Successes achieved in terms of maintenance planning and
implementation-Hydro Power Plants on the Nile River
Nobert MatarutseTechnical DirectorEskom Uganda
LimitedUganda
Introduction and background
• Prior to year 2001 Uganda had a vertically integrated power utility, Uganda Electricity Board, responsible for power generation, transmission and distribution of electricity. No regulatory framework was in place
• Uganda Electricity Generation Company Limited was born out of the de-regulation of the electricity industry in Uganda
Introduction Cont’d
• De-regulation was motivated by among other reasons, the need to improve service delivery, increasing electrification rate and as a way of increasing accountability and provide a fertile environment for investment in this critical industry.
Introduction Cont’d
• Prior to de-regulation power industry was characterised by frequent power blackouts, trips and dwindling plant capacity and high operating costs.
• Eskom Uganda Limited is a wholly owned subsidiary of Eskom Enterprises SA. It was formed in 2002 and won a 20 year concession to operate and maintain two power plants on white Nile, Uganda from 1st April 2003.
Nalubaale and Kiira Power Stations
• Installed Capacity Nalubaale 10 X 18MW= 180MW-Vertical Shaft Kaplan Units
• Ist unit commissioned in 1954. All units uprated and refurbished in between 1992-1998-Uprated from 15MW to 18MW each
• Installed Capacity Kiira 5 X 40MW= 200MW-Vertical Shaft Propeller Units
• Total Installed Capacity For Complex= 380MW
• Peak Generation current 217MW due to hydrological Constraints
Nalubaale and Kiira Power Stations
Nalubaale PS Kiira PS
Rated Head (m)
18.9 20.8
Specific water consumption factor (m3/kWh)
19.8 18.02
Previous Planning Philosophy
• Uganda Electricity Generation Company Limited (UEGCL) being a parastatal was not bound by any Power Purchase Agreement.
• UEGCL had a time based planning philosophy
• UEGCL declared installed capacity and were paid based on same.
• UEGCL’s planning was based on OEM’s recommendations provided soon after rehabilitation
Previous Planning Philosophy
• UEGCL were in charge of the complex for slightly more than 2 years during which time they used a job card system for managing routines and defects
Eskom’s Planning Methodology
• Time and condition based
• Microsoft access based deviation management system was established
• Deviation management system which is still in place is like a manual (s.c.a.d.a) system
• Plant history developed by the creation of the centralised documentation center.
Eskom’s Planning Methodology
• Plant history so developed was key as it enabled proper trending of critical plant parameters and performance of plant.
• Plant history was also utilised to kick start plant intervention programs with a view to stimulate continuous improvement.
• 10 year Technical Plan and Life of Plant Plans developed.
• System Engineering and modification programs established
Service Level Agreements
• Power Purchase Agreement
• Concession and Assignment Agreement
• Generation Licence
• Water Permit
• Support Agreement
• Heads of Agreement
Maintenance Philosophy
• 36 monthly cycle-maintenance outage-30days
• 18 monthly cycle-detailed inspection-15days feeds into 36 Monthly cycle maintenance
• 6 monthly cycle-1day routine
• Using condition monitoring schemes installed, maintenance outages are effected before breakdowns
Maintenance Planning and Implementation
• Outage management procedure in place
• Pre and post outage planning meetings
• KKS plant break down system used for physical assets identification.
• Work packages-for standardisation-doing things right first time.
• Annual plan submitted to system operator 120 days before the following year.
• Annual plan takes into account outage scheduling
Power Generation Performance Indicators
• The following were and are still being measured on a monthly basis in order to guide plant performance and ensure service delivery;
Power Generation Performance Indicators
• Plant Availability
• Plant Reliability
• Unplanned Automatic Grid Separations
• Planned Outage Rate
• Forced Outage Rate (including Mode change failures)
• Plant Load Factor
• Plant Efficiency
Plant Availability Benchmarks
Company CountryAvailability
Mighty River Power
New Zealand 92.4%
Meridian EnergyNew Zealand 94.0%
British Columbia Hydro Canada 96.4%
Eskom Uganda Ltd Uganda 96.0%
Dropping water
levels led to
reduction in
available energy
U2 VT explosion (Trfr 11kV cable
and surge arresters damaged)
outage lasted over 300hrs
- Unit 10 rotor earth fault – outage
lasted approx 100hrs
Performance Outlook
• Conjunctive operation with downstream power plants.
• Commissioning of an integrated computerised maintenance management system that relates to functional areas of the business.
• Increased plant optimisation
Performance Outlook
• Improvement in manpower utilisation
• Increased cost effectiveness
• Further improvement in service delivery
• Focus on quality assurance
• Increased focus on risk management
Intervention measures employed to achieve performance
• replacement of dc systems
• modification of protection schemes
• modification of governing systems
• installation of vibration monitoring
• installation of partial discharge scheme
• transformer replacement
• circuit breaker replacement
• surge arrestors replacement
Intervention measures employed to achieve performance
• System engineering including in-depth incident investigations.
• Standardisation of maintenance tasks and procedures
• Enforcement of statutory maintenance
• Training and development including exposure programs.
• Performance management.
The End
• Thank You