Subject: Geotechnical Report, Intersection Improvements ...The objective of this study is to...
Transcript of Subject: Geotechnical Report, Intersection Improvements ...The objective of this study is to...
July 9, 2010 Revised December 2, 2011 Mr. Sunil Taori, P.E. Volkert & Associates, Inc. 5400 Shawnee Road, Suite 301 Alexandria, Virginia 22312 Subject: Geotechnical Report, Intersection Improvements, Huguenot Trail (Route
711) at Pleasants Road (Route 616), Powhatan County, Virginia, VDOT Project No. 0711-072-180-R201, C501 (Schnabel No. 09130227)
Dear Mr. Taori: SCHNABEL ENGINEERING, LLC (Schnabel) is pleased to submit our geotechnical engineering report for this project. This report was prepared according to our submittal, and authorized by email from Volkert & Associates, Inc. on May 13, 2010. We are pleased to be of service to you on this project. Please call us if you have any questions. Sincerely, SCHNABEL ENGINEERING, LLC
Evan B. Morris, P.E. Assistant Project Manager EBM:mr Cc: Volkert & Associates, Inc. Attn: Mr. Phil Lohr, P.E.
GEOTECHNICAL REPORT Intersection Improvements Huguenot Trail (Route 711) at Pleasants Road (Route 616) Powhatan County, Virginia VDOT Project No. 0711-072-180-R201, C501 Schnabel Reference #09130227
July 9, 2010
Revised December 2, 2011
Geotechnical Report Intersection Improvements Huguenot Trail (Route 711) at Pleasants Road (Route 616) Powhatan County, Virginia VDOT Project No. 0711-072-180-R201, C501 Schnabel Project No. 09130227 July 9, 2010 Revised December 2, 2011 Prepared for: Mr. Sunil Taori, P.E. Volkert & Associates, Inc. 5400 Shawnee Road, Suite 301 Alexandria, Virginia 22312 Prepared by: SCHNABEL ENGINEERING, LLC One West Cary Street Richmond, Virginia 23220 Phone: (804) 649-7035 Fax: (804) 783-8023
Evan B. Morris, P.E. Edward G. Drahos. P.E.
Assistant Project Manager Project Manager
EXECUTIVE SUMMARY Our subsurface exploration indicates the site is underlain by medium dense to dense sand FILL and firm to very stiff consistency clay FILL materials over generally firm to hard consistency and medium dense to very dense natural terrace soils. Ground water was encountered in three of the borings that were drilled adjacent to existing culverts. This site is generally considered suitable for construction of the proposed intersection improvements. However, the borings indicated the presence of loose density sands (i.e. soils with Standard Penetration Test N values of 5 or less) to depths of about 2 to 4 ft below the existing ground surface in four of the 19 borings. These soils may not be suitable for support of the proposed fill, pavement or minor structures and may need to be undercut and replaced with compacted structural fill. The QA Engineer should evaluate actual undercut depths during construction. Ground water was encountered within a few feet of the invert grades of the existing culverts. These culverts will be replaced with larger diameter pipes that will bear at deeper elevations. Accordingly, water should be anticipated within the culvert excavations. This executive summary is provided solely for purposes of overview. Any party that relies on this report must read the full report. This executive summary omits several details, any one of which could be very important to the proper application of the report.
Project 09130227 / December 2, 2011 Schnabel Engineering Consultants, Inc.
TABLE OF CONTENTS
1 INTRODUCTION .............................................................................................................. 1-1
1.1 Scope of Services ............................................................................................... 1-1 1.2 Site Description ................................................................................................... 1-1 1.3 Proposed Construction ....................................................................................... 1-1
2 DATA COLLECTION AND ANALYSIS ........................................................................... 2-1
2.1 Geology ............................................................................................................... 2-1 2.2 Data Collection Techniques ................................................................................ 2-1 2.3 Generalized Subsurface Stratigraphy ................................................................. 2-1 2.4 Soil Laboratory Testing ....................................................................................... 2-2 2.5 Ground Water ...................................................................................................... 2-2
3 GEOTECHNICAL RECOMMENDATIONS...................................................................... 3-1
3.1 Earthwork and Grading ....................................................................................... 3-1 3.2 Fill Settlement ..................................................................................................... 3-3 3.3 Culvert ................................................................................................................. 3-3 3.4 Culvert Bedding Material ..................................................................................... 3-4 3.5 Unsuitable Materials ........................................................................................... 3-4 3.6 Pavements .......................................................................................................... 3-4
4 CONSTRUCTION CONSIDERATIONS .......................................................................... 4-1
4.1 Earthwork ............................................................................................................ 4-1
5 LIMITATIONS .................................................................................................................. 5-1
Appendices: Appendix A: Subsurface Exploration Data Appendix B: Soil Laboratory Test Results
Appendix C: Calculations
Project 09130227 / December 2, 2011 Schnabel Engineering Consultants, Inc.
1 INTRODUCTION
1.1 Scope of Services
The objective of this study is to evaluate the subsurface conditions and to provide recommendations regarding the design of earthwork, pavement and minor structures for this project. The scope of this study is as defined in our submittal and authorized in the notice-to-proceed letter from Volkert & Associates, Inc. dated November 20, 2009 and confirmation email dated May 13, 2010. Our services included subsurface exploration, field engineering, soil laboratory testing and development of geotechnical engineering recommendations.
1.2 Site Description
The project site will include about 0.26 mile along Huguenot Trail (Rte 711) west of Pleasants Road (Rte 616) and 0.21 mile along Huguenot Trail east of Pleasants Road. The project site will also extend about 0.06 mile north along Pleasants Road. Project Stations increase to the east along Huguenot Trail and to the north along Pleasants Road. Along Huguenot Trail, the west end of the site is at about El 270. Grades along the alignment increase to about El 285 at the intersection with Pleasants Road, then dip to about El 276 and rise to about El 280 at the east end of the project. Grades along Pleasants Road decrease from about El 285 at the intersection to about El 280 at the north end of the project. The site is generally open and grassy with shallow ditches on both sides of the roadways. Two culverts extend below Huguenot Trail at about Stations 14+50 and 26+50. These culverts vary from 15 to 18 inches in diameter, respectively. We obtained the project and site information from the electronic plans by Volkert & Associates, Inc. and through our site visits.
1.3 Proposed Construction
The project will include shifting the alignment of Pleasants Road to intersect Huguenot Trail at a right angle, adding left and right turn lanes on Huguenot Trail and improving the vertical alignment of Huguenot Trail to achieve the proper intersection site distance. The project will extend about 2,000 ft along Huguenot Trail and 450 ft along Pleasants Road. Along Huguenot Trail, Station 10+00 will be at the west end of the project, the intersection with Pleasants Road will move from about Station 22+91 to Station 22+00, and Station 30+00 will be at the east end of the project. Along Pleasants Road, the intersection with Huguenot Trail is at Station 50+00, and the north end of the project will be at about Station 54+55. The pavement will be replaced from about Station 18+00 to Station 26+50 along Huguenot Trail and from the intersection to Station 53+53 along Pleasants Road. The existing pavement between the new pavement sections and the ends of the project will be resurfaced. Additionally, new shoulders will be constructed along both sides of Huguenot Trail and Pleasants Road to the project limits. A
Project 09130227 / December 2, 2011 1-1 Schnabel Engineering Consultants, Inc.
Project 09130227 / December 2, 2011 1-2 Schnabel Engineering Consultants, Inc.
new right turn lane will be constructed from westbound Huguenot Trail to Pleasants Road and a new left turn lane will be constructed from eastbound Huguenot Trail to Pleasants Road. The existing 18 inch culvert at Station 14+50 will be replaced with a 48 inch diameter culvert, and the existing 15 inch culvert at Station 26+50 will be replaced with a 24 inch culvert. We understand the new culverts will be concrete. The high point in the current alignment of Huguenot Trail is in the vicinity of the new intersection location. This area will be cut up to about 5 ft, vertically, to increase sight distance. The maximum cut will be between about Stations 21+00 and 22+00, and taper to zero at about Station 18+00 to the west and Station 24+50 to the east. The existing grades adjacent to the road are generally about 1 ft to 3 ft higher than the pavement in this area, so cuts up to 8 ft deep are anticipated. About 1 to 2 ft of fill, as measured along the proposed Huguenot Trail construction baseline, will be placed to the east and west of the cut area. There are drainage swales that cross Huguenot Trail at about Stations 14+50 and 26+50, and the ground surface is generally about 2 to 3 ft below the existing pavement level. Up to about 5 ft of fill will be needed in these areas. Huguenot Trail will include two 12 ft wide travel lanes, but will be wider near the intersection where the turn lanes will be added. The proposed shoulders will be about 8 ft wide. Pleasants Road will be about 24 ft wide with rounded corners at the intersection. According to the VDOT Inter-departmental Memorandum dated March 10, 2009, the average daily traffic counts in 2009 for Huguenot Trail west and east of the intersection with Pleasants Road were 2,425 vpd (with 4% trucks) and 2,976 vpd (with 1% trucks), respectively. The average daily traffic count in 2009 for Pleasants Road was about 1,491 vpd (with 5% trucks). The growth rate was 2.4% for Huguenot Trail and 0.5% for Pleasants Road. There is a 50/50 directional split and the design year is 2035. This memo is included in Appendix C for reference. Please note that the directional splits shown in the memo refer to the peak hourly traffic counts. The 50/50 split applies to the average daily traffic counts. We obtained the site information from the electronic site plan provided to us by Volkert & Associates, Inc. and through our site visits. Traffic data was also provided by Volkert & Associates, Inc.
2 DATA COLLECTION AND ANALYSIS
2.1 Geology
We reviewed existing geologic data and information in our files. Based on this review, the geologic stratigraphy consists of upland terrace deposits of Pliocene geologic age or older. The terrace deposits are alluvial soils that typically consist of a mixture of clay, silt, sand and gravel. These soils typically exhibit moderate strength and compressibility.
2.2 Data Collection Techniques
Ayers and Ayers of Powhatan, Virginia drilled nineteen borings at this site under our observation. Specific observations, remarks and logs for the borings, classification criteria and sampling protocols are included in Appendix A. Approximate boring locations are shown on Figures A1, A2 and A3 in Appendix A. Standard Penetration Tests (SPTs) were performed in the borings according to ASTM D-1586. SPT samples will be retained up to 45 days beyond the issuance of our final report for this project, then provided to the VDOT Richmond District for long term storage, if desired. We will contact Richmond District Materials to coordinate delivery.
2.3 Generalized Subsurface Stratigraphy
We have characterized the following generalized subsurface soil stratigraphy based on the boring data presented in Appendix A:
Table 1: General Subsurface Strata Stratum/ Geology Stratum Depth (ft) Generalized Stratum Description
Stratum A/ Fill
From the ground surface to depths of about 2 to 4 ft in seven of the borings.
Lean clay, clayey sand and silty sand FILL, contains crushed stone, roots and gravel, generally firm to very stiff consistency and medium dense to dense.
Stratum B/ Terrace
Below Stratum A and inter-layered with Stratum C to depths of about 2 to 12 ft in 16 of the borings.
FAT CLAY (CH), ELASTIC SILT (MH) and LEAN CLAY (CL), contains varying amounts of sand and gravel, generally firm to hard consistency.
Stratum C/ Terrace
Below and inter-layered with Stratum B to the maximum depth of exploration, about 10 to 20 ft, in 15 of the borings.
CLAYEY SAND (SC), SILTY SAND (SM), CLAYEY GRAVEL (GC) and SILTY GRAVEL (GM), generally medium dense to very dense. Varying amounts of gravel were encountered in the sandy soils.
About 0.3 to 0.5 ft of rootmat and topsoil, etc was encountered at the ground surface in the borings drilled beyond the existing pavement. Borings 10BH-007,10BH-013 and 10BH-015 were drilled in Huguenot Trail, and Boring 10BH-018 was drilled in Pleasants Road. The Huguenot
Project 09130227 / December 2, 2011 2-1 Schnabel Engineering Consultants, Inc.
Trail pavement was found to be about 7.8 inches to 10 inches thick, and the Pleasants Road pavement was about 5 inches thick. We did not observe any crushed stone base course under the pavement at any of these boring locations. The materials directly below the pavement consisted of existing fill classified as lean clay clayey sand. The group symbols indicated within the parentheses in the above table and on the logs in Appendix A represent the Unified Soil Classification System Group Symbols per ASTM D-2487 based on visual classification and limited laboratory testing of the samples. Criteria for visual classification of soil samples are included in Appendix A. Some variation can be expected between samples visually classified and samples classified in the laboratory.
2.4 Soil Laboratory Testing
Our geotechnical laboratory conducted tests on selected samples obtained in the borings. This testing aided in the classification of soils encountered in the subsurface exploration and provided data for use in the development of our geotechnical recommendations. Natural moisture content tests were performed on the SPT samples in accordance with ASTM D-2216. The results of the remaining laboratory tests are presented in Appendix B. Atterberg Limits and grain size analyses were also performed on selected SPT samples and bulk samples in accordance with ASTM D-4318 and ASTM D-422, respectively, to aid in the classification of soils encountered in the borings. The results of these tests are shown in Appendix B. The results of the testing performed on the bulk samples, including moisture content tests, are in the Summary of Laboratory Tests in Appendix B. These test results are not shown on the boring logs to avoid confusion with test results on jar samples that are shown on the logs. California bearing ratio (CBR) and moisture-density relationship tests were performed on the composite bulk samples in accordance with VTM-8, and VTM-1, respectively. CBR tests were conducted on bulk samples of silty clayey SAND, sandy elastic SILT and clayey SAND from Strata A, B and C, respectively. Laboratory CBR values between 11.6 and 26.8 with swell values of 0 to 0.3 percent were obtained for these soils. The maximum dry density and optimum moisture content for compaction of the coarse-grained soils tested (Strata A and C) varied from about 125.7pcf to 114.4 pcf and 9.4 percent to 14.4 percent, respectively. Natural moisture content values for the existing sandy materials from the same strata varied from about 8.3 to 25.4 percent. The maximum dry density and optimum moisture content for compaction of the fine-grained soils tested (Stratum B) varied from about 99.8 pcf to 102.7 pcf and 19.8 percent to 21.2 percent, respectively. Natural moisture content values for the existing fine-grained materials from the same stratum generally varied from about 14.4 to 30.2 percent.
2.5 Ground Water
Water level readings obtained in the borings during and after completion are noted on the logs. We observed ground water during drilling at depths of about 2 ft to 4 ft below the ground surface, approximate El 260.0 to 273.5, in three borings near the existing culverts, Borings 10BH-004,
Project 09130227 / December 2, 2011 2-2 Schnabel Engineering Consultants, Inc.
Project 09130227 / December 2, 2011 2-3 Schnabel Engineering Consultants, Inc.
10BH-005 and 10BH-013. Ground water was not encountered in the remainder of the borings, and the borings were backfilled for safety upon completion. A water observation well was installed in Boring 10BH-004, near the south end of the culvert under Huguenot Trail. We recorded a ground water level in the well at a depth of about 1.2 ft, El 260.8, about 24 days after the well was installed. The water levels recorded on the logs likely represent perched ground water in the areas of the culverts. Perched ground water can occur when lower permeability materials retard surface water infiltration. Perched ground water could occur at other locations on site and at higher elevations than those recorded on the logs. Fluctuations in the hydrostatic water table should be anticipated depending on variations in precipitation, surface runoff, evaporation, leaking utilities, pumping, stream levels and similar factors.
3 GEOTECHNICAL RECOMMENDATIONS
3.1 Earthwork and Grading
The earthwork and grading will consist of cutting up to 5 ft below the existing grades at the intersection and placement of up to about 5 ft of fill to the east and west of the intersection. Applicable VDOT specifications and standards for earthwork on this project include the 2007 VDOT Road and Bridge Specifications including all revisions, and the current revisions for each section of the VDOT Road and Bridge Standards.
3.1.1 Fill and Pavement Subgrade Preparation
Fill subgrades should be stripped of vegetation, topsoil and organic matter according to the 2007 VDOT Road and Bridge Specifications and revisions. Fill subgrades steeper than 4H:1V should be benched. Topsoil and organic matter should be removed before benches are cut to reduce the amount of deleterious material within the soils cut from the benches. Conditions for using the material cut from the benches as compacted structural fill are discussed in Section 3.1.2 below and include limiting the amount of organic material. Clearing and grubbing should be performed according to Section 301 of the VDOT Road and Bridge Specifications. Stumps, roots, topsoil, other perishable material and nonperishable objects should be removed from fill subgrades less than 5 feet below the pavement subgrade level and should not be used as fill. We expect the fill subgrade level will be within about 5 ft of the proposed pavement subgrade level over most, if not all, of the project site. Our subsurface exploration indicated forest litter, rootmat and/or topsoil were encountered to depths of about 0.3 ft to 0.5 ft below the ground surface. The topsoil depths at each of the boring locations are shown on the logs in Appendix A. Stripping typically results in some disturbance and contamination of near-surface soils, particularly during periods of wet weather. Accordingly, we recommend considering a topsoil stripping depth of about 0.5 ft for the site. The soils of Strata A, B and C are expected in the proposed fill and pavement subgrades. Soft or loose soils (i.e. soils with SPT N values of 5 or less) were encountered in the areas of the borings included in Table 2. Accordingly, we anticipate undercut could be required in these areas before placement of the new fill or construction of the pavement. Soft or loose soils were generally not encountered at shallow depths in the remaining borings.
Table 2: Estimated Undercut Depths
Boring Number
Roadway Location
Approx. Station
Approx. Ground Surface Elev. (ft)
Est. Lowest Elev. of
Soft/Loose Soil (ft)
Approx. Undercut Depth (ft)
Condition
10BH-003 Huguenot 14+40 265 263 2 Fill Subgrade
10BH-004 Huguenot 14+60 262 258 4 Fill Subgrade
10BH-019 Pleasants 54+00 280 278 2 Pave Subgrade
Project 09130227 / December 2, 2011 3-1 Schnabel Engineering Consultants, Inc.
In addition to the soft or loose soils indicated in Table 2, loose sand fill of Stratum A with an SPT N value of 5 was encountered between depths of about 4 ft and 6.5 ft in Boring 10BH-013. This loose sand is overlain by about 4 ft of dense (N-value greater than 30) clayey and silty sand fill. It is possible that some undercutting of soft or loose embankment fill could be required at this location where the embankment will be widened. The natural soils below the fill at this location consisted of stiff consistency clay. The project QA Engineer should evaluate the suitability of the actual subgrades in the field before any undercut is performed. The undercut volume can be conservatively estimated by considering the unsuitable materials extend the full width of the pavement and to adjacent borings where unsuitable materials were not encountered. Depending on the time of year, the soft or loose materials included in Table 2 may be drier and not need to be undercut, or the near surface soils on this site may be wetter, and additional material may need to be removed. Accordingly, fill and pavement subgrades should be proofrolled with a loaded dump truck to evaluate their suitability to support the new fill or pavement at the time of construction. Areas that exhibit excessive pumping or rutting should be undercut and replaced with compacted structural fill as described in Section 303 of the 2007 VDOT Road and Bridge Specifications. Undercut volumes should be evaluated by cross sectioning as described in Section 303.06(a)3 of the 2007 VDOT Road and Bridge Specifications. Subgrades to receive compacted structural fill should be scarified to a depth of 6 inches and compacted according to Section 305.03(a)1 of the 2007 VDOT Road and Bridge Specifications. The upper 6 inches of pavement subgrades should be compacted to at least 100 percent of the maximum dry density per VTM-1, Standard Proctor. Materials considered unsuitable for support of the proposed fill should be undercut and replaced with new compacted structural fill or crushed stone. Materials that are considered unsuitable due to high moisture content but would otherwise be considered suitable, may be moisture conditioned and reused. If stripping and earthwork operations are performed during an extended period of warm, dry weather, drying of wet materials will be easier. The use of these materials as compacted structural fill will depend on the soil moisture content at the time they are used as fill and the Contractor's ability to limit contamination of these materials with organic matter during stripping and undercutting. As an alternative to removing and replacing any unsuitable materials, fine-grained soils could be chemically stabilized using lime. If this option is selected, we should be provided with a sample of the product to be used, and we can develop a laboratory testing program to evaluate the ratio of lime to soil material.
3.1.2 Compacted Structural Fill
Compacted structural fill should consist of material classifying MH, CL, ML, SC, SM, SP, SW, GC, GM, GP, or GW per ASTM D-2487 with at least 30% coarse-grained materials retained on a No. 200 sieve. Most of the non-organic, on-site soils are expected to meet this criterion. If off-site borrow materials are needed, they should classify SC, SM, SP, SW, GC, GM, GP or GW per ASTM D-2487.
Project 09130227 / December 2, 2011 3-2 Schnabel Engineering Consultants, Inc.
Our pavement evaluation is based on a design CBR value of 8.9. Accordingly, borrow material placed within 3 ft, vertically, of the pavement subgrade level should have a CBR value of at least 8.9. Embankment fills should be constructed according to the 2007 VDOT Road and Bridge Specifications, Section 303.04(h). The material should meet the requirements for maximum particle size within the fill. Compacted structural fill should be placed in maximum 8-inch thick horizontal, loose lifts and should be compacted to at least 95 percent of maximum dry density per VTM-1, Standard Proctor. The moisture content of the fill material should be less than 2 percent above the optimum moisture content for the material used. We expect most of the materials excavated during construction will be considered suitable for use as fill. However, successful reuse of these materials will depend on the natural moisture content of soils encountered during excavation. We anticipate that scarifying and drying of portions of the on-site soils will be needed before the recommended compaction can be achieved. Drying of these soils will likely result in some delay, and drying might not be possible during late fall, winter and early spring. Accordingly, we recommend that the earthwork be performed during the warmer, drier times of the year from about May to October.
3.2 Fill Settlement
Up to about 5 ft of fill is proposed for this site. We evaluated the settlement of the proposed fill using the soil properties estimated based on the results of the Standard Penetration Testing, the classification of the materials and the computer program FoSSA (Foundation Stress and Settlement Analysis) Version 2.0, © 2003-2007. We have also considered that the fill material will be the near-surface materials excavated during grading activities near the intersection. We evaluated the section where the fill is expected to be the thickest, about 5 ft thick at Station 16+00. The thickness of the fill is relatively constant (about 1 ft thick) over the width of the existing pavement and thicker under the proposed shoulder. The FoSSA output shows about 0.01 ft of settlement in the Initial and Final Elevations columns, but not in the Total Settlement column. This is because the program is rounding values that are less than 0.01 ft, and the units cannot be changed to inches. Accordingly, we estimate magnitude of the total settlement is expected to be less than about ½ inch, and differential settlement along the south side of the pavement is expected to be equal to the total settlement value. The output from our analyses is included in Appendix C.
3.3 Culvert
The proposed culvert pipes should be constructed on subgrade materials prepared and evaluated as described in Section 3.2.1. The bedding material and backfill material should be constructed as described in Section 302 of the 2007 VDOT Road and Bridge Specifications, and in Sections 3.2.2 and 3.2.3 of this report, respectively. Backfill and bedding material should be placed according to page 107.04 of the VDOT Road and Bridge Standards.
Project 09130227 / December 2, 2011 3-3 Schnabel Engineering Consultants, Inc.
3.4 Culvert Bedding Material
In accordance with VDOT Standard Specification 302.03(a)2.b, bedding material for the culverts should consist of VDOT No. 25 or 26 aggregate unless standing or running water is present in the excavation. If standing or running water is present, the pipe bedding material shall be VDOT No. 57 crushed stone below a 4 inch cap of VDOT No. 25 or 26 aggregate. The invert of the existing 18 inch diameter culvert pipe is at about El 263 to El 264. Ground water was encountered at about El 260.8 to El 261 in Borings 10BH-004 and 10BH-005, and the culvert typically conducts a small creek. Accordingly, water should be anticipated within the culvert excavation. The bedding material shall be uniformly compacted and shall be at least 4 inches in depth for culverts sections and 6 inches deep under the headwalls. Furthermore, the bedding material shall contact at least 10 percent of the overall height of the pipe. The bedding material should meet the requirements outlined in VDOT Standard Specification 302.03(a)2.b. Drainage geotextile in accordance with VDOT Standard Specification 245.03 (c) should be installed to limit the migration of fines from the foundation materials into the bedding material.
3.5 Unsuitable Materials
Materials that classify as OH, OL and CH, in accordance with the Unified Soil Classification System (USCS), materials classifying as MH, CL and ML with less than 30% retained on a No. 200 sieve, materials that contain more than 2 percent by weight organic matter, materials that exhibit a California Bearing Ratio (CBR) value less than 8.9 per VTM-8 or a CBR swell value greater than 2 percent as determined by the same test method are considered unsuitable. Saturated or very dry and/or loose or very soft coarse- and fine-grained soils that exhibit excessive pumping or rutting under the weight of construction equipment are also considered unsuitable unless they can be moisture conditioned through either mechanical or chemical means to an acceptable moisture content that allows adequate compaction as described in Section 3.2.2 above. Topsoil, peat, coal and carbonaceous shale are also unsuitable. Materials considered to be unsuitable should not be used as fill. If unsuitable materials are encountered in cut areas to a depth of at least 3 ft below pavement subgrades, within 2 ft beneath the bedding of minor structures or laterally within 2 ft beyond the outside edge of the pavement shoulders or bedding limits of the minor structures, they should be removed or modified in place to provide adequate support for the proposed fill, pavement or minor structures.
3.6 Pavements
Pavement subgrades should be prepared as discussed in Section 3.1.1. Compacted structural fill for pavement support should be placed and compacted as described in Section 3.1.2. Dense-graded aggregate placed as pavement base course should be compacted to at least 100 percent of maximum dry density per VTM-1, Standard Proctor. Dense-graded aggregate should be placed in maximum 8-inch thick loose lifts. The proposed pavement sections were developed in general accordance with the 1993 AASHTO
Pavement Design Procedure. We considered a subgrade resilient modulus, Mr, of 13,350 psi,
Project 09130227 / December 2, 2011 3-4 Schnabel Engineering Consultants, Inc.
Project 09130227 / December 2, 2011 3-5 Schnabel Engineering Consultants, Inc.
based on a design CBR value of 8.9. This value represents 2/3 of the average laboratory CBR
values after discarding the high and low CBR values.
The following pavement sections are recommended for the travel lanes and shoulders of the two
roads:
Huguenot Trail (Route 711)
Asphalt Concrete Surface Course, VDOT SM-12.5A = 1.5 inches
Asphalt Concrete Base Course, VDOT BM-25.0 = 4.0 inches
Dense-Graded Aggregate Base Course, VDOT 21B = 8.0 inches
Pleasants Road (Route 616)
Asphalt Concrete Surface Course, VDOT SM-12.5A = 1.5 inches
Asphalt Concrete Base Course, VDOT BM-25.0 = 3.0 inches
Dense-Graded Aggregate Subbase Course, VDOT 21B = 6.0 inches
The intersection should be paved according to the pavement section recommended for Huguenot
Trail. Our pavement design calculations are included in Appendix C. The VDOT memorandum
including the traffic data used in our calculations is also included in Appendix C.
We understand maintenance of traffic pavement may be required to facilitate the proposed
construction. We have considered the MOT traffic section will be in use for less than one year.
We recommend using the following MOT sections:
Huguenot Trail - MOT
Asphalt Concrete Surface Course, VDOT IM-19.0A = 2.0 inches
Dense-Graded Aggregate Base Course, VDOT 21B = 6.0 inches
Pleasants Road - MOT
Asphalt Concrete Surface Course, VDOT IM-19.0A = 2.0 inches
Dense-Graded Aggregate Base Course, VDOT 21B = 6.0 inches
Project 09130227 / December 2, 2011 3-6 Schnabel Engineering Consultants, Inc.
We used the computer program DARWin 3.1 by AASHTOWare to perform our design calculations. We have evaluated the pavement sections and the proposed MOT pavement considering the parameters summarized in Table 3 below and the traffic volumes developed by VDOT. The outputs of these analyses are included in Appendix E.
Table 3: Pavement Design Parameters
Parameter Huguenot Tr Pleasants Rd Huguenot Tr MOT
Pleasants Rd MOT
Classification High Volume Secondary
Farm to Market Secondary
High Volume Secondary
Farm to Market Secondary
2009 AADT (vpd) 2425 W, 2976 E 1491 -- -- 2035 AADT (vpd) 4500 W, 5500 E 1700 -- -- 2015 AADT (vpd) -- -- 2730 W, 3350 E 1529 Analysis Period 20 years 20 years 1 year 1 year Growth Rate 2.4% 0.5% 2.4% 0.5% Soil Resilient Modulus 13,350 psi 13,350 psi 13,350 psi 13,350 psi Initial Serviceability 4.2 4.0 4.2 4.0 Terminal Serviceability 2.8 2.5 2.8 2.5 Standard Deviation 0.49 0.49 0.49 0.49 Reliability 85 75 85 75 Number of Lanes in DD 1 1 1 1 Lane Dist. Factor 100 100 100 100 Directional Split 50/50 50/50 50/50 50/50 Percent Trucks 4% W, 1% E 5% 4% W, 1% E 5% ESAL Factor for Trucks 1.05 1.05 1.05 1.05 DD=Design Direction Our analysis considers proper grading to provide runoff from the pavement surface and beyond the limits of paved areas will be provided. Adequate control of surface drainage will be a very important consideration for the overall development related to the pavement design. The area surrounding pavements should be graded to direct surface water away from paved areas. Since traffic data indicates more than 1,000 vehicles per day on Huguenot Trail and Pleasants Road, UD-4 pavement drains should be provided along both roads. Pavement subdrains should be daylighted or connected to a storm sewer. Utility excavations within pavement areas should be backfilled with compacted structural fill.
4 CONSTRUCTION CONSIDERATIONS
4.1 Earthwork
The on-site soils are susceptible to moisture changes, will be easily disturbed and may be difficult to compact under wet weather conditions. Drying and reworking of the soils are likely to be difficult during wetter winter months. We recommend that the earthwork phases of this project be performed during the warmer, drier times of the year to limit the potential for disturbance of on-site soils. Traffic on stripped or undercut subgrades should be limited to reduce disturbance of underlying soils. Site drainage should be provided to maintain subgrades free of water and to avoid saturation and disturbance of the subgrade soils before placing compacted structural fill, pavement base course or bedding material. This will be important during all phases of the construction work. Weakened subgrade soils should be recompacted, or removed and replaced as recommended by the QA Engineer. Subgrade soils in the area of the culverts under Huguenot Trail are expected to be wet and easily disturbed. Additional bedding material may be needed as a working platform to set the pipes and place the backfill. The QA Engineer should make recommendations for working platforms based on observation of subgrade conditions in the field. Depending on the volume of water, temporary dewatering such as trenching and/or pumping from sumps will likely be needed to control the surface and/or ground water. Care should be exercised during excavation for the culvert pipes so that as little disturbance as possible occurs at the foundation level. Loose or soft soils should be carefully cleaned from the bottom of the excavation before placing bedding material. These subgrades should be observed during construction by the project QA Engineer to evaluate whether subgrade soils are as recommended in this report.
Project 09130227 / December 2, 2011 4-1 Schnabel Engineering Consultants, Inc.
5 LIMITATIONS
The analyses and recommendations submitted in this report are based on the information revealed by our exploration. An attempt has been made to provide for normal contingencies, but the possibility remains that unexpected conditions might be encountered during construction. This report has been prepared to aid in the evaluation of this site and to assist in the design of the project. It is intended for use concerning this specific project. Our recommendations are based on information on the site and proposed construction as described in Section 1. Substantial changes in traffic, locations or grades should be brought to our attention so we can modify our recommendations as needed. We have endeavored to complete the services identified herein in a manner consistent with that level of care and skill ordinarily exercised by members of the profession currently practicing in the same locality and under similar conditions as this project. No other representation, express or implied, is included or intended, and no warranty or guarantee is included or intended in this report, or any other instrument of service.
Project 09130227 / December 2, 2011 5-1 Schnabel Engineering Consultants, Inc.
APPENDIX A
SUBSURFACE EXPLORATION DATA
Subsurface Exploration Procedures General Notes for Subsurface Exploration Logs
Identification of Soil Boring Logs, 10BH-001 through 10BH-019
Location Plan, Figures A1, A2 and A3
Project 09130227 / December 2, 2011 Schnabel Engineering Consultants, Inc.
SUBSURFACE EXPLORATION PROCEDURES Boring Procedures Drillers advanced the borings using hollow-stem augers. A plug device was used to block off the center opening in the hollow-stem auger to prevent cuttings from entering the augers during drilling. At the designated depth, the drillers removed the plug and performed the Standard Penetration Test. Water or drilling fluid was not introduced into the boring using this procedure, unless indicated on individual logs. Water level data are indicated on the logs. Standard Penetration Test Results The numbers in the Sampling Data column of the boring logs represent Standard Penetration Test (SPT) results. Each number represents the blows needed to drive a 2-inch O.D., 1-3/8 inch I.D. split-spoon sampler 6 inches, using a 140-pound hammer falling 30 inches. The sampler is typically driven a total of 18 or 24 inches. The first 6 inches are considered a seating interval. The total of the number of blows for the second and third 6-inch intervals is the SPT “N value”. The Standard Penetration Test is conducted according to ASTM D-1586. Soil Classification Criteria The group symbols on the logs represent the Unified Soil Classification System Group Symbols (ASTM D-2487) based on visual observation and limited laboratory testing of the samples. Criteria for visual identification of soil samples are included in this appendix. Some variation can be expected between samples visually classified and samples classified in the laboratory. Pocket Penetrometer Results The values following “PP=” in the sampling data column of the logs represent pocket penetrometer readings. Pocket penetrometer readings provide an estimate of the unconfined compressive strength of fine-grained soils. Water Observation Wells A temporary water observation well was installed in Boring 10BH-004 by inserting a hand-slotted, 1¼-inch PVC pipe. The pipe was capped and the area surrounding the pipe was backfilled with cuttings from the boring. Boring Locations and Elevations Our personnel staked the borings using a sub-meter backpack Trimble GPS unit. Approximate boring locations are shown on Figure A1. Ground surface elevations at the boring locations were referenced in the field using a hand level to the existing edge of pavement grades shown on the profiles provided by Volkert & Associates, Inc. These locations and elevations should be considered no more accurate than the methods and plans used to obtain them.
Project 09130227 / December 2, 2011 Schnabel Engineering Consultants, Inc.
GENERAL NOTES FOR SUBSURFACE EXPLORATION LOGS
1. Numbers in sampling data column next to Standard Penetration Test (SPT) symbols indicate blows required to drive a 2-inch O.D., 1⅜-inch I.D. sampling spoon 6 inches using a 140 pound hammer falling 30 inches. The Standard Penetration Test (SPT) N value is the number of blows required to drive the sampler 12 inches, after a 6-inch seating interval. The Standard Penetration Test is performed in general accordance with ASTM D1586.
2. Visual classification of soil is in accordance with terminology set forth in “Identification of Soil.” The ASTM D2487 group symbols (e.g., CL) shown in the classification column are based on visual observations.
3. Estimated water levels indicated on the logs are only estimates from available data and may vary with precipitation, porosity of the soil, site topography, and other factors.
4. Refusal at the surface of rock, boulder, or other obstruction is defined as an SPT resistance of 100 blows for 2 inches or less of penetration.
5. The logs and related information depict subsurface conditions only at the specific locations and at the particular time when drilled or excavated. Soil conditions at other locations may differ from conditions occurring at these locations. Also, the passage of time may result in a change in the subsurface soil and water level conditions at the subsurface exploration location.
6. The stratification lines represent the approximate boundary between soil and rock types as obtained from the subsurface exploration. Some variation may also be expected vertically between samples taken. The soil profile, water level observations and penetration resistances presented on these logs have been made with reasonable care and accuracy and must be considered only an approximate representation of subsurface conditions to be encountered at the particular location.
7. Key to symbols and abbreviations:
S-1, SPT Sample No., Standard Penetration Test 5+10+1 Number of blows in each 6-inch increment UD-1, UNDIST Sample No., 2” or 3” Undisturbed Tube Sample Rec=24”, 100% Recovery in inches, Percent Recovery C-1, CORE Core No., Rock Core Run = 5.0 ft Run length in feet REC = 60", 100% Recovery in inches, Percent Recovery RQD = 60", 100% RQD in inches, Percent RQD MC Moisture Content PP Pocket Penetrometer Reading (tsf) FD Flame Ionization Detector Reading (ppm) PD Photoionization Detector Reading (ppm) GP Geostick Penetration Reading (inches) LL Liquid Limit PL Plastic Limit TPH Total Petroleum Hydrocarbons
IDENTIFICATION OF SOIL I. DEFINITION OF SOIL GROUP NAMES (ASTM D2487) SYMBOL GROUP NAME
Coarse-Grained Soils More than 50% retained on No. 200 sieve
Gravels – More than 50% of coarse fraction retained on No. 4 sieve Coarse, ¾” to 3” Fine, No. 4 to ¾”
Clean Gravels Less than 5% fines
GW WELL GRADED GRAVEL
GP POORLY GRADED GRAVEL
Gravels with fines More than 12% fines
GM SILTY GRAVEL GC CLAYEY GRAVEL
Sands – 50% or more of coarse Fraction passes No. 4 sieve Coarse, No. 10 to No. 4 Medium, No. 40 to No. 10 Fine, No. 200 to No. 40
Clean Sands Less than 5% fines
SW WELL GRADED SAND
SP POORLY GRADED SAND
Sands with fines More than 12% fines
SM SILTY SAND SC CLAYEY SAND
Fine-Grained Soils 50% or more passes the No. 200 sieve
Silts and Clays – Liquid Limit less than 50 Low to medium plasticity
Inorganic CL LEAN CLAY ML SILT
Organic OL ORGANIC CLAY ORGANIC SILT
Silts and Clays – Liquid Limit 50 or more Medium to high plasticity
Inorganic CH FAT CLAY MH ELASTIC SILT
Organic OH ORGANIC CLAY ORGANIC SILT
Highly Organic Soils Primarily organic matter, dark in color and organic odor PT PEAT
II. DEFINITION OF SOIL COMPONENT PROPORTIONS (ASTM D2487) Examples
Adjective Form
GRAVELLY SANDY
>30% to <50% coarse grained component in a fine-grained soil
GRAVELLY LEAN CLAY
CLAYEY SILTY
>12% to <50% fine grained component in a coarse-grained soil
SILTY SAND
“With” WITH GRAVEL WITH SAND
>15% to <30% coarse grained component in a fine-grained soil
FAT CLAY WITH GRAVEL
WITH GRAVEL WITH SAND
>15% to <50% coarse grained component in a coarse-grained soil
POORLY GRADED GRAVEL WITH SAND
WITH SILT WITH CLAY
>5% to <12% fine grained component in a coarse-grained soil
POORLY GRADED SAND WITH SILT
III. GLOSSARY OF MISCELLANEOUS TERMS
SYMBOLS ............................ Unified Soil Classification Symbols are shown above as group symbols. A dual symbol “-“ indicates the soil belongs to two groups. A borderline symbol “/” indicates the soil belongs to two possible groups.
FILL ........................................ Man-made deposit containing soil, rock and often foreign matter. PROBABLE FILL................... Soils which contain no visually detected foreign matter but which are suspect with regard
to origin. DISINTEGRATED ROCK (DR) ........................................
Residual materials with a standard penetration resistance (SPT) between 60 blows per foot and refusal. Refusal is defined as a SPT of 100 blows for 2” or less penetration.
PARTIALLY WEATHERED ROCK (PWR) .........................
Residual materials with a standard penetration resistance (SPT) between 100 blows per foot and refusal. Refusal is defined as a SPT of 100 blows for 2” or less penetration.
BOULDERS & COBBLES ..... Boulders are considered rounded pieces of rock larger than 12 inches, while cobbles range from 3 to 12 inch size.
LENSES ................................. 0 to ½ inch seam within a material in a test pit. LAYERS ................................. ½ to 12 inch seam within a material in a test pit. POCKET ................................ Discontinuous body within a material in a test pit. MOISTURE CONDITIONS ..... Wet, moist or dry to indicate visual appearance of specimen. COLOR .................................. Overall color, with modifiers such as light to dark or variation in coloration.
15.7
15.0
12.0
12.7
15.9
0.0 / 269.06-INCHES FOREST LITTER, ROOTMAT AND TOPSOILTOPS0.5 / 268.5Brown, sandy LEAN CLAY, firm, moist [TERRACE] CL2.0 / 267.0Brown, fine to coarse clayey SAND, medium dense, moist SCSAME, brown and gray, trace gravel below 3 ft
SAME, dense below 7 ft
Bottom of Hole @ 259.0 ft Elevation
PAGE 1 OF 1
10BH-001
10BH-001
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 23LLONGITUDE: 77.839366° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)Not Encountered During Drilling
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
268
266
264
262
260
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
STATION: 10+27LATITUDE: 37.603822° NSURFACE ELEVATION: 269.0 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadPAVEMENT
Date(s) Drilled: 05/25/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
3
4
7
10
9
3
9
14
13
16
4
9
12
17
21
0.5
1.5
2
3.5
4
5.5
7
8.5
10
22.5
21.7
24.6
19.0
21.4
0.0 / 267.05-INCHES ROOTMAT AND TOPSOIL TOPS0.4 / 266.6Brown, sandy lean clay FILL, contains roots, firm, moist [FILL]FL2.0 / 265.0Yellow-brown and gray, LEAN CLAY with sand, stiff, moist[TERRACE] CL
SAME, trace gravel, hard below 4 ft
6.5 / 260.5Brown and gray, FAT CLAY, trace gravel, hard, moist CH
SAME, very stiff below 8.5 ft
Bottom of Hole @ 257.0 ft Elevation
PAGE 1 OF 1
10BH-002
10BH-002
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 26RLONGITUDE: 77.838690° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)Not Encountered During Drilling
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
266
264
262
260
258
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
STATION: 12+46LATITUDE: 37.603532° NSURFACE ELEVATION: 267.0 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadPAVEMENT
Date(s) Drilled: 05/25/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
3
4
4
14
8
3
5
12
15
12
3
9
28
20
15
0.4
1.5
2
3.5
4
5.5
7
8.5
10
48.3
20.2
14.4
15.8
18.9
40 23
0.0 / 265.06-INCHES FOREST LITTER, ROOTMAT AND TOPSOILTOPS0.5 / 264.5Brown, FAT CLAY, contains roots, soft, moist [TERRACE] CH2.0 / 263.0Brown and gray, LEAN CLAY with sand, contains roots, firm,moist CL
4.0 / 261.0Gray-brown, fine to medium clayey SAND, trace gravel,medium dense, moist SC
6.5 / 258.5Gray and light brown, sandy LEAN CLAY with gravel, very stiff,moist CL
8.5 / 256.5Gray and orange-brown, fine to medium clayey SAND, mediumdense, moist SC
Bottom of Hole @ 255.0 ft Elevation
PAGE 1 OF 1
10BH-003
10BH-003
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 30LLONGITUDE: 77.837990° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)Not Encountered During Drilling
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
264
262
260
258
256
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
STATION: 14+41LATITUDE: 37.603529° NSURFACE ELEVATION: 265.0 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadCULVERT
Date(s) Drilled: 05/25/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
1
2
5
11
7
2
3
6
10
8
2
5
8
12
12
0.5
1.5
2
3.5
4
5.5
7
8.5
10
29.8
22.2
16.0
13.1
15.7
21.5
46 25
0.0 / 262.06-INCHES ROOTMAT AND TOPSOIL TOPS0.5 / 261.5Brown, lean clay with sand FILL, contains roots, firm, moist[TERRACE] FL2.0 / 260.0Brown and gray, fine to coarse clayey SAND, trace gravel,loose, wet SC
SAME, dense, moist below 4 ft
SAME, brown-gray, medium dense, wet below 7 ft
SAME, gray and light orange-brown, moist below 9 ft
SAME, light brown-gray, wet below 12.5 ft
Bottom of Hole @ 247.0 ft Elevation
PAGE 1 OF 1
10BH-004
10BH-004
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 43RLONGITUDE: 77.837994° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck). 1 1/4" PVC Water Observation Well (W.O.W.) installed to 15 ft uponcompletion.
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)FIRST ENCOUNTERED AT 2.0 ft DEPTH
STABILIZED AT 1.2 ft AFTER 72 HOURS
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
260
255
250
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
12
14
STATION: 14+64LATITUDE: 37.603262° NSURFACE ELEVATION: 262.0 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadCULVERT
Date(s) Drilled: 05/25/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
2
2
4
5
9
4
2
2
13
6
9
5
4
3
26
7
10
6
0.5
1.5
2
3.5
4
5.5
7
8.5
9
10.5
12.5
13.5
14
15.8
25.0
9.0
13.6
11.4
10.6
0.0 / 263.06-INCHES ROOTMAT AND TOPSOIL TOPS0.5 / 262.5Orange-brown, fine to coarse clayey sand FILL, containsgravel, loose, moist [FILL] FL2.0 / 261.0Light brown and gray, clayey GRAVEL, dense, wet[TERRACE] GC
SAME, moist below 4 ft
13.0 / 250.0Yellow-brown, silty GRAVEL, wet GMSAME, very dense below 18.5 ft
Bottom of Hole @ 248.6 ft Elevation
PAGE 1 OF 1
10BH-005
10BH-005
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 39RLONGITUDE: 77.837551° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)FIRST ENCOUNTERED AT 2.0 ft DEPTH
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
260
255
250
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
12
14
STATION: 16+13LATITUDE: 37.603249° NSURFACE ELEVATION: 263.0 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadPAVEMENT
Date(s) Drilled: 05/25/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
3
3
18
15
9
30
4
3
22
16
17
70/5
5
30
24
19
20
0.5
1
1.5
2
3.5
4
5.5
7
8.5
9
10.5
13.5
14.4
18.1
24.2
24.3
25.1
20.7
18.6
74 34
0.0 / 274.04-INCHES ROOTMAT AND TOPSOIL TOPS0.3 / 273.7Red-brown, sandy ELASTIC SILT, contains roots, stiff, moist[TERRACE] MH2.0 / 272.0Red-brown, ELASTIC SILT with sand, trace gravel, very stiff,moist MH
SAME, hard below 4 ft
6.5 / 267.5Red-brown and brown, sandy ELASTIC SILT with gravel, veryhard, moist MH
12.0 / 262.0Brown, fine to medium silty SAND with gravel, medium dense,moist SM
Bottom of Hole @ 259.0 ft Elevation
PAGE 1 OF 1
10BH-006
10BH-006
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 15LLONGITUDE: 77.836796° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)Not Encountered During Drilling
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
270
265
260
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
12
14
STATION: 18+01LATITUDE: 37.603250° NSURFACE ELEVATION: 274.0 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadPAVEMENT
Date(s) Drilled: 05/25/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
3
5
5
10
25
16
3
8
16
26
38
11
7
12
18
49
52
11
0.3
1.5
2
3.5
4
5.5
7
8.5
9
10.5
13.5
15
16.3
22.4
18.1
10.1
14.3
0.0 / 275.07 3/4" ASPHALT (2 pieces) ASPH0.6 / 274.4Gray, lean clay with sand FILL, very stiff, moist [FILL] FL
2.0 / 273.0Red-brown, fine to coarse clayey SAND with gravel, mediumdense, moist [TERRACE] SC
SAME, dense, trace gravel below 4 ft
SAME, light yellow-brown, very dense below 7 ft
SAME, light yellow-brown and light gray, very dense below 8.5 ft
Bottom of Hole @ 265.0 ft Elevation
PAGE 1 OF 1
10BH-007
10BH-007
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 2LLONGITUDE: 77.836622° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)Not Encountered During Drilling
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
274
272
270
268
266
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
STATION: 18+35LATITUDE: 37.603159° NSURFACE ELEVATION: 275.0 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadPAVEMENT
Date(s) Drilled: 05/24/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
19
4
11
16
23
9
4
15
24
18
7
9
17
30
14
1
1.5
2
2.5
3.5
4
5.5
7
8.5
10
14.9
18.6
13.4
13.2
16.3
16.0
0.0 / 282.0No Ground Cover0.01 / 281.99Red-brown, sandy LEAN CLAY, trace gravel, contains roots,stiff, moist [FILL] CL2.0 / 280.0Dark yellow-brown, silty GRAVEL with sand, dense, moist[TERRACE] GM
4.0 / 278.0Yellow-brown and red-brown, fine to coarse clayey SAND withgravel, very dense, moist SC
SAME, dense below 7 ft
SAME, very dnse below 9 ft
12.0 / 270.0Dark red-brown, fine to coarse clayey SAND, trace gravel,medium dense, moist SC
Bottom of Hole @ 267.0 ft Elevation
PAGE 1 OF 1
10BH-008
10BH-008
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 13RLONGITUDE: 77.836202° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)Not Encountered During Drilling
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
280
275
270
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
12
14
STATION: 18+25LATITUDE: 37.603007° NSURFACE ELEVATION: 282.0 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadPAVEMENT
Date(s) Drilled: 05/24/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
3
11
20
13
12
4
4
13
40
15
26
5
7
20
40/5
23
27
8
0.01
1.5
2
3.5
4
5.4
7
8.5
9
10.5
13.5
15
21.8
25.3
24.8
12.0
15.8
14.5
10.1
0.0 / 286.04-INCHES ROOTMAT AND TOPSOIL TOPS0.3 / 285.7Red-brown, ELASTIC SILT with sand, very stiff, moist[TERRACE] MH
SAME, very hard, trace gravel below 4 ft
6.5 / 279.5Orange-brown and red-brown, fine to medium clayey SANDwith gravel, very dense, moist SC
9.0 / 277.0Orange-brown and brown, fine to coarse clayey SAND, dense,moist SC
SAME, medium dense below 9 ft
17.0 / 269.0Light brown, fine to coarse silty SAND with gravel, trace gravel,medium dense, moist SM
Bottom of Hole @ 266.0 ft Elevation
PAGE 1 OF 1
10BH-009
10BH-009
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 26LLONGITUDE: 77.835656° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)Not Encountered During Drilling
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
285
280
275
270
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
12
14
16
18
20
STATION: 21+30LATITUDE: 37.603034° NSURFACE ELEVATION: 286.0 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadPAVEMENT
Date(s) Drilled: 05/25/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
4
7
11
14
16
19
16
9
9
30
32
21
11
14
19
18
38
33
28
9
13
0.3
1.5
2
3.5
4
5.5
7
8.5
9
10.5
14
15.5
18.518.9
20
14.4
25.0
25.8
11.3
12.5
18.4
18.4
0.0 / 286.54-INCHES ROOTMAT AND TOPSOIL TOPS0.3 / 286.2Red-brown, sandy ELASTIC SILT, contains roots, firm, moist[TERRACE] MHSAME, very stiff below 2 ft
SAME, stiff below 4 ft
6.5 / 280.0Light brown and red-brown, fine to coarse silty SAND, tracegravel, dense, moist SM
8.5 / 278.0Yellow-brown, fine to coarse silty SAND with gravel, verydense, moist SM
12.0 / 274.5Brown, fine to coarse clayey SAND, trace gravel, mediumdense, moist SC
Bottom of Hole @ 266.5 ft Elevation
PAGE 1 OF 1
10BH-010
10BH-010
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 22RLONGITUDE: 77.835376° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)Not Encountered During Drilling
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
285
280
275
270
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
12
14
16
18
20
STATION: 22+25LATITUDE: 37.602809° NSURFACE ELEVATION: 286.5 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadPAVEMENT
Date(s) Drilled: 05/24/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
2
6
5
13
23
8
12
3
8
5
17
27
8
9
5
10
7
27
29
10
17
0.3
1.5
2
3.5
4
5.5
7
8.5
9
10.5
12
14
15.5
18.5
20
15.2
23.8
24.8
21.4
14.7
11.9
0.0 / 282.06-INCHES ROOTMAT AND TOPSOIL TOPS0.5 / 281.5Red-brown, ELASTIC SILT with sand, contains roots, stiff,moist [TERRACE] MHSAME, very stiff below 2 ft
6.3 / 275.7Red-brown and yellow-brown, sandy FAT CLAY, hard, moistCH
9.0 / 273.0Brown, fine to medium clayey SAND with gravel, dense, moistSC
Bottom of Hole @ 267.0 ft Elevation
PAGE 1 OF 1
10BH-011
10BH-011
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 23LLONGITUDE: 77.834929° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)Not Encountered During Drilling
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
280
275
270
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
12
14
STATION: 23+23LATITUDE: 37.602922° NSURFACE ELEVATION: 282.0 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadPAVEMENT
Date(s) Drilled: 05/24/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
2
4
7
10
11
12
3
8
8
17
19
12
8
11
12
19
22
18
0.5
1.5
2
3.5
4
5.5
7
8.5
9
10.5
13.5
15
26.9
24.6
20.6
23.4
23.7
0.0 / 277.56-INCHES TOPSOIL TOPS0.5 / 277.0Orange-brown, ELASTIC SILT with sand, contains mica, firm,moist [TERRACE] MH
SAME, stiff below 4 ft
7.0 / 270.5Red-brown and orange-brown, sandy FAT CLAY, very stiff,moist CH
SAME, hard below 8.5 ft
Bottom of Hole @ 267.5 ft Elevation
PAGE 1 OF 1
10BH-012
10BH-012
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 25RLONGITUDE: 77.834369° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)Not Encountered During Drilling
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
276
274
272
270
268
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
STATION: 25+23LATITUDE: 37.602563° NSURFACE ELEVATION: 277.5 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadPAVEMENT
Date(s) Drilled: 05/24/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
3
4
4
7
8
3
3
5
10
15
5
4
8
15
20
0.5
1.5
2
3.5
4
5.5
7
8.5
10
11.1
8.3
16.3
20.3
20.6
20 7
NP
0.0 / 277.510-INCHES ASPHALT ASPH0.8 / 276.7Gray-brown, fine to coarse clayey sand FILL, contains crushedstone, dense, moist [FILL] FL
2.5 / 275.0Red-brown, fine to coarse silty sand FILL, trace gravel, dense,moist FL
4.0 / 273.5Gray-brown, sandy lean clay FILL, firm, wet FL
6.5 / 271.0Gray-brown, sandy LEAN CLAY, trace gravel, stiff, moist[TERRACE] CL
8.5 / 269.0Gray-brown, sandy FAT CLAY, trace gravel, stiff, moist CH
Bottom of Hole @ 267.5 ft Elevation
PAGE 1 OF 1
10BH-013
10BH-013
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 0LONGITUDE: 77.834071° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)FIRST ENCOUNTERED AT 4.0 ft DEPTH
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
276
274
272
270
268
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
STATION: 26+15LATITUDE: 37.602607° NSURFACE ELEVATION: 277.5 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadCULVERT
Date(s) Drilled: 05/24/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
18
10
2
5
5
16
15
3
7
6
14
17
2
8
9
1
1.5
2
2.5
3.5
4
5.5
7
8.5
10
22.3
26.5
26.6
25.4
15.8
0.0 / 277.04-INCHES ROOTMAT AND TOPSOIL TOPS0.3 / 276.7Red-brown, ELASTIC SILT with sand, trace gravel, firm, moist[TERRACE] MHSAME, very stiff below 2 ft
4.0 / 273.0Orange-brown and yellow-brown, LEAN CLAY with sand, tracegravel, hard, moist CL
6.5 / 270.5Dark yellow-brown, fine to coarse silty SAND, trace gravel, verydense, moist SM
8.0 / 269.0Light brown, fine to medium clayey SAND, dense, moist SC
Bottom of Hole @ 267.0 ft Elevation
PAGE 1 OF 1
10BH-014
10BH-014
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 19LLONGITUDE: 77.833640° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)Not Encountered During Drilling
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
276
274
272
270
268
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
STATION: 27+29LATITUDE: 37.602573° NSURFACE ELEVATION: 277.0 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadPAVEMENT
Date(s) Drilled: 05/25/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
3
5
8
12
12
3
10
14
23
15
4
13
21
28
20
0.3
1.5
2
3.5
4
5.5
7
8.5
10
10.2
30.2
24.0
21.7
18.8
0.0 / 281.510-INCHES ASPHALT ASPH0.8 / 280.7Gray-brown, fine to medium clayey sand FILL, contains gravel,medium dense, moist [FILL] FL2.0 / 279.5Red-brown, ELASTIC SILT, stiff, moist [TERRACE] MH
4.0 / 277.5Orange-brown and red-brown, FAT CLAY with sand, very stiff,moist CH
6.5 / 275.0Brown, fine to medium clayey SAND, medium dense, moist SC
SAME, light yellow-brown and light gray below 8.5 ft
Bottom of Hole @ 271.5 ft Elevation
PAGE 1 OF 1
10BH-015
10BH-015
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 0LONGITUDE: 77.833001° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)Not Encountered During Drilling
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
280
278
276
274
272
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
STATION: 29+28LATITUDE: 37.602333° NSURFACE ELEVATION: 281.5 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadPAVEMENT
Date(s) Drilled: 05/24/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
7
5
7
8
8
7
6
12
10
10
7
8
16
15
11
0.8
1.5
2
2.5
4
5.5
7
8.5
10
9.9
23.5
27.8
13.0
19.3
20.4
0.0 / 286.04-INCHES ROOTMAT AND TOPSOIL TOPS0.3 / 285.7Brown, fine to medium silty SAND, contains roots, loose, moist[TERRACE] SM2.0 / 284.0Red-brown, ELASTIC SILT with sand, very stiff, moist MH
6.5 / 279.5Red-brown and light yellow-brown, fine to coarse clayey SANDwith gravel, dense, moist SC
Bottom of Hole @ 271.0 ft Elevation
PAGE 1 OF 1
10BH-016
10BH-016
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 13RLONGITUDE: 77.835301° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)Not Encountered During Drilling
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
285
280
275
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
12
14
STATION: 50+84LATITUDE: 37.603111° NSURFACE ELEVATION: 286.0 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadPAVEMENT
Date(s) Drilled: 05/25/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
2
8
8
18
15
20
3
12
12
17
15
20
3
18
12
19
18
25
0.3
1.5
2
3.5
4
5.5
7
8.5
9
10.5
13.5
15
12.1
23.2
27.1
24.6
21.2
23.1
12.5
53 24
0.0 / 284.04-INCHES ROOTMAT AND TOPSOIL TOPS0.3 / 283.7Brown, fine to medium silty SAND, contains roots, trace gravel,loose, moist [TERRACE] SM2.0 / 282.0Brown, ELASTIC SILT with sand, contains roots, very stiff,moist MH
12.0 / 272.0Light brown and yellow-brown, fine to coarse silty SAND withgravel, very dense, moist SM
Bottom of Hole @ 269.0 ft Elevation
PAGE 1 OF 1
10BH-017
10BH-017
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 5LLONGITUDE: 77.835362° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)Not Encountered During Drilling
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
280
275
270
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
12
14
STATION: 52+08LATITUDE: 37.603504° NSURFACE ELEVATION: 284.0 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadPAVEMENT
Date(s) Drilled: 05/25/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
2
7
7
8
7
26
3
8
9
11
9
40
5
9
12
15
12
34
0.3
1.5
2
3.5
4
5
5.5
7
8.5
9
10.5
13.5
15
9.2
22.1
23.5
22.0
19.7
0.0 / 281.55-INCHES ASPHALT ASPH0.4 / 281.1Red-brown, fine to medium clayey sand FILL, medium dense,moist [FILL] FL2.0 / 279.5Red-brown, ELASTIC SILT with sand, firm, moist [TERRACE]MH
4.0 / 277.5Red-brown, sandy ELASTIC SILT, very stiff, moist MH
SAME, stiff below 7 ft
8.5 / 273.0Red-brown, fine to medium clayey SAND with gravel, mediumdense, moist SC
Bottom of Hole @ 271.5 ft Elevation
PAGE 1 OF 1
10BH-018
10BH-018
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 5RLONGITUDE: 77.835332° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)Not Encountered During Drilling
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
280
278
276
274
272
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
STATION: 53+00LATITUDE: 37.603734° NSURFACE ELEVATION: 281.5 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadPAVEMENT
Date(s) Drilled: 05/24/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
21
2
4
6
6
11
3
7
6
7
7
4
9
7
13
0.5
2
3.5
4
5.5
7
8.5
10
12.4
25.4
24.8
24.2
23.2
0.0 / 280.04-INCHES ROOTMAT AND TOPSOIL TOPS0.3 / 279.7Brown, sandy ELASTIC SILT, firm, moist [TERRACE] MH
2.0 / 278.0ELASTIC SILT with sand, trace gravel, stiff, moist MH
SAME, very stiff below 7 ft
8.5 / 271.5Red-brown, sandy ELASTIC SILT, trace gravel, very stiff, moistMH
Bottom of Hole @ 270.0 ft Elevation
PAGE 1 OF 1
10BH-019
10BH-019
FIELD DESCRIPTION OF STRATA
GROUND WATER
PAGE 1 OF 1OFFSET: 19RLONGITUDE: 77.835292° WCOORD. DATUM: NAD 83
REMARKS: Rig Type: CME-45B (Truck).
Copyright 2011, Commonwealth of Virginia
SP
T_L
OG
:091
302
27 V
DO
T F
OR
MA
T L
OG
S.G
PJ:
8.2.
918:
092
710:
12/
2/1
1
LAB DATA
MO
IST
UR
E C
ON
TE
NT
(%
)
PLA
ST
ICIT
Y IN
DE
X
PILL
LIQ
UID
LIM
IT
SO
IL R
EC
OV
ER
Y (
%)
CO
RE
RE
CO
VE
RY
(%
)Not Encountered During Drilling
DIP °
R O C K
SA
MP
LE L
EG
EN
D
S O I L
PROJECT #:LOCATION:STRUCTURE:
ELE
VA
TIO
N (
ft)
278
276
274
272
270
DE
PT
H (
ft)
SA
MP
LE IN
TE
RV
AL
RO
CK
QU
ALI
TY
DE
SIG
NA
TIO
N
ST
AN
DA
RD
PE
NE
TR
AT
ION
TE
ST
HA
MM
ER
BLO
WS
FIELD DATA
ST
RA
TA
LE
GE
ND
JOIN
TS
ST
RA
TA
2
4
6
8
10
STATION: 54+25LATITUDE: 37.604058° NSURFACE ELEVATION: 280.0 ft
0711-072-180-R201-C501Huguenot Trail at Pleasant RoadPAVEMENT
Date(s) Drilled: 05/24/2010Drilling Method(s): 2-1/4" I.D. Hollow Stem AugerSPT Method: Safety Hammer (140 lb)Other Test(s): Not ApplicableDriller: Ayers & Ayers, Inc.Logger: B. Azumah
3
5
6
6
10
2
5
6
5
12
3
8
9
13
13
0.3
1.5
2
3.5
4
5.5
7
8.5
10
APPENDIX B
SOIL LABORATORY TEST RESULTS
Summary of Laboratory Tests (2) Gradation Curves (2) Atterberg Limits (1)
Moisture Density Relationship (5)
Project 09130227 / December 2, 2011 Schnabel Engineering Consultants, Inc.
10BH-0034.0 - 5.5
261.0 - 259.5Jar
Brown and gray, clayey SAND, trace gravel,SC 14.4 40 17 23 31.3 61.6 14.8 -- --
-- -- -- --
10BH-0042.0 - 4.0
260.0 - 258.0Jar
Brown, fine to coarse clayey SAND, tracegravel, SC 22.2
74 40 34 58.9 81.8 1.3 -- ---- -- -- --
10BH-010 26.50.0 - 5.0
286.5 - 281.5Bulk
Red-brown, sandy elastic SILT, tracegravel, MH, A-7-5
C
B 67 35 32 61.7 86.8 0.0 21.2102.1 21.1 0.1 14.0
10BH-0130.0 - 5.0
277.5 - 272.5Bulk
Red-brown, silty, clayey SAND, trace gravel,SC-SM, A-4 A 20 13 7
46 21 25 43.9 77.1 0.3 -- ---- -- -- --
10BH-0050.0 - 5.0
263.0 - 258.0
C
Bulk 46 24 22 35.8 65.9 11.3 114.3 14.4113.4 12.8 0.3 11.8
10BH-0067.0 - 8.5
267.0 - 265.5Jar B 25.1
40.5 79.7 2.5 125.7 9.4125.7 8.3 0.0 26.8
10BH-0131.0 - 1.5
276.5 - 276.0
11.1
JarRed-brown, silty, clayey SAND, trace gravel,SC-SM A 11.1 20 13 7 36.4 76.8 5.1 -- --
-- -- -- --
Sheet 1 of 2
BoringNo.
Summary Of Laboratory TestsAppendix
Description of SoilSpecimen
Project Number: 09130227
Notes: 1. Soil tests in general accordance with ASTM standards.2. Soil classifications are in general accordance with ASTM D2487(as applicable), based on testing indicatedand visual classification.3. Key to abbreviations: NP=Non-Plastic; -- indicates no test performed
Project:
SampleDepth
ft
Elevationft
SampleType
DY
NA
MIC
LA
B S
UM
MA
RY
091
3022
7 S
CH
NA
BE
L LO
GS
.GP
J S
CH
NA
BE
L D
ATA
TE
MP
LATE
200
8_04
_22.
GD
T 6
/16/
10
CB
R D
ry D
ensi
tyA
t Com
pact
ion
(pcf
)
CB
R M
oist
ure
Con
tent
(%)
CB
R P
erce
nt S
wel
l
Max
imum
Dry
Den
sity
(pcf
)
Stra
tum
Plas
tic L
imit
CB
R V
alue
% P
assi
ngN
o. 4
0 Si
eve
Opt
imum
Moi
stur
eC
onte
nt (%
)
Liqu
id L
imit
% P
assi
ngN
o. 2
00 S
ieve
Nat
ural
Moi
stur
e (%
)
Plas
ticity
Inde
x
% R
etai
ned
No.
4 S
ieve
25.4Red-brown, fine to coarse clayey SAND,trace gravel, SC, A-7-6
C
Intersection ImprovementsHuguenot Trail at Pleasant RoadPowhatan County, VA
102.7
Red-brown, sandy elastic SILT, tracegravel, MH
10BH-0132.5 - 4.0
275.0 - 273.5Jar
Red-brown, fine to coarse silty SAND, tracegravel, SM A 8.3 NP NP NP 35.0 85.0 0.4 -- --
-- -- -- --
10BH-0160.0 - 5.0
286.0 - 281.0Bulk
Red-brown, sandy elastic SILT, tracegravel, MH, A-7-5 54 32 22 66.0 90.0 0.4 99.8 19.8
99.6 19.5 0.3
B
11.6
10BH-0175.0 - 10.0
279.0 - 274.0Bulk
Red-brown, sandy elastic SILT, tracegravel, MH, A-7-6 53 29 24 64.4 91.0 0.2 102.5 20.0
102.0 19.1 0.2 14.0
Sheet 2 of 2
BoringNo.
Summary Of Laboratory TestsAppendix
Description of SoilSpecimen
Project Number: 09130227
Notes: 1. Soil tests in general accordance with ASTM standards.2. Soil classifications are in general accordance with ASTM D2487(as applicable), based on testing indicatedand visual classification.3. Key to abbreviations: NP=Non-Plastic; -- indicates no test performed
24.6
25.2
Project:
SampleDepth
ft
Elevationft
SampleType
DY
NA
MIC
LA
B S
UM
MA
RY
091
3022
7 S
CH
NA
BE
L LO
GS
.GP
J S
CH
NA
BE
L D
ATA
TE
MP
LATE
200
8_04
_22.
GD
T 6
/16/
10
CB
R D
ry D
ensi
tyA
t Com
pact
ion
(pcf
)
CB
R M
oist
ure
Con
tent
(%)
CB
R P
erce
nt S
wel
l
Max
imum
Dry
Den
sity
(pcf
)
Stra
tum
Plas
tic L
imit
CB
R V
alue
% P
assi
ngN
o. 4
0 Si
eve
Opt
imum
Moi
stur
eC
onte
nt (%
)
Liqu
id L
imit
% P
assi
ngN
o. 2
00 S
ieve
Nat
ural
Moi
stur
e (%
)
Plas
ticity
Inde
x
% R
etai
ned
No.
4 S
ieve
B
Intersection ImprovementsHuguenot Trail at Pleasant RoadPowhatan County, VA
100
0.0010.010.1110100
U.S. SIEVE OPENING IN INCHES200100 140604023 3/41.5 6 81041
U.S. SIEVE NUMBERS50
31.343.935.858.961.7
30
GRADATION CURVES
4 3
GRAIN SIZE IN MILLIMETERS
PE
RC
EN
T FI
NE
R B
Y W
EIG
HT
1/23/8
HYDROMETER
6 16 2014
%Sand53.955.852.939.838.3
D30D604.0 ft2.0 ft0.0 ft7.0 ft0.0 ft
ASTM D422ASTM D422ASTM D422ASTM D422ASTM D422
Test Method D100.3950.2040.3080.088
D100199.537.59.54.75
LL PL PI
10BH-003
10BH-004
10BH-005
10BH-006
10BH-010
4.0 ft
2.0 ft
0.0 ft
7.0 ft
0.0 ft
40
46
46
74
67
17
21
24
40
35
23
25
22
34
32
%Clay10BH-00310BH-00410BH-00510BH-00610BH-010
%Silt%Gravel14.80.311.31.30.0
Specimen
Sample DescriptionBrown and gray, clayey SAND, trace gravel, SC
Brown, fine to coarse clayey SAND, trace gravel, SC
Red-brown, sandy elastic SILT, trace gravel, MH, A-7-5
Specimen
Contract: 09130227SIE
VE
5 S
HE
ET
091
3022
7 S
CH
NA
BE
L LO
GS
.GP
J S
CH
NA
BE
L D
ATA
TE
MP
LATE
200
8_04
_22.
GD
T 6
/16/
10 fine coarseCOBBLES SILT OR CLAY
medium fineSANDGRAVEL
coarse
Red-brown, fine to coarse clayey SAND, trace gravel, SC,A-7-6
Project: Intersection ImprovementsHuguenot Trail at Pleasant RoadPowhatan County, VA
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
Red-brown, sandy elastic SILT, trace gravel, MH
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
0.0010.010.1110100
U.S. SIEVE OPENING IN INCHES200100 140604023 3/41.5 6 81041
U.S. SIEVE NUMBERS50
40.536.435.066.064.4
30
GRADATION CURVES
4 3
GRAIN SIZE IN MILLIMETERS
PE
RC
EN
T FI
NE
R B
Y W
EIG
HT
1/23/8
HYDROMETER
6 16 2014
%Sand57.058.564.633.635.4
D30D600.0 ft1.0 ft2.5 ft0.0 ft5.0 ft
ASTM D422ASTM D422ASTM D422ASTM D422ASTM D422
Test Method D100.1960.2180.192
D10025199.5199.5
LL PL PI
10BH-013
10BH-013
10BH-013
10BH-016
10BH-017
0.0 ft
1.0 ft
2.5 ft
0.0 ft
5.0 ft
20
20
NP
54
53
13
13
NP
32
29
7
7
NP
22
24
%Clay10BH-01310BH-01310BH-01310BH-01610BH-017
%Silt%Gravel2.55.10.40.40.2
Specimen
Sample DescriptionRed-brown, silty, clayey SAND, trace gravel, SC-SM, A-4
Red-brown, silty, clayey SAND, trace gravel, SC-SM
Red-brown, fine to coarse silty SAND, trace gravel, SM
Red-brown, sandy elastic SILT, trace gravel, MH, A-7-5
Red-brown, sandy elastic SILT, trace gravel, MH, A-7-6
Specimen
Contract: 09130227SIE
VE
5 S
HE
ET
091
3022
7 S
CH
NA
BE
L LO
GS
.GP
J S
CH
NA
BE
L D
ATA
TE
MP
LATE
200
8_04
_22.
GD
T 6
/16/
10 fine coarseCOBBLES SILT OR CLAY
medium fineSANDGRAVEL
coarse
Project: Intersection ImprovementsHuguenot Trail at Pleasant RoadPowhatan County, VA
0
20
40
60
80
0 20 40 60 80 100
PLA
STI
CIT
Y IN
DE
X
ATTERBERG LIMITS
CL-ML
Brown and gray, clayey SAND, trace gravel, SC
Brown, fine to coarse clayey SAND, trace gravel, SC
Red-brown, sandy elastic SILT, trace gravel, MH, A-7-5
Red-brown, silty, clayey SAND, trace gravel, SC-SM, A-4
Red-brown, silty, clayey SAND, trace gravel, SC-SM
Red-brown, sandy elastic SILT, trace gravel, MH, A-7-5
Red-brown, sandy elastic SILT, trace gravel, MH, A-7-6
ML
CL CH
LIQUID LIMIT
MH
DescriptionFinesPIPLLL
40
46
46
74
67
20
20
54
53
17
21
24
40
35
13
13
32
29
23
25
22
34
32
7
7
22
24
31
44
36
59
62
41
36
66
64
10BH-003
10BH-004
10BH-005
10BH-006
10BH-010
10BH-013
10BH-013
10BH-016
10BH-017
4.0 ft
2.0 ft
0.0 ft
7.0 ft
0.0 ft
0.0 ft
1.0 ft
0.0 ft
5.0 ft
SpecimenPLOTTED DATA REPRESENTS SOIL PASSING NO. 40 SIEVE
Contract: 09130227ATT
ER
BE
RG
_LIM
ITS
091
3022
7 S
CH
NA
BE
L LO
GS
.GP
J S
CH
NA
BE
L D
ATA
TE
MP
LATE
200
8_04
_22.
GD
T 6
/16/
10
Red-brown, fine to coarse clayey SAND, trace gravel, SC, A-7-6
Project: Intersection ImprovementsHuguenot Trail at Pleasant RoadPowhatan County, VA
Red-brown, sandy elastic SILT, trace gravel, MH
106.0
107.0
108.0
109.0
110.0
111.0
112.0
113.0
114.0
115.0
116.0
117.0
118.0
9 11 13 15 17 19 21WATER CONTENT, %
VTM1
Comments:
DR
Y D
EN
SIT
Y, p
cf
MOISTURE DENSITY RELATIONSHIP
114.314.4
Test Methods:
Sample Description:
Opt. Moisture (%):Max. Dry Density (pcf):Assumed Specific Gravity:
Sample Source: 10BH-005, 0.0 ft
Red-brown, fine to coarse clayey SAND,trace gravel, SC, A-7-6
2.64
Project: Intersection ImprovementsHuguenot Trail at Pleasant RoadPowhatan County, VA
Contract: 09130227
Liquid Limit (LL): 46Plasticity Index (PI): 22% Retained #4 Sieve: 11.3% Passing # 200 Sieve: 35.8
CO
MP
AC
TIO
N 0
9130
227
SC
HN
AB
EL
LOG
S.G
PJ
SC
HN
AB
EL
DA
TA T
EM
PLA
TE 2
008_
04_2
2.G
DT
6/2
8/10
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
14 16 18 20 22 24 26 28WATER CONTENT, %
VTM1
Comments:
DR
Y D
EN
SIT
Y, p
cf
MOISTURE DENSITY RELATIONSHIP
21.2
Test Methods:
Sample Description:
Opt. Moisture (%):Max. Dry Density (pcf):Assumed Specific Gravity:
Sample Source: 10BH-010, 0.0 ft
Red-brown, sandy elastic SILT, tracegravel, MH, A-7-5
2.64
Project: Intersection ImprovementsHuguenot Trail at Pleasant RoadPowhatan County, VA
Contract: 09130227
Liquid Limit (LL): 67Plasticity Index (PI): 32% Retained #4 Sieve: 0.0% Passing # 200 Sieve: 61.7
CO
MP
AC
TIO
N 0
9130
227
SC
HN
AB
EL
LOG
S.G
PJ
SC
HN
AB
EL
DA
TA T
EM
PLA
TE 2
008_
04_2
2.G
DT
6/2
8/10
102.7
116.0
117.0
118.0
119.0
120.0
121.0
122.0
123.0
124.0
125.0
126.0
127.0
128.0
3 5 7 9 11 13 15WATER CONTENT, %
VTM1
Comments:
DR
Y D
EN
SIT
Y, p
cf
MOISTURE DENSITY RELATIONSHIP
125.79.4
Test Methods:
Sample Description:
Opt. Moisture (%):Max. Dry Density (pcf):Assumed Specific Gravity:
Sample Source: 10BH-013, 0.0 ft
Red-brown, silty, clayey SAND, tracegravel, SC-SM, A-4
2.62
Project: Intersection ImprovementsHuguenot Trail at Pleasant RoadPowhatan County, VA
Contract: 09130227
Liquid Limit (LL): 20Plasticity Index (PI): 7% Retained #4 Sieve: 2.5% Passing # 200 Sieve: 40.5
CO
MP
AC
TIO
N 0
9130
227
SC
HN
AB
EL
LOG
S.G
PJ
SC
HN
AB
EL
DA
TA T
EM
PLA
TE 2
008_
04_2
2.G
DT
6/2
8/10
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
14 16 18 20 22 24 26 28WATER CONTENT, %
VTM1
Comments:
DR
Y D
EN
SIT
Y, p
cf
MOISTURE DENSITY RELATIONSHIP
99.819.8
Test Methods:
Sample Description:
Opt. Moisture (%):Max. Dry Density (pcf):Assumed Specific Gravity:
Sample Source: 10BH-016, 0.0 ft
Red-brown, sandy elastic SILT, tracegravel, MH, A-7-5
2.58
Project: Intersection ImprovementsHuguenot Trail at Pleasant RoadPowhatan County, VA
Contract: 09130227
Liquid Limit (LL): 54Plasticity Index (PI): 22% Retained #4 Sieve: 0.4% Passing # 200 Sieve: 66.0
CO
MP
AC
TIO
N 0
9130
227
SC
HN
AB
EL
LOG
S.G
PJ
SC
HN
AB
EL
DA
TA T
EM
PLA
TE 2
008_
04_2
2.G
DT
6/2
8/10
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
13 15 17 19 21 23 25 27WATER CONTENT, %
VTM1
Comments:
DR
Y D
EN
SIT
Y, p
cf
MOISTURE DENSITY RELATIONSHIP
102.520.0
Test Methods:
Sample Description:
Opt. Moisture (%):Max. Dry Density (pcf):Assumed Specific Gravity:
Sample Source: 10BH-017, 5.0 ft
Red-brown, sandy elastic SILT, tracegravel, MH, A-7-6
2.64
Project: Intersection ImprovementsHuguenot Trail at Pleasant RoadPowhatan County, VA
Contract: 09130227
Liquid Limit (LL): 53Plasticity Index (PI): 24% Retained #4 Sieve: 0.2% Passing # 200 Sieve: 64.4
CO
MP
AC
TIO
N 0
9130
227
SC
HN
AB
EL
LOG
S.G
PJ
SC
HN
AB
EL
DA
TA T
EM
PLA
TE 2
008_
04_2
2.G
DT
6/2
8/10
Project 09130227 / December 2, 2011 Schnabel Engineering Consultants, Inc.
APPENDIX C
CALCULATIONS
Fill Settlement, Station 16+00 (7) VDOT Inter-Departmental Memorandum, Traffic Data for Design Purposes (1)
Huguenot Trail Pavement (1) Pleasants Road Pavement (1)
Huguenot Trail MOT (1) Pleasants Road MOT (1)
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
FoSSA -- Foundation Stress & Settlement Analysis Huguenot Trail at Pleasant Road Present Date/Time: Fri Jun 25 15:07:45 2010 G:\.....n Improvements Huguenot Trail at Pleasants Road Powhatan Co\Calcs\STA 16+00 Settlement.2ST
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
Huguenot Trail at Pleasant Road Report created by FoSSA(2.0): Copyright (c) 2003-2009, ADAMA Engineering, Inc.
PROJECT IDENTIFICATION
Title: Huguenot Trail at Pleasant Road Project Number: 09130227 - Client: Volkert & AssociatesDesigner: N. DumasStation Number: 16+00
Description:STA 16+00
Company's information:
Name: Schnabel EngineeringStreet: One West Cary Street
Richmond, VA 23221Telephone #: 804-649-7035Fax #: 804-649-7051E-Mail:
Original file path and name: G:\2009 Jo ..... ts Road Powhatan Co\Calcs\STA 16+00 Settlement.2STOriginal date and time of creating this file: Fri Jun 25 14:36:43 2010
GEOMETRY: Analysis of a 2D geometry
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
Huguenot Trail at Pleasant Road Copyright © 2003-2009 ADAMA Engineering, Inc. www.GeoPrograms.com License number FoSSA-200236
Page 1 of 7
www.GeoPrograms.com
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
FoSSA -- Foundation Stress & Settlement Analysis Huguenot Trail at Pleasant Road Present Date/Time: Fri Jun 25 15:07:45 2010 G:\.....n Improvements Huguenot Trail at Pleasants Road Powhatan Co\Calcs\STA 16+00 Settlement.2ST
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
INPUT DATA -- FOUNDATION LAYERS -- 2 layers
Wet UnitWeight,[lb/ft³]
Poisson's Ratio Descriptionof Soil
1 125.00 0.40 Existing Fill2 135.00 0.30 Terrace Gravel
INPUT DATA -- EMBANKMENT LAYERS -- 1 layers
Wet UnitWeight,[lb/ft³]
Descriptionof Soil
1 125.00 New Fill
INPUT DATA OF WATER
Point #
Coordinates (X, Z) :(X) (Z)[ ft.] [ ft.]
1 -50.00 261.002 50.00 261.00
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
Huguenot Trail at Pleasant Road Copyright © 2003-2009 ADAMA Engineering, Inc. www.GeoPrograms.com License number FoSSA-200236
Page 2 of 7
www.GeoPrograms.com
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
FoSSA -- Foundation Stress & Settlement Analysis Huguenot Trail at Pleasant Road Present Date/Time: Fri Jun 25 15:07:45 2010 G:\.....n Improvements Huguenot Trail at Pleasants Road Powhatan Co\Calcs\STA 16+00 Settlement.2ST
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
DRAWING OF SPECIFIED GEOMETRY
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
Huguenot Trail at Pleasant Road Copyright © 2003-2009 ADAMA Engineering, Inc. www.GeoPrograms.com License number FoSSA-200236
Page 3 of 7
www.GeoPrograms.com
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
FoSSA -- Foundation Stress & Settlement Analysis Huguenot Trail at Pleasant Road Present Date/Time: Fri Jun 25 15:07:45 2010 G:\.....n Improvements Huguenot Trail at Pleasants Road Powhatan Co\Calcs\STA 16+00 Settlement.2ST
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
IMMEDIATE SETTLEMENT, Si
Node #
Layer
(k)
Settlement along section:X
[ ft.]
Y
[ ft.]
Young'sModulus, E[lb/ft ²]
Poisson'sRatio,
Settlementof eachlayer, Si(k)[ ft.]
InitialZ
[ ft.]
FinalZ *
[ ft.]
Total SettlementSum of Si(k),
[ ft.]
1 0.00 0.00 268.00 268.00 0.001 500000 0.4000 0.00022 2000000 0.3000 0.0003
2 1.06 0.00 268.00 268.00 0.001 500000 0.4000 0.00022 2000000 0.3000 0.0003
3 2.12 0.00 268.00 268.00 0.001 500000 0.4000 0.00022 2000000 0.3000 0.0004
4 3.18 0.00 268.00 268.00 0.001 500000 0.4000 0.00022 2000000 0.3000 0.0004
5 4.24 0.00 268.00 268.00 0.001 500000 0.4000 0.00022 2000000 0.3000 0.0005
6 5.31 0.00 268.00 268.00 0.001 500000 0.4000 0.00022 2000000 0.3000 0.0006
7 6.37 0.00 268.00 268.00 0.001 500000 0.4000 0.00022 2000000 0.3000 0.0006
8 7.43 0.00 268.00 268.00 0.001 500000 0.4000 0.00022 2000000 0.3000 0.0007
9 8.49 0.00 267.87 267.87 0.001 500000 0.4000 0.00032 2000000 0.3000 0.0009
10 9.55 0.00 267.60 267.60 0.001 500000 0.4000 0.00052 2000000 0.3000 0.0010
11 10.61 0.00 267.32 267.32 0.001 500000 0.4000 0.00072 2000000 0.3000 0.0011
12 11.67 0.00 267.05 267.05 0.001 500000 0.4000 0.00092 2000000 0.3000 0.0013
13 12.73 0.00 266.78 266.77 0.001 500000 0.4000 0.00112 2000000 0.3000 0.0014
14 13.80 0.00 266.50 266.50 0.001 500000 0.4000 0.00122 2000000 0.3000 0.0016
15 14.86 0.00 266.23 266.22 0.001 500000 0.4000 0.00132 2000000 0.3000 0.0018
16 15.92 0.00 265.95 265.95 0.001 500000 0.4000 0.00152 2000000 0.3000 0.0019
17 16.98 0.00 265.68 265.67 0.001 500000 0.4000 0.00162 2000000 0.3000 0.0021
18 18.04 0.00 265.40 265.40 0.001 500000 0.4000 0.00172 2000000 0.3000 0.0023
19 19.10 0.00 265.13 265.13 0.001 500000 0.4000 0.00172 2000000 0.3000 0.0024
20 20.16 0.00 264.86 264.85 0.001 500000 0.4000 0.00172 2000000 0.3000 0.0026
21 21.22 0.00 264.58 264.58 0.001 500000 0.4000 0.00172 2000000 0.3000 0.0027
22 22.29 0.00 264.31 264.30 0.001 500000 0.4000 0.00182 2000000 0.3000 0.0029
23 23.35 0.00 264.03 264.03 0.001 500000 0.4000 0.00182 2000000 0.3000 0.0030
24 24.41 0.00 263.76 263.75 0.001 500000 0.4000 0.00172 2000000 0.3000 0.0031
25 25.47 0.00 263.48 263.48 0.001 500000 0.4000 0.00162 2000000 0.3000 0.0032
*Note: Final Z is calculated assuming only 'Immediate Settlement' exists.
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
Huguenot Trail at Pleasant Road Copyright © 2003-2009 ADAMA Engineering, Inc. www.GeoPrograms.com License number FoSSA-200236
Page 4 of 7
www.GeoPrograms.com
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
FoSSA -- Foundation Stress & Settlement Analysis Huguenot Trail at Pleasant Road Present Date/Time: Fri Jun 25 15:07:45 2010 G:\.....n Improvements Huguenot Trail at Pleasants Road Powhatan Co\Calcs\STA 16+00 Settlement.2ST
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
IMMEDIATE SETTLEMENT, Si
Node #
Layer
(k)
Settlement along section:X
[ ft.]
Y
[ ft.]
Young'sModulus, E[lb/ft ²]
Poisson'sRatio,
Settlementof eachlayer, Si(k)[ ft.]
InitialZ
[ ft.]
FinalZ *
[ ft.]
Total SettlementSum of Si(k),
[ ft.]
26 26.53 0.00 263.21 263.20 0.001 500000 0.4000 0.00152 2000000 0.3000 0.0033
27 27.59 0.00 262.93 262.93 0.001 500000 0.4000 0.00132 2000000 0.3000 0.0033
28 28.65 0.00 262.71 262.70 0.001 500000 0.4000 0.00142 2000000 0.3000 0.0033
29 29.71 0.00 262.76 262.75 0.001 500000 0.4000 0.00142 2000000 0.3000 0.0033
30 30.78 0.00 262.81 262.81 0.001 500000 0.4000 0.00132 2000000 0.3000 0.0033
31 31.84 0.00 262.86 262.86 0.001 500000 0.4000 0.00132 2000000 0.3000 0.0032
32 32.90 0.00 262.92 262.91 0.001 500000 0.4000 0.00122 2000000 0.3000 0.0031
33 33.96 0.00 262.97 262.96 0.001 500000 0.4000 0.00112 2000000 0.3000 0.0031
34 35.02 0.00 263.02 263.02 0.001 500000 0.4000 0.00132 2000000 0.3000 0.0029
35 36.08 0.00 263.07 263.07 0.001 500000 0.4000 0.00122 2000000 0.3000 0.0028
36 37.14 0.00 263.12 263.12 0.001 500000 0.4000 0.00112 2000000 0.3000 0.0027
37 38.20 0.00 263.18 263.17 0.001 500000 0.4000 0.00102 2000000 0.3000 0.0025
38 39.27 0.00 263.23 263.22 0.001 500000 0.4000 0.00092 2000000 0.3000 0.0024
39 40.33 0.00 263.28 263.28 0.001 500000 0.4000 0.00092 2000000 0.3000 0.0022
40 41.39 0.00 263.33 263.33 0.001 500000 0.4000 0.00092 2000000 0.3000 0.0020
41 42.45 0.00 263.38 263.38 0.001 500000 0.4000 0.00082 2000000 0.3000 0.0019
42 43.51 0.00 263.44 263.43 0.001 500000 0.4000 0.00072 2000000 0.3000 0.0017
43 44.57 0.00 263.49 263.49 0.001 500000 0.4000 0.00052 2000000 0.3000 0.0015
44 45.63 0.00 263.54 263.54 0.001 500000 0.4000 0.00042 2000000 0.3000 0.0013
45 46.69 0.00 263.59 263.59 0.001 500000 0.4000 0.00032 2000000 0.3000 0.0011
46 47.76 0.00 263.64 263.64 0.001 500000 0.4000 0.00022 2000000 0.3000 0.0010
47 48.82 0.00 263.70 263.70 0.001 500000 0.4000 0.00012 2000000 0.3000 0.0008
48 49.88 0.00 263.75 263.75 0.001 500000 0.4000 -0.00002 2000000 0.3000 0.0007
49 50.94 0.00 263.80 263.80 0.001 500000 0.4000 -0.00012 2000000 0.3000 0.0005
50 52.00 0.00 263.85 263.85 0.001 500000 0.4000 -0.00022 2000000 0.3000 0.0004
*Note: Final Z is calculated assuming only 'Immediate Settlement' exists.
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
Huguenot Trail at Pleasant Road Copyright © 2003-2009 ADAMA Engineering, Inc. www.GeoPrograms.com License number FoSSA-200236
Page 5 of 7
www.GeoPrograms.com
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
FoSSA -- Foundation Stress & Settlement Analysis Huguenot Trail at Pleasant Road Present Date/Time: Fri Jun 25 15:07:45 2010 G:\.....n Improvements Huguenot Trail at Pleasants Road Powhatan Co\Calcs\STA 16+00 Settlement.2ST
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
TABULATED GEOMETRY: INPUT OF FOUNDATION SOILS
Found.Soil #
Point #
Coordinates (X, Z) :(X) (Z)[ ft.] [ ft.]
D E S C R I P T I O N
1 Existing Fill1 -50.00 264.702 -18.50 266.003 -12.00 268.004 8.00 268.005 28.50 262.706 55.00 264.00
2 Terrace Gravel1 -50.00 261.002 55.00 261.00
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
Huguenot Trail at Pleasant Road Copyright © 2003-2009 ADAMA Engineering, Inc. www.GeoPrograms.com License number FoSSA-200236
Page 6 of 7
www.GeoPrograms.com
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
FoSSA -- Foundation Stress & Settlement Analysis Huguenot Trail at Pleasant Road Present Date/Time: Fri Jun 25 15:07:45 2010 G:\.....n Improvements Huguenot Trail at Pleasants Road Powhatan Co\Calcs\STA 16+00 Settlement.2ST
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
TABULATED GEOMETRY: INPUT OF EMBANKMENT SOILS
Embank.Soil #
Point #
Coordinates (X, Z) :(X) (Z)[ ft.] [ ft.]
D E S C R I P T I O N
New Fill1 X1 = -35.50 [ft]X2 = 52.00 [ft]
1 -22.00 268.002 19.70 268.903 29.70 268.404 39.70 266.85
Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0 FoSSA Version 2.0
Huguenot Trail at Pleasant Road Copyright © 2003-2009 ADAMA Engineering, Inc. www.GeoPrograms.com License number FoSSA-200236
Page 7 of 7
www.GeoPrograms.com
PRELIMINARY
To: Adam Wilkerson
From: Ron Svejkovsky
Route: 711 Huguenot Trail Rd P\PMS / UPC#: 19056
County/City: Powhatan County Project: 0711-072-180
From: .3 mi. west of Rt 616 To: .15 mi. east of Rt 616
Ad Date: Design Year: 2035
Subject: Traffic Data for Design Purposes, Intersection Project
Attached is the information requested in your memorandum of December 5, 2008
Route 711
west of int.
Route711
east of int.
Route 616
north of int.
Present Year ADT 2009 2425 2976 1491
Design Year ADT 2035 4500 5500 1700
Design Hour Volume 2035 439 532 232
Directional Distribution Factor 80-20 70-30 70-30
% Trucks Peak (4-5) 1% 1% 3%
% Trucks Peak (6-7) 0% 0% 1%
% Trucks Peak (8-13) 1% 0% 0%
% Trucks Daily (4-5) 2% 1% 3%
% Trucks Daily (6-7) 1% 0% 1%
% Trucks Daily (8-13) 1% 0% 1%
Functional Classification Rural Minor
Arterial
Rural Minor
Arterial Local
Further Remarks:
Route 711 Corridor Study AGR used for preliminary projections;(2.4% for Route 711; 0.5% for Route 616); higher than VEC and SPS rates
Sensitivity analyses are being done to help determine appropriate designRoute 711 is on the RRPDC Bike/Ped Plan “On-Road Facility (existing)”
For additional information, please contact Ron Svejkovsky at (804) 524-6002.
cc:
D. Totten
B. Solomonov
T. A. Bridewell
T. Holmes
D. Dreis
C. Tucker
W. Johnson
W. Pribble
highest overall (all approaches) 1-hour peak hours chosen (7-8 AM, 4:15-5:15 PM)
VIRGINIA DEPARTMENT OF TRANSPORTATION
INTER-DEPARTMENTAL MEMORANDUM
March 10, 2009
2013
There are multiple peaks due to admin, guard, and trainee shift changes at the prisons; the
Page 1
1993 AASHTO Pavement Design
DARWin Pavement Design and Analysis System
A Proprietary AASHTOWare
Computer Software Product
Flexible Structural Design Module
Huguenot Trail - Pavement Design
Flexible Structural Design
18-kip ESALs Over Initial Performance Period 1,059,096
Initial Serviceability 4.2
Terminal Serviceability 2.8
Reliability Level 85 %
Overall Standard Deviation 0.49
Roadbed Soil Resilient Modulus 13,350 psi
Stage Construction 1
Calculated Design Structural Number 2.80 in
Simple ESAL Calculation
Performance Period (years) 20
Two-Way Traffic (ADT) 2,730
Number of Lanes in Design Direction 1
Percent of All Trucks in Design Lane 100 %
Percent Trucks in Design Direction 100 %
Percent Heavy Trucks (of ADT) FHWA Class 5 or Greater 4 %
Average Initial Truck Factor (ESALs/truck) 1.05
Annual Truck Factor Growth Rate 0 %
Annual Truck Volume Growth Rate 2.4 %
Growth Compound
Total Calculated Cumulative ESALs 1,059,096
Specified Layer Design
Layer
Material Description
Struct
Coef.
(Ai)
Drain
Coef.
(Mi)
Thickness
(Di)(in)
Width
(ft)
Calculated
SN (in)
1 VDOT SM-12.5A 0.44 1 1.5 - 0.66
2 VDOT BM-25.0 0.44 1 4 - 1.76
3 VDOT 21B 0.12 1 8 - 0.96
Total - - - 13.50 - 3.38
Page 1
1993 AASHTO Pavement Design
DARWin Pavement Design and Analysis System
A Proprietary AASHTOWare
Computer Software Product
Flexible Structural Design Module
Pleasants Road - Pavement Design
Flexible Structural Design
18-kip ESALs Over Initial Performance Period 614,696
Initial Serviceability 4
Terminal Serviceability 2.5
Reliability Level 75 %
Overall Standard Deviation 0.49
Roadbed Soil Resilient Modulus 13,350 psi
Stage Construction 1
Calculated Design Structural Number 2.36 in
Simple ESAL Calculation
Performance Period (years) 20
Two-Way Traffic (ADT) 1,528
Number of Lanes in Design Direction 1
Percent of All Trucks in Design Lane 100 %
Percent Trucks in Design Direction 100 %
Percent Heavy Trucks (of ADT) FHWA Class 5 or Greater 5 %
Average Initial Truck Factor (ESALs/truck) 1.05
Annual Truck Factor Growth Rate 0 %
Annual Truck Volume Growth Rate 0.5 %
Growth Compound
Total Calculated Cumulative ESALs 614,696
Specified Layer Design
Layer
Material Description
Struct
Coef.
(Ai)
Drain
Coef.
(Mi)
Thickness
(Di)(in)
Width
(ft)
Calculated
SN (in)
1 VDOT SM-12.5A 0.44 1 1.5 - 0.66
2 VDOT BM-25 0.44 1 3 - 1.32
3 VDOT 21B 0.12 1 6 - 0.72
Total - - - 10.50 - 2.70
Page 1
1993 AASHTO Pavement Design
DARWin Pavement Design and Analysis System
A Proprietary AASHTOWare
Computer Software Product
Flexible Structural Design Module
Huguenot Trail - MOT
Flexible Structural Design
18-kip ESALs Over Initial Performance Period 41,880
Initial Serviceability 4.2
Terminal Serviceability 2.8
Reliability Level 85 %
Overall Standard Deviation 0.49
Roadbed Soil Resilient Modulus 13,350 psi
Stage Construction 1
Calculated Design Structural Number 1.59 in
Simple ESAL Calculation
Performance Period (years) 1
Two-Way Traffic (ADT) 2,730
Number of Lanes in Design Direction 1
Percent of All Trucks in Design Lane 100 %
Percent Trucks in Design Direction 100 %
Percent Heavy Trucks (of ADT) FHWA Class 5 or Greater 4 %
Average Initial Truck Factor (ESALs/truck) 1.05
Annual Truck Factor Growth Rate 0 %
Annual Truck Volume Growth Rate 2.4 %
Growth Compound
Total Calculated Cumulative ESALs 41,880
Specified Layer Design
Layer
Material Description
Struct
Coef.
(Ai)
Drain
Coef.
(Mi)
Thickness
(Di)(in)
Width
(ft)
Calculated
SN (in)
1 VDOT IM-19.0 0.44 1 2 - 0.88
2 VDOT 21B 0.12 1 6 - 0.72
Total - - - 8.00 - 1.60
Page 1
1993 AASHTO Pavement Design
DARWin Pavement Design and Analysis System
A Proprietary AASHTOWare
Computer Software Product
Flexible Structural Design Module
Pleasants Road - MOT
Flexible Structural Design
18-kip ESALs Over Initial Performance Period 29,300
Initial Serviceability 4
Terminal Serviceability 2.5
Reliability Level 75 %
Overall Standard Deviation 0.49
Roadbed Soil Resilient Modulus 13,350 psi
Stage Construction 1
Calculated Design Structural Number 1.38 in
Simple ESAL Calculation
Performance Period (years) 1
Two-Way Traffic (ADT) 1,528
Number of Lanes in Design Direction 1
Percent of All Trucks in Design Lane 100 %
Percent Trucks in Design Direction 100 %
Percent Heavy Trucks (of ADT) FHWA Class 5 or Greater 5 %
Average Initial Truck Factor (ESALs/truck) 1.05
Annual Truck Factor Growth Rate 0 %
Annual Truck Volume Growth Rate 0.5 %
Growth Compound
Total Calculated Cumulative ESALs 29,300
Specified Layer Design
Layer
Material Description
Struct
Coef.
(Ai)
Drain
Coef.
(Mi)
Thickness
(Di)(in)
Width
(ft)
Calculated
SN (in)
1 VDOT IM-19.0 0.44 1 2 - 0.88
2 VDOT 21B 0.12 1 6 - 0.72
Total - - - 8.00 - 1.60