Success Stories of Large Capacity fixed dome biogas plants installed in Punjab
(1). Large Capacity PAU Model Biogas Plant of capacity 2500 m3 / day (5 x 500
m3/d capacity each) installed in a Industry namely M/s Bhatinda Ceramics Pvt.
Ltd., Bathinda, Punjab for Power Generation / Thermal Applications.
Installation of the Project = June, 2012
Cost of the Project = 399.68 Lakh
Subsidy received from MNRE = 75.00 Lakh
Administrative charges to PAU Ludhiana = 7.5 Lakh
Electricity generation per day = 2200 to 2500 unit
Saving of Industrial Fuel per day
(by replacing industrial fuel by biogas for
operating the Tunnel Kiln of the Industry) = 600 Ltr.
Cost of Industrial fuel = Rs. 20000/- per day.
(2). Large Capacity PAU Model Biogas Plant of capacity 120 m3 / day installed in a
R. S. Dairy Farm, V.P.O. – Bahadurpur, District – Ropar, Punjab for supply
of biogas to 75 nos. of households in the village.
Installation of the Project = April, 2012
Cost of the Project = 15.00 Lakh
Central Financial Assistance from MNRE = Nil
Total No. of houses in the Village = 75
No. of Cattle available with Dairy Farm = 150
Daily dung collection (appx.) = 3000 Kg.
Total Investment made by = Dilbar Singh
No. of gas connections in operation = 70
No. of Families having individual biogas plants = 02
Duration of Biogas supply to the households = 2 hours each
for 3 times in Morning, Noon and Evening.
Average consumption of biogas per family = 1.5 m3 – 2 m3
Payment for using biogas = Free of cost
Any break down in the system during the
period from April, 2012 to October, 2017 = No
Maintenance of Gas Pipeline system and
other accessories = Payment to the
plumber is being made
by the beneficiaries
Utilization of Bio-digested slurry = It is filled in the tanker
having capacity of
5000 litre as such and
is being sold
@ Rs. 700/- per tanker.
(3). Large Capacity PAU Model Biogas Plant of capacity 100 m3 / day installed in
a Lambra Kangri Multipurpose Cooperative Service Society Ltd.,
District – Hoshiarpur, Punjab for supply of biogas to 44 nos. of households
in the village.
• No. of Families providing Cattle dung : 28• No. of Cattle available with these
families: 175
• Daily dung collection (approximately) : 2500 Kg.• Capacity of biogas plant : 100 m3
• Year of Installation of Biogas Plant : April, 2016• At present, No. of gas connections in
operation: 44
• Cost of per kg cattle dung provided bythe society to the farmers
: 10 paisa per kg
• Duration of Biogas supply to thehouseholds
: From 4:00 AM to 10:00 PM daily
• Average consumption of biogas perfamily
: 1.0 m3 – 2 m3
• Payment being collected from thehouseholds for using biogas
: Upto 10m3 - Rs. 10/m3
10m3 to 20m3 - Rs. 8/m3
>20m3 - Rs. 6/m3
• Average monthly bill of biogas : Rs. 200/- to Rs. 300/-• Maintenance of Gas Pipeline system
and other accessories: The Maintenance cost for this project is
being made by the Society.• Utilization of Bio-digested slurry : It is filled in the tanker having capacity of
5000 litre as such and is being sold @ Rs.800/- per tanker.
• Satisfaction of the families / householdsby using biogas
: They are very happy and most of them arenot using LPG / any other alternative fuelfor their daily cooking needs.
• Technical Guidance provided forinstallation and operation of the project
: School of Renewable Energy Engineering,Punjab Agricultural University, Ludhiana.
• Financial support : Ministry of New and Renewable Energy(MNRE), Govt. of India, New Delhi
(P1) Inauguration of Biogas Plant by Shri K.S. Pannu (I.A.S.), Secretary Irrigation Department, Punjab
(P2) Inauguration of Biogas Plant by Shri K.S. Pannu (I.A.S.), Secretary Irrigation Department, Punjab