LEGEND GIZA, FAYOUM & RAVEN FLDS DEV. Subsea Field Development The project involves EPC and installation of a subsea infrastructure from 12 wells, with 49 miles of umbilicals and 136 miles of pipelines. CHISSONGA FPSO FPSO Project officially delayed due to low oil prices. Contractors have been asked to revise bids down by 20%. MARINER EAST 2 PIPELINE Onshore Pipeline Mariner East 2 is the 2 nd phase of the company’s plan to transport 275,000 b/d of various NGLs from processing and fractionation complexes to Sunoco Logistics’ MHIC. SOUTH SANTA CRUZ/BARATARIA Subsea Field Development The project consists in the development of ~23 km of pipe-in- pipe flowline. Installation of flowline end terminations, fabrication and installation of jumpers; and pre-commissioning for the flowline. ~$2650M EPC On Hold 5000002 FIND NEW BUSINESS OPPORTUNITIES IN THE INDUSTRIAL WORLD. CONTACT [email protected] FOR MORE INFO BP ~$750M EPCI Feb’16 To Be Awarded Subsea 7 Sunoco ~$2.5B EPC Feb’16 Fluor n.a. EPCI Feb’16 Technip Awarded On Hold Cancelled Contract value Award date Engineering Co./ EPC Contractor (Country of Execution) Contract type Clients SupplHi Project ID 4000202 RHOURDE-NOUSS LPG PLANT Upstream Onshore Conventional The contract includes the EPC, commissioning and testing of hardware and software for the plant. ABB will revamp the treatment and fractionation unit that was damaged in 2009. ~$100M EPC Feb’16 1000238 7000121 4000204 1000231 11000327 11000293 BALTIC GAS PROJ. Upstream Onshore Conventional FID is expected by year end 2016. The project consists in two small offshore developments connected to an onshore gas plant (for which Jacobs is executing pre-FEED studies). Baltic Gas ~$10M pre-FEED Feb’16 Jacobs SUMGAYIT E/PE PLANT Petrochemical The project includes EPC activities up to start up and guarantee test run. The plant will rely on the Ineos Innovene S technology with a capacity of 120,000 t/y. SOCAR ~$180M EPC Feb’16 Maire Tecnimont Group BOROUGE NEW BOG COMP. Petrochemical The SOW includes EPC services for a new Boil Off Gas (BOG) compressor project at the plant. It will also entail a number of tie-ins to the existing facility. Borouge n.a. EPC Feb’16 Linde Engineering FORTUNA OFFSHORE FLD. FLNG Subsea Field Development FID reported on track by mid-2016, first gas is expected in 2019. The proposed development involves the initial drilling of up to 7 development wells to be tied back to the FLSO vessel. ~$350M EPC Jul’16 To Be Awarded 4000163 TAKREER RUWAIS REFINERY Refining The project consists in improving efficiency at the GUP to enhance power generation and water production, while reducing adverse environmental impacts. FAHUD-SOHAR GAS PIPELINE Onshore Pipeline Dual pipeline 14 inches and 32 inches. Pipelines to feed the Liwa Plastics Complex and the North Power Station respectively. The pipelines are expected to be completed within 38 months. SAUDI KAYAN CRACKING FURNACE Petrochemical The project should boost ethylene production capacity of the plant in Jubail. Completion is expected in the second half of 2017. Saudi Kayan ~$95M EPC Feb’16 ORPIC ~$304M EPC Feb’16 Punj Lloyd TAKREER ~$20M FEED Feb’16 Jacobs 10000399 7000150 11000329 JAMBARAN-TIUNG BIRU FLD. DEV. Upstream Onshore Conventional Expected to start construction before the end of next year so that Pertamina can meet its target of going on-stream in 2019. Pertamina ~$1.4B EPC May'16 1000053 To be awarded UPDATES ON KEY OIL&GAS PROJECT STATUS FROM PREVIOUS MONTH, FEBRUARY ‘16 SUPPLHI PROJECTS DATABASE PLAJU REFINERY Refining State-owned Pertamina has cancelled the Plaju project with Chinese state-owned Sinope. Once completed, the expansion would have doubled the current capacity of 118000 b/d. Pertamina Sinopec ~$3B EPC Cancelled To be awarded 10000409 DOUGLAS CHANNEL LNG LNG Onshore Liquefaction AltaGas Inc., partner in the Douglas Channel LNG plant, announced the decision to cancel the project that had an expected in-service date in late 2017. AltaGas ~$500M EPC Cancelled n.a. 6000034 ÅSGARD OFFSHORE FLD LPW Subsea Field Development Statoil awarded Aker Solutions for a concept study for the LPW (Low Pressure Well) project at Åsgard A to sustain future production. Statoil ~$10M pre-FEED Feb’16 Aker Solutions 4000211 TRESTAKK FLD SUBSEA TIEBACK Subsea Field Development The field will be developed as a tieback to Asgard FPSO. FEED to be executed in Oslo office, in cooperation with Technip and FMC Technologies (in fact, Forsys is a Technip/FMC JV) Statoil n.a. FEED Feb’16 4000206 OSEBERG VESTFLANKEN 2 WHP Offshore Shallow Water The project will provide 110M BOE and is profitable even in a low oil price scenario. The SOW consists of the construction, transportation and installation of the unmanned platform. Statoil ~$97M EPCI Feb’16 3000266 PROJECTS DB SAMPLE FREE MARKET REPORT, Jan ‘16

Transcript of SupplHi Projects Database Main Updates - February

Page 1: SupplHi Projects Database Main Updates - February

LEGEND

GIZA, FAYOUM & RAVEN FLDS DEV.Subsea Field DevelopmentThe project involves EPC and installation of a subsea

infrastructure from 12 wells, with 49 miles of umbilicals and

136 miles of pipelines.

CHISSONGA FPSOFPSO Project officially delayed due to low oil prices. Contractors have

been asked to revise bids down by 20%.

MARINER EAST 2 PIPELINEOnshore PipelineMariner East 2 is the 2nd phase of the company’s plan to

transport 275,000 b/d of various NGLs from processing and

fractionation complexes to Sunoco Logistics’ MHIC.

SOUTH SANTA CRUZ/BARATARIASubsea Field DevelopmentThe project consists in the development of ~23 km of pipe-in-

pipe flowline. Installation of flowline end terminations, fabrication and

installation of jumpers; and pre-commissioning for the flowline.

Maersk ~$2650M

EPC On Hold

5000002

FIND NEW BUSINESS OPPORTUNITIES IN THE INDUSTRIAL WORLD. CONTACT [email protected] FOR MORE INFO

BP ~$750M

EPCI Feb’16To Be Awarded Subsea 7

Sunoco ~$2.5B

EPC Feb’16

Fluor

Deep Gulf Energy II n.a.

EPCI Feb’16

Technip

Awarded On Hold Cancelled

Contract value

Award date

Engineering Co./

EPC Contractor(Country of Execution)Contract type

Clients

SupplHi Project ID

4000202

RHOURDE-NOUSS LPG PLANTUpstream Onshore ConventionalThe contract includes the EPC, commissioning and testing of

hardware and software for the plant. ABB will revamp the

treatment and fractionation unit that was damaged in 2009.

Sonatrach ~$100M

EPC Feb’16

1000238

7000121

4000204

ABB

1000231 11000327 11000293

BALTIC GAS PROJ.Upstream Onshore ConventionalFID is expected by year end 2016. The project consists in two

small offshore developments connected to an onshore gas

plant (for which Jacobs is executing pre-FEED studies).

Baltic Gas ~$10M

pre-FEED Feb’16Jacobs

SUMGAYIT E/PE PLANTPetrochemicalThe project includes EPC activities up to start up and

guarantee test run. The plant will rely on the Ineos Innovene S

technology with a capacity of 120,000 t/y.

SOCAR ~$180M

EPC Feb’16

Maire Tecnimont

Group

BOROUGE NEW BOG COMP.PetrochemicalThe SOW includes EPC services for a new Boil Off Gas (BOG)

compressor project at the plant. It will also entail a number of

tie-ins to the existing facility.

Borouge n.a.

EPC Feb’16

Linde Engineering

FORTUNA OFFSHORE FLD. FLNG Subsea Field DevelopmentFID reported on track by mid-2016, first gas is expected in

2019. The proposed development involves the initial drilling of

up to 7 development wells to be tied back to the FLSO vessel.

Ophir Energy ~$350M

EPC Jul’16

To Be Awarded

4000163

TAKREER RUWAIS REFINERYRefiningThe project consists in improving efficiency at the GUP to

enhance power generation and water production, while

reducing adverse environmental impacts.

FAHUD-SOHAR GAS PIPELINE Onshore PipelineDual pipeline 14 inches and 32 inches. Pipelines to feed the

Liwa Plastics Complex and the North Power Station respectively. The

pipelines are expected to be completed within 38 months.

SAUDI KAYAN CRACKING FURNACEPetrochemicalThe project should boost ethylene production capacity of the

plant in Jubail. Completion is expected in the second half of

2017.

Saudi Kayan ~$95M

EPC Feb’16

CTCI

ORPIC ~$304M

EPC Feb’16

Punj Lloyd

TAKREER ~$20M

FEED Feb’16

Jacobs

10000399

7000150

11000329

JAMBARAN-TIUNG BIRU FLD. DEV.Upstream Onshore ConventionalExpected to start construction before the end of next year so

that Pertamina can meet its target of going on-stream in 2019.

Pertamina ~$1.4B

EPC May'16

1000053

To be awarded

UPDATES ON KEY OIL&GAS PROJECT STATUS FROM PREVIOUS MONTH, FEBRUARY ‘16SUPPLHI PROJECTS DATABASE

PLAJU REFINERYRefiningState-owned Pertamina has cancelled the Plaju project with

Chinese state-owned Sinope. Once completed, the expansion

would have doubled the current capacity of 118000 b/d.

Pertamina

Sinopec ~$3B

EPC CancelledTo be awarded

10000409

DOUGLAS CHANNEL LNGLNG Onshore LiquefactionAltaGas Inc., partner in the Douglas Channel LNG plant,

announced the decision to cancel the project that had an

expected in-service date in late 2017.

AltaGas ~$500M

EPC Cancelled

n.a.

6000034

ÅSGARD OFFSHORE FLD LPWSubsea Field DevelopmentStatoil awarded Aker Solutions for a concept study for the LPW

(Low Pressure Well) project at Åsgard A to sustain future

production.

Statoil ~$10M

pre-FEED Feb’16

Aker Solutions

4000211

TRESTAKK FLD SUBSEA TIEBACK Subsea Field DevelopmentThe field will be developed as a tieback to Asgard FPSO. FEED

to be executed in Oslo office, in cooperation with Technip and

FMC Technologies (in fact, Forsys is a Technip/FMC JV)

Statoil n.a.

FEED Feb’16

Forsys Subsea

4000206

OSEBERG VESTFLANKEN 2 WHPOffshore Shallow WaterThe project will provide 110M BOE and is profitable even in a

low oil price scenario. The SOW consists of the construction,

transportation and installation of the unmanned platform.

Statoil ~$97M

EPCI Feb’16

Heerema Marine

Contractors

3000266