Submitted to the Electrical & ElectronicsEngineeringProgrammeutpedia.utp.edu.my/9504/1/2007 - Design...
Transcript of Submitted to the Electrical & ElectronicsEngineeringProgrammeutpedia.utp.edu.my/9504/1/2007 - Design...
DESIGN OF ELECTRICAL SYSTEM FOR OFFSHORE PLATFORM
By
SUHAIDA ABD KADIR ALJAILANI
FINAL PROJECT REPORT
Submitted to the Electrical & Electronics Engineering Programme
in Partial Fulfillment of the Requirements
for the Degree
Bachelor ofEngineering (Hons)
(Electrical & Electronics Engineering)
Universiti Teknologi Petronas
Bandar Seri Iskandar
31750 Tronoh
Perak Darul Ridzuan
© Copyright 2007
by
Suhaida Abd Kadir Aljailani, 2007
n
CERTIFICATION OF APPROVAL
DESIGN OF ELECTRICAL SYSTEM FOR OFFSHORE PLATFORM
by
Suhaida Abd Kadir Aljailani
Approved:
A project dissertation submitted to the
Electrical & Electronics Engineering Programme
Universiti Teknologi PETRONAS
in partial fulfilment of the requirement for the
Bachelor ofEngineering (Hons)
(Electrical & Electronics Engineering)
Ir. Perumal Nallagownden
Project Supervisor
UNIVERSITI TEKNOLOGI PETRONAS
TRONOH, PERAK
June 2007
111
CERTIFICATION OF ORIGINALITY
This is to certify that I am responsible for the work submitted in this project, that the
original work is my own except as specified in the references and acknowledgements,
and that the original work contained herein have not been undertaken or done by
unspecified sources or persons.
&*£• •Suhaida Abd KAdir Aljailani
IV
ABSTRACT
Design of electrical system is indeed important in many operations not to disregard
the operation for offshore platform. Offshore operations acquire its own generation of
power supplyto support the facilities on the platform. Designing the electrical system
for any operations involves three main elements which are generation, distribution
and protection. Design process involves much analysis. Software simulation is
conducted replacing the manual methods of calculations. This simulation process
reduces error during calculations and time consume in design process. The objectives
of this project are to provide design of the electrical system demand for an offshore
platform and to design the mostoptimum system including the selection of generators
for the system. Studies and research of power system has been conducted. The
network has been designed and modeled. Simulation on the network performance
which includes loadflow and fault analysis has been conducted. The methodology and
scope of study are as follows:
Conceptual design
Gathering ofnecessary power system components and data
Simulating, troubleshooting andanalysis the modeled powersystem
ACKNOWLEDGEMENTS
I would like to take this opportunity to give my warmest gratitude to everyone who
has involved in making my final year project a success. First of all, I would like to
thank my Project Supervisor, Mr. Ir. Perumal Nallagownden who has been willing to
share and spend his tight schedule in guiding me throughout completing the project.
Without his motivation and guidance I will not be able to achieve the main goal of the
project.
Special thanks to Mdm Rosehayati Ahmad (training supervisor), for sharing her
experienced and knowledge as well as her time to entertain my queries and doubts at
the early stage ofthe project.
I would like to give appreciation and thank to the Final Year Project Committee.
Without their management and coordination, the flow of this project might not be as
expected.
Special thank to Ms Siti Hawa, Mr Yaasin and all technicians of Electrical
Engineering Programme for being very helpful.
Lastly to my parents who have help me in many ways. Not to forget to all my friends
and others who have help in the project directly or indirectly.
VI
TABLE OF CONTENTS
LIST OF TABLES ix
LIST OF FIGURES x
LIST OF ABBREVIATIONS xi
CHAPTER 1 INTRODUCTION 1
1.1 Background of Study 1
1.2 Problem Statement 2
1.3 Objectives and Scope of Study 3
1.3.1 Objectives 3
1.3.2 Scope of study 4
CHAPTER 2 LITERATURE REVIEW 5
2.1 System design 5
2.2 Power System Design and Equipment Selection 6
2.2.1 Regulations 7
2.2.2 Hazardous areas 8
2.2.3 Main Power Supply 9
2.2.4 Emergency Power Sources 10
2.2.5 Cable Systems 10
2.2.6 Motors and Transformers 10
2.2.7 Power system studies 11
2.2.8 Power system protection 12
CHAPTER 3 METHODOLOGY / PROJECT WORK 13
3.1 Project flow 13
3.1.1 Simulation tool 13
CHAPTER 4 RESULTS AND DISCUSSION 15
4.1 Load analysis 15
4.2 Power generation analysis 17
4.3 Modeling and simulation 18
4.3.1 Single line diagram 18
4.3.2 Loadflow 21
4.3.2.1 Scenariol: normal condition 21
4.3.2.2 Scenario2: one generator set is turn off. 23
vn
4.3.2.3 Scenario3: emergency condition... 25
4.3.2.4 Summary of loadflow results 27
4.3.3 Fault analysis 27
4.3.4 Protection 29
CHAPTER 5 CONCLUSION 30
5.1 Summary 30
5.2 Recommendation 31
5.2.1 Perform other analysis 31
5.2.2Comparison result with other software 31
REFERENCES 32
APPENDICES 33
Appendix A PROCESS FLOW CHART 34
Appendix BLOADLIST 36
Appendix C LOAD FLOW ANALYSIS : SCENARIO 1 38
Appendix D LOAD FLOW ANALYSIS : SCENARIO 2 45
Appendix E LOAD FLOW ANALYSIS : SCENARIO 3 52
AppendixF FAULTSTUDY AND ANALYSIS 59
vm
LIST OF TABLES
Table 1 Description ofeach scenario 27
Table 2 Summaryofrated MW values ofgenerator set at different scenario 27
IX
LIST OF FIGURES
Figure 1 Typical Electrical System Design ofOil Production Platform 6
Figure 2 Project Process Workflow 14
Figure 3 Single Line Diagram 20
Figure 4 Scenario 1 22
Figure 5 Scenario 2 24
Figure 6 Scenario 3 26
Figure 7 Three Phase Fault Analysis 28
EOR
DEG
IEC
CENELEC
IP
CCVT
HVDC
DC
AC
DOL
UPS
GTG
HV
LV
PTS
LIST OF ABBREVIATIONS
Enhance Oil Recovery
Diesel Engine Generator
International Electrotechnical Commission
European Committee for Electrotechnical Standardization
Ingress Protection
Close-cycled Vapour Turbogenerator
High Voltage Direct Current
Direct Current
Alternating Current
Direct On Line
Uninterruptible Power Supply
Gas Turbine Genarator
High Voltage
Low Voltage
PETRONAS Technical Standard
xi
CHAPTER 1
INTRODUCTION
1.1 Background of Study
An oil platform is a large structure that caters machinery needed for drilling
process and accommodation for workers on the platform. Platform may be
attached to the ocean floor or floating. There are few types of structure design
dependson the complexity of the offshore industry itself.
Normally, oil platform are located a few hundreds kilometers away from the
shore. Lately due to reducing amount of oil, many oil companies haveexpand
the drilling process to deepwater region. Platform usually consists of a few
modules such as drilling module, power generation module, gas lift module
and etc. Each module is built to support main operation on the mother
platform.
Offshore installations are complex accommodation and industrial plants
operating in high sulfiirous and humidity environments [1], Offshore
installation demands the highest possible security of supply. Interruptions in
the operation will caused production loss as well as endanger the lives of
personnel. Thus, in system design and operation measurement to raise the
supplysecurityto the highest level is taken into consideration.
Power system should be ensure safe to operate and maintain, reliable which
allow continuity of power supply and energy-efficient. Moreover it is
necessary that power systemare designedto be stableand protectedunder any
conceivable disturbance. Design of power system involves much analysis. In
the past, design processes are tedious and timeconsuming as calculations with
mathematical modeling are required. However with the availability of
computer aided tool now, the design processes are modeled differently.
The electrical system consists of three major components:
i. Generation
ii. Transmission
iii. Distribution
This project involves design of the electrical system for water injection
platform. Water injection and gas injection are most widely used Enhanced
Oil Recovery (EOR) methods. EOR is a method used to artificially increase
reservoirpressure in order to supplement the naturaloil drive mechanism.
1.2 Problem Statement
Offshore platforms have one basic objective that is safe production. Offshore
structures range from simple operation to complex processing centers located in
extremely tough environmental conditions with a large operation and maintenance
workforce. Different operations on a platform require different design of electrical
installation.
Equipment selection and location on offshore platforms is in accordance with the
hazardous area classification and the need to have a safe, reliable and secure
installation requiring minimum maintenance [1]. Unscheduled interruptions to
production caused by equipment failure are costly and its maintenance is complex.
Designing an electrical system for platform requires information from other
disciplines such as the mechanical, structural, instrument and etc. This is because the
electrical system designed shall meet the requirement of equipments planned to be
installed on the platform. With the data of expected load required for the process on
the platform known, will then the size and type of the generator to be used can be
estimated and designed.
In general, design criteria of an optimum generation system are reliability, adequacy
and economically. Whereas in distribution system details of its accessibility to the
load, standardize in voltage and current and the utilities to be supplied should be
taken into consideration. Protection is important to prevent the system from
experiencing fault such as short circuit, overload, undervoltage, lightning and etc.
Fault at the network affects the operation of a platform. Shutting down the operation
will halt the production and affect the cost ofthe project.
Modeling and simulation of the power system is conducted to determine its
performances. Operating characteristics of the equipments, power system behaviour
and acceptable assumptions are required to obtain an accurate implementation of
simulation and interpretation of the results.
Detail studies have to be conducted and analyzed to determine the most practicable
electrical system implementation. Throughout the project, selection of power
generation, distribution and protection will be discussed.
1.3 Objectives and Scope of Study
1.3.1 Objectives
i. Understand the design of electrical system for offshore platform by
conducting feasibility studies on the power generation, power distribution and
protection,
ii. To estimate the load capacities based on the information gathered from the
consultants,
iii. To design a schematic diagram of the overall electrical system using ERACS
software,
iv. To conduct loadflow (power flow), fault analysis using ERACS software.
1.3.2 Scope ofstudy
The scope of study can be summarized as literature review on fundamental of
electrical system installation for offshore platform specifically to cater the demand of
facilities on water injection platform module. Focus will be emphasized on the
generation, distribution and protection consideration. Ultimately, the study will come
out with the most suitable design as intended.
To conduct the simulation study of the network, the author has chosen ERACS
software. Among the analysis conducted with the software are as discussed below:
• Load analysis to determine the capacitiesof the powergeneration and distribution
of the equipment. This analysis verifies whether the steady-state voltage drops
and transient voltage deviations are within the acceptable operating limits of the
equipment.
• Fault analysis is carried out to find out power interrupting ratings and to ensure
that the electrical equipmentwill withstand the short circuit current.
CHAPTER 2
LITERATURE REVIEW
2.1 System design
The purpose of an electrical supply network is to provide continuous supply of power
to meet the requirement of varying load, andto do it with a high degree of reliability.
To ensure that the electrical supply is economical andwitha minimum riskof failure,
a supply network must have:
• Adequate powerto cope with the highestpossible load
• Provision of surpluspowerand distributing equipment capacity
• Switchgear, transformers and cables are capable of continuous operation in the
most rough conditions
• Switchgear, transformers and cablesare rated to carry the maximum short-circuit
fault currents
• A protective system capable of isolating faulty equipment with minimum of
interference to the rest ofthe network and with minimum damage.
• Battery-supported supplies for activities that cannotbe tolerate even a short power
interruption
• For offshore installations some means of starting a platform from cold; which is
usually known as a 'black start'
System design must be based upon the continuous maximum rating. In order for a
system to be designed to carry out its fiinctions as mentioned above, following
information must be available:
• Total electrical connected load
• Nature ofeach item of the load
• Installation of the load
• Diversity of the connected load under various conditions
• Topography of the installation
Figure 1 below shows the power system of a largeoil production platform. There are 3 by 50%
ratedgenerators withactualratings increased to about25MW. The feeders from themain 11 kV
busbar areduplicated radialfeeds viathe transformers to lower voltages.
EmergencyGenerator
11 kV
© Main Generation
3x25MW
3,3 kV
®
•*•
•*•
Sea Water LiftFin: Piinip0.2 - 1.0MW
© <s>
Water InjecUonGas CompressionMain Oil Lino1-8MW
^
DrillingMotors750 kW
—K»
®4i5V
ISI[M) (M) i^LZ^i OTSLoads 1^^ (M)o-250kW
Figure 1 Typical Electrical System Designof Oil Production Platform
2.2 Power System Design and Equipment Selection
In the design of electrical installation few important aspects need to be considered to
comply with good engineering practice.
2.2.1 Regulations
PETRONAS technical standard (PTS) is a guideline used in all PETRONAS offshore
as well as onshore operation. One of the main PTS in electrical is the PTS
33.64.10.10. This PTS gives minimum technical requirements for the design,
engineering and installation of electrical facilities. In this PTS it covers design &
engineering principles, electrical system design, design & selection requirements for
equipment & cables, engineering & installation requirements and design &
engineering requirements for particular installations.
Standards, codes & regulations in PTS 33.64.10.10 is based on the publications of the
International Electrotechnical Commission (IEC) and on the relevant documents
issued by the European Committee for Electrotechnical Standardization (CENELEC).
Two main considerations are:
• The design and engineering of the electrical installation shall satisfy ail legal
requirements of the national and/or local authorities of the country in which the
electrical installation will be located.
• The electrical installation shall be suitable for the site conditions as specified by
the Principal.
The design of the electrical installation shall be based on the provision of a safe and
reliable supply of electricity at all times. The design of electrical systems and
equipment shall ensure that all operating and maintenance activities can be performed
safely and conveniently and shall permit periods of continuous operation. The
insulating and dielectric materials used in all electrical equipment shall be non-toxic
and shall not contain compounds that are persistent and/or hazardous environments:
contaminants.
PTS 33.64.10.10 also classify protection against explosion and fire hazards:
• The electrical apparatus shall be properlyselect for areas where flammable gas or
vapour risks may arise.
• Area classification and the selectionof apparatus for use in areas where there is a
flammable dust hazard shall be in accordance with IEC 61241.
In general the design of the electrical installation shall correspond to any specific
design criteria, philosophy and objective that may be stated in the project definition
phase. The philosophies to be employed depend on the size and complexity of the
installation. The conceptual designs and philosophies relating to the electrical system
shall be adequately illustrated by a system design description such as a key line
diagram, basic layout drawings and functional/outline specifications. System studies
and protection reports, etc., shall be provided in support of the design. The scope of
the system studies shall be defined.
In this project, the author will followPTS 33.64.10.10 as guideline to design the most
optimum electrical design. Besides this PTS33.64.10.10 there are several sub-PTS to
supportother specific requirements ofelectrical design.
2.2.2 Hazardous areas
The selection and installation of equipment in hazardous areas is generally based on
national and international codes or standards, e.g. IEC 79 and BS5345 [1]. Generator
packages, switchrooms and transformers are usually kept outside the hazardous areas
but not for equipment directly related to the process such as motors driving pumps,
fans and compressors together with process heating, light fittings and instrumentation
devices. In practice most hazardous areas are of the zone 2 classification with small
pockets of zone 1 around vents and larger areas around the drilling facilities [1].
Equipment located in hazardous areas will further be classified by IP model Code of
Safe Practice Part 15. In addition equipment in exposed areas has higher protection
(IP rating) against ingressof solidmaterial and/ormoisture[1].
2.2.3 Main Power Supply
The main power supply usually consists of generators driven by turbine gas engine
prime movers. However depending on the power demand of the facilities operation,
then type of power generation is selected. There are a few types of power generation.
Each of this power generation has its own maximum capacity and advantage as well
as disadvantages. Below are a few ways to generate power:
i. Gas turbine generator
• Power rating: >1MW
ii. Microturbine
« Power rating: 30kW, 80kW, lOOkW
iii. CCVT (close-cycled vapour turbogenerator)
« Power rating: 3kW to 5kW
iv. Submarine cable
• Two main concerns:
- High cost Installation and distance
- Materials to be used
v. Diesel generator
• needs to be re-fuel and produce pollutants
vi. HVDC (high voltage direct current)
• Impractical to be used for large demand application as it will
require massive converter to convert DC to AC. Most
equipment requires alternating. It obliges wider area to be
installed.
vii. Gas engine
viii. Tap power from grid
ix. Solar panel
• Costly to be installed
• Only suitable for small power distribution usage
The cable size and distribution voltage are governed by the load and distance
involved. Centralized power generation and distribution can potentially minimize
maintenance costs whilst improving the safety and the reliability of operations [1].
2.2.4 Emergency Power Sources
In most design emergency power sources consists of diesel driven generators, battery
system or combination ofboth. The main purpose ofhaving Emergency generators is:
• To provide power to essential load e.g. utility pumps, platform floodlights and
etc
• To provide black start operation
• As back-up power supply in the event of power failure at main power
generation
• As platform main power source during planned shutdown period
2.2.5 Cable Systems
In general all cables are flame retardant with higher fire resistant specifications
reserved for high risk areas and critical circuits (i.e. escape route lighting, shutdown
and safety systems including fire alarms, fire pumps, gas detection etc.). All cables
are armoured except in a few cases (control rooms and other clean, internal, non-
hazardous areas with additional mechanical limited to essential services in
accommodation modules [1].
2.2.6 Motors and Transformers
Motors are generally squirrel cage induction type with DOL starting. Transformers
are synthetic liquid sealed types or dry cast resin units [1].
Design of electrical system installation begins with the estimation of the electrical
load capacity. The consumption of electrical loads depends on the facilities installed.
Electrical single line diagram is produced to show the power distribution and the flow
10
of the process involving electrical component. Electrical distribution system starts
from the main power generator and then being step down through distribution
transformers. From step down transformer, power will be flowed to the loads. In
between the line, protection devices such as circuit breaker, bus tie, relays are being
placed. Emergency or back up equipment for instance diesel generator and UPS
system are also installed to ensure a continuous power flow.
Guidelines on the design and selection of the power distribution equipment are
analyzed. Study on the protection requirement for generators, electric motors, feeders
and small power, lightingand etc is considered. Literature review of the facilities on
the platform such as the cabling system, electric motors, lighting and etc is prepared.
2.2.7 Power system studies
Designing power systems involves performing several studies to evaluate the
efficiency of the power delivery in the network. Beside these studies are conducted to
measure the suitability of equipment selected for the network.
Two main studies are conducted throughout the project:
i. Loadflow
This study analyzes system's capability to adequately supply to the connected load.
Real and reactive power flow and bus voltages and currents are determined.
ii. Fault analysis
Fault analysis determines the maximum fault current obtained during system
disturbance. Increasing level of available short circuit current is often due to
expansion of plant and adding larger loads to the network. Dangerous situation will
occurs if the short circuit capacity exceeds the capacity ofprotective device. In power
system, protective device acts to interrupt fault currents during fault conditions.
However high short circuit current may cause violent failure of the device and cause
severe damage to the device and network.
11
2.2.8 Power systemprotection
Electrical system must be protected against damage which may occur during
abnormal conditions. There are two types ofabnormalities:
i. Chronic condition - operation outside the designed ratings due to overloading
or incorrect functioning of the system
ii. Acute condition - fault conditions due usually to breakdown of some part of
the system
Thus to overcome this abnormalities a protection scheme is required in electrical
system design. Principles ofprotection system are:
i. To maintain electrical supplies to the system as possible after a fault has been
isolated
ii. To protect equipments on the plant from damage due to abnormal conditions
and faults
iii. To isolate faulted equipment to limit the risk
iv. To limit damage to the cable system resulting from a fault
The basic principle of protection is to disconnect and isolate the faulty part of the
system. This is to ensure that the fault is not sustained and aggravated by a continuing
flow ofpower into it and to prevent damages to the rest of the system.
No system of protection can be designed without knowing the conditions in the
network which it has to protect. Therefore the level fault currents at various point of
the network must be known first before selecting the best protection system
12
CHAPTER 3
METHODOLOGY / PROJECT WORK
3.1 Project flow
Planning is the most important aspects in conducting a project. Well planned project
ensures a systematical procedure throughout the project and enable the work to be
done within a specified time requirement.
As for this project, the author started off by performing literature review on electrical
system design to familiarize with the system. Next all the necessary data is collected
and the estimated load for the network is calculated and tabulated using EXCEL
software. Then power generation analysis is performed to select the most reliable
generating system for the network. Performances of the network are observed by
conducting power flow and protection analysis using ERACS software. Results from
the simulations are analyzed and last but not least all necessary information is being
documented.
A process flow chart is outlined (refer to APPENDIX A) in order to cater the project
schedule. Time management is important to ensure that the project is feasible and
could be completed within the allocated time frame.
3.1.1 Simulation tool
ERACS software is a PC-based, fully integrated and user friendly. To start simulating
network, data is entered and saved in a central database. This software is able to
predict system behaviour under both normal and abnormal conditions depending on
how the user sets the setting. ERACS helps to reduce error in calculations compares
to normal hand calculations.
13
The procedure ofthe project implementation is illustrated as Figure2 below:
Perform Literature
IIdentified
IData Gathering
Start
n\ Load
ISimulate network
system with ERACS
ILoadflow
Lii
Short-circuit
IProtection
M Analyze and Interpret ?Report
Figure 2 Project Process Workflow
14
CHAPTER 4
RESULTS AND DISCUSSION
4.1 Load analysis
The load analysis is done to establish the running and peak load at the water injection
platform and subsequently size the generator set rating. The analysis is done by
considering the operating scenario of the pumps that required the generator running at
its maximum capacity
Once the information on the load required for each of the equipment is collected,
peak load or the demand for the platform facilities can be estimated. Based on the
data collected from the design department, value of load required for each of the
equipment is entered in a spreadsheet (refer to APPENDIX B). From the spreadsheet,
estimated peak load is determined.
Based on the spreadsheet attached in Appendix B each of the equipment has been
categorized to continuous, intermittent and standby as per PTS 33.64.10.10. These
categories show the performing usage of the equipment. Below briefly explained the
difference between all three loads:
Continuous - All loads that are required continuously or cyclically for normal
operation and which may be reasonably expected to occur simultaneously
(e.g. HVAC, UPS, battery chargers etc).
Intermittent - All process and utility loads required for normal operation but
neither operating continuously nor simultaneously (e.g. Compressor Pre Lube
Oil Pump Motor).
15
* Standby - All loads required during the maintenance or changeover from a
duty to standby or during abnormal circumstances.
According to PETRONAS Technical Standard (Rev 12), electrical loads shall be
classified as performing a service, which is vital, essential or non-essential.
Vital Service
• A vital service is actually a safety matter. The failure of this service during
operation or when failing is called upon can causes an unsafe condition of the
process or installation jeopardize life or cause damage to the installation. The
energy source, lines of supply and the equipment performing a vital service
shall be completely duplicated.
Essential Service
• An essential supply is related to economic matter. Therefore the economics of
partial or complete duplication of the energy source of the lines of supply or
of the equipment performing essential service shall be evaluated in relation to
the consequences of service interruptions that will affect the quality or the
quantity ofthe product.
Non-essential Service
• According to PTS definitions, non-essential service is defined as services,
whichfall underneither vital nor essential category.
Formula to calculate the peak load based on PTS is as shown below:
- Peak load (kW) = (100% oftotal continuous load) + (30% oftotal intermittent
load @ the largest individual intermittent load whicheveris higher) + (10% of
total standby load@ the largest individual standby load whichever is higher)
16
In designpracticeestimating the demandof load shall include the possibility of future
growth of the platform. Roughly the estimation of future growth of a platform is
taken to be 25% of its estimated peak load.
Below is the estimation of the overall load required for the platform including fiiture
growth:
• From the load list, the peak load = 1345.42 kW
• Total estimated load = total peak load x 25% growth
= 1345.42x125%
= 1681.78 kW
= 1.7MW
4.2 Power generation analysis
Based on the load list in APPENDIX B, the most suitable main generator option is the
gas turbine generator. Gas turbine generator has a rotary engine that extracts energy
from a flow of combustion gas. The upstream compressor is coupled to a downstream
turbine, and a combustion chamber in-between. Gas turbine mechanism can be
explained as follow:
• Energy is released when air is mixed with fuel and ignited in the combustor
• Combustion increases the temperature, which in turn increases the pressure
resulting in an increase in the velocity and volume of the gas flow
• The gas is directed through a nozzle over the turbine's blades, spinning the
turbine and powering the compressor
17
There are a few conditions that leadto the selection of the generating system:
• Load demand - Cover all the required load for the process to be carried out on
the platform
" Space
• Weight
• Reliability - Performance of the generator should be taken into consideration.
The most reliable generator shall be the one that can withstand up to the
expected year ofprocess, robust and less maintenance
Based on the load analysis, two gas turbines each rated at 1.175MW are chosen. Both
turbines will be running to cater the platform demand. Each turbine is equally loaded.
Power supply is secured as long as turbines are healthy. With two GTG, platform
loads will have more flexibility to cater for bigger motor load, this can eliminate
future unforeseen problems should there bechanges inthe equipment ratings.
Diesel engine generator is available as back-up power supply, incase of platform
shutdown due to processupset.
4.3 Modeling and simulation
4,3.1 Single line diagram
Based on the information of the equipment planned to be installed on the platform,
single line diagram is drawn. The single line diagram shows the AC electrical
generation and distribution systemofthe plant including all HV feeds, main LV feeds
and sub-distribution boards and etc.
The design andmodel of power system network for the water injection platform is as
shown in Figure 3. Referring to Figure 3, the network consists of 2 main busbarsand
18
2 sub-busbars. Busbar 1 is rated at 6.6kV known as HV (high voltage) busbar
whereas Busbar 2 known as LV (low voltage) busbar, Busbar 3 and Busbar 4 are both
rated at 0.4kV. The network consists of two main GTG each rated at 1.1785MW and
a standby DEG rated at 0.8MW. DEG is connected at Busbar 3. An auto-recloser is
added in between busbar 2 and busbar 3. The auto-recloser is placed on the connector
that connects the two busbar. In normal condition the auto-recloser switch will be in
open position. Once the sensor in the auto-recloser detects voltage level changes from
the utility line, its switch will be closed to allow the standby generator to supply
power to the essential loads. Two transformers are connected in between HV busbar
and LV busbar. These transformer forms a step-down process from 6.6kV of HV
busbar to 0.4kV ofLV busbar. Motors placed at these busbars indicate the machinery
as listed in the load list (APPENDIX B).
19
bu
sb
ar
1
bu
sb
ar
3b
a
ats
Figu
re3
£ing
\eLi
neDi
agram
20
4.3.2 Loadflow
Loadflow is a study performing the analysis and calculates the steady state conditions
of the power system network. Loadflow calculation can be done manually however it
will be time consuming and impractical to do for a big system. Thus with the help of
ERACS software the tedious calculation can be simplified. ERACS will determine
the network voltage profile, current and real and reactive power flows. Three
scenarios are created to examine the loadflow analysis.
4.3.2.1 Scenario!: normal condition
During normal operation of the platform two turbine generators shall be running in
parallel. The turbine generators are connected to HV busbar. Motors rated 200kW and
above are connected to this busbar.
For the low voltage busbar, two power transformers are connected. Motors rated
below 200kW are connected to the LV busbar. For emergency and black start
purpose, one emergency diesel generator is installed. The emergency diesel generator
is connected to an auto-recloser. During normal operation of the platform the
emergency generator shall not be running and auto-recloser between Busbar 2 and
Busbar 3 will be in OPEN position. On detection of dead bus, Diesel Generator set
will get started automatically and supplies to Busbar 2 and Busbar 4. The network is
as shown ifFigure 4 below. The simulation result is as shown in APPENDIX C.
21
bu
sb
ar!
pV:1
.0pu
V;
6.6
kV
AV
:0
.0'
P:0
.2M
W
Q:
0.3
56
MV
Ar
t:0
.03
6k
A
T P:
0.0
MW
Q:
0.0
MV
Ar
!:0
.0k
A
bu
sb
ar
2
pV:1
.001
puV
:0
.4k
V
AV
:0
.00
*
Lo
ad
flo
w
=0:
1.01
.9M
WV
mx:
bu
sb
ar
23
G:
1.7
7M
VA
rpV
mn:
1.0
pu=
L:
1.0
19
MW
Vm
n:
bu
sb
ar
1
DL
:2
.15
5M
VA
rl3
Fm
x:2
47
.98
kA
:>L
O:
0.0
01
MW
3F
mx:
bu
sb
ar
3
3L
O:
-0.3
85
MV
Ar
l3F
rrm
:7
.52
2k
A
3a
se
10
0.0
MV
A3
Fm
n:
bu
sb
ar
1
Hz:
50
,0H
z.h
er:
5D
Vm
x1.
001
puC
on
v:
1.4
30
5E
-6
ir
P:0
.
Q;0
1:0.
1
(GSJ
P:0-
51M
WQ
:0
.88
5M
VA
r
I:0
.08
9k
A
(QS)
P:0.
51M
WQ
:0
.88
5M
VA
r
!:0
.08
9k
A
tfT
V¥
YJ
P:0
.35
MW
Q:
0.3
78
MV
Ar
I:0
.04
5k
A
00
1M
W
12
1M
VA
r
74
kA
w
P;0
.00
3M
W
Q:
0.1
21
MV
Ar
I:0
.17
4k
A
IP:
0.2
8M
W
1Q
:2
.98
MV
Ar
II:
0.2
62
kA
P:0
.2M
W
0:0
.35
6M
VA
r
I:0
.03
6k
A
IP:
0.3
49
MW
1Q
:3
.30
5M
VA
r
11
:0.2
91
kA
R0
.OM
W
Q:
0.0
MV
Ar
I:0
.0k
A
P:
0.2
MW
Q:
0.3
56
MV
Ar
I:0
.03
6k
A
2P
:0
.28
MW
2Q
:2
.98
3M
VA
r
±21
:4.
321
kA2"
LW
T
2P
:0
.34
9M
W
2Q
:3
.30
1M
VA
r
21:4
.78
7k
A
Y>
P:
0.0
2M
W
Q:
0.1
21
MV
Ar
1:0
.17
?k
A
bu
sb
ar
4
pV:1
.001
puV
:0
.4k
V
AV
:0.
001
*K
V
UH
P:
0.04
MW
1Q
:0
.22
6M
VA
r
11
:0.3
31
kA
2R
0.0
4M
W
2Q
:0
.22
6M
VA
r
NJ/2
I,0.
331
kA IT
"
P:
0.0
05
MW
Q:
0.1
21
MV
Ar
I:0
.17
4k
A
P:0
.02
MW
Q:
0.1
13
MV
Ar
,1:0
.16
5kA
,-
P:0
.02
MW
Q:
0.1
13
MV
Ar
I:0
.16
5k
A
Fig
ured
Scer
iafio
A/'
22
,91
R0
.0M
W
1Q
:-0
.39
1M
VA
r
11:0
.56
4k
A
P:
0.0
MW
Q:
0.0
MV
Ar
LO
.Ok
A
bu
sb
ar:
pV:1
.0pu
V:
0.4
kV
AV
0.2
13
*
P:
0.0
MW
Q:
0.0
MV
Ar
l:Q
.0k
A
ats
yP:
0.0M
WQ
:0
.0M
VA
r
kA
Gb
a
2P
:0
.0M
W
2Q
:0
.0M
VA
r
2l:
0.0
kA
4.3.2.2 Scenario2: one generatorset is turn off
During this operation of the platform only one turbine will be running. Since the total
load of the network is still within the capacity of the generator set therefore not much
different is observed in the real and reactive power rated at each of the motor. The
only difference observes during this scenario is the amount of power generated at the
turbine.
During this operation of the platform the emergency generator shall not be running
and auto-recloser between Busbar 2 and Busbar 3 will be in OPEN position. On
detection of dead bus, Diesel Generatorset will get startedautomatically and supplies
to Busbar 2 and Busbar 4. The network is as shown if Figure 5 below. The
simulation result is as shown in APPENDIX D.
23
15o r*- rs.
T". . . o
.a
a o R.... CD
.r-, Q. O J-:
^f
*r
^
en l^ -*-CD 01 37
. . . . o
a. o ^
S25^- en -^
no^
ll3O O
o
CL Q ^
•n i— -a--tr o r--
ci ri ^. . . . T
a. o —www
11,a o -^
.... CD
CL O ^
•^
a. o j_-W CM CM
•*&
^
o o =.... CD
Q. O -
*S5•^ to -^-^ LT> t£Jwon
ddq. . - . C3
o -^ o^ CD d
<
-Q-S"5 >^
^^o 9 ^ o o R.... CD • • CD
a a •• CL O —i—i—i—
sS2^3CD CM T
S^ 5
ci 3 itsSi Q.-Q
X £ c
III
CO
CO 05 ^ 0CTJ _Q CO _Q
w .a tn -• to en
£ X £ c yc £ c p .. c
lip
M
.. • • m £<.,oq S •-J—i _j ~J as m •>OHOIDIU
C4
4.3.2.3 Scenario3: emergencycondition
During this operation of the platform the emergency generator shall be running and
auto-recloser between Busbar 2 and Busbar 3 will be in CLOSE position. On
detection of dead bus, Diesel Generatorset will get startedautomatically and supplies
to Busbar 2 and Busbar 4. The network is as shown if Figure 6 below. The
simulation result is as shown in APPENDIX E.
25
bu
sb
ar
1
pV:
0.0
pu
V:
0.0
kV
AV
:0
.0°
P:
0.0
MW
Q:
0.0
MV
Ar
I:0
.0k
A
P:
0.0
MW
Q:
0.0
MV
Ar
i:0
.0k
A
P:
0.0
MW
Q:
0.0
MV
Ar
I:0
.0k
A
P:
0.0
MW
Q:
0.0
MV
Ar
I:0
.0k
A
bu
sb
ar
2
pV:
0.9
94
puV
:0
.39
8k
V
AV
:0
.06
8°
Load
flow
|?
G:
0.0
?M
WVm
x:bu
sbar
3j
3G
:0
.31
5M
VA
rpV
mn:
0.9
94
pu3
L0
.06
9M
WV
mn
:b
usb
ar
43
L:
0.7
MV
Ar
i3F
mx
:26
1.6
6k
A>
LO
:0
.00
1M
W3
Fm
x:
bu
sb
ar
33
LO
:-0
.38
5M
VA
ri3F
mn:9
7,373
kAj
3ase:
10
0.0
MV
A3
Fm
n:
bu
sb
ar
4t
-iz:
50
.0H
ztte
r:2
jsV
mx
1.0
pu
Conv
:9.0
897E
-7j
1 (Ml)
P:
0.0
01
MW
0:0
.11
9M
VA
r
I:0
.17
3k
A
(Ml)
\
P:
0.0
02
MW
Q:
0.1
19
MV
Ar
I:0
.17
3k
A
1P
:0.0
MW
1Q
:0
.0M
VA
r
1l:
0.0
kA
P:
0.0
MW
Q:
0.0
MV
Ar
I:0
.0k
A
P:
0.0
MW
Q:
0.0
MV
Ar
I:0
.0k
A 1P
:0.0
MW
1Q
:0
.0M
VA
r
1l:
0.0
kA
A^
P:
0.0
MW
Q:
0.0
MV
Ar
I:0
.0k
A
bu
sb
ar
3
pV:
1.0
puV
:0
.4k
V
AV
:0
.0°
2P
:0
.0M
W
2Q
:0
.0M
VA
r
:2i:
0.0
kA
P:
0.0
MW
Q:
0.0
MV
Ar
I:0
.0k
A
2P
:0
.0M
W
2Q
:0
.0M
VA
r
21:
0.0
kA
P:
0.0
MW
O:
0.0
MV
Ar
I:0
.0k
A
P:
0.0
2M
W
Q:
0.1
19
MV
Ar
I:0
.17
6k
A
bu
sb
ar
4
nH
P:
0.0
4M
W1
G:
0.2
23
MV
Ar
II:
0.3
28
kA
2P
:0
.04
MW
2Q
:0
.22
3M
VA
r
21:
0.3
28
kA
\'
^7
•r
P:
0.0
05
MW
Q:
0.1
19
MV
Ar
i:0
.17
3k
A
pV:
0.99
4pu
TP:
0.02
MW
V:
0.3
98
kV
0:0
.11
1M
VA
r
AV
:0
.06
9°
/T
\!:
0.1
64
kA
IMIJ
P:
0.0
2M
W
Q:
0.1
11
MV
Ar
I:0
.16
4k
A
Fig
ure
6S
cena
rio
3
26
r
IP:
0.0
69
MW
..1
Q:
0.7
MV
Ar
II:
1.0
21
kA
P:
0,0
MW
Q:
0.0
MV
Ar
I:0
.0k
A
ats
(GSJ
P:0,
07M
WQ
:0
.31
5M
VA
r
I:0
.46
5k
A
ba
2P
:0
,07
MW
2Q
:0
.31
5M
VA
r
21:
0.4
65
kA
4.3.2.4 Summary ofloadflow results
Table 1 Description ofeach scenario
Scenario Description
1Two turbine generators are running, ail transformers are in operation, alltie-breakers are closed, auto-recloser is opened.
2Only one turbine generator is running, all transformers are in operation,all tie-breakers are closed, auto-recloser is opened.
3Auto-recloser is closed, only DEG operates, all transformer are notoperating, all tie-breakers to the HV side are opened
Table 2 Summary ofrated MW values ofgenerator set at different scenario
Scenario GEN1 GEN 2 STANDBY GEN
1 0.501 MW 0.501 MW OMW
2 OMW 1.001 MW OMW
3 OMW OMW 0.052 MW
4.3.3 Fault analysis
The fault analysis is done to calculate the perspective fault current at main
switchboard and subsequently size the busbar rating. The network is as shown if
Figure 7 below. The simulation result is as shown in APPENDIX F.
27
bu
sb
ar
1
lp:7
.522
kA
Ip:0
.405
kA
bu
sb
ar
2
ip:1
22.7
3kA
¥ lp:0
.0kA i^
IMI
(fcgj'
lp:2.5
05kA
Ip:
0.40
3kA
T
ip:2
.333
kA
J)Ip
:2.3
33kA
(QS)
ip:2
.505
kA
Ip:0
.452
kAj
Ip:0.
452
kA
lp:0
.4Q
5kA
lp:
0.40
5kA
bu
sb
ar
3
ip:
247.
98kA
ip:5
3.90
5kA
—x—
!p:D
.0kA
ip:5
3.90
5kA
lp:O
.0kA
51? U
p:5.
596
kA.
<)<
i.
Ip:2
.333
kA.
1lp
:0.0
kA9
ats
lp:2
.332
kA
2lp
:ll6
.14
kA
ip:0
.0kA
bu
sb
ar
4
lp:1
21
.74
kA
TV
lp:2
.799
kAn
lp:2
.799
kA
(Ml)
Fig
ure
7T
hree
Pha
seF
ault
Ana
lysi
s
28
(GSj
lp:2
47.98
kA
[]b
a
V
2lp:
0.0
kA
4.3.4 Protection
As the operation of the electrical system involves not only machineries but human
life, safety is certainly an important issue. Any unsafe act is a treat to human, network
and system performance. Therefore protection system is designed to provide a safe
workspace for personnel and minimize damage to the overall system as well as
isolating faultydevices fromthe system.
Protection of a system has the main function to ensure automatic disconnection in
occurrence of short circuit. Some of the protection attributes to select appropriate
protection system ofa network are as listed below:
• Selectivity
• Security
• Sensitivity
• Dependability
• Speed
29
5.1 Summary
CHAPTERS
CONCLUSION
As mention previously, design of electrical power systems involves much
analysis. It is essential to perform these analyses in order to design the most
optimum power systems.
A schematic diagram (refer to figure 1) was drawn based on information
obtained from the load list (refer to APPENDIX B). Once the schematic
diagram is obtained, performance analysis is conducted. First, the loadflow
analysis is conducted. Three scenarios are created and the results are obtained
as shown in FIGURE 4, 5 and 6. A detail result of each scenario is as attached
in APPENDIX C, D and E. From the loadflow analysis conducted the total
load of the whole network is 1.019 MW. Power supplied by the main
generators is equally shared depending on the total network load. Difference
of each scenario is as shown in Table 1 and 2. Fault analysis result is as
obtained in figure 7 and detail result of the analysis as attached in APPENDIX
F.
By conducting the loadflow analysis, it enables sizing of the generator as well
as designing the overall distribution of the network. The fault analysis on the
other hand enables the most appropriate protection scheme for the network.
Both analyses are indeed required in order to have the most optimum design
of an electrical system.
30
It can be concluded that the simulation studies are crucial in design of power
system. Simulation improves the routinedesign and allows easier performance
assessment of the power system. In order to perform the simulation with
ERACS software, it is important to put the right rating and assumption in
order to obtain correct simulation ofthe networks.
5.2 Recommendation
5.2.1 Perform other analysis
ERACS software provides other program modules. Thus the analysis of the network
can be extend by conducting other modules such as harmonic impedance, transient
stability and others in order to have better understanding of the performance of the
electrical design.
5.2.2 Comparison result with other software
There is other software which is also able to perform power performance analysis.
Results of simulation from other software can be compared. This can broaden the
scope of simulation.
31
REFERENCES
1. http://ieeexplore.ieee.org/iel3/1167/7720/00324143.pdf
2. http://ieeexplore.ieee.org/iel3/5185/14025/00643437.pdf
3. http://ieeexplore.ieee.org/iel3/1160/4020/00154193.pdf
4. http://en.wikipedia.org/wiki/Oil_platform
5. http://www.abb.com/Industries
6. http://en.wikipedia.org/wiki/Gas turbine
7. Mohd Zhafri b Nasaruddin, Final Year Project Final Report, An Integrated
Approach For The Best Selection OfOffshore Power Generation.
8. Tan Yan Choon, 1st edition, Design and Specification of Power Distribution
and Protection Systems in Building, Amos Technologies PTE LTD
9. PETRONAS Technical Standard (PTS) Revl 2
32
APPENDICES
33
APPENDIX A
PROCESS FLOW CHART
34
Set objective and project for FYPpart II
•Q'
Literature review on the powersystem protection
<>
Progress report preparation
•Q"
Select appropriate data requiredfor the simulation
%•>
Work on the designing power system
<>*£.
Progress report II in preparation
p*
Work on the simulation
<**£.
Troubleshooting
<>
Final report preparation
•o*
Oral presentation
Process Flow Chart
35
d
V
7\
APPENDIX B
LOADLIST
36
EQ
UIP
.
NO
.
DE
SC
RIP
TIO
Na
.
(0 o _l
n c 0)
Hi
0)
m
c 0)
w <n
tit
c o z
3 « as
•a CO
s m
LO
AD
RA
TIN
G
rr
FA
CT
OR
A Bre
-
at
load
facto
rC
FA
CT
OR
at
loa
d
facto
rC
Co
nti
nu
ou
s
rr
inte
rmit
ten
tS
tan
d-b
y
RT
kW
kW
ind
ecim
als
ind
ecim
als
co
s(p
kW
kV
Ar
kW
kV
Ar
kW
kV
Ar
1.0
21
.20
2.1
3
17
0.0
0
17
0.0
02
00
.00
17
0.0
0
29
7.5
03
50
.00
29
7.5
03
50
.00
17
.00
20
.00
42
.50
50
.00
42
.50
17
0.0
0
17
0.0
02
00
.00
34
.00
17
.00
20
.00
17
.00
42
.5G
|T
OT
AL
Ap
par
ent
Po
wer
Po
wer
Facto
r
Peak
Lo
ad
10
14
.36
54
7.5
01
7.8
99
.66
53
6.8
42
89
.76
Co
nn
ecte
dL
oad
=S
um
mat
ion
ofm
otor
s/
load
rati
ngs
11
52
.69
20
.33
61
0.0
5
Pea
kL
oad
=T
otal
Co
nti
nu
ou
sL
oad
0.8
80
.88
0.8
8
+0
.3x
To
tal
Inte
rmit
ten
tL
oad
+0.
1x
Tot
alS
tan
db
yL
oad
13
45
.42
kW
Defin
itions
.Ab
sQrbe
d|og
dsb)
Cons
umed
loads
G-"St
and-by
";loa
dsreq
uired
inem
ergen
cieso
nly-f
orpu
mps
shaf
tloa
don
duty
poin
t;E
-"C
ontin
uous
";all
load
sth
atm
ayco
ntin
uous
lyor
thos
eof
norm
ally
not
- for
instr
umen
tatio
nco
mpu
ters
,com
mun
icat
ion,
bere
quire
dfo
rnor
mal
oper
atio
n,in
clud
ing
runn
ing
elec
tnca
llydn
ven
units
,sta
nd-b
yfo
rair
cond
ition
ing,
the
requ
ired
load
durin
gful
llig
htin
g.no
rmall
yru
nnin
gste
am-d
riven
ones
(e.g
.op
erat
ion
ofpl
ant
F-"
Inte
rmitt
enta
ndsp
ares
";th
elo
ads
requ
ired
pum
ps)
-for
light
ing
durin
gda
rkho
urs
fori
nter
med
iate
pum
ping
,sto
rage
,loa
ding
,etc
.-f
orw
orks
hop,
the
aver
aget
otal
load
inno
rmal
and
allel
ectri
cals
pare
sofe
lect
rical
lydr
iven
units
full
op
erat
ion
No
tes:
1N
avig
atio
nal
aid
syst
emis
sola
rpo
wer
ed.
37
APPENDIX C
LOAD FLOW ANALYSIS : SCENARIO 1
38
ERACS
Loadflow
module
By
ERA
Technology
Ltd.
ERACS
Version:
3.5.0.
Loadflow
Version:
3.5.0
Run
on
13-Jun-2007
by
Supervisor
from
data
set
up
on
13-Jun-20Q7
by
Supervisor
Network
Name
Data
State
Name
prac_l
17/4
SYSTEM
STATISTICS
Study
Base
MVA
=100.000
Study
Base
Frequency
(Hz)
=50.000
Number
of
Busbars
=4
Number
of
Shunts
=0
Number
of
Lines
=1
Number
of
Cables
=1
Number
of
Transformers
=2
Number
of
Tap
Changers
=0
Number
of
Synchronous
Machines
=3
Number
of
Induction
Machines
=14
Number
of
Wind
Turbine
Generators
=0
Number
of
Bus
Sections
=0
Number
of
Series
Elements
=0
BUSBAR
DATA
Busbar
Identifier
Nominal
kV
Three
Phase
Fault
MVA
kA
busbar
1
busbar
2
busbar
3
busbar
4
LINE
DATA
6.6
00
0.4
00
0.4
00
0.4
00
150.0
31.0
31.0
31.0
13.122
44.745
44.745
44.745
Single
Phase
Fault
MVA
kA
200.0
45.0
45.0
45.0
17.495
64.952
64.952
64.952
STUDY
PARAMETERS
Load
Power
Multiplier
=Load
Reactive
Multiplier
=Convergence
Tolerance
=Convergence
Control
=Maximum
Iterations
Overload
Flag
Level
Automatic
Tap
Changers
Transf.
Shift
Angle
(deg.)
0.0
30.0
0.0
30.0
Nominal
Bus
Freq.
(Hz)
50.0
50.0
50.0
50.0
1.000000
1.000000
0.000005
=Method
2
25
=100.0%
Of
Rating
OFF
Page
No.
1
First
Second
Line
No.Of
Line
Library
Busbar
Busbar
Identifier
Ccts
Length
Key
Rating
Positive
Sequence
(kA)
R(pu)
X(pu))
B(pu)
Zero
Sequence
R(pu)
X(pu)
B(pu)
0.01000
0.01000
0.00000
Equivalent
Pi
Model
busbar
2busbar
41
21.00
11
1.000
0.01000
0.01000
0.00000
39
Run
on
13-Jun-2007
by
Supervisor
fromdata
set
up
on
13-Jun-2007
by
Supervisor
Network
Name
:prac__l
Data
State
Name
:17/4
CABLE
DATA
First
Busbar
Second
Busbar
Cable
Identifier
No.Of
Ccts
Cable
Length
Library
Key
Rating
(kA)
Positive
R(pu)
Sequence
X(pu)
B(pu)
Zero
Sequence
R(pu)
X(pu)
B(pu)
Equivalent
Pi
Model
busbar
2busbar
3connector
11
1.00
cable1
2.500
0.3821
1.0990
0.0039
0.5382
1.0990
0.0042
CABLE
OPEN
TRANSFORMER
DATA
System
Winding
Rating
Winding
Angle
Pos/Neg.
Sequence
Zero
Sequence
Neutral
Earth
Busbar
No.
(MVA)
Type
(deg.)
R(pu)
X(pu)
R(pu)
X{pu)
R(pu)
X(pu)
Voltage
Off-Nom
Ratio
Tap
(%)
DATA
for
Transformer
with
ID.
trans_a
busbar
11
150.000
D
busbar
22
150.000
YN
DATA
for
Transformer
with
ID.
trans_b
busbar
11
150.000
D
busbar
22
150.000
YN
INDUCTION
MACHINE
DATA
Busbar
Identifier
Motor
Identifier
busbar
1Ml
busbar
1M2
busbar
1M3
busbar
1M5
busbar
1M6
busbar
1M4
busbar
2M8
busbar
2M9
busbar
2motor
7
busbar
2motor
7
busbar
2M10
busbar
1M7
busbar
4m2
No.Of
Library
Units
Key
1motor
1
1motor
1
1motor
3
1motor
3
1motor
1
1motor
1
1motor7
1motor8
1motoric
1motor10
1motor9
1motor
1
1motor22
No.
of
units
1using
library
key
trans_a
30.00
0.0016
0.0158
0.0016
0.0158
0.0000
0.0000
1.0000
0.20
0.00
0.0016
0.0158
0.0016
0.0158
0.0000
0.0000
1.0000
0.20
No.
of
units
30.00
0.0016
0.00
0.0016
1using
library
key
trans_a
0.0158
0.0016
0.0158
0.0000
0.0000
1.0000
0.00
0.0158
0.0016
0.0158
0.0000
0.0000
1.0000
0.20
Motor
Ratings
MVA
MW
kV
Input
Slip
Stator
Magnet.
Standstill
Rotor
Running
MW
(%)
R{pu)
X(pu)
X(pu)
R(pu)
X(pu)
R{pu)
X(pu)
1..080
0.200
6.,600
0.200
0.2778
0,.0050
0.1200
3.0000
0.0250
0..1000
0.0150
0.1500
1. .080
0.200
6..600
0.200100.0000
0,.0050
0.1200
3.0000
0.0250
0.,1000
0.0150
0.1500
NOT
IN
SERVICE
1..080
0.350
6.,600
0.350
0.4861
0,.0050
0.1200
3.0000
0.0250
0..1000
0.0150
0.1500
1. .080
0.350
6..600
0.350100.0000
0..0050
0.1200
3.0000
0.0250
0..1000
0.0150
0.1500
NOT
IN
SERVICE
1.,080
0.200
6.,600
0.200
0.2778
0,.0050
0.1200
3.0000
0.0250
0..1000
0.0150
0.1500
1. .080
0.200
6.,600
0.200
0.2778
0..0050
0.1200
3.0000
0.0250
0,.1000
0.0150
0.1500
0,.405
0.001
0.,415
0.001
0.0048
0..0054
0.1292
3.2292
0.0269
0..1076
0.0161
0.1615
0..405
0.002
0..415
0.002
0.0100
0..0054
0.1292
3.2292
0.0269
0,.1076
0.0161
0.1615
0,.405
0.005
0.,415
0.005
0.0199
0..0054
0.1292
3.2292
0.0269
0,.1076
0.0161
0.1615
0..405
0.005
0.,415
0.005100.0000
0..0054
0.1292
3.2292
0.0269
0,.1076
0.0161
0.1615
NOT
IN
SERVICE
0,.405
0.020
0,,415
0.020
0.0797
0.,0054
0.1292
3.2292
0.0269
0,.1076
0.0161
0.1615
1,.080
0.200
6.,600
0.200100.0000
0..0050
0.1200
3.0000
0.0250
0..1000
0.0150
0.1500
NOT
IN
SERVICE
0..405
0.020
0..400
0.020
0.0741
o..0100
0.1000
3.5000
0.0200
0..1000
0.0150
0.1500
40
Run
on
13-Jun-2007
by
Supervisor
from
data
set
up
on
13~Jun-2007
by
Supervisor
Network
Name
:prac_l
Data
State
Name
:17/4
INDUCTION
MACHINE
DATA
Busbar
Identifier
Motor
:Identifier
No.Of
Library
Units
Key
Motor
Ratings
MVA
MW
kV
Input
MW
Slip
(%)
Stator
R(pu)
X(pu)
Magnet.
X(pu)
Standstill
R(pu)
X(pu)
Rotor
Running
R(pu)
X(pu)
busbar
4m3
1motor22
0.405
0.020
0.400
0.020
0.0741
0.0100
0.1000
3.5000
0.0200
0.1000
0.0150
0.1500
SYNCHRONOUS
MACHINE
DATA
Busbar
Machine
Type
No.Of
Library
Identifier
Identifier
Units
Key
busbar
1Gen
aSLACK
2Gen
a
busbar
1Gen
bSLACK
2Gen
a
busbar
3SLACK
1Gen
b
Generator
Ratings
MVA
BASE
MW
kV
Assigned
V(pu)
MW
Pos.
Sequence
Neg.
Sequence
Zero
Sequence
MVAR
R(pu)
X(pu)
R(pu)
X(pu)
R(pu)
X(pu)
5.000
2.350
6.600
1.000
0.000
0.000
0.0125
0.1800
Neutral
earthing
0.0000
0.0000
5.000
2.350
6.600
1.000
0.000
0.000
0.0125
0.1800
Neutral
earthing
0.0000
0.0000
31.000
0.800
0.400
1.000
0.000
0.000
0.0125
0,1800
41
0.0500
0.2400
0.0000
0.0000
0.0500
0.2400
0.0000
0.0000
0.0125
0.0550
0.0000
0.0000
0.0125
0.0550
0.0000
0.0000
0.0500
0.2400
NEUTRAL
O/C
Run
on
13-Jun-2007
by
Supervisor
from
data
set
up
on
13-Jun-2007
by
Supervisor
:prac_l
Network
Name
Data
State
Name
17/4
AT
STUDY
END
-No
of
iterations
=5
Convergence
=0.1431S-05
VoltageRange
from
l.OOOpuatbusbar1
to
l.OOlpuatbusbar2
AC
BUSBARVALUES
Busbar
Identifier
Merge
Busbar
Type
PU
Voltage
Synch.
Machines
kV
ANG-DEG
MW
MVAr
IndMotor
Load
MW
MVAr
Shunt
MW
Loads
3Phase
Fault
MVAr
kA
X/R
Ph
-E
Fault
kA
X/R
busbar
1SLACK
1..000
6.600
0.000
1.019
1.770
0.950
1.446
0.000
0.000
7.52
18,.384
8.39
8,,413
busbar
3SLACK
1..000
0.400
0.213
0.000
0.000
0.000
0.000
0.000
0.000
247.98
14,.400
busbar
2LOAD
1,.001
0.400
0.000
0.000
0.000
0.029
0.484
0.000
0.000
122.73
18,.253
165.95
10.,483
busbar
4LOAD
1..001
0.400
0.001
0.000
0.000
0.040
0.226
0.000
0.000
121.74
16..132
164.03
9.,529
BUSBAR
TOTALS
1.019
1.770
1.019
2.155
0.000
0.000
TOTAL
BUS
LOAD
1.019
2.155
SYSTEM
LOSSES
0.0
01
-0
.38
5
LIN
EV
AL
UE
S
First
Busbar
Second
Busbar
Branch
Identifier
No.Of
Ccts
Rating
kA
First
MW
End
Flow
MVAr
kA
Second
MW
End
Flow
MVAr
kA
Loading
(%)
O/L
FLAG
busbar
2busbar
41_2
11.000
0.040
0.226
0.331
-0.040
-0.226
0.331
33.1
CABLE
VALUES
First
Busbar
Second
Busbar
Branch
Identifier
No.Of
Ccts
Rating
kA
First
MW
End
Flow
MVAr
kA
Second
MW
End
Flow
MVAr
kA
Loading
O/L
FLAG
busbar
2busbar
3connector
11
2.500
0.000
-0.391
0.564
0.000
0.000
0.000
22.5
42
Run
on
13-Jun-2007
by
Supervisor
from
data
set
up
on
13-Jun-2007
by
Supervisor
Network
Name
:prac_l
Data
State
Name
:17/4
TRANSFORMER
VALUES
Transformer
No.Of
Identifier
Units
Winding
Connected
No.
Busbar
Winding
kV
Voltage
Ratio
Off
Nominal
Tap
%Rating
MVA
Flow
From
Busbar
MW
MVAr
Current
kA
Percent
O/L
Loading
Flag
trans
a1
1busbar
16.600
1.0000
0.200
150.000
-0.280
-2.980
0.262
2.0
2busbar
20.400
1.0000
0.200
150.000
0.280
2.983
4.321
2.0
trans
b1
1busbar
16.600
1.0000
0.000
150.000
0.349
3.305
0.291
2.2
2busbar
20.400
1.0000
0.200
150.000
-0.349
-3.301
4.787
2.2
BRANCH
LOSS
SUMMARY
(MW)
SERIES
LOSSES
0.001
SHUNT
LOSSES
0.000
TOTAL
LOSSES
0.001
(MVAr)
0.006
-0.391
-0.385
INDUCTION
MACHINE
VALUES
Busbar
Machine
No.Of
Slip
Terminal
Voltage
Machine
Input
Current
O/L
Identifier
Identifier
Units
%kV
MW
MVAr
kA
Flag
busbar
1Ml
10.30
6.600
0.200
0.356
0.036
busbar
1M2
1MACHINE
DISCONNECTED
busbar
1M3
10.53
6.600
0.350
0.378
0.045
busbar
1M5
1MACHINE
DISCONNECTED
busbar
1M6
10.30
6.600
0.200
0.356
0.036
busbar
1M4
10.30
6.600
0.200
0.356
0.036
busbar
2M8
10.00
0.400
0.001
0.121
0.174
busbar
2M9
10.01
0.400
0.003
0.121
0.174
busbar
2motor
71
0,02
0.400
0.005
0.121
0.174
busbar
2motor
71
MACHINE
DISCONNECTED
busbar
2M10
10.09
0.400
0.020
0.121
0.177
busbar
1M7
1MACHINE
DISCONNECTED
busbar
4m2
10.08
0.400
0.020
0.113
0.165
busbar
4m3
10.08
0.400
0.020
0.113
0.165
43
Run
on
13-Jun-2007
by
Supervisor
from
data
set
up
on
13-Jun-2007
by
Supervisor
Network
Name
:prac_l
Data
State
Name
:17/4
SYNCHRONOUS
MACHINE
VALUES
Busbar
Identifier
Machine
Identifier
No.Of
Units
Terminal
Voltage
kV
Power
MW
Output
MVAr
Current
kA
O/L
Flag
busbar
1
busbar
1
busbar
3
Gen
a
Gen
b
2 2 1
6.600
6.600
0.400
0.510
0.510
0.000
0.885
0.885
0.000
0.089
0.089
0.000
44
APPENDIX D
LOAD FLOW ANALYSIS : SCENARIO 2
45
ERACS
Loadflowmodule
By
ERA
Technology
Ltd.
ERACS
Version:
3.5.0.
Loadflow
Version:
J.s.u
Run
on
13-Jun-2007
by
Supervisor
from
data
set
up
on
13-Jun-2007
by
Supervisor
Network
Name
Data
State
Name
prac_l
17/4
SYSTEM
STATISTICS
Study
Base
MVA
=100.000
Study
Base
Frequency
(Hz)
=50.000
Number
of
Busbars
=4
Number
of
Shunts
=0
Number
of
Lines
=1
Number
of
Cables
=1
Number
of
Transformers
=2
Number
of
Tap
Changers
=0
Number
of
Synchronous
Machines
=3
Number
of
Induction
Machines
=14
Number
of
Wind
Turbine
Generators
=0
Number
of
Bus
Sections
=0
Number
of
Series
Elements
=0
BUSBAR
DATA
Busbar
Identifier
Nominal
kV
Three
Phase
Fault
MVA
kA
busbar
1
busbar
2
busbar
3
busbar
4
6.6
00
0.4
00
0.4
00
0.4
00
150.0
31.0
31.0
31.0
13.122
44.745
44.745
44.745
Single
Phase
Fault
MVA
kA
20
0.0
45
.0
45
.0
45
.0
17
.49
5
64
.95
2
64
.95
2
64
.95
2
STUDY
PARAMETERS
Load
Power
Multiplier
=Load
Reactive
Multiplier
=Convergence
Tolerance
=Convergence
Control
Maximum
Iterations
=
Overload
Flag
Level
=Automatic
Tap
Changers
Transf.
Shift
Angle
(deg.)
0.0
30
.0
0.0
30
.0
Nominal
Bus
Freq.
(Hz)
50
.0
50
.0
50
.0
50
.0
1.000000
1.000000
=0.000005
=Method
2
25
=100.0%
Of
Rating
OFF
fage
wo,
LINE
DATA
First
Busbar
Second
Busbar
Line
Identifier
No.Of
Ccts
Line
Length
Library
Key
Rating
(kA)
Positive
Sequence
R(pu)
X(pu))
B(pu)
Zero
Sequence
R(pu)
X(pu)
B(pu)
Equivalent
Pi
Model
busbar
2busbar
41_2
11.00
1_1
1.000
0.01000
0.01000
0.00000
0.01000
0.01000
0.00000
46
Run
on
13-Jun-2007
by
Supervisor
from
data
set
up
on
13-Jun-ZUU7
by
Supervisor
Network
Name
:prac_l
Data
State
Name
:17/4
CABLE
DATA
First
Busbar
Second
Busbar
Cable
Identifier
No.Of
Ccts
Cable
Length
Library
Key
Rating
(kA)
Positive
Sequence
R(pu)
X(pu)
B(pu)
Zero
Sequence
R{pu)
X(pu)
B(pu)
Equivalent
pi
Model
busbar
2busbar
3connector
11
1.00
cablel
2.500
0.3821
1.0990
0.0039
0.5382
1.0990
0.0042
CABLE
OPEN
TRANSFORMER
DATA
System
Winding
Rating
Winding
Angle
Pos/Neg.
Sequence
Zero
Sequence
Neutral
Earth
Busbar
No.
(MVA)
Type
(deg.)
R(pu)
X(pu)
R(pu)
X(pu)
R(pu)
X{pu)
Voltage
Off-Nom
Ratio
Tap
(%)
DATA
for
Transformer
with
ID.
trans__a
busbar
11
150.000
D
busbar
22
150.000
YN
DATA
for
Transformer
with
ID.
trans_b
busbar
11
150.000
D
busbar
22
150.000
YN
INDUCTION
MACHINE
DATA
Busbar
Identifier
Motor
Identifier
No.Of
Library
Units
Key
No.
of
units
30.00
0.0016
0.00
0.0016
1using
library
key
trans_a
0.0158
0.0016
0.0158
0.0000
0.0158
0.0016
0.0158
0.0000
No.
of
units
1using
library
key
trans_a
30,00
0.0016
0.0158
0.0016
0.0158
0.0000
0.00
0.0016
0.0158
0.0016
0.0158
0.0000
0.0000
0.0000
0.0000
0.0000
1.0000
1.0000
1.0000
1.0000
0.20
0.20
0.00
0.20
Motor
Ratings
MVA
MW
kV
Input
MW
Slip
(%)
Stator
R(pu)
X(pu)
Magnet,
X(pu)
Standstill
Rotor
Running
R(pu)
X(pu)
R(pu)
X(pu)
busbar
1Ml
1motor
11.080
0.200
6.600
0.200
0.2778
0.0050
0.1200
3.0000
0.0250
0.1000
0.0150
0.1500
busbar
1M2
1motor
11.080
0.200
6.600
0.200100.0000
0.0050
0.1200
3.0000
0.0250
0.1000
0.0150
0.1500
NOT
IN
SERVICE
busbar
1M3
1motor
31.080
0.350
6.600
0.350
0.4861
0.0050
0.1200
3.0000
0.0250
0.1000
0.0150
0.1500
busbar
1M5
1motor
31.080
0.350
6.600
0.350100.0000
0.0050
0.1200
3.0000
0.0250
0.1000
0.0150
0.1500
NOT
IN
SERVICE
busbar
1M6
1motor
11.080
0.200
6.600
0.200
0.2778
0.0050
0.1200
3.0000
0.0250
0.1000
0.0150
0.1500
busbar
1M4
1motor
11.080
0.200
6.600
0.200
0.2778
0.0050
0.1200
3.0000
0.0250
0.1000
0.0150
0.1500
busbar
2M8
1motor7
0.405
0.001
0.415
0.001
0.0048
0.0054
0.1292
3.2292
0.0269
0.1076
0.0161
0.1615
busbar
2M9
1motorS
0.405
0.002
0.415
0.002
0.0100
0.0054
0.1292
3.2292
0.0269
0.1076
0.0161
0.1615
busbar
2motor
71
motorlO
0.405
0.005
0.415
0.005
0.0199
0.0054
0.1292
3,2292
0.0269
0.1076
0.0161
0.1615
busbar
2motor
71
motor10
0.405
0.005
0.415
0.005100.0000
0.0054
0.1292
3.2292
0.0269
0.1076
0.0161
0.1615
NOT
IN
SERVICE
busbar
2M10
1motor9
0.405
0.020
0.415
0.020
0.0797
0.0054
0.1292
3.2292
0.0269
0.1076
0.0161
0.1615
busbar
1M7
1motor
11.080
0.200
6.600
0.200100.0000
0.0050
0.1200
3.0000
0.0250
0.1000
0.0150
0.1500
NOT
IN
SERVICE
busbar
41
motor22
0.405
0.020
0.400
0.020
0.0741
0.0100
0.1000
3.5000
0.0200
0.1000
0.0150
0.1500
47
Run
on
13-Jun-20U7
by
Supervisor
irom
aata
set
up
on
u-jun-zuu/oy
supervisor
Network
Name
:prac_l
Data
State
Name
:17/4
INDUCTION
MACHINE
DATA
Busbar
Motor
Identifier
identifier
No.Of
Units
Library
Key
Motor
Ratings
MVA
MW
kV
Input
MW
Slip
(%)
Stator
R(pu)
X(pu)
Magnet.
X(pu)
Standstill
R(pu)
X(pu)
Rotor
Running
R(pu)
X(pu)
busbar
41
motor22
0.405
0.020
0.400
0.020
0.0741
0.0100
0.1000
3.5000
0.0200
0.1000
0.0150
0.1500
SYNCHRONOUS
MACHINE
DATA
Busbar
Machine
Type
No.Of
Library
Identifier
Identifier
Units
Key
busbar
1Gen
aSLACK
2Gen
a
busbar
1Gen
bSLACK
2Gen
a
busbar
3SLACK
1Gen
b
Generator
Ratings
MVA
BASE
MW
kV
Assigned
V(pu)
MW
Pos.
Sequence
Neg.
Sequence
Zero
Sequence
MVAR
R(pu)
X(pu)
R(pu)
X(pu)
R(pu)
X(pu)
5.000
NOT
IN
SERVICE
1.000
0.000
0.000
0.0125
0.1800
Neutral
earthing
0.0000
0.0000
5.000
2.350
6.600
1.000
0.000
0.000
0.0125
0.1800
Neutral
earthing
0.0000
0.0000
31.000
0.800
0.400
1.000
0.000
0.000
0.0125
0.1800
48
0.0500
0.2400
0.0000
0.0000
0.0500
0.2400
0.0000
0.0000
0.0125
0.0550
0.0000
0.0000
0.0125
0.0550
0.0000
0.0000
0.0500
0.2400
NEUTRAL
O/C
Run
on
13-Jun-2007
by
Supervisor
from
data
set
up
on
13-Jun-2007
by
Supervisor
Network
Name
:prac_l
Data
State
Name
:17/4
AT
STUDY
END
-No
of
iterations
=6
Convergence
=0.3994E-05
Voltage
Range
from
l.OOOpu
at
busbar
1to
l.OOlpu
at
busbar
2
AC
BUSBAR
VALUES
Busbar
Busbar
Voltage
Synch.
Machines
Ind
Motor:Load
Shunt
Loads
3Phase
Fault
Ph
-E
Fault
Identifier
Merge
Type
PU
kV
ANG-DEG
MW
MVAr
MW
MVAr
MW
MVAr
kA
X/R
kA
X/R
busbar
1SLACK
I.000
6.600
0.000
1.019
1.770
0.950
1.446
0.000
0.000
5.10
21.165
5.46
9.101
busbar
3SLACK
1.000
0.400
0.618
0.000
0.000
0.000
0.000
O.OOQ
0.000
247.98
14.400
busbar
2LOAD
1.001
0.400
0.000
0.000
0.000
0.029
0.484
0.000
0.000
83.54
21.048
116.32
13.365
busbar
4LOAD
1.001
0.400
0.001
0.000
0.000
0.040
0.226
0.000
0.000
83.11
19.151
115.41
12.276
BUSBAR
TOTALS
1.019
1.770
1.019
2.155
0.000
0.000
TOTAL
BUS
LOAD
1.019
2.155
SYSTEM
LOSSES
0.001
-0.385
LINE
VALUES
First
Busbar
Second
Busbar
Branch
Identifier
No.Of
Ccts
Rating
kA
First
MW
End
Flow
MVAr
kA
Second
MW
End
Flow
MVAr
kA
Loading
O/L
FLAG
busbar
2busbar
41_2
11.000
0.040
0.226
0.331
-0.040
-0.226
0.331
33.1
CABLE
VALUES
First
Busbar
Second
Busbar
Branch
Identifier
No.Of
Ccts
Rating
kA
First
MW
End
Flow
MVAr
kA
Second
MW
End
Flow
MVAr
kA
Loading
(%)
O/L
FLAG
busbar
2busbar
3connector
11
2.500
0.000
-0.391
0.564
0.000
0.000
0,000
22.5
49
Run
on
13-Jun-2007
by
Supervisor
from
data
set
up
on
13-Jun-2007
by
Supervisor
Network
Name
:prac_l
Data
State
Name
:17/4
TRANSFORMER
VALUES
Transformer
No.Of
Identifier
Units
Winding
Connected
No.
Busbar
Winding
kV
voltage
Ratio
Off
Nominal
Tap
%Rating
MVA
Flow
From
Busbar
MW
MVAr
Current
kA
Percent
O/L
Loading
Flag
trans
a1
1busbar
16.600
1.0000
0.200
150.000
-0.280
-2.980
0.262
2.0
2busbar
20.400
1.0000
0.200
150.000
0.280
2.983
4.321
2.0
trans
b1
1busbar
16.600
1.0000
0.000
150.000
0.349
3.305
0.291
2.2
2busbar
20.400
1.0000
0.200
150.000
-0.349
-3.301
4.787
2.2
BRANCH
LOSS
SUMMARY
(MW)
1[MVAr)
SERIES
LOSSES
0.001
0..006
SHUT*IT
LOSSES
0.000
-0..391
tot;
LOSSES
0.001
-=
-0,.385
INDUCTION
MACHINE
VALUES
Busbar
Machine
No.Of
Slip
Terminal
Voltage
Machine
Input
Current
O/L
Identifier
Identifier
Units
%kV
MW
MVAr
kA
Flag
busbar
1Ml
10.30
6.600
0.200
0.356
0.036
busbar
1M2
1MACHINE
DISCONNECTED
busbar
1M3
10.53
6.600
0.350
0.378
0.045
busbar
1M5
1MACHINE
DISCONNECTED
busbar
1M6
10.30
6.600
0.200
0.356
0.036
busbar
1M4
10.30
6.600
0.200
0.356
0.036
busbar
2M8
1O.OO
0.400
0.001
0.121
0.174
busbar
2M9
10.01
0.400
0.003
0.121
0.174
busbar
2motor
71
0.02
0.400
0.005
0.121
0.174
busbar
2motor
71
MACHINE
DISCONNECTED
busbar
2M10
10.09
0.400
0.020
0.121
0.177
busbar
1M7
1MACHINE
DISCONNECTED
busbar
41
0.08
0.400
0.020
0.113
0.165
busbar
41
0.08
0.400
0.020
0.113
0.165
50
Kun
on
u-Jun-iiuu/oy
supervisor
trom
data
set
up
on
13-Jun-20Q7
by
Supervisor
Network
Name
:prac_l
Data
State
Name
:17/4
SYNCHRONOUS
MACHINE
VALUES
Busbar
Machine
No.Of
Terminal
Voltage
Power
Output
Current
O/L
Identifier
Identifier
Units
kv
MW
MVAr
kA
Flag
busbar
1Gen
a2
MACHINE
DISCONNECTED
busbar
1Gen
b2
6.600
1.019
1.770
0.179
busbar
31
0.400
0.000
0.000
0.000
51
APPENDIX E
LOAD FLOW ANALYSIS : SCENARIO 3
52
Run
on
13-Jun-2007
by
Supervisor
from
data
set
up
on
13-Jun-2007
by
Supervisor
Network
Name
Data
State
Name
prac_l
17/4
SYSTEM
STATISTICS
Study
Base
MVA
=100.000
Study
Base
Frequency
(Hz)
=50.000
Number
of
Busbars
=4
Number
of
Shunts
=0
Number
of
Lines
=1
Number
of
Cables
=1
Number
of
Transformers
=2
Number
of
Tap
Changers
=0
Number
of
Synchronous
Machines
=3
Number
of
Induction
Machines
=14
Number
ofWind
Turbine
Generators
=0
Number
of
Bus
Sections
=0
Number
of
Series
Elements
=0
BUSBAR
DATA
Busbar
Identifier
Nominal
kV
Three
Phase
Fault
MVA
kA
busbar
1
busbar
2
busbar
3
busbar
4
LINE
DATA
6.600
0.400
0.400
0.400
150.0
31.0
31.0
31.0
13.122
44.745
44.745
44.745
STUDY
PARAMETERS
Load
Power
Multiplier
Load
Reactive
Multiplier
Convergence
Tolerance
Convergence
Control
Maximum
Iterations
Overload
Flag
Level
Automatic
Tap
Changers
-1.000000
=1.000000
=0.000005
=Method
2
25
=100.0%
Of
Rating
OFF
Single
Phase
Fault
MVA
lilt
Transf..Shift
Nominal
Bus
kA
Angle
(deg.)
Freq.
(Hz)
17.495
0.0
50.0NOT
IN
USE
64.952
0.0
50.0
64.952
0.0
50.0
64.952
0.0
50.0
200.0
45.0
45.0
45.0
First
Second
Line
No.Of
Line
Library
Busbar
Busbar
identifier
Ccts
Length
Key
Rating
Positive
Sequence
Zero
Sequence
(kA)
R(pu)
X(pu))
B(pu)
R(pu)
X(pu)
B(pu)
0.01000
0.01000
0.00000
Equivalent
Pi
Model
busbar
2busbar
41
21.00
11
1.000
0.01000
0.01000
0.00000
53
Run
on
ij-dun-zuu'
Dy
supervisoi
iromuota
ssl,
up
un
j.j-
Network
Name
:prac_l
Data
State
Name
:17/4
CABLE
DATA
First
Busbar
Second
Busbar
Cable
Identifier
No.Of
Ccts
Cable
Library
Length
Key
Rating
Positive
Sequence
(kA)
R(pu)
X(pu)
B(pu)
Zero
R(pu)
Sequence
X(pu)
B(pu)
0.0042
Equivalent
Pi
Model
busbar
2busbar
3connector
11.00
cablel
2.500
0.3821
1.0990
0.0039
0.5382
1.0990
TRANSFORMER
DATA
System
Winding
Rating
Winding
Angle
Pos/Neg.
Sequence
Zero
Sequence
Neutral
Earth
Busbar
No.
(MVA)
Type
(deg.)
R(pu)
X(pu)
R{pu)
X(pu)
R(pu)
X(pu)
Voltage
Off-Norn
Ratio
Tap
(%)
DATA
for
Transformer
with
ID.
trans___a
busbar
11
150.000
D
busbar
22
150.000
YN
DATA
for
Transformer
with
ID.
trans_b
busbar
11
150.000
D
busbar
22
150.000
YN
INDUCTIONMACHINE
DATA
Busbar
Identifier
Motor
Identifier
busbar
1Ml
busbar
1M2
busbar
1M3
busbar
1M5
busbar
1M6
busbar
IM4
busbar
2M8
busbar
2M9
busbar
2motor
7
busbar
2motor
7
busbar
2M10
busbar
1M7
busbar
4
No.Of
Library
Units
Key
1motor
1
1motor
1
1motor
3
1motor
3
1motor
1
1motor
1
1motor7
1motor8
1motor10
1motor10
1motor9
1motor
1
1motor22
No.
of
units
30.00
0.0016
0.00
0.0016
No.
of
units
30.00
0.0016
0.00
0.0016
1using
library
key
trans^a
0.0158
0.0016
0.0158
0.0000
0.0158
0.0016
0.0158
0.0000
1using
library
key
trans_a
0.0158
0.0016
0.0158
0.0000
0.0158
0.0016
0.0158
0.0000
0..0000
1.0000
0..20
0.,0000
1.0000
0..20
OPEN
AT
SYSTEM
BUS
0..0000
1.0000
0..00
0,.0000
1.0000
0..20
OPEN
AT
SYSTEM
BUS
Motor
Ratings
MVA
MW
kV
Input
Slip
Stator
Magnet.
Standstill
Rotor
Running
MW.
(%)
Rfpu)
X(pu)
X(pu)
R(pu)
X(pu)
R(pu)
X(pu)
1..080
0.,200
6..600
0..200
0.,2778
0..0050
0.,1200
3..0000
0..0250
0..1000
0.,0150
0,.1500
NOT
IN
SERVICE
1..080
0.,200
6,,600
0..200100..0000
0,.0050
0.,1200
3,.0000
0,.0250
0,,1000
0,,0150
0..1500
NOT
IN
SERVICE
1..080
0..350
6.,600
0..350
0..4861
0,.0050
0.,1200
3..0000
0..0250
0.,1000
0..0150
0..1500
NOT
IN
SERVICE
1..080
0..350
6,.600
0,.350100..0000
0..0050
0,.1200
3,.0000
0,.0250
0,,1000
0.,0150
0..1500
NOT
IN
SERVICE
1..080
0,.200
6..600
0..200
0..2778
0,.0050
0..1200
3..0000
0..0250
0..1000
0..0150
0..1500
NOT
IN
SERVICE
1..080
0..200
6,.600
0,.200
0,.2778
0..0050
0,,1200
3,.0000
0..0250
0.,1000
0,.0150
0..1500
NOT
IN
SERVICE
0..405
0..001
0..415
0..001
0..0048
0..0054
0..1292
3..2292
0..0269
0.,1076
0,.0161
0..1615
0..405
0..002
0,.415
0,.002
0,.0100
0..0054
0,.1292
3..2292
0..0269
0,.1076
0,.0161
0..1615
0..405
0..005
0..415
o..005
0..0199
0..0054
0..1292
3..2292
0..0269
0..1076
0,.0161
0,.1615
0..405
0..005
0..415
0..005100..0000
0..0054
0,.1292
3..2292
0..0269
0,.1076
0,.0161
0..1615NOT
IN
SERVICE
0.405
0.020
0..415
0.020
0..0797
o..0054
0,.1292
3.2292
o..0269
0..1076
0..0161
0..1615
1.080
0.200
6..600
0.200100..0000
0.0050
0..1200
3.0000
0.0250
0..1000
0..0150
0,.1500NOT
IN
SERVICE
0..405
0.020
0.400
0.020
0.0741
0.0100
0,.1000
3.5000
0..0200
0,.1000
0..0150
0..1500
54
Run
on
i.j-Jun-<;uu/oy
supervisor
rrom
aata
sei
up
on
ij-juu-^uv/
uy
sufjcivisui
Network
Name
:prac_l
Data
State
Name
:17/4
INDUCTION
MACHINE
DATA
Busbar
Motor
Identifier
Identifier
No.Of
Units
Library
Key
Motor
Ratings
MVA
MW
kV
Input
MW
Slip
(%)
Stator
R(pu)
X(pu>
Magnet.
X(pu)
Standstill
R(pu)
X(pu)
Rotor
Running
R(pu)
X(pu)
busbar
41
motor22
0.405
0.020
0.400
0.020
0,0741
0.0100
0.1000
3.5000
0.0200
0.1000
0.0150
0.1500
SYNCHRONOUS
MACHINE
DATA
Busbar
Machine
Type
No.Of
Library
Identifier
identifier
Units
Key
busbar
1Gen
aSLACK
2Gen
a
busbar
1Gen
bSLACK
2Gen
a
busbar
3SLACK
1Gen
b
Generator
Ratings
MVA
BASE
MW
kV
Assigned
V(pu)
MW
Pos.
Sequence
Neg.
Sequence
Zero
Sequence
MVAR
R(pu)
X(pu)
R(pu)
X(pu)
R(pu)
X(pu)
5.000
NOT
IN
SERVICE
0.000
0.000
0.000
0.0125
0.1800
Neutral
earthing
0.0000
0.0000
5.000
NOT
IN
SERVICE
0.000
0.000
0.000
0.0125
0.1800
Neutral
earthing
0.0000
0.0000
31.000
0.800
0.400
1.000
0.000
0.000
0.0125
0.1800
55
0.0500
0.2400
0.0000
0.0000
0.0500
0.2400
0.0000
0.0000
0.0125
0.0550
0.0000
0.0000
0.0125
0.0550
0.0000
0.0000
0.0500
0.2400
NEUTRAL
O/C
^SL
oadf
low
mod
ule
°*"""
*~
fro
m"d
ata
set
up
on13
-Jun
-'2U
U7
bysu
perv
iso
r'o
n13
-Jun
-200
7by
Supe
rvi*
work
Name
:ff-
1a
Sta
teN
ame
:l'
/*^
on
==
2C
on
ver
gen
ce-
0.9
09
0E
-06
STUD
YEN
D-
Noof
ifc"
*;£0
from
0.99
4pu
atbu
sbar
4to
l.OO
Opu
atbu
sbar
3V
olt
ag
eK
aii
ys
*•*•
VALUES
Busbai
rMerge
Type
BU
SBA
R
tsbar
ientifie
asbar1
iisbar
3usbar
2usbar
4
LINEVALUES
First
Busbar
SLACK
LOAD
LOAD
Second
Busbar
PU
Voltage
kV
ANG-DEG
BUSDISCONNECTED
1000
0.400
0.000
0*994
0.398
0.068
q',994
0.398
0.069
BUSBAR
TOTALS
TOTAL
BUS
LOAD
SYSTEM
LOSSES
Synch.
Machines
MW
MVAr
0.0
70
0.0
00
0.0
00
0.0
70
0.0
69
0.0
01
0.3
15
0.0
00
0.0
00
0.3
15
0.7
00
-0
.38
5
Ind
Motor
Load
MW
MVAr
0.0
00
0.0
29
0.0
40
0.0
69
0.0
00
0.4
77
0.2
23
0.7
00
Branch
No.Of
Rating
First
End
identifier
Ccts
kAMW
MVAr
Flow
busbar
2busbar
41_2
1.000
0.040
0.223
kA
0.328
CABLEVALUES
First
Busbar
bu
sbar
2
Second
Busbar
bu
sb
ar
3
Branch
No.Of
Rating
Identifier
Ccts
kA
co
nn
ecto
r1
2.5
00
First
End
Flow
MW
MVAr
kA
-0
.06
9-0
.70
01
.02
1
56
Shunt
MW
0.0
00
0.0
00
0.0
00
0.000
Second
MW
Loads
MVAr
0,000
0.000
0.000
0.000
Phase
Fault
kA
X/R
261.66
14.406
98.08
4.625
97.37
4.528
Ph
-E
Fault
kA
X/R
1.83-747.767
1.83-283.784
1.83-274.766
End
Flow
MVAr
kA
Loading
O/L
(%)
FLAG
-0.040
-0.223
0.328
32.8
Second
MW
0.0
70
End
Flow
MVAr
kA
0.3
15
0.4
65
Loading
O/L
(%)
FLAG
40
.8
Run
on
ij-jun-i;uu/
by
supervisor
trom
aata
set
upon
u-Jun-zim/by
supervisor
Network
Name
:prac_l
Data
State
Name
:17/4
SYNCHRONOUS
MACHINE
VALUES
Busbar
Machine
No,Of
Terminal
Voltage
Power
Output
Current
O/L
Identifier
Identifier
Units
kV
MW
MVAr
kA
Flag
busbar
1Gen
a2
MACHINE
DISCONNECTED
busbar
1Gen
b2
MACHINE
DISCONNECTED
busbar
31
0.400
0.070
0.315
0.465
58
APPENDIX F
FAULT STUDY AND ANALYSIS
59
ERACS
Fault
module
By
ERA
Technology
Ltd.
ERACS
Version:
3.5.U.
Fault
Version:
3.b.U
Page
No.
IRun
on
13-Jun-2007
by
Supervisor
from
data
set
up
on
13-Jun-2007
by
Supervisor
Network
Name
:prac__l
Data
State
Name
:17/4
Study
Name
:sc
FAULT
IMPEDANCE
VALUES
Rph(pu)
Rph(ohm)
Xph(pu)
Xph(ohm)
Rgnd(pu)
Rgnd(ohm)
Xgnd(pu)
Xgnd(ohm)
0.000
0.000
0.000
0.000
0.000
0.000
0.000
0.000
REACTANCE
SELECTION:
Synchronous
machine
Positive
Sequence
reactance
is
employed
and
asynchronous
machines
are
included
in
the
systemmodel.
60
Run
on
ij-jun-zuu/
ay
supervisor
rrom
aata
set
up
on
u-jun-zuu
/Dy
supervisor
Network
Name
:prac_l
Data
State
Name
:17/4
Study
Name
:Three
phase
fault
at
busbar
busbar
1
FAULT
CURRENTS
Bus
ID
busbar
1
Ip(kA)
7.522
18.384
-86.9
In(kA)
0.000
0.000
0.0
Iz(kA)
0.000
0.000
0.0
Ir(kA)
7.522
18.384
-86.9
Iy(kA)
7.522
18.383
153.1
Ib(kA)
7.522
18.386
33.1
Ires(kA)
0.000
0.000
0.0
BUSBAR
VOLTAGES
Bus
ID
Vp(kV)
Vn{kV)
Vz(kV)
Vr(kV)
Vy(kV)
Vb(kV)
Vres(kV)
busbar
10.000
0.0
0.000
0.0
0.000
0.0
0.000
0.0
0.000
0.0
0.000
0.0
0.000
0.0
MVA
55.986
Magnitude
Angle
(deg)
Magnitude
X/R
Ratio
Angle
(deg)
TRANSFORMER
CURRENTS
Tx
ID
BUS
NO
Wnd
No
Ip(kA)
In(kA)
Iz(kA)
Ir(kA)
iy(kA)
Ib
(k
A)
Ires(k
A)
trans_a
trans
b
busbar
1
busbar
1
INDUCTION
MACHINE
CURRENTS
IM
ID
Bus
ID
Ml
busbar
1
M2
M3
busbar
1
busbar
1
0.4
52
91
.7
0.4
52
91
.7
Ip(kA)
0.405
-91.1
0.0
00
0.0
0.0
00
0.0
In(kA)
0.000
0.0
Machine
disconnected.
0.4
03
-9
2.9
0.0
00
0.0
0.0
00
0.0
0.0
00
0.0
Iz(kA!
0.0
00
0.0
0.0
00
0.0
0.4
52
91
.7
0.4
52
91
.7
Ir(kA)
0.4
05
-9
1.1
0.4
03
-9
2.9 61
0.4
52
-2
8.3
0.4
52
-2
8.3
Iy(kA)
0.4
05
14
8.9
0.4
03
14
7.1
0.4
52
-1
48
.3
0.4
52
-1
48
.3
0.0
00
0.0
0.0
00
0.0
Magnitude
Angle
(deg)
Magnitude
Angle
(deg)
Ib(k
A)
Ires(k
A)
0.4
05
28
.9
0.4
03
27
.1
0.0
00
0.0
0.0
00
0.0
Magnitude
Angle
(deg)
Magnitude
Angle
(deg)
Run
on
u-jun-^uuv
by
supervisor
trom
aata
set
up
on
u-Jun-iiUU/by
supervisor
Network
Name
:prac_l
Data
State
Name
:17/4
Study
Name
:Three
phase
fault
at
busbar
busbar
1
Ip(kA)
In(kA)
Machine
disconnected.
Iz(kA)
ir(kA)
iy(kA)
Ib(kA)
Ires(kA)
INDUCTION
MACHINE
CURRENTS
IM
ID
Bus
ID
M5
busbar
1
M6
busbar
10.405
0.000
0.000
0.405
0.405
0.405
0.000
Magnitude
-91.1
0.0
0.0
-91.1
148.9
28.9
0.0
Angle
(deg
busbar
10.405
0.000
0,000
0.405
0.405
0.405
0.000
Magnitude
-91.1
0.0
0.0
-91.1
148.9
28.9
0.0
Angle
(deg
busbar
1Machine
disconnected.
M4
M7
SYNCHRONOUS
MACHINE
CURRENTS
SM
ID
Gen
a
Bus
ID
Ip(kA)
In(kA)
Iz(kA)
Ir(kA)
Iy(kA)
Ib(kA)
Ires(kA)
busbar
12.505
0.000
0.000
2.505
2.505
2.505
0.000
Magnitude
-85.1
O.O
0.0
-85.1
154.9
34.9
0.0
Angle
(deg)
busbar
12.505
0,000
0.000
2.505
2.505
2.505
0.000
Magnitude
-85.1
0.0
0.0
-85.1
154.9
34.9
0.0
Angle
(deg)
Gen
b
NEUTRAL
EARTHING
VOLTAGES
SCURRENTS
Parent
ID
Synchronous
Machine
with
ID
Gen
a
Synchronous
Machine
with
ID
Gen
b
Vre
s(k
V)
0.0
00
0.0
0.0
00
0.0
Ires(k
A)
0.0
00
0.0
0.0
00
0.0
Magnitude
Angle
(deg)
Magnitude
Angle
(deg)
62
Run
on
13-Jun-2007
by
Supervisor
from
data
set
up
on
l3-Jun-2007
by
supervisor
Network
Name
Data
State
Name
Study
Name
prac_l
17/4
Three
phase
fault
at
busbar
busbar
2
FAULT
CURRENTS
Bus
ID
Ip(kA)
In(kA)
Iz(kA)
Ir(kA)
Iy(kA)
Ib(kA)
Ires(kA)
MVA
busbar
2122.728
18.253
-86.9
0.000
0.000
0.0
0.000
0.000
Q.O
122.728
18.253
-86.9
122.728
18.251
153.1
122.728
18.254
33.1
0.000
0.000
0.0
85.029
Magnitude
X/R
Ratio
Angle
(deg)
BUSBAR
VOLTAGES
Bus
ID
Vp(kV)
Vn(kV)
Vz(kV)
Vr(kV)
Vy(kV)
Vb(kV)
Vres(kV)
busbar
20.000
0.0
0.000
0.0
0.000
0.0
0.000
0.0
0.000
0.0
0.000
0.0
0.000
0.0
LINE
CURRENTS
Line
ID
Bus
ID
12
busbar
2
CABLE
CURRENTS
Ip(kA)
5.596
92.5
In(kA)
0.000
0.0
Iz(kA)
0.000
0.0
ir(kA)
5.596
92.5
ly(kA)
5.596
-27.5
Ib(kA)
5.596
-147.5
Magnitude
Angle
(deg)
Ires(kA)
0.000
0.0
Cable
ID
Bus
ID
lp(kA)
In(kA)
Iz(kA)
Ir(kA)
Iy(kA)
Ib(kA)
Ires(kA)
connector
1busbar
20.000
0.0
0.000
0.0
0.000
0.0
0.000
0.0
0.000
0.0
0.000
0.0
0.000
0.0
63
Magnitude
Angle
(deg)
Magnitude
Angle
(deg)
Run
on
is-Jun-uuuv
by
supervisor
trom
data
set
up
on
u-Jun-zuu/
Dy
supervisor
Network
Name
:prac_l
Data
State
Name
:17/4
Study
Name
:Three
phase
fault
at
busbar
busbar
2
TRANSFORMER
CURRENTS
Tx
ID
Bus
No
Wnd
No
Ip(JcA)
trans__a
trans
b
busbar
2
busbar
2
INDUCTION
MACHINE
CURRENTS
IM
ID
Bus
ID
53.905
93.3
53.905
93.3
Ip(kA)
In(kA)
0.000
0.0
0.000
0.0
In(kA)
Iz(kA)
0.000
0.0
0.000
0.0
Iz(kA)
Ir(kA)
53.905
93.3
53.905
93.3
Ir(kA)
Iy(kA)
53.905
-26.7
53.905
-26.7
Iy(kA)
Ib(kA)
53.905
-146.7
53.905
-146.7
Ires(kA)
0.000
0.0
0.000
0.0
Ib(kA)
Ires(kA)
Magnitude
Angle
(deg)
Magnitude
Angle
(deg)
M8
busbar
22.333
-88.6
0.000
0.0
0.000
0.0
2.333
-88.6
2.333
151.4
2.333
31.4
0.000
0.0
Magnitude
Angle
(deg)
M9
busbar
22.333
-88.7
0.000
0.0
0.000
0.0
2.333
-88.7
2.333
151.3
2.333
31.3
0.000
O.O
Magnitude
Angle
(deg)
motor_7
busbar
22.333
-88.8
0.000
0.0
0.000
0.0
2.333
-88.8
2.333
151.2
2.333
31.2
0.000
0.0
Magnitude
Angle
(deg)
motor
7busbar
2Machine
disconnected.
M10
busbar
22.332
-89.3
0.000
0.0
0.000
0.0
2.332
-89.3
2.332
150.7
2.332
30.7
0.000
0.0
Magnitude
Angle
(deg)
NEUTRAL
EARTHING
VOLTAGES
&CURRENTS
Parent
ID
Winding
2of
Transformer
with
ID
trans___a
Winding
2of
Transformer
with
ID
trans_b
Vres(kv)
0.000
0.0
0.000
0.0
ires(kA)
0.000
0.0
0.000
0.0
Magnitude
Angle
(deg)
Magnitude
Angle
(deg)
64
Run
on
u-jun-^uu/
Dy
supervisor
rrom
aata
set
up
on
u-jun-iiuuv
by
supervisor
Network
Name
Data
State
Name
Study
Name
prac_l
17/4
Three
phase
fault
at
busbar
busbar
3
FAULT
CURRENTS
Bus
ID
Ip(kA)
In(kA)
Iz(kA)
Ir(kA)
Iy(fcA)
Ib(kA)
Ires(kA)
MVA
busbar
3247.984
14.400
-85.8
0.000
0,000
0.0
0.000
0.000
0.0
247.984
14.400
-85.8
247.984
14.399
154.2
247.984
14.401
34.2
0.000
0.000
0.0
171.808
BUSBAR
VOLTAGES
BUS
ID
Vp(kV)
Vn(kV)
Vz(kV)
Vr(kV)
Vy(kV)
Vb(kV)
Vres(kV)
busbar
30.000
0.0
0.000
0.0
0.000
0.0
0.000
0.0
0.000
0.0
0.000
0.0
0.000
0.0
Magnitude
Angle
(deg)
CABLE
CURRENTS
Cable
ID
Bus
ID
Ip(kA)
In(kA)
Iz(kA)
Ir(kA)
Iy<kA)
lb(kA)
Ires(kA)
connector
1On
busbar
busbar
3is
disconnected.
SYNCHRONOUS
MACHINE
CURRENTS
SM
ID
Bus
ID
ip(kA)
In(kA)
Iz(kA)
ir(kA)
Iy(kA)
Ib(kA)
Ires(kA)
busbar
3247.984
-85.8
0.000
0.0
0.000
0.0
247.984
-85,8
247.984
154.2
247.984
34.2
0.000
0.0
65
Magnitude
X/R
Ratio
Angle
(deg)
Magnitude
Angle
(deg)
Run
on
xj-jun-^uu/
Dy
supervisor
rrom
aata
set
up
on
u-dun-zuu
/oy
supervisor
Network
Name
:prac_l
Data
State
Name
:17/4
Study
Name
:Three
phase
fault
at
busbar
busbar
4
FAULT
CURRENTS
BUS
ID
Ip(kA)
In(kA)
Iz(kA)
Ir(kA)
Iy(kA)
Ib(kA)
Ires(kA)
MVA
busbar
4121.738
16.132
-86.5
0.000
0.000
0.0
0.000
0.000
0.0
121.738
16.132
-86.5
121.738
16.131
153.5
121.738
16.134
33.5
0.000
0.000
0.0
84.342
BUSBAR
VOLTAGES
Bus
ID
busbar
4
Vp(kV)
0.000
0.0
LINE
CURRENTS
Line
ID
Bus
ID
12
busbar
4
INDUCTION
MACHINE
CURRENTS
IM
ID
Bus
ID
busbar
4
busbar
4
Vn(kV)
0.000
0.0
Ip(kA)
116.141
93.6
Ip(kA)
2.799
-87.5
2.799
-87.5
Vz(kV)
0.000
0.0
In(kA)
0.000
0.0
In(kA)
0.000
0.0
0.000
0.0
Vr(kV)
0.000
0.0
lz(kA)
0.000
0.0
Iz(kA)
0.000
0.0
0.000
0.0
Vy(kV)
0.000
0.0
Ir(kA)
116.141
93.6
Ir(kA)
2.799
-87.5
2.799
-87.5 66
Vb(kV)
0.000
0.0
Iy(kA)
116.141
-26.4
Iy(kA)
2.799
152.5
2.799
152.5
Vres(kV)
0.000
0.0
Ib(kA)
116.141
-146.4
Ib(kA)
2.799
32.5
2.799
32.5
Magnitude
Angle
(deg)
Ires(kA)
0.000
0.0
Ires(kA)
0.000
0.0
0.000
0.0
Magnitude
X/R
Ratio
Angle
(deg)
Magnitude
Angle
(deg)
Magnitude
Angle
(deg)
Magnitude
Angle
(deg)