Summer 2018 - Fall 2020...

14
UC San Diego North Torrey Pines Living Learning Neighborhood Summer 2018 - Fall 2020 Construction Rev 8

Transcript of Summer 2018 - Fall 2020...

Page 1: Summer 2018 - Fall 2020 Constructionsenate.ucsd.edu/media/314737/...ntplln-academic-presentation-rev8-f… · Summer 2018 2019 2020 Fall Winter Spring Summer Fall Winter Spring Summer

UC San DiegoNorth Torrey Pines Living Learning Neighborhood

Summer 2018 - Fall 2020 Construction

Rev 8

Page 2: Summer 2018 - Fall 2020 Constructionsenate.ucsd.edu/media/314737/...ntplln-academic-presentation-rev8-f… · Summer 2018 2019 2020 Fall Winter Spring Summer Fall Winter Spring Summer

UC San DiegoNorth Torrey Pines Living Learning Neighborhood

A New CommunityPROJECT INFORMATION

Goals:

Address EnrollmentGrowth

Integrate Living andLearning in oneCommunity

Permanent Home forSixth College

Key Elements

1,636,000 GSF

2,000 UndergraduateBeds

1,200 undergroundparking stalls

General AssignmentClassrooms

Academic Space forDivisions of SocialSciences and Arts &Humanities

Rev 8

Page 3: Summer 2018 - Fall 2020 Constructionsenate.ucsd.edu/media/314737/...ntplln-academic-presentation-rev8-f… · Summer 2018 2019 2020 Fall Winter Spring Summer Fall Winter Spring Summer

UC San DiegoNorth Torrey Pines Living Learning Neighborhood

ResourcesRESOURCES

Rev 8

UCSD Living & Learning Website:livinglearning.ucsd.edu

UCSD Campus Map:maps.ucsd.edu/map

NTPLLN Construction Website:livinglearning.ucsd.edu/construction

NTPLLN Frequently Asked Questions:livinglearning.ucsd.edu/construction/faq

UCSD Transportation Website:transportation.ucsd.edu

UCSD Parking and Shuttle Alert:transportation.ucsd.edu/engage/firsttoknow

UCSD Transportation Virtual Town Hall:transportation.ucsd.edu/engage/virtualtownhall

UCSD Live Shuttle Map:ucsdbus.com/map

Page 4: Summer 2018 - Fall 2020 Constructionsenate.ucsd.edu/media/314737/...ntplln-academic-presentation-rev8-f… · Summer 2018 2019 2020 Fall Winter Spring Summer Fall Winter Spring Summer

Const.Site

UC San DiegoNorth Torrey Pines Living Learning Neighborhood

Trucking Route & Worker Vehicle Route

Summer

2018 2019 2020

Fall Winter Spring Summer Fall Winter Spring Summer

KEY

Trucking Route

Worker Vehicle Route

Construction Site

Contractor Parking

Gen

esee

Ave

La J

olla

Vill

age

Dr

N Torrey Pines Rd

Gilman Dr

Contractor Parking

Trucks from the south willexit I-5 at Gilman Driveand stage on GilmanDrive. Trucks from thenorth will exit I-5 atGenesee Avenue andtravel along North TorreyPines Road.

NOTES

N

Rev 8

Page 5: Summer 2018 - Fall 2020 Constructionsenate.ucsd.edu/media/314737/...ntplln-academic-presentation-rev8-f… · Summer 2018 2019 2020 Fall Winter Spring Summer Fall Winter Spring Summer

UC San DiegoNorth Torrey Pines Living Learning Neighborhood

Off Site Construction Logistics Plan

Summer

2018 2019 2020

Fall Winter Spring Summer Fall Winter Spring Summer

KEY

Contractor Morning ShuttleRoute

Contractor AfternoonShuttle Route

Trucking Route

Alternate Trucking Route

Construction Site Fence

Const.SiteP302

P303

P206

P304

P384

P357

PangeaParking

Structure

Typical Work Hours: 7:00 AM - 3:30 PMMonday - Friday

Construction workers willarrive at the contractorparking area (glider port)5:30 AM - 7:00 AM andshuttle to the constructionsite.

An afternoon shuttle willbe utilized from 3:00 PM - 4:30 PM fromthe site to the glider port.

NOTES

N

Rev 8

ContractorParking

UCSD Parking

Page 6: Summer 2018 - Fall 2020 Constructionsenate.ucsd.edu/media/314737/...ntplln-academic-presentation-rev8-f… · Summer 2018 2019 2020 Fall Winter Spring Summer Fall Winter Spring Summer

UC San DiegoNorth Torrey Pines Living Learning Neighborhood

Shuttle Routes & Available Parking

Summer

2018 2019 2020

Fall Winter Spring Summer Fall Winter Spring Summer

KEY

UCSD West CampusConnector Shuttle Route

Alternate UCSD WestCampus ConnectorShuttle Route DURINGCONSTRUCTION

UCSD South CampusShuttle Route

UCSD SIO Shuttle Route

UCSD Shuttle Stop

UCSD Shuttle StopUnavailable DURINGCONSTRUCTION

PangeaParking

StructureCraig

VenterInstitute

Const.Site

MuirCollege

MuirField

GalbraithHall

FutureOsler

ParkingStructureFall 2018

Veterans AffairsMedical Center

GeiselLibrary

AtkinsonHall

ThurgoodMarshallCollege

HopkinsParking

Structure

P102

P103

P206

P303P304

P302

P310

N

MandevilleCenter

UCSD Shuttle Tracking:

ucsdbus.com/map

Walking Times from theMandeville Center ShuttleStop:

2 Minutes to Faculty Club

3 Minutes to Muir College

4 Minutes to Peterson

NOTES

Rev 8

Page 7: Summer 2018 - Fall 2020 Constructionsenate.ucsd.edu/media/314737/...ntplln-academic-presentation-rev8-f… · Summer 2018 2019 2020 Fall Winter Spring Summer Fall Winter Spring Summer

UC San DiegoNorth Torrey Pines Living Learning Neighborhood

Conditions Prior to the Start of Construction

Summer

2018 2019 2020

Fall Winter Spring Summer Fall Winter Spring Summer

Parking LotP208

Parking LotP207

P302P303KEY

Pedestrian Route

Existing UCSDShuttle Route

Existing UCSDShuttle Stop

N

Rev 8

Page 8: Summer 2018 - Fall 2020 Constructionsenate.ucsd.edu/media/314737/...ntplln-academic-presentation-rev8-f… · Summer 2018 2019 2020 Fall Winter Spring Summer Fall Winter Spring Summer

MUIR COLLEGE LN

UC San DiegoNorth Torrey Pines Living Learning Neighborhood

Conditions During Construction

Summer

2018 2019 2020

Fall Winter Spring Summer Fall Winter Spring Summer

P302P303

KEY

Pedestrian Route

Construction Fence

Periodic Lane Closureswith Traffic Control

UCSD Shuttle StopUnavailable DURINGCONSTRUCTION

N

Construction Hours:

Mon - Fri, 7 AM - 3:30 PM

There will be a 6' tall chainlink fence with green screensurrounding theconstruction site, job sitetrailers, and contractorparking lot at the glider port.

There will be no site lightingafter hours. Contractor willbe required to light the newbuilding's stair towers atnight.

NOTES

Construction Site

Periodic laneclosures duringSUMMERS for

utility work

NewEntrance and

Exit Lanes

Rev 8

NewSidewalk

Periodic laneclosures duringSUMMERS for

utility work

Page 9: Summer 2018 - Fall 2020 Constructionsenate.ucsd.edu/media/314737/...ntplln-academic-presentation-rev8-f… · Summer 2018 2019 2020 Fall Winter Spring Summer Fall Winter Spring Summer

UC San DiegoNorth Torrey Pines Living Learning Neighborhood

Excavation & Early Foundations

Summer

2018 2019 2020

Fall Winter Spring Summer Fall Winter Spring Summer

2021

Fall Winter Spring

Rev 8

Page 10: Summer 2018 - Fall 2020 Constructionsenate.ucsd.edu/media/314737/...ntplln-academic-presentation-rev8-f… · Summer 2018 2019 2020 Fall Winter Spring Summer Fall Winter Spring Summer

UC San DiegoNorth Torrey Pines Living Learning Neighborhood

Late Foundations & Above Ground Structure

Summer

2018 2019 2020

Fall Winter Spring Summer Fall Winter Spring Summer

2021

Fall Winter Spring

Rev 8

Page 11: Summer 2018 - Fall 2020 Constructionsenate.ucsd.edu/media/314737/...ntplln-academic-presentation-rev8-f… · Summer 2018 2019 2020 Fall Winter Spring Summer Fall Winter Spring Summer

UC San DiegoNorth Torrey Pines Living Learning Neighborhood

Above Ground Structure & Building Envelope

Summer

2018 2019 2020

Fall Winter Spring Summer Fall Winter Spring Summer

2021

Fall Winter Spring

Rev 8

Page 12: Summer 2018 - Fall 2020 Constructionsenate.ucsd.edu/media/314737/...ntplln-academic-presentation-rev8-f… · Summer 2018 2019 2020 Fall Winter Spring Summer Fall Winter Spring Summer

UC San DiegoNorth Torrey Pines Living Learning Neighborhood

Building Envelope & Interior Finishes

Summer

2018 2019 2020

Fall Winter Spring Summer Fall Winter Spring Summer

2021

Fall Winter Spring

Rev 8

Page 13: Summer 2018 - Fall 2020 Constructionsenate.ucsd.edu/media/314737/...ntplln-academic-presentation-rev8-f… · Summer 2018 2019 2020 Fall Winter Spring Summer Fall Winter Spring Summer

UC San DiegoNorth Torrey Pines Living Learning Neighborhood

Sitework Completion

Summer

2018 2019 2020

Fall Winter Spring Summer Fall Winter Spring Summer

2021

Fall Winter Spring

Rev 8

SCHOLARS DRIVE

Page 14: Summer 2018 - Fall 2020 Constructionsenate.ucsd.edu/media/314737/...ntplln-academic-presentation-rev8-f… · Summer 2018 2019 2020 Fall Winter Spring Summer Fall Winter Spring Summer

UC San DiegoNorth Torrey Pines Living Learning Neighborhood

Project Completion

Summer

2018 2019 2020

Fall Winter Spring Summer Fall Winter Spring Summer

2021

Fall Winter Spring

N. TORREY PINES ROADMUIR

COLL

EGE DRIV

E

Rev 7