Quality Rating = {(Quantity Accepted *100) / Quantity Supplied}
Delivery Rating = 100/{1+(1.5*Actual Time For Delivery / Given Time For Delivery)*(Required
G = Given Time
A = Actual Time
S.no.PO. No. PO. Date Supplier Name
Delivery Date
Specified Actual1 4039 04/04/2011 Crescent Paper's 10/04/2011 03/05/2011
6 4044 05/04/2011 Crescent Paper's 10/04/2011 23/04/2011
10 4048 18/04/2011 Crescent Paper's 25/04/2011 09/05/2011
13 4251 21/04/2011 Crescent Paper's 26/04/2011 03/05/2011
21 4259 09/05/2011 Crescent Paper's 15/05/2011
23 4261 14/05/2011 Crescent Paper's 22/05/2011 20/05/2011
26 4264 14/05/2011 Crescent Paper's 22/05/2011 16/05/2011
27 4265 21/05/2011 Crescent Paper's 26/05/2011
2 4040 04/04/2011 Asian Paper Industries 15/04/2011 12/04/2011
7 4045 05/04/2011 Asian Paper Industries 07/04/2011 20/04/2011
16 4254 25/04/2011 Asian Paper Industries 27/04/2011 02/05/2011
18 4256 27/04/2011 Asian Paper Industries 29/04/2011 10/05/2011
19 4257 02/05/2011 Asian Paper Industries 15/05/2011 10/05/2011
20 4258 05/05/2011 Asian Paper Industries 10/05/2011 23/05/2011
3 4041 05/04/2011 Nikita Paper's 09/04/2011 23/04/2011
5 4043 05/04/2011 Nikita Paper's 10/04/2011 19/04/2011
9 4047 11/04/2011 Nikita Paper's 16/04/2011 16/05/2011
12 4050 19/04/2011 Nikita Paper's 20/04/2011 03/05/2011
14 4252 21/04/2011 Nikita Paper's 27/04/2011 20/05/2011
15 4253 23/04/2011 Nikita Paper's 29/04/2011 09/05/2011
17 4255 27/04/2011 Nikita Paper's 02/05/2011 09/05/201124 4262 14/05/2011 Nikita Paper's 20/05/2011
25 4263 14/05/2011 Nikita Paper's 20/05/2011
28 4266 24/05/2011 Nikita Paper's 30/05/2011
29 4267 28/05/2011 Nikita Paper's 10/06/2011
4 4042 05/04/2011 Dev Handmade Paper 09/04/2011 19/04/2011
8 4046 09/04/2011 Dev Handmade Paper 14/04/2011 20/05/2011
11 4049 18/04/2011 Dev Handmade Paper 26/04/2011 20/05/2011
22 4260 10/05/2011 Dev Handmade Paper 15/05/2011
8/6/2019 Supplier Evaluation Hand Paper Apr-2011-12
http://slidepdf.com/reader/full/supplier-evaluation-hand-paper-apr-2011-12 2/7
Supplier Evaluation
Rev. 0 (1/8/06)
Quantity - Delivered Quantity In Time)/Required Quantity)}
R = Required Quantity In Given Time
D = Delivered Quantity In Given Time
QuantityG A R D
Ordered Actual Accepted4800 4835 4835
3000 1250 1250
3800 3456 3456
3000 3360 3226
9300
32300 8804 8730
3800 3780 3780
6100
50 80 80
30 30 30
55 52 52
50 38 38
200 37 37
154 45 45
2400 3440 3440
12400 10213 10125
4200 4167 4167
5900 6113 5947
6500 8974 8885
2200 2364 2356
7500 5203 520320900
10100
10000
12200
2000 2330 2330
3500 3522 3522
2500 2995 2905
3500
Quality
Rating
8/6/2019 Supplier Evaluation Hand Paper Apr-2011-12
http://slidepdf.com/reader/full/supplier-evaluation-hand-paper-apr-2011-12 3/7
Delivery
Rating
Total
Rating
8/6/2019 Supplier Evaluation Hand Paper Apr-2011-12
http://slidepdf.com/reader/full/supplier-evaluation-hand-paper-apr-2011-12 4/7
Supplie
Rev.
Quality Rating = {(Quantity Accepted *100) / Quantity Supplied}
Delivery Rating = 100/{1+(1.5*Actual Time For Delivery / Given Time For Delivery)*(Required Quantity -
G = Given Time
A = Actual Time
S.no.PO. No. PO. Date Supplier Name
Delivery Date
Specified Actual Ordered1 4151 02/04/2011 Rajasthan Lining House 12/04/2011 12/04/2011 5000
2 4152 02/04/2011 Earth Enterprises 15/04/2011 09/05/2011 50
38 4196 25/05/2011 Earth Enterprises 05/06/2011 105
3 4153 04/04/2011 Saras Creations 08/04/2011 05/04/2011 100
13 4164 12/04/2011 Saras Creations 18/04/2011 15/04/2011 400
27 4182 07/05/2011 Saras Creations 15/05/2011 10/05/2011 2000
42 4201 27/05/2011 Saras Creations 12/06/2011 1000
4 4154 05/04/2011 V.L.Sales 10/04/2011 12/04/2011 40
12 4163 12/04/2011 V.L.Sales 18/04/2011 18/04/2011 635
16 4168 21/04/2011 V.L.Sales 25/04/2011 26/04/2011 260
23 4178 02/05/2011 V.L.Sales 10/05/2011 10/05/2011 525
26 4181 05/05/2011 V.L.Sales 10/05/2011 10/05/2011 470
29 4184 10/05/2011 V.L.Sales 15/05/2011 11/05/2011 27
33 4190 16/05/2011 V.L.Sales 20/05/2011 470
41 4200 26/05/2011 V.L.Sales 31/05/2011 600
21 4176 30/04/2011 Om Dye Chem Industries 05/05/2011 03/05/2011 75
25 4180 03/05/2011 Om Dye Chem Industries 10/05/2011 07/05/2011 870
36 4194 23/05/2011 Om Dye Chem Industries 28/05/2011 50
43 4202 27/05/2011 Om Dye Chem Industries 28/05/2011 12
5 4155 06/04/2011 Abhinandan Packers & Movers 10/04/2011 07/04/2011 100
28 4183 09/05/2011 Abhinandan Packers & Movers 15/05/2011 10/05/2011 112
31 4187 12/05/2011 Abhinandan Packers & Movers 16/05/2011 13
37 4195 23/05/2011 Abhinandan Packers & Movers 28/05/2011 123
6 4156 09/04/2011 Roopsi Trading Company 16/04/2011 16/04/2011 15
19 4172 22/04/2011 Roopsi Trading Company 28/04/2011 27/04/2011 10
7 4157 11/04/2011 M.L.Industries 20/04/2011 25/04/2011 13000
17 4169 21/04/2011 M.L.Industries 05/05/2011 07/05/2011 37000
32 4189 14/05/2011 M.L.Industries 20/05/2011 439 4197 25/05/2011 M.L.Industries 30/05/2011 30002
8 4158 11/04/2011 Moin Dye Chem 15/04/2011 16/04/2011 50
9 4159 12/04/2011 S.M.Dye Chem 18/04/2011 16/04/2011 440
10 4160 12/04/2011 Rishi Industries 18/04/2011 16/04/2011 210
11 4161 12/04/2011 Shree Shyam Polymer 18/04/2011 16/04/2011 200
30 4186 12/05/2011 Shree Shyam Polymer 15/05/2011 13/05/2011 200
34 4191 16/05/2011 Shree Shyam Polymer 20/05/2011 200
40 4199 26/05/2011 Shree Shyam Polymer 29/05/2011 200
14 4166 16/04/2011 Govind Traders 20/04/2011 23/04/2011 100
8/6/2019 Supplier Evaluation Hand Paper Apr-2011-12
http://slidepdf.com/reader/full/supplier-evaluation-hand-paper-apr-2011-12 5/7
15 4167 16/04/2011 S.B.Traders 20/04/2011 16/04/2011 2
22 4177 02/05/2011 S.B.Traders 05/05/2011 04/05/2011 42
24 4179 03/05/2011 S.B.Traders 10/05/2011 07/05/2011 114
18 4170 21/04/2011 Shivi Enterprises Pvt. Ltd. 22/04/2011 21/04/2011 300
20 4174 27/04/2011 Shivi Enterprises Pvt. Ltd. 05/05/2011 03/05/2011 2500
35 4192 18/05/2011 Anu Sales 24/05/2011 200
44 4203 28/05/2011 The SNTF Corporation 02/06/2011 200
8/6/2019 Supplier Evaluation Hand Paper Apr-2011-12
http://slidepdf.com/reader/full/supplier-evaluation-hand-paper-apr-2011-12 6/7
r Evaluation
0 (1/8/06)
Delivered Quantity In Time)/Required Quantity)}
R = Required Quantity In Given Time
D = Delivered Quantity In Given Time
QuantityG A R D
Actual Accepted5000 5000
50 50
104.8 104.8
400 400
1900 1900
40 40
629.24 629.24
260 260
516.2 516.2
470 470
26.22 26.22
75 75
870 870
100 100
112 112
14.8 14.8
10 10
12750 12750
37500 37500
50 50
440 440
210 210
200 200
200 200
100 100
Quality
Rating
Delivery
Rating
Total
Rating