Subsea cable laying: from theory to practice HALIFAX, 6 NOVEMBER 2014

Transcript of Subsea cable laying: from theory to practice - · PDF filefrom theory to practice . HALIFAX, 6...

Page 1: Subsea cable laying: from theory to practice - · PDF filefrom theory to practice . HALIFAX, 6 NOVEMBER 2014. Test site background . 1. Location . 2. ... Initial cable design required

Subsea cable laying: from theory to practice

HAL

IFAX

, 6 N

OVE

MBE

R 2

014

Page 2: Subsea cable laying: from theory to practice - · PDF filefrom theory to practice . HALIFAX, 6 NOVEMBER 2014. Test site background . 1. Location . 2. ... Initial cable design required

Test site background 1. Location 2. Description

Our experience 1. Initial cable design 2. Contractor requested change 3. The compromise 4. Initial logistics 5. Unforeseen event 6. Agreed solution between all parties 7. Revised logistics 8. Cable burial

Conclusions

Page 3: Subsea cable laying: from theory to practice - · PDF filefrom theory to practice . HALIFAX, 6 NOVEMBER 2014. Test site background . 1. Location . 2. ... Initial cable design required

Test site background

Page 4: Subsea cable laying: from theory to practice - · PDF filefrom theory to practice . HALIFAX, 6 NOVEMBER 2014. Test site background . 1. Location . 2. ... Initial cable design required

LOCATION 1

BILBAO

DONOSTIA SAN SEBASTIÁN

VITORIA-GAZTEIZ

ARMINTZA

Biscay Marine Energy Platform

Page 5: Subsea cable laying: from theory to practice - · PDF filefrom theory to practice . HALIFAX, 6 NOVEMBER 2014. Test site background . 1. Location . 2. ... Initial cable design required

DESCRIPTION

Test centre ready to operate 2

• 4 Berths 20 MW connected to the grid • Environmental monitoring • Water depth 50-90 m • 24/7 Surveillance and emergency response • Close enough for fast access

Page 6: Subsea cable laying: from theory to practice - · PDF filefrom theory to practice . HALIFAX, 6 NOVEMBER 2014. Test site background . 1. Location . 2. ... Initial cable design required

Our experience

Page 7: Subsea cable laying: from theory to practice - · PDF filefrom theory to practice . HALIFAX, 6 NOVEMBER 2014. Test site background . 1. Location . 2. ... Initial cable design required

INITIAL CABLE DESIGN 1

Main Characteristics

•3 phases

•13.2 kV •5 MW

Counter helix double armour

Page 8: Subsea cable laying: from theory to practice - · PDF filefrom theory to practice . HALIFAX, 6 NOVEMBER 2014. Test site background . 1. Location . 2. ... Initial cable design required

2

Initial cable design required carousel

The contractor requested a change to simple armoured cable to avoid carousel

CONTRACTOR REQUESTED CHANGE

Page 9: Subsea cable laying: from theory to practice - · PDF filefrom theory to practice . HALIFAX, 6 NOVEMBER 2014. Test site background . 1. Location . 2. ... Initial cable design required

3

Double armoured cable without counter helix

•Storable in a hold

•No necessity for a carousel

THE COMPROMISE

Page 10: Subsea cable laying: from theory to practice - · PDF filefrom theory to practice . HALIFAX, 6 NOVEMBER 2014. Test site background . 1. Location . 2. ... Initial cable design required

4 INITIAL LOGISTICS

+

+ +

Sent vessel with connectors to Drammen Pick up subsea cables During journey to Bilbao technicians joined connectors and cables Laying of the four Subsea cables

Page 11: Subsea cable laying: from theory to practice - · PDF filefrom theory to practice . HALIFAX, 6 NOVEMBER 2014. Test site background . 1. Location . 2. ... Initial cable design required

Not viable – Alternative cable was not-sufficiently coilable

5 UNFORESEEN EVENT

Page 12: Subsea cable laying: from theory to practice - · PDF filefrom theory to practice . HALIFAX, 6 NOVEMBER 2014. Test site background . 1. Location . 2. ... Initial cable design required

6

Last minute all party meeting in Drammen Several solutions suggested

Barge with cables stored on a carousel

AGREE SOLUTION BETWEEN ALL PARTIES

Page 13: Subsea cable laying: from theory to practice - · PDF filefrom theory to practice . HALIFAX, 6 NOVEMBER 2014. Test site background . 1. Location . 2. ... Initial cable design required

7 REVISED LOGISTICS

+

+ +

Sent vessel with connectors directly to Bilbao

Barge with subsea cables from Drammen to Bilbao

Transfer cables and the connectors from barge to vessel one by one

Laying of the subsea cables one by one

+

+

Page 14: Subsea cable laying: from theory to practice - · PDF filefrom theory to practice . HALIFAX, 6 NOVEMBER 2014. Test site background . 1. Location . 2. ... Initial cable design required

8

•Non-consolidated substrate not as expected

•Inadequate equipment of the vessel

Cable burial carried out by divers

CABLE BURIAL

Page 15: Subsea cable laying: from theory to practice - · PDF filefrom theory to practice . HALIFAX, 6 NOVEMBER 2014. Test site background . 1. Location . 2. ... Initial cable design required

Conclusions

Page 16: Subsea cable laying: from theory to practice - · PDF filefrom theory to practice . HALIFAX, 6 NOVEMBER 2014. Test site background . 1. Location . 2. ... Initial cable design required

Lessons learnt

1

Expect the unexpected: technical & non-technical issues

Problem solving: all parties must work together as a team

Detailed seabed studies best carried out immediately prior to the cable laying

CONCLUSIONS