Submitted Report

download Submitted Report

of 51

Transcript of Submitted Report

  • 8/3/2019 Submitted Report

    1/51

    A.Company ProfileName of the company : Jaypee Rewa Plant (JRP)

    Jaiprakash Associates Limited

    Cement Division.

    Establishment Year : 1986

    Chairman : Mr. Manoj Gaur

    No of Employees : 3330

    Products

    Production Capacity : 3.3 MTPA

    Motto : Work for Quality, Safety,Health

    & Environment

    Product Range (Cement)

    Type - Grade Brand Name

    OPC-53 SUPER PLUS

    OPC-43 TIGER

    OPC-33 BUNIYAD

    OPC - IRS T-

    40/53S

    BULAND

    PPC BUNIYAD

    PPC BULAND

    PPC

  • 8/3/2019 Submitted Report

    2/51

    B.Brief HistoryYear 1979:

    Jaiprakash Associates Private Ltd. (JAPL) formed. Ultra Rasayan Udyog Ltd. was formed for setting up

    Malathion Technical plant in Sikandrabad (U.P.),

    which was changed to Jaiprakash Enterprises Ltd.

    Year1980:

    Hotel Siddharth was set up.Year1982:

    Hotel Vasant Continental was set up.Year1986:

    Commissioning of 1st unit of 1 MTPA Jaypee RewaPlant.

    Formation of Jaiprakash Industries Ltd. (JIL) byamalgamating JAPL into Jaypee Rewa Cement Plant.

    Year1991:

    Commissioning of 2nd unit of 1.5 MTPA Jaypee RewaPlant (JRP) in District Rewa (M.P).

    Year1992:

    Formation of JaiprakashHydro Power Ltd (JHPL).

  • 8/3/2019 Submitted Report

    3/51

    Year1995:

    Formation Jaiprakash Power Ventures Ltd (JPVL). Hotel Jaypee Residency Manor set up.

    Year1996:

    Commissioning of 1.7 MTPA Jaypee Bela Plant (JBP) inDistrict Rewa, M.P.

    Year1999:

    Jaypee Palace Hotel, Agra set up.Year2000:

    Acquisition of land for Jaypee Greens Ltd.Year 2001:

    Commissioning of .6 MTPA Jaypee Blending Units atAllahabad district in U.P. The first of its kind in the

    country.

    Jaypee Institute of Information Technology (DeemedUniversity Since November 1, 2004) at Noida, U.P.

    Year2002:

    Commissioning of 1.0 MTPA grinding unit in districtAmbedkar Nagar in U.P.

    Jaypee University of Information Technology (StateUniversity), Waknaghat was set up.

  • 8/3/2019 Submitted Report

    4/51

    Year2003:

    Commissioning of 25 MW captive Thermal PowerPlant-1 at JRP.

    Formation of Jaiprakash Associates Ltd (JAL) formedby merging JIL with Jaypee cement Ltd.

    Year2004:

    Commissioning of 25MW captive Thermal PowerPlant-2 at JRP.

    Commencement of Work for setting up 3MnTPACement Plant at Baga & Baghri at District Solan in H.P.

    and 1.5 MTPA.

    Year2005:

    Successful completion of up-gradation scheme,enhancing the total capacity of Rewa Operation to

    7.0 MTPA.

    Shares of JHPL Listed on BSE/NSE. First hydro powercompany to be listed in the country.

    Year2006:

    Setting up of Madhya Pradesh Jaypee MineralsCorporation Ltd. (MPJMCL).

    Commissioning of 38.5MW captive Thermal PowerPlant-3 at Jaypee Rewa plant.

    Railway siding operational at Jaypee Bela plant.

    Commencement of work for setting up a new greenfield 1.5 MTPA cement plant in district Sidhi, M.P.

    Acquisition of cement plants & assets of U.P. StateCement Corporation Limited (in Liquidation) of 2.5

    MTPA capacity.

  • 8/3/2019 Submitted Report

    5/51

    Acquisition of Gujarat Anjana Cement Limited forsetting up a Green field cement plant of 1.2 MTPA

    capacities Bhuj district in Kutch, Gujarat.

    Year2007:

    Signing of MOU with Gujarat Mineral DevelopmentCorporation (GMDC) for setting up a new Green Field

    Cement Plant of 1.2 MTPA capacity, in JV in Kutch

    district, Gujarat.

    Signing of MOU with Government of H.P, or setting upa new Green Field Cement Plant of 2.0 MTPA capacity

    at Chamba district in H.P.

  • 8/3/2019 Submitted Report

    6/51

    C.IntroductionJaypee Rewa cement is sub division of

    Jaiprakash Associates Ltd. Jaiprakash

    Associates is one of the biggest construction

    companies in India. Mr. Manoj Gaur is the

    Executive chairman of this company with its

    head office is in New Delhi.

    Jaypee Rewa cement is single largest

    production unit. Its annual production is

    about 3.3 Million Tons. There are two units installed for the production of

    clinker namely Unit-1 &Unit-2.

    Unit-1: Supplied by Krupp. Plysious (Germany). 1.5 million ton capacity was

    commission in December 1986.

    Unit-2: Supplied by F. L. Smidth (Denmark) 1.8 million ton capacity was

    commission in April 1991.

  • 8/3/2019 Submitted Report

    7/51

    D.Cement ManufacturingProcess

    I. MiningThe cement manufacturing process

    starts from the mining of limestone,which is the main raw material for

    making cement. Limestone is excavated

    from the quarries at about 6 m from

    ground level after drilling and blasting

    and than loaded on to the dumpers

    which transport the material and

    unload it into the hoppers of limestone crusher.

    II. Crushing Stacking & Reclaiming ofLimestone:

    The limestone crusher crushes the limestone to

    approximately 70 to 80mm size and discharge

    the material onto a Belt Conveyer which takes itto the Stacker via the Bulk Material Analyzer.

    The material is stacked in longitudinal

    stockpiles and than Limestone is extracted

    transversely from the stockpiles by the

    Reclaimers and conveyed to the Raw Mill

  • 8/3/2019 Submitted Report

    8/51

    hoppers for grinding of raw meal.

    III. Crushing Stacking & Reclaiming ofCoal:

    The process of making cement

    clinker requires heat. Coal is used as

    the fuel for providing heat. Raw coal

    is stored in the coal yard. Raw coal is

    dropped on a belt conveyer from a

    hopper and is taken to a crusher for

    being crushed. Crushed coal

    discharged is stored in the longitudinal stockpiles from where it is

    reclaimed by the Reclaimer and taken to the coal mill hopper for grinding it

    to fine coal.

    IV. Raw Meal Drying/Grinding &Homogenization:

    Reclaimed limestone along with some laterite

    stored in their respective hoppers is fed to the

    Raw Mill for fine grinding. The hot gases coming

    from the Cooler House are used in Raw Mill fordrying. Grounded Raw Meal is than transported

    to the Electrostatic Precipitator (ESP) /Bag

    house, where it is collected and then stored and homogenized in the

    concrete SILO. Raw meal extracted from the SILO is than fed to the top of

    the pre-heater for pyro-processing.

  • 8/3/2019 Submitted Report

    9/51

    V. ClinkerizationCement clinker is made by

    pyro-processing of Kiln feed

    in the pre-heater and the

    rotary Kiln. Fine coal and air

    is used as fuel to heat the

    Kiln and the pre-calciner

    located at the bottom of the

    5/6 stage pre-heater. Hot clinker discharged from the Kiln drops on the

    gate cooler and gets cooled. The clinker discharged by the Cooler House

    falls onto the pan conveyor and it is than transported to the clinker

    stockpiles/SILO. The clinker is than taken from the stockpiles/SILO to the

    Ball Mill Hoppers for cement grinding.

    VI. Cement Grinding & StorageClinker and Gypsum (for OPC) and also Pozzolana (for PPC) are extracted

    from their respected hoppers and fed to the cement mill. These ball mills

    ground the fed materials to a fine powder. The mill discharge is than fed to

    the elevator, which takes the material to the separator, which separates

    fine product and the coarse material. The latter is sent to the mill inlet

    again for regrinding and the fine product is stored in concrete SILO.

    VII. PackingCement extracted from SILO is than conveyed to the automatic electronic

    packers where it is packed in 50 Kg polythene bags and dispatched in

    trucks.

  • 8/3/2019 Submitted Report

    10/51

    SHUTDOWN OPERATIONS

    INKILN AND COOLER HOUSE

    (UNIT-2)

    I. Detailed Descriptiona. Rotary Kiln

    Kiln is cylindrical rotary equipment rotating on supporting rollers at about

    3.5 RPM and discharges on the completion of calcinations reactions. Firingis done from Kiln outlet with the help of burner pipe.

    i. Technical specification of Rotary Kiln:Unit-2

    Maker FLS

    Pre-calciner SLC

    Diameter 4.75 M

    Length 75 MCapacity 5500 TPH

    Rpm 3.8

    Burner pipe Duoflex

    Slope 8

    Fuel Used Coal

    Thrust roller Hydraulic

  • 8/3/2019 Submitted Report

    11/51

    Thermal Load 14.44

    Supporting Roller 6nos

    ii. Construction:a. Kiln inlet (consist seal, grease pump, lines, cylinders etc)b. Girth gear (Gear, pinion, spray system)c. Thrust roller (Hydraulic cylinder, oil line)d. Supporting roller & tyre (Consist of bearing, chair plate, bolts etc)e. Kiln outlet seal (S.S shims, crown shell, seal)f. Burner pipe(consist of air pipe, coal pipe, diesel pipe etc)

    Kiln inlet

    Kiln inlet is sealed by sealing arrangement. Greasing is done by

    pneumatic pump seal. It consists of 10 to 14 segments so that it can be

    mounted and disassembled from Kiln inside. A conical section forms an

    extension of the inlet ring. A brick retaining ring has been mounted at

    the end of conical section.

    Girth Gear

    Kiln is rotating by Gear pinion arrangement.

    Girth gear is mounted on Kiln with the help of

    spring plates.

  • 8/3/2019 Submitted Report

    12/51

    Specifications of Girth Gear are as follows:

    KILN GIRTH GEAR

    P.C.D. 7149 mm

    No. of Teeth 220

    Width of Teeth 640 mm

    Thrust Roller

    The function of thrust roller is to control

    axial moment of Kiln in both upward &

    downward directions.

    Supporting Rollers & Tyre

    Supporting rollers are for support of Kiln. They are in contact with tyre

    which is fitted in Kiln shell.

    Kiln Outlet

    There is a sealing arrangement at Kiln outlet.

    Burner Pipe

    It is for firing of fine coal into the

    Kiln. Air is controlled by damper

    and fine coal by solid flow meter.

    Duoflex type of burner is used inKiln Unit-2

  • 8/3/2019 Submitted Report

    13/51

    iii. MaintenanceRefractory Lining

    The high temperature inside the Kiln leads to severe

    thermal shocks which cause cracks in the brick lining as

    well as Castable. Also, during the half yearly maintenance as

    the Kiln is stopped, leads to high temperature changes

    which causes cracks in the brick lining. This may cause the

    molten liquid to reach the Kiln shell causing damage to it.

    Hence the Kiln stoppages are usually averted as much as

    possible. It may be noted that temperature of shell does not

    rise beyond 300 C

    The Castable is used wherever brick lining cannot be used

    in Kiln generally in sections which are not straight.

    Process of Replacing Brick Lining

    Check the refractorybrick lining during the

    maintenance time.

    If the brick lining iscracked than we replace

    the lining.

    The cost of brick lining isquite high so we use

    bricks according to the

    temperature they are

    supposed to sustain. Usually high alumina percentage bricks

    are placed near the Kiln Inlet where the temperature is

    highest and material flows in molten form.

  • 8/3/2019 Submitted Report

    14/51

    During lining of bricks a ceramic plate is placed in betweenthe two refractory bricks using adhesive. This is provided to

    avoid stresses in the brick during thermal expansion.

    A Ram is placed inside the Kiln which presses and supportsthe brick lining.

    The last brick to be placed is known as Key Brick which isplaced with 2 shims maximum in order to tighten the whole

    ring.

    When the entire lining is completed, the pneumaticallydriven brick lining machine is used in order to press the

    lining for final fit.

    The bricks which were used were DALMIA 625 and 425where first letter denotes the diameter and last two the

    thickness of insulation.

    For e.g.: 625 means the brick is for lining 6 m diameter Kilnand insulation thickness is 250 mm. Since the diameter of

    the Kiln is 4.75 m so these bricks are placed in the ratio of

    1:1.

    Castable is placed over the tip casting plate by weldingsmall sections

    over the tip

    casting plates and

    than filling

    Castable in it.

    After the Castable

    has solidified we

    cut the extruding

    parts. And remove

    the support plates.

  • 8/3/2019 Submitted Report

    15/51

    Tip Casting Plate

    The Tip Casting plate is placed

    at the tip of the Kiln outlet.

    These plates are those overwhich a ring of Castable lining

    is made. These plates protect

    the Kiln shell from the hot

    molten material when the

    Castable lining has worn off due to the continuous abrasive

    action of between molten material and tip.

    Process

    Tip Casting Plate is imported from outside and is placed just

    on the tip of the Kiln and screwed to the tip. Later this forms

    a base for the Castable.

    Chair Plate, Shims and Guide Blocks

    The live ring migration is

    equal to the relative motion

    between Kiln Shell and Tyre

    during a single revolution. It

    is an indicator of ovality of

    Kiln Shell. Chair plates are

    inserted between the Kiln

    Shell and Tyre and Shims areinserted in between to

    reduce the clearance. This

    stops the mitigation. It should be seen that mitigation of

    Tyre does not exceed beyond 20 mm as it would reduce

    Kiln lining life.

  • 8/3/2019 Submitted Report

    16/51

    Guide blocks are also provided to keep the live ring in its

    axial position on the Kiln shell. This implies the transfer of

    axial thrust on the Kiln shell between live ring and side

    guides. The relative moment of the face depends upon the

    ovality of Kiln shell. Therefore, there is a chance of high

    wear.

    The maximum clearance between the guide blocks and the

    tyre should not exceed 4 mm.

    At the time I was at the Plant a design change of guide block

    was taking place. Previously adjustable guide blocks used to

    be bolted over the Chair Plates. But over a period of time the

    nuts used to get jammed and were no longer adjustable

    hence the newer version of guide blocks were directly

    bolted over the Chair Plates.

    Crown Shell and Sealing Plate

    Due to high

    temperature andoxidation due to

    atmosphere

    surrounding it the

    crown shell and sealing

    plate may wear off and

    get damaged. So during

    shut down these

    damaged plates need to

    be checked and should be replaced if damage to them is

    more than a limit.

    The function of Crown shell is that it acts a nozzle for the air

    blowing from side cooling the lip of the Kiln.

  • 8/3/2019 Submitted Report

    17/51

    Also Sealing plate does not allow the hot gases from the Kiln

    to escape thus trapping energy.

    Rollers

    Rollers are also

    checked because

    they sustain heavy

    loads hence even a

    small particle will

    lead to great loss

    and wear the

    surface. These

    rollers are not

    replaced rather grinded so as to make them polished and

    workable.

  • 8/3/2019 Submitted Report

    18/51

    b.Cooler HouseIt is a vital part of Kiln System and a decisive influence on plant performance.

    It is for the cooling of clinker (less than 100 degree), as produced in Kiln.

    i. Technical Specification of Grate cooler

    ii. Main Functions of Cooler HouseClinker cooler has two main functions to perform. These are as follows:

    1. To cool the hot clinker quickly (from 1400to normally 100-200 degrees).2. To provide necessary hot air byrecuperating as much heat as possible from

    hot clinker by heating up air use for

    combustion of coal in pre-calciner and Kiln.

    After introduction of red hot clinker into

    the cooler, it falls over IKN plates. These

    are fixed grate plates and hence to move

    the clinker an air blaster is placed at the

    start of the Cooler House. After this the

    clinker moves to mechanically driven

    gates. These grates are such that one row of grates is fixed and one row of

    Type Folax

    Make FLS(Germany)

    Capacity 5500 TPD

    Size 37.8m length*5.1m width

    No. of gates 4

    No. of cooling Air fan 11

  • 8/3/2019 Submitted Report

    19/51

    grates is reciprocating with the help of motor. These reciprocating grates

    ate installed over a beam which moves over the rollers. The grates are

    having holes from which pressurized air flows and cools the clinker

    quickly.

    Clinker cools down gradually as it moves, due to the air blown by the

    centrifugal air pumps which is taken from the atmosphere. Air flowing

    from below through the cooling grate plates helps in cooling the clinker

    quickly

    Clinker escaping out of the cooler is fed to a hammer crusher, since lumpy

    material requires crushing. Crushed material is transported to clinker silo

    through deep bucket conveyor. Temperature of clinker escaping out of

    cooler is about 208oC.

    iii. Grate Cooler operationThe grate cooler operates with a cross current principle in which the

    clinker moves horizontally while cooling air blow in from below through

    the grate and clinker layer.

  • 8/3/2019 Submitted Report

    20/51

    As the hot clinker falls from Kiln, it forms clinker bed on the grate plates

    and is than transported through the cooler over alternatively fixed and

    reciprocating grates. At the inlet of Cooler House, clinker is quenched and

    spread evenly across the cooler width by the cooling air. The grate is

    fabricated in order to obtain a thick clinker layer and a uniform

    distribution of air through the clinker bed in the interest of heat recovery.

    During the clinker transportation

    from the cooler, a part of dust and

    small size clinkers fall off from the

    grates and get collected into

    hoppers under the grates. These

    hoppers have dust bin valves attheir bottom which opens only

    when a certain weight has been

    reached. The dust is released in the

    same DBN conveyors which carry

    the clinkers. The drag chain and

    rotary air lock system feed these

    clinkers and dust to clinker

    transport system. A dust collecting ESP is also installed known as cooler

    ESP. Exhaust gases from collection is fed to the ESP for dust collection.

    iv. ConstructionCooler parts are as follows:

    IKN Grate (fixed) - IKN kids, Fans

    Cooler I-IV Grate - S.S Grate plates, S.S Bolts

    Cooler Fans - Fan, Belts, Pulley, Motors

    Hammer Crusher: - Hammers, Pans, Rollers

  • 8/3/2019 Submitted Report

    21/51

    IKN Grate

    It is a stationary grate plate. Previously, there

    used to be similar S. S Plates in place of IKN

    plate but a change was made by the productiondepartment. They are not only having a

    guaranteed 1 year life but also have increased

    the production of Unit-2.

    IKN-KIDS

    There are 6 to 8 stationary and stepped enclosed air beams. These air

    beams are aerated by individual ducts. Refractory side dams are used to

    collect and aerate segregated clinker from discharge. Air blasters are

    used to avoid snowman formation.

    S.S Grate Plates

    These plates are of old design. It

    has holes over it with air blowing

    from below. Due to air blowing

    with heavily from below causes

    widening of air holes which causes

    clinker to pass from it to lower

    chamber where rollers

    reciprocating the plates are

    placed.

  • 8/3/2019 Submitted Report

    22/51

    Fans

    For Cooling purposes high efficiency fans are placed below over the

    ground which suck air and send it for cooling

    Cooler Fan

    Maker REITZ

    Fan Capacity- In/Out 46190m3/hr,

    45360 m3/hr

    Pressure 4.7 KPa

    RPM 1480

    Hammer

    At discharge end of cooler hammer crusher is provided consisting of a

    rotor with shaft. Hammers are mounted on each row. Hammers are

    casted out of high chrome or manganese steel. Clinker is crushed to a

    size of 15-25mm by Hammer Crusher.

    v. MaintenanceShutdown Activities

    All Cooler Grate Plates, Side Blocks should be checkedIf we find that the Grate Plates have worn off too much by

    abrasion action of clinker or high velocity air gushing from below

    than it is replaced. During my visit this operation was going in the

    Cooler House. The old Grate Plates had their holes widened due

    the high velocity air and also the thickness of those plates was

    reduced due to the Clinker abrasive action. The replaceable lip is

    also checked. A lip is provided in order to hold the side grate

  • 8/3/2019 Submitted Report

    23/51

    plates. These plates in a row are welded to each other and any gap

    bigger than 3 to 5 mm is filled between the Grate Plates.

    All compartment internals as pull rod, single and twin supporting rollersand grease lines should be checked.

    All Grate connecting rod and non-drives must be checked Dust valve hopper leakage should be checked for holes etc which needs to

    be patched and under Grate compartment jail needs to repaired/replaced

    Just below the Grate plates there is a net type arrangement which

    is used to allow the dust to fall into hopper connected to dust

    valves. This net sometimes gets clogged by large clinkers which

    need to be removed. Also sometimes they may create a hole in the

    hopper causing leakage.

    The net over the leaking hopper

    is cut in this and the hopper is

    thoroughly checked for holes and

    repaired.

    Hammer crusher hammers, impactplates, lining needs to be repaired/

    replaced

    Hammers get worn off due to

    continuously striking the clinker and

    breaking it to smaller pieces. The

    hammer are either replaced or used

    again by reversing them.

    The impact plate just below the crusheralso gets worn off by continuously

    striking clinker over it. There might be

    holes created in them. The size of the

    crushed piece can also be set by a screw

    provided for changing inclination of

  • 8/3/2019 Submitted Report

    24/51

    impact plate.

    Also hard basing is done at the end of the Cooler House so as to

    protect it from continuous abrasion taking from the moving

    clinker. The welding alloy LH 745S is used for this purpose itprovides hard surface at high temperature.

    Pan conveyor or damaged track wheels should be checked and changed. Under Grate beams etc. should be checked All Cooler Fan Belts, bearing, Impellers should be checked.

  • 8/3/2019 Submitted Report

    25/51

    A.Company ProfileName of the company : Bokaro Steel Plant (SAIL)

    Establishment Year : 1972

    Chairman : Mr. S.P Verma

    No of Employees : 25000

    Products

    Production Capacity : 4.3 MTPA Steel

    Products

    CokeAmmonium Sulphate

    Naphthalene

    Crude Anthracene

    Road Tar

    Crude Benzol

    Nitration Grade Benzene and

    Toluene

    Solvent Naphtha

    Light Pyridine

    Ferrous Sulphate

    Pig Iron

    Steel

  • 8/3/2019 Submitted Report

    26/51

    B.IntroductionBokaro Steel Plant, the biggest steel complex in India, was designed with

    the collaboration of former USSR. It is one of the main units of Public

    Sector Organization, Steel Authority of India (SAIL). Bokaro Steel City is

    situated on the bank of river Damodar in the North, river Garga in the

    East, Chas-Ramgarh road in the south and Muri -Chandrapura line in the

    west. It is about 50 kms from Dhanbad, which is on the main Delhi-

    Howrah Railway line. It has been long acknowledged that Bokaro would

    be one of the best possible locations for a large sized Iron & Steel Plant.

    Its present capacity is 4.3 MT and is rapidly modernizing itself to double

    its production. At present it is working with 5 Blast Furnaces and 8 Coke

    Oven batteries.

    Units of Bokaro Steel Plant

    1. Raw Material & Handling Plant (RMHP)2. Coke Ovens3. By Product Plant4. Sintering Plant5. Blast Furnace6. Steel Melting Shop7. Slabbing Mill8. Hot Strip Mill9. Hot Rolled Coil Finishing

    10. Cold Rolling Mill11. Roll Grinding and Bearing Shop12. Slag Granulation Plant13. Scrap & Salvage Department14. Refractory15. Research & Control Lab16. Inspection & Quality Control17. Industrial Engineering Department18. Water Supply19. Oxygen Plant20. Acetylene Plant

  • 8/3/2019 Submitted Report

    27/51

    21. Protective Gas Plant22. Machine Shop23. Forge Shop24. Structural Shop25.

    Steel Foundry26. Pattern Shop

    27. Ingot Mould Foundry28. Iron & Copper Foundry29. Thermal Power Plant30. Production Planning & Control

  • 8/3/2019 Submitted Report

    28/51

    C.Brief Description of UnitsVisited

    I. Raw Material & Handling PlantPurpose:

    1. To obtain homogeneity ofchemical and physicalcomposition of different raw

    materials received from

    different sources by method of

    blending.

    2. To keep an optimum stock ofmaterials in order to take care

    of irregularities of supplyarising due to strike in railways, mines etc.

    3. To release the wagons irrespective of consumption of material bycustomers. Thus, it avoids the demurrage charges.

    II. Coke OvensMetallurgical and Engineering Industries generally require coke as fuel.For the production of solid, porous, coke ovens of certain characteristic

    properties needed.

  • 8/3/2019 Submitted Report

    29/51

    In Bokaro Steel Plant, coke is chiefly used as fuel and for reduction of

    iron ore. The Coke Oven here is largest in India. It has got 8 batteries at

    present. Each battery contains 69 ovens.

    The process of making coke consists of the destructive distillation of

    coal in the absence of air. The coal is heated in closed chamber thereby

    driving out the volatile components present in the coal and leave

    behind the residue called coke. This phenomenon is called as the

    carbonization of coal. The carbonization of coal can be carried out at

    different temperature depending upon the type of coke we need.

    Different sections of Coke Oven plant are:

    1. Coal Tower2. Coal Handling Plant3. Coke Oven Battery4. Coke Sorting Plant

    III. By Product PlantThe high temperature carbonization of coal is basically adopted for production of

    metallurgical coke for use in Blast Furnace. The gas so produced is also used as fuel

    for making, shaping and treatment of steel after detailed process of cleaning to make

    it suitable for plant uses. In the process of cleaning some primary by-products,

    namely crude tar, benzol, ammonium sulphate etc are obtained. The primary and

    secondary chemicals that can be produced from these are of great importance for

    the growth of chemical industry.

    IV. Sintering PlantIt has been found that the production rate can be increased if the raw

    material is sent into the Blast Furnace in sintered form. Keeping this in

    view, BSL has the largest plant in India. There is provision for partially

  • 8/3/2019 Submitted Report

    30/51

    cooling the sinter on the machine itself. The ignition furnace is of double

    hearth and provision is there for adding extra amount of coke on the

    topmost layer of the charge. This plant not only helps in supplying a

    suitable charge for the Blast Furnace, but also eliminates other intricate

    problem.

    V. Blast FurnaceIt is the root plant of any steel producing complex. It is the unit where

    reduction of Iron Ore takes place. Hot metal is the final product from

    the Blast Furnace. There are five furnaces, each of capacity 2640 Tons/

    Day with a useful volume of 2000 cubic meter. The annual capacity of

    Blast Furnace is 4.82 MT.

    VI. Steel Melting ShopThe raw material for the Steel Melting

    Shop is Hot Metal coming from Blast

    Furnace. Here pure oxygen is blown

    into the hot metal. Impurities are

    oxidized and metal is transformed

    into steel.

    The Steel Melting Shop at Bokaro is

    largest in India with an annual

    production of almost 4.3 MT. There

    are 5 LD Converters in SMS 1 of 100 T each where as in SMS 2 these LD

    converters are of annual capacity of 300 T each. The steel produced is

    meant for plates and sheets.

  • 8/3/2019 Submitted Report

    31/51

    VII. Auxiliary ShopsThe main function of Auxiliary Shops of

    Bokaro Steel Plant is to extend help in a

    specified manner to the principal

    production line by producing spare parts

    to exact specifications. The objective of

    the set up of various Auxiliary Shops is

    the economization of the production

    complex and/or easy running of the production process. Some of these

    Shops are as follows:

    1. Ingot Mould Foundry2. Steel Foundry3. Forge Shop4. Machine Shop5. Structural Shop6. Pattern Shop

  • 8/3/2019 Submitted Report

    32/51

    D.Detailed DescriptionI. Raw material and handling plant

    This plant deals with the raw materials which are coming from various

    sources. It deals with around 10 MT of raw material per annum that

    amounts to about 400 to 500 wagons which has to be unloaded per day

    with each wagon carrying 60-70 tons per wagon. Mr. R.R. Kumar (AGM

    RMHP) described about the plant and gave an introduction about its

    operations and functions.

    a.Functions of RMHP1. Unloading of Raw Materials within a given time

    The material which comes within the plant by the well spread railway

    routes within the plant has to be unloaded as quickly as possible. For

    this purpose Tipplers are provided in the yard where each wagon is

    uncoupled and placed inside the Tippler and tilted to be emptied. The

    amount of wagons which have to be emptied is so much sometimes

    that they have to remain docked in the yard for days and because of

    this reason the company has to pay a heavy leverage of 10 15 Crores

    each year.

    2. Storage with proper blendingThis function is achieved by two types of machines Stacker and

    Reclaimer. To keep the plant running we need continuous supply of

    raw materials which is achieved by stacking them in 18 different

    beds. Since the quality of material may differ hence blending is

    needed. Stacker distributes the material in piles horizontally using

    boom conveyors. so when Reclaimer reclaims the material, it takes

  • 8/3/2019 Submitted Report

    33/51

    the entire pile at a time hence blending the different composition or

    material together.

    3. Supply to Internal CustomersThese are the following Internal Customers of RMHP

    1. Refractory Material Plant (RMP)2. Blast Furnace3. Sintering Plantb.Types of raw material

    c. ProcessThe Raw Material coming from different parts of the world reaches

    RMHP via rail routes to the captive yard inside RMHP. At this yard

    there are 4 Tipplers located whose function is to unload the raw

    materials. There are 3 cradle tipplers and 1 hydraulic tippler. Thecradle type tippler has a cradle located at top and on 1 side on which

    the BOX wagon rests while it is being toppled by an angle of 170

    where as the hydraulic tippler holds the wagon by hydraulic arms

    and topples it. The cradle type unloads a wagon at the rate of 20

    wagons/hr where as the hydraulic type unloads it at the rate of 12

    RAW MATERIAL SIZE SOURCE

    Iron Ore Lump

    (Hematite)

    10-40 mm Kiriburu,

    Meghanathburu

    Iron Ore Fines

    (Hematite)

  • 8/3/2019 Submitted Report

    34/51

    wagons /hr. But the cradle type Tippler may cause damage to the

    wagons which may increase railways cost of material handling and is

    quite noisy.

    There is a R & C sampling lab also known as Yard Lab nearby

    consisting of equipments such as jaw crusher, evaporator etc. This

    lab takes sample from each rake (59 wagons) of material arriving at

    the yard. They do the physical size test and classify the material as

    fines and lump. For chemical test the material is converted to a fine

    powder and sent to the R & C Lab where a spectrometer test is done

    in order to determine the composition of the raw material. This is

    done so as to maintain the quality of the raw material.

    Below each Tippler there are two hoppers located which empty the

    raw material over to oppositely moving conveyor belts which empty

    it in a chute moving over a conveyor which carries it to the junction

    house. The junction house than decides where the raw material has

    to be sent. There are numerous junction houses within the plant

    which keeps the track of material movement. Each junction house

    has 3 conveyors moving in each direction in which 2 are used and 1

    is kept in case of breakdown of one of them.

    The junction house sends the material for stacking in 18 beds

    (280m*27.5m*9m) with the help of double boom stackers. The raw

    material in beds is as follows:

    Bed 1 Sinter (It could be either purchased sinter in

    case of shortage or it could be for storage

    during breakdown)

    Bed 2 to 6 Iron Ore Fines

    Bed 7 to 10 Iron Ore Lump

    Bed 11 to 14 Flux for Sintering Plant

  • 8/3/2019 Submitted Report

    35/51

    Bed 15 to 17 Materials for RMP

    Bed18 Sinter, L.D, Slag, Corzite

    There are 2 stackers for Bed 15 to 18 and rest 4 stackers for Bed 1 to

    14. These stackers moves between the bed and could be moved from

    one position to other by placing it on a platform. These stackers

    could stack at the rate of 1200 Tons/Hr. Similarly there are 6 barrel

    type Reclaimers, 1 Bucket Wheel Reclaimer and 1 Shovel and

    Travelling Reclaimer which are used for reclaiming the raw material

    and sending it to the customers. The Barrel Type Reclaimer reclaims

    the material at the rate of 1000 Tons/ hr and Bucket Wheel

    Reclaimer reclaims at the rate of 500 Tons/ Hr.

    There are screening units for limestone and lump ore within the

    RMHP. The raw materials have to travel miles within the plant so

    there is possible breakage of materials hence they have to be

    screened before sending it to the internal customers since the size of

    material is very important during charging. The capacity of both

    screens is 500 Tons/Hr.

  • 8/3/2019 Submitted Report

    36/51

    II. Blast Furnace and Pig CastingMachine

    a.Raw materialMATERIAL SOURCE

    Iron Ore RMHP

    Coke Coke Oven

    Sinter Sintering Plant

    Limestone RMHP

    b.ProcessThe raw materials (Iron Ore, Coke, Sinter, Limestone etc.) are carried

    to the blast furnace by conveyor belts from their respective sources

    (RMHP, Coke Oven, Sintering Plant). The notable part during

    charging is the size of the charge. Hence the fines and the lumps of

    ores are separated in the RMHP itself. Further during material

    handling of raw materials there is fine generated at different levels

    so there are Vibrating Dust Separators at the start of the Blast

    Furnace from where fines are separated and sent to the sinter plant

    to be converted into Crude or Spongy Iron.

    The raw material is emptied into their respective hoppers until they

    reach Skip Pit where the raw material is weighed by weighbridge and

    is loaded in the Skip (13.5-14.5 m3). In a Shift maximum 45 charges

    are done with each charge having 20 skips. A same schedule is

    followed for each charge. There could be a positive or negativedifference of 500 Kg but the total raw material in each charge

    remains the same. The Skip moves over the rail in the skip bridge

    and empties the contents at the top of the Blast Furnace. The skip is

    operated by means of the skip wrench located in the wrench house.

  • 8/3/2019 Submitted Report

    37/51

    The hot blast is supplied from the stoves to the bustle pipe and is

    blown through the tuyers at the bottom of the Blast Furnace

    respectively located in the Cast House. The molten Iron and Slag flow

    through the iron runner and the Slag runner. These runners are

    made up of refractory powder (CaCO3, Al2O3, and SiO3) which needs

    to be rebuilt after every 2 months. A new L&T furnace has a Siphon

    Hall which sucks and separates Slag from the Iron thus there is no

    need of two different tap holes. Just beneath the Cast house, at the

    end of the runner there is a ladle wagon run by a locomotive which

    carries the molten Slag to a Slag yard where it is stored in pits and

    molten Iron to SMS. About 5% of this Pig Iron is sent to the Pig

    Casting Machine (PCM). At the end of each runner there is manually

    controlled swivel and rocker type runner which helps in pouring themolten material in ladles.

    The waste gases from the blast furnace are taken through uptakes

    and gas outlets to the dust catcher and further to the Gas Cleaning

    Plant (GCP). This cleaned gas is taken through gas pipes to the stoves

    for heating the blast pipes. There are checker plates in it which can

    me made of refractory material or graphite which gets heated up and

    the heats the cold blast sent by turbo-blasters which is sent to Bustle

    pipe. The gaseous products of combustion evolved in the hot blast

    stoves are exhausted through the chimney.

    c. Blast FurnaceThe foundation has to carry a very heavy load. It constitutes piles

    driven to the bed rock over which a huge reinforced concrete

    structure is constructed. The steel columns mounted on the concrete

    ring support the mantle ring. The Blast Furnace shell and the insidebrickwork is supported by mantle ring. The hearth bottom consisting

    of fireclay bricks and carbon blocks is laid out within concrete ring.

    The hearth is a cylindrical portion where the iron slag notch and

    tuyers are located. The bosh is the section which slopes outwards

    just above the hearth. The body is again a cylindrical portion above

  • 8/3/2019 Submitted Report

    38/51

    the bosh. The shaft which is in the form of a cone comprises the

    portion above the body. The throat cylindrical in form is at the top of

    the shaft.

    There are box type coolers within the refractory lining of the throatand shaft through which water circulates. The coolers are mounted

    to the shell of the Blast Furnace. The bottoms of the hearth and side

    walls are having plate type coolers.

    In 2000 m3 Blast Furnace, the Iron notch is situated at the height of

    1.1 m above hearth bottom. The slag notch is located at a height of

    1.8 m above iron notch. The tuyers through which the blast is blown

    are located at a height of 3.4m above the iron notch. Hot blast from

    the stoves passes through the Bustle pipe and tuyers (28 no.) into

    Blast Furnace. The Bustle pipe is located at a height of 5.5m above

    the iron notch. Another important feature of the recently

    modernized Blast Furnaces is Coal Dust Injection System (CDI).

    Previously the company was planning to replace the old coke based

    furnaces by gas based furnace due to poor availability of

    metallurgical coke and high cost of import of metallurgical coke from

    Australia and New-Zealand. But CDI reduced the present

    consumption of coke by 50%.

    The charging mechanism is Bell Less Type. These systems use

    multiple hoppers to contain each raw material, which is then

    discharged into the blast furnace through valves. These valves are

    more accurate at controlling how much of each constituent is added,

    as compared to the skip or conveyor system, thereby increasing the

    efficiency of the furnace. Some of these bell-less systems also

    implement a chute/bin in order to precisely control where the

    charge is placed. This valve system is easy to control and have

    replaced the old Bell Systems. In the Furnace, a stirrer is placed for

    equally distributing the raw material inside. A Bleeder Valve is

    placed at the top of the Blast Furnace to release pressure if it exceeds

    10000kg also a wench is provided to open it as and when required.

  • 8/3/2019 Submitted Report

    39/51

    In the cast house, the electric mud gun, tap drilling machine and the

    slag notch stopper is located. Tap Hole drilling machine is used for

    drilling out and opening the Hole (iron notch) for tapping the hot

    metal. The closing of the hole at the end of tapping is accomplished

    by means of clay gun. The opening and closing of slag notch is carried

    out by the slag notch stopper.

    Reduction by means of CO begins in the shaft and proceeds in steps

    from the highest Iron Oxide (Fe2O3) to the intermediate oxide

    (Fe3O4) and further down to the lowest oxide (FeO).The reaction

    between FeO and CO is

    FeO + CO = Fe + CO2

    This is called indirect reduction of the iron and takes place around

    600-1000 C. The chemical reaction between FeO and solid C is:

    FeO + C =Fe + CO

    This is called as the direct reduction of Iron and takes place around

    1100 C. Usually 50-60% of iron is reduced in the blast furnace by

    indirect reduction and 40-50% by direct reduction. This metallic iron

    formed initially is in the solid state since the melting point of pureiron is 1540 C

    The carburization of the spongy metallic iron takes place in the

    presence of CO and its melting point is lowered to around 1200 C.

    This carburized iron with about 2 % C melts and drops through the

    incandescent coke on the wall of the wall of the furnace hearth. At

    this time the iron absorbs more carbon up to 4% and settles at the

    hearth bottom as liquid pig iron.

    The reduction of Manganese, Silicon and Phosphorous from the

    charge takes place in the furnace simultaneously with the reduction

    and carburization of Iron. These elements also go over into the pig

    iron.

  • 8/3/2019 Submitted Report

    40/51

    The slag forms at the lower part of the shaft due to the oxides of Iron,

    Lime, Silica and Alumina. Liquid ferrous slag is formed at 1200 C and

    at a certain proportion of the above oxides. As it moves down into

    the hearth, it is heated and dissolves coke ash, fluxes and the

    remainder of ore gangue

    The production of each Blast Furnace is about 2600-3000Tons/Day.

    d. Pig Casting MachineAbout 5% of the production of Blast Furnace is sent to PCM because:

    1. Poor quality of Hot Metal2. SMS Breakdown3. Excess production by Blast Furnace & SMS not able to process

    the entire lot.

    Vital Equipments are:

    1. Wagon Shunting Wrench2. Ladle Shunting Wrench3. Ladle Tilting Wrench4. Belt5. 4 PCM6. 2 Lime Preparation Plant (LPP)

    The molten material comes to the PCM via Locomotive and than a

    ladle shunting wrench is used to pick the ladle and place the ladle for

    pouring where another wrench tilts the ladle over a conveyor belt

    with pig cast coated with lime. The lime sprayed over the Pig Cast

    does not allow the Pig Iron to stick to the cast. Water is sprayed over

    the Pig Cast to cool it as the conveyor is moving. Just beneath, whereporing takes place over the Pig Cast, there are plates below which

    dont allow the splashing to damage the machine elements below.

    The splashed metal is again taken for pouring by a skip. This

    prevents the loss of material.

  • 8/3/2019 Submitted Report

    41/51

    Limestone is used to prepare the Lime by mixing it with water. A

    large amount of heat is evolved during this process. This is pumped

    to the Lime sprayer which sprays it over the Pig Cast from below.

    This process is continuous with the conveying action. The Pig Cast is

    kept in the Cold Pig Yard and can be transported using Locomotives.

    There are 4 electromagnetic cranes having 10 Ton capacity each

    which are used for transferring Pig Iron to the Wagon.

    At the time of my visit the PCM was closed for maintenance.

  • 8/3/2019 Submitted Report

    42/51

    III. Machine ShopIn order to keep the plants

    continuously in working conditioneach plants have their own Area

    Repair Workshop which deals

    with the specific maintenance

    problem of that Plant.

    The Machine Shop is the Centre

    Repair Workshop where parts are

    given final touches. It has got 4

    Bays, LE (Light Engineering), ME

    (Medium Engineering), HE (Heavy

    Engineering) and Assembly Bay. Each Bay has got an overhead Crane

    with a capacity varying from 5 tons to 30 tons.

    LE Bay houses simple lathes and turret lathes with bed length varying

    from about 1m to 3.5m. It also has small size gear hobbing machine and

    milling machines.

    ME Bay houses medium size gear hobbing machine, Gear shapingmachine etc.

    HE Bay houses Asias largest vertical boring machine with stroke length

    of 4m. It also houses other large size vertical and horizontal boring

    machines.

    The Assembly Bay is the place where the parts are assembled and final

    product is ready for dispatch.

    Near the Machine there is another shop Structural Shop which houses

    an Annealing Furnace which is used for annealing large size ladles etc.

  • 8/3/2019 Submitted Report

    43/51

    IV. Forge ShopThe Forge Shop is a part of auxiliary shops of Bokaro Plant. It takes its

    raw material from Steel Foundry and from outside as per specificationand supplies it to the internal customer Production Planning Shop (PPS)

    which gets the further work done by Machine Shop

    a.Machines

    b. ProcessThe job is first heated in the furnace at about 1200-1250C just below

    the melting point of iron. Then it is picked up by crane incase the job

    exceeds human holding capacity and the pneumatic ally driven jaws of

    manipulator holds it. The manipulator jaws are pneumatically driven

    and not hydraulically because we require impulse action in the jaw

    arms of manipulator. When the hammer strikes the job, the job applies

    impulse force over the jaws which if hydraulically driven remain rigid

    hence the job breaks where as the pneumatically driven hammers are

    flexible to impulse force and leaves and holds the job immediately as

    Steam & Air Forging Hammer NO

    5T 1

    3T 1

    2T 1

    Pneumatic Forging Hammers

    1T 2

    4T 2

    25T 2

    2 Ton Forging Manipulator 2

    1 Ton Forging Manipulator 2

    Band Saw 1

    Bogie Hearth Furnace 3

    Box Type Furnace 2

  • 8/3/2019 Submitted Report

    44/51

    hammer strikes. The manipulator moves over the railroad by a

    mechanical drive and because we require accurate movements of arms

    of jaws we use hydraulically driven mechanism.

    During forging due to heavy forces over the job its crystal structuredistorts which is improved by heat treatment. Sometimes a job becomes

    soft on cooling in case of copper where as sometimes the job becomes

    hard in case of iron. Hence annealing and seasoning is done later for

    proper hardness of the job. The hardness is checked by the Inspector

    who pierces the job and checks the depth and measures it with the

    standard. Sometimes rough sizing of job is also required in that case the

    Forge Shop has a band saw which cuts the job in blanks. Sometimes the

    job is not required immediately but after a period of time. In that casethe job is sent to open entry where they are seasoned in open to

    improve the crystal structure of the part.

    There are two types of furnaces present in the shop

    1. Bogey TypeThis type of furnace is used for heating the job entirely at a

    single time. There is a bogey in which the job is placed and it

    goes inside the furnace.

    2. Box TypeThis type of furnace is used if the job is not to be heated

    entirely i.e. a part of it is kept outside and part of it is heated

    in the furnace.

    The fuel which is used in the furnace is Coke Oven Gas and Oxygen in

    the ratio of 1:4 and small amount of Hydrogen.

  • 8/3/2019 Submitted Report

    45/51

  • 8/3/2019 Submitted Report

    46/51

    A centre core is also prepared from High Silica Sand and additives. The

    mixture is prepared as follows:

    1. High Silica Sand : 100 Kg2.

    Part A (Binder) : 20 Kg

    3. Part B (Hardener) : 1 Kg4. Part C (Accelerator) : 4 Kg

    The mixture is thoroughly mixed and it is placed inside the Core Box but

    it is not rammed. It sets itself to the size of the pattern and thats why it

    is known as self setting sand. It is than sent to 3 ovens where it is heated

    with CO gas for 10 hours and than it is cooled for 1 hour inside the oven

    and 1 hr outside the oven. The stopper dryer is than used for drying the

    core by keeping it at 100-120 C for about 48 hours.

    The mold is prepared from the two parts the drake and the copes After

    these two things are prepared than the mold is prepared by placing the

    prepared core over the drake and keeping the cope over it. A sheet

    pattern is placed in between the core and case of cope. The molding

    sand is sand now filled in between the core and the case and rammed by

    sand slinger.

    Now as the mold is prepared, hot metal coming from the Blast Furnaceis poured in the mould through the runner and the gate present in the

    mould and it is kept for solidification for about 72 hours. Later the cope

    and drake is lifted using a cope lifting machine. A 5 % coal powder is

    added in the additives in molding sand which when comes in contact

    with the hot metal causes a gaseous layer to be formed between the

    casting and the sand. The graphite paint is also applied over the molding

    sand which prevents the sand fusion.

    To collapse the core, we strike the casting over iron pillars and thus the

    core collapses and breaks away.

    It must be noted that Silica Sand cannot be used for molding basic

    materials (Magnesium etc.) since Silica Sand is slightly acidic. For this

    purpose Olivine Sand is used which is generally found in Europe.

  • 8/3/2019 Submitted Report

    47/51

    After the Ingot Mould is prepared the milling operation is performed

    over the ends of the molds to remove the bulges or extra material

    attached.

    Finally, the Ingot Mold is placed over bottom plate. This bottom plateacts like a reinforced plate for holding the Ingot Mould and sent to Steel

    Melting Shop (SMS).

    The Ingot Moulds have a life of about average 25 castings.

    The Ingot Molds are of following specification:

    1. 17 Ton2. 20 Ton3. 25 Ton4. 28 Ton

    The first two are having ribs so that the Ingot formed gets ribs for

    holding it in Slabbing Mill.

    There are two other foundries namely:

    b.Iron and Copper FoundryIt is where non-ferrous alloys such as copper, brass, zinc and aluminum

    as well as Cast Iron casting are done.

    c. Steel Foundry :The foundry takes scrap steel from the SMS and use it for its casting

    purposes.

  • 8/3/2019 Submitted Report

    48/51

    VI. Steel Melting Shopsa.Steel Melting Shop (SMS)-1

    The Steel Melting Shop-1 consists of 4 L-D Convertors which is used for

    converting the Hot Metal from the Blast Furnace into Ingots.

    Process

    The process of converting hot metal into is a 5 step process. It is as

    follows:

    1. Hot Metal from the furnace is supplied by rail routes to SMS-1 throughladles to Mixer Bay Mixer which use CO gas as fuel. The furnaces are

    preheated to about 1300 C to prevent metal sticking to the furnaces.

    This heating is done in order to prevent the hot metal sticking to the

    ladle. This is done in order to homogenize the old hot metal and the new

    feed.

    2. The Hot Metal is sent to the LD Convertor via ladles (5 No each of 130Ton) which reduces the C % to .10 to .15 %. In this Limestone and

    Dolomite is added to remove the impurities in the form of slag. Oxygen

    blasting is done in order which causes the impurities to burn away by

    forming oxides and the proceeding chemical reaction causes the

    temperature rise.

    3. After conversion is completed, tapping is done. During tapping, Ferro-Mg and Silicon-Mg is added to remove oxygen which can cause blister to

    be formed in casting. If the carbon percentage has decreased too much

    than re-carburization is done using coke bags which is purged through

    Argon Gas.

    4. After tapping is done in the ladle, the ladle is lifted using cranes andtapping is done using sliding gate mechanism. The gate is opened which

    is fitted below the ladle and the mould is filled. Aluminum shots added

  • 8/3/2019 Submitted Report

    49/51

    to the casting if oxygen content is found to be high since it forms Al2O3

    which is lighter and floats over the surface.

    b.Steel Melting Shop (SMS)-2 & CCSThis is a new shop which is set up in conjunction with continuous

    casting shop. The process of conversion from hot metal to steel is same

    as in the case of SMS-1. The only difference is that here we have only 2

    converters instead of 5 in SMS-1 but of higher capacity of 300 Tons.

    In continuous casting shop we have a Steel Refining Unit in which the

    refining of steel is done. It is used for heating a ladle of 300 Tons at a

    time using an electric arc. The Aluminum bricks are added which are

    used for removing oxidized material from the crude steel also the

    refining of other elements such as Cr, Mn etc is done. The ladle is than

    kept over a car and sent to the continuous casting machine over which it

    lifted by crane and kept over high Cr manganese pipe which could

    sustain higher temperature. This fluid as flows starts solidifying and

    passes through the mold thereby taking the shape of slab. Now it is cut

    to the actual size by means of acetylene gas. The Slab is than send to Hot

    Strip Mill to produce steel rolls upto thickness of 2 mm which is later

    sent to the Cold Roll Mill for reducing its thickness to .15 mm.

  • 8/3/2019 Submitted Report

    50/51

    VII. Coke Oven and BPPThe main purpose of the coke oven is to provide blast furnace quality coke to

    the blast furnace. During the process of coke preparation a large amount ofvolatile material and dust escapes which is processed in the By-Product Plant

    which to give a range of products which are used in various fields like

    pharmacy, roads, railways etc.

    The coke arrives via rail routes to the tippler (2 No which unloads in the

    similar fashion as in the case of RMHP and send via 2 conveyor belts to the

    Silo. There are 81 Silo. These Silo's are numbered from 1 to 53 odd numbers, 2

    to 54 even numbers and 1A to 53A odd numbers. Capacity of each Silo is 2500

    Tons. Each Silo consists of coal coming from a different source namely

    Australia, New-Zealand, Karghali, Kathara, Moonidi, and Jharia etc. These coals

    have different ash percentage and different volatile material. The captive coal

    mines of the SAIL produces coal of various qualities having ash percentage

    between 15-25% where as the imported coal have ash percentage between 7-

    8%. So accordingly these need to mix in order to obtain coke. The Indian Coal

    and imported coal are mixed in the ratio of 1:4 almost. From the Silo the coal

    is sent to Hammer Crusher which has a capacity of crushing 350Tons/Hr.

    which crushes the coal to about -3.2 mm size. The homogenization and mixingof coal used to occur via mixture but now it is not anymore used. The mixing

    occurs automatically when the coal is transferred through several conveyor

    belts. From t

    The crushed coke is transferred to Coal Tower (4 no's) with each having a

    capacity of 3200 Tons. From there the coal i supplied to the 8 Coke Oven

    Batteries.

    Coke Oven Battery consists of 69 coke ovens and 70 heating walls. In eachCoke Oven there are 3 charging holes on the top and is charged by the

    charging car. On the side of the Coke Oven one would see a huge Push car

    which is used to ram out the coke prepared in the oven. The leveling ram

    levels the top of the coal. On the other Side one would see the Guide car which

    supports the rammed column of coke and guides it to the quenching car.

  • 8/3/2019 Submitted Report

    51/51

    The Coke Oven walls are made up of refractory material having hole in

    between through which the Coke Oven Gas and Blast Furnace Gas as a fuel are

    burnt which causes the bricks to become red hot. There is no air inside the

    oven so the coal burns without air at about 1200 C. The flue pipes of the

    refractory tunnel s connected by the flue tunnel with Twin reverse valve by

    help of which flow reverses after some time. The two heating walls are

    connected over the top by means of pipes. It carries the burnt gas out through

    the chimney. The top of the coke oven is connected by pipes coming out which

    is connected to the pipe which carries the burnt particles and volatile particles

    to the By Product Plant.

    From the coke oven it is sent for quenching in Quenching Tower where water

    is dropped from the overhead pipe. The Quenched coke is sent for CokeCrushing Station and than to Coke Screening Station from where the coke of

    25 mm size is sent to Blast Furnace and coke of size between 25-80 mm is

    sent to crushing station again.