Summary Report - Transport & Mobility Leuven · Rhine rail route. The study was carried out in...
Transcript of Summary Report - Transport & Mobility Leuven · Rhine rail route. The study was carried out in...
3RX Feasibility study alternative Rhein – Ruhr Rail Connection
DECEMBER 2017
Summary Report
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
2
Authors:
WIM SPIT Overall project leader
KRIS CASTELEYN Work package Environment
ROBERT JAN ROOS Work package Technical
GRIET DE CEUSTER Work package SCBA
KOEN VERVOORT Work package Traffic
WOLF-DIETRICH GEITZ Work package Financing
Robert jan roOS
Consultant
CARL VERELST Project manager
Version:
Final - December 2017
"The sole responsibility of this publication lies with the author. The European Union
is not responsible for any use that may be made of the information contained
therein."
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
3
CONTENTS
TABLE OF FIGURES 5
PREFACE 7
1 BACKGROUND 9
1.1 History of the Iron Rhine 9
1.2 Market logic Iron Rhine 9
1.3 Government policies 10
2 THE 3RX ROUTE 13
2.1 Present situation 13
2.2 Review of the present infrastructure 16
2.3 Identified measures 17
2.4 Environmental feasibility of measures 19
2.5 Investment costs 3RX 20
2.6 Costs of other alternatives 23
2.7 Planning 23
3 TRAFFIC DEMAND 25
3.1 Present traffic 25
3.2 Future traffic 29
4 SOCIO-ECONOMIC COSTS AND BENEFITS 33
4.1 Methodology 33
4.2 Project effects 34
4.3 Results 35
4.4 Sensitivity analysis 37
5 FINANCIAL ANALYSIS 41
6 FINANCING OPTIONS 43
7 RISK ANALYSIS 45
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
4
8 NEXT STEPS 49
8.1 Legal road map 49
8.2 Process architecture 52
APPENDIX A 57
APPENDIX B – TASK REPORTS 59
R1 – Introduction 61
R2 – The logic of a solution Iron Rhine 63
R3 - Present situation 65
R4 & R5 – Required Quality and Capacity 67
R6 – Environmental Assessment 69
R7 – Stakeholder analysis 71
R8 & R9 – Road map for realization 73
R10 – Atlas 75
T1 – T4 – Costs, Technical variants and planning 77
E1 – Present traffic 79
E2 – Traffic forecast 81
E3 – E5 – Social Cost Benefit Analysis (SCBA) 83
E6 – Risk analysis 85
E7 – Financial analysis 87
E8 – Financing options 89
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
5
TABLE OF FIGURES
Figure 1: Planning of works 24
Figure 2: Share of East-West rail freight traffic for the relevant O-D’s (% train count,
2015) 26
Figure 3: Montzen border crossing train counts per day in 2015 28
Figure 4: Montzen border crossing train counts per day in 2015 28
Figure 5: Autonomous growth of East-West rail freight trains (daily counts) 29
Figure 6: Different steps within a SCBA (Based on Gauderis, 2013) 33
Figure 7: Flow chart showing project management connected with public relations 54
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
7
PREFACE
This report presents the findings of a study of the feasibility of the 3RX route: an
alternative rail route between the seaports of the North Sea and the industrial Rhein
Ruhr Area in Germany, which is based on existing rail infrastructure. The 3RX route
has been developed as an alternative option for reactivation of the Historical Iron
Rhine rail route.
The study was carried out in December 2015-December 2017 and was financed by
the Flemish Government with co-financing by the European Union (Connecting
Europe Facility).
This summary report is based on the various task reports that have been prepared
during the study. It describes the various analyses carried out and summarizes the
main findings of the task reports. It does not contain new information. More details can
be found in these task reports.
The study was overseen by a Steering Committee consisting of representatives of the
five national and regional governments involved, i.e.:
• Flanders
• North Rhine-Westphalia
• Belgium
• Germany
• The Netherlands
The list of members of the Steering Committee can be found in Appendix A to this
report.
The study has been carried out by a consortium of companies from the three
countries involved: Arcadis (Belgium, Germany, The Netherlands), Railistics
(Germany), Transport and Mobility Leuven (Belgium) and Ecorys (The Netherlands).
On behalf of the consortium I would like to express my gratitude to the members of
the Steering Committee for their valuable contributions to the study and the
stimulating discussions on the various reports.
In addition I would like to thank the representatives of the three infrastructure
providers involved: Infrabel, DB-Netz and ProRail.
Last, but not least, I would like to thank the Flemish government for providing the
support we needed, thereby enabling this challenging study.
Rotterdam, December 2017
Wim Spit, Project leader
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
9
1 BACKGROUND
1.1 History of the Iron Rhine
The Treaty of London of 1839, which formalized the separation between Belgium and
the Netherlands, gave Belgium the right to establish a direct rail connection between
Antwerp and Germany across Dutch territory. The subsequent Iron Rhine Treaty of
1873 set out the modalities of a rail connection between Antwerp and
Mönchengladbach, via Weert and Roermond. This route is called the ‘historical Iron
Rhine route’.
The Iron Rhine was operational as a rail freight transport route until 1991. After years
of inactivity, in 1999 the Belgian and Dutch ministers signed a Memorandum of
Understanding with the purpose of reactivating the dormant historical route. However,
in the years that followed no agreement could be reached on the division of costs of
its reactivation.
In 2005 the case was brought to the Permanent Court of Arbitration. The tribunal
confirmed Belgium’s right of way to Germany across Dutch territory. Equally so the
tribunal determined the methodology for the division of costs of reactivation of the
route between the two countries.
However, the prospect of a reactivated historical route met with strong opposition,
partially because the rail section passes through the Dutch nature reserve De
Meinweg. Alternative routes were considered to find a more acceptable and viable
solution. One such alternative is the ‘A52 route’ which follows the route of the A52
motorway in Germany. Another alternative is the so-called “Dritte Weg” or Rhein-Ruhr
Rail Connection (3RX).
This report focuses on the technical, environmental and economic feasibility of this
3RX-route. In the economic appraisal the route is compared with the two other
alternatives to revitalise the ”Iron Rhine”, namely the Historical Route and the A52-
route.
1.2 Market logic Iron Rhine
Presently the Montzen-route is the predominant route for rail freight transport between
the Flemish seaports and the German hinterland. However, this route has several
limitations. Firstly, the competitiveness of the Montzen-route versus road transport is
negatively affected by its longer transport distance and longer transport time. The
longer distance partially results from the southern bend around the Netherlands,
before tracks go up north again to the Ruhr Area.
Secondly, several characteristics of the route such as the inclinations along the route
and the need to change direction at Aachen for southbound trains, have a negative
impact on time and costs.
Thirdly, there are few alternatives to the Montzen-route. The alternative Brabant-,
Betuwe- and Athus-Meuse routes all imply much longer travel distances, as well as
the need for trains to change direction. Moreover, the capacity of these routes to cope
with additional rail freight is limited. This means that in case of a major calamity on the
Montzen route east-west rail freight transport is considerably hampered.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
10
1.3 Government policies
European Union
Although the Iron Rhine is not part of the TEN-T Core Network, European policy (e.g.
TEN-T Coordinator) considers it a relevant route. The project aligns with the broader
rail freight transport agenda which sets out the EU’s objective to promote sustainable
mobility by rebalancing the modal split in favour of rail.
Belgium
The Iron Rhine is acknowledged by the Federal and Flemish governments as
important infrastructure, which potentially adds economic value to the Flemish ports
and contributes to a range of policy objectives, including modal shift and reduced
emissions. Positive spill-over effects are considered to exist for the regions of Kempen
and Northern Limburg, although there are also local concerns over adverse impacts.
Flanders’ rail strategy
Recently it has been decided that electrification of the line Mol-Neerpelt-Hamont, one
of Flanders’ rail priorities, will be realised by 2020. This project was included in the
virtuous debt settlement. The investment works cost € 46 million and are co-financed
by Europe.
Germany
In Germany rail infrastructure investments are prioritized by both federal and regional
policy as a means to mitigate road congestion and pollution. While the importance of
the Iron Rhine is acknowledged, local concerns regarding noise pollution are explicitly
addressed and externalities should be targeted through appropriate measures.
In the Bundesverkehrswegeplan 2030 that was published in 2016 a project is included
that specifically aims at facilitating passenger and freight rail traffic between Venlo and
Mönchengladbach. This project envisages, among other things, a double track
between Kaldenkirchen and Dülken. The cost benefit analysis was finalized in
November 2017 and shows a favourable result. The Bundesverkehrswegeplan now
rates the project as “Vordringlicher Bedarf”. This means that preparations for the
realisation can be started.
New coalition agreement in North Rhine-Westphalia
The chapter on logistics and transport in the new NRW coalition agreement of June
2017 explicitly mentions the importance of cross border railway connections,
specifically for freight transport: “At the European level we commit, together with our
partners in Belgium and the Netherlands, to a highly-performing railway connection
between the port of Antwerp and the European hinterland. This is also in the interest
of North Rhine-Westphalia.”
The Netherlands
In the Netherlands government policy acknowledges the importance of rail freight
transport, but the national government is not explicit about the Iron Rhine. The
instances when the Iron Rhine is discussed typically relate to local concerns about
noise pollution and environmental impacts. At the same time there are opportunities
identified in terms of synergies with logistic services and passenger transport in
Limburg.
In 2015 the province of Limburg started two CEF co-financed studies into
improvement of border crossing rail passenger traffic between the Netherlands and
Belgium and The Netherlands and Germany respectively. Some of the passenger
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
11
services are envisaged to use sections of the 3RX-route (i.e. Hamont – Weert and
Venlo – Mönchengladbach).
New coalition agreement in the Netherlands
The new Dutch coalition agreement of October 2017 reads as follows: “Following the
Belgian investment in the Antwerpen-Hamont line, the connecting section Hamont-
Weert will be reactivated for passenger trains, with co-funding from the regional
authorities. We will also examine how we can improve the connection from Eindhoven
to Germany.” This is part of a broader strategy to work towards eliminating obstacles
which people experience in the border regions.
Conclusion
It is concluded that governments generally favour a modal shift towards rail and
greater seaport-hinterland connectivity via rail. Reactivation of the Iron Rhine could fit
within this framework.
Local opposition, predominantly in the Netherlands, however, needs to be
acknowledged. Several concerns have an impact on the debate. These concerns
mainly are related to the environmental impacts and the impacts on living conditions
along the line.
Recently various decisions have been taken by the Belgian and German governments
to invest in infrastructure on the rail routes Mol – Hamont and Kaldenkirchen-
Odenkirchen which are part of the 3RX route. In the Netherlands the focus is on
improving cross border passenger services with Belgium and Germany.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
13
2 THE 3RX ROUTE
The main goal of this study is to assess the technical, environmental, financial and
economic feasibility of the 3RX route. The route is compared to the previously studied
Historical Iron Rhine and A52-routes. All three routes can be seen as options for
revitalisation of the Iron Rhine. Compared to the other two options, the 3RX uses
existing and operational rail infrastructure as much as possible, while at the same time
taking into account the limitations posed by ecologically sensitive areas.
2.1 Present situation
General overview
The Historical Iron Rhine route (named “‘historical route” in this report) consists of
several railway lines in Belgium, the Netherlands and Germany. It runs from Antwerp
via Lier and northern Belgium to the town of Weert in the Netherlands. From there it
continues to Roermond and Mönchengladbach to connect to the industrial areas in
the Rhein Ruhr Area.
Map 1: The Historic Iron Rhine, parallel routes and hinterland connections, Source: ARTECORAIL, Task report R10: Atlas
The 3RX route is a variation on the historical route, as it follows a different route
between Roermond and Mönchengladbach. Instead of continuing east from
Roermond, the 3RX route diverts north to the town Venlo. From Venlo the route runs
southeast to the town of Viersen in Germany, and from thereon either south to
Mönchengladbach / Cologne or to Duisburg in the northeast.
The A52-route lies in between the historical and 3RX routes and includes a new
section of rail between Roermond and Mönchengladbach (shown as a dotted line on
the map).
Lastly, the Montzen-route connects Antwerp via Lier to Aarschot and continues via the
village of Montzen to Aachen. From here trains can go either north to
Mönchengladbach or east to Cologne and beyond.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
14
Present use
At present there are no regular trains running the full length of either the historical or
the 3RX-route. The ore train from the port of Antwerp to the zinc factory at Budel near
the Belgian-Dutch border has the highest mileage on the original route. Meanwhile
there is intense freight traffic from/to Germany along parallel routes in Belgium
(Montzen-route) and the Netherlands (Brabant-route, Betuwe-route).
Infrastructure
The historical and 3RX-routes run through three countries and have a variety of
systems for signalling and power supply. In Belgium the track is electrified with the
Belgian 3000 Volt DC system up to the station of Mol and has the Belgian signalling
system with TBL train protection system. In the Netherlands it has only got catenary
between Weert and Roermond, as well as between Venlo and the German border.
Between Weert and Roermond it is electrified with the Dutch 1800 Volt DC and in
Venlo there are both the Dutch 1800 Volt as well as the German 15000 Volt AC
system. The tracks for passenger traffic are equipped with a switchable system and
the tracks for freight traffic have the 1800 Volt on the west, no catenary in the middle
and 15000 Volt on the east up to the German border and further.
The signalling system in the Netherlands is the Dutch system with automatic train
protection by the ATB system. There is no ATB system between the Belgian border
and Weert. At the stations of Weert, Roermond and Venlo there is ATB EG (first
generation) with an added layer of ATB VV (improved version). The ATB EG is also
active on the section between Weert and Roermond. On the Maas railway line
between Roermond and Venlo the ATB NG (new generation) is the train protection
system. At Venlo and into Germany there is the German Indusi train protection system
(also known as PZB).
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
15
Map 2: Infrastructure characteristics; source: ARTECORAIL Task report E3: Present infrastructure
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
16
Gradients
3RX route
The 3RX-route generally runs through very flat terrain and most gradients can be
found at bridges to cross rivers and canals. Between Venlo and Kaldenkirchen,
however, there is a considerable natural incline with a steep gradient. It rises from a
height of 22 metres (above sea level) to 42 metres in just over 2,250 metres. In the
past the heaviest freight trains (up to 5,400 tons excl. locomotives) used banking
locomotives to push the train onto and over the slope when track conditions were poor
(slippery due to leaves in the fall).
There is a risk of heavy trains coming to a stop on the gradient and this happens
occasionally. In such an event a helper locomotive from Venlo pulls the train back at
the cost of delays. There are no other significant gradients along the route.
Montzen route
The Montzen route also features some slopes with high gradients. Train weight is
limited to 1,550 tons from Aachen to Belgium. With a banking engine to push the train
onto the slope from Aachen the maximum weight increases to 2,200 tons for a single
locomotive train. In comparison, the Betuwe route has a maximum weight of 3,600
tons for a single locomotive.
2.2 Review of the present infrastructure
A detailed review has been made of the infrastructure of the 3RX route. Below the
results are summarized by section.
Antwerp - Mol
The railway between the stations of Antwerp and Mol consists of a double track
electrified line. From Antwerp to Lier there are about 30 freight trains every day in both
directions. Between Lier and Mol this number drops to less than 10 freight trains in
both directions. On the first stretch of the track from Antwerp to Lier there is intensive
passenger traffic that shares the track with the freight trains.
Mol - Weert
The railway section between the stations of Mol (Belgium) and Weert (The
Netherlands) consists of a single track non-electrified line. The track is in service at
the moment, but there are no regular trains running the full distance between Hamont
and Weert. Zinc ore trains use the section between Mol and Budel just across the
border in The Netherlands. Because of environmental legislation freight train traffic is
presently limited to a maximum of 51 trains per week.
Points of attention for improvement of the track section Hamont - Weert to allow
intensive freight train traffic between the Netherlands and Belgium include:
• Level Crossing Safety (adding automatic level crossings and changes of the
annunciation)
• Alignment; adjusting the alignment (removal of nods)
• Drainage (ballast bed lies low)
• Structures (state and capability for higher speeds and loads)
• Installing Automatic Train Protection System (ATPS)
• Connection at Weert (Interference with other traffic and ATPS)
• Environment (noise/vibration/wildlife)
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
17
Weert - Roermond
The railway line between the stations of Weert and Roermond is part of the Dutch
core railway network and is used by both intercity passenger trains and freight trains.
It is an electrified double track line without intermediate stations or branches and
features a bridge over the river Maas near Roermond.
Present freight traffic avail of two paths (train time slots) an hour in both directions,
which are used by several freight trains per day, both international as domestic. The
section serves as a freight route from the Netherlands to Belgium via Maastricht –
Luik. There are passing opportunities at the stations of Weert and Roermond.
Roermond – Venlo
The railway line between the stations of Roermond and Venlo, also known as the
southern Maas-line, is part of the Dutch regional railway network. It is used by
regional passenger trains and by freight trains. It consists of a single track line with
three intermediate stations, all with passing possibilities, though only two of a length
suitable for freight traffic.
Freight traffic avails of two paths an hour in both directions, which are used by several
freight trains a day. The section serves as a freight route from the Netherlands to
Germany via Venlo – Kaldenkirchen and to Belgium via Maastricht and also serves
domestic freight traffic.
Venlo – Mönchengladbach
The railway line between the border station of Venlo (the Netherlands) and
Mönchengladbach (Germany) is used by regional and freight trains. It is partly double
track and partly single track line, equipped with the German catenary and signalling
system. Between Venlo and Kaldenkirchen it features a serious gradient.
Present freight traffic consists of three paths an hour in both directions which are used
by several trains a day. It is an important freight route from the Netherlands to
Germany and beyond and also serves as a back-up route during problems or
maintenance on the cargo dedicated Betuwe-route.
Between Venlo and Mönchengladbach runs the RE 13 (Regional-Express) passenger
services as Maas – Wupper Express, a regional train service from Eurobahn which
operates every hour in both directions.
2.3 Identified measures
General
This feasibility study uses the same basic assumptions as previous reports on the two
other alternatives (Historical Route and A52). This implies that the 3RX route has
been designed in such a way that it offers capacity for (at least) 72 freight trains per
day (both ways together). This number of freight trains is based on former studies and
checked against the traffic forecast.
Below follows the full list of basic assumptions for the design of the route:
Capacity: 72 freight trains a day, 36 in each direction
Train characteristic: Train length 750m; Maximum axle load of 22,5 tons (class D)
Electrification: Fully electrified line
Change of direction:
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
18
• Based on the present infrastructure, freight trains have to change direction twice
(in Roermond, Venlo) or three times (also in Viersen). According to railway
operators consulted by the study team the route should have at maximum one
change of direction, in order to have a commercially viable route. More than one
time changing direction is not an option, as this would not deliver a competitive rail
product. In principle this change of direction can take place in either Roermond,
Venlo or Viersen.
• Freight trains changing direction have an additional technical turnaround time of at
least 45 minutes (sometimes longer in case of lack of capacity).
Connections:
• The length of connections should be sufficient for freight trains to enter and leave
the main track without disturbing other trains and lead to capacity problems.
• There should be enough double track/passing tracks to ensure a robust rail
network, taking into account possible delays of freight trains.
Travelling time:
• The travelling time for passenger trains is derived from their present operating
schedule.
• The travelling time for freight trains is estimated by means of track length and
average speed. This average speed is 80 km/h between Kaldenkirchen and
Dülken (trains don’t have to stop).
Based on these track quality expectations the necessary and potentially needed
measures have been identified for each section of the 3RX route. They are
summarized on the table below.
Table 1 Identified measures for 3RX
Section Identified measures
Lier – Herentals Possibly addition and/or lengthening of passing tracks
Possibly addition of Dynamic Traffic Management
Herentals – Mol Possibly elongation of passing tracks (Herentals)
Maybe addition of passing tracks
Mol – Hamont
Possibly elongation of the tracks used by freight trains (Mol)
Electrification of circa 32 kilometres of track
Addition and/or elongation of passing tracks
In case of growing traffic partial or complete doubling needed
Hamont – Weert
Electrification of freight tracks (Hamont)
Possibly addition and/or elongation of passing tracks (Hamont)
Electrification of circa 9 kilometres of track
Installing signalling system and automatic train protection
system
Upgrade level crossings
Possibly raise track speed
Weert
Two tracks at the junction (one for eastbound and one for
westbound 3RX trains) or creation of waiting tracks of 750
meters at Weert station
New bridge across the canal and possibly a fly-over
Weert – Roermond
Optimize freight paths
Implement Dynamic Traffic Management
Risk Analysis of the level crossings
Roermond – Venlo
Connection curve east of the Maas bridge (Roermond)
Doubling parts of the existing single track sections
Risk Analysis of the level crossings
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
19
Venlo
Possibly connection curve near Tegelen
If no curve is available the following measures are needed:
• Number of tracks on the Venlo freight section;
• To make it possible that the 3RX train can enter and
leave the freight section with DB-Netz 15.000 Volts AC
and ProRail 1.500 DC catenary system;
• The train safety system on the freight section has to be
changed;
• Creation of (extra) tracks with a length, net train length,
of 750 meters plus the length of (shunting) locomotives;
• Noise reduction for the environment
Venlo – Monchengladbach
Doubling parts of the existing single-track sections.
Connection curve at Viersen
Risk Analysis of the level crossings
Source: ARTECORAIL Task report R4/R5: Required quality and Required capacity
2.4 Environmental feasibility of measures
The measures necessary to develop the 3RX-route have been assessed on their
environmental effects. The main conclusions are as follows.
In Belgium, no land take will occur because only a doubling of the track is necessary.
The doubling of the track can increase the disturbance of surrounding areas. These
effects do not differ between the Historical route, A52 route and 3RX-route.
In the Netherlands and Germany, the modifications of the track for shunting or curves
will cause additional environmental effects. The variants where trains make use of the
yard cause more nuisance (noise and vibrations) and have a higher risk for local
residents. This is a logical consequence of the fact that a curve (or tunnel) prevent
that trains have to drive through the urban area. The curve (and tunnel) options,
however, imply that a new track must be constructed so that land take occurs. The
effects do depend on the location and dimensions of the new track.
Along the existing track, the number of local residents that will be hampered will
increase. Measures to reduce the nuisance caused by noise and vibrations will be
necessary.
Further investigations will be needed once the combination options for yards/curves is
chosen and when the modifications of the track have been elaborated in more detail.
Section Hamont - Weert
In the Netherlands, the 3RX route crosses the Birds Directive area “Weerter- and
Budelerbergen & Ringselven”. On this section presently exist a maximum allowed
number of freight trains.
For the Belgian/Dutch border to Weert, a request for reactivation has been submitted
by ProRail. Opinions on the request have been submitted and eventually a decision has
been made at the session of the Council of State. This decision specifies that a
maximum 51 freight trains per week are allowed. It also specifies a calculation rule if
freight paths are used during vulnerable time periods. The Council of State has
substantiated its decision.
On 7 October 2014, the Secretary of State of Economic Affairs responded to the
"decision on the appeal", in which, alongside substantive issues such as the number of
trains per day, it is specified that if a decision to reactivate the Iron Rhine were to be
made, it would entail a wholly new procedure with further decisions.
Without mitigating measures, the noise contour of 40 dB LAeq, 24h is located
approximately 690 m from the railway and the 45 dB contour approximately at 390 m.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
20
As in the current situation there are almost no trains on the railway between the
Belgian/Dutch border and Weert, a significant disturbance will occur within this Natura
2000 area. An acoustic barrier of 5 to 6 m high will be needed to ensure a standstill
situation. The effects of nitrogen deposition are not considered relevant since full
electrification is assumed.
2.5 Investment costs 3RX
Based on the necessary measures identified by section, cost estimates have been
prepared for the measures needed. Some measures are needed in all configurations
of the 3RX-route. These are the so-called fixed elements.
For other elements of the route, in particular at Roermond, Venlo and Viersen, various
options have been developed, which either consist of works in the station yards (in
case of a change of direction) or construction of a curve connection two rail sections.
These are the variable elements of the route.
The tables below give an overview of the development costs of the fixed and variable
elements, inclusive of provisions for risks, excluding VAT. All estimates have an
uncertainty margin of +/- 30%.
Table 2 Investment costs fixed elements 3RX-route (in million Euro, price level 2015, excluding VAT)
Sections Works Cost (mln Euro)
Mol – Hamont – border BE-NL Electrification 70.0 a)
Track doubling Neerpelt-
Balen 46.5
Track doubling Neerpelt -
Hamont 26.5
Weert Connection Weert 62.3
Weert – Roermond - Venlo ERTMS 15.9
Roermond – Venlo Track doubling 213.4
Kaldenkirchen – Dülken Track doubling 114.4 b)
TOTAL FIXED ELEMENTS 549.0 c)
TOTAL FIXED ELEMENTS
corrected for decisions taken 388.3
Source: Task report T1-4 Cost and timing a) The total cost estimate of the electrification is 70.0 mln. A major part of this (46.3 mln) is already covered by the CEF project Mol – Hamont – Weert, which is co-funded by CEF. b) Cost estimate prepared by German consultants for the BVWP project 025. c) Due to developments in 2017 investment In Mol - Hamont and Kaldenkirchen - Dülken have already been decided by the respective governments. The net additional investment cost for fixed elements is therefore lower.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
21
Table 3 Investment costs for various options for variable elements of the 3RX-route (in mln Euro, price level 2015, excluding VAT)
Station Works Cost (mln Euro) a)
Roermond Yard 45.7
Curve 128.2
Venlo Yard 24.4
Buried curve 407.4 plus 103.4 b)
Bored tunnel 762.0 plus 103.4 b)
Viersen Yard 0
Above ground curve 84.4
Single track curve
at ground level 19.0 c)
Double track curve
at ground level 68.5
Buried curve 327.8
Bored curve 802.6
Source: ARTECORAIL, Task report T1-4: Costing and timing a) Mean estimate, with an uncertainty margin of + / - 30%. b) When a curve is chosen additional works are needed on the track between Venlo and Kaldenkirchen (80.7 mln) and in Kaldenkirchen yard (22.7 mln) c) Option developed for the German federal ministry as part of BVWP project 025. It does not satisfy the condition that freight trains do not interrupt other traffic.
Combination of the options for the variable elements gives several possible
configurations for development of the 3RX-route. The most expensive combination of
options to develop the 3RX route requires € 2.3 billion (excluding VAT, including risk
provisions). This gives a route with three curves, implying that no change of direction
is required. It also has optimal embedding in the physical environment, including a
tunnel near Venlo.
Cheapest option 3RX
The cheapest option that has the required quality (only one change direction) and
quantity (72 trains per day), requires a total investment of € 770 million (excluding
VAT, including risk provision). This combination has curves in Roermond and Viersen
(i.e. the double track curve at ground level). If the single track option is taken in
Viersen total costs would be approximately € 50 million lower.1
This cost estimate does not yet take into account the decisions that have recently
been taken by the Belgian and German governments, on electrification of Mol -
Hamont (with co-financing from CEF) and on the BVWP project 025 Kaldenkirchen -
Odenkirchen (including track doubling Kaldenkirchen – Dülken and a single track
curve in Viersen). When these decided investments are taken into account, the
additional costs for construction works needed realise the 3RX amount to € 590
million.
1 This option does not satisfy the design criterion of a capacity of 72 freight trains per day.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
22
The following table shows total additional costs for this configuration of the 3RX
project, including risk provisions, but excluding VAT and study costs.
Table 4: Additional investment costs 3RX (million euro), including mitigating measures and provision for risk, excluding VAT
BE NL DE Total
Track Belgium € -96.70
(electrification already
in ref: € -46.30)
Weert € -62.32
ERTMS € -15.88
Track doubling
Roermond-Venlo
€ -213.44
Curve at Roermond € -128.19
Yard Venlo € -24.42
Full double track curve
at Viersen
(level 0 variant)
€ -49.50
(already in reference
case: € -19.00)
Kaldenkirchen- Dülken (already in reference
case: € -114.40)
Total € -96.70 € -444.25 € -49.50 € -590.45
Source: ARTECORAIL, Task report E3/E4/E5: Social cost benefit analysis
In addition the costs for preparatory studies have to be taken into account. Adding the
study costs to the investment costs gives the following total costs.
Table 5: Total investment costs including study costs (million euro) excluding VAT.
BE NL DE Total
3RX € -97 € -467 € -51 € -614
Source: ARTECORAIL, Task report E3/E4/E5: Social cost benefit analysis
The following table shows the incremental investment and preparation costs including
VAT. It should be noted that the SCBA has been carried out in factor costs, which
means that taxes and duties are not included. The information below is shown for
budget purposes only.
Table 6: Total investment costs including study costs (million euro) including VAT (19% in case of Germany, 21% in case of Belgium and The Netherlands).
BE NL DE Total
3RX € -117 € -564 € -61 € -742
Source: ARTECORAIL
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
23
2.6 Costs of other alternatives
In the past cost estimates have been prepared for the Historic route and the A52
route. These have been updated for the purpose of the SCBA. The table below
summarizes the costs for the three alternatives. It shows that the investment costs are
the highest for the Historic route, followed by the A52.
Table 7: Total investment costs (million euro) excluding VAT and excluding study costs
BE NL DE Total
3RX € -96.70 € -444.25 € -49.50 € -590.45
HIS € -96.70 € -611.00 € -459.00 € -1.166.70
A52 € -96.70 € -311.00 € -571.00 € -978.70
Source: ARTECORAIL, Task report E3/E4/E5: Social cost benefit analysis
2.7 Planning
The next diagram shows a feasible planning of construction works. It does not include
the time required for political decisions, nor for authorisation procedures and possible
objections. It does, however, allow time for testing and releasing the track in the final
phase.
The need for preparation studies varies by country, but will take 8 to 10 years in The
Netherlands. Design and construction varies per section and is estimated to take
between 7 and 13 years (see figure below).
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
24
Figure 1: Planning of works
Source: ARTECORAIL, Task report T1-4: Costing and timing
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
25
3 TRAFFIC DEMAND
3.1 Present traffic
A detailed analysis has been carried out of available traffic data in the relevant area.
These data relate to base year 2015 and were provided by the infrastructure
managers Infrabel, DB-Netz and ProRail. In the analysis the data have been used on
realised traffic. Note that this data set shows a lower traffic level than the data on
planned traffic which are also available. The analysis has resulted in the following
insights.
Route characteristics
Operators currently identify two competitive routes catering for east-west flows
between Belgium and the Rhein Ruhr Area (and destinations further beyond): the
Brabant route and the Montzen route. The Brabant route is a logical choice when the
payload per locomotive is higher, compensating the disadvantage of crossing an
additional country (The Netherlands). However, the Montzen route is the most
advantageous route from cost, organisational and technical perspective. While trains
with a heavier payload could encounter issues, the route is the most competitive
between Belgium and the east.
Table 8: Characteristics rail freight transport Antwerp – Duisburg via Brabant or Montzen route
Kilometres
Direction changes (count)
Path quality (hours lost)
Total cost per freight train
Brabant route 235 1 1 € 4,800
Montzen route 256 0 0 € 4,500
Source: ARTECORAIL, Task report E1: Present traffic
Use
Data provided by Infrabel and ProRail show that in 2015 on an annual basis about
26,000 trains moved between Belgium and the east, constituting about 16.4 million
net tonnes of freight. This reflects on average 71 trains per day. This is the total of the
Montzen border crossing and all transit trains through the Netherlands. So, not all of
these trains pass the border crossings at Venlo (i.e. Brabant route) or Montzen.
Of the selected flows about 86% of the freight trains take the Montzen-route (on
average 61 trains daily) and about 14% (on average 10 trains daily) the Brabant-route,
clearly emphasizing the dominance of the Montzen-route. Trains on the Brabant route
include transit traffic and trains from or to the south of the Netherlands. The traffic with
origin or destination in the south of the Netherlands accounts for about 44% of total
trains. The traffic on the Montzen- route mostly heads to or originates from Antwerp
(48%), with the rest of Flanders and Wallonia taking shares of 41% and 11%
respectively.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
26
Figure 2: Share of East-West rail freight traffic for the relevant O-D’s (% train count, 2015)
Source: ARTECORAIL Task report E1: Present traffic, based on Infrabel (2015) and ProRail (2015)
14%
86%
Brabant route
Montzen route
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
27
Table 9: Freight volumes between selected EU regions (net mtons, 2015)
Destination
Origin
Flan
de
rs (
ex.
An
twe
rp)
An
twe
rp
Wal
lon
ia
Fran
ce
Ge
rman
y
Ital
y
Luxe
mb
urg
Swit
zerl
and
The
Ne
the
rlan
ds
UK
Oth
er
Gra
nd
To
tal
Flanders (ex. Antwerp) n.a. n.a. n.a. 0,02 1,71 1,75 0,10 0,09 0,35 0,00 0,15 4,17
Antwerp n.a. n.a. n.a. 0,44 2,96 1,42 0,43 1,16 1,04 0,03 7,48
Wallonia n.a. n.a. n.a. 0,60 1,37 0,23 0,36 0,01 0,48 0,00 3,06
France 0,02 0,51 0,08 0,00 0,00 0,00 0,03 0,66
Germany 1,88 2,13 0,39 0,01 0,19 0,00 0,01 0,12 4,73
Italy 1,72 0,60 0,07 0,00 2,39
Luxemburg 0,01 0,74 0,03 0,00 0,00 0,78
Switzerland 0,01 0,38 0,10 0,02 0,00 0,50
The Netherlands 0,21 0,61 0,29 0,01 0,04 0,01 1,17
UK 0,11 0,11
Other 0,23 0,02 0,00 0,00 0,25
Grand Total 4,09 4,99 0,96 1,09 6,40 3,41 0,89 1,26 1,92 0,13 0,18 25,31
Source: ARTECORAIL, Task report E1: Present traffic; based on Infrabel (2015)
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
28
On an average day the capacity of the Montzen route is sufficient to cope with the
number of freight trains. However, the figures also show that the number of trains vary
from day to day, and also during the day. Bottlenecks do occur, easily resulting in
delays and extra costs for freight. So the current situation is not optimal, especially at
peak times. This is exacerbated in situations when maintenance is carried out or in
case of calamities along the Montzen route.
Figure 3: Montzen border crossing train counts per day in 2015
Source: ARTECORAIL Task report E1: Present traffic, based on Infrabel (2015);
The figure below shows the same figures, but categorized to number of trains per day
in 2015. The figure once more illustrates the varying numbers of trains along the
Montzen route daily.
Figure 4: Montzen border crossing train counts per day in 2015
Source: ARTECORAIL Task report E1: Present traffic; based on Infrabel (2015)
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
29
3.2 Future traffic
This section provides an analysis of the future transport flows between Belgium and
its eastern hinterland for 2030 and 2040, in a situation with and without the (three
alternatives for the) Iron Rhine.
Future rail traffic (without new connection)
It is expected that the number of trains under autonomous growth in the medium
scenario shall increase to 103 trains by 2030 and 115 trains by 2040. This reflects a
growth of 45% to 62% compared to the current situation (71 trains).
In the low growth scenario, the number of trains is expected to increase to 95 trains by
2030 and 103 trains by 2040. This reflects a growth of 34% and 45% compared to the
current situation (71 trains per day).
Finally, in the high growth scenario the number of trains is expected to increase to 113
trains by 2030 and 129 trains by 2040. This reflects a growth of respectively 59% and
82%, compared to the current situation.
Figure 5: Autonomous growth of East-West rail freight trains (daily counts)
Source: ARTECORAIL Task report E2: Future Traffic
From a purely infrastructural perspective it can be argued that the capacity of both the
Montzen and the Brabant routes are both sufficient to deal with the growing number of
trains till 2040, provided that traffic is evenly spread over the week and throughout the
year.
However, with growing traffic the reliability of train services may increasingly become
an issue. Congestion effects could occur during certain peak moments depending on
the season, the weekday and the time of day. Calamities may intensify capacity
issues.
113
129
103
115
71
95103
0
20
40
60
80
100
120
140
20
15
20
16
20
17
20
18
20
19
20
20
20
21
20
22
20
23
20
24
20
25
20
26
20
27
20
28
20
29
20
30
20
31
20
32
20
33
20
34
20
35
20
36
20
37
20
38
20
39
20
40
Traffic (daily train count)
High Medium Low
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
30
Situation with a new connection
The Iron Rhine, be it the historical route, 3RX or A52, is primarily a competitive
alternative for traffic between the North Sea ports and the Rhein Ruhr Area (and
beyond). From a rail operator’s point-of-view the three alternatives differ in terms of
length and in the number of direction changes required.
Between Antwerp and Duisburg the Montzen route offers a direct route via Aachen,
even though it is a relatively long itinerary. Of the three Iron Rhine alternatives
considered, the A52-route provides a shorter itinerary without direction changes. Also
between Antwerp and Cologne the A52-route offers a direct connection without
direction changes.
From a rail operator’s point of view (based on total costs) the A52-route is the most
attractive route, followed by the historical route and the 3RX route. The differences in
competitiveness are substantial. The 3RX, assuming a design without a curve at
Venlo, always means one direction change and a longer route towards Duisburg and
Cologne. Reactivation of the historical route would not mean a need for direction
changes between Antwerp and Cologne.
The calculations for the medium growth scenario show that in 2040 for respectively
the 3RX-, the A52- and the historic route a total of 21, 50 and 36 freight trains will use
the Iron Rhine on a daily average. The Iron Rhine does substantially relieve the
Montzen route and the Brabant route. In all scenarios and alternatives the number of
trains on the Iron Rhine remains below the design limit of 72 trains per day on
average.
Table 10: Number of trains per Iron Rhine alternative in all scenarios, including the 3RX light and three curves alternatives (average daily train counts, in both directions)
2015
2030 2040
Low Medium High Low Medium High
Autonomous growth
Bra 10 a 12 13 15 13 15 17
Mon 61 82 90 99 89 100 113
TOTAL 71 95 103 113 103 115 129
3RX (2 curves)
Alternative
Bra 10 7 7 8 7 8 9
Mon 61 71 78 85 77 87 97
3RX X 17 19 20 18 21 23
TOTAL 71 95 104 113 103 115 130
A52 Alternative
Bra 10 4 4 4 4 4 5
Mon 61 52 57 62 56 63 71
A52 X 41 45 49 44 50 56
TOTAL 71 96 105 115 105 117 132
Historical Route
Bra 10 5 5 6 5 6 6
Mon 61 61 67 73 66 74 83
Hist X 29 32 35 32 36 40
TOTAL 71 95 104 114 103 116 130
Source: ARTECORAIL; Task Report E3: Future Traffic
a: Trains on the Brabant route include transit traffic and trains from or to the south of the Netherlands. The traffic with origin or destination in the south of the Netherlands accounts for about 44% of total trains.
The design of the 3RX route determines its competitiveness. A route including a curve
at Venlo, together with curves at Roermond and Viersen, results in a more attractive
option and a competitiveness comparable to that of the historical route. The analysis
also shows that in case of a lower quality (e.g. in case of ‘border penalties’) the
competitiveness of the 3RX significantly decreases, as can be seen from the following
table.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
31
Table 11: Number of trains per Iron Rhine alternative in all scenarios including train path delay (average daily train counts, in both directions)
2015
2030 2040
Low Medium High Low Medium High
3RX Time penalty
Bra 10 8 9 10 9 10 11
Mon 61 78 85 93 84 95 106
3RX X 9 10 11 10 11 12
TOTAL 71 95 104 113 103 115 129
Source: ARTECORAIL; Task Report E3: Future Traffic
The results show that the attractiveness of the three Iron Rhine alternatives
significantly decreases when taking into account the time penalty for passing The
Netherlands. Also less modal shift does occur. The sensitivity analysis thus underlines
the importance of establishing efficient operations on the Iron Rhine in order to
become a competitive alternative and attract traffic from the Brabant and Montzen-
routes.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
33
4 SOCIO-ECONOMIC COSTS AND BENEFITS
4.1 Methodology
The economic feasibility of the 3RX project has been assessed based on a cost-
benefit analysis. As each of the three countries involved has its own methodology for
carrying out a CBA, one common methodology has been developed which is as close
as possible to the European guidelines such as “Guide to COST-BENEFIT ANALYSIS
of investment projects, Economic appraisal tool for Cohesion Policy 2014-2020” and
„Better Regulation Guidelines and Toolbox“ van de EC .
For the practical execution of the SCBA we follow the different steps as described by
“Standaardmethodiek voor MKBA van transportinfrastructuurwerken – Algemene
leidraad”. This is consistent with the EU guidelines and the other national guidelines .
Where relevant, results from the previous studies for the project alternatives studied
before (Historical Iron Rhine and A52) have been used. However, as the transport
forecasts were updated, we redid some of the previous analyses. Hence the results
cannot be compared one to one with the 2009 study.
The figure below shows the different steps within a SCBA.
Figure 6: Different steps within a SCBA (Based on Gauderis, 2013)
Source: ARTECORAIL, Task report E3/E4/E5: Social cost benefit analysis
Reference case
An important aspect is the description of the reference case. The reference case is
the situation in which the Iron Rhine is not reactivated. This does not mean that
nothing else happens. It is based on the current situation (“as is”) including (transport)
policy which is already decided.
For example, CEF funding has been guaranteed for the electrification of the Belgian
section Mol-Weert. The project will receive a subsidy of 18.52 million euro (40% of the
eligible costs – estimated at 46.3 million Euro by Infrabel), and is part of the MIP of
Infrabel. This will impact the investment costs needed for all alternatives. We will
assume that this 46.3 million is decided policy. Hence the additional investment costs
for Belgium decrease.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
34
Another element in the reference case is the doubling of the Kaldenkirchen-Dülken
section. In the BVWP 2030 study, a cost estimate of 114.4 million Euro has been
made for this.
4.2 Project effects
In this step we describe the expected and relevant effects of the reactivation of the
Iron Rhine. This step takes into account the input which will come from previous
studies and the Spatial-environmental and Technical work package. Within this step
no calculations are made. The goal is to identify the most important effects and to
describe them qualitatively. The different effects can be categorized in four groups:
• Direct effects
• Indirect effects
• External effects
• Project costs.
The direct effects on the transport system follow from the differences in costs (time
and monetary) of transport and the freight flows in the reference and the project
alternatives. In this case they include the effects for rail within the project area. This
includes the effects on the infrastructure manager (infrastructure fee) as well as on the
operators (operational costs, time and money). These are strongly connected to the
results of the financial model and the traffic forecasts. For this project the following
direct effects are relevant:
a. Changes in monetary transport costs rail
b. Changes in travel time rail
c. Changes in robustness rail
d. Changes in infrastructure fee revenue
e. Changes in tax revenue (changes in excise duty revenue, changes in tax revenue
inland waterways)
f. Changes in travel time road via changes in congestion
g. Changes in travel time road due to rail crossings
h. Effects on passenger rail
The indirect effects are the effects of the reactivation on the wider economy. The idea
is that lower transport costs increase the competitiveness of companies, increasing
sales, production and employment. Goods and services become cheaper, increasing
the purchasing power of the consumer. Note that these wider economic effects also
include shifts in economic activity between regions.
In this SCBA we did not include the calculation of the indirect effects, but the order of
magnitude which can be expected can be found in a previous study2 . In this study the
wider economic benefits of the historical Iron Rhine were calculated. The total welfare
gain from the improved railway connection amounted to 16% of transport benefits
(consumer surplus). The indirect effects were largely associated to the Ruhr Area. For
Belgium, the main benefit was located in the port region (agglomeration of Antwerp).
Surprisingly, the rest of Belgium and the Netherlands experienced a positive welfare
effect too. This was because of cheaper imports supplied from the German Ruhr area.
The external effects describe the impact of the project on the human environment and
nature. They are called external as they are not compensated for. We can distinguish
three types of external effects:
• The external effects of the infrastructure itself (use of space, visual intrusion, etc.);
• The external effects linked to the use of the infrastructure and the changes in
transport flows (air pollution, noise, traffic safety, etc.);
2 Heyndrickx, C., Koops, O., Ivanova. O (2011). The TIGER model: Application of detailed passenger and freight transport in a regional CGE setting.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
35
• The impact on the environment caused by possible changes in location of
economic activity.
The quantification of the external effects is based as much as possible on the
outcome of the environmental assessment. The following external effects are taken
into account, although not all of them are quantified:
a. Change in emissions: air pollutants and greenhouse gasses (CO2, NOx, SOx, PM)
(rail, road, inland waterways)
b. Change in noise (rail and road)
c. Change in accidents (rail and road)
d. Change in external safety (rail)
e. Change in marginal road wear and tear costs
f. Loss of recreational opportunities
g. Vibrations due to rail
h. Loss of living environment
i. Landscape
j. Ecology
k. Soil and water
l. Agriculture
The project costs. This is the difference in
a. investment costs
b. cost of maintenance
c. cost renewal
d. the cost of mitigating measures
between the project alternative and the reference.
4.3 Results
The following table shows the results of the SCBA for the 3RX project under the
medium economic scenario. It gives the discounted value of future costs and benefits
for the years up to 2030 (assumed construction period) and 30 years of operation
(2031-2060). Future benefits and costs have been discounted using a discount rate of
3%.
The table shows that the benefits of the 3RX are € 365 million (discounted value)
lower than costs. The benefit-cost ratio of the 3RX is 0.16.
The relatively low level of benefits is mainly due to the fact that 3RX is quasi perfect
substitute to the Montzen route. Trains shift from the Montzen route to the 3RX, with
some benefits for the consumers (less travel time and costs, however not very much,
as 3RX is only slightly better than the Montzen route).
The environmental impacts are rather small, most are positive. The reason for this is
that quite some mitigation measures are foreseen in the project itself. Also, the 3RX-
route is somewhat shorter, with positive overall effects on e.g. noise in Belgium.
The modal shift from road and inland shipping to rail is very low (again due to the
relative small benefits of the 3RX versus the Montzen route). Road congestion and
time losses at road-rail crossings both improve. The first due to a few less trucks on
motorways, and the second due to foreseen mitigation measures in the project.
Table 12: Social cost benefit analysis: overview, scenario “3RX route – medium”, NPV (at 3% discount rate) for 2015 in million €2015
TOTAL BE NL DE world
Direct effects
on consumers
rail consumer surplus € 34.78 € 17.35 € 4.99 € 12.38 € 0.06
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
36
TOTAL BE NL DE world
rail robustness € 22.17 € 10.82 € 0.13 € 9.48 € 1.73
road congestion € 9.16 € 3.54 € 1.76 € 3.86 € 0.00
road time at crossings € 2.10 € -1.47 € 3.44 € 0.10 € 0.03
Direct effects
on infrastructure
rail infrastructure fee € 1.50 € -6.48 € 7.71 € 0.20 € 0.07
Effects on the
government
tax revenue € -1.50 € -0.44 € -0.32 € -0.74 € -0.01
External effects rail emissions € -0.32 € 1.40 € -1.67 € -0.04 € -0.02
road emissions € 1.17 € 0.33 € 0.20 € 0.64 € 0.00
iww emissions € 0.35 € 0.22 € 0.11 € 0.03 € 0.00
rail noise € 5.76 € 5.78 € 0.00 € 0.00 € -0.01
road noise € 0.08 € 0.02 € 0.01 € 0.04 € 0.00
rail accidents € 0.29 € -0.54 € 0.81 € 0.02 € 0.01
road accidents € 0.08 € 0.03 € 0.01 € 0.03 € 0.00
road wear & tear costs € 0.18 € 0.05 € 0.03 € 0.10 € 0.00
recreation opportunities € -1.12 € -0.33 € -0.79 € 0.00 € 0.00
vibration € -0.35 € 0.04 € -0.38 € -0.01 € -0.00
landscape € -0.00 € 0.00 € -0.00 € -0.00 € 0.00
ecology € -4.39 € -4.39 € 0.00 € 0.00 € 0.00
soil and water PM PM PM PM € 0.00
Project costs investment costs € -433.78 € -69.69 € -327.34 € -36.74 € 0.00
renewal costs € -1.18 € 0.00 € -1.06 € -0.12 € 0.00
maintenance costs € 0.38 € 41.69 € -37.49 € -3.81 € 0.00
TOTAL NPV € -364.65 € -2.08 € -349.86 € -14.58 € 1.87
benefit-cost ratio 0.16 0.93 0.04 0.64
Source: ARTECORAIL, Task report E3/E4/E5: Social cost benefit analysis
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
37
The following tables give the results for all alternatives under all three scenarios in net
present value terms and in terms of benefit-cost ratio.
Table 13: Social cost benefit analysis: overview for all 9 scenarios/variants, NPV (at 3% discount rate) for 2015 in million €2015
3RX HIST A52
Low € -374 € -545 € -175
Medium € -365 € -495 € -86
High € -358 € -463 € -30
Source: ARTECORAIL, Task report E3/E4/E5: Social cost benefit analysis Table 14: Social cost benefit analysis: overview for all 9 scenarios/variants, benefit-cost ratios (at 3% discount rate) for 2015
3RX HIST A52
Low 0.14 0.40 0.78
Medium 0.16 0.45 0.89
High 0.18 0.49 0.96
Source: ARTECORAIL, Task report E3/E4/E5: Social cost benefit analysis
The SCBA shows a negative result at the 3% discount rate for all variants and
scenario’s. The cost of the new infrastructure is for 3RX in all scenario’s (much)
higher than the benefits, which mainly consist of the consumer surplus and
robustness.
The other two alternatives, Historical route and A52, show a picture similar to 3RX.
The results for the Historical route are more negative than for 3RX, which is mainly
due to its higher investment costs that wipes out the higher benefits.
The results for A52 are less negative than for 3RX, which is mainly due to the
relatively high transport benefits of this alternative that compensate its higher costs. It
should be noted, though, that recently a much higher cost estimate became available
for the A52-route, which has a high impact on this result (see sensitivity analysis
below).
Note also that the results of the SCBA are only slightly better if a higher economic
scenario is assumed. Conversely, the results are only slight more negative in case of
a low economic growth scenario.
4.4 Sensitivity analysis
The following sensitivity analyses have been carried out.
3RXlight variant
The 3RX variant focusses on upgrading a number of existing railway sections in the
Maas-Rhein-Ruhr border region linking Weert with Viersen via Roermond and Venlo.
This 3RXlight alternative can be seen as a first step in a fully developed Iron Rhine. It
consists of:
• All fixed elements (Lier-border, Weert, Weert-Roermond, Maaslijn)
• Curve at Roermond but only a single track instead of a double track
• No curve at Viersen: use the yard
• Use of the yard in Venlo
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
38
The result for the 3RX light is less negative € -304 million euro for 3RXlight option
(benefit-cost ratio 0.16), versus € -365 million for 3RX.
3RXlater variant
In this variant, the investment costs are made 10 years later than in the regular 3RX
variant. Consequently, the operation of the railway link will also be 10 years later,
starting in 2040. The transport forecast based on economic assumptions obviously
remains the same, but the effect of the project starts only in 2040. Thus, the
calculation of the effects will start as well in 2040 and not 2030 as in the regular 3RX.
Compared to the regular 3RX variant, the result for the 3RX later variant is less
negative: € -285 million for 3RXlater (benefit cost ratio 0.12) versus € -365 million for
3RX.
This is due to the fact that all effects are smaller because they are more depreciated
(2040 versus 2030). Also, the benefits of consumer surpluses are higher in later
years due to the autonomous growth. The negative effects (investment costs) still
outnumber the positive effects (consumer surplus), but in absolute terms the
difference gets smaller.
3RXexpensive variant
This variant takes into account a possible higher cost of the 3RX variant on the
German side, as there is uncertainty about the costs. This cost variant is higher as it
is based on more expensive solution for the Viersen curve.
Compared to the regular 3RX variant, the total is more negative: € -464 million for
3RXexpensive variant (benefit cost ratio 0.13), versus € -365 million for 3RX.
3RXpenalty variant
In the report on traffic forecasts, a sensitivity analysis is calculated in which an extra
penalty for cross border traffic is included. No full-fledged analysis has been carried
out for this variant, but tentative analysis gives the following results.
In this case traffic on the 3RX would be 50% lower. The effect on the consumer
surpluses would be in the same order of magnitude. The 3RX project has a consumer
surplus of € 35 million. In a sensitivity where the cross border effect is taken into
account in a more stringent way, this would lower by € 10 to 20 million. Emissions,
safety and congestion would be also affected however these effects are small, and
are equally positive as negative.
The benefit-cost ratio will be lower, as can be seen in the table below, assuming a €15
million lower consumer surplus.
Table 15: Social cost benefit analysis: overview, scenario “3RXpenalty – medium”, costs, benefits, NPV for 2015 in million €2015,
benefits costs NPV bc ratio
3RX € 69.93 € -417.91 € -364.65 0.16
3RXpenalty € 54.93 € -417.91 € -379.65 0.13
difference € -15.00 € 0.00 € -15.00
Source: ARTECORAIL, Task report E3/E4/E5: Social cost benefit analysis
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
39
A52expensive variant
This variant takes into account a possible higher cost of the A52 variant on the
German side, as there is uncertainty about the costs. This cost of this variant are also
higher as it is based on another technical solution for the Viersen curve3. Total costs
for this variant are estimated at € 1.7 billion.
Compared to the regular A52 variant, the outcome of the SCBA for the A52 expensive
variant is much more negative: € -640 million euro (benefit-cost ratio 0.52) versus
€ -86 million for A52.
3 Gegenüberstellung Machbarkeitsstudie 3RX – BVWP PF 2-025-V01
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
41
5 FINANCIAL ANALYSIS
Revenues from Track access charges
Based on the before mentioned train numbers and train kilometres, revenues for each
of the three Infrastructure Manager’s (Infrabel, ProRail, DB Netz) have been
calculated using the average income for infrastructure manager:
• Average income per train for Infrabel (Belgium): 1,45 € / kilometre
• Average income per train for ProRail (Netherlands): 3,46 € / kilometre
• Average income per train for DB Netz (Germany): 3,28 € / kilometre.
The final incomes of infrastructure manager are depending on the type of route and
vary significantly. The results for all routes in different time frames for all three
infrastructure managers are summarised in the following table and are based on the
average operational days of 300 per year.
Costs and revenues 3RX
With the mentioned track access charges and train numbers the expected revenues
for each IM can be calculated in more detail for the 3RX-route. The results show that
the expected yearly income per IM manager will increase slowly, and could reach 3
million Euros until 2040, that represents a fairly low income for all involved
infrastructure managers.
Table 16: Forecasted annual income from Track Access Charges 3RX- route only
Year Forecasted no. of trains
Infrabel ProRail DB Netz Total 3RX
2030 17 732,105 € 1,002,293 € 1,168,451 € 2,902,849 €
2040 19 818,235 € 1,120,210 € 1,305,916 € 3,244,360 €
Source: ARTECORAIL, Task report E7: Financial analysis
Utilising the various scenarios and the associated maintenance costs, the percentage
of the maintenance costs that are covered by income from the tack access charges
has been determined. For ProRail, by 2040 the track access charges will cover
between 32% and 33% of the annual maintenance costs, depending on the scenario
chosen.
Due to the low maintenance costs encountered by DB Netz in the CBA variant and the
high revenue from TAC, DB Netz covers all of relative maintenance expenses.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
43
6 FINANCING OPTIONS
The various financing options for the 3RX project have been analysed and several
funding options for rail infrastructure projects have been described. Financing of rail
infrastructure is concentrated along three main sources of support; at the European
level, contributions from the national and regional governments, and private investors
through a public-private segment of financing (Public-private-partnership). Based on
the description and analysis the following conclusions are drawn.
It is strongly recommended that the 3RX project seeks all available sources of
financing, starting at the European level followed by contributions from the national or
regional/ provincial governments that should represent a majority of the overall project
investment. A third financing option that includes involvement of a private partner may
be less likely, as every investor seeks a clear business case (return on investment)
offered by the project, but due to low income from track access charges, this is
unlikely to be achievable in the 3RX project.
The central question of the EU co-funding is related to the (non-) involvement of the
3RX line on the TEN-T core network. According to regulation 1316/2013, the line is
not a part of the TEN-T core network, but the option of inclusion in the Core network in
the case of the agreement between involved Member States still exists and should be
verified. Additionally, it needs to be considered that the Commission will carry out a
review of the implementation of the core network by 31 December 2023 and there is a
possibility the status of the 3RX line can change after the review phase.
The chances of a contribution from the EU through co-funding of CEF calls for core
network, blending, project bond initiative or EFSI are until that stage not very
probable. However, other sources of financing such as EIB loans could present
possible options. A very positive sign of the recognised importance of the 3RX railway
line from the EC point of view is the recently approved funding for the electrification
between Mol and Weert in the amount of 18.52 million Euro.
Contributions from the national and regional governments are recommended and
should form the main part of the overall project investment package. Experience of the
EU Member States indicates that rail infrastructure financing from government
budgets is the prevailing source of financing in rail infrastructure projects. In all three
countries, regional participation in the financing of transport infrastructure projects
also occurs. Some successful cases of mixed financial contribution from the national
and regional level are Stuttgart – Ulm and the Liefkenshoek link. These examples
show that projects in all three involved countries can be (pre)-financed by regional
authorities, aside from contributions by the national governments.
The involvement of a private partner is recommended, but on the other hand, the
private partner must see a clear business opportunity and the contribution and interest
of the private partner strongly depend on the return on investment that the project can
offer. The situation where a private partner would take a major share in the financing
of the line is unlikely if the only benefit would come from the track access charges.
The formation of an independent project company (SPV) is recommended, even if the
project will not involve private partners. It can be formed as a completely new
company (like Rail Baltica), consisting of different stakeholders (example Keyrail,
Betuweroute). The advantage of a project company is that it can more consistently
manage the budget and time constraints of the project.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
45
7 RISK ANALYSIS
Risk management in infrastructure projects is complicated, but many risks that occur
are common to many large projects. Due to the complexity and involvement of three
countries in the 3RX project which brings along different political and social interests,
new potential risks were identified (such as environmental issues, organisational
model, etc.).
Risks identified for the 3RX project can be grouped into different levels, such as
technical, financial, social and legal or political. The technical risks depend on the
technical complexity of the project (traffic forecast, competition, and organisational
model) which is in the case of 3RX much higher than for a single country project. The
financial risk primarily consists of securing sufficient funding and potential cost
overrun. Finally, the social and political risks include the political decision-making
process and public perceptions of the 3RX.
Table 17: Risks identified for the 3RX project
Risk Group Risk Effect
Financial
Funding
Lack of available budget,
Inflation, unavailability to find a
private partner
Cost overrun Higher costs of the project
Delay Longer implementation, higher
costs of the project
Transport policy Delay in the implementation,
higher costs
Technical and other factors
Traffic forecast Lower demand, lower income
from TAC
Competition Lower demand than expected
Organisational model Problems in the operational
tasks
ERTMS
Risk impact of new safety rules
on use of yard for change of
direction
Legal, political, social and
environmental
Public opposition of different
stakeholders Delay and higher costs
Legal Delay and higher costs
Natura 2000 Lower capacity
Source: ARTECORAIL, Task report E6: Risk analysis
For these risks mitigation measures have been identified. Table 15 summarizes all the
risks, their probability, impact, overall risk, their mitigation measures, and their
residual risk. There will be no remaining residual high risk for the project as measures
are available and likely to be implemented to manage potential overall risks.
Additionally, risk mitigation strategies and criteria for the key risks are explained.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
46
Table 18: Risk mitigation
Risk Probability Impact Overall
risk
Mitigation
measures
Residual
risk
Different costing
methods C
Imprecise
costing
calculation
Low
Precise evaluation of
costing methods before
the start of the project.
Close monitoring of the
situation after the
project start is required.
Low
Delay in project
implementation B
Construction
delay High
Set up a strong project
management unit, and
close monitoring of the
situation before and
during the construction
phase, that includes
time control and
appropriate scheduling.
Additional Investment in
early-stage engineering
and design can reduce
the effect of project
delay.
Moderate
Insufficient
funding C
Construction
delay Moderate
Identification of all
possible sources of
funding, including EU
funds, private partner
and national/regional
contributions. Possible
PPP models should be
taken into account.
Low
Legal D Construction
delay Moderate
Following the situation,
possible changes in the
legislation.
Low
Organisational
model D
Operational
and
organisational
issues
Low
Set up an appropriate
model for 3 different
countries, with an
agreement between
partners, who is
responsible for a certain
part of the project risk.
Low
Cost overruns A
Higher
investments
costs than
initially
planned
High
Set up of a strong
project management
unit. Precise planning
before and during the
construction phase is
required, taking into
account all unexpected
costs that may occur.
Additional Investment in
early-stage engineering
and design can reduce
the effect of cost
overruns.
Moderate
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
47
Risk Probability Impact Overall
risk
Mitigation
measures
Residual
risk
Competition B Lower
demand High
Closely monitor the
performance and modal
split from Antwerp
Moderate
Transport policy D Construction
delay Moderate Close monitoring Low
Realised vs.
forecasted traffic A
Lower traffic
than expected High
Careful estimations
based on realistic
scenarios and close
monitoring on the
situation.
Moderate
ERTMS C Safety aspect Low
Close monitoring of the
safety rules and its
impact on use of the
yard.
Low
Environmental B Lower
capacity High
Further analysis in the
second step of the
project and evaluation
of the potential
environmental
mitigation measures.
Moderate
Probability: A – very likely; B – likely; C – about as likely as not; D – unlikely; E-very unlikely
Risk Level: Low; Moderate; High; Unacceptable
Source: ARTECORAIL, Task report E6: Risk analysis
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
49
8 NEXT STEPS
8.1 Legal road map
Various legal steps are needed for implementing the 3RX variant on Belgian, Dutch
and German territory. The nature and the extent of the works determine the permits
needed and the time period which should be provided for this. In order to get the
permits studies need to be carried out.
Belgium
In accordance with applicable legislation, the works and exploitation are subject to
permits (planning permission and environmental permits), authorizations and road
permits.
In this case, one must also consider the need to compile a project EIA. In addition, to
obtain a permit for track doubling, the regional plan will first need to be modified via a
Regional Spatial Implementation Plan (RSIP). The RSIP is legally subject to a plan
EIA (environmental impact assessment to account for development proposals). If
negative impacts are identified in the plan EIA, mitigating measures will be formulated
and must be reflected in the SIP guidelines so that the impacts in question can be
mitigated. The government will also initiate the SIP (and the necessary impact
assessments). Nonetheless, various stakeholders can signal the need to compile an
SIP. Formal decision-making will be made at political level.
Expropriation (perhaps partial) will also be needed in order to carry out the work.
Considering the potential transport of hazardous goods (e.g. SEVESO products and
chemical substances from storage/transshipment to processing), the issue of safety
must be thoroughly investigated in the plan EIA. The need for an environment safety
report (OVR) will be examined after consultation and based on the preliminary
investigation.
Two options
Because procedures will be started after this study, two formal approaches (tracks)
can be followed for realisation:
1.TRACK 1: Integrated spatial process with expropriation followed by environmental
permit
• Integrated spatial process RSIP and plan EIA
• Simultaneous expropriation for public utility
• Environmental permit including draft project EIA
2.TRACK 2: Complex project with expropriation
• Complex project
• Expropriation for public utility
The Netherlands
For the 3RX on Dutch territory there are a number of procedures that can be tailored.
These are:
1.The ProRail core process
2.The MIRT - framework for Long-Term Programme for Infrastructure, Spatial
Planning and Transport (National Government)
3.The Infrastructure (Planning Procedures) Decree (and co-ordination arrangement)
4.Permits (Environmental Licensing (General Provisions) Bill (Wabo))
5.The designation of a reservation area for 3RX in the Rarro (Ordinance on General
Spatial Planning Regulations)
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
50
The core process and the MIRT are processes for arriving at good decision making.
The Infrastructure (Planning Procedures) Decree goes through a statutory procedure
that is also aimed at arriving at a balanced decision. The final product is the
Infrastructure (Planning Procedures) Decree, which is an implementing decision.
During the Infrastructure (Planning Procedures) Decree process, environmental
permits may also be applied for in advance of the decision for matters that already
apply within the current spatial plans and decisions.
Germany
New railroad projects in Germany are being planned based on the Federal Transport
Infrastructure Plan (Bundesverkehrswegeplan) and on the requirement plan according
to the Federal Railways Improvements Act (Bundesschienenwege-Ausbaugesetz).
These plans build upon a forecast of the traffic development, which is relevant for the
following need of coordination and approval process. In that way, the requirements for
the expected traffic volume, an increased demand in infrastructure and an
environmental friendly design are met. Furthermore, these data built the baseline for
the dimension of noise and vibration protection as well as for the Environmental
Impact Assessment and the assessment of the Natura2000 directives.
Regional Planning Procedure
To make sure that big infrastructural projects are in line with the public interest and
are also compatible with material and legal requirements they must undergo a
Regional Planning Procedure (Raumordnungsverfahren - ROV). This procedure is
executed as an internal administrative procedure by the district government. During
the ROV all affected planning authorities and associations are involved, for example
nature conservation organizations. Within the procedure alternatives are investigated
and unsuitable solutions can be discarded at this early planning stage.
Before this procedure is conducted there should to be a preliminary assessment if a
Regional Planning Procedure is necessary.
The documents submitted by the applicant are send to the various planning
authorities and other parties. The documents contain an explanatory report, detailed
maps, graphs, and explanations as well as an Environmental Impact Assessment.
Plan Approval Procedure
Railway facilities, including the tracks, electrification, and ancillary buildings, can only
be build or changed through a Plan Approval Procedure (Planfeststellungs- /
Plangenehmigungsverfahren). The approval process is conducted by the Federal
Railway Authority (Eisenbahnbundesamt -EBA).
Afterwards the application will be send to the affected hearing authority in the relevant
state. In the present case this are going to be the district governments of Viersen and
Mönchengladbach, who must conduct the public hearing autonomous and
independent. The public hearing includes that the documents will be laid out in the
communities of affected citizens and that they are able to issue statements and
objections about the project. Other affected authorities and third-parties must be given
the opportunity to hand in a statement, too. If appropriate a public discussion should
be organized. The public hearing process ends with a statement by the hearing
authority, which is send to the EBA.
Based on the submitted documents of the project initiator and the hearing authorities,
the EBA determines the admissibility of the project in regards to all affected public
interest. It is the task of the EBA to balance the affected issues by consideration of all
public and private interest. Through provisions and official requirements, the EBA
ensures that third-party rights will not be affected. The plan can be seen as an
equivalent to a building permit.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
51
Studies to be carried out
In order to be able to demonstrate the acceptability of spatial developments, studies
should be carried out as a rule. The following table summarizes the possible studies
and indicates when such a study should in all probability be carried out.
Table 19 Studies that may be needed in each of the three countries involved
Study When necessary
Archaeology
• When departing from the existing rail
destination and the land in the applicable
zoning plan is assessed as having an
archaeological value
Soil • When departing from the existing rail
destination
Cultural history
• If cultural historical values or monuments are
concerned and the development could have
an effect on this
Explosives
• When departing from the existing rail
destination and there is any reason for
encountering explosives. The latter will
quickly become an issue in the area
concerned since the necessary war activities
took place there. Furthermore, it concerns a
track that already existed before WW2 and
railways were a likely target for destruction
External safety
• If the transportation of dangerous substances
is an issue, and:
• the track gets closer to a (limited)
vulnerable function and/or
• it will be used more frequently, and/or
• it will be used at a higher speed, and/or
• other or more dangerous substances will
be transported
Noise
• If other rolling stock will be used, and/or
• If the track gets closer to a vulnerable
function /destination, and/or
• If it will be used more frequently, and/or
• If it will be used at a higher speed, and/or
• If the surface over which it travels changes
Landscape
• If visible activities take place in the
surrounding area, and/or
• If activities take place on the track that are
visible from a distance
Air quality
• If other rolling stock will be used, and/or
• If the track gets closer to a vulnerable
function /destination, and/or
• If it will be used more frequently, and/or
• If it will be used at a higher speed (with a
view to harder braking)
Nature – Flora and fauna
• If other rolling stock will be used, and/or
• If the track gets closer to a vulnerable
flora/fauna (including the National Nature
Network) or crosses these areas, and/or
• If it will be used more frequently, and/or
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
52
Study When necessary
• If it will be used at a higher speed
Nature – Natura2000
• If it cannot be ruled out in advance that there
are significant effects are to be expected.
This can also be an issue:
• If other rolling stock will be used, and/of
• If the track gets closer to a vulnerable
nature or crosses these areas, and/or
• If it will be used more frequently, and/or
• If it will be used at a higher speed
Damage risk-analysis
• If it is expected that (legal) persons will be
disadvantaged by the new development. This
study only makes sense if the initiator still
allows its plans to be affected by any
planning damage claims
Vibrations
• If other rolling stock will be used, and/or
• If the track gets closer to a vulnerable
function /destination, and/or
• If it will be used more frequently, and/or
• If it will be used at a higher speed, and/or
• If the surface over which it travels changes
Traffic
• If activities take place that lead to the
removal of traffic connections and/or new
traffic connections
Water
• When departing from the existing rail
destination, and:
• The surface hardening increases
significantly, and/or;
• Degradation of the surface water takes
place, and/or
• Degradation of the groundwater takes
place
Water safety
• If there are water barriers in the area of
activity
• If activities take place in areas that are part of
the flow carrying or water-storage regime
Source: ARTECORAIL, Task Report R8/R9: Legal road map and process architecture
8.2 Process architecture
The above mentioned the formal procedures that the project should go through in the
respective countries. In addition to these legal provisions, the complexity of the project
lies in the fact that adjustments are necessary in three countries for the success of the
project. A political process will have to lead to unambiguous agreements between
Belgium, the Netherlands and Germany to start legal proceedings. The process
should serve all the interests of the stakeholders through participation and
communication with the stakeholders.
A thorough utility and necessity analysis will create support from those directly
involved and citizens, making decision-making faster. This concerns answering the
central question: Why is a project like the 3RX necessary?
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
53
Participation: walking three tracks
Alongside the formal, official track of legal procedures there must also be political
consensus. We bring the participation under three tracks: the political, the legal/formal
and communication track.
Political track
As the project will require an international treaty between Germany, Belgium and the
Netherlands, the establishment of a 3RX steering group at the highest level
between the treaty partners will be a necessity. From the start of the project
(preparation of the planning), an advisory board may advise the client on issues of
stakeholders. This advisory board can act as a link to the political level.
A first step is to make a Memorandum of Understanding (MoU) with the countries
concerned. This MoU has no legal status. The (accelerated) continuation of ministerial
consultations between Belgium and the Netherlands regarding existing agreements is
crucial here.
Legal/Formal track
The formal track is described in section 8.1. The procedures are aligned at maximum
and are open and accessible to all concerned. An important role for formal track is
that the national process commits counsellors at regular intervals. They inform about
the progress of the project at national level (content, planning and risks). They report
to the 3RX steering group. This steering group is expected to be assisted by
thematic working groups (e.g. concerning infrastructure, spatial, economic,
communication, financial and taxation modes of transport, etc.). These thematic
working groups can be composed nationally, bilaterally or with all countries.
Communication track
As high local and regional public interest in this project is very likely, it makes sense to
integrate communication and public participation into the project structure and
planning. The public as a key-stakeholder should not only be informed about the
project, but also integrated into the planning and design process. Communication as a
component of project planning can reduce the risks of potential interruption of the
planning-process by stakeholder initiated conflicts.
As this is a pure freight traffic project, certain stakeholder-groups may receive it as a
threat to the living conditions in the neighbourhoods and communities. Noise, traffic
disturbance and potential transport of hazardous goods might shrink the perceived
quality of life and so foster the establishment of citizens’ initiatives.
Communicating honestly on face-to-face level with stakeholders, clearing their
concerns and illustrating implications transparently from the very beginning of the
project is the basis of reducing speculations and being able to lead the dialogue.
Integration of planning and communication
Connecting the operational communication strategy, the participation process and
public relations with defined project management -phases (see figure) enables an
integrated transparent and reliable perceived communication strategy.
From this it follows, that windows for communication operations should be
implemented when setting up the overall project and its structure. The
communication’s project-structure is based on and strongly connected to the overall
project-structure and its topics. Needed resources like a communications team, or a
budget for information events should also be included in the overall project-plan. Clear
roles and responsibilities like an official speaker, should be defined in advance, prior
to the project-start. The communications team should be included in all internal
meetings, which could have an effect on the public perception, to ensure the steering
of the dialogue.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
54
Figure 7: Flow chart showing project management connected with public relations
Source: Verein Deutscher Ingenieure (2015): VDI 7000 - Frühe Öffentlichkeitsbeteiligung bei Industrie- und Infrastrukturprojekten. Berlin
A precise internal preparation for the participation and communication strategy is
crucial. The overall and detailed planning of different parts of the communication-
strategy should be closely connected to the project-progress. For being able to steer
the dialog (not just react), preparation is needed.
A project-environment-analysis offers insights for designing an elaborate
communication-strategy. Having a deep look into the history of the project and the
project-areas to understand the stakeholder’s perspective is important. There is also
the option for a more detailed stakeholder- and issue-mapping. Based on this, the
preparation of crisis communication material should be decided. Information-cascades
must be prepared as a structure for the official communication of project-progresses
and news, and to prevent ruffling feathers.
Windows of opportunity for dialogue
The on-going communication and public relation should offer different ways of
communication to reach a broad group of stakeholders. Having a homepage, and
working with the press is the basis. But there are also different ways of explaining the
project and its impacts to different stakeholders. For example simulating acoustical
freight traffic noise (with and without noise-protection) at information events, or
showing the functionality of whisper-breaks. It pays off to be transparent about the
planning-process and not raise hope by initialising a participation if there is nothing to
decide about. The focus should be on explaining the planning process and the project
with its impacts in a very transparent manner.
Success factors
In comparison to other rail-projects, this just freight traffic-project falls into a difficult
category when it comes to raising acceptance.
• Integrating the project-communication at the very beginning and developing a
communication project-structure with resources and defined information-events
(that tell about the method and the status of planning) ensure the basis of a
transparent perceived communication.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
55
• It is crucial to find and align with local politicians, trade associations and advocates
for the project on the ground. So the abstract economic benefit gets personally
demonstrated in the particular area.
• There should be clear benefits for the local stakeholders. For example a voluntary
stronger noise-protection as needed by law or other optional add-ons like replacing
level-crossings by a bridge or a tunnel or a renovated train station for the public.
Framing the rebuilding as a chance to optimize the local rail infrastructure from a
stakeholder’s perspective might be an important point.
As the project is not an entire new construction, there will not be a wide range of
options for participation. Communicating transparently about the project and its
opportunities and not raising unrealizable hopes in terms of participation is crucial,
especially because of the long story of the project.
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
57
APPENDIX A
Members of the Steering Committee
Germany
Jürgen Papajewski / Dr. Martina Habibes (Federal Ministry of Transport and Digital
Infrastructure)
Rainer Stefan Hiltermann (German Embassy Brussels, Belgium)
North Rhine-Westphalia
Dietmar Rosarius (NRW Ministry of Transport)
Norbert Lammering (Representation of NRW to the EU)
The Netherlands
Robert de Jong (Dutch Ministry of Infrastructure and the Environment)
Henk Meeldijk (Dutch Ministry of Infrastructure and the Environment)
Marcel Tijs (Dutch Ministry of Infrastructure and the Environment)
Kasper vander Gugten / Lotte Lankveld (Dutch Embassy Brussels, Belgium)
Belgium
Frederik De Ridder (Belgian Ministry of Transport)
Filip Van Vracem (Belgian Ministry of Transport)
Stefaan De Weireld (Office of Belgian Minister of Transport Bellot)
Dirk Verdickt (Office of Belgian Minister of Transport Bellot)
Flanders
Reginald Loyen (Flemish Ministry of Mobility and Public Works)
Filip Vandermeulen (Office of Flemish Minister of Mobility and Public Works Weyts)
Jurian Van Parys (Flemish Ministry of Foreign Affairs)
Pim Bonne (Flemish Ministry of Mobility and Public Works)
Koen Haverbeke (General Representative of the Government of Flanders in
Germany)
Axel Buyse (General Representative of the Government of Flanders in The
Netherlands)
Natasja Duhem (Deputy General Representative of the Government of Flanders in
The Netherlands)
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
77
T1 – T4 – Costs, Technical variants and planning
THV AR-T-ECO-RAIL
Arcadis – TML – ECORYS - Railistics
83
E3 – E5 – Social Cost Benefit Analysis (SCBA)