Summer i Zing

download Summer i Zing

of 64

Transcript of Summer i Zing

  • 8/2/2019 Summer i Zing

    1/64

    Types ofHydropower

    Facilities

    1

  • 8/2/2019 Summer i Zing

    2/64

    ImpoundmentHydropower- uses a damto store water. Water may

    be released either to meetchanging electricity needs

    or to maintain a constantwater level.

    2

  • 8/2/2019 Summer i Zing

    3/64

    Run-of-River Projects-utilize theflow of water within the natural

    range of the river, requiringlittle or no impoundment. Run-

    of-river plants can be designedusing large flow rates with low

    head or small flow rates withhigh head

    3

  • 8/2/2019 Summer i Zing

    4/64

    Microhydropower Projects -produce 300 kilowatts (kW) or

    less. Microhydro plants canutilize low heads or high heads

    4

  • 8/2/2019 Summer i Zing

    5/64

    Diversion Hydropower -channels a portion of the river

    through a canal or penstock,but may require a dam

    5

  • 8/2/2019 Summer i Zing

    6/64

    Pumped storage - pumps water from a

    lower reservoir to an upper reservoirat times when demand for electricity

    is low. During periods of highelectrical demand, the water is

    released back to the lower reservoirto generate electricity.

    6

  • 8/2/2019 Summer i Zing

    7/64

    What is Micro Hydro? Micro-hydro is generally

    less than 300 kW.

    Hydro power is costeffective in a limited

    number of places.

    Hydro is moreconsistent than wind or

    solar. Hydro is concentrated

    solar energy.

    7

  • 8/2/2019 Summer i Zing

    8/64

    Micro Hydro Costs

    High Capital Cost

    Labor and Earth Moving Equipment Civil Works and Penstocks

    Low Operating Cost No Fuel

    Inexpensive maintenance

    Especially economic for Do-It-Yourself.

    8

  • 8/2/2019 Summer i Zing

    9/64

    Micro Hydro is Run-of-River

    No water storage.

    Much simpler to design and build.

    Less environmental impact.

    May be seasonally dependent. Some schemes have a small reservoir for

    supplying peak daily loads.

    9

  • 8/2/2019 Summer i Zing

    10/64

    Water Rights Sufficient water must be available.

    Fish or riparian habitat must not be affected.

    Other licensed users take precedence.

    Environmental impact must be addressed.

    Erosion due to civil works Water temperature increased due to low

    water.

    Dams are not recommended.

    Easements required if crossing private land.

    10

  • 8/2/2019 Summer i Zing

    11/64

    AC systems

    River flow must exceed peak demand.

    Standard wiring and electrical equipment. Components

    Generator Induction

    Synchronous

    Frequency Control and Governors

    Voltage Control

    Diversion loads11

  • 8/2/2019 Summer i Zing

    12/64

    Grid Tie Systems

    Utility Concerns

    Fault Protection Line Worker and

    Public Safety

    Power Quality Metering Options

    12

  • 8/2/2019 Summer i Zing

    13/64

    Line Worker and Public Safety

    Islanding

    Generator supplies an isolated portion of gridduring a power outage.

    Poses safety hazard to line workers.

    Inverters meet UL standards

    Induction Generators (Motors)

    13

  • 8/2/2019 Summer i Zing

    14/64

    Power

    An instantaneous measure.

    The ability to do work. Measured in Watts and Horsepower.

    746 W = 1 hp

    Hp = Flow (cfs) x Head (feet) x .88.8

    14

  • 8/2/2019 Summer i Zing

    15/64

    Hydro Power

    Site Assessment potential power

    Loads required power System capacity designed power

    Locating the Intake Locating the Powerhouse

    15

  • 8/2/2019 Summer i Zing

    16/64

    Site Assessment Flow

    The design flow will be a percentage of the

    measured stream flow. Design flow determines penstock size

    Design flow determines nozzle size Head

    - Elevation difference between the penstock

    intake and the turbine

    Penstock length.

    Often the major cost.16

  • 8/2/2019 Summer i Zing

    17/64

    Measuring Flow

    Velocity-Area Method

    Velocity Head Flow Meter

    Weir method Bucket method

    17

  • 8/2/2019 Summer i Zing

    18/64

    Determining Area

    Average Depth = Sum of (N)depths

    N

    Area = Stream Width x Average Depth

    1 2 3 ...

    N18

  • 8/2/2019 Summer i Zing

    19/64

    Measuring Velocity

    Stream velocity varies with depth.

    19

  • 8/2/2019 Summer i Zing

    20/64

    Float Method

    20

  • 8/2/2019 Summer i Zing

    21/64

    Weir method

    21Reference: Canyon Industries Inc., Micro-hydro Design

  • 8/2/2019 Summer i Zing

    22/64

    Weir Method

    22Reference: Inversin, Micro-hydropower Sourcebook

  • 8/2/2019 Summer i Zing

    23/64

    Bucket Method

    23

  • 8/2/2019 Summer i Zing

    24/64

    Head

    24

    Vertical distance from inlet to turbine for

    impulse turbine. Vertical distance from inlet to tail water for

    reaction turbine.

  • 8/2/2019 Summer i Zing

    25/64

    Measuring Head

    Inclinometer

    Altimeter Hose and Pressure gauge

    Level

    25

  • 8/2/2019 Summer i Zing

    26/64

    An Inclinometer

    Also called an Abney Level.

    L is measured with a tape or hip chain.

    H = L x sin (a)H3

    H2

    H1

    L1

    L3

    L2

    a1

    a2

    a3

    a

    26

  • 8/2/2019 Summer i Zing

    27/64

    Altimeters

    Measuring relative height, therefore

    absolute calibration is not necessary. The interval between measurements must

    be short to avoid error from weather

    changes.

    Best to take multiple readings.

    27

  • 8/2/2019 Summer i Zing

    28/64

    Hose and Pressure Gauge Accurate and simple method.

    Bubbles in hose cause errors.

    Gauge must have suitable scale and be calibrated.

    Use hose a measuring tape for penstock length.

    H1

    28

  • 8/2/2019 Summer i Zing

    29/64

    Using a Level

    Use a person or a measured pole.

    Htotal = A + B + C + D

    29

  • 8/2/2019 Summer i Zing

    30/64

    Static Head vs. Net Head

    Static head is the vertical distance from

    the intake to the power house Net head takes into account friction loss

    Pipe sizing rule of thumbA pipe diameter should be chosen so that only

    10 15% of the static head is lost in pipe

    friction. Tables are available for every pipematerial, diameter and flow rate.

    30

  • 8/2/2019 Summer i Zing

    31/64

    Locating the Intake

    Choose a site with a stable stream bed.

    Constant flow stream Bedrock

    Small gradient

    The inside of bends accumulate sediment.

    The outside of bends are subject to

    erosion and flood damage.

    Place the intake along a straight section.

    31

  • 8/2/2019 Summer i Zing

    32/64

    Intake and Powerhouse

    Flood conditions must be planned for.

    Composition and nature of stream beddetermines erosion and future path

    changes.

    Natural features can protect civil works.

    Locate upstream to avoid competing with

    other water users.

    Access for construction and maintenance.

    32

  • 8/2/2019 Summer i Zing

    33/64

  • 8/2/2019 Summer i Zing

    34/64

    Civil Works

    Diversion

    Intake Silt Basin

    Trash Rack Screen

    Penstock Power House

    Weir

    Direct Intake

    Head Race

    Trash RackSilt Basin

    Penstock34

  • 8/2/2019 Summer i Zing

    35/64

    Civil Works

    The river flow will be

    seasonally variable. Sediment must be

    removed.

    Must be accessible for

    construction.

    Erosion occurs if water

    flows around weirs.

    35

  • 8/2/2019 Summer i Zing

    36/64

    Diversion

    Weirs maintain the water level at the

    intake. A Weir does not store water.

    Natural riverbed features may be used. Weirs may also be :

    Concrete

    Gabions

    Wood

    36

  • 8/2/2019 Summer i Zing

    37/64

    Weir

    The sluice is a short length of pipe for

    clearing away sediment.

    Artificial Weir

    Sluice

    37

  • 8/2/2019 Summer i Zing

    38/64

    Weir

    If spring run-off is not severe, the penstock

    may lead directly from the weir.

    Screened Intake Weir

    Penstock

    38

    S

  • 8/2/2019 Summer i Zing

    39/64

    Sluice

    A Sluice allows sediment removal. 39

    Wi W ll

  • 8/2/2019 Summer i Zing

    40/64

    Wing Walls

    Wing walls prevent erosion and flood

    damage to the civil works. Natural rock walls along a stream can

    serve the same purpose.

    Walls may be built from:

    Gabions

    Concrete

    Rock and mortar

    Wood 40

    I t k D th

  • 8/2/2019 Summer i Zing

    41/64

    Intake Depth

    Pipe intakes should be submerged deep

    enough not to draw air.

    H = (0.0622) Q2

    / D4

    H = intake depth[in]

    Q = flow rate [gpm]

    D = pipe diameter [in]

    41

    I t k D th

  • 8/2/2019 Summer i Zing

    42/64

    Intake Depth

    Rule of thumb pipe should be

    submerged 3x the pipe diameter Screening is the weak point

    Intake structures are the mostmaintenance intensive part of hydro

    42

    Sid I t k

  • 8/2/2019 Summer i Zing

    43/64

    Side Intake

    Place a side intake far enough upstream

    to avoid silt deposited behind the weir.

    Head Race

    Weir

    Side Intake

    Wing Wall

    Silt

    43

    Di t I t k

  • 8/2/2019 Summer i Zing

    44/64

    Direct Intake

    A direct intake allows silt to be drawn into

    the head race to settle in the silt basin.

    Weir

    Direct Intake

    Head Race

    Silt Basin

    Wing Wall

    44

    T h I t k

  • 8/2/2019 Summer i Zing

    45/64

    Trench Intake

    A trench intake in a rapidly flowing stream

    allows large debris to pass over. The rapid flow keeps the rack clear.

    Trash Rack

    45

    Screens

  • 8/2/2019 Summer i Zing

    46/64

    Screens

    Screens should be half the nozzle

    diameter. A self-cleaning screen design is best.

    The screen area must be relatively large.Screen

    PenstockHead Race

    Silt Basin46

    Trash Rack

  • 8/2/2019 Summer i Zing

    47/64

    Trash Rack

    The trash rack should be at least two pipediameters from the pipe inlet.

    If the trash rack is not situated in the mainstream it is easier to clean.

    If the head race is a pipe, a rack is

    necessary.

    Drilled PVC Pipe will serve as a trash rack.

    47

    Ice and Snow

  • 8/2/2019 Summer i Zing

    48/64

    Ice and Snow

    48

    Frazil ice super cooled

    water sticks toeverything

    Submerging the intake

    allows the ice to float.

    Snow may prevent

    penstocks from freezing.

    Penstock

  • 8/2/2019 Summer i Zing

    49/64

    Penstock

    49

    Materials

    Diameter Friction

    Pressure Rating Valves

    Gauges Thrust Block

    Penstocks

  • 8/2/2019 Summer i Zing

    50/64

    Penstocks A vent prevents vacuum collapse of the penstock. A pressure gauge should always be installed.

    Valves that close slowly prevent water hammer.

    50Penstock

    ValveVent

    Pressure Gauge

    Valve

    AnchorBlock

    Penstocks

  • 8/2/2019 Summer i Zing

    51/64

    Penstocks

    A short straight penstock is least

    expensive. A channel or culvert may be used to

    reduce penstock length.

    Pipe laid in the creek will abrade.

    Penstocks deliver water under pressure.

    Usually the major expense.

    51

    Slide, Anchor and Thrust Blocks

  • 8/2/2019 Summer i Zing

    52/64

    ,

    Prevent unwanted

    movement of penstock. Required at bends and

    reductions.

    Anchor blocks use mass

    to prevent movement.

    Thrust blocks are used

    with buried penstocks.

    52

    After bay and Tailrace

  • 8/2/2019 Summer i Zing

    53/64

    After bay and Tailrace

    Removes water from power

    house and turbine. Designed to prevent

    erosion.

    Must be large with enough

    slope to prevent water

    backing up in turbine.

    53

    Head Race

  • 8/2/2019 Summer i Zing

    54/64

    Head Race

    It may be less expensive to run low

    pressure pipe or a channel to a short

    penstock.

    54

    4

    Penstock

    6

    Penstock

    Head

    Race

    Turbines

  • 8/2/2019 Summer i Zing

    55/64

    Turbines

    55

    Water under pressure contains energy.

    Turbines convert the energy in water intorotating mechanical energy.

    Impulse turbines convert the kineticenergy of a jet of water to mechanical

    energy.

    Reaction turbines convert potential energyin pressurized water to mechanical

    energy.

    Selected References

  • 8/2/2019 Summer i Zing

    56/64

    Selected References

    Microhydro by Scott Davis

    Microhydro Design Manual by AdamHarvey

    Waterturbine.com for picohydro units BC Hydro Handbook

    Idaho National Labs

    56

    Impulse Turbines

  • 8/2/2019 Summer i Zing

    57/64

    Impulse Turbines

    Tolerate sand.

    Easy to fabricate. Efficient at wide a range

    of head and flow. A nozzle converts

    pressurised water into a

    high-speed jet of water.

    57Pelton Turbine Canyon Industries

    Pelton Turbines

  • 8/2/2019 Summer i Zing

    58/64

    Pelton Turbines

    At least one jet of water

    strike the buckets atatmospheric pressure.

    Maximum jet diameter

    about 1/3 bucket width.

    More jets increase flow

    and are used at lowhead.

    580.61m Pelton Dependable Turbines Ltd.

    Turbine application

  • 8/2/2019 Summer i Zing

    59/64

    Turbine application

    Head (pressure)

    Turbine High

    (30m +)

    Medium Low

    (

  • 8/2/2019 Summer i Zing

    60/64

    Generators

    Types of Generators Synchronous

    Induction

    DC generators

    Characteristics of Generators

    Selecting a Generator

    Voltage Regulation

    Governing (speed and frequency) Mechanical

    Electronic

    60

    Synchronous Generator

  • 8/2/2019 Summer i Zing

    61/64

    Synchronous Generator

    Used in almost all stand-alone

    applications. Single phase used up to 10 kW.

    Most three phase are smaller than

    equivalent single phase.

    61

    Induction Generator

  • 8/2/2019 Summer i Zing

    62/64

    Induction Generator

    Just an induction motor with negative slip.

    Used most often with grid-tie systems. Used by some for battery based systems.

    62

    DC Alternator

  • 8/2/2019 Summer i Zing

    63/64

    Produces rectified

    alternating current. Readily available.

    Easy to service.

    63

    Electronic Governing

  • 8/2/2019 Summer i Zing

    64/64

    g

    Frequency governing is used for

    synchronous generators. Voltage governing is used for induction

    generators

    Diversion Loads

    A load must always be present.

    Water heating or air heating.

    Diversion loads may be useful loads.

    64