Sub-metering : Demonstrated the need for advanced controls

10
ZNE adaptive lighting retrofits for Recreation Center & Offices and future plans at UCSB Student Affairs

description

ZNE adaptive lighting retrofits for Recreation Center & Offices and future plans at UCSB Student Affairs. Sub-metering : Demonstrated the need for advanced controls. With LED (18K Lumen) and Advanced Controls. Energy Saving Approaching 80% in areas with LED Fixtures and Advanced Controls. - PowerPoint PPT Presentation

Transcript of Sub-metering : Demonstrated the need for advanced controls

Page 1: Sub-metering : Demonstrated  the need for advanced controls

ZNE adaptive lighting retrofits for Recreation Center & Offices and future plans at UCSB

Student Affairs

Page 2: Sub-metering : Demonstrated  the need for advanced controls

Sub-metering: Demonstrated the need for advanced controls

Page 3: Sub-metering : Demonstrated  the need for advanced controls

With LED (18K Lumen) and Advanced Controls

Page 4: Sub-metering : Demonstrated  the need for advanced controls

Energy Saving Approaching 80% in areas with LED Fixtures and Advanced Controls

Page 5: Sub-metering : Demonstrated  the need for advanced controls

Effectiveness of retrofit highlights need to control Emergency fixtures

Usage Prio

r to Retro

fit (P2S Audit)

Combined Usa

ge Post Retro

fit

Controlle

d Fixtures U

sage (6

9x)

Emergency Fixt

ures Usa

ge (7x)

010002000300040005000600070008000

Electrical Consumption Detail - Pre and Post Retrofit of the MAC Gymnasium - February 2014

KWH

Page 6: Sub-metering : Demonstrated  the need for advanced controls

Solar efficiency improved over prior years with energy efficiency gains

2009 2010 2011 2012 2013 2014 -

50,000

100,000

150,000

200,000

250,000

0.0%

10.0%

20.0%

30.0%

40.0%

50.0%

60.0%

Solar Generation compared to total consumption from Jan-uary through April

Total KWH Use PV Generation Net KwH Balance % Solar

Page 7: Sub-metering : Demonstrated  the need for advanced controls

Portfolio of SA Buildings

Page 8: Sub-metering : Demonstrated  the need for advanced controls

Portfolio of Buildings - plans

Page 9: Sub-metering : Demonstrated  the need for advanced controls

Future plans• Air or Ground Source Heat Pumps for Pool Heating• Expanding lighting retrofits to take advantage of SEP incentive cycle• HVAC - Roof top units such as catalyst – partnership with SPEED and

SCE• Sub-metering to ensure gains achieved remain• Increased solar PV presence on rooftops to complement energy

efficiency measures – requires another 423kW to be ZNE on electrical consumption