 SUMMARY OF FIDIC RED BOOK An Extension of the Time f or Comple tion ( Sub- Clause 8.4 ) Contractor shall be entitled to receive an extension of the time for completion of which the taking over of the works has delayed. An extension of the time for completion will be caused by any of the following points among others a substantial change in the !uantity of an item of work included in the contract" an adverse climatic conditions" any other matters giving an entitlement to extension of time under of #$%$C document" unforeseeable condition caused by epidemic or governmental actions" or any delay caused by the employer" employer&s personnel" or the employer&s other contractors.  The Contractor shall give notice about the extension time to the Employer in accordanc e with 'ubClause *.+ [Contractor ’s Claims].  The Change to %esign (refer to Sub-Clause 3.3)  The change to design may be initiated by the Employer at any time prior to issuing the Taking,ver Certi-cate for the orks. The Contractor shall comply wit h the ins tru cti ons giv en by the Emp loy er . henever pra cti cab le" the change to design shall be given in writing. The change to design constitutes a /ariation must be followed to Clause +0 [Variations and Adjustments] .

description

Particular Condition

Transcript of Summary of Fidic Red Book

SUMMARY OF FIDIC RED BOOK

An Extension of the Time for Completion (Sub-Clause 8.4)Contractor shall be entitled to receive an extension of the time for completion of which the taking over of the works has delayed. An extension of the time for completion will be caused by any of the following points among others: a substantial change in the quantity of an item of work included in the contract, an adverse climatic conditions, any other matters giving an entitlement to extension of time under of FIDIC document, unforeseeable condition caused by epidemic or governmental actions, or any delay caused by the employer, employers personnel, or the employers other contractors.The Contractor shall give notice about the extension time to the Employer in accordance with Sub-Clause 20.1 [Contractors Claims].

The Change to Design (refer to Sub-Clause 3.3)The change to design may be initiated by the Employer at any time prior to issuing the Taking-Over Certificate for the Works. The Contractor shall comply with the instructions given by the Employer. Whenever practicable, the change to design shall be given in writing. The change to design constitutes a Variation must be followed to Clause 13 [Variations and Adjustments].

Bahwa kontraktor berhak mendapat hak atas perpanjangan waktu penyelesaian pekerjaan yang menyebabkan serah terima pekerjaan menjadi terlambat. Hak atas perpanjangan waktu dapat disebabkan oleh poin-poin berikut: Perubahan mendasar dalam kuantitas suatu pekerjaan, dimana hal tersebut sudah termasuk di dalam kontrak. Keadaan cuaca yang sangat buruk. Hal lain yang dapat memberikan perpanjangan waktu dan telah didasari oleh suatu sub klausa dalam FIDIC. Suatu hal yang tidak dapat diperkirakan sebelumnya akibat wabah atau kebijakan pemerintah. Keterlambatan atau kesulitan yang disebabkan oleh Pengguna Jasa sendiri, maupun oleh individu atau kelompok yang dipekerjakan oleh Pengguna Jasa.Kontraktor harus menyampaikan pemberitahuan tentang hak atas perpanjangan waktu kepada Pengguna Jasa didasarkan pada Sub-Klausa 20.1 tentang Klaim oleh Kontraktor.

Perubahan gambar atau desain dapat dilakukan sebelum diterbitkannya Berita Acara Serah Terima Pekerjaan. Perubahan gambar atau desain oleh Pengguna Jasa harus diikuti oleh Kontraktor. Apabila memungkinkan, perintah diberikan secara tertulis. Perubahan gambar atau desain yang berkaitan dengan suatu Perubahan akan mengikuti klausul 13 Variasi dan Penyesuaian.