CONTROL TABLE

FITTINGS

Scope of Inspection

QCT No. : P.013313 D 11013 140

Frequency Document type

4 FINAL INSPECTION TEST

4.1 Marking - all PTS & P.O. certif. 3.2 Perform witness point reiew report

4.2 - all PTS & P.O. certif. 3.2 Perform hold point reiew report

4.3 7 all PTS

Protection suitable for 6 months,

Easily removable by wire brushing or

by grinding. Not produce toxic

vapour or smoke when heated

report Perform random witness point reiew report

4.4 Final Documentation (CMTR) 6.2, 6.3 & 6.4 all PTS & P.O. CMTR, 3.2 certificates, IRN etc. certif. 3.2 Perform hold point review report

LEGEND:

(*) Fittings from the same heat of steel of the same shape and the same main pipe/plate dimension of the fittings

LOT - A lot consists of all fittings from one heat of steel with same initial wall thickness, from the same furnace charge for final heat treatment, from the same shape and the same main pipe/plate dimension.

RT : Radiographic test PT : Liquid penetrant test MT : Magnetic particle test HT : Heat treatment VT : Visual test P : Performed

R : Review W : Witness TPIA : Third Party Inspection Agency; Control Authority : Owner / Owner's representatives

Hold point = No further steps may be undertaken before the intervention of the appointed responsible takes place.

Witness point = The appointed responsible has to be notified of the operation in advance, but production will continue whether the intervention took place or not.

Note: 1

2 The supplier shall submit their own detailed QAP prepared on the basis of the above for approval of Owner/Owner's representative and TPIA for each sizes.

3

4

5

6

7

8

9

10 In case of conflict between purchase specification, contract documents and QAP, more stringent conditions shall be applicable.

Heat treatment start and stop temperature chart shall be witnessed & signed by TPIA. Power failure log book / sheet shall be maintained

For All Forging Materials, The Specimen Shall Be Taken From The Integral Part of The Forging.

Corosion Protection paint

The Above Testing and acceptance critera are minimum requirements, however, equipment supplier shall ensure that the product also comply to the additional requirements as per Technical specifications and data sheets.

Certification requirements shall comply with European Standard EN 10204 (latest edition)- 3.2 Type.

TPIA along with Owner/Owner representative shall review/approve all the documents related to QAP/Quality manuals/Drawings etc.submitted by supplier.

Contractor shall in coordination with Sub vendor shall issue detailed Production and Inspection schedule indicating the dates and the locations to facilitate Owner/Owner's representative and TPIA to organise Inspection.

Inspector's stamp

Supplier shall submit Calibration certificates of all Instruments/Equipment to be used for Inspection and Testing to TPIA with relavant procedures and updated standards for TPIA reveiew/Approval.

TPIA will have Right to Inspect minimum 10% of all manufacturing activities on each day or as specified above.

Rev.0 Supply of Pig Launcher / Receiver Page 3 of 3

Page 75 of 78

Date: 23.04.2019 Revision: 0

Prepared : GG

Checked : RP

Approved : AR

PTS

chap. ManufacturerTPIA

(By Manufacturer /

Contractor)

Control Authority

0

9.1 1 per purchase order specification procedure Perform review point review point

- Fabrication and Control procedure 9.1 specification procedure Perform review point review point

9.1, 2 and 3 specification procedure Perform review point review point

9.2, 2 specification procedure Perform review point review point

2, 4, 5, 6 & 7 specification procedure Perform review point review point

6 specification procedure Perform review point review point

As per PTS specification procedure Perform review point review point

1 BASE MATERIAL

5.1.1 1 per lot* PTS / Mat. Spec. certif. 3.2 Perform hold point review report

5.1.21 per lot* (1 set of 3

specimen per temp. range)PTS / Mat. Spec. certif. 3.2 Perform hold point review report

CHEMICAL COMPOSITION

Check chemical analysis 3.10 1 per heat PTS-Table1 Perform review report review report

2 FABRICATION AND TESTS

2.1. 4.3 all fittings T/T Graph PTS certif. 3.2 PerformWitness Point

(Loading & Unloading)review report

- time temperature chart 4.3.1 1 per furnace charge T/T Graph PTS report Perform review report review report

- micrographic examination 4.3.2 1 per lot* ASTM E 112 Grain size : range 8 to 12 certif. 3.2 Perform hold point review report

2.2. certif. 3.2 Perform hold point review report

S.No.

- material part list

1.2

1.1

Applied standard e/o

ProcedureAcceptance criteria

Tensile tests (YS, UTS, YS/UTS, %EL, RA, Bend etc.

as applicable)

- non destructive testing procedures

- list of operation in manufacturing and control

Charpy Impact test at temp. as per Mat. Spec.

- painting procedure

QUALITY CONTROL TABLE

FLANGES

CONTROL BEFORE MANUFACTURING

Document type

- dimensional drawings

ACTIVITY

- heat treatment procedure

Mechanical tests

(remark : marking transfer by TPIA)

Frequency

Mechanical tests

(remark : marking transfer by TPIA)

Heat treatment (Loading & Unloading shall be

witnessed by TPIA, Power failure log shall be

maintained)

Scope of Inspection

QCT No. : P.013313 D 11013 141

Rev.0 Supply of Pig Launcher / Receiver Page 1 of 3Page 76 of 78

Date: 23.04.2019 Revision: 0

Prepared : GG

Checked : RP

Approved : AR

PTS

chap. ManufacturerTPIA

(By Manufacturer /

Contractor)

Control AuthorityS.No.

Applied standard e/o

ProcedureAcceptance criteria

QUALITY CONTROL TABLE

FLANGES

Document typeACTIVITY Frequency

Scope of Inspection

QCT No. : P.013313 D 11013 141

2.2.1 - 4.2.4 & 5.1.11 sample per lot of HT per

Raw material Heat

ASTM A 350 § 6.1.3 +

E/R <= 0.85 / PTSPTS & Mat. Spec. certif. 3.2 Perform hold point review report

2.2.2 - 4.2.4 & 5.1.22 sets of 3 specimens per lot

of HT per RM Heat

ISO 148 - Charpy V-

Notch

- For CS at -200C Energy is

35J/cm²(Avg.), 28J/cm²(Ind.)

- For LTCS at -200C Energy is

35J/cm²(Avg.), 28J/cm²(Ind.)

and Material Standard’s impact test

temperature requirements or -450C,

Whichever is lower.

certif. 3.2 Perform hold point review report

3 NON DESTRUCTIVE EXAMINATIONS (NDE)

3.1 Radiographic examination 6.1.1 and 6.1.3.4 All butt welds ASME Section-V Girth welds : API 1104 section 6.0 certif. 3.2 Perform witness point review report

3.2 Ultrasonic inspection6.1.2.1, 6.1.2.2,

6.1.2.4 & 6.1.3.3100%

ASME Section-V, Art-23,

SA-388ASME section VIII division1 UF-55 certif. 3.2 Perform witness point review report

3.3 Magnetic particle inspection6.1.2.1, 6.1.2.4,

6.1.3.2 & 6.1.3.5100% ASME Section-V

ASME section VIII division1

appendix 6certif. 3.2 Perform witness point review report

After machining

- 6.1.2.4 & 6.1.3.5 all finished bevels ASME Section-V PTS § 5.3.3.5. certif. 3.2 Perform witness point review report

-6.1.2.1, 6.1.2.2,

6.1.2.4 & 6.1.3.3

wall thickness ≥ 6 mm all

finished bevelsASME Section-V PTS § 5.3.3.5. certif. 3.2 Perform witness point review report

3.5 6.1.2.3 & 6.1.3.1 100% PTS certif. 3.2 Perform hold point review report

10% NPS ≤ 6"

100% NPS > 6"3.6

Charpy Impact test for flanges (Longitudinal &

Transverse)

PTS

Tension test for flanges (YS, UTS, YS/UTS,

%EL, RA, Bend etc. as applicable)

Performcertif. 3.2 witness point review reportDimensionnal examination 6.1.2.5

Magnetic particle or liquid penetrant of the

bevels

Ultrasonic inspection of 25 mm of base material

Visual examination

3.4

Rev.0 Supply of Pig Launcher / Receiver Page 2 of 3Page 77 of 78

Date: 23.04.2019 Revision: 0

Prepared : GG

Checked : RP

Approved : AR

PTS

chap. ManufacturerTPIA

(By Manufacturer /

Contractor)

Control AuthorityS.No.

Applied standard e/o

ProcedureAcceptance criteria

QUALITY CONTROL TABLE

FLANGES

Document typeACTIVITY Frequency

Scope of Inspection

QCT No. : P.013313 D 11013 141

4 FINAL INSPECTION TEST

4.1 - all PTS & P.O. certif. 3.2 Perform witness point reiew report

4.2 - all PTS & P.O. certif. 3.2 Perform hold point reiew report

4.3 7 all PTS

Protection suitable for 6 months,

Easily removable by wire brushing

or by grinding. Not produce toxic

vapour or smoke when heated

report Perform random witness point reiew report

4.4 Final Documentation (CMTR) 6.2, 6.3 & 6.4 all PTS & P.O. CMTR, 3.2 certificates, IRN etc. certif. 3.2 Perform hold point review report

LEGEND:

(*) Fittings from the same heat of steel of the same shape and the same main pipe/plate dimension of the fittings.

LOT - A lot consists of all fittings from one heat of steel with same initial wall thickness, from the same furnace charge for final heat treatment, from the same shape and the same main pipe/plate dimension.

RT : Radiographic test PT : Liquid penetrant test MT : Magnetic particle test HT : Heat treatment VT : Visual test P : Performed

R : Review W : Witness TPIA : Third Party Inspection Agency; Control Authority : Owner / Owner's representatives

Hold point = No further steps may be undertaken before the intervention of the appointed responsible takes place.

Witness point = The appointed responsible has to be notified of the operation in advance, but production will continue whether the intervention took place or not.

Note: 1

2

3

4

5

6

7

8

9

10

11

Certification requirements shall comply with European Standard EN 10204 (latest edition).

In case of conflict between purchase specification, contract documents and QAP, more stringent conditions shall be applicable.

Marking

Inspector's stamp

Corosion Protection paint

Heat treatment start and stop temperature chart shall be witnessed & signed by TPIA. Power failure log book / sheet shall be maintained.

For All Forging Materials, The Specimen Shall Be Taken From The Integral Part of The Forging.

The supplier shall submit their own detailed QAP prepared on the basis of the above for approval of Owner/Owner's representative and TPIA, for each size. Impact test at -20 deg C shall be conducted in addition to respective material requirement.

Certification requirements shall comply with European Standard EN 10204 (latest edition)-3.2 issued by TPIA and Vendor.

The Above Testing and acceptance critera are minimum requirements, however, equipment supplier shall ensure that the product also comply to the additional requirements as per Technical specifications and data sheets.

Supplier shall submit Calibration certificates of all Instruments/Equipment to be used for Inspection and Testing to TPIA with relavant procedures and updated standards for TPIA reveiew/Approval.

TPIA will have Right to Inspect minimum 10% of all manufacturing activities on each day or as specified above. Owner reserves the right to inspect any quantity of item at any time during execution.

TPIA along with Owner/Owner representative shall review/approve all the documents related to QAP/Quality manuals/Drawings etc.submitted by supplier.

Contractor shall in coordination with Sub vendor shall issue detailed Production and Inspection schedule indicating the dates and the locations to facilitate Owner/Owner's representative and TPIA to organise Inspection.

Rev.0 Supply of Pig Launcher / Receiver Page 3 of 3Page 78 of 78

At the helm of the Energy Transition, Tractebel provides a full range of engineering and advisory servicesthroughout the life cycle of its clients’ projects, including design and project management. As one of the world’sleading engineering and advisory companies and with more than 150 years of experience, it's our mission toactively shape the world of tomorrow. With about 5,000 experts and presence in more than 70 countries, we areable to offer our customers multidisciplinary solutions in energy, water and urban.

TRACTEBEL ENGINEERING PVT. LTD.Intec House 37Institutional Area, Sector 44122 002 - Gurgaon - INDIAtractebel-engie.com

Antik ROYtel. + 91 124 471 2260fax + 91 124 469 [email protected]