WATERPROOFING SPECIFICATIONS AND METHODOLOGIES PODIUM SLAB 101 Concrete Waterproofing and Durability Enhancement Using Supershield DPC Crystalline Technology www.supershieldglobal.com PODIUM SLAB - PREREQUISITE FOR SUPERSHIELD WATERPROOFING TREATMENT l The PODIUM SLAB that is to be treated should be minimum 7 days old. l The pipe penetrations through the horizontal brick walls should be packed and plastered to a minimum thickness of 25 mm with the ratio of 1:3 cement mortar. l The side walls that are of non-concrete should be plastered to a minimum thickness of 25 mm with the ratio of 1:3 cement mortar to a height of minimum 6" above the nearest floor level. SUPERSHIELD SPECIFICATION AND APPLICATION METHODOLOGY Provide, mix and brush apply two coats of SUPERSHIELD CRYSTALGUARD, single compound Deep Penetrating Capillary (DPC) waterproofing system that generates a non-soluble crystalline formation of dendritic fibers within the pores and capillary tracts of the concrete @ 1.5 Kg/m² for two coats on the PODIUM SLAB and to the adjacent curb wall that are of concrete to the height of 6" above the filling level. Provide, mix and brush apply two coats of SUPERSHIELD FLEXI, two component material that forms seamless flexible membrane @ 1.5 ² on the side walls to height of 6" above the filling level. The coating should overlap a minimum 1” over the crystalline coating at the junction. Concrete Substrate Non concrete substrate with plastering Kg/m TWO COATS OF CRYSTALGUARD @ 1.5 Kg/m² PODIUM SLAB - 101 Page 1 of 3 SUPERSHIELD CRYSTALGUARD FIRST COATING SUPERSHIELD CRYSTALGUARD SECOND COATING PODIUM SLAB COVING SUPERSHIELD FLEXI FIRST COAT SUPERSHIELD FLEXI SECOND COAT

Transcript of SUPERSHIELD FLEXI FIRST COAT SUPERSHIELD FLEXI SECOND … · A) Manufacturer : Manufacturer should...

Page 1: SUPERSHIELD FLEXI FIRST COAT SUPERSHIELD FLEXI SECOND … · A) Manufacturer : Manufacturer should publish a third party product quality assurance certificate from a notified body

WATERPROOFING SPECIFICATIONS AND METHODOLOGIES

PODIUM SLAB 101

Concrete Waterproofing and Durability Enhancement Using Supershield DPC Crystalline Technology

www.supershieldglobal.com

PODIUM SLAB - PREREQUISITE FOR SUPERSHIELD WATERPROOFING TREATMENT

l The PODIUM SLAB that is to be treated should be minimum 7 days old.

l The pipe penetrations through the horizontal brick walls should be packed and plastered to a minimum

thickness of 25 mm with the ratio of 1:3 cement mortar.

l The side walls that are of non-concrete should be plastered to a minimum thickness of 25 mm with the ratio

of 1:3 cement mortar to a height of minimum 6" above the nearest floor level.

SUPERSHIELD SPECIFICATION AND APPLICATION METHODOLOGY

Provide, mix and brush apply two coats of SUPERSHIELD CRYSTALGUARD, single compound Deep Penetrating

Capillary (DPC) waterproofing system that generates a non-soluble crystalline formation of dendritic fibers within

the pores and capillary tracts of the concrete @ 1.5 Kg/m² for two coats on the PODIUM SLAB and to the adjacent

curb wall that are of concrete to the height of 6" above the filling level.

Provide, mix and brush apply two coats of SUPERSHIELD FLEXI, two component material that forms seamless

flexible membrane @ 1.5 ² on the side walls to height of 6" above the filling level. The coating should

overlap a minimum 1” over the crystalline coating at the junction.

Concrete Substrate

Non concrete substrate with plastering

Kg/m

TWO COATS OF CRYSTALGUARD @ 1.5 Kg/m²

PODIUM SLAB - 101 Page 1 of 3

SUPERSHIELD CRYSTALGUARD FIRST COATING

SUPERSHIELD CRYSTALGUARD SECOND COATING

PODIUM SLAB

COVING

SUPERSHIELD FLEXI FIRST COAT

SUPERSHIELD FLEXI SECOND COAT

Page 2: SUPERSHIELD FLEXI FIRST COAT SUPERSHIELD FLEXI SECOND … · A) Manufacturer : Manufacturer should publish a third party product quality assurance certificate from a notified body

Application Methodology

Curing

Watch Points

Performance Criteria

1) Surface preparation - The concrete substrate that is to be applied with SUPERSHIELD CRYSTALGUARD must

be free from foreign materials and to be micro cleaned by mechanical means like wire brushing or vacuum

cleaning.

2) Pre-wetting - Concrete surface must be thoroughly saturated with clean water prior to the coating to ensure

moisture presence inside the pores and capillaries and remove any excess water and ensure surface is touch dry

while coating.

3) Mixing of CRYSTALGUARD - Mix SUPERSHIELD CRYSTALGUARD powder with clean water to form a slurry

consistency with 5 parts of powder and 2 parts of water.

4) Application of CRYSTALGUARD - Apply the first coat of SUPERSHIELD CRYSTALGUARD as a slurry

consistency on the concrete surface.

5) Second coat of CRYSTALGUARD - Apply the second coat of SUPERSHIELD CRYSTALGUARD as a slurry

consistency on first coat after a minimum of 4 hours gap.

Continue with the SUPERSHIELD FLEXI membrane coating on the non-concrete substrate after 8 hours of

crystalline coating.

6) Mixing of FLEXI - Mix SUPERSHIELD FLEXI A component (Powder) with SUPERSHIELD FLEXI B

Component (Liquid) as per the pre-measured packaging.

7) Application of FLEXI - Apply the first coat of SUPERSHIELD FLEXI as a slurry consistency on the non-

concrete plastered side walls, overlapping the crystalline coating for 2" at the junction.

8) Second coat FLEXI - Apply the second coat of SUPERSHIELD FLEXI as a slurry consistency on the first coat

after a minimum of 4 hours gap.

l The SUPERSHIELD CRYSTALGUARD coating should be cured with a misty fog spray of clean water, 24 hours

after the application and to be kept moist for minimum 3 days.

l The SUPERSHIELD FLEXI should be air cured for minimum 3 days and protected from water/ rain for

minimum 18 hours.

Cracks, horizontal, vertical joint sealing, tie hole, pipe penetrations, construction joints, expansion joints and

other defects in the concrete that is to be waterproofed should be treated as per the SUPERSHIELD specification

and application methodology.

Crystalline waterproofing system should meet or exceed the performance requirements as specified herein.

l Crystalline Penetration : Crystallizing capability of waterproofing material shall be evidenced by

www.supershieldglobal.com

WATERPROOFING SPECIFICATIONS AND METHODOLOGIES

PODIUM SLAB - 101 Page 2 of 3

PODIUM SLAB 101

Concrete Waterproofing and Durability Enhancement Using Supershield DPC Crystalline Technology

TWO COATS OF CRYSTALGUARD @ 1.5 Kg/m²

Page 3: SUPERSHIELD FLEXI FIRST COAT SUPERSHIELD FLEXI SECOND … · A) Manufacturer : Manufacturer should publish a third party product quality assurance certificate from a notified body

independent SEM (Scanning Electron Microscope) photographs documenting penetration of needle like

crystal formation deep within concrete.

l Self-healing capability and permeability resistance : Independent testing performed according to U.S. Army

Corps of Engineers CRD-C48-73 "Permeability of Concrete".

l Testing on the effectiveness of coating from negative side of concrete : Independent testing that

demonstrates the capability of the coating to seal the leakage/dampness from negative side.

l Resistance to chloride ion penetration : Independent testing performed according to ASTM C 1202-03

should exhibit a resistance of 100% better than that of the untreated specimen.

l Potable Water Approval : Independent testing shall be performed according to EN or NSF Standard 61, and

approval for use of waterproofing material on structures holding potable water shall be evidenced.

A) Manufacturer : Manufacturer should publish a third party product quality assurance certificate from a notified

body with continuous surveillance audit or CE certificate with FPC (Factory Production Control) as per the

harmonized standard EN to prove that the facility from where the material is produced for the project has

undergone the required testing and extensive inspection and is under continuous surveillance by a notified body

appointed by the European union as per the European norms for the system. Manufacturers who cannot provide

the performance test data specified herein and FPC certificate shall not be considered for the project.

B) Applicator : Waterproofing applicator shall be experienced in the installation of cementitious crystalline

waterproofing materials and shall be approved by the manufacturer in writing.

A) Manufacturer's Warranty : Manufacturer shall provide standard product warranty executed by authorised

company official.

B) Applicator's Warranty : Applicator shall warrant the waterproofing installation against defects caused by

faulty workmanship or materials for a period of (specify term) years from Date of Substantial Completion. The

warranty will cover the surfaces treated and will bind the applicator to repair, at his expense, any and all leaks

through the treated surfaces which are not due to structural weaknesses or other causes beyond applicator's

control such as fire, earthquake and cyclone.

Product data sheets, Application guidelines, Material safety data sheet, CE certificate, Summary of test Reports.

Quality Assurance

Warranty

Submittals

www.supershieldglobal.com

WATERPROOFING SPECIFICATIONS AND METHODOLOGIES

PODIUM SLAB - 101 Page 3 of 3

PODIUM SLAB 101

Concrete Waterproofing and Durability Enhancement Using Supershield DPC Crystalline Technology

TWO COATS OF CRYSTALGUARD @ 1.5 Kg/m²

Page 4: SUPERSHIELD FLEXI FIRST COAT SUPERSHIELD FLEXI SECOND … · A) Manufacturer : Manufacturer should publish a third party product quality assurance certificate from a notified body

www.supershieldglobal.com

PODIUM SLAB - PREREQUISITE FOR SUPERSHIELD WATERPROOFING TREATMENT

Provide, mix and brush apply two coats of SUPERSHIELD FLEXI, two component material that forms seamless

flexible membrane @ 1.5 Kg/m² on the side walls to the height of 6" above the filling level. The coating should

overlap a minimum 1” over the crystalline coating at the junction.

l The PODIUM SLAB that is to be treated should be minimum 7 days old.

l The pipe penetrations through the horizontal brick walls should be packed and plastered to a minimum

thickness of 25 mm with the ratio of 1:3 cement mortar.

l The side walls that are of non-concrete should be plastered to a minimum thickness of 25 mm with the ratio

of 1:3 cement mortar to a height of minimum 6" above the nearest floor level.

SUPERSHIELD SPECIFICATION AND APPLICATION METHODOLOGY

Provide, mix and brush apply one coat of SUPERSHIELD CRYSTALGUARD, single compound Deep Penetrating

Capillary (DPC) waterproofing system @ 0.75 Kg/m² and one coat of SUPERSHIELD CRYSTALGUARD ULTIMA,

single compound highly concentrated crystalline coating as a top coat that forms hard surface finish @ 0.75

Kg/m² on the PODIUM SLAB and to the curb wall that are of concrete to the height of 6" above the filling level

that generates a non-soluble crystalline formation of dendritic fibers within the pores and capillary tracts of the

concrete with hard surface finish.

Concrete Substrate

Non concrete substrate with plastering

WATERPROOFING SPECIFICATIONS AND METHODOLOGIES

PODIUM SLAB 102 2ONE COAT OF CRYSTALGUARD AND ONE COAT OF CRYSTALGUARD ULTIMA @ 1.5 Kg/m

Concrete Waterproofing and Durability Enhancement Using Supershield DPC Crystalline Technology

PODIUM SLAB - 102 Page 1 of 3

SUPERSHIELD CRYSTALGUARD COATING

SUPERSHIELD CRYSTALGUARDULTIMA COATING

PODIUM SLAB

COVING

SUPERSHIELD FLEXI FIRST COAT

SUPERSHIELD FLEXI SECOND COAT

Page 5: SUPERSHIELD FLEXI FIRST COAT SUPERSHIELD FLEXI SECOND … · A) Manufacturer : Manufacturer should publish a third party product quality assurance certificate from a notified body

Application Methodology

Curing

Watch Points

1) Surface preparation - The concrete substrate that is to be applied with SUPERSHIELD CRYSTALGUARD

/ULTIMA must be free from foreign materials and to be micro cleaned by mechanical means like wire brushing or

vacuum cleaning.

2) Pre-wetting - Concrete surface must be thoroughly saturated with clean water prior to the coating to ensure

moisture presence inside the pores and capillaries and remove any excess water to ensure surface is touch dry

while coating.

3) Mixing of CRYSTALGUARD - Mix SUPERSHIELD CRYSTALGUARD powder with clean water to form a slurry

consistency with 5 parts of powder and 2 parts of water.

4) Application of CRYSTALGUARD - Apply one coat of SUPERSHIELD CRYSTALGUARD as a slurry

consistency on the concrete surface.

5) Mixing of CRYSTALGUARD ULTIMA - Mix SUPERSHIELD CRYSTALGUARD ULTIMA powder with clean water

to form a slurry consistency with 5 parts of powder and 2 parts of water.

6) Application of CRYSTALGUARD ULTIMA - Apply one coat of SUPERSHIELD CRYSTALGUARD ULTIMA as a

slurry consistency on the CRYSTALGUARD coating minimum after 4 hours gap as a top coating.

Continue with the SUPERSHIELD FLEXI membrane coating on the non-concrete substrate after 8 hours of

crystalline coating.

7) Mixing of FLEXI - Mix SUPERSHIELD FLEXI A component (Powder) with SUPERSHIELD FLEXI B

Component (Liquid) as per the pre-measured packaging.

8) Application of FLEXI - Apply the first coat of SUPERSHIELD FLEXI as a slurry consistency on the non-

concrete plastered side walls, overlapping the crystalline coating for 2" at the junction.

9) Second coat FLEXI - Apply the second coat of SUPERSHIELD FLEXI as a slurry consistency on the first coat

after a minimum of 4 hours gap.

l The SUPERSHIELD CRYSTALGUARD/ ULTIMA coating should be cured with a misty fog spray of clean water,

24 hours after the application and to be kept moist for minimum 3 days.

l The SUPERSHIELD FLEXI should be air cured for minimum 3 days and protected from water/ rain for

minimum 18 hours.

Cracks, horizontal, vertical joint sealing, tie hole, pipe penetrations, construction joints, expansion joints and

other defects in the concrete that is to be waterproofed should be treated as per the SUPERSHIELD specification

and application methodology.

www.supershieldglobal.com

WATERPROOFING SPECIFICATIONS AND METHODOLOGIES

PODIUM SLAB - 102 Page 2 of 3

PODIUM SLAB 102 2ONE COAT OF CRYSTALGUARD AND ONE COAT OF CRYSTALGUARD ULTIMA @ 1.5 Kg/m

Concrete Waterproofing and Durability Enhancement Using Supershield DPC Crystalline Technology

Page 6: SUPERSHIELD FLEXI FIRST COAT SUPERSHIELD FLEXI SECOND … · A) Manufacturer : Manufacturer should publish a third party product quality assurance certificate from a notified body

Performance Criteria

Quality Assurance

Warranty

Submittals

Crystalline waterproofing system should meet or exceed the performance requirements as specified herein.

l Crystalline Penetration : Crystallizing capability of waterproofing material shall be evidenced by

independent SEM (Scanning Electron Microscope) photographs documenting penetration of needle like

crystal formation deep within concrete.

l Self-healing capability and permeability resistance : Independent testing performed according to U.S. Army

Corps of Engineers CRD-C48-73 "Permeability of Concrete".

l Testing on the effectiveness of coating from negative side of concrete : Independent testing that

demonstrates the capability of the coating to seal the leakage/dampness from negative side.

l Resistance to chloride ion penetration : Independent testing performed according to ASTM C 1202-03

should exhibit a resistance of 100% better than that of the untreated specimen.

l Potable Water Approval : Independent testing shall be performed according to EN or NSF Standard 61, and

approval for the use of waterproofing material on structures holding potable water shall be evidenced.

A) Manufacturer : Manufacturer should publish a third party product quality assurance certificate from a notified

body with continuous surveillance audit or CE certificate with FPC (Factory Production Control) as per the

harmonized standard EN to prove that the facility from where the material is produced for the project has

undergone the required testing and extensive inspection and is under continuous surveillance by a notified body

appointed by the European Union as per the European norms for the system. Manufacturers who cannot provide

the performance test data specified herein and FPC certificate shall not be considered for the project.

B) Applicator : Waterproofing applicator shall be experienced in the installation of cementitious crystalline

waterproofing materials and shall be approved by the manufacturer in writing.

A) Manufacturer's Warranty : Manufacturer shall provide standard product warranty executed by authorised

company official.

B) Applicator's Warranty : Applicator shall warrant the waterproofing installation against defects caused by faulty

workmanship or materials for a period of (specify term) years from Date of Substantial Completion. The warranty

will cover the surfaces treated and will bind the applicator to repair, at his expense, any and all leaks through the

treated surfaces which are not due to structural weaknesses or other causes beyond applicator's control such as

fire, earthquake and cyclone.

Product data sheets, Application guidelines, Material safety data sheet, CE certificate, Summary of test reports.

www.supershieldglobal.com

WATERPROOFING SPECIFICATIONS AND METHODOLOGIES

PODIUM SLAB - 102 Page 3 of 3

PODIUM SLAB 102 2ONE COAT OF CRYSTALGUARD AND ONE COAT OF CRYSTALGUARD ULTIMA @ 1.5 Kg/m

Concrete Waterproofing and Durability Enhancement Using Supershield DPC Crystalline Technology

Page 7: SUPERSHIELD FLEXI FIRST COAT SUPERSHIELD FLEXI SECOND … · A) Manufacturer : Manufacturer should publish a third party product quality assurance certificate from a notified body

www.supershieldglobal.com

PODIUM SLAB - PREREQUISITE FOR SUPERSHIELD WATERPROOFING TREATMENT

PODIUM SLAB

Provide, mix and brush apply two coats of SUPERSHIELD FLEXI, two component material that forms seamless

flexible membrane @ 1.2Kg/m² on the side walls to height of 6" above the filling level. The coating should overlap

a minimum 1” over the crystalline coating at the junction.

l The that is to be treated should be minimum 7 days old.

l The pipe penetrations through the horizontal brick walls should be packed and plastered to a

minimum thickness of 25 mm with the ratio of 1:3 cement mortar.

l The side walls that are of non-concrete should be plastered to a minimum thickness of 25 mm with the ratio

of 1:3 cement mortar to a height of minimum 6" above the nearest floor level.

SUPERSHIELD SPECIFICATION AND APPLICATION METHODOLOGY

Provide, mix and brush apply one coat of SUPERSHIELD CRYSTALGUARD, single compound Deep Penetrating

Capillary (DPC) waterproofing system @ 0.75 Kg/m² and one coat of SUPERSHIELD MULTIGUARD, single

compound cementitious Multiseal coating that generates a non-soluble crystalline formation of dendritic fibers

within the pores and capillary tracts of the concrete and also form a repellant barrier on the surface @ 0.75 Kg/m²

on to the PODIUM SLAB and to the adjacent curb wall that are of concrete to the height of 6" above the filling

level.

Concrete Substrate

Non concrete substrate with plastering

WATERPROOFING SPECIFICATIONS AND METHODOLOGIES

PODIUM SLAB 103

Concrete Waterproofing And Durability Enhancement Using Supershield DPC Crystalline & Multiseal Technology

2ONE COAT OF CRYSTALGUARD AND ONE COAT OF MULTIGUARD @ 1.5 Kg/m

PODIUM SLAB- 103 Page 1 of 3

SUPERSHIELD CRYSTALGUARD COATING

SUPERSHIELD MULTIGUARD COATING

PODIUM SLAB

COVING

SUPERSHIELD FLEXI FIRST COAT

SUPERSHIELD FLEXI SECOND COAT

Page 8: SUPERSHIELD FLEXI FIRST COAT SUPERSHIELD FLEXI SECOND … · A) Manufacturer : Manufacturer should publish a third party product quality assurance certificate from a notified body

Application Methodology

Curing

Watch Points

1) Surface preparation - The concrete substrate that is to be applied with SUPERSHIELD CRYSTALGUARD

/MULTIGUARD must be free from foreign materials and to be micro cleaned by mechanical means like wire

brushing or vacuum cleaning.

2) Pre-wetting - Concrete surface must be thoroughly saturated with clean water prior to the coating to ensure

moisture presence inside the pores and capillaries and remove any excess water to ensure surface is touch dry

while coating.

3) Mixing of CRYSTALGUARD - Mix SUPERSHIELD CRYSTALGUARD powder with clean water to form a slurry

consistency with 5 parts of powder and 2 parts of water.

4) Application of CRYSTALGUARD - Apply one coat of SUPERSHIELD CRYSTALGUARD as a slurry

consistency on the concrete surface.

5) Mixing of MULTIGUARD - Mix SUPERSHIELD MULTIGUARD powder with clean water to form a slurry

consistency with 5 parts of powder and 2 parts of water.

6) Application of MULTIGUARD - Apply one coat of SUPERSHIELD MULTIGUARD as a slurry consistency on the

concrete surface as a top coat after 3 days gap.

Continue with the SUPERSHIELD FLEXI membrane coating on the non-concrete substrate after 8 hours of

crystalline coating.

7) Mixing of FLEXI - Mix SUPERSHIELD FLEXI A component (Powder) with SUPERSHIELD FLEXI B

Component (Liquid) as per the pre-measured packaging.

8) Application of FLEXI - Apply the first coat of SUPERSHIELD FLEXI as a slurry consistency on the non-

concrete plastered side walls, overlapping the crystalline coating for 2" at the junction.

9) Second coat FLEXI - Apply the second coat of SUPERSHIELD FLEXI as a slurry consistency on the first coat

after a minimum of 4 hours gap.

l The SUPERSHIELD CRYSTALGUARD coating should be cured with a misty fog spray of clean water, 24 hours

after the application and to be kept moist for minimum 3 days.

l The SUPERSHIELD MULTIGUARD coating should be air cured for minimum 3 days and protected from water/

rain for minimum 18 hours.

l The SUPERSHIELD FLEXI should be air cured for minimum 3 days and protected from water/ rain for

minimum 18 hours.

Cracks, horizontal, vertical joint sealing, tie hole, pipe penetrations, construction joints, expansion joints and

other defects in the concrete that to be waterproofed should be treated as per the

SUPERSHIELD specification and application methodology.

www.supershieldglobal.com

WATERPROOFING SPECIFICATIONS AND METHODOLOGIES

PODIUM SLAB - 103 Page 2 of 3

PODIUM SLAB 103

Concrete Waterproofing And Durability Enhancement Using Supershield DPC Crystalline & Multiseal Technology

2ONE COAT OF CRYSTALGUARD AND ONE COAT OF MULTIGUARD @ 1.5 Kg/m

Page 9: SUPERSHIELD FLEXI FIRST COAT SUPERSHIELD FLEXI SECOND … · A) Manufacturer : Manufacturer should publish a third party product quality assurance certificate from a notified body

Performance Criteria

Quality Assurance

Warranty

Submittals

Crystalline waterproofing system should meet or exceed the performance requirements as specified herein.

l Crystalline Penetration : Crystallizing capability of waterproofing material shall be evidenced by

independent SEM (Scanning Electron Microscope) photographs documenting penetration of needle like

crystal formation deep within concrete.

l Self-healing capability and permeability resistance : Independent testing performed according to U.S. Army

Corps of Engineers CRD-C48-73 "Permeability of Concrete".

l Testing on the effectiveness of coating from negative side of concrete : Independent testing that

demonstrates the capability of the coating to seal the leakage/dampness from negative side.

l Resistance to chloride ion penetration : Independent testing performed according to ASTM C 1202-03

should exhibit a resistance of 100% better than that of the untreated specimen.

l Potable Water Approval : Independent testing shall be performed according to EN or NSF Standard 61, and

approval for the use of waterproofing material on structures holding potable water shall be evidenced.

A) Manufacturer : Manufacturer should publish a third party product quality assurance certificate from a notified

body with continuous surveillance audit or CE certificate with FPC (Factory Production Control) as per the

harmonized standard EN to prove that the facility from where the material is produced for the project has

undergone the required testing and extensive inspection and is under continuous surveillance by a notified body

appointed by the European Union as per the European norms for the system. Manufacturers who cannot provide

the performance test data specified herein and FPC certificate shall not be considered for the project.

B) Applicator : Waterproofing applicator shall be experienced in the installation of cementitious crystalline

waterproofing materials and shall be approved by the manufacturer in writing.

A) Manufacturer's Warranty : Manufacturer shall provide standard product warranty executed by authorised

company official.

B) Applicator's Warranty : Applicator shall warrant the waterproofing installation against defects caused by faulty

workmanship or materials for a period of (specify term) years from Date of Substantial Completion. The warranty

will cover the surfaces treated and will bind the applicator to repair, at his expense, any and all leaks through the

treated surfaces which are not due to structural weaknesses or other causes beyond applicator's control such as

fire, earthquake and cyclone.

Product data sheets, Application guidelines, Material safety data sheet, CE certificate, Summary of test reports.

www.supershieldglobal.com

WATERPROOFING SPECIFICATIONS AND METHODOLOGIES

PODIUM SLAB - 103 Page 3 of 3

PODIUM SLAB 103

Concrete Waterproofing And Durability Enhancement Using Supershield DPC Crystalline & Multiseal Technology

2ONE COAT OF CRYSTALGUARD AND ONE COAT OF MULTIGUARD @ 1.5 Kg/m

Page 10: SUPERSHIELD FLEXI FIRST COAT SUPERSHIELD FLEXI SECOND … · A) Manufacturer : Manufacturer should publish a third party product quality assurance certificate from a notified body

www.supershieldglobal.com

PODIUM SLAB - PREREQUISITE FOR SUPERSHIELD WATERPROOFING TREATMENT

PODIUM SLAB

Provide, mix and brush apply two coats of SUPERSHIELD FLEXI, two component material that forms seamless

flexible membrane @ 1.2 Kg/m² on the side walls to height of 6" above the filling level. The coating should

overlap a minimum 1” over the crystalline coating at the junction.

l The that is to be treated should be minimum 7 days old.

l The pipe penetrations through the horizontal brick walls should be packed and plastered to a

minimum thickness of 25 mm with the ratio of 1:3 cement mortar.

l The side walls that are of non-concrete should be plastered to a minimum thickness of 25 mm with the ratio

of 1:3 cement mortar to a height of minimum 6" above the nearest floor level.

SUPERSHIELD SPECIFICATION AND APPLICATION METHODOLOGY

Provide, and spray apply one coat of SUPERSHIELD MULTISEAL 100, water based colorless liquid enhanced

with Multiseal technology that forms hydrated and hygroscopic crystals in the pores and capillary tracts of the

concrete with a repellant barrier finish on the surface @ 200 Ml/m² on the PODIUM SLAB and to the adjacent

curb wall that are of concrete to the height of 6" above the filling level.

Concrete Substrate

Non concrete substrate with plastering

WATERPROOFING SPECIFICATIONS AND METHODOLOGIES

PODIUM SLAB 104

Concrete Waterproofing And Durability Enhancement Using Multiseal Technology

2ONE COAT OF MULTISEAL 100 @ 200 Ml/m

PODIUM SLAB - 104 Page 1 of 3

SUPERSHIELD MULTISEAL 100 COATING

PODIUM SLAB

COVING

SUPERSHIELD FLEXI FIRST COAT

SUPERSHIELD FLEXI SECOND COAT

Page 11: SUPERSHIELD FLEXI FIRST COAT SUPERSHIELD FLEXI SECOND … · A) Manufacturer : Manufacturer should publish a third party product quality assurance certificate from a notified body

Application Methodology

Curing

Watch Points

Performance Criteria

1) Surface preparation - The concrete substrate that is to be applied with SUPERSHIELD MULTISEAL 100 must

be free from foreign materials and to be micro cleaned by mechanical means like wire brushing or vacuum

cleaning.

2) Pre-wetting - Concrete surface must be thoroughly saturated with clean water prior to the coating to ensure

moisture presence inside the pores and capillaries and remove any excess water and ensure surface is

predominantly dry while coating to enhance SUPERSHIELD MULTISEAL 100 impregnation.

3) Mixing of MULTISEAL 100 - No mixing is required and should not be diluted with water or by any other means.

4) Application of MULTISEAL 100 - Apply one coat of SUPERSHIELD MULTISEAL 100 evenly by means of

spraying and ensure the surface is completely impregnated with SUPERSHIELD MULTISEAL 100.

Continue with the SUPERSHIELD FLEXI membrane coating on the non-concrete substrate after 8 hours of

crystalline coating.

5) Mixing of FLEXI - Mix SUPERSHIELD FLEXI A component (Powder) with SUPERSHIELD FLEXI B

Component (Liquid) as per the pre-measured packaging.

6) Application of FLEXI - Apply the first coat of SUPERSHIELD FLEXI as a slurry consistency on the non-

concrete plastered side walls, overlapping the crystalline coating for 2" at the junction.

7) Second coat FLEXI - Apply the second coat of SUPERSHIELD FLEXI as a slurry consistency on the first coat

after a minimum of 4 hours gap.

l The SUPERSHIELD MULTISEAL 100 coating should be air cured and protected from water/ rain for at least 4

hours.

l The SUPERSHIELD FLEXI should be air cured and protected from water/ rain for minimum 18 hours.

Cracks, horizontal, vertical joint sealing, tie hole, pipe penetrations, construction joints, expansion joints and

other defects in the concrete that is to be waterproofed should be treated as per the SUPERSHIELD specification

and application methodology.

Crystalline waterproofing system should meet or exceed the performance requirements as specified herein.

l Crystalline Penetration : Crystallizing capability of waterproofing material shall be evidenced by

independent SEM (Scanning Electron Microscope) photographs documenting penetration of needle like

crystal formation deep within concrete.

www.supershieldglobal.com

WATERPROOFING SPECIFICATIONS AND METHODOLOGIES

PODIUM SLAB - 104 Page 2 of 3

PODIUM SLAB 104

Concrete Waterproofing And Durability Enhancement Using Multiseal Technology

2ONE COAT OF MULTISEAL 100 @ 200 Ml/m

Page 12: SUPERSHIELD FLEXI FIRST COAT SUPERSHIELD FLEXI SECOND … · A) Manufacturer : Manufacturer should publish a third party product quality assurance certificate from a notified body

l Self-healing capability and permeability resistance : Independent testing performed according to U.S. Army

Corps of Engineers CRD-C48-73 "Permeability of Concrete".

l Testing on the effectiveness of coating from negative side of concrete : Independent testing that

demonstrates the capability of the coating to seal the leakage/dampness from negative side.

l Resistance to chloride ion penetration : Independent testing performed according to ASTM C 1202-03

should exhibit a resistance of 100% better than that of the untreated specimen.

l Potable Water Approval : Independent testing shall be performed according to EN or NSF Standard 61, and

approval for the use of waterproofing material on structures holding potable water shall be evidenced.

A) Manufacturer : Manufacturer should publish a third party product quality assurance certificate from a notified

body with continuous surveillance audit or CE certificate with FPC (Factory Production Control) as per the

harmonized standard EN to prove that the facility from where the material is produced for the project has

undergone the required testing and extensive inspection and is under continuous surveillance by a notified body

appointed by the European Union as per the European norms for the system. Manufacturers who cannot provide

the performance test data specified herein and FPC certificate shall not be considered for the project.

B) Applicator : Waterproofing applicator shall be experienced in the installation of cementitious crystalline

waterproofing materials and shall be approved by the manufacturer in writing.

A) Manufacturer's Warranty : Manufacturer shall provide standard product warranty executed by authorised

company official.

B) Applicator's Warranty : Applicator shall warrant the waterproofing installation against defects caused by faulty

workmanship or materials for a period of (specify term) years from Date of Substantial Completion. The warranty

will cover the surfaces treated and will bind the applicator to repair, at his expense, any and all leaks through the

treated surfaces which are not due to structural weaknesses or other causes beyond applicator's control such as

fire, earthquake and cyclone.

Product data sheets, Application guidelines, Material safety data sheet, CE certificate, Summary of test reports.

Quality Assurance

Warranty

Submittals

www.supershieldglobal.com PODIUM SLAB - 104 Page 3 of 3

WATERPROOFING SPECIFICATIONS AND METHODOLOGIES

PODIUM SLAB 104

Concrete Waterproofing And Durability Enhancement Using Multiseal Technology

2ONE COAT OF MULTISEAL 100 @ 200 Ml/m