Sumitomo VRB
-
Upload
vanadium-guru -
Category
Documents
-
view
222 -
download
6
description
Transcript of Sumitomo VRB
Distributed Generation
with High
Penetration of
Renewable Energy
Sources
Description of Vanadium Redox Flow BatteryAt the end of 2001 CESI installed a VRB manufactured by SEI (Sumitomo Electric Industries). As the system had to be connected to the battery laboratory for testing activity, it had been installed on the terrace above the lab. As a consequence, for this particu-lar installation, SEI added two sub-tanks under the stack for collecting the electrolyte falling from the cells during non func-tioning period of the system and two sub-pumps in order to force the electrolyte from the sub-tanks to the main tanks.
maximum power the main can supply is defined; if the load needs more power is the battery that helps the main. When the power of the load is lower than that the main can supply the battery can be recharged.
In any case there is the su-pervision of the controller for battery integrity. The perform-ances of VRB would be good also for power quality systems (PQS) applications in which the battery has to supply peak power for very short time.
Result realised by:
Results: The battery is under test in CESI laboratory battery.
> Preliminary tests for its characterisation
> Tests simulating peak shaving applications
> Efficiency of the converter, of the battery and of the system
> Measurement of self discharge rate
> Behaviour of the system with ohmic and inductive load, balanced and unbalanced
> Measurement of the effect of temperature on battery performances
> Measurement of internal resistance of the battery
> Efficiency variation depending on charge/discharge management procedure
> Valuation of safety aspects
Project Highlight No.06
Stack main characteristics
Construction 100 unit cells
Rated power – energy
45 kW – 2 hours
Rated DC voltage 125 V
Rated DC current 370 A
DC voltage range 100 ÷ 155 V
Electrolyte Tanks
Material Polyethylene
Capacity 4 m3
Quantity 2
AC/DC Converter
Supply 3phase 400V, 50 Hz
Rated power
70 kVA
Efficiency 90%
Operating mode
Charge: constant current, constant power, constant voltageDischarge: constant current, constant power
Energy Storage for Distributed Generation:SUMITOMO Vanadium Redox Flow Battery (VRB)
ControllerO
per
tati
on
mo
de 1 year mode (programme the
operation for the year)
Continuous operation (routine of charge, standby, discharge, standby)
Following the load operation (charge, discharge or standby operation depending on the need of power by the loads connected to the system)
Main features of VRB are summarised in the following table:
VRB installed at CESI is part of a Peak Shaving System (PSS) with an AC/DC converter. During the “following the load” mode of operation the
VRB stack
VRB tanks
MASTHEAD
The project DISPOWER is partially
funded by the European Commis-
sion, DG Research
Duration:
01.01.2002 - 31.12.2005
Contract no.
ENK5-CT-2001-00522
Co-ordinationISET e.V.
Prof. Dr. Jürgen Schmid
Königstor 59
D-34119 Kassel
Phone: +49 561 7294-0
Fraunhofer ISE
Dr. Tim Meyer
Heidenhofstr. 2
D-79110 Freiburg
Phone: +49 761 4588-0
LiabilityThe authors are solely responsible
for this publication, it does not
represent the opinion of the
European Community and the
European Community is not
responsible for any use that
might be made of date appearing
therein. Despite thorough control
all information in this brochure is
provided without guarantee. Un-
der no circumstances will liability
be assumed for loss or damage
sustained through the use of
information provided.
AuthorsCESI: Centro Elettrotecnico
Sperimentale Italiano Giacinto
Motta S.p.A.
Contact:
CESI
Antonio Buonarota
Via Rubattino 54,
I - 20134 Milano / Italy
Phone: +39 0221255269
Fax: +39 0221255626
email: [email protected]
Date: 2003-12-04
No: 06
Technical Details:
New systems like this under study
need to be investigate both from
the point of view of performances
and in respect to their lifetime. VRB
efficiency is strongly influenced
by ambient temperature but also
managing strategy of the battery
(i.e. charging power/current and the
definition of ending discharge and
recharge criteria) are fundamental.
Still, in a flow (circulation of electro-
lyte) battery, total efficiency is strongly
dependent by the time during which
the two main pumps are running. It
is easy to understand that in a PQS
application in which the battery has
to supply energy to the load very
rarely, in general it is a mistake to take
running the pumps all the time. But in
any case the battery must be ready in
a few milliseconds to supply energy:
that means the stack has to be always
full of electrolyte and the pumps must
start very quickly.
A careful examination has been paid
to understand the effect on perform-
ances of these aspects.
Efficiency of the system
For calculating the charge/discharge
process efficiency avoiding systematic
errors it is necessary to be sure that
the initial and final state of charge of
the battery are the same. The state
of charge of SEI Redox flow battery
is measured only through the battery
voltage: the end of charge and the
end of discharge are managed by the
controller through battery voltage.
In other words it is fixed a value of
voltage for stopping the charge proc-
ess, i.e. 150 V, and another value,
i.e. 100 V, for stopping discharge
process. These values are always the
same whatever is the power used for
recharge and that used for discharge
the battery. Thus, the energy dis-
charged or charged depends strongly
on the value of current. As a conse-
quence, the real physical final charge
and discharge states are not the same.
Also the influence of the tempera-
ture on the internal resistance of the
battery (the lower the electrolyte
temperature, the higher the internal
resistance) makes worse this aspect.
Battery efficiency had been obtained
with constant discharge power from
20 to 45 kW and constant recharge
power from 20 to 60 kW according to
10 setup implemented by the manu-
facturer in the controller.
A positive message that is possible
obtain from the tests is that it is pos-
sible reaching efficiency of about 90 %
but it is necessary to implement a
procedure for the management of the
system.CESI i working on this matter
for setting up an optimised managing
procedure of the system in order to
improve the detection of the real state
of charge of the battery, thus optimis-
ing the efficiency and the exploitation
of the battery.
During a first set of tests simulating
peak shaving applications the battery
worked “on time basis” arranging
in advance the time of starting and
ending of recharge and discharge
process. Evidently with this operating
mode it is possible to take switch off
the pumps and also to take empty the
stack in order to reduce acid corrosion
of the membrane. In this condition
it is sufficient switch on the pumps a
few minutes before starting discharge
o recharge of the battery.
A second set of tests had been
conducted during which the battery
had been managed as in a real peak
shaving application supplying to the
load the part of the power that the
network is not able to supply. With
this “following the load” mode of
operation it is not more possible to
take empty the stack and stopped the
pumps.
VRB self-discharge
Another important parameter that
influences VRB efficiency and has to
take in due consideration in defining
its managing procedure is the self-
discharge. Self-discharge is a common
phenomenon in electrochemical accu-
mulators and consists in consumption
of the energy contained in the battery
without external loads connected
to it. Self-discharge losses in VRB
are very intense especially when the
pump are running but, as already
said, in certain mode of operation, the
pumps must always run. Typical self-
discharge value for lead-acid batteries
is 3 % per month. For VRB that value
is reached and exceeded in one day.
This is another reason for switch off
the pumps all the times it is possible.
VRB pictorial diagram