Study on Asphalt Pavement Technologies - CRP · Study on Asphalt Pavement Technologies Targeting...
Transcript of Study on Asphalt Pavement Technologies - CRP · Study on Asphalt Pavement Technologies Targeting...
Study on Asphalt Pavement Technologies Study on Asphalt Pavement Technologies Targeting the Prevention of Global Warming Targeting the Prevention of Global Warming
Masahiko Iwama, Tamotsu Yoshinaka, , Tamotsu Yoshinaka, Shinobu Omoto and Nobuyuki NemotoShinobu Omoto and Nobuyuki Nemoto
International Road Federation International Road Federation 1616th th World MeetingWorld Meeting
May 25th to 28th 2010, Lisbon, Portugal
Outline of Presentation
� Use of Warm-Mix Asphalt- Basic concept- Laboratory test results- Laboratory test results- CO2 reduction at paving work
� Solar Heat-blocking Pavement- Basic concept- Effect of temperature reduction- Case study (Airport taxiway)
� Conclusions
Warm-mix Asphalt - Background -
Warm-Mix Asphalt:- Reduction in CO2
- Improvement of workability, especially in winter- Improvement of workability, especially in winter• In 1997, NIPPO developed the additive agent
called “ECOFINE”• It can be used for both straight and modified
asphalts• 30 °°°°C to reduction in mixing temperature was
achieved
What is ECOFINE ?Forming-based special additive agent for WMA technologyProduction: Fine forms occur in bitumen
A volume of bitumen increases considerablyWorkability of bitumen will be improved
Laying: Good compaction is achieved by “bearing effect”
●
Laying: Good compaction is achieved by “bearing effect”Roller Compaction
Asphalt mixture
Coarse aggregate Mastic
Fine forms
Properties of ECOFINE-Micro-form generation-
• Add the agent of 2 kg/ton • Keep forming state for a long duration;
• Laboratory: Approx. 120 min.• Site: 4 to 5 hours• Site: 4 to 5 hours
Special Additive
100
200
300
400
0 20 40 60 80 100 120 140
Bit
um
en %
by
Vo
lum
e
Duration Time of Foaming (min.)
Foaming Agent only
Special Additive
Straight Asphalt 60/80, 130°CSpecial Additive : 7% by mass of bitumen
Warm-mix AsphaltLaboratory test results
100
101
102
103
Co
mp
acti
on
Deg
ree
(%)
■■■■ ECOFINE■■■■ Without Additive
Dense Asphalt Concrete / Max.Size13mmStraight Bitumen 60/80Mixing Temp. : 130℃
Normal Asphalt MixtureMixng Temp. : 160℃Compac.Temp. : 140℃
95
96
97
98
99
100
707070708080808090909090100100100100110110110110120120120120130130130130
Co
mp
acti
on
Deg
ree
Compaction Temperature (℃℃℃℃)
Mixing Temp. : 130℃
Warm-mix AsphaltLaboratory test results
1.4
1.8
2.2
10 10 10 10 12 12 12 12 14 14 14 14 16 16 16 16
Rav
ellin
g A
bra
sio
n (
cm2 )
Mar
shal
l Sta
bilit
y M
arsh
all S
tabi
lity
Mar
shal
l Sta
bilit
y M
arsh
all S
tabi
lity (
kNkN kNkN) Dense Asphalt Concrete / Max.
Size13mm Straight Bitumen 60/80
0.2
0.6
1
1.4
0 0 0 0 2 2 2 2 4 4 4 4 6 6 6 6 8 8 8 8
10 10 10 10
Normal Asphalt Mixture
ECOFINE 30℃℃℃℃ Lower
Without Additive 30℃℃℃℃ Lower
Rav
ellin
g A
bra
sio
n
Mar
shal
l Sta
bilit
y M
arsh
all S
tabi
lity
Mar
shal
l Sta
bilit
y M
arsh
all S
tabi
lity
Stability
RavellingAbrasion
ECOFINE
Simplification of paving equipment train:CO2 reduction at paving work
� Simplified compaction train was examined
Section A (Control)Mixture: at normal temp. without additiveRollers: 10 t macadam roller +
pneumatic tired roller
Section B (Trial)Mixture: at normal temp. with additiveRollers: 6 t combined roller
100 m 100 m
3.75 mPlane figure
Construction condition and test resultsType of Mix.
ItemsSurface Mixture Type 20
Applied Section A (Control) B (Simplified)
Special Addition 0 3.5
Mixing Conditions
Capacity of Mixer 2,000 kg/batch
Dry Mixing Time (sec) 10
Wet Mixing Time (sec) 36Conditions Wet Mixing Time (sec) 36
Mixing Temp. (゚C) 160
Compaction (time)
Macadam Roller 3 -
Pneumatic Tired Roller 7 -
6 t Combined Roller - 11
Cored SampleDensity (g/cm3) 2.339 2.324
Air Void (%) 4.8 5.4
Compaction Degree (%) 98.9 98.6
Evenness (σ) (mm) 0.79 0.78
CO2 reduction at paving work- Calculated CO2 emission -
PneumaticTired Roller40
50
60
Dis
char
ge
(kg/h)
52.9 ((((kg/h))))
53%
• Approx.53% of CO2 reduction can be saved thanks to the special additive
AsphaltPaver
4 tonCombined Roller
AsphaltPaver
MacadamRoller
0
10
20
30
40
Cal
cula
ted
CO
22 22 D
Simplified Normal Combination
24.8 ((((kg/h))))
Solar HeatSolar Heat--blocking Pavementblocking Pavement
Solar Heat-blocking Pavement- Background -
Urban areas and pavements in JapanUrban areas and pavements in Japan� Surface temperatures of asphalt pavement reach
60゚゚゚゚C or higher in summer Asphalt surfaces cover approx. 20% of urban areas � Asphalt surfaces cover approx. 20% of urban areas
� Pavement is a source of heat, similar to concrete structures
Hotter pavement:Hotter pavement:- leads to the urban heat island phenomenon- may affect the heath of pedestrians due to the
higher temperatures
Basic concept of solar reflective technology
Surface course of hot mix asphalt
◆◆◆◆ Low reflection for the visible rays
◆◆◆◆ High reflection for the near infrared raysSolar radiation
Hollow ceramic particle Highly reflective pigment
Aggregate
Asphalt
Apply high albedo and dark colored
thin treatment materials
Component of hot mix asphalt
Albedo characteristics of treatment materials
60
80
100
Alb
edo
(%
)Visiblerays
Near-infrared rays
New surface treatment materials L*40(dark gray)
Albedo: Degree of reflection
�Straight asphalt has a very low albedo�Dark-gray treatment materials have a low albedo for visible rays, but
a very high albedo (about 90%) for near-infrared rays
0
20
40
60
400 600 800 1000 1200 1400 1600 1800 2000 2200500 1000 1500 2000
Alb
edo
(%
)
Wavelength (nm)
Normal paint materials L*40(dark gray)
Straight asphalt 60/80
Performance of heat blocking pavement
40
50
60
70S
urfa
ce te
mpe
ratu
re (
C゚) 8/11 - 8/13 2004 Kyoto
16゚゚゚゚C
Dense graded surfaceSolar heat-blocking pavement
Max. air temperature:37.8゚C
10
20
30
Sur
face
tem
pera
ture
8/11 8/12 8/130:00 0:00 0:00
Ambient temperature
� The maximum temperature of the conventional pavement rose to 57.4゚゚゚゚C
� The temperature of the treated surface was reduced by about 16゚゚゚゚C
Case study- Rutting mitigation at airport taxiway -
B’-runway
Construction area
Narita International Airport
3
63 2
4
1
0
25
B747
A300
MD11
B757
B737
A320,,,,310 Other
Small11%%%%
A380≒≒≒≒0
Size:
� Temperatures both in conventional surface and S.H.P. were measured at 20 mm, 80mm and 200mm below the surface
Terminal 1, 2
A-runway
area
Garage
12
19
25
B777
A340,,,,330
B767
Large62%%%%
Middle27%%%%
Size:
Temperature of pavements
Surface (20 mm below)
010203040506070
Max
. tem
pera
ture (°C
)
12 3 6 9 12 3 6 9 12 3 6 9 120 12 24 36
Max
. tem
pera
ture
12 3 6 9 12 3 6 9 12 3 6 9 12
Milled Surface (200 mm below)
010203040506070
0 12 24 36
Max
. tem
pera
ture (
°C) Conventinal
S.H.PAmbinet temp.
12 3 6 9 12 3 6 9 12 3 6 9 12
2006 2007 2008
Month
30
40
50
30
40
50
Rut
dep
th (
mm
)
Max
. ru
t dep
th (
mm
)
Rut depth (S.H.P.) Rut depth (Conventional)
Max. rut depth (Conventional)
34Max. rut depth (S.H.P.)
Differences of rut depth
0 0 0 1 00 0 0 1 00
10
20
30
0
10
20
30
2 months 1 year 1.5 years 2 years 2.5 years 3 years 3.5 years 4 years 4.5 years
Rut
dep
th (
mm
)
Max
. ru
t dep
th (
mm
)
2006.7 2007 2008 2009
16
After
Conclusions
� The application of micro-forms WMA(ECOFINE) enables the production and laying temperature to be 30 °°°°C lower than normal bitumen.
� Approx. 50% of CO2 generation can be reduced by � Approx. 50% of CO2 generation can be reduced by decreasing the number and size of rollers.
� The reduction in surface temperatures for the heat-blocking pavement is approximately 16 °°°°C .
� This technology would be effective to the rutting as the rate of rut depth was approximately a half, compared to the dense-graded asphalt surface at the taxiway .
Thank youThank youThank youThank you
Properties of ECOFINE Estimated CO2 emission; 30 to 50 °C reduction
20
22
Dis
char
ge
(kg/ton)Asumption for calculation : Moisture content % agg. : 3% Ambient Temp. : 30゚゚゚゚C
14
16
18
100110120130140150160170180
M ixing Temperature (゚゚゚゚C )
Est
imat
ed C
O2
D
14%23%
Case studies- Highway maintenance -
• Divided the maintenance area into 4 sections
• Compared construction time between Control and ECOFINE sections in surface, binder course and L.S.M.
L = 400 m
Section A (ECOFINE)
Section B(Control)
Section C(ECOFINE)
Section D(Control)
Surface
Binder course
Surface
Large Stone Mix (L.S.M.)
2 cm
3 cm
2 cm
5 cm
W=3.5 m
t = 4 cm
t = 10 cm
L = 400 m
: Thermo-Couple
Plane figure
Sectiont = 6 cm
Case studies - Highway maintenance -
Mixture Surface Binder course Large Stone Mix.
Control ECO ECO FINEFINE
Control ECO ECO FINEFINE
Control ECO ECO FINEFINE
ItemFINEFINE FINEFINE FINEFINE
Density (g/cm3)
2.314 2.309 2.369 2.363 2.379 2.378
Air Void (%)
5.7 5.9 4.1 4.3 4.6 4.6
Compaction Degree (%) 97.7 97.5 100 99.8 99.0 99.0
Case studies - Highway maintenance -
Item
Section
Rut depth (mm) Evenness (mm) Skid resistance (BPN)
After construction
After 6 months
After construction
After 6 months
After construction
After 6 months
Note: Section A Surface + Binder course (ECOFINE) , B Surface + Binder course (Control)
Section C Surface + Large Stone Mix. (ECOFINE), D Surface + Large Stone Mix. (Control)
construction 6 months construction 6 months construction 6 months
A 1 1 0.86 1.03 70 72
B 2 2 0.74 0.82 73 68
C 1 1 0.98 0.84 72 70
D 1 1 0.79 0.82 74 71
Case studies - Highway maintenance - Surface & Binder courses
90
120
150
180
empe
ratu
re (
°C)
ECOFINE BinderControl BinderECOFINE SurfaceControl SurfaceExisting SurfaceAmbient Temp.
○○○○
△△△△
4cm6cm
Surface (((( TypeA ))))
Binder
Location ofThermo-Couple
Time diffrence when surface temp. is at 60°C about 50 min.
0
30
60
90
0 60 120 180 240 300 360 420 480
Time (min.)
Tem
pera
ture
(°C
)
Temp.difference of Surface Layer : about 4°C Temp.difference of Binder Layer : about 4°C
Case studies - Highway maintenance - Surface & Large Stone Mix.
90
120
150
180T
empe
ratu
re (
°C)
ECOFINE L.S.M. ((((Section C))))Control L.S.M. ((((Section B))))ECOFINE Surface ((((Section C))))Control Surface ((((Section D))))Existing SurfaceAmbient temp.
4cm
10cm
Surface(TypeⅡⅡⅡⅡ Modified B)
Large Stone Mix
●
●
Location ofThermo-Couple
Time diffrence when surface temp. is at 60°C about 70 min.
0
30
60
90
0 60 120 180 240 300 360 420 480
Time( min.)
Tem
pera
ture
(°C
)
Temp.difference of Surface Layer : about 8°C Temp.difference of Large Stone Mix : about 6°C
Environmental issuesHotter pavement:Hotter pavement:- leads to the urban heat island phenomenon- may affect the heath of pedestrians due to the
higher temperatures
Public demand to reduce the temperature of road pavementPublic demand to reduce the temperature of road pavement
Research & DevelopmentBasic conceptHighly reflective pigmentHighly reflective pigmentHighly reflective for near-infrared rays→ Prevention of heatingLow reflectivity for visible rays→ Enables various colors to be selected
Hollow ceramic particlesHollow ceramic particles- Reflect solar radiation to the atmosphere
Hollow ceramic particles
(5~150µm)
What is solar radiation?
1,500
2,000
W/m2
� Solar radiation mainly consists of visible rays and near-infrared rays and includes some ultraviolet rays
� 50% of solar energy is visible rays; the rest is near-infrared rays
0
500
1,000
150 360 750 3,000nm
VisibleVisibleraysrays
NearNear--infrared raysinfrared raysUltravioletrays
Infrared rays
NearNear--infrared raysinfrared rays
≒≒≒≒≒≒≒≒50%50%
Visible raysVisible rays
≒≒≒≒≒≒≒≒50%50%
Section of pavements
Solar Heat-blocking Pavement Conventional Surface
▲▲▲
Surface (20 mm below)Inter layer (80 mm below)
Milled surface (200 mm below)
Depth ofThermo-couple
Surface: Large stone mix. (Modified Asphalt)
Bituminous stabilization
Cement stabilization
Crusher-run
Coated layer
t= 80 mm
Binder course: Large stone mix. (Modified Asphalt) t=120 mm
t=200 mm
t=500 mm
t=300 mm
Constructionoverview
Thermo-couple