Summary Progress Of Facade Works
-
Upload
sameh-ibrahim-bsc-civil-eng-pmp-gradieaust-pg-dip -
Category
Documents
-
view
21 -
download
4
Transcript of Summary Progress Of Facade Works
CLIENT: Zabeel Investement CLIENT: Zabeel Investement CLIENT: Zabeel Investement CLIENT: Zabeel Investement
L.I.CL.I.CL.I.CL.I.C
Planning Departement
Package No. : D0469
Planned Preogress % Actual Progress % Variance % Ahead/Behind
External Facades 76.37% 37.80% -38.57% Behind
Residential Tower N4 84.55% 47.57% -37% Behind
Residential Tower N3 83.32% 50.22% -33% Behind
Residential Tower N2 67.42% 47.27% -20% Behind
Residential Tower N1 66.06% 43.17% -23% Behind
Residential Tower S3 79.67% 49.91% -30% Behind
Residential Tower S2 81.62% 52.10% -30% Behind
Residential Tower S1 80.68% 50.55% -30% Behind
Hotel Tower H1 74.38% 0.00% -74% Behind
Hotel Tower H2 69.39% 0.00% -69% Behind
Planned Progress % Actual Progress % Variance % Ahead/Behind
External Facades 76.37% 37.80% -38.57% Behind
Residentials 77.66% 48.68% -29% Behind
Hotel 71.88% 0.00% -72% Behind
Anantara Palm Jumeirah and Tiara Residences
Progress Of Facades Works Month : 26January2008
Type Of WorkCurrent Month (Up to 26January08)
Type Of WorkCurrent Month (Up to 26January08)