SUMMARY OF CONSTRUCTION PROJECTS · SUMMARY OF CONSTRUCTION PROJECTS CLEBURNE COUNTY County Totals...
Transcript of SUMMARY OF CONSTRUCTION PROJECTS · SUMMARY OF CONSTRUCTION PROJECTS CLEBURNE COUNTY County Totals...
![Page 1: SUMMARY OF CONSTRUCTION PROJECTS · SUMMARY OF CONSTRUCTION PROJECTS CLEBURNE COUNTY County Totals Job No. Job Name Rte. Sec. Type Work Status Let Date Date Length (Mi) Cost Project](https://reader034.fdocuments.in/reader034/viewer/2022051607/6038fb2a81f9b113bb0de832/html5/thumbnails/1.jpg)
Program Management CleburneFebruary 10, 2021
![Page 2: SUMMARY OF CONSTRUCTION PROJECTS · SUMMARY OF CONSTRUCTION PROJECTS CLEBURNE COUNTY County Totals Job No. Job Name Rte. Sec. Type Work Status Let Date Date Length (Mi) Cost Project](https://reader034.fdocuments.in/reader034/viewer/2022051607/6038fb2a81f9b113bb0de832/html5/thumbnails/2.jpg)
SUMMARY OF CONSTRUCTION PROJECTS
CLEBURNE COUNTYCounty Totals
CostLength (Mi)Type WorkJob Name Rte.Job No. Sec. Status Let Date Date
Project Totals
CostLength (Mi)
Sub. Comp.
Estimated or
- PE OnlyHwy. 65 – Hwy. 5 (Passing Lanes) P.E. 25
Addt'l Rte.-Sec.: Faulkner 25-1
$02 Under Construction - $0001657*
- PE OnlyHwy. 67 – Hwy. 25 P.E. 5
Addt'l Rte.-Sec.: Lonoke 5-12; White 5-13/14
- 15 Programmed - - 001748*
Safety ImprovementsGuy – Heber Springs (Safety Impvts.) (Sel. Secs.) (S) 8.1225
Addt'l Rte.-Sec.: Faulkner 25-1
$1 - $5 M2 Scheduled Sep. 2021 8.52 $1 - $5 M012227
Bridge RehabilitationDistricts 4, 5, 8 & 9 Bridge Preservation (2020) (S) 0.11110
Addt'l Rte.-Sec.: Various
$402,5456 Under Construction May. 2020 Mid 2021 1.68 $6,147,965012351*
- Bridge RehabilitationDistricts 5 & 10 Bridge Preservation (2021) (S) 25
Addt'l Rte.-Sec.: Various
< $1 M3 Scheduled Apr. 2021 - $1 - $5 M012378*
Passing LanesFaulkner Co. Line – Hwy. 107 (Passing Lanes) (S) 2.4225 $4,242,0012 Completed Feb. 2012 Jun. 2014 2.42 $4,242,001050166
Major WideningHwy. 110 East – Sunny Meadow (Heber Springs) (S) 0.7725 $5,066,0073B Completed Oct. 2009 Oct. 2011 0.77 $5,066,007050175
- Safety ImprovementsHwy. 25/Hwy. 110 Signal (Heber Springs) (S) 25
Addt'l Rte.-Sec.: Cleburne 110-6
$183,2083 Completed Jul. 2010 Feb. 2011 - $183,208050211
- Roadside AppurtenancesSugarloaf Mountain Summit Trail (Heber Springs) (S) $38,850Completed Sep. 2010 Jul. 2014 - $38,850050219*
Structure & ApproachesMidway Branch Str. & Apprs. (S) 0.55225 $8,139,4803 Completed Feb. 2012 Nov. 2015 0.55 $8,139,480050228
- Roadside AppurtenancesHeber Springs SRTS I (2010) $92,478Completed Jul. 2013 Mar. 2015 - $92,478050239*
ResurfacingGreers Ferry Dam – Hwy. 92 (Overlay) (S) 10.3025 $1,436,9883 Completed Apr. 2011 Sep. 2011 10.30 $1,436,988050246
- EnhancementHeber Springs Sulphur Creek Trail (ATEP-11) (S) $149,998Completed Jul. 2013 Sep. 2014 - $149,998050257*
Passing LanesHwy. 25 Spur – Locust Grove (Passing Lanes) (S) 2.3325 $3,828,8573 Completed Oct. 2015 Oct. 2016 2.33 $3,828,857050261
Passing LanesWest of Windwood Dr. – East (Passing Lane) (S) 1.1616 $2,749,58612 Completed Aug. 2016 Jun. 2017 1.16 $2,749,586050262
- MiscellaneousDistrict 5 Bridge Painting (Phase I) (2013) (S) 16
Addt'l Rte.-Sec.: Independence 122-1; Izard 5-17; White 67-12, 157-1, 367-17
$343,37811 Completed Jun. 2013 Mar. 2014 - $3,576,399050290*
Passing LanesWest of River Bluff Rd. – East (Passing Lane) (S) 1.2616 $1,824,89612 Sub. Completed Sep. 2018 Oct. 2019 1.26 $1,824,896050315
Safety ImprovementsHwy. 25 – White Co. Line (Safety Impvts.) (Sel. Secs.) (S) 10.4816 $823,00012 Completed Apr. 2018 Oct. 2018 10.48 $823,000050316
- EnhancementHeber Springs Ely Dr. Sidewalks (TAP-16) (S) $125,361Completed Oct. 2017 Jun. 2018 - $125,361050326*
- EnhancementWalking Trail Rehab. (Greers Ferry) (RTP-15) (S) $43,750Under Construction Nov. 2016 - $43,750050332*
- EnhancementS. Broadway Trail Ext. (Heber Springs) (RTP-15) (S) < $1 MProgrammed - < $1 M050333*
- EnhancementWedding Ford Rd. Sidewalk (Heber Springs) (TAP-15) (S) < $1 MProgrammed - < $1 M050335*
- EnhancementQuitman Sidewalks (TAP-15) (S) $245,000Completed Jul. 2017 Mar. 2018 - $245,000050336*
Structures & ApproachesMill & Piney Creek Strs. & Apprs. (S) 0.6325 $3,670,5002 Under Construction Jun. 2019 Mid 2021 0.63 $3,670,500050341
Program Management CleburneFebruary 10, 2021
* Job not shown on county map.
![Page 3: SUMMARY OF CONSTRUCTION PROJECTS · SUMMARY OF CONSTRUCTION PROJECTS CLEBURNE COUNTY County Totals Job No. Job Name Rte. Sec. Type Work Status Let Date Date Length (Mi) Cost Project](https://reader034.fdocuments.in/reader034/viewer/2022051607/6038fb2a81f9b113bb0de832/html5/thumbnails/3.jpg)
SUMMARY OF CONSTRUCTION PROJECTS
CLEBURNE COUNTYCounty Totals
CostLength (Mi)Type WorkJob Name Rte.Job No. Sec. Status Let Date Date
Project Totals
CostLength (Mi)
Sub. Comp.
Estimated or
ResurfacingVan Buren Co. Line – Greers Ferry (S) 8.1016 $2,077,53311 Completed Feb. 2017 Jun. 2017 8.10 $2,077,533050345
ResurfacingHwy. 25 – Hwy. 25 (Heber Springs) (S) 5.5025 $1,622,9173B Sub. Completed May. 2020 Sep. 2020 5.50 $1,622,917050346
- EnhancementQuitman Sidewalks Ph. 2 (TAP-16) (S) $277,286Under Construction Jul. 2020 - $277,286050348*
ResurfacingHwy. 25 – Hwy. 225 (Quitman) (S) 2.14356 $291,0182 Completed Jul. 2017 Nov. 2017 2.14 $291,018050376
ResurfacingHwy. 16 – Greers Ferry Lake (S) 6.8225 $1 - $5 M3 Scheduled 2022 6.82 $1 - $5 M050399
Structure & ApproachesCadron Creek Str. & Apprs. (S) 0.3825 $1 - $5 M2 Scheduled Aug. 2021 0.38 $1 - $5 M050413
Base StabilizationHwy. 16 Slide Repair (Cleburne Co.) (S) 0.27CS $1,100,000Sub. Completed Oct. 2019 Apr. 2020 0.27 $1,100,000050428*
- EnhancementHeber Springs First Security Ped. Bridge (TAP-19) (S) < $1 MProgrammed - < $1 M050430*
- EnhancementWest Side Schools Hwy. 92 Flashing Beacons (TAP-19) (S) 92 < $1 M5 Programmed - < $1 M050431*
ResurfacingHwy. 25 – East (S) 3.41110 < $1 M6 Scheduled May. 2021 3.41 < $1 MA50004
ResurfacingGreers Ferry Overlay (Sel. Secs.) (S) 2.28CS $273,498Completed Sep. 2013 Dec. 2013 2.28 $273,498C12001*
ResurfacingQuitman Overlay (Sel. Secs.) (S) 1.89CS $189,517Completed Jul. 2014 Nov. 2014 1.89 $189,517C12002*
- ResurfacingHeber Springs Overlay (Sel. Secs.) (S) CS $283,224Completed Jul. 2017 Dec. 2017 - $283,224C12003*
ResurfacingGreers Ferry Overlay No. 2 (Sel. Secs.) (S) 2.45CS $217,709Completed Apr. 2018 Nov. 2018 2.45 $217,709C12004*
ResurfacingQuitman Overlay No.2 (Sel. Secs.) (S) 1.17CS $115,492Completed Feb. 2019 May. 2019 1.17 $115,492C12005*
- ResurfacingConcord Overlay (S) CS $213,337Sub. Completed Feb. 2020 Apr. 2020 - $213,337C12006*
- ResurfacingFairfield Bay Surfacing & Olay(sel. Secs.)(s) CS
Addt'l Rte.-Sec.: Van Buren CS
$143,956Completed Sep. 2014 Dec. 2014 - $287,912C76014*
ResurfacingCo. Rd. 142 – Hwy. 124 (S) 9.96110
Addt'l Rte.-Sec.: White 110-7
$1,174,5356 Completed Apr. 2011 Jul. 2011 10.49 $1,230,885FS5007
ResurfacingHwy. 25 – Pangburn (S) 12.2216
Addt'l Rte.-Sec.: White 16-13
$2,380,06512 Completed Jun. 2011 Oct. 2011 14.09 $2,686,142FS5009
ResurfacingHwy. 107 – Hwy. 25 (Sel. Secs) (S) 5.05110
Addt'l Rte.-Sec.: Cleburne 110-6
$1,062,9035 Completed Jun. 2011 Aug. 2011 5.05 $1,062,903FS5010
ResurfacingHwy. 16 – Hwy. 25 (S) 14.4992 $2,203,9205 Completed Jul. 2011 Nov. 2011 14.49 $2,203,920FS5012
ResurfacingHwy. 92 – Hwy. 87 (S) 7.4225 $1,307,7893 Completed Jul. 2011 Nov. 2011 7.42 $1,307,789FS5014
ResurfacingTaylor Rd. (Log Mile 12.9) – East (Pryor Mtn.) (S) 0.7016 $153,49711 Completed Jul. 2011 Nov. 2011 0.70 $153,497FS5015
ResurfacingNarrows Bridge – West (S) 4.9316 $671,00711 Completed Mar. 2012 Jul. 2012 4.93 $671,007FS5016
ResurfacingHwy. 25 – East (S) 3.20110 $520,6516 Completed Mar. 2012 Jul. 2012 3.20 $520,651FS5017
ResurfacingHwy. 157 – Hwy. 25 (S) 10.1487
Addt'l Rte.-Sec.: Independence 87-4
$1,571,3633 Completed Mar. 2012 Jun. 2012 16.24 $2,534,457FS5018
Program Management CleburneFebruary 10, 2021
* Job not shown on county map.
![Page 4: SUMMARY OF CONSTRUCTION PROJECTS · SUMMARY OF CONSTRUCTION PROJECTS CLEBURNE COUNTY County Totals Job No. Job Name Rte. Sec. Type Work Status Let Date Date Length (Mi) Cost Project](https://reader034.fdocuments.in/reader034/viewer/2022051607/6038fb2a81f9b113bb0de832/html5/thumbnails/4.jpg)
SUMMARY OF CONSTRUCTION PROJECTS
CLEBURNE COUNTYCounty Totals
CostLength (Mi)Type WorkJob Name Rte.Job No. Sec. Status Let Date Date
Project Totals
CostLength (Mi)
Sub. Comp.
Estimated or
ResurfacingFaulkner Co. Line – Hwy. 5 (Sel. Secs.) (S) 8.1025 $1,067,3522 Completed Mar. 2012 Aug. 2012 8.10 $1,067,352FS5019
ResurfacingHwy. 87 – North (S) 4.4625
Addt'l Rte.-Sec.: Independence 25-4
$577,5563 Completed May. 2012 Jun. 2012 5.16 $671,577FS5022
ResurfacingDiamond Bluff Rd. – Hwy. 25 (S) 8.8316 $1,106,16611 Completed Apr. 2013 Aug. 2013 8.83 $1,106,166FS5029
ResurfacingHwy. 25 – Hwy. 16 (S) 7.86337 $1,003,0402 Completed Jul. 2013 Jan. 2014 7.86 $1,003,040FS5033
ResurfacingHwy. 25 – North (S) 4.765
Addt'l Rte.-Sec.: Stone 5-16
$591,86615A Completed Apr. 2014 Jul. 2014 12.63 $1,557,543FS5034
ResurfacingHwy. 25 – Hwy. 36 (S) 5.41124
Addt'l Rte.-Sec.: Faulkner 124-9; White 124-10
$1,387,9158 Completed Sep. 2010 Jun. 2011 7.94 $2,041,051FSX001
Resurface & Shoulder
Resurfacing
Hwy. 65 – Quitman (S) 1.82124
Addt'l Rte.-Sec.: Van Buren 124-7
$329,1958 Completed Sep. 2010 May. 2011 9.74 $1,732,604FSX002
Resurface & ShoulderHwy. 92 – Hwy. 225 (S) 2.61356
Addt'l Rte.-Sec.: Van Buren 356-1
$448,7542 Completed Sep. 2010 May. 2011 9.32 $1,602,691FSX003
ResurfacingHwy. 65 – Hwy. 16 East (Sel. Secs.) (S) 1.2392
Addt'l Rte.-Sec.: Van Buren 92-3
$218,7724 Completed Jul. 2011 Jan. 2012 12.91 $2,187,722FSX004
RehabilitationHwy. 9 – Hwy. 16 (Rehab.) (F) 1.2392
Addt'l Rte.-Sec.: Conway 92-2; Van Buren 92-3
$248,0004 Completed Jul. 2014 Sep. 2015 26.59 $5,373,000FSX005
ResurfacingWhite County Line-North(striping&overlay)(s) 4.50CR $329,126Completed May. 2012 Jul. 2012 4.50 $329,126SA1248*
ResurfacingHwy. 25-North (Overlay) (S) 2.38CR $254,589Completed Jul. 2014 Oct. 2014 2.38 $254,589SA1249*
ResurfacingHwy. 16-East (Overlay) (S) 3.95CR $420,083Completed Jul. 2015 Dec. 2015 3.95 $420,083SA1250*
ResurfacingHwy. 110-Hwy. 110 (Hirma Rd.) (Overlay) (S) 5.90CR $608,604Completed Jun. 2016 Feb. 2017 5.90 $608,604SA1251*
ResurfacingHwy. 25 - West (Overlay) (S) 1.90CR $151,259Completed Apr. 2018 Nov. 2018 1.90 $151,259SA1253*
ResurfacingIda - South (Overlay)(s) 5.01CR $497,487Completed Jun. 2019 Aug. 2019 5.01 $497,487SA1254*
- ResurfacingHwy. 107 - East (Overlay) (S) CS $288,984Sub. Completed May. 2020 Jul. 2020 - $288,984SA1255*
ResurfacingStone Co. Line North & South (Overlay) (S) 3.20CR
Addt'l Rte.-Sec.: Stone CR
$356,385Completed Jul. 2013 Sep. 2013 3.35 $371,235SA7630*
$68,894,252213.80Totals For All Projects In Cleburne County
Program Management CleburneFebruary 10, 2021
* Job not shown on county map.