Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC)...

35
1 Submissions of Lake Ontario Waterkeeper Re: Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area Initiative (PHAI), and participating in the Commission Meeting process. Notice of Public Meeting, Ref. 2016-M-01 October 3, 2016 Submitted to: Participant Funding Program Administrators [email protected] and the CNSC Secretariat [email protected] Cc: Julia Szymanski [email protected], and Adam Levine [email protected]

Transcript of Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC)...

Page 1: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

1

Submissions of Lake Ontario Waterkeeper

Re: Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on

Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area Initiative (PHAI), and participating in the

Commission Meeting process.

Notice of Public Meeting, Ref. 2016-M-01

October 3, 2016

Submitted to: Participant Funding Program Administrators [email protected] and the CNSC Secretariat [email protected] Cc: Julia Szymanski [email protected], and Adam Levine [email protected]

Page 2: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

2

TABLE OF CONTENTS

Executive Summary …………………………………………………………………………………… 3 Background ………………………………………………………………………………………..…… 5

• About Lake Ontario Waterkeeper ……………………………………………………………. 5 • About the PHAI ………………………………………………………………………………… 5 • A visit to the PHAI sites while preparing these submissions ……………………………… 7

Water quality concerns in Lake Ontario.…………………………………………………………… 8 Water Effluent concerns and the PHAI project ………………………………………. ……….… 9 Interjurisdictional cooperation and the PHAI …………………………………………………… 12

• The MOECC’s involvement with the PHAI ………………………………………………… 12 The PHAI’s Public Information Program …………………………………………………………. 14 Conclusion …………………………………………………………………………………………….. 16 Appendix I: Independent Review of Hydrological Issues Pertaining to the Review of the CNSC Staff Status Report on CNL’s Port Hope Area Initiative, Wilf Ruland, P. Geo, October 3, 2016

Appendix II: Wilf Ruland, P. Geo CV Appendix III: Pippa Feinstein, JD CV Appendix IV: Compiled Questions and Answers between Mr. Ruland, Ms. Feinstein and PHAI staff

Appendix V: Meeting notes from Site Visit, September 23, 2016

Page 3: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

3

EXECUTIVE SUMMARY The Port Hope Area Initiative (PHAI) is an internationally significant undertaking. It is the biggest radioactive waste clean-up project in Canadian history, and involves one of the largest nuclear waste holding facilities in North America. The PHAI is comprised of two distinct projects: the Port Hope waste relocation project (“Port Hope Project”), and the Port Granby waste relocation project (“Port Granby Project”). Together, both projects seek to clean up a combined two-million cubic metres (m3) of low-level radioactive waste from various sites across Port Hope and Port Granby. The Port Hope Project involves excavating 1,223,250 m3 of historic radioactive waste from several sites around the town of Port Hope to a Long-term Waste Management Facility (PH LTWMF) just north of the community. The project was subject to an environmental assessment (EA) under the Canadian Environmental Assessment Act, 1992 (CEAA, 1992) which was conducted from 2001 to 2007. In 2009, the CNSC granted a five-year Nuclear Waste Substance Licence to Atomic Energy Canada Limited (AECL) to implement the project. In 2012, AECL applied to have its licence extended for ten years. This was granted by the Canadian Nuclear Safety Commission (CNSC), making the current licence valid until December 31, 2022. The Port Granby Project involves the removal of 450,000 m3 of historic radioactive waste from the existing and poorly contained Port Granby waste management facility to a new above-ground waste management facility (the PG LTWMF) 700 metres north of the Lake Ontario shoreline. The Port Granby Project was also subject to a federal EA under CEAA, 1992 and the project was approved in 2009. After a public hearing in September 2010, the CNSC granted AECL a ten-year licence to implement this project. Both Port Granby and Port Hope’s new LTWMFs have their own Waste Water Treatment Plants (WWTPs) to treat the sites’ stormwater and leachate before it is released into Lake Ontario. AECL/CNL’s licences for both projects authorize it to:

• Develop and construct new long-term waste facilities; • Remediate historic waste sites; • Transport waste to its facilities; and • Conduct long-term maintenance and monitoring of its waste sites.

Lake Ontario Waterkeeper (Waterkeeper) has been involved with decision-making processes for the PHAI for almost a decade. The organization has also enjoyed long-standing relationships with many Port Hope residents since its founding in 2001. Waterkeeper is very aware of the beauty of the Port Hope and Port Granby areas: their preserved historical town buildings and houses; their active aquatic communities along the lake’s shoreline, the Ganaraska River, and local creeks; their local beaches; and their stunning cycling and walking trails. Waterkeeper is sensitive to issues involving environmental concerns over the nuclear waste contamination throughout Port Hope and Port Granby, as well as the social stigma that has accompanied these concerns. Waterkeeper is committed to assisting the local community and PHAI project management to carry out the initiative in a transparent, cooperative, and effective way. Waterkeeper is also dedicated to ensuring PHAI facilities and operations are held to a high

Page 4: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

4

standard, so that the legacy waste in the community is removed responsibly and stored and treated well. Waterkeeper was provided with participant funding in order to be able to intervene in this matter before the CNSC and has retained two experts to examine the PHAI and make recommendations for its improvement:

• Wilf Ruland, P. Geo, an experienced Hydrogeologist who examined the potential impacts of the PHAI activities and facilities on local surface water. He examined and made recommendations concerning the LTWMF and WWTP plans for both Port Hope and Port Granby projects as well as environmental monitoring for the PHAI and relevant environmental release limits.

• Pippa Feinstein, JD, counsel and case manager for Waterkeeper who examined and made recommendations concerning interjurisdictional regulation of the PHAI and the quality of the PHAI’s Public Information Program (PIP).

Overall, both Mr. Ruland and Ms. Feinstein were impressed with the work that has been undertaken on the PHAI to date. The design of the LTWMFs and WWTPs are state of the art, and the technology being used to implement the initiative is very impressive. Similarly, the PHAI’s efforts to engage the community and share information about its work have been extensive. At the same time, there is room for improvement. The following is a summary of Waterkeeper’s recommendations for improvements to the PHAI. Each will be discussed in greater detail and with more context in the remainder of these submissions below. A more detailed and comprehensive list of recommendations can also be found in the conclusion of these submissions.

1. The LTWMFs and WWTPs should have more comprehensive, explicit, and enforceable effluent release limits. Additions of effluent release limits for Uranium and other contaminants of primary concern (COPC) should be added to the existing CNSC licenses for these facilities, and design objectives for facilities should be adopted as licence limits;

2. Monitoring plans for the LTWMFs and WWTPs should be extended to cover a longer period of time. Because the environmental threats of radioactive contamination remain for centuries, a longer monitoring regime for the LTWMFs and WWTPs is required than what is currently specified;

3. Better inter-jurisdictional cooperation between the federal and Ontario

governments is still required. While the federal government has taken on a leadership role in the PHAI, the Ministry of Environment and Climate Change (MOECC) must still ensure non-radioactive contaminants falling under provincial jurisdiction are meeting provincial standards;

4. The PHAI’s PIP should be strengthened by including more data sharing with the

public. Results of environmental sampling should be made public and the PHAI should notify the public of any reportable release events.

Page 5: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

5

Background

About Lake Ontario Waterkeeper

Waterkeeper is a grassroots environmental organization that uses research, education, and legal tools to protect and restore the public’s right to swim, drink, and fish in Lake Ontario. Founded in 2001, Waterkeeper is a non- political registered charity focusing on environmental research and justice issues in the public interest. It is dedicated to protecting and celebrating the Lake Ontario watershed, including the wetlands, streams, rivers, and creeks that flow into the lake.

Waterkeeper also works with communities to facilitate the use of environmental laws to protect their rights to swim, drink, and fish. The organization participates in legal processes to help ensure that environmental decisions are made on the basis of sound and tested scientific evidence by independent decision-makers and in the public interest. Waterkeeper is participating in the current PHAI Update meeting process to ensure the Commission considers the public’s need for a swimmable, drinkable, fishable Lake Ontario when examining CNSC staff’s update report.

About the PHAI The PHAI is comprised of the Port Hope Project and the Port Granby Project. Waterkeeper has been studying each project, and has been involved in several decision-making processes for them before the CNSC and MOECC for almost a decade. Each project is discussed below, in addition to Waterkeeper’s past involvement and concerns. The Port Hope Project involves the remediation of large volumes of low-level radioactive waste from a variety of locations throughout the municipality, including:

• 450,000 m3 of waste from the existing Welcome Waste Management Facility; • 572,000 m3 of waste from Port Hope’s harbour, the Highland Drive Municipal Landfill,

and residential properties; • 150,000 m3 of legacy waste from the Cameco Port Hope Conversion Facility (PHCF) as

well as waste from building demolition associated with Cameco’s Vision in Motion project; and

• 51,250 m3 of waste from contaminated industrial waste sites including the Port Hope Centre Pier, Lions Park, and the municipal sewage treatment plant.

Much of this legacy waste was a product of the ore refining activity undertaken in Port Hope which began in the 1930s. Water from the harbour and lakes was used by the new refining facilities to extract radium from the ore brought down from Deloro’s northern mine. At that time, there wasn’t a proper understanding of the harm these activities, or the waste they produced, could have on the health of locals and the environment. Unfortunately, radioactive waste and byproducts from the refining process were spread over the town in several smaller landfills, or else salvaged as building materials in residents’ homes. By the 1970s, this legacy waste was considered a significant problem, and from 1976 to 1980, the federal government assisted with an effort to clean up legacy waste sites. That initiative removed approximately 100,000 m3 of waste, although it led to the discovery of significantly more waste in need of excavation and treatment. A task force was subsequently instituted to

Page 6: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

6

find a home for this waste. After a survey of many other communities across the country, none of which were ultimately prepared to accept the waste, Port Hope and Port Granby began plans to hold and manage the waste in their home communities. By this time, the Port Granby waste site had already become a source of concern as it was seeping significant amounts of contaminated effluent into the lake. Being so close to the shoreline which was quickly eroding, the containment of radioactive waste at that site was becoming increasingly more precarious with time.1 As early as 2001, Waterkeeper studied and expressed concern about the lack of containment at the old Port Granby waste facility. The organization prepared a report discussing the sources of contamination at the site, as well as their environmental effects. Importantly, Waterkeeper at this time was also concerned about the apparent lack involvement by the then Ministry of Environment (MOE) in addressing the environmental damage caused by the poorly contained Port Granby waste site.2 Also in 2001, Port Hope, Port Granby and the federal government signed an agreement to initiate the PHAI and store legacy waste in a more contained and safe way in both communities. Several years later, when plans for the PHAI were developed and the EA was completed, Waterkeeper intervened in the 2009 licence hearing for the Port Hope Project. At that hearing it submitted the following:

• That CNSC staff’s proposed criteria for permissible effluent discharges were inappropriate, as some values were hundreds of times above the Provincial Water Quality Objectives (PWQOs);

• That the MOE must exercise its jurisdiction over provincially-regulated contaminants at the LTWMF;

• That limits on effluent should be explicitly delineated as licence requirements in the CNSC licence itself;

• That both federal and provincial agencies had jurisdiction over radioactive and non-radioactive waste respectively, and that better coordination between federal and provincial authorities on this issue was required;

• That the project should have had more explicit and documented financial guarantees and a Preliminary Decommissioning Plan at the time of the licence hearing. Neither had been addressed in AECL’s application; and

• That AECL did not release objective information or data to the public about its project. Instead it provided “subjective, inaccurate, inaccessible, opaque, and broad messaging about its activities”.3

In 2012, when AECL applied to extend its licence for another ten years, Waterkeeper argued the following:

• That there was a significant lack of procedural, technical, and policy advice in planning for the project;

11977EnvironmentalImpactStudy(EIS)forPortGranby,conductedbyEldoradoNuclearLimitedpursuanttotheEnvironmentalAssessmentReviewProcessAct(EARPA).2LakeOntarioWaterkeeper,AStudyofLeaksatthePortGranbyLow-LevelWasteManagementFacility,2001.3LakeOntarioWaterkeeper,ReviewoftheEnvironmentalAssessmentandlicenceapplicationforthePortHopeLong-TermLow-LevelRadioactiveWasteManagementProject,2009.

Page 7: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

7

• That the project’s wastewater standards continued to be extremely lax, far exceeding other government standards. While the CNSC noted the standards would be temporary, and re-evaluated once AECL constructed a new wastewater facility, Waterkeeper argued that revised regulatory standards should be set before the construction of a new system. Waterkeeper also requested that the process for setting these standards be subject to meaningful public participation (either via an EA or Environmental Bill of Rights (EBR) hearing);

• That the CNSC and MOE were still not collaborating or consulting one another about the regulation of nuclear and non-nuclear industrial waste requiring disposal; and

• That AECL’s approach to public consultation was very poor. Waterkeeper requested a more robust public engagement strategy from the company.4

Of these concerns, some have been addressed by the PHAI, and others persist. Since Waterkeeper’s comments in 2012, the CNSC has created a Jurisdictional Regulatory Group (JRG) in which the Commission ensures it communicates with the MOECC at least semi-annually, providing project updates to two regional offices. Furthermore, the PHAI’s approach to public engagement has increased with its Public Information Exchange (PIE) resource centre, active community outreach program, and an easy-to-navigate website. Its WWTPs are also state of the art, providing reverse osmosis treatment to effluent water they will receive, which will significantly mitigate any adverse impacts of the release of treated water into Lake Ontario. However, more work is required. More comprehensive effluent limits still need to be better delineated in CNSC licences, and amounts should conform to all applicable laws and guidelines. Furthermore, it will be important for the PHAI to release actual sampling results from its environmental monitoring programs to ensure that the PHAI public messaging about the safety of the projects can be supported by proper scientific evidence. Finally, the MOECC should be more involved in the project than is currently the case. While it is a step in the right direction to have established the JRG, the MOECC must also be more hands-on in efforts to ensure the PHAI projects meet Ontario’s environmental laws and guidelines. A visit to the PHAI sites while preparing these submissions On September 23, 2016, Wilf Ruland and Pippa Feinstein met with Sarah Anderson, Glenn Case, and Pierre LeBel at the PHAI Management Office in Port Hope for a site visit and to discuss potential issues of concern for Waterkeeper. The meeting lasted three hours and involved a tour of the Port Hope and Port Granby LTWMF construction areas, as well as the Highland Drive site and the Port Hope Harbour. Information obtained during this meeting has been used to help inform these submissions, and notes from the meeting have been included as Appendix V to this submission. 4LakeOntarioWaterkeeper,InterventionbeforetheCNSCconcerningAECL”sapplicationtoremovetheholdpointsandtoamendtheexpirydateofWasteNuclearSubstanceLicenceforthePortHopeLong-TermLow-LevelRadioactiveWasteManagementProject,2012.

Page 8: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

8

Water quality concerns in Lake Ontario When considering the environmental impacts of the PHAI and measuring its success, it is imperative to do so with a view to its historical and environmental context.

Despite many human stressors, the Lake Ontario watershed remains resilient and continues to support diverse ecosystems. Lake Ontario’s archipelagos, beaches, bays, tributaries, islands and wetlands provide many opportunities for swimming, canoeing, fishing, nature observation and other forms of recreation. Lake Ontario also provides drinking water to over 9-million Americans and Canadians

Along the shoreline of Lake Ontario in the Port Hope area, alewife, rainbow smelt, threespine stickleback, and lake whitefish spawn. The Ganaraska River has resident populations of brown trout, brook trout, rainbow trout, and walleye. Northern pike and lake whitefish also spawn in the river which provides nursery habitat for these species. The Ganaraska River, is a “key producer” spawning site for wild chinook salmon and coho salmon.5 During Ms. Feinstein and Mr. Ruland’s site visit on September 23rd, over 70 people were lined up on either side of the Ganaraska watching one of the semi-annual salmon spawning runs.

The Port Hope Harbour also provides sheltered warmer water for a modest aquatic community. Smallmouth bass, yellow perch, and spottail shiner all enjoy habitat in the harbour. The Harbour also hosted the marina of the Port Hope Yacht Club for 50 years before the club stopped operating earlier this year. The West Beach, located just west of Port Hope’s harbour and the PHCF, provides important recreational space along the lakeshore. In summer, it is filled with wildflowers just above its pebble beach, and the beach includes a small park with a play area for children. The waterfront trail running along between Port Hope and Port Granby also sees lots of traffic, particularly on the weekends as many cyclists and joggers enjoy the scenic path. At the same time, the area around Port Hope has been designated by the federal government under the Great Lakes Water Quality Agreement as an Area of Concern “because a review of available data indicated that water quality and environmental health were severely degraded”.6 The focus of the remediation efforts has been on Port Hope’s harbour. The AoC’s most recent Status of Beneficial Use Impairments from 2010 stresses the importance of PHAI efforts to remediate local waterbodies. Ultimately, while the north shore of the lake is resilient, it is still fragile. All development and activity that could affect the water quality of the lake must be pursued in sensitive ways that mitigate any adverse impact to the greatest extent possible. While cleaning up areas of contamination is important for the long-term health of this part of our lake, cleanup activities will still be disruptive. The discussion below includes a description of the PHAI’s impacts on local water quality and offers recommendations for how these impacts may be further mitigated.

5Appendix E, the Environmental Assessment Report for Cameco’s Port Hope Conversion Facility Relicensing Application, CNSC Staff CMD 16-H8 at p21.6“PortHopeAreaofConcern”,EnvironmentandClimateChangeCanada,online:www.ec.gc.ca.

Page 9: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

9

Water Effluent Concerns and the PHAI Project Mr. Ruland has explained in his review of the PHAI that the new LTWMFs are very secure and that the new WWTPs are state of the art. He notes that efforts to remove waste from contaminated sites across Port Hope and the older Welcome and Port Granby low-level radioactive waste facilities will result in the immediate and permanent improvement of groundwater and surface water quality in those locations. He also finds the Clean-up Criteria for the remediation of these older waste facilities to be adequate and appropriate. Mr. Ruland explains that the areas that require more CNSC attention concern the establishment of effluent limits on the WWTPs, and the monitoring plans for the facilities during their operations and post-closure. With regards to effluent limits, Mr. Ruland recommends the following: That the site licenses for the older Port Granby and Welcome waste management facilities be immediately amended to include an Effluent Discharge Level of 0.15 mg/L for Uranium. Currently, neither the older Port Granby Waste Management Facility nor the Welcome Waste Management Facility’s CNSC licenses include any limit on Uranium effluent at all. The Port Granby Waste Management Facility’s only liquid effluent limit was Radium-226 (at 0.37bq/L) and the Welcome Waste Management Facility’s only liquid effluent limits were for Radium-226 (also at 0.37bq/L) and Arsenic (at 0.5mg/L). Mr. Ruland explains that Uranium is a “key indicator” of low-level radioactive waste and a surrogate for the presence of many other potentially harmful contaminants. He asserts the lack of Uranium liquid effluent release limits is neither proactive nor precautionary.7 As such he recommends that Uranium discharge limits be immediately included in both facilities’ licenses. He believes an effluent discharge limit of 0.15 mg/L to be sufficient. The design objectives for both the new Port Hope WWTP and Port Granby WWTP should be made licence conditions for those facilities. Mr. Ruland has found that the current design objectives for the WWTP in The Port Granby Environmental Management Plan are adequate. Further, given the monitoring results from the Port Granby WWTP (which began operating this past April), the WWTPs should easily be able to operate well below these design objectives.

7 Independent Review of Hydrological Issues Pertaining to the Review of the CNSC Staff Status Report on CNL’s Port Hope Area Initiative, Wilf Ruland, P. Geo, October 3, 2016, p 7 (the “Ruland Report”).

Page 10: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

10

Design Objectives are not in and of themselves effluent limits. However, including these design objectives as licence conditions for both the Port Hope and Port Granby WWTPs will make them legally enforceable effluent release limits. If a CNSC regulated facility is found to contravene its licence conditions, it can be subject to disciplinary action such as fines (“Administrative Monetary Penalties”), temporary licence suspension, revocation, or prosecution.8 Action Levels for the Port Hope and Port Granby WWTPs should be set within 12 months of the commencement of these facilities’ operation. Mr. Ruland agrees that the proposal to set Action Levels once 12 months worth of each WWTPs’ monitoring data is available, is reasonable. Mr. Ruland stresses that these Action Levels should be significantly lower than the WWTPs’ effluent release limits. He also recommends that established Action Levels cover all the parameters listed in Table D-3 produced above. Mr. Ruland explains that this list is sufficiently comprehensive to protect the local environment and Lake Ontario. Especially important is the fact that it contains all the identified Contaminants of Potential Concern (COPCs) for both WWTPs: Arsenic, Cobalt, Radium-226, and Uranium. Heavy metals to be monitored downstream from the Port Granby LTWMF should be explicitly delineated and more comprehensive. Currently, the parameter list for the proposed downstream aquatic environment water quality monitoring program at Port Granby’s WWTP ensures that “heavy metals” will be tested for without specifying which metals this term actually includes. An explicit list should be developed. 8CanadianNuclearSafetyCommission,“TheCNSC’sapproachtocomplianceverificationandenforcement”,online:http://nuclearsafety.gc.ca/.

Page 11: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

11

Mr. Ruland recommends that this list be at least as comprehensive as the the parameters listed in Table D-3 pf Port Granby’s EMP provided above. Furthermore, Mr. Ruland raises concern over the fact that no regulatory levels for downstream monitoring have been established except for Uranium. As such, Mr. Ruland recommends that Control Levels and Action Levels be set for the three other Port Granby COCs: Arsenic, Radium-226 and Cobalt. Regulatory Levels for the Port Hope Environmental Management Plan must be clarified. The Port Hope EMP requires further information and direction concerning the specifics of its proposed monitoring program for downstream aquatic environment quality. Mr. Ruland found the descriptions of the program in section 5.1 of the EMP to be “rambling and unfocussed”.9 The Port Hope WWTP effluent monitoring program should be more comprehensive. Mr. Ruland could not find a parameter list for effluent monitoring at the WWTP. Further, the only proposed licence limits and Action Levels for the facility concerned Arsenic and Radium-226. Mr. Ruland recommends that Effluent Release Limits corresponding to the Design Objectives in the License Conditions Handbook should be imposed on the Port Hope WWTP. Surface water monitoring downstream from the Port Hope LTWMF should be explicitly delineated and more comprehensive Mr. Ruland found the Port Hope downstream surface water quality monitoring program didn’t include a parameter list. He recommends that at a minimum, it should include all the parameters included in the design objectives table in the Port Hope Licence Conditions Handbook. The Control Levels and Action Levels for Uranium proposed in the Port Granby EMP should be adopted in the Port Hope EMP Currently, the Port Hope EMP is lacking any specific values for its Control Levels or Action Levels for Uranium. As such, Mr. Ruland recommends that the existing Uranium Control Level proposed in the Port Granby EMP of 0.0016 mg/L and the proposed Action Level of 0.012 mg/L be applied to the Port Hope EMP. Mr. Ruland also recommends that in addition to adopting these Action Levels and Control Levels for Uranium, the CNSC should develop suitable Control Levels and Action Levels for the two other COPCs; Arsenic and Radium-226. Downstream water quality monitoring in Lake Ontario at the effluent release points for the Port Granby and Port Hope WWTPs should continue as long as the facilities are operating. Mr. Ruland noted he is very impressed by the design of both the Port Hope and Port Granby LTWMFs and their respective WWTPs. At the same time, he cautions that there may still be the possibility that unforeseen problems may arise. Continuous and comprehensive effluent monitoring can alert the PHAI staff of any problems which may otherwise go unnoticed. As 9RulandReport,p10.

Page 12: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

12

such regular monitoring can help prevent environmentally harmful releases and must thus continue as long as the facilities are active.

There should be a longer-term monitoring plan for the facility after the WWTPs close. Mr. Ruland recommends that downstream surface water monitoring in nearby creeks to the Port Granby and Port Hope LTWMFs should continue at quarterly intervals for a minimum of five years after the facilities close. After this time, the creeks should still be monitored semi-annually for 20 years, and annually for an additional 25 years. By this 50-year mark, Mr. Ruland recommends that periodic checks should be made every five years to confirm the integrity of the LTWMF’s covers, and the water quality in nearby streams. These five-year periodic inspections of the LTWMF tops and nearby creeks should continue for 500 years. The PHAI must include a plan for managing contaminated water in the harbour during PHAI and VIM dredging and excavation activity. When the PHAI and Cameco’s Vision in Motion project begin their planned dredging and excavating activities in and around the harbour, the harbour water will become especially contaminated. The harbour mouth will be closed to the lake during these remediation activities so as to prevent aquatic species’ contact with the released contamination. However, as the harbour remains closed over this time, inflows of rainwater, groundwater and stormwater will increase the volume of contaminated water. The PHAI and VIM need to create a plan to manage this significant amount of contaminated water. A plan is needed to address how contaminated harbour water will be treated and managed once dredging and excavation work ceases and the harbour mouth is opened again. Mr. Ruland highlights how important it will be for the PHAI and VIM project to monitor the impact of contaminated harbour water on local lake water quality. He recommends that monitoring of lake water beyond the mouth of the harbour occur at least monthly and after any rain events of more than 50mm. Interjurisdictional Cooperation and the PHAI The Ontario Ministry of Environment and Climate Change’s involvement with the PHAI Waterkeeper still finds the absence of Ontario involvement in the PHAI troubling. In its explanation of the Port Hope Area of Concern, the federal Ministry of the Environment and Climate Change explains “Undertaking environmental restoration requires a large amount of scientific and technical expertise, local knowledge and hard work. One agency or group cannot engage in such a large task on their own without the help of others”. The Ministry then lists the participants that contribute to these PHAI efforts: Natural Resources Canada, Atomic Energy of Canada Limited, Public Works and Government Services Canada, the Municipality of Port Hope, and the Municipality of Clarington.10 The MOECC is also excluded from the federal-municipal agreement establishing the PHAI and its terms of reference. 10EnvironmentandClimateChangeCanada,“PortHopeAreaofConcern”,online:www.ec.gc.ca.

Page 13: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

13

Waterkeeper has wanted the province to play a more significant role in the PHAI since 2001. After raising this issue with the province at that time, Waterkeeper’s files include an MOE letter in which it explains that since the federal government was involved in addressing Port Granby’s and Port Hope’s waste, the MOE would not also be involved in its licensing process, nor would it conduct a complimentary environmental assessment for the PHAI.11 The 2005 draft of the PHAI EA study report confirmed that the MOE would not undertake a complimentary EA. Rather, the Ministry committed to preparing comments concerning the federal EA once that review was completed. That being said, the MOE “expected that implementation [of the PHAI projects] will consider provincial legislative codes, and guidelines with regards to discharges and management of non-radiological waste”.12 Importantly, the PHAI’s own EA report confirmed that even if the province was not leading this initiative, the provincial Environmental Bill of Rights (EBR), Environmental Protection Act (EPA), Ontario Water Resources Act (ODRA), and the Sustainable Development Act (SDA) were all applicable to the PHAI.13 During the 2007 hearing before the CNSC, submissions from CNSC staff on the EA for the Port Hope Project confirmed provincial regulations were applicable to the project, citing the Provincial Water Quality Objectives and sediment guidelines.14 In 2013, the CNSC established a Jurisdictional Regulatory Group (JRG) including both the CNSC and Peterborough and Pickering offices of the MOECC. Meetings between these authorities has since been convened by the CNSC twice a year and has mainly involved one-way communication from the CNSC to the MOECC. This is done mainly by providing PHAI progress updates to MOECC officers. During the September 23, 2016 site visit, PHAI staff confirmed that ECAs were required for municipal landfill sites and temporary generator systems, but that they were not required for the LTWMFs or WWTPs, due to the involvement of federal authorities. However, if the EPA and ODRA are applicable to the PHAI, it is unclear exactly why the WWTPs and LTWMFs would be automatically exempt from having to obtain ECAs for their activities. According to both Acts, ECAs are required for facilities that release pollutants into the water, or stores waste. Further, certain non-radioactive contaminants stored at the LTWMFs and treated at the WWTPs are provincially regulated substances. Other elements of the PHAI such as the remediation of the Highland Drive landfill and the stockpiling of municipal waste during that process would require MOECC oversight and amendments to the landfill’s existing ECA. Waterkeeper recommends that space be made for the MOECC to meaningfully provide regulatory oversight to aspects of the PHAI with which it shares jurisdiction with the federal government. If it determines that separate ECAs are not required for the WWTPs and LTWMFs, it should at least be able to participate in processes that set regulatory effluent limits and Action Levels for the facilities so that it can ensure the PHAI facilities adhere to provincial environmental laws and regulations. The PHAI should also share its raw environmental monitoring data results 11CommunicationswiththeMOEConcerningtheFederalEnvironmentalAssessmentforthePortHopeAreaRemediation,2001.12PHAIDraftEnvironmentalAssessmentStudyReport,2005atp7-67.13Ibidp7-69.14CNSChearing2007atp85.

Page 14: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

14

with the local MOECC offices so that their officers can verify the facilities’ compliance with provincial standards. The PHAI’s Public Information Program A Public Information Program (PIP) for the PHAI is required by section 3(j) of the Nuclear Safety Control Act. This section states the purpose of a PIP is to “inform persons living in the vicinity of the site of the general nature and characteristics of the anticipated effects on the environment and the health and safety of persons that may result from the activity to be licensed”.15 The “primary goal of PIP is to ensure: 1) the health, safety and security of persons and environment is effectively communicated, and 2) a commitment to and protocol for ongoing timely information”.16 The objectives of the PHAI’s Public Information Program are to:

• Provide the public and other stakeholders with effective access to timely information in order to prepare them for upcoming work and help them understand project activities, programs, timing, environmental protection and mitigation measures, long-term benefits and economic opportunities.

• Build and maintain active support for and confidence in the PHAI with the public and all levels of political leadership in the host communities by ensuring that stakeholders are fully briefed on the background, goals and current developments of the projects.

• Position the PHAI Management Office as the primary source for accurate project information to reduce the potential for externally generated project delays that may result from misinformation and misconceptions.

• Provide open and transparent public disclosure about unplanned project activities and events, proportionate with the public’s perception of risk and the level of public interest in the PHAI’s activities.17

The PHAI’s information-sharing methods include the Project Information Exchange (PIE). The PIE is housed in the foyer of the PHAI management office. It contains to scale models of what the Port Hope and Port Granby LTWMFs will both look like once completed. It also contains several bookshelves of information about the two projects for members of the public to take and learn from. Resources range from one-page explanations of radiological testing and where and when this will happen in the community, to larger maps and plans for PHAI excavations, to several hundred-page reports about the PHAI’s EAs and commissioned public attitude surveys. Other information-sharing methods include and online communications, newsletters, after-hours telephone access, presentations, site tours, public information sessions, media relations, participation in external events, key stakeholder liaisons. Postcards with information about the PHAI are given to local businesses, the PHAI hosts school trips, and goes to community events to share information about the initiative with local residents. There are also Citizen Liaison Groups in Port Hope and Port Granby that seek to increase the transparency of the project. These Committees determine their own action goals and discussion topics at the start of each year. Recent goals/topics have included: environmental monitoring;

15PublicInformationandDisclosure,RG/GD99.3at1.3.16Ibidat2.117CanadianNuclearLaboratories,PHAIPhase2PublicInformationProgram,section3.

Page 15: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

15

communication plans between the PHAI and the pubic; compliance with regulations; explanations of major project sites; and property values in the community. Meetings of these Committees include roundtable discussions and ‘feature’ (i.e. more directed) discussions with relevant experts. The Committees meet quarterly. From this review, PHAI’s PIP appears to be quite robust and its information is being made very accessible. One important aspect that is missing from the PIP is any significant data-sharing component. There is also some lack of clarity about about exactly what kinds of environmental incidents must be reported on the PHAI website. All reportable incidents pursuant to CNSC and MOECC laws and regulations should be reported to the PHAI website within four days of their occurrence or discovery. The PIP’s Public Disclosure Protocol (PDP) notes, “The PHAI Management Office is committed to providing open and transparent public disclosure about unplanned project activities such as:

• Events that have off-site effects or could result in public interest and concern and/or media attention

• Serious vehicle or industrial accidents • Operational developments that result in significant changes to facility design or operation

or to project schedule • Natural events such as floods that have an impact on project activities.18

There is a clear and visible tab on the PHAI website’s homepage that reads “Public Disclosures”. The tab leads to a webpage for PHAI to report incidents. One incident from April 21, 2016 is already reported: it involved a small quantity of untreated ground/surface water being discharged when a pipe was broken during the construction of the Port Granby LTWMF. Waterkeeper commends the PHAI for its work and considerable community engagement. The organization also understands that proactive information disclosure is one of the top issues Citizen Liaison Groups are interested in discussing more in the coming years. In order to assist these groups and the PHAI in this endeavor, Waterkeeper recommends that the PDP be amended to confirm that all reportable incidents to the CNSC and MOECC be uploaded onto its website. Waterkeeper also recommends that all incident reports include: an online posting date, the date of the accident (or estimated date), and estimated or known quantities and concentrations of any releases. If this information is not known at the time of posting, it should be noted as an incident update to the original notice as soon as the relevant information is obtained. All PHAI monitoring results should be reported clearly on the PHAI website and in real time when feasible. PHAI staff have confirmed that quarterly monitoring results from the WWTP will be provided on the PHAI website, as the facilities are commissioned. The PHAI website already contains a significant amount of information concerning environmental monitoring, explaining in simple terms the monitoring it conducts for air quality, noise, and odour,

18CanadianNuclearLaboratories,PHAIPhase2PublicInformationProgram,section6.

Page 16: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

16

groundwater and soil quality, surface water quality, fish and fish habitat, and plant and wildlife. The website already provides real-time weather monitoring data. Waterkeeper recommends that sampling results from each of these types of monitoring should be posted to the PHAI website within four days of being received or analysed. Depending on whether sampling occurs weekly, monthly posting would ideally be weekly or monthly. However, if all monitoring results (rather than calculated averages) would be provided in the PHAIs quarterly compliance reports this may be acceptable. Once this data is posted, it should also remain online, so as to facilitate members of the public’s comparisons with subsequent sampling results.

Since 2011, the federal government has promoted increased data sharing by its departments, including Environment Canada, Fisheries and Oceans Canada, and Natural Resources Canada.19 Given the significant involvement of the federal government with the PHAI, ensuring that the project meets its goals for publicly available and usable data would be consistent with its promises in this area.

Conclusion The following is a summary of Waterkeeper’s recommendations for improvements to the PHAI:

1. That the site licenses for the older` Port Granby and Welcome waste management facilities be immediately amended to include an Effluent Discharge Level of 0.15 mg/L for Uranium;

2. The design objectives for both the new Port Hope WWTP and Port Granby WWTP should be made licence conditions for those facilities;

3. Action Levels for the Port Hope and Port Granby WWTPs should be set within 12 months of the commencement of these facilities’ operation;

4. Heavy metals to be monitored downstream from the Port Granby LTWMF should be explicitly delineated and more comprehensive;

5. Regulatory Levels for the Port Hope Environmental Management Plan must be clarified; 6. The Port Hope WWTP effluent monitoring program should be more comprehensive; 7. Surface water monitoring downstream from the Port Hope LTWMF should be explicitly

delineated and more comprehensive; 8. The Control Levels and Action Levels for Uranium proposed in the Port Granby EMP

should be adopted in the Port Hope EMP; 9. Downstream water quality monitoring in Lake Ontario at the effluent release points for the

Port Granby and Port Hope WWTPs should continue as long as the facilities are operating;

10. There should be a longer-term monitoring plan for the facility after the WWTPs close. 11. The PHAI must include a plan for managing contaminated water in the harbour during

PHAI and VIM dredging and excavation activity;

19PressRelease,“MinisterDayLaunchesOpenDataPortal”TreasuryBoardofCanadaSecretarial,March17,2011,online:www.tbs-sct.gc.ca.

Page 17: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

17

12. A plan is needed to address how contaminated harbour water will be treated and managed once dredging and excavation work ceases and the harbour mouth is opened again;

13. That space be made for the MOECC to meaningfully provide regulatory oversight to aspects of the PHAI with which it shares jurisdiction with the federal government;

14. All reportable incidents pursuant to CNSC and MOECC laws and regulations should be reported to the PHAI website within four days of their occurrence or discovery;

15. All monitoring results should be reported clearly on the PHAI website and in real time where feasible.

Page 18: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

Independent Review of Hydrogeological Issues

Pertaining to the Review of the CNSC Staff Status Report

on CNL’s Port Hope Area Initiative

Prepared for:

Lake Ontario Waterkeeperc/o Mr. Mark Mattson, President

Prepared by Wilf Ruland (P. Geo.)

766 Sulphur Springs RoadDundas, Ontario

L9H 5E3(905) 648-1296

[email protected]

October 3rd, 2016

page 1

Page 19: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

Table of Contents

1) Introduction............................................................................................................................. 3

2) Background and Overview of the PHAI................................................................................. 4

3) Water Quality Protection Measures........................................................................................ 4.................................................................................................................a) Introduction 4

b) ........................................................Current LLRW Locations are Poorly Controlled 5c) .................................................Long Term Waste Management Facilities are Secure 5

...........................................................................d) Environmental Protection Programs 6

4) Waste Water Treatment Plants (WWTPs) ............................................................................... 6.................................................................................................................a) Introduction 6

...............................................................b) Historic and Future Effluent Release Limits 7

5) Water Quality Monitoring Programs...................................................................................... 8.................................................................................................................a) Introduction 8

................................................................b) Regulatory Levels in the Port Granby EMP 8........................................c) Port Granby WWTP Effluent Quality Monitoring Program 9

d) Downstream Surface Water Quality Monitoring Program for Port Granby LTWMF 9.................................................................e) Regulatory Levels in the Port Hope EMP 10

f) ........................................Port Hope WWTP Effluent Quality Monitoring Programs 10..g) Downstream Surface Water Quality Monitoring Program for Port Hope LTWMF 11

h) ............Duration of the Downstream Surface Water Quality Monitoring Programs 11..........................................i) Wrap Up Comments on the PHAI Monitoring Programs 12

6) Water Management in the Sealed-off Port Hope Harbour and Monitoring in the Lake .. 12

7) Discussion .............................................................................................................................. 13

8) Conclusions............................................................................................................................ 14

9) Recommendations.................................................................................................................. 15

Appendix 1) List of Documentation Reviewed or Referenced................................................. 17

page 2

Page 20: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

1) Introduction

I am a hydrogeologist, and I have worked as a professional for 30 years (2 years in Germany and 28 years in Canada). I am a specialist in groundwater and surface water contamination issues, and have investigated many such issues over the course of my consulting career. I have given testimony as an expert witness on hydrogeological issues before various boards, including the Environmental Review Tribunal, the Environmental Assessment Board, the Joint Board, the Ontario Municipal Board, the Niagara Escarpment Commission, and the Canadian Nuclear Safety Commission (CNSC). A copy of my Curriculum Vitae is available upon request.

I’ve been retained as an expert by Lake Ontario Waterkeeper (LOW) to provide an independent review of the CNSC Staff Report on Canadian Nuclear Laboratories Ltd. (CNL) Port Hope Area Initiative (PHAI). I should note that LOW received CNSC funding to support my review.

The focus of my review are the potential groundwater and surface water quality impacts related to inorganic, organic, and radiological contaminants which may be associated with any aspect of the PHAI’s Port Hope and Port Granby projects.

The adequacy of the Port Hope Area Initiative’s two projects (from a water quality protection perspective) can be measured at this time by the degree to which these projects provide:

- an accurate understanding of existing soil, groundwater and surface water conditions in the Port Hope Area;- a well thought-out and comprehensive plan to mitigate or eliminate potential soil, groundwater and surface water quality impacts caused by historic Low Level Radioactive Waste (LLRW) in the Port Hope area;- appropriate water quality monitoring plans and follow-up monitoring plans;- realistic contingency plans;- adequate oversight for the project by PHAI staff, as well as adequate oversight and regulation by the CNSC.

In order to carry out my work, I have reviewed numerous documents and the most important of these are listed as references in Appendix 1 of this review.

I toured the area of the PHAI Port Hope and Port Granby Projects (on September 23rd, 2016), and asked questions about various aspects of the proposal of the PHAI representatives who were present on the day of the tour. I also submitted (through LOW) an information request and a series of questions - most of which were discussed during the site tour.

This review outlines my findings, conclusions and recommendations following my review of the CNSC Staff Report on CNL’s Port Hope Area Initiative (PHAI). The CNSC Staff Report on the PHAI is a Commission Member Document or CMD (No. 16-M44), which provides an excellent background and overview description of the current status of the PHAI.

In the course of my review I have carefully considered numerous background documents which are available regarding the PHAI, and following my review I can report that I do not disagree with any aspect of the information which is provided in the CMD. In fact, I can highly recommend the CMD as providing a concise but reasonably detailed summary of the current status of the PHAI.

page 3

Page 21: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

In my comments which follow I will be highlighting some key aspects of the information which is provided in the CMD on the PHAI, and I will be outlining some areas where I believe the PHAI could be strengthened going forward.

2) Background and Overview of the PHAI

The PHAI is a process under which the federal government is offering to accept historic low-level radioactive waste (LLRW) from across Port Hope and environs, and to secure these in two dedicated long-term waste management facilities (LTWMFs) - one in Port Hope and one near Port Granby. The details of this program are spelled out in a Federal Agreement with local governments.

There are several major LLRW sources in Port Hope, and a multitude of smaller ones. The CMD indicates that the wastes from these sources will be going to the two LTMFs as follows:

Port Granby LTWMF- 450,000 m3 of LLRW from the existing Port Granby WMF (situated very near Lake Ontario)

will be relocated 700 meters inland to the Port Granby LTWMF.

Port Hope LTWMF- 450,000 m3 of LLRW from the existing Port Hope WMF will be relocated to the new Port

Hope LTWMF (on the same site);- 51,250 m3 will be coming from 3 contaminated industrial waste sites (Port Hope Center Pier,

Lions Park, and the Port Hope sewage treatment plant;- following detailed radiological surveys of 4800 properties, it is estimated that small amounts of

LLRW waste will be coming from an estimated 375 residential properties;- 572,000 m3 of LLRW will be coming from various remediation sites including the Port Hope

Harbour, the Highland Drive Municipal Landfill, and the aforementioned residential properties;- 150,000 m3 of Cameco-owned legacy wastes (generated prior to 1988) as well as additional

contaminated soils and wastes from building demolition associated with the Cameco Vision in Motion (VIM) project will be coming to the LTWMF.

The Clean-up Criteria are provided in the CNSC Site Licenses, and I have no issue with them. Following completion of the PHAI all of the above LLRW sources will be remediated - with the exception of the Cameco Port Hope Conversion Facility, which even after completion of the PHAI will have some contaminated soil and contaminated groundwater under various buildings.

3) Water Quality Protection Measures

a) IntroductionThe remediation works associated with the PHAI’s Port Hope Project and the Port Granby project are both entirely in keeping with the mission of LOW. They will result in the mitigation and/or elimination of LLRW contamination at major and minor site across the Port Hope area - leaving behind vastly improved soil, groundwater and surface water quality.

page 4

Page 22: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

The following aspects of the PHAI will result in much improved water quality:- LLRW wastes and soils will be removed from numerous poorly controlled sites across the Port

Hope area, and will be deposited in 2 secure LTWMFs;- the 2 LTWMFs are designed with state of the art features to provide secure and permanent

containment of the LLRWs which they receive;- wastewater from each of the LTWMFs will be treated at a dedicated waste water treatment plant

(WWTP), before being discharged to Lake Ontario.

I will discuss each of these water quality protection measures in more detail below.

b) Current LLRW Locations are Poorly ControlledThe LLRW wastes in Port Hope date back to a time when little was known about the potentially harmful nature and the safe storage of such wastes. As a result, none of the locations at which the LLRWs are presently situated are what I would consider well-designed or well-controlled when it comes to the prevention of groundwater and surface water contamination.

After-the-fact efforts have been made to investigate and mitigate water contamination with mixed results, depending on the waste location being considered.

In all cases, relocation of the wastes to the secure LTWMFs will result in an immediate and permanent improvement to groundwater and/or surface water quality at the current LLRW waste locations. As such, it is a very good thing that the Port Hope Project and the Port Granby Project are now in the implementation phase. Contaminated soils and wastes from the LLRW sites will be deposited in well-designed and secure sites, which are discussed in more detail in the next section of this review. The Clean-up Criteria for LLRW site remediation are provided in the CNSC Site Licenses for each project’s LTWMF, and are adequate and appropriate.

c) Long Term Waste Management Facilities are SecureThe design of the LTWMFs is unique in my experience with landfills and industrial and hazardous waste sites in Ontario. The LTWMs have been designed to both prevent leakage of contaminated water out of the facilities, and to prevent rainfall from getting into the facilities once they are closed.

A state of the art base liner will prevent leakage of contaminated liquids out of the facilities. While the designs of the liners are subtly different in response to the differing geology at each of the LTWMF locations, both consist of multiple layers of mainly synthetic materials (bolstered by the liquid retention capabilities of natural clay). The thickness of the base liners of the LTWMFs is 1.35 meters, and both allow for containment and collection of any contaminated liquids being generated by the wastes.

A unique and likewise state of the art cover system will prevent rainfall from getting into either of the facilities once they are filled and closed. The designs of the cover systems are slightly different in response to the differing planned end uses of each of the LTWMF locations, but both consist of multiple layers of natural and synthetic materials designed to shed incoming rainfall (to prevent it from seeping into the underlying wastes), and to minimize gamma radiation at the ground surface above the covers. The thickness of the LTWMF cover systems is over 2 meters.

page 5

Page 23: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

The unique (in Canada) combination of an impermeable cover and an impermeable base liner (with leachate collection facilities) for the LTWMFs constitutes what I am calling a “clamshell” design, which will ensure that after closure the LLRWs inside the LTWMFs will first be slowly dewatering and will then remain entombed for the very long term.

d) Environmental Protection ProgramsNotwithstanding the the innovative designs discussed above, very thorough Environmental Protection Plans (EPPs) have been developed for each of the LTWMFs.

Each of the EPPs includes careful consideration of the following issues:- safely managing the incoming wastes;- air quality protection including dust prevention/mitigation;- managing storm water and storm events, including erosion and sediment control;- managing potentially contaminated water;- spill prevention and mitigation (including safe fueling and maintenance) plans;- radiological security including personnel and equipment decontamination;- environmental monitoring plans for air, groundwater, stormwater, and treated surface water;- a variety of contingency plans including responses to potential fires, storm events, accidents,

and spills;- proactive personnel training programs.

I have few issues with the component parts of the EPPs for the two projects. My main concerns relate to the effluent release limits and the downstream receiving surface water quality monitoring programs for each facility, and these are discussed in more detail in Section 4) below.

4) Waste Water Treatment Plants (WWTPs)

a) Introduction Contaminated liquids will be generated by rain falling onto the wastes being deposited in the LTWMFs for as long as they are open to the elements. Once the final cover installation has been completed (preventing further wetting of the wastes by rainfall), the flow of liquids should reduce to an easily managed trickle within a few years as the wastes dewater.

The WWTPs for the Port Hope Project and the Port Granby Project are different in design, reflecting the different nature of the wastes they will be receiving. The wastes coming into the PH LTWMF are metals-rich, and in order to deal with the metals the wastewater will first be processed through chemical precipitation followed by clarification and sand filtering. The wastes coming into the PG LTWMF are high in organic matter (ammonia nitrate), and in order to deal with these the wastewater will first be subject to biological treatment.

Following the first treatment steps described above, wastewater at both WWTPs will then be further treated through reverse osmosis systems - in which the wastewater is forced through a membrane in order to remove the most problematic contaminants including uranium, arsenic and radium. The resulting treated water will be very low in contaminants, far lower than if treated through conventional waste water treatment facilities. Contaminant levels in effluent from the WWTPs should be close to drinking water quality following the reverse osmosis treatment.

page 6

Page 24: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

The reverse osmosis systems on the new WWTPs generate a contaminated solid byproduct, which will be disposed of in the LTWMFs while they are open. In the longer term the liquid flows requiring treatment and the resultant byproduct production should rapidly dwindle, but in the interim post-closure period there will be solids requiring secure long-term storage/disposal coming from the WWTPs.

The WWTPs are the critical final step in the containment and protection of the environment from the LLRWs, so diligent maintenance and downstream monitoring to ensure and confirm their proper functioning is essential. Likewise essential are robust discharge limits for the treated wastewater - which has been a problem in the past.

b) Historic and Future Effluent Release LimitsIn my review of the historic discharge limits in the CNSC Licenses for the wastewater treatment facilities at the Welcome WMF and the Port Granby WMF I was surprised to find that there was no effluent release limit for Uranium in liquid effluent for either facility.

The only contaminant with a release limit for liquid effluent at the Port Granby WMF was Radium-226 (with a limit of 0.37 Bq/L). Only two contaminants had a release limit at the Port Hope WMF - Radium-226 (with a limit of 0.37 Bq/L) and Arsenic (with a limit of 0.5 mg/L).

In my professional opinion these historic limits in CFSC Licenses for the wastewater treatment facilites at the PH WMF and the PG WMF were inadequate, and were not protective of the natural environment. Uranium is the key indicator of LLRW contamination in the Port Hope area and is a surrogate for the presence of many other also potentially harmful contaminants.

My interpretation of the lack of liquid effluent release limits for Uranium in the CFSC Licenses is that there was effectively no limit set by the regulator on the amount of Uranium (and the many other parameters which also had no discharge limit) being discharged in liquid effluent from the facilities. I do not consider this to be either proactive or precautionary. I should note that the liquid effluent being discharged from the facilities ended up in Lake Ontario.

Looking forward a sophisticated new WWTP is in operation, treating leachate and contaminated water from the Port Granby WMF (and from the PG LTWMF once it begins receiving waste). I have seen “Design Objectives for the LTWMF Water Treatment System” covering numerous contaminants in the License Conditions Handbook for the Port Granby facility. I can support these Design Objectives, and in fact I expect that the effluent being discharged from the WWTP will easily meet the Design Objectives. I would however like to see the CNSC give “teeth” to these Design Objectives by making them Effluent Release Limits on the Site License. My sense is that Design Objectives are not enforceable - Effluent Release Limits are.

Likewise a new state of the art WWTP will soon be in operation and treating leachate and contaminated water from the Port Hope WMF (and from the PH LTWMF once it begins receiving waste). I have seen “Design Objectives for the LTWMF Water Treatment System” covering numerous contaminants in the License Conditions Handbook for the Port Hope facility. I can support these Design Objectives, and in fact I expect that the effluent being discharged from the WWTP will easily meet the Design Objectives. I would however like to see the CNSC give “teeth” to these Design Objectives by making them Effluent Release Limits on the Site License.

page 7

Page 25: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

5) Water Quality Monitoring Programs

a) IntroductionFor any contaminated waste management facility, an important confirmation of successful site design and operations is provided by water quality monitoring conducted in the natural environment downgradient and downstream of the site. There are quite a few separate components to the water quality monitoring programs for the Port Hope and Port Granby projects.

I will not be providing comments on the groundwater quality monitoring, as my funding did not allow that and because I see very little potential for the the PHAI to cause groundwater quality impacts. Instead, there will be a progressive improvement in groundwater quality as existing poorly controlled LLRW locations are excavated and relocated to the new and secure LTWMFs. The groundwater quality impacts from the existing LLRW locations will diminish steadily over time once the sources are removed, and there will be negligible impacts from the LTWMFs.

The program for downstream surface water quality monitoring is described in the September 2011 Environmental Monitoring Program (EMP) for the Port Granby Project and in the August 2012 EMP for the Port Hope Project.

There are many components to the surface water quality monitoring programs. These include monitoring at the LTWMFs and their nearby WWTPS, and in Port Hope at some of the existing major existing LLRW locations. The monitoring is further subdivided into phases which correspond to the 2 remaining phases of the projects:- the current construction and development phase (which is the time at which any downstream

impacts are most likely);- the long-term post-closure maintenance and monitoring phase.

I will be focussing my comments on water quality monitoring being done during the current construction and development phase. I will start with comments on components of the Port Granby EMP, and follow with comments on components of the Port Hope EMP.

b) Regulatory Levels in the Port Granby EMPSpecific regulatory levels have been developed for the surface waters which are downstream of the Port Granby LTWMF and WWTP. As set out in Section 5.1 of the Port Granby EMP, the following three tiers of levels have been established:

Regulatory Level – It is anticipated that regulatory levels will be specified in the Site License as not to be exceeded in carrying out the licensed activities. These levels are contaminant concentrations that have been established by regulatory authorities to ensure the protection of human health and the environment.

Action Level - These levels are set below the regulatory levels to warn of a potential adverse environmental effect and allow actions/contingency plans to be implemented to correct the situation. It is anticipated that the Site License will require the licensee to establish acceptable action levels for the LTWMF. The license will also outline the requirement to report to the CNSC exceedances of the action levels.

page 8

Page 26: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

Administrative Control Level - These lower concentration value administrative control levels are established to warn of potential environmental effects before the action levels have been exceeded. When these administrative control levels are exceeded, an action plan will be implemented at the operations level to increase surveillance, identify the root cause and implement the appropriate contingency/mitigative action plan to control the release/exposure.

It is indicated in Section 5.1.1.1 that the key contaminants of potential concern (COPCs) in drainage water, groundwater and surface water at the Port Granby WMF are Arsenic, Cobalt, Radium-226 and Uranium.

c) Port Granby WWTP Effluent Quality Monitoring ProgramThe effluent monitoring program for the critical construction and development phase are provided in EMP Section 6.1.

Effluent quality monitoring is to be conducted weekly, which I consider to be an appropriate frequency. The parameter list for the effluent monitoring is provided in EMP Table D-3, and I consider this list to be appropriate.

It is my professional opinion that Effluent Release Limits corresponding to the Design Objectives in Table D-3 should be imposed on the Port Granby WWTP by the CNSC - these should be hard upper limits on the permitted quality of the effluent releases (compliance to be verified through the weekly monitoring).

Section 6.1 of the Port Granby EMP also indicates that Action Levels should be established once 12 months worth of data have been obtained following the commissioning of the new WWTP, and this is a reasonable proposal. I would however recommend that the proposed Action Levels (which should be significantly lower than the effluent release limits) should cover all of the parameters listed in Table D-3, and in particular the COPCs Arsenic, Cobalt, Radium-226 and Uranium.

d) Downstream Surface Water Quality Monitoring Program for Port Granby LTWMFThe downstream surface water quality monitoring program during the critical construction and development phase is described in EMP Section 8.1.3.1. Monitoring will be quarterly (which is appropriate) and suitable monitoring locations have been established - upstream and downstream of the site, and in Lake Ontario at the effluent diffuser and 20 meters to either side of it.

There is an incomplete reference to the Table intended to be showing monitoring methodologies at the top of page 8-13 of the PG EMP - I am assuming the reference should be to Table D-17. Table D-17 provides the parameter list for the proposed aquatic environment water quality monitoring program, but simply states that the parameter list will include “heavy metals” instead of listing them individually. I consider this to be a mistake - the individual parameters to be monitored should be specified and should at a minimum include all of the metals in Table D-3.

No regulatory levels have been established except for the following (for Uranium):- an Administrative Control Level of 0.0016 mg/L (which is appropriate);- an Action Level of 0.012 mg/L (which is appropriate).

page 9

Page 27: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

I would urge the CNSC to also require that Control Levels and Action levels be set for the 3 other Port Granby COPCs (Arsenic, Cobalt, and Radium -226).

e) Regulatory Levels in the Port Hope EMPThe discussion in Section 5.1 of the Port Hope EMP of regulatory levels for the downstream surface waters receiving treated effluent coming from the LTWMF is rambling and unfocussed, and requires some editing so that it can provide clear direction for the effluent and downstream water quality monitoring programs in the EMP.

It is indicated in Section 5.1.1.1 that the key contaminants of potential concern (COPCs) in drainage water, groundwater and surface water at the Port Hope WMF are Arsenic, Radium-226 and Uranium.

f) Port Hope WWTP Effluent Quality Monitoring ProgramThe effluent monitoring program for the critical construction and development phase in discussed in EMP Section 6.1.

Effluent quality monitoring is to be conducted weekly, which I consider to be an appropriate frequency. The parameter list for the effluent monitoring is not provided - instead reference is made to a parameter list from a different report. I consider this to be poor practice - the EMP should include its own parameter list for effluent monitoring. At a minimum the parameter list should include all of the parameters listed in the Design Objectives table on page 18 of the Port Hope License Conditions Handbook.

The EMP indicates in Section 6.1 that Table B-1 provides the License Limits and Action Levels for the current wastewater treatment facility. Review of Table B-1 reveals that there are only license limits for two contaminants (Arsenic and Radium-226) - I support the license limits for those parameters. But given that Uranium is ubiquitous in the LLRWs and on the list of COPCs for the Port Hope WMF and LTWMF, I find it inexplicable that there is no License Limit for Uranium in the discharges from the wastewater treatment facilities. This oversight should be corrected immediately.

Looking forward it is my professional opinion that Effluent Release Limits corresponding to the Design Objectives in the License Conditions Handbook should be imposed on the Port Hope WWTP by the CNSC - these should be hard upper limits on the permitted quality of the effluent releases (compliance to be verified through the weekly monitoring).

Section 6.1 of the EMP indicates that Action Levels should be established once 12 months worth of data have been obtained following the commissioning of the WWTP, and this is a reasonable proposal. I would however recommend that the proposed Action Levels (which should be significantly lower than the effluent release limits) should cover all of the parameters listed in the Design Objectives table in the Port Hope License Conditions Handbook, and in particular should include the COPCs Arsenic, Radium-226 and Uranium.

page 10

Page 28: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

g) Downstream Surface Water Quality Monitoring Program for Port Hope LTWMFAs mentioned previously, there is a rather lengthy discussion of regulatory levels in Section 5.1 of the Port Hope EMP. It is not clear from this discussion which of the many regulatory levels listed under the heading “Environmental Monitoring and Assessment” are intended to apply to the downstream water quality monitoring program.

The actual downstream surface water quality monitoring program during the critical construction and development phase is described in Section 8.1.3.1 of the EMP. Monitoring will be quarterly (which is appropriate) and suitable monitoring locations have been established - in Brand Creek upstream and downstream of the site, and in Lake Ontario at the effluent diffuser and 20 meters to either side of it.

A parameter list is not specified in Section 8.1.3.1 of the EMP - I recommend that at a minimum the parameter list should include all of the parameters listed in the Design Objectives table in the Port Hope License Conditions Handbook. More likely is that the EMP’s authors intended the parameter list in Table D-3 of the Port Hope EMP to be used (as it is in other parts of the Port Hope surface water monitoring program).

The only regulatory levels to be specified in Section 8.1.3.1 is a Control Level for Uranium, at 0.015 mg/L - which seems high for a Control Level. By contrast the Control Level for Uranium proposed in the Port Granby EMP is 0.0016 mg/L, which I consider to be more appropriate. There is no Action Level established for Uranium in the Port Hope EMP - I would recommend that the Action Level of 0.012 from the Port Granby EMP be adopted. I would also urge the CNSC to require that Control Levels and Action levels be set for the 2 other Port Hope COPCs (Arsenic and Radium-226).

h) Duration of the Downstream Surface Water Quality Monitoring ProgramsThere is no end-point or minimum duration specified for the downstream surface water monitoring programs for the 2 LTWMFs and their respective WWTPs.

Given the potentially hazardous and/or toxic nature of the wastes being deposited in the LTWMFs, the design goal of the LTWMFs has been to keep these isolated from the environment over the very long term. While I do not anticipate any issues, long-term monitoring is an essential component of ensuring that the design goal is met.

I recommend that downstream water quality monitoring in Lake Ontario continue for as long as the WWTPs are in operation and discharging treated effluent to the lake. I recommend that downstream surface water monitoring in the nearby creeks should continue at the present quarterly frequency for a minimum of 5 years after site closure, and that after that monitoring can be stepped down to semi-annually for 20 years, and after that down to annually for another 25 years.

At the 50 year point, a decision can be made about the need for further regular downstream monitoring. In my professional opinion it would be appropriate for periodic checks to made on the LTWMFs to confirm integrity of their covers (perhaps every 5 years), and for downstream surface water quality monitoring to be conducted during such inspections. These inspections (with downstream monitoring) should continue for a minimum of 500 years.

page 11

Page 29: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

i) Wrap Up Comments on the PHAI Monitoring ProgramsI have spent considerable time carefully examining and providing comments regarding key sections of the Port Hope and Port Granby EMPs which focus on effluent quality monitoring and downstream surface water quality monitoring.

I have done so because these are the critical safeguards for the downstream natural environment including Lake Ontario. I am very impressed by the design of both the Port Hope and Port Granby LTWMFs and their respective WWTPs, but even with the best design there is always the possibility that unforeseen problems may arise leading to higher than predicted releases of contaminants from these facilities. In the event of such an occurrence, monitoring of effluent quality and downstream surface water quality can provide an essential indicator of problems which may otherwise go unnoticed.

6) Water Management in the Sealed-off Port Hope Harbour and Monitoring in the Lake

One aspect of the Port Hope waterfront remediation which involves both the PHAI and Cameco is the remediation of the Port Hope Harbour. The Harbour is to be dredged to remove the contaminated sediments which have made it one of 43 designated Great Lakes Areas of Concern under the Canada - United States Great Lakes Water Quality Agreement.

The PHAI and Cameco Vision in Motion (VIM) plans include a provision for fish to be removed from the Port Hope Harbour beforehand - with the Harbour then being sealed off for the duration of the project during which Harbour impacts are anticipated. While this provides assurance that efforts are being made to prevent harm to fish, there is a broader question regarding how the contaminated water in the Harbour is going to be handled.

The various VIM and PHAI operations taking place in and around the harbour will be causing the harbour water to be contaminated during a years-long period. This would not be a problem, except that there are ongoing inflows to the harbour (of rainfall, groundwater and storm water) and the Harbour mouth is to be sealed off so there will be no place for the surplus (contaminated) water to go.

I have not been able to find any information in the VIM or PHAI documentation on how the surplus contaminated water from the Port Hope Harbour is going to be handled during the VIM/PHAI project period. This is clearly an issue which needs to addressed, as otherwise there will be an ongoing poorly controlled and untreated flow of contaminated Harbour water into Lake Ontario.

Monitoring will be critical to ensure that impacted Harbour water is not causing unacceptable contamination of Lake Ontario. The PHAI monitoring proposals are provided in the Port Hope EMP, and the Port Hope Harbour is discussed in Section 9.1.3.3. Review of Section 9.1.3.3 indicates that this aspect of the EMP has not yet been thought through or properly developed.

There is no reference to plans to monitor water quality in Lake Ontario (just beyond the Harbour mouth), but I strongly recommend that such monitoring should be carried out. Lake Ontario water quality monitoring should be done frequently (at minimum on a monthly basis, plus after

page 12

Page 30: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

any rain events exceeding 50 mm), and should include the full list of COPCs identified for the PHCF. The results of this monitoring should be made publicly available.

It could be argued that the Lake Ontario monitoring should be done either partly or entirely through the VIM project (rather than through the PHAI project), but the question of who does the monitoring is immaterial from my perspective - what is important is that the monitoring be done, that it be reviewed by competent technical people who will ensure that any developing issues are dealt with quickly and thoroughly, and that the results will be made publicly available.

7) Discussion

As an independent technical reviewer of the CMD on the PHAI project, I find myself in the happy position of being able to report to my clients at LOW that I whole-heartedly support the 2 projects at the heart of the PHAI.

The current locations at which LLRWs are stored are not well-secured from the perspective of preventing environmental contamination. Their relocation to the 2 well-designed and secure LTWMFs will be an entirely positive development for the people and the environment in the Port Hope area. This a major project - unprecedented in Canada - and it has obviously been well-funded, well-designed, and thought through with careful attention to details.

The removal of the LLRW materials from across the Port Hope area will provide a significant and permanent improvement in water quality on-site and downgradient/downstream of each of the properties from which the wastes are being removed, and these improvements will ripple down the watershed to also benefit Lake Ontario.

The clean-up criteria for remediation of the LLRW sites across the Port Hope area are adequate, and consistent with criteria used in other clean-ups around the province. They will allow the community to move forward with confidence.

I do not have any real concerns about the technical design details of the LTWMFs and the WWTPs for the PH Project or the Port Granby Project. I find both project designs to be impressive in terms of their innovation, scope and attention to detail.

The only issues I am raising and providing recommendations on pertain to:- the regulation of such projects by the CNSC, which needs to be bringing the site licenses up to

date so that the effluent discharge limits better reflect the capabilities of the new WWTPs (as discussed in Section 4);

- the monitoring programs for the projects, which could use some fine-tuning (as discussed in Section 5).

I am also providing recommendations on an area of overlapping responsibility between the VIM and PHAI projects, namely the management of the Port Hope Harbour clean-up. I could not find plans for management of the contaminated water being generated in the sealed off Harbour in either the VIM or PHAI documentation, but such plans (and plans for downstream monitoring in Lake Ontario) will clearly be needed.

page 13

Page 31: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

8) Conclusions

1) There is a major existing problem in Port Hope, caused by the presence of numerous locations at which there are low-level radioactive wastes (LLRWs). These locations come in all sizes from very small to very large, but what they have in common is that the wastes were deposited many years ago and that the wastes are not properly controlled for the long-term.

2) The Port Hope Area Initiative (PHAI) is a unique and major LLRW remediation project, which is aimed at providing secure long-term management of the LLRWs from around Port Hope. The PHAI has its basis in a legal agreement between the Federal Government and local communities, and involves a major clean-up of the LLRW locations in Port Hope which is unprecedented in Canada.

3) Seen from the perspective of groundwater and downstream surface water quality, the PHAI projects will provide major and permanent environmental benefits. Contaminated soils and wastes are to be relocated to secure LTWMFs from numerous impacted properties and storage facilities across the Port Hope area. The long-term result will be mitigation or elimination of contaminants on these properties and at these facilities, and immediate decreases in contaminant discharges to the waters of Port Hope Harbour and Lake Ontario.

4) The CNSC’s regulation of the existing major historic waste sites has not been adequate. There have been no effluent release limits applied to Uranium discharges in treated wastewater from the Port Hope and Port Granby Waste Management Facilities. Realistic and environmentally protective regulatory levels for effluent quality are required for the new Port Hope and Port Granby wastewater treatment plants (WWTPs) going forward, as discussed in Section 4 of this review.

5) Fortunately it should not be a problem for the WWTPs to meet stringent effluent quality limits. Initial testing of the effluent from the Port Granby WWTP shows exceptionally low levels of various COPCs and other contaminants of concern.

6) The downstream surface water quality monitoring programs for the Port Hope and Port Granby projects require some fine-tuning, as described in Section 5 of this review.

7) The management of the Port Hope Harbour clean-up is an area of overlapping responsibility between the VIM and PHAI projects. I could not find plans for management of the contaminated water being generated in the sealed off Harbour in either the VIM or PHAI documentation, but such plans (and plans for downstream monitoring in Lake Ontario) will clearly be needed - as discussed in detail in Section 6 of this review.

8) Recommendations are provided below to address the issues identified in Sections 4, 5, and 6 of this review.

page 14

Page 32: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

9) Recommendations

1) The Effluent Release Limits contained in the Site Licenses for the Port Hope and Port Granby Long-Term Low-Level Radioactive Waste Management Projects should immediately be amended to include an Effluent Release Limit of 0.15 mg/L for Uranium.

2) The “Design Objectives for the LTWMF Water Treatment System” in the License Conditions Handbook for the Port Granby facility should be made Effluent Release Limits on the Site License by the CNSC. Likewise, the “Design Objectives for the LTWMF Water Treatment System” in the License Conditions Handbook for the Port Hope facility should be made Effluent Release Limits on the Site License by the CNSC.

3) Action Levels should be established once 12 months worth of data have been obtained following the commissioning of the new Port Granby WWTP, and these Action Levels (which should be significantly lower than the effluent release limits) should cover all of the parameters listed in Table D-3 of the Port Granby EMP - in particular the COPCs Arsenic, Cobalt, Radium-226 and Uranium.

4) Table D-17 of the Port Granby EMP provides the parameter list for the proposed downstream aquatic environment water quality monitoring program, but simply states that the parameter list will include “heavy metals” instead of listing them individually. The individual parameters to be monitored should be specified and should at a minimum include all of the metals in Table D-3. No regulatory levels for downstream monitoring have been established except for Uranium. I recommend that the CNSC should also require that Control Levels and Action levels be set for the 3 other Port Granby COPCs (Arsenic, Cobalt, and Radium-226).

5) The discussion in Section 5.1 of the Port Hope EMP of regulatory levels for the downstream surface waters receiving treated effluent coming from the LTWMF is rambling and unfocussed, and requires some editing so that it can provide clear direction for the effluent and downstream water quality monitoring programs in the EMP.

6) Action Levels should be established once 12 months worth of data have been obtained following the commissioning of the Port Hope WWTP, and these Action Levels (which should be significantly lower than the effluent release limits) should cover all of the parameters listed in the Design Objectives table in the Port Hope License Conditions Handbook - in particular should include the COPCs Arsenic, Radium-226 and Uranium.

page 15

Page 33: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

9) Recommendations - continued

7) Section 8.1.3. of the Port Hope EMP dos not provide a parameter list for the proposed downstream aquatic environment water quality monitoring program. A parameter list should be specified and should at a minimum include should include all of the parameters listed in the Design Objectives table in the Port Hope License Conditions Handbook.

8) The Control Level for Uranium proposed in the Port Granby EMP of 0.0016 mg/L should be adopted in the Port Hope EMP, and likewise the Action Level of 0.012 mg/L from the Port Granby EMP should be adopted in the Port Hope EMP. I also recommend that the CNSC require Control Levels and Action levels to be set for the 2 other Port Hope COPCs (Arsenic and Radium-226).

9) I recommend that downstream water quality monitoring in Lake Ontario at the effluent release point for each facility continue for as long as the Port Hope and Port Granby WWTPs are in operation and discharging treated effluent to the lake.

10) I recommend that downstream surface water monitoring in the nearby creeks to the Port Hope and Port Granby LTWMFs should continue at the present quarterly frequency for a minimum of 5 years after site closure, and that after that monitoring can be stepped down to semi-annually for 20 years, and after that down to annually for another 25 years. Starting at the 50 year point, I recommend that it would be appropriate for periodic checks to made on the LTWMFs to confirm integrity of their covers (perhaps every 5 years), and for downstream surface water quality monitoring to be conducted during such inspections. These inspections (with downstream monitoring) should continue for a minimum of 500 years following closure of the LTWMFs.

11) The final plan for handling contaminated water from the Port Hope Harbour during the VIM/PHAI project period should be provided for public/stakeholder review once it has been completed. It is not clear from the documentation who is responsible for this issue, but it needs to be addressed by either Cameco or the PHAI.

12) The plan for monitoring Lake Ontario outside the Harbour mouth during the VIM/PHAI project period should also be provided for public/stakeholder review at that time. Lake Ontario water quality monitoring is required and should be done at minimum on a monthly basis (plus after any rain events exceeding 50 mm), and should include the full list of COPCs identified for the PHCF. The results of this monitoring should be made publicly available. Cameco and the PHAI will need to determine who is responsible for the monitoring.

page 16

Page 34: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

Appendix 1- References The references considered in the course of preparing this review include the following:

Progress Update, Port Hope Area Initiative, Public Meeting Scheduled for November 9, 2016. Commission Member Document (CMD16-M44). Dayed Sept. 2, 2016

2015 Port Granby Annual Compliance Report, Port Granby Project. Issued April 2016 by Canadian Nuclear Laboratories.

Waste Nuclear Site Licence No. WNSL-W1-2311.01/2021, Port Granby LLRW Management Project. Issued to Canadian Nuclear Laboratories by the CNSC on Oct. 22, 2014.

License Conditions Handbook WNSL-W1-LCH-2311, Revision 1, Port Granby LLRW Management Project. Issued by Nuclear Processing and Facilities Division, December 4, 2014.

ENVIRONMENT AL MONITORING PLAN PORT GRANBY PROJECT, PHAI Management Office, AECL. 2011/09/01.

PORT GRANBY PROJECT BIOPHYSICAL EFFECTS MONITORING PLAN, PHAI Management Office, AECL. 2011/07/27

SCREENING REPORT , The Port Granby Long-Term Low-Level Radioactive Waste Management Project. August 2009. Prepared by Natural Resources Canada and the CNSC.

2015 Port Hope Annual Compliance Report, Port Hope Project. Issued April 28, 2016 by Canadian Nuclear Laboratories.

Waste Nuclear Site Licence No. WNSL-W1-2310.01/2022, Port Hope LLRW Management Project. Issued to Canadian Nuclear Laboratories by the CNSC on Oct. 22, 2014.

License Conditions Handbook WNSL-W1-LCH-2310, Revision 1, Port Hope LLRW Management Project. Issued by Nuclear Processing and Facilities Division, December 4, 2014.

ENVIRONMENT AL MONITORING PLAN PORT HOPE PROJECT, PHAI Management Office, AECL. 2012/08/23.

PORT HOPE PROJECT BIOPHYSICAL EFFECTS MONITORING PLAN, PHAI Management Office, AECL. 2012/03/03.

SCREENING REPORT , The Port Hope Long-Term Low-Level Radioactive Waste Management Project. December 2006. Prepared by Natural Resources Canada and the CNSC.

page 17

Page 35: Submission of Lake Ontario Waterkeeper - Reviewing Canadian Nuclear Safety Commission (CNSC) staff’s status report on Canadian Nuclear Laboratories Limited’s (CNL) Port Hope Area

CNSC COMMISSION MEMBER DOCUMENT (CMD: 16-H8.1). Submitted: 02 September 2016 by Cameco. Cameco PHCF Request for a Licensing Decision Regarding: Renewal of Operating Licence FFOL-3631.0/2017 for the Port Hope Conversion Facility

CNSC Commission Member Document (CMD: 16-H8). Submitted 02 September 2016 by CNSC Staff. Regarding A Licence Renewal Commission Public Hearing. Scheduled for: 9-10 November 2016

Cameco 2017 LICENCE RENEWAL APPLICATION FOR THE PHCF. Supplemental VIM Dated February 1, 2016

Cameco 2017 LICENCE RENEWAL APPLICATION FOR THE PHCF. Dated November 20, 2015

CNSC Record of Proceedings, Including Reasons for Decision regarding the Comprehensive Study Report for Cameco Corporation's Proposed Redevelopment of the Port Hope Conversion Facility (Vision 2010). May 30,2012

page 18