Study on the Application of the Kent Index Method on the Risk ...

11
Hindawi Publishing Corporation e Scientific World Journal Volume 2013, Article ID 360705, 10 pages http://dx.doi.org/10.1155/2013/360705 Research Article Study on the Application of the Kent Index Method on the Risk Assessment of Disastrous Accidents in Subway Engineering Hao Lu, 1 Mingyang Wang, 1 Baohuai Yang, 2 and Xiaoli Rong 1 1 College of Defense Engineering, PLA University of Science and Technology, Nanjing 210007, China 2 Nanjing KunTuo Civil Engineering Technology Co., Ltd., Nanjing 210007, China Correspondence should be addressed to Hao Lu; [email protected] Received 12 January 2013; Accepted 20 February 2013 Academic Editors: R. Degenhardt and X. F. XU Copyright © 2013 Hao Lu et al. is is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited. With the development of subway engineering, according to uncertain factors and serious accidents involved in the construction of subways, implementing risk assessment is necessary and may bring a number of benefits for construction safety. e Kent index method extensively used in pipeline construction is improved to make risk assessment much more practical for the risk assessment of disastrous accidents in subway engineering. In the improved method, the indexes are divided into four categories, namely, basic, design, construction, and consequence indexes. In this study, a risk assessment model containing four kinds of indexes is provided. ree kinds of risk occurrence modes are listed. e probability index model which considers the relativity of the indexes is established according to the risk occurrence modes. e model provides the risk assessment process through the fault tree method and has been applied in the risk assessment of Nanjing subway’s river-crossing tunnel construction. Based on the assessment results, the builders were informed of what risks should be noticed and what they should do to avoid the risks. e need for further research is discussed. Overall, this method may provide a tool for the builders, and improve the safety of the construction. 1. Introduction Creating a perfect design in subway engineering is difficult because of complex geological environment and difficulties in completely obtaining basic information. e influence of current large-scale subway construction, the limited con- struction period, and poor management caused by the lack of skilled personnel contribute to the increase in the occurrence of accidents in subway construction. us, the issue of safety has become very serious [1, 2]. Accidents indicate that subway construction affects the ambient environment (ground build- ings, transportation, underground structures, underground pipes, etc.), endangers people’s lives, compromises property security, and causes serious economic losses [2]. Several typical subway construction accidents are shown in Table 1. Plenty of new urgent tasks are being proposed because of the serious safety issue in subway engineering. One of these tasks is to study the safety risk management method. In recent years, the utilization of risk assessment in subway engineering has significantly increased and has provided particular economic benefits and research results [35]. e book “Code for Risk Management of Underground Works in Urban Rail Transit” [6] published in 2011 provides a reference for the application of risk management in subway engineering and considers the classification standard of prob- ability and consequence. However, in the application process, the risk factors that influence scope, occurrence mechanism, and potential damage mechanism in subway construction are very complex. Risk management involves many disciplines such as natural science, social science, engineering technol- ogy, system science, and management science. us, deter- mining if a probability distribution hypothesis is appropriate becomes difficult when tunnel and underground engineering risks are studied with the probability method [7, 8]. us, obtaining the “real” probability value of an accident is difficult [9]. Kent used the index method to study pipeline accidents. He believes that pipeline accidents cannot be accurately

Transcript of Study on the Application of the Kent Index Method on the Risk ...

Hindawi Publishing CorporationThe Scientific World JournalVolume 2013, Article ID 360705, 10 pageshttp://dx.doi.org/10.1155/2013/360705

Research ArticleStudy on the Application of the Kent Index Method on the RiskAssessment of Disastrous Accidents in Subway Engineering

Hao Lu,1 Mingyang Wang,1 Baohuai Yang,2 and Xiaoli Rong1

1 College of Defense Engineering, PLA University of Science and Technology, Nanjing 210007, China2Nanjing KunTuo Civil Engineering Technology Co., Ltd., Nanjing 210007, China

Correspondence should be addressed to Hao Lu; [email protected]

Received 12 January 2013; Accepted 20 February 2013

Academic Editors: R. Degenhardt and X. F. XU

Copyright © 2013 Hao Lu et al. This is an open access article distributed under the Creative Commons Attribution License, whichpermits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.

With the development of subway engineering, according to uncertain factors and serious accidents involved in the constructionof subways, implementing risk assessment is necessary and may bring a number of benefits for construction safety. The Kentindex method extensively used in pipeline construction is improved to make risk assessment much more practical for the riskassessment of disastrous accidents in subway engineering. In the improved method, the indexes are divided into four categories,namely, basic, design, construction, and consequence indexes. In this study, a risk assessment model containing four kinds ofindexes is provided. Three kinds of risk occurrence modes are listed. The probability index model which considers the relativityof the indexes is established according to the risk occurrence modes. The model provides the risk assessment process through thefault tree method and has been applied in the risk assessment of Nanjing subway’s river-crossing tunnel construction. Based onthe assessment results, the builders were informed of what risks should be noticed and what they should do to avoid the risks.The need for further research is discussed. Overall, this method may provide a tool for the builders, and improve the safety of theconstruction.

1. Introduction

Creating a perfect design in subway engineering is difficultbecause of complex geological environment and difficultiesin completely obtaining basic information. The influence ofcurrent large-scale subway construction, the limited con-struction period, and poormanagement caused by the lack ofskilled personnel contribute to the increase in the occurrenceof accidents in subway construction. Thus, the issue of safetyhas become very serious [1, 2]. Accidents indicate that subwayconstruction affects the ambient environment (ground build-ings, transportation, underground structures, undergroundpipes, etc.), endangers people’s lives, compromises propertysecurity, and causes serious economic losses [2]. Severaltypical subway construction accidents are shown in Table 1.

Plenty of new urgent tasks are being proposed becauseof the serious safety issue in subway engineering. One ofthese tasks is to study the safety risk management method.In recent years, the utilization of risk assessment in subway

engineering has significantly increased and has providedparticular economic benefits and research results [3–5].

The book “Code for Risk Management of UndergroundWorks in Urban Rail Transit” [6] published in 2011 providesa reference for the application of risk management in subwayengineering and considers the classification standard of prob-ability and consequence. However, in the application process,the risk factors that influence scope, occurrence mechanism,and potential damagemechanism in subway construction arevery complex. Risk management involves many disciplinessuch as natural science, social science, engineering technol-ogy, system science, and management science. Thus, deter-mining if a probability distribution hypothesis is appropriatebecomes difficult when tunnel and underground engineeringrisks are studied with the probability method [7, 8]. Thus,obtaining the “real” probability value of an accident is difficult[9].

Kent used the index method to study pipeline accidents.He believes that pipeline accidents cannot be accurately

2 The Scientific World Journal

Table 1: Several typical subway construction accidents in China.

Time City Loss2004-3-17 Guangzhou 1 death [10]2007-3-28 Peking 6 deaths [11]

2007-2-5 NanjingThe ground collapsed, andmany residents were affected

[12]2008-11-15 Hangzhou 21 deaths [13]

predicted, and risk assessment does not provide an accuratecalculation based on the probability theory. Insufficientsample size or calculation quantity is usually regarded asthe reason for the inaccurate calculation, but in truth, themain reason is that too many assumptions are made inthe computation or collection of samples, which leads tothe inaccuracy of the assessment result. Kent’s method doesnot consider the “real” probability; the indexes in Kent’smethod contain the probability and are not tied to the “real”probability, which is very persuasive [9].

By adopting advanced techniques from the Kent indexmethod and considering the limitation of the applicationof Kent’s method in subway engineering, a model that canbe applied to risk assessment of disastrous accidents insubway engineering is developed in this paper.This paper alsoprovides a reference for quantitative evaluation of disastrousrisks involved in subway engineering and other similar fields.

2. Improvement of the Kent Index Method

Kent’s method does not intentionally evade the subjectivefactors in risk assessment. In fact, his method adoptedseveral feasible measures to reduce the negative influenceof these factors, thereby providing a good reference forrisk assessment in subway engineering. Several researchershave questioned the expert scoring method because of itsalleged subjectivity. In truth, opinion, experience, intuition,and other unquantifiable resources are used if knowledgeon the matter is limited. Thus, risk assessment becomes atleast partially subjective [9]. Moreover, subjectivity is foundin any and all risk assessment methodologies. However,experts also have limitations.The assessment results obtainedthrough the expert scoring method could be inconsistentbecause of the discrepancy between individual and diffusedthought. In the same way that experts need the guidance ofa risk manager to normalize their thoughts, several researchmethods (including theoretical research, value simulated, testdemonstration, etc.) should be used to minimize subjectiveinfluences.

Kent’s method has many advantages. Thus, it is exten-sively applied in pipeline risk assessment. Unfortunately, itsdisadvantages restrict its application in other fields.

One of the disadvantages of Kent’s method is that nospecific method or train of thought is used to determineweight, which is very important in risk assessment. Weight ismainly obtained through the experience of an expert, and noperfect solution exists to solve this problem. In the opinion

of the author, determining the weight value is an iterativeprocess whose result can be perfected through repeatedapplication.

Another disadvantage is the assumption regarding theindependence of the indexes. In risk analysis, the indexesare assumed to be independent. This assumption could havedifferent effects on the analysis of different objects. Thus, themethod is not suitable for all cases.

Pipeline risk is a relatively simple problem, only one acci-dent, the bursting of the pipeline. In underground engineer-ing, for example, the common risk factors include collapse,water gushing, surface subsidence, and so on, and a signif-icant correlation exists among these factors. Thus, ensuringconstruction safety by merely applying Kent’s method isdifficult. The method must be modified before being appliedin underground engineering safety risk assessment.

Several suggestions have been proposed for the appli-cation of Kent’s method in underground engineering riskassessment.

(a) Practical engineering should be the basis of research;the basic concept of risk must be utilized to make riskassessment more feasible.

(b) In determining the weight value and other data, exist-ing research results should be considered togetherwith an expert scoring method.

(c) An effective assessment cannot be achieved by merecalculation of the summing indexes because of thecomplex relationship among strata condition, design,and construction (they affect one another). Thus, themodel needs to be improved first.

3. Improved Index Method Model

3.1. Index Categories. Based on the characteristics of sub-way construction, indexes are divided into four cate-gories, namely, basic, design, construction, and consequenceindexes.Thediversity of subway constructionmethods causesthe indexes to be different in the different constructionmethods. In this paper, the shield method of construction isutilized as an example.

The basic indexes mainly refer to the attributes of engi-neering that cannot be routinely changed and are beyondthe control of the operators. These attributes are determinedimmediately after line selection, which considers existinghydrological conditions [14, 15], geological conditions [16],surrounding environment conditions, and tunnel parametersincluding the size of the tunnel, slope, turning radius, and soon [17].

“Design” in this paper refers to the idea that can preventthe risks caused by the basic indexes and provide convenienceand guidance in the construction process. It is the precondi-tion of construction. In view of the characteristics of shieldtunneling, the main design indexes include the following:reinforced design, environmental protection design, precip-itation design, construction method design, shield machinedesign, and segment design [18].

The construction indexes mostly focus on managementand operation during the period of construction.Theymainly

The Scientific World Journal 3

include the selection of construction methods and level ofconstruction technology, analysis of the influence of the con-struction period, specification of the external constructionenvironment, and control measures.

The consequence indexes include five aspects, namely,environmental loss, economic loss, social loss, casualties, andconstruction time loss.

The definition and relationship of these four kinds ofindexes are shown in Figure 1.

3.2. Risk Assessment Model. The most commonly accepteddefinition of risk is often expressed as a mathematical equa-tion:

𝑅 = 𝑓 (𝑃, 𝑐) , (1)

where 𝑅: risk; 𝑃: event probability; 𝑐: event consequence.Considering the basic model, the index method model

can be expressed as

𝑅 = 𝑃 × 𝑐,

𝑃 = 𝑓1(𝐵,𝐷, 𝐶) ,

𝑐 = 𝑓2(consequences index) ,

(2)

where 𝐵: basic index;𝐷: design index; 𝐶: construction index.In the above expression, 𝑃 does not represent the exact

probability, only the probability index. The scope of 𝑃 isnot from 0 to 1; however, its value contains the meaningof probability and has a positive correlation with the realprobability (the higher the value, the greater the probabilityof risk).

The probability index is composed of the basic, design,and construction indexes. The consequence index representslosses caused by an accident or accidents, as shown inFigure 2.

3.3. Probability Index Model. The probability index is animportant part of risk. The combined form of the probabilityindex is obtained in this study. Different accidents havedifferent risk occurrencemodes because accidents occur withdifferent mechanisms. The indexes that can cause accidentsare related and cannot be studied independently.

Considering the characteristics of subway construction,the occurrence modes of disastrous accidents can be con-cluded as follows.

3.3.1. Design Indexes-Insensitive Mode. This mode considersthe basic index as a risk source, together with improperconstruction management and operation, which leads to theoccurrence of the risk. The design index does not often workin accidents. For example, the factors of shield axis riskcontrol such as uniformity of formation, tunnel slope, andturning radius are mainly basic indexes; the constructionindexes including the construction level, experience, anddesign indexes have a very insignificant relationship with therisk.

3.3.2. Basic Index-Insensitive Mode. The risk of the occur-rence of accidents in this mode has no relationship with thebasic indexes; the occurrence is mainly caused by improperdesign and construction. For example, the deformation ordamage to the base in the shield moving-out constructionis mainly caused by the poor design safety coefficient andimproper operation.

3.3.3. Comprehensive Mode. The above two models involveonly two types of indexes; however, most accidents occurbecause of the combined action of the attributes of the tunnel(strata, environment, tunnel diameter, buried depth, andothers), design factors, and construction factors. These threekinds of indexes compose a relationship chain. The probabil-ity value changes when one of the indexes changes, such asthe risk of collapse, during shield moving-out construction.

The above three occurrence modes are the bases of riskassessment for an accident. An accident may involve one ormore modes. The fault tree analysis method can be used todetermine the accident occurrence mode.

The probability calculation model is obtained based onthe above three modes.(a) Design Indexes-Insensitive Mode. The probability index isaffected by the basic and construction indexes. In view ofthe influence of the construction indexes on probability, theconstruction coefficient 𝐶

𝑘is introduced:

construction coefficient 𝐶𝑘

=construction index C

construction standard value Cs,

(3)

where the construction standard value is a constant setin advance. It represents the construction level in generaland does not reduce nor increase the disastrous accidentprobability.

The risk probability is given by

𝑃 = 𝐵 × 𝐶𝐾= 𝐵 × (

𝐶

𝐶𝑆

) . (4)

The value of the construction coefficient is about 1. If thevalue is greater than 1, the construction increases the risk ofaccidents and vice versa.(b) Basic Index-Insensitive Mode. Similar to the design index-insensitivemode, the construction coefficient𝐶

𝑘and the con-

struction standard value 𝐶𝑠are introduced. The calculation

model is defined as

𝑃 = 𝐷 × 𝐶𝐾= 𝐷 × (

𝐶

𝐶𝑆

) . (5)

(c) Comprehensive Mode. The design coefficient 𝐷𝐾

andconstruction coefficient 𝑆

𝑘are introduced:

design coefficient 𝐷𝐾=

design index 𝐷design standard value 𝐷

𝑠

. (6)

The calculation model of this mode is given by

𝑃 = 𝐵 × 𝐷𝑘× 𝐶𝑘. (7)

4 The Scientific World Journal

Basic index Design index Construction index Consequences index

LossAttributes Response Guide Operation

Figure 1: Relationship between indexes.

Basic index Design index Construction index

Consequencesindex

Risk

Probability index

Figure 2: Improved index method model.

3.4. Combining the Basic Indexes and Design Indexes. Thesimplest method to combine the basic and design indexes isto consider them separately and then establish the basic indexvector. One has

𝐵 = [𝐵1, 𝐵2, 𝐵3, 𝐵4⋅ ⋅ ⋅ 𝐵𝑚] , (8)

where 𝐵i represents the 𝑖th basic index.To establish the design index vector, the following equa-

tion is utilized:

𝐷 = [𝐷1, 𝐷2, 𝐷3, 𝐷4⋅ ⋅ ⋅ 𝐷𝑛] , (9)

where𝐷𝑗represents the 𝑗th design index.

The results of the calculation can be expressed as

sum (𝐵) × sum (𝐷)(𝑛 × 𝐷

𝑠). (10)

In cases where the basic and design indexes are interre-lated, this simple calculation method is feasible. However, inpractical engineering, several design indexes may not affectall basic indexes. Considering the foundation consolidationrisk in the shieldmoving-out construction as an example [18],different reinforcement designs have different effects. Severalof these designs do not reduce the risk caused by several basicindexes, as shown in Figure 3. When the above calculationis used, the risk may appear to be lower or higher. Thus, thematrix𝐾

𝑚,𝑛is introduced to solve this problem:

𝐾(i, 𝑗) ={{{{

{{{{

{

0, the 𝑖th basic index does notaffect the 𝑗th design index,

1, the 𝑖th basic index affectsthe 𝑗th design index,

(11)

where 𝑖 = 1, 2, 3, . . . , 𝑚, 𝑗 = 1, 2, 3, . . . , 𝑛.

Table 2: Indicators of economic losses.

Disaster grade Disastrous Veryserious Serious Moderate Slight

Economic loss(¥ ×million) >10 3–10 1–3 0.3–1 <0.3

Score 20 16 12 8 4

The results of the calculation can be expressed as

𝐵𝑚× 𝐾𝑚,𝑛× (𝐷

𝐷𝑠

) . (12)

3.5. Consequence Indexes. The indicators of the five kinds oflosses can be obtained according to the literature [6]. Theeconomic losses are utilized as an example, as shown inTable 2.

4. Risk Assessment Process

Disastrous accidents are risk assessment subjects. The initialsteps are to identify the disastrous accidents that happenin subway engineering, to understand the risk occurrencemechanism, and to conduct risk assessment. The fault treeanalysis method is a good way to recognize the accidentoccurrence mechanism. It can be used with other riskassessment methods. The basic events in an accident can beobtained by utilizing the fault treemethod.Through the studyof these basic events, the relationship between the accidentand the indexes could be determined, the risk occurrencemode could be obtained, and the calculation model would beprovided. The risk assessment process is shown in Figure 4.

5. Risk Acceptance Criteria

In accordancewith the scoring rules and characteristics of theindex method, the risk acceptance criteria are determined.The risk level is divided into four grades, namely, unaccept-able, unwilling to accept, acceptable, and negligible, as shownin Table 3.

6. Case Study

The risk assessment conducted for the river-crossing tunnelconstruction of Nanjing subway line 10 was utilized as anexample. The basic introduction of the tunnel is shown inTable 4.

6.1. Risk Assessment. The first step in risk assessment is riskidentification, which aims to predict potential accidents and

The Scientific World Journal 5

Risk events in the shieldmoving-out constructionFoundation consolidation

method

Freezing method

Mixing pile

Precipitation

Tunnel face stability in portal part

Stratum settlement in portal part

Water leakage

Fail to keep slurry balance

Shield machine subsidence

Chemical churning pile

Figure 3: Relationship between formation reinforcement design and risk events.

Risk

Index methodAccident

Building fault tree

Analyzing faulttree

Basic events

Relationshipbetween accident

and indexes

Relationshipbetween basic events

and indexes

Risk occurrencemode

Calculation model

Riskprobability

index

Establishmentof the scoring

rules

Risk consequenceindex

Figure 4: Risk assessment process diagram.

to determine the factors of these accidents. A longer tunnelmay be divided into several sections according to the strataconditions before risk identification. The conditions of thetunnel’s environment are affected by shield tunneling.

As the conditions along the subway line’s route change, sodoes risk. Risk is not constant. Therefore, examining a longtunnel in shorter sections is more efficient.The risk evaluatormust decide on a strategy to create sections to obtain anaccurate risk value. Each section has its own risk assessmentresults. Breaking the subway line into many short sectionsincreases the accuracy of the assessment for each section,but may result in higher costs of data collection, handling,and maintenance. Longer sections (fewer in number), on

the other hand, may reduce data costs, but may also reduceaccuracy because the average or worst case characteristicsdominate if the conditions change within the section [9].

The considered attributes in sectioning or segmenting thetunnel include

(i) strata characteristics,(ii) environment conditions,(iii) buried depth.

The next step is to identify the risk and risk factors.The risk identification process is shown in Figure 5. Themain steps are collecting data, making the questionnaire,

6 The Scientific World Journal

Table 3: Risk acceptance criteria.

Risk value Risk grade Risk acceptancelevel Response principle

0–1600 IV Negligible Risk management canbe implemented.

1600–3600 III Acceptable

Risk management canbe implemented, andrisk managementmeasures can betaken.

3600–4800 II Unwilling toaccept

Risk managementshould beimplemented toreduce the risk, butthe cost of reducingthe risk must not behigher than the riskloss.

>4800 I Unacceptable

Risk managementmeasures must betaken to reduce therisk to grade II.

Table 4: Basic introduction of the tunnel.

Tunnel mileage K11 + 251–K14 + 857Tunnel design Single tunnel, double trackTunnel diameter (outer/inner) 11.2/10.2Tunnel buried depth 5m to 35mShield type Slurry shield

Stratum silt layer, fine sand; 4-4e1round gravel layer

Depth of river 0m to 25.5mPermeability coefficient 5.43× 10−7 to 8.87× 10−4 cm ⋅ s

identifying the risk, and giving opinions and suggestions [19].Three persons are involved in the risk identification process,namely, the risk evaluator, the expert, and the technologyperson or operators. The risk evaluators, who function asguides, collect data, make the questionnaires, and send thequestionnaires to the experts for risk identification. Theexperts, as important participants, utilize their experienceand finish the questionnaires. The technology person oroperators, as the personnel in charge of practical engineering,give their opinions and suggestions on the identified risks,which are obtained by synthesizing the opinions of theexperts. Based on the investigation, environment survey,shield selection, and preliminary design data, the risks insections are identified and are shown in Table 5.

The fault tree and index methods are utilized to analyzeand assess the accidents. Face instability, which is the mostnotable accident, is used as an example.

Based on the fault tree, the risk occurrence mode of faceinstability and the related basic, design, and constructionindexes can be obtained. The results are shown in Table 6.

Table 5: Risks or accidents identified in Section 3.

No. Risk/accident1 Face instability2 Cutter head and tool wear3 Large size bearing breaking4 Failure of bearing seal5 Failure of hoisting jack6 Mud cake7 Clogging at the exit of slurry8 Failure of tail skin brush9 Failure of pushing axis control10 leakage water at the segment11 Failure of segment erection12 Segment uplift13 Jammed grouting pipe14 Bad grouting effect

Table 6: Risk occurrence mode of face instability and the relatedindexes.

Occurrence mode Comprehensive modeRelated indexes

Basic indexes (no.)

Affects the limit support stressratio (B1)Change of strata (B2)Overbreak of the affected strata(B3)

Design indexes (no.)

Shield-excavating equipmentdesign (D1)Shield-pushing equipmentdesign (D2)Strata adaptability of the shield(D3)

Construction indexes (no.)

Level of the constructiontechnology (C1)Construction period (C2)Construction environment (C3)Control measures (C4)

The limit support stress ratio is the ratio of the value of limit support stressto original lateral geostress, where the limit support stress refers to theminimum stress that can support face stability.

6.2. Key Parameters in the Probability Index

(a) Standard value. The score scope, design standardvalue, and construction standard value are deter-mined and shown in Table 7 in accordance with therisk calculation model.

(b) 𝐾m,𝑛. Based on the construction experiences and thecomprehensive scoring of the expert, the weights ofeach basic and design index and the relationshipbetween the basic and design indexes are determinedand shown in Figure 6.

In Figure 6, the meaning of 𝐵1, 𝐵2, 𝐵3, 𝐷1, 𝐷2, 𝐷3,

𝐷4, 𝐶1, 𝐶2, 𝐶3, and 𝐶

4can be got from Table 6, and

the length of the column represents the weights. The

The Scientific World Journal 7

Data collection Making questionnaire Identifying risk Giving opinionsand suggestions

Technology personor operatorsExpertRisk evaluator

Figure 5: Risk identification process.

Table 7: Several key parameters.

Indexes Scorescope Notes

Basic indexDesign indexConstruction index𝐷𝑘

𝑆𝑘

0–1000–100>05050

If the score is lower, theprobability index is alsolower. The constructionindex is unlimited, whichshows that even though thebasic index is not large, thepossibility of an accidenthappening would still behigh in poor constructionconditions.

connecting line indicates the correlation between thedesign and basic indexes.

Thus, we obtain

𝐾m,𝑛 is [

[

1 0 1

0 1 1

1 0 0

]

]

. (13)

(c) Weights. Obtaining the weights of the indexes is avery important task in risk assessment. The resultsof existing research and advanced study methods arefully utilized to obtain the weights. The factors thataffect the limit support stress ratio, according to theresults of existing research, mainly include the burieddepth of the tunnel, friction angle and cohesion ofthe soil, and depth of the groundwater and river.However, no data provide the weights of these factors.

The numerical simulation method is used to obtain theweights in this study. The simulation model is shown inFigure 7, which also contains the effects of the abovemen-tioned factors on the limit support stress ratio.

From the numerical simulation results, increasing theburied depth, friction angle, and cohesion reduces the limitsupport stress ratio. However, increasing the depth of theunderground water and the river increases the limit supportstress ratio. Groundwater depth has the biggest impact onlimit support stress ratio, followed by river depth, burieddepth, cohesion, and friction angle. The weights of thesefactors are shown in Table 8.

100

0

B1

B2

B3

D1

D2

D3

C1

C2

C3

C4

Figure 6: Relationship between the basic and design indexes.

Depth of river

Buried depth

CohesionFriction angle

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

0 10 20 30 40 50

Lim

it su

ppor

t stre

ss ra

tio

Depth of underground water

Figure 7: Simulation model and results.

8 The Scientific World Journal

Table 8: Weights of the factors that affect the limit support stressratio.

Factor WeightRiver depth 0.13Buried depth 0.11Friction angle 0.05Cohesion 0.07Depth of underground water 0.64

Risk

scor

es

50004000300020001000

01 2 3 4 5 6 7 8 9 10 11 12

Risk number

Section 1Section 2Section 3Section 4

Section 5Section 6Section 7

Figure 8: Accidents and risk scores in the different sections.

6.3. Summary of Results and Analysis. Based on the three keyparameters, risk assessment can be finalized after establishinga scoring rule. The accidents and the types of risks in eachsection must be provided.

The accidents and risk scores in each section are shown inFigure 8. In the figure, the risks which are represented by risknumber are shown in Table 5. These data are considered asthe preliminary risk assessment results.They do not considerthe influence of construction. The construction indexes aredifficult to evaluate before the construction period becausethe construction index is more dependent on the attitudeof the construction personnel (whether or not the construc-tion personnel are active and conscientious). The results inFigure 8 reflect the influence of the basic and design indexes.The risk assessment is conducted to inform the constructionpersonnel what risks they should pay more attention to andwhat measures to take. The risk events that have high scoresare face instability, tool wear, and shield tail seal failure.We suggest that construction personnel pay special attentionto these three risk events in the shield-driving process andprepare risk control measures.

During the construction period, the score of the construc-tion indexes is obtained according to the measures that theconstruction personnel have taken and their attitude.The riskprobability indexes in the preliminary risk assessment and theconstruction process (including the construction indexes) areshown in Figure 9. The shadow in Figure 9 represents theinfluence of the construction index.The arrowheads indicatethe increase or decrease in the index score. An upwardarrowhead means the score increases, whereas a downwardarrowhead means the score is reduced. The probability indexalmost decreases because several measures have been takento reduce the risk and more attention has been given tothe risk events. However, for the face instability risk event

100

80

60

40

20

0Face instability

Risk events

Prob

abili

ty in

dexe

s sco

res

120

Section 1Section 2Section 3Section 4

Section 5Section 6Section 7

Cutter headand tool wear

Failure of tailskin brush

Figure 9: Risk probability index in the preliminary risk assessmentand construction process.

in Section 1, the index increases because when tunnelingbegins, the operators of the shield machine need to adaptto the performance of the machine itself. They adjust andoptimize the shield-tunneling parameters by monitoring thedata until it achieves the optimum result. During this period,the construction increases the probability index.

Construction information is provided to verify the valid-ity of this study’s risk assessment model. Throughout theconstruction period, the face instability risk event does nothappen. This finding is consistent with our risk assessmentresults. For the aforementioned risk event, the scores inmost of the sections are around 40, which indicate that theprobability is between “rarely” and “occasionally.” Only thefirst section has the score of about 60, which means thatthe event is close to “possible” but the probability is still“occasionally.” The frontal soil deformation of the tunnelingface reflects the probability of the risk. The deformationvalues in the different sections are shown in Figure 10. At theinitial point of 100m, the range of the deformation valuesis between −30mm and 10mm. The deformation values atthe other points are around −20mm to 10mm, and most ofthem are around −10mm to 5mm.The above analysis showsthat the construction indexes affect the probability of the riskevent. The changing trend is consistent with the result of therisk assessment.

The values of segment uplifting are also provided toverify the assessment model for the risk events, as shownin Figure 11. The segment-uplifting values are within therange of −10mm to 30mm, which is acceptable according tothe code for the construction and acceptance of the shield-tunneling method [20].

Based on the monitoring data, risk assessment can beapplied in subway construction. This assessment indicateswhich risks the construction personnel are not willing toaccept, those they can accept, and those they ignore.

The Scientific World Journal 9

2010

0−10

−20

−30

−40

−50

0 100 200 300 400 500 600Def

orm

atio

n va

lues

Tunneling distance (m)

Figure 10:The frontal soil deformation values of the tunneling face.

604020

0−20

0 500 1000 1500 2000 2500 3000 3500Tunneling distance (m)

Upl

iftin

g va

lues

of

segm

ent

Figure 11: Values of segment uplifting.

7. Conclusion and Discussion

The purpose of this paper is to establish a qualitative-quantitative risk assessment model. The risk events changeas the external environment changes; thus, the probabilityof the risk events happening also changes. If the value ofthe change is not large, adjusting the risk score by using thequalitative analysis method becomes difficult. With regardto general qualitative risk assessment, this study’s modelshould easily adapt to the dynamic changes of the risk. Withregard to general quantitative risk assessment, this modeldoes not need to obtain the “real” probability, a process whichcosts much money. The probability index can be obtainedby substituting the data in the scoring model with the dataobtained from an existing document or information. Ourassessmentmodel can be compared to a thermometer and therisk value to temperature. The thermometer indicates whatclothes people shouldwear; similarly, through our assessmentmodel, construction personnel are informed of the safetysituation and also the risks involved. Thus, the constructionpersonnel would know how to respond in case an accidentoccurs.

An improved index method is established to address theabove purpose. Four kinds of indexes are considered in theimproved method, namely, (1) basic, (2) design, (3) construc-tion, and (4) consequence indexes. Indexes (1), (2), and (3)constitute the probability index, and the calculation modelof which is provided based on three accident occurrencemodes. Considering the correlation between the basic andthe design indexes, the coefficient matrix 𝐾

𝑚,𝑛is introduced.

The basic index model is then finalized. Different risk eventshave different occurrence mechanisms and risk factors.Thus,no single formula can express the relationship between therisk index and the known parameters. In this paper, therisk assessment for the river-crossing tunnel construction ofNanjing subway line 10 was utilized as an example, and faceinstability as a risk event was discussed in detail.

This risk assessment model can be applied to the assess-ment of disastrous accidents in the design and constructionstages. In the design stage, the results of risk assessment canbe obtained without considering the construction indexes.The results of risk assessment can be an important referencein the selection of design schemes. The construction indexesare considered in the construction stage. Based on the currentconstruction conditions, a dynamic risk assessment wascarried out for dynamic security control during the periodof construction.

This risk assessment model has been verified by theNanjing subway engineering. When the risk occurrencemechanism is not completely clear, the analysis of the riskevents still relies on previous engineering experience, whichis very crucial for the reliability of the index model. JohnHudson, a famous British geotechnical engineering expert,talked about the importance of “collective memory” in theInternational Top-Level Forum on Engineering Science andTechnology Development Strategy-Safe Construction andRisk Management of Major Underground Engineering [21].He suggested that previous engineering data and experienceshould be sorted to establish a big shared database. Theauthors think that the establishment of this database is veryimportant for the ongoing development of risk assessmentmethods.

Acknowledgment

This project was supported by the Science Fund for CreativeResearch Groups of the National Natural Science Foundationof China (no. 51021001).

References

[1] Q. H. Qian, “Continuous citifying and utilizing urban under-ground space,” World Sci-Tech R and D, vol. 20, no. 3, pp. 4–9,2003 (Chinese).

[2] Q. Qian and X. Rong, “State, issues and relevant recommen-dations for security risk management of china’s undergroundengineering,” Chinese Journal of Rock Mechanics and Engineer-ing, vol. 27, no. 4, pp. 649–655, 2008 (Chinese).

[3] S. D. Eskesen, P. Tengborg, J. Kampmann, and T. HolstVeicherts, “Guidelines for tunnelling risk management,” Tun-nelling andUnderground Space Technology, vol. 19, no. 3, pp. 217–237, 2004.

[4] H. H. Choi, H. N. Cho, and J. W. Seo, “Risk assessment meth-odology for underground construction projects,” Journal ofConstruction Engineering and Management, vol. 130, no. 2, pp.258–272, 2004.

[5] H. W. Huang, “State-of-art of the research on risk managementin construction of tunnel and underground works,” Proceedingsof RiskManagement onMetro andUnderground Projects, pp. 16–26, 2005 (Chinese).

[6] Ministry of Housing and Urban-Rural Development of China,Code for Risk Management of UndergroundWorks in Urban RailTransit, Guangming Daily Publishing House, Peking, China,2011.

[7] M. L. Lu, “Review on risk assessment methods for tunnellingand underground projects,” Journal of Engineering Geology, vol.14, no. 04, pp. 0462–0469, 2006 (Chinese).

10 The Scientific World Journal

[8] M. H. Faber and M. G. Stewart, “Risk assessment for civil engi-neering facilities: critical overview and discussion,” ReliabilityEngineering and System Safety, vol. 80, no. 2, pp. 173–184, 2003.

[9] W. Kent Muhlbauer, Pipeline Risk Management Manual Ideas,Techniques, and Resources, Gulf Professional Publishing, Hous-ton, Tex, USA, 3rd edition, 2004.

[10] G. X. Zhou, “An accident happened in Guangzhou metro con-struction, and caused one death,” 2004 http://news.sohu.com/2004/03/19/78/news219497815.html.

[11] X. G. Luo, “collapse accident happened in construction of 10 lineof Beijing subway,” 2007, http://news.xinhuanet.com/politics/2007-05/08/content 6071419.htm.

[12] Nanjing Morning News, “Collapse Leads to Natural Gas Explo-sion inNanjing Subway Tunnel,” 2007, http://news.sina.com.cn/c/p/2007-02-06/031812237328.html.

[13] X. C. Wang, “Hangzhou subway collapse accident is recognizedas a major liability accident,” 2010, http://news.xinhuanet.com/society/2010-02/09/content 12961265.htm.

[14] F. Pellet, F. Descoeudres, and P. Egger, “The effect of water seep-age forces on the face stability of an experimental microtunnel,”Canadian Geotechnical Journal, vol. 30, no. 2, pp. 363–369, 1993.

[15] W. Broere, “Influence of excess pore pressures on tunnel facestability,” in (Re)Claiming the Underground Space, J. Saveur, Ed.,pp. 759–765, International Tunnelling Association, Swets andZeitlinger, 2003.

[16] P. D. Buhan, A. Cuvillier, L. Dormieux, and S. Maghous, “Facestability of shallow circular tunnels driven under thewater table:a numerical analysis,” International Journal For Numerical andAnalytical Methods in Geomechanics, vol. 23, pp. 79–95, 1999.

[17] Y. Li, “Stability analysis of large slurry shield-driven tunnel insoft clay,”Tunnelling andUnderground Space Technology, vol. 10,pp. 1–10, 2008 (Chinese).

[18] JSCE, Tunnel Standard Code and Commentary, China BuildingIndustry Press, Peking, China, 2011.

[19] C. B. Chapman and S. Ward, “Project risk managementprocesses,” in Techniques and Insights, John Wiley & Sons,Chichester, UK, 1997.

[20] Ministry of Housing and Urban-Rural Development of China,Code for Construction and Acceptance of Shield TunnellingMethod, China Building Industry Press, Peking, China, 2008.

[21] A. John Hudson, “Design methodology for the safety of under-ground rock engineering,” in Proceedings of the InternationalTop-Level Forum on Engineering Science and Technology Devel-opment Strategy-Safe Construction and Risk Management ofMajor Underground Engineering, Wuhan, China, 2012.

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

RoboticsJournal of

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Active and Passive Electronic Components

Control Scienceand Engineering

Journal of

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Hindawi Publishing Corporation http://www.hindawi.com

Journal ofEngineeringVolume 2014

Submit your manuscripts athttp://www.hindawi.com

VLSI Design

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Shock and Vibration

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Civil EngineeringAdvances in

Acoustics and VibrationAdvances in

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Electrical and Computer Engineering

Journal of

Advances inOptoElectronics

Hindawi Publishing Corporation http://www.hindawi.com

Volume 2014

The Scientific World JournalHindawi Publishing Corporation http://www.hindawi.com Volume 2014

SensorsJournal of

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Modelling & Simulation in EngineeringHindawi Publishing Corporation http://www.hindawi.com Volume 2014

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Chemical EngineeringInternational Journal of Antennas and

Propagation

International Journal of

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

Navigation and Observation

International Journal of

Hindawi Publishing Corporationhttp://www.hindawi.com Volume 2014

DistributedSensor Networks

International Journal of