Summit Avenue @ Ayd Mill Rd
![Page 2: Summit Avenue Bridge](https://reader033.fdocuments.in/reader033/viewer/2022050104/626c692dd5f65658bb23364d/html5/thumbnails/2.jpg)
What will the road look like?
![Page 3: Summit Avenue Bridge](https://reader033.fdocuments.in/reader033/viewer/2022050104/626c692dd5f65658bb23364d/html5/thumbnails/3.jpg)
200’ wide, divided road, historic avenue with broad medians & boulevards
![Page 4: Summit Avenue Bridge](https://reader033.fdocuments.in/reader033/viewer/2022050104/626c692dd5f65658bb23364d/html5/thumbnails/4.jpg)
200’ wide, divided road, historic avenue with broad medians & boulevards
![Page 5: Summit Avenue Bridge](https://reader033.fdocuments.in/reader033/viewer/2022050104/626c692dd5f65658bb23364d/html5/thumbnails/5.jpg)
Highlights of Road Design • Roads are narrower between Syndicate and Griggs • There is less paved surface (1/2 acre less) • Pedestrian crossings are shorter • Accessibility is better • Visibility is better
![Page 6: Summit Avenue Bridge](https://reader033.fdocuments.in/reader033/viewer/2022050104/626c692dd5f65658bb23364d/html5/thumbnails/6.jpg)
What will the bridge look like?
![Page 7: Summit Avenue Bridge](https://reader033.fdocuments.in/reader033/viewer/2022050104/626c692dd5f65658bb23364d/html5/thumbnails/7.jpg)
77’ wide bridge structure, carrying 2 vehicle lanes, 2 bike lanes, and 2 sidewalks
Ayd Mill Road CP Railway
(East) (West)
![Page 8: Summit Avenue Bridge](https://reader033.fdocuments.in/reader033/viewer/2022050104/626c692dd5f65658bb23364d/html5/thumbnails/8.jpg)
Highlights of Bridge Design
• The deck is narrower • Sidewalks and bike lanes are wider • A “buffer” separates the vehicle lane and bike lane • The new bridge is “Joint-less” • Aesthetic features are more reminiscent of historic era
![Page 9: Summit Avenue Bridge](https://reader033.fdocuments.in/reader033/viewer/2022050104/626c692dd5f65658bb23364d/html5/thumbnails/9.jpg)
When will work occur?
![Page 10: Summit Avenue Bridge](https://reader033.fdocuments.in/reader033/viewer/2022050104/626c692dd5f65658bb23364d/html5/thumbnails/10.jpg)
Anticipated Schedule
Fall 2019
• TC Marathon (October 6, 2019) • Install detours, protections • Demo existing bridge
Winter-Spring 2020
• Construct new abutments, pier, and walls • Set beams, form and pour deck • Backfill abutments and stabilize slopes
Summer 2020
• Complete bridge items: sidewalk, railing, lighting • Reconstruct roads, utilities, storm water system • Re-open Summit Avenue by end of September
(Actual sequence of work will be determined by the contractor)
![Page 11: Summit Avenue Bridge](https://reader033.fdocuments.in/reader033/viewer/2022050104/626c692dd5f65658bb23364d/html5/thumbnails/11.jpg)
How will we be detoured?
![Page 12: Summit Avenue Bridge](https://reader033.fdocuments.in/reader033/viewer/2022050104/626c692dd5f65658bb23364d/html5/thumbnails/12.jpg)
Traffic during Construction • Summit Avenue will be closed (except to local access) • Ayd Mill Road will be reduced to one lane in each direction • Syndicate, Grand, and Dunlap will temporarily change
• We will implement our plan, then observe actual patterns.
We will have adjustments ready to go, if needed.
• We will coordinate with our contractor to determine construction phasing and its effects on traffic.
• Expect some inconvenience and delay, be safe, be patient.
![Page 13: Summit Avenue Bridge](https://reader033.fdocuments.in/reader033/viewer/2022050104/626c692dd5f65658bb23364d/html5/thumbnails/13.jpg)
Generalized Vehicle Detour
![Page 14: Summit Avenue Bridge](https://reader033.fdocuments.in/reader033/viewer/2022050104/626c692dd5f65658bb23364d/html5/thumbnails/14.jpg)
Generalized Bike/Ped Detour
![Page 15: Summit Avenue Bridge](https://reader033.fdocuments.in/reader033/viewer/2022050104/626c692dd5f65658bb23364d/html5/thumbnails/15.jpg)
What are the next steps?
![Page 16: Summit Avenue Bridge](https://reader033.fdocuments.in/reader033/viewer/2022050104/626c692dd5f65658bb23364d/html5/thumbnails/16.jpg)
Next Steps • Project will be brought to City Council for approval. • Plans will be submitted to the State on 4/1/2019. • Project must be Federally authorized by 6/30/2019. • Pending approval, construction starts 10/7/2019. • If approval is delayed, construction will not occur until 2020.
• Updates will be posted to stpaul.gov/summit-bridge