STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN...

66
SUMMER INTERNSHIP REPORT STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ESSAR POWER Jamnagar, Gujarat UNDER THE GUIDANCE OF Mr. S.K.Choudhary, Principal Director, CAMPS, NPTI & Mr.K.B.Makadia, Head,VPCL,ESSAR POWER Submitted by Abhijit Mishra ROLL NO: 02 MBA (POWER MANAGEMENT) (Under the Ministry of Power, Govt. of India) Affiliated to MAHARSHI DAYANAND UNIVERSITY, ROHTAK September- 2013

Transcript of STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN...

Page 1: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

SUMMER INTERNSHIP REPORT

STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS

POWER BY CAPTIVE POWER PLANTS

At ESSAR POWER

Jamnagar, Gujarat

UNDER THE GUIDANCE OF

Mr. S.K.Choudhary, Principal Director, CAMPS, NPTI &

Mr.K.B.Makadia, Head,VPCL,ESSAR POWER

Submitted by

Abhijit Mishra ROLL NO: 02

MBA (POWER MANAGEMENT)

(Under the Ministry of Power, Govt. of India)

Affiliated to

MAHARSHI DAYANAND UNIVERSITY, ROHTAK

September- 2013

Page 2: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

DECLARATION

I, Abhijit Mishra, Roll No.2 student of MBA (POWER MANAGEMENT) at National Power Training Institute, Faridabad hereby declare that the Summer Training Report entitled -

“STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF

SURPLUS POWER BY CAPTIVE POWER PLANTS”

is an original work and the same has not been submitted to any other Institute for the award of any other degree.

A Seminar presentation of the Training Report was made on 27 August, 2013 and the suggestions as approved by the faculty were duly incorporated.

Presentation In charge Signature of the Candidate

(Faculty)

Countersigned

Director/Principal of the Institute

ii NATIONAL POWER TRAINING INSTITUTE

Page 3: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

ACKNOWLEDGEMENT

I have taken efforts in this project. However, it would not have been possible without the kind

support and help of many individuals and organizations. I would like to extend my sincere

thanks to all of them.

I would like to thank Mr. K.B. Makadia HEAD-VPCL for showering his constant

support,guidance and helping me understand the things better in the organization.

I am highly indebted to Mr. S.K. Choudhary,Principal Director,NPTI for his guidance and

constant supervision as well as for providing necessary information regarding the project &

also for his support in completing the project.

I would like to express my gratitude towards my parents & member of VADINAR POWER

COMPANY LTD for their kind co-operation and encouragement which help me in completion

of this project.

I would like to express my special gratitude and thanks to industry persons for giving me such

attention and time.

My thanks and appreciations also go to my colleague in developing the project and people who

have willingly helped me out with their abilities.

ABHIJIT MISHRA

iii NATIONAL POWER TRAINING INSTITUTE

Page 4: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

LIST OF ABBREVIATIONS

ABT Availability Based Tariff CPP Captive Power Plant

CSS Cross Subsidy Surcharge

EA Electricity Act 2003

KW Kilowatt

MW Megawatt NEP National Electricity Policy NTP National Tariff Policy

PLF Plant Load Factor

PPA Power Purchase Agreement

REC Renewable Energy Certificate

RLDC Regional Load Dispatch Centre ROE Return On Equity RPO Renewable Purchase Obligation

RPPC Rajasthan Power Procurement Committee

SEB State Electricity Board

SLDC State Load Dispatch Centre

STU State-Tranmission Utility

TPH Tons Per Hour

CDM Clean Development Mechanism

OERC Orissa Electricity Regulatory Commission.

RVPN- Rajasthan Rajya Vidyut Prasaran Nigam Limited) iv NATIONAL POWER TRAINING INSTITUTE

Page 5: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Contents DECLARATION ................................................................................................................. ............................ ii

ACKNOWLEDGEMENT ........................................................................... .................................................... iii

LIST OF ABBREVIATIONS ....................................................................................................... ..................... iv

EXECUTIVE SUMMARY ............................................................................................... .............................. vii

ABOUT THE COMPANY ........................................................................................................... .................... 1

Chapter 1: CAPTIVE POWER PLANT .............................................................................................. .............. 3

1.1 Regulatory Provisions ....................................................................................................... .......... 4

Chapter 2: CAPTIVE POWER SCENARIO IN INDIA .................................................................................. ..... 7

2.1 CAPTIVE POWER POLICY OF DIFFERENT STATES ....................................................................... . 8

2.1.1 ORISSA ...................................................................................................................... .......... 8

2.1.2 GUJARAT .................................................................................................... ........................ 9

2.1.3 MAHARASHTRA ............................................................................................................... . 10

2.1.4 RAJASTHAN ....................................................................................................................... 11

2.1.5 WEST BENGAL ................................................................................................................. . 13

2.2 Captive Co-Generation Policy ................................................................................. .................. 14

2. Definition of Cogeneration ................................................................................ ........................... 14

3. Objectives of the Policy ................................................................................................................ 14

4. Process for creation of Cogeneration Facility ............................................................................ .. 15

5. Cogeneration Plants ..................................................................................................................... 15

6. Qualifying Requirements ..................................................................... ......................................... 15

7. Tariff fixation ........................................................................................... ..................................... 17

8. Procedure for Obtaining Qualifying Status ................................................................................ .. 18

9. Generation Schedule ...................................................................................................... .............. 18

2.3 PERMISSION AND APPROVAL: ................................................................................................ . 18

2.4 CONDITIONS FOR USAGE OF CAPTIVE POWER ....................................................................... . 20

2.5 CONCERNS: .................................................................................................... ........................... 20

2.6 ADVANTAGES: ......................................................................................................................... . 21

Chapter 3: POWER EXPORT BY CPPs (VIA OPEN ACCESS) ....................................................................... . 22

\ 3.1 INTRODUCTION ....................................................................................................................... . 22

3.2 PROBLEM STATEMENT ............................................................................................ ................. 23

3.3 SECTIONS OF EA-2003 GOVERNING OPEN ACCESS ................................................................ . 23

Captive Generation – Section 9 (2) .................................................................................................. 23

v NATIONAL POWER TRAINING INSTITUTE

Page 6: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Functions of CTU – Section 38 (2) (d) .......................................................................................... 24

Functions of STU – Section 39 (2) (d) .......................................................................................... 24

Wheeling Charges – Section 42 (2) .............................................................................................. 25

Additional Surcharge – Section 42 (4) ......................................................................................... 25

Functions of State Commission – Section 86 (1) .......................................................................... 25

3.4 Categorization of Open Access ............................................................................................... 26

3.5 Open Access Charges: ............................................................................................................ 27

3.6 PROCEDURE FOR ALLOTMENT OF OPEN ACCESS: ................................................................... 27

3.7 ROLE OF DIFFERENT AGENCIES IN OPEN ACCESS .................................................................... 29

1. NLDC (National Load Dispatch Centre) .................................................................................. 29

4. STU (State Transmission Utility) ............................................................................................ 30

3.8 Open Access in Gujarat .......................................................................................................... 31

Open Access Rules: ..................................................................................................................... 32

Impact of Open Access ............................................................................................................... 35

Reasons for Thrust in Open Access ............................................................................................. 35

The Problems of Open Access ..................................................................................................... 35

Possible solutions for Denial of Open Access for Captive Power Plants ....................................... 37

ABT Settlement .......................................................................................................................... 38 Chapter4: SALE OF POWER THROUGH SHORT TERM MARKET TRANSACTIONS ............................. 40

Volume of Short-term Transactions of Electricity ........................................................................ 40

Price of Short-term Transactions of Electricity ............................................................................ 41 Chapter 5: SALE OF SURPLUS POWER THROUGH POWER EXCHANGE............................................... 46

INDIAN ENERGY EXCHANGE ........................................................................................................ 47 Chapter 6: RECOMMENDATIONS ........................................................................................................ 56 BIBLIOGRAPHY .................................................................................................................................... 59

vi NATIONAL POWER TRAINING INSTITUTE

Page 7: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

EXECUTIVE SUMMARY

India has a huge power shortage (demand supply gap), which is retarding the nation’s progress. Hence, we need to work simultaneously on all fronts to increase the availability of power.

Captive power plants (CPPs) have been installed by many industries and commercial

establishments all over the country,

These captive power plants are mainly intended to generate electricity for their own use by

industries. With provision in Electricity Act 2003 for wheeling of captive power through open

access and emphasis given to captive power in National Electricity Policy (NEP) 2005, surplus

power from captive power plants were emerging as a important source of electricity supply for

fulfillment of demand.

Government is also making a conscious attempt to encourage captive generation by earmarking

the coal blocks to be dedicatedly used by these plants. Captive generator has a number of fuel

options today. The choice could be between oil, natural gas, naphtha, biogas or coal.

Availability of open access is the major issues related to the strengthening of intra state and

inter-state transmission network, reasonable tariff and availability of additional fuel required

by captive power plants. Harnessing the surplus power from the Captive Power Plants has the following advantages:

-Partially bridge the gap between Demand &

Supply. -Optimize the investment made in CPPs -Improve the efficiency of CPPs by operating at a higher PLF (Plant Load Factor).

-Additional revenues could be generated by the CPPs by sale of surplus power

This report consists of detailed study of implementation of open access mechanism for sale

of surplus power of Captive power plants by intensive study of the existing provisions in the

Electricity Act 2003, National Electricity Policy, Captive Power Policy, and National Tariff

Policy.

vii NATIONAL POWER TRAINING INSTITUTE

Page 8: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

ABOUT THE COMPANY

Essar Energy, a first mover among the private-sector players in the Indian

power industry, currently has a total installed generation capacity of 3,910 MW.

Essar Energy is one of India's leading private power producers with a 15-year operating track

record. The company's power business currently has seven operational power plants in India

and one operational power plant in Algoma, Canada, with a total installed generation capacity

of 3,910 MW.

Vadinar Power Company Limited Captive power plant of Essar oil

Vadinar P2 power plant consists of a multi-fuel (coal, naphtha, oil) co-generation power plant with 325 MW of power capacity and 900 tons per hour (tph) of steam capacity.

Steam from the facility is be provided to Essar Oil's Vadinar refinery and power supplied to Essar Oil, Essar Steel and the merchant market.

Fuel for Vadinar P2 is provided by Essar Oil and Essar Steel in line with their purchase requirements.

OPERATING

Vadinar Power - Jamnagar (120 MW) The Vadinar Power power plant, located at the Vadinar refinery complex, is one of the

Vadinar refinery's captive power and steam co-generation plant. The plant is a 120 MW

refinery residue-based multi-fuel, captive, co-generation plant, with capacity to generate 77

MW of power and 230 tph of steam.

Essar Oil provides the fuel required at the power plant to generate the power and steam for the

power plant's operations.

Vadinar P1- Gujarat (380 MW) The Vadinar P1 power plant, located at the Vadinar refinery complex, is the Vadinar refinery's

second captive power plant. This plant is a 380 MW natural gas-fired combined- cycle plant. This

plant was the first to be commissioned since the Company's IPO in May 2010.

Page 9: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Essar Oil provides the fuel required at the power plant to generate the power and steam for the

power plant's operations.

Vadinar P2 - Gujarat (510 MW) Vadinar P2 power plant consists of a multi-fuel (coal, naphtha, light cycle oil, clarified slurry

oil and furnace oil) co-generation power plant with 325 MW of power capacity and 900 tons

per hour (tph) of steam capacity. Steam from the facility will be provided to Essar Oil's

Vadinar refinery and power supplied to Essar Oil, Essar Steel and the merchant market.

Fuel for Vadinar P2 will be provided by Essar Oil and Essar Steel in line with their

purchase requirements.

2 NATIONAL POWER TRAINING INSTITUTE

Page 10: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Chapter 1: CAPTIVE POWER PLANT

Captive power Plants are developed to cater the industrial demand in the scenario where the

electricity supplied by the utilities is short in supply or is of bad quality. Captive plants over the

years have been evolved from plants owned by single promoter to group captive to the medium

of maximizing the benefit by selling its surplus power.

In India, captive power took on a new shape when the first group captive was set up by three

companies—Gujarat State Fertilizers and Chemicals Ltd, Gujarat Alkalies and Chemicals Ltd

and Petrofils Cooperative Ltd, along with the Gujarat Electricity Board - Gujarat Industries

Power Co. Ltd. After meeting the needs of promoter companies, the surplus was sold to the

state government. Then came other large captive power plants of corporate groups such as

Vedanta, Essar, Reliance, etc which sold its surplus power to the state electricity boards

through 15-25 year PPAs. The opportunities emerged after the enforcement of the Electricity

Act-2003 in the form of delicensing of generation, implementation of open access and setting

up of common trading platform, has made the captive power plants an attractive option to

industries to meet their in-house requirement on one hand to maximise their profits from sale of

the surplus power from their captive plants on the other.

Apart from the mentioned benefits, other ones are associated with the option of selling the

surplus power through the power exchanges, depending upon the technology used claiming the

incentives under clean development mechanism (CDM), earning energy efficiency certificates,

renewable energy certificates. Although the trading of these certificates is currently not in

practice in India but very soon this is to be adopted in Indian power markets.

On the other hand the Government is also making a conscious attempt to encourage captive

generation by earmarking the coal blocks to be dedicatedly used by these plants.

3 NATIONAL POWER TRAINING INSTITUTE

Page 11: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

1.1 Regulatory Provisions

Captive power plants are a necessity for the Indian electricity scenario. The Electricity Act

2003 has been a landmark in institutionalizing captive power. Captive power generation also

finds mention in the National Electricity Policy and the Electricity Rules 2005. A draft captive

policy is also in the pipeline. Some of the important provisions highlighting captive power are

listed below:

Provisions for Captive Power Plants in Electricity Act 2003- Captive generating

plant is defined under Section 2 (8). It is a power plant set up by any person to generate

electricity primarily for his own use and includes a power plant set up by any

cooperative society or association of persons for generating electricity primarily for use

of members of such cooperative society or association. Section 9 (1) further stipulates

that a person may construct, maintain or operate a captive generating plant and

dedicate transmission lines. It also provides that supply of electricity from the captive

generating plant through the grid shall be regulated in the same manner as the

generating station of a generating company. Section 42 (2) states that surcharge (for

meeting the requirements of cross-subsidy) on wheeling charge shall not be leviable in

case open access is provided to a person who has established a captive generating plant

for carrying the electricity to the destination of his own use.

Provisions for Captive Power Plants in National Electricity Policy- In consonance

with the Electricity Act 2003, the National Electricity Policy emphasizes that the liberal

provision in the Act with respect to setting up of captive power plant has been made

with a view to not only securing reliable, quality and cost effective power but also to

facilitate creation of employment opportunities through speedy and efficient growth of

industry. The provision relating to captive power plants to be set up by group of

consumers is primarily aimed at enabling small and medium industries or other

consumers that may not individually be in a position to set up plant of optimal size in a

cost effective manner. It needs to be noted that efficient expansion of small and

medium industries across the country would lead to creation of enormous employment

opportunities. The Policy further states that a large number of captive and standby

generating stations in India have surplus capacity that could be supplied to the grid

continuously or during certain time periods. These plants offer a sizeable and 4 NATIONAL POWER TRAINING INSTITUTE

Page 12: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

potentially competitive capacity that could be harnessed for meeting demand for power.

Under the Act, captive generators have access to licensees and would get access to

consumers who are allowed open access. Grid inter-connections for captive generators

shall be facilitated as per section 30 of the Act. This should be done on priority basis to

enable captive generation to become available as distributed generation along the grid.

Appropriate commercial arrangements would need to be instituted between licensees

and the captive generators for harnessing of spare capacity energy from captive power

plants. The appropriate Regulatory Commission shall exercise regulatory oversight on

such commercial arrangements between captive generators and licensees and determine

tariffs when a licensee is the off-taker of power from captive plant. Towards this end,

non-conventional energy sources including co-generations could also play a role.

Provisions for Captive Power Plants in Electricity Rules 2005- These rules state

that no power plant shall qualify as a 'captive generating plant' under section 9 read

with clause (8) of section 2 of the Act unless it satisfies the following conditions.

(a) Incase of a power plant it is stipulated that not less than 26% of the ownership is held by

the captive user and the user has to consume a minimum of 51 % of the aggregate electricity

generated in such plant. Incase the captive power plant is set up by a cooperative society, the

conditions mentioned above shall be satisfied collectively by all the members. In case of

association of persons, the captive users shall hold not less than 26% of the ownership of the

plant in aggregate and such captive users shall consume not less than 51% of the electricity

generated, determined on an annual basis, in proportion to their shares in ownership of the

power plant within a variation not exceeding 10%.

(b) in case of a generating station owned by a company formed as special purpose vehicle for

such generating station, a unit or units of such generating station identified for captive use and

not the entire generating station shoould have 26% of the proportionate equity out of the total

equity of the company related to the generating unit(s) identified as captive plants. For example

in a generating station with two units of 50 MW each namely Units A and B, one unit of 50

MW namely Unit A may be identified as the Captive Generating Plant. The captive users shall

hold not less than thirteen percent of the equity shares in the company (being the twenty six

percent proportionate to Unit A of 50 MW) and not less than fifty one percent of the electricity

generated in Unit A determined on an annual basis is to be consumed by the captive users.

5 NATIONAL POWER TRAINING INSTITUTE

Page 13: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

(c) It shall be the obligation of the captive users to ensure that the consumption by the Captive

Users at the percentages mentioned above is maintained and in case the minimum percentage of

captive use is not complied with in any year, the entire electricity generated shall be treated as

if it is a supply of electricity by a generating company.

6 NATIONAL POWER TRAINING INSTITUTE

Page 14: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Chapter 2: CAPTIVE POWER SCENARIO IN INDIA

Captive Power refers to generation from a unit set up by industry for its exclusive consumption.

The estimates on captive power capacity in the country vary with the Central Electricity

Authority putting the figure at about 11600 MW while industry experts feel that it is much

higher, close to 20000 MW Industrial sector is one of the largest consumers of electrical energy

in India.

However, a number of industries are now increasingly relying on their own generation (captive

and cogeneration) rather than on grid supply, primarily for the following reasons:

• Non-availability of adequate grid supply

• Poor quality and reliability of grid supply

• High tariff as a result of heavy cross subsidization

The State Governments and SEBs have been concerned about the growing importance of

Captive Power Plants on account of the following reasons:

• Captive plants may have adverse impacts on the finances of the utility, such as:

• Industrial load is the main source for cross-subsidising revenue flows

• Billing and collection is much more efficient for HT consumers

• SEBs ability to service escrow accounts for security packages is also reduced

• Non-optimal growth of the sector.

• Problems in grid management especially in case of states with surplus power

• Adverse environmental impacts arising from types of fuels used and from higher emissions

per unit of production, as compared to large power plants

• Reliability of power supply from captive and cogen plants as a source of firm power

7 NATIONAL POWER TRAINING INSTITUTE

Page 15: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Source-CEA The industry in India pays among the highest tariffs in the world and is not assured of the

quality of supply. In this era of globalization, it is essential that electricity of good quality

be provided at reasonable rates for economic activity so that competitiveness increases.

2.1 CAPTIVE POWER POLICY OF DIFFERENT STATES

2.1.1 ORISSA

The permission for setting up Cogeneration/captive power plant will have to be

obtained from the Orissa Electricity Regulatory Commission (OERC).

The capacity of the cogeneration/captive power plant will be limited to the extent

required to meet 100% of the heat and power requirement of the industries concerned

on a sustained basis or to a larger extent necessary for the economic viability of the

project.

Surplus power from such plants would be purchased by the GRIDCO after negotiation

on a project to project basis.

8 NATIONAL POWER TRAINING INSTITUTE

Page 16: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

GRIDCO will permit wheeling of power over its transmission system subject to

carrying capacity of the transmission system. It will also allow sale of surplus power by

the industry to other industries within and outside the state to the extent permitted by

State government. Bilateral sale to the other state will be permitted on a specific

approval of the state government

Interconnection of the Cogeneration/captive power plant with the State Grid would be

at the cost of industry satisfying the technical requirement

The Cogeneration/captive power plant may be set up either by the promoters themselves

or by a separate company and shall abide by all relevant Acts and Rules in force

primarily the Indian Electricity Act, 1910, the Electricity Supply Act, 1948 and Orissa

Electricity Reform Act, 1995.

2.1.2 GUJARAT

Any industrial undertaking to set up captive power plant requires the consent of the

Gujarat Electricity Board (GEB) under section 44(1) of the Electricity (Supply) Act,

1948.

Banking of electrical power with GEB/Licensee would not be permitted.

Permission for installation of standby generating sets to work as additional source of

power would be permitted up to two times the consumers contract demand/ contracted

load with GEB/Licensee or demand equivalent to capacity of its own regular source of

power supply.

Wheeling of electrical power from captive power plant of an industrial company to the

other industrial units within the same company or to any/all industrial units of its group

companies is allowed. Minimum quantity of power to be wheeled shall not be less than

5% of the installed capacity of the captive power plant or 5MW, whichever is more,

among the group companies taken together subject to the condition that supplying

company consumes at least 50% of the generated power.

Wheeling charges are 13.5 paisa per kWh and 21 paisa per kWh for power delivered at

EHV and HV level respectively subject to revision from time to time.

Wheeling of power is also not allowed when system frequency is 51 Hz and above

No night hour tariff concession shall be admissible for power consumed/drawn from the

grid during night period. 9 NATIONAL POWER TRAINING INSTITUTE

Page 17: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

System losses shall be considered as 10% for power delivered at EHV and 15% in case

of power delivered at HV and the same would be deducted from the account of recipient

unit.

The rate for purchase of surplus power would be decided by GEB and will depend on

the fuel being used and would be on cost plus basis, where the fuel cost will be decided

by GEB on normative basis for each quarter for each type of fuel and gross calorific

value

The State government is empowered to prescribe terms and conditions relating to

electricity supply and tariff for such supply.

The electrical energy supplied/wheeled to different recipient units of group companies

from captive power plant of a supplying company would be subjected to payment of

Electricity Duty as per schedule I of the Bombay Electricity Duty Act, 1958 and Tax on

sale of electricity as per the provisions of Gujarat Tax on saleof electricity Act, 1985, as

amended from time to time.

2.1.3 MAHARASHTRA

The permission for installation and running the captive power plant will be granted by

the government and the capacity of the CPP will be limited to cover the existing

demand (MW) plus 1/3 of existing demand in MW or demand in MW for future

expansion.

Third party sale is allowed and in this case a tripartite agreement will have to be signed

between the Board, CPP owner and the third party receiving power from CPP.

CPP can sell surplus power to maximum two industrial units and is also restricted up to

25 percent of the generated units (kWh).

Captive generating company or any other company intending to sell surplus electricity

to third parties would require a prior permission from the Energy Department of the

State Government under section 28 of the Indian Electricity Act 1910.

The wheeling charges and transmission losses are determined in terms of distance

transmitted. The wheeling charges and transmission losses are determined as 2% and

5% respectively for a distance of 050 km; 4% and 8% respectively for a distance of

50200 km; and 6% and 10% respectively for a distance above 200 km.

10 NATIONAL POWER TRAINING INSTITUTE

Page 18: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Rate at which surplus power would be purchased would be decided by MSEB and it

will

In case of planned shut-down of the CPP, the excess demand recorded over and above

the revised contract demand will be charged at double the normal demand charge rate of

the respective tariff in force from time to time.

2.1.4 RAJASTHAN

A Captive Power Plant supplying Power to Captive Power Consumer/s wholly using its

own independent transmission lines and not connected with the RVPN’s grid system

would be considered Category ‘A’ Captive Power Plant.

A Captive Power Plant supplying power to Captive Power Consumer/s wholly using

RVPN/Discom’s transmission lines would be considered Category ‘B’ Captive Power

Plant.

A Captive Power Plant supplying power to Captive Power Consumer/s, partly using

RVPN/Discom’s and partly its own independent transmission lines and connected with

the RVPN/Discom’s grid system would be considered Category ‘C’ Captive Power

Plant.

Captive Power Consumers who have contract demand from the Discom(s) would be

referred to as Category-I. Captive Power Consumer, while those who do not have the

same would be referred to as Category-II. Captive Power Consumer.

Fuel Source and Capacity Restriction

The Captive Power Plant may use any conventional fuel subject to restrictions imposed

by GOI. Captive Power Producer shall be responsible for arranging allocations, linkages

and clearances required for the fuel for the Captive Power Plant from the concerned

authority.

Installed generating capacity of the Captive Power Plant of Categories ‘B’ & ‘C’ shall

not exceed the demand of its consumers and prescribed line losses.

Voltage of supply

The voltage of supply of power to RVPN/Discom(s) grid from Captive Power Plants

(Categories ‘B’ and ‘C’) shall be subject to RVPN/Discom’s approval, but shall

normally be as under :- 11 NATIONAL POWER TRAINING INSTITUTE

Page 19: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Upto 10 MW 33 kV Upto 50 MW 132 kV

In excess of 50 MW 132 kv or 220 kV (at RVPN/Discom’s option)

Nominal frequency for power supply will be 50 Hz. However flow of energy will be

regulated as per the instructions of State Load Despatch Centre as per system

requirement in the high frequency regime.

Amended vide Notification No. F.12(17) Energy/93 Dated : 26 Feb.2002 issued by

GOR.

The Power factor of power delivered by Captive Power Plant shall normally be 0.8

(lag.)

Supply of power by Discom(s) to Captive Power Plant during the construction, startup

and shut down of Plant will be at HT large industrial load tariff.

System Stand by Charges/ Fixed Charges

The captive Consumers of Category-I will be required to pay "fixed and other charges"

to Discom(s) as per applicable tariff determined by Rajasthan Electricity Regulatory

Commission.

CPP of category "B" and "C" requiring RVPN/ Discom(s) system standby support will

be required to bear system standby charges @ Rs. 4.5 lacs per MVA per year payable

on monthly basis in advance and indexed to the H.T. large industrial tariff applicable a s

on 1.7.99.

Wheeling/Transmission Charges & T&D Losses

Captive Power Plants using RVPN/Discom’s Grid System for wheeling of power/

energy will have to bear wheeling charges and T&D losses equivalent to 12.5% of the

energy supplied for wheeling to the Captive Power Consumers at 132 kV (and above)

and 17.5% of the energy supplied for wheeling to the Captive Power Consumers at 33

kV.

Inadvertent flow of power to RVPN

The policy does not envisage regular sale of surplus energy to the RVPN grid.

However, only inadvertent net flow of power/energy to the RVPN grid at a system

frequency upto 50.2 Hz. shall be paid at a rate of 65% of H.T. large industrial tariff

including fuel surcharge applicable to large industrial loads for the months of November 12 NATIONAL POWER TRAINING INSTITUTE

Page 20: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

to June and @ 60% of the energy charges applicable under large industrial tariff for the

months of July to October.

*** In case of supply of surplus power in the RVPN Grid at system frequency above

50.2 Hz., the rate of inadvertent supply of such energy shall be @ 70 paisa per unit.

In case it is not possible to determine the inadvertent flow of energy above & below

50.2 Hz. due to absence of frequency based data of consumption of each consumer, the

same shall be determined pro rata on the basis of frequency profile of delivered energy.

For this purpose the Captive Power Plant will maintain a daily log of hourly generation

and frequency, a copy of which will also be furnished to the RVPN/Discom(s) on a

daily basis.

Amended vide Notification No. F.12(17) Energy/93 Dated : 26 Feb.2002 issued by

GOR.

** Incorporated as per Notification No. F.12(17) Energy/93 Dated : 26 Feb.2002 issued

by GOR.

*** Modified as per Notification No. F.12(17)Energy/93 Dated 18.01.2003 issued by

GoR.

Sale of power from Captive Power Plant to consumers outside the State will not be

permitted.

All Captive Power Consumers drawing power from Captive Power Plant through

RVPN/Discom(s) system will abide by General Conditions of Supply of Power from

Discom(s).

2.1.5 WEST BENGAL

Transmission and wheeling of power generated: The Wheeling facility will be provided

by the WBSEB/CESC at a uniform wheeling charge of 2% of cost of power wheeled,

irrespective of the distance from the generating station.

Banking facilities: The board permits the electricity generated to be banked for a period

of six months.

An industrial undertaking not carrying on continuous process of production may draw

power from the bank at any time of the day except during evening hours.

Sale of power to WBSEB/CESC: 13 NATIONAL POWER TRAINING INSTITUTE

Page 21: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

The generated power not used by the industrial undertaking within a period of six

months will be deemed to have been sold to the WBSEB/CESC.

Tariff for sale of power will be determined for each generating station separately upon

consideration of various factors such as generating cost based on total investment (less

central govt. grant), debt equity ratio, depreciation, O&M, return on equity, debt service

conditions, etc., as is done for large thermal/hydro power generating station.

2.2 Captive Co-Generation Policy

It is generally recognized that industry in general and a process industry in particular needs

energy in more than one form and if the energy requirements and supply to the industrial units

are carefully planned the overall efficiency of a very high order is possible to achieve. With the

combined objectives of promoting better utilisation of precious energy resources in the

industrial activities and creation of additional power generation capacity in the system,

encouragement to co-generation plants in the country is being suggested.

2. Definition of Cogeneration

2.1 A cogeneration facility is defined as one which simultaneously produces two or

more forms of useful energy such as electric power and steam, electric power and shaft

(mechanical) power etc. Cogeneration facilities, due to their ability to utilize the available

energy in more than one form, use significantly less fuel input to produce electricity, steam,

shaft power or other forms of energy than would be needed to produce them separately. Thus

by achieving higher efficiency, cogeneration facilities can make a significant contribution to

energy conservation.

3. Objectives of the Policy

3.1 As electricity and heat are fundamental inputs to most of the industrial activities the

present policy strives to achieve the dual objectives of achieving higher efficiency in fuel use in

the industry as well as the availability of surplus electricity to the State grid, by combining

power and heat generation for industrial use.

14 NATIONAL POWER TRAINING INSTITUTE

Page 22: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

4. Process for creation of Cogeneration Facility

4.1 With a view to promote setting up of cogeneration plants, it is proposed that the

industry having cogeneration potential would be allowed to develop a power generating facility

without necessarily going through the competitive bidding process, for projects of any size. In

addition, in such cases the projects for the purpose of CEA clearance would be treated in the

same way as any proposal for setting up of captive plant is required to be treated by the State

Government under section 44 of the Electricity (Supply) Act, 1948.

5. Cogeneration Plants

5.1 Two basic cogeneration cycles have been identified:

Topping Cycle: Any facility that uses fuel input for power generation and also utilizes for

useful heat for other industrial activities. In any facility with a supplementary firing facility, it

would be required that the useful heat, to be utilized in the industrial activities, is more than the

heat to be supplied to the system through the supplementary firing by at least 20%.

Bottoming Cycle: Any facility that uses waste industrial heat for power generation by

supplementing heat from any fossil fuel.

6. Qualifying Requirements

6.1 A facility may qualify to be termed as cogeneration facility if it satisfies certain

operating and efficiency standards which are explained below.

(I) Qualifying Requirements for Topping Cycle:

The qualifying requirements for topping cycle would depend on the type of fuel used as the

overall efficiency levels likely to be achieved for power generation varies with the choice of

fuel. Essentially, any cogeneration facility meeting the efficiency requirement will be more

efficient than any combination of separately generated electricity and steam using the state-of

art- technology. As such while setting the efficiency standards, the achievable efficiency in case

of a particular fuel has been kept in consideration. In addition, for all cases of cogeneration

facility, it would be required that at least 20% of the total energy output is in the form of useful

thermal energy.

15 NATIONAL POWER TRAINING INSTITUTE

Page 23: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

As the cogeneration project would be feeding power to the state grid, in order to maintain grid

stability and facilitate proper planning of the power system, it would be required that the

cogeneration facility must be available to supply at least 5MW of power for at least 250 days in

a year.

(a) Using coal as fuel

Assuming that the achievable thermal efficiency for power generation using coal as fuel hovers

around 35% while the boiler efficiency for steam generation observed in Indian industries is

about 90%, the efficiency standard set for any cogeneration facility is as under:

The sum of useful power output and one half the useful thermal output be greater than 45% of

the facility s energy consumption.

(b) Using Liquid Fuel

Assuming that the achievable thermal efficiency for power generation using liquid fuel based

combined cycle power generation system is about 50% while the boiler efficiency for steam

generation observed in Indian industries is about 85-90%, the efficiency standard set for any

cogeneration facility is as under:

“The sum of useful power output and the useful thermal output be greater than 65% of

the facility’s energy consumption.”

(c) Refinery Bottoms as fuels

Refinery Bottoms or those by products of refining process would be permitted to be used as

fuel for cogeneration facilities to be set up by any petroleum refining unit which can not be

easily marketed due to transportation problems or due to low heat content. However, to qualify

as a cogeneration plant, the sum of useful power output and one half the useful thermal output

be greater than 45% of the facility s energy consumption. And in any calendar year, not less

than 90% of the total heat input for the facility should come from refinery residue or the

refinery bottom.

(II) Qualifying Requirements for Bottoming Cycle

16 NATIONAL POWER TRAINING INSTITUTE

Page 24: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

In case of bottoming cycle, the total useful power out put in any calendar year must not be less than 50% of the total heat input through supplementary firing.

7. Tariff fixation

7.1 While fixing tariff from a cogeneration plant, the basic consideration would be to

share the benefits of higher efficiency. In addition, the other advantage available to the industry

is availability of assured supply of power and possibly at a tariff lower than what the SEBs

normally charge from their industrial consumers due to cross subsidization. On the other hand

SEBs also stand to benefit from the fact that they qet surplus power at a rate lower than the

marginal cost. However, in the bargain SEBs would have to let go some of their good

customers. The tariff should, therefore, reflect these issues.

7.2 The tariff can be fixed by the SEB by making adjustments for the higher efficiency

and applying the same on the marginal cost of generation. Accordingly, the SEB can notify an

acceptable tariff, reflecting the modified marginal cost of generation and pay at that rate for the

life of the plant barring major fuel price escalations.

7.3 Alternatively, the SEBs may chose to notify the first year tariff in two parts, fixed

and variable, and announce an tariff escalation formula considering the fact that with the

servicing of debt, recovered through depreciation, the fixed cost component comes down every

year and at the same time the fuel cost increases due to fuel escalation.

7.4 However, realizing the fact that ultimately the power sector would be required to

move away from the cost based tariff structure, to get the full benefits we can probably use

cogeneration plants for this switch over as even if there is slight error in fixing of the marginal

tariff the damage would be very limited and can be corrected quickly in the subsequent

cogeneration plants. This would also provide useful bench marks for other major IPPs.

17 NATIONAL POWER TRAINING INSTITUTE

Page 25: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

7.5 In case of topping cycle plants using refinery bottom as fuel, the tariff would be

fixed by the SEB on negotiated basis, providing for recovery of fixed costs of the power

generating facility and the variable cost which could be determined by making adjustments for

efficiency factors and other operational factors. Typically, the tariff for such plants may be

represented by

Tariff = FCC + 0.8*Variable cost

8. Procedure for Obtaining Qualifying Status

8.1 The Qualifying Status to any facility would be granted by the State Government.

The power producer would be required to submit the necessary documents to the State

Government/SEB to establish fulfillment of the qualifying requirements in terms of efficiency

criterion, choice of fuel, power generation technology and the stages of heat absorption in the

industry.

9. Generation Schedule

9.1 As the availability of surplus power to be fed into the State grid will vary during the day

depending on the operating cycle of the industry and may also vary with season if the industrial

operations are season specific such as sugar mills etc. the power producer and the SEB/State

Government would be required to mutually work out the schedule for power supply to the grid

considering the industry and grid requirements. sd/-

2.3 PERMISSION AND APPROVAL:

1. Permission for installation of Captive Power Plant is to be obtained from SEB under

Section 44 of Electricity (Supply) Act, 1948. For captive power generation exceeding

25 MW, SEB will accord permission under Section 44 of Electricity (Supply) Act,

1948 only after consulting the Central Electricity Authority as per Section 44 (2A) of

Electricity (Supply) Act, 1948.

2. The following would be eligible to install a Captive Power Plant:-

a) A consumer of electricity

b) A group comprising more than one consumer as a joint venture.

18 NATIONAL POWER TRAINING INSTITUTE

Page 26: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

c) An actual user of power but not a consumer.

d) A group of actual users of power, but not consumers, as a joint venture.

e) A group comprising both consumers and actual users of power as a joint

venture but excluding A Generating Company@ as defined under

Section 2(4-A) of Electricity (Supply) Act 1948.

If the captive plant falls under the category of hydro or co-generation plant, such plant,

irrespective of its size and status of power supply position in the State, may be

permitted liberally.

If the Captive Power Plant is based on coal or liquid fuel or gas and if the State is deficit in

power supply, the installation of such captive power plant could normally be allowed and

the capacity of the plant permitted up to 200% of the requirement of the industry for its own

use.

If the Captive Power Plant is based on coal, liquid fuel or gas and the State is surplus in

power, the installation of such captive plants can still be considered in the following

cases:-

i. If the industry requires uninterrupted power supply due to the nature of the

industry and if the State/SEB or Successor entity are not able to guarantee

supply of such requirements, the proposal for setting up of such a captive power

plant for the uninterrupted power supply requirement of the industry can be

considered.

ii. If the industry requires quality power supply (within the stipulated variations

in voltage and frequency) and if the State/SEB or Successor entity are not in a

position to guarantee the power supply of such stringent requirements, the

proposal for installation of the captive power plant of the required capacity can

be considered.

iii. If the cost of generation from the captive plant is found to be lower compared

to the tariff of the power supply from the grid, the proposal may be considered

after thoroughly examining the cost and tariff aspects. 1. Banking facilities may also be provided to the Captive Power Plants so that available

19 NATIONAL POWER TRAINING INSTITUTE

Page 27: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

capacities are utilised to the extent possible and when required. The rates for banking

may be determined on mutually agreed terms. 4) Units in Special Economic Zones (SEZ) and industrial estates may be allowed to set up

CPPs liberally.

If the CPP is of co-generation in nature, and the capacity exceeds 25 MW, the proposals shall

be forwarded to CEA for consultation under Section 44(2A) of Electricity (Supply) Act, 1948

duly certified by the concerned Utilities that the proposal qualifies for the status of co-

generation. (In this regard, MOP Resolution No.A-40/95-IPC.I, dated 6th November, 1996 may

be seen for reference). Permission of State Electricity Board is required to synchronize and operate with the Grid.

All statutory clearances for setting up the CPP have to be obtained by the owner of the CPP

of his own accord.

2.4 CONDITIONS FOR USAGE OF CAPTIVE POWER

Energy generated from captive power generating units: i) Can be used by the owner of the captive power generation plant. ii) Can be used by sister concern (s) of the owner of the captive power generation plant. iii) Balance power after usage in items (i) and (ii) above can be sold to SEB, if required by

them. iv) Third Party sale is also permissible, with the approval of SEB.

Captive generator could be asked not to draw power from the grid during peak seasons/hours.

2.5 CONCERNS:

While on the other hand the concern of the owners of captive and cogen plants stems from:

• Non-remunerative tariff structure for surplus power produced by them

• No risk sharing in case of nonavailability of fuel, change in variable cost due to switching of fuel after entering into power purchase agreement (PPA), etc

• Inadequacies in wheeling and banking facilities

20 NATIONAL POWER TRAINING INSTITUTE

Page 28: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

• High contract demand charges.

• High level of duties and taxes on sale of power

• High wheeling losses assumed for power to be sold to grid by captive or cogen plant

• Need to devote time and energy to an activity, which is not their core business

• Restrictions on the minimum amount of power to be wheeled

• If the captive power plant (CPP) fails, charges for back-up or standby power from the grid are

twice the normal rate for captive plants

• No formal policy for purchase of cogenerated power (in most of the states) It is estimated that

about 30% of the total energy requirement of the Indian industry is currently met through in

house power plants

2.6 ADVANTAGES:

One of the most important prerequisite to set up an industry is assured, consistent quality power

at affordable rates to remain globally competitive. Only captive power generation (CPP) meets

all these criteria and not the power supply by SEBs and grid. A large spectrum of industrial

sectors, viz. cement, steel and iron, non-ferrous (aluminium, zinc etc.), chemicals, textile,

engineering, paper, sugar, tyre etc.are not only responsible for national infrastructure build-up

but they also convert natural raw materials to goods used in further industries triggering

economic chain of activities for the nation. All continuous process industries and factories

working in three shifts can’t survive without CPP or back-up power.

Harnessing the surplus power from the Captive Power Plants has the following advantages:

Partially bridge the gap between Demand & Supply.

Optimize the investment made in CPPs

Improve the efficiency of CPPs by operating at a higher PLF (Plant Load Factor).

Additional revenues could be generated by the CPPs by sale of surplus power

21 NATIONAL POWER TRAINING INSTITUTE

Page 29: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Chapter 3: POWER EXPORT BY CPPs (VIA OPEN ACCESS)

3.1 INTRODUCTION

The Electricity Act, 2003 aims at bringing about competition with the ultimate objective

of ensuring efficiency gains resulting from competition for the consumers. Competition with

regulatory oversight is the hallmark of the legislation - and it recognises the important role of

the regulatory commissions in the wake of the challenges that opening of the sector poses for

consumers and other stakeholders.

In the context of competition, open access is the corner-stone of the Act. Open Access has

been conceived as an important tool of introducing competition in the electricity industry and

ensuring choice to buyers and suppliers of electricity. The Act envisages Open Access in transmission and distribution network. Open Access in

transmission has been allowed from the very beginning and without any fetter. However, in so

far as Open Access in distribution is concerned, the law envisages introduction of such Open

Access in phases with due consideration of the operational constraints and existence of cross

subsidy between consumer categories.

This responsibility of phased introduction of open access in distribution has been

bestowed on State Electricity Regulatory Commissions. Through an amendment in the Act, it

has, however been provided that the State Commissions shall provide by January, 2009 open

access to all consumers with load exceeding 1 MW. The issue of open access for consumers

with load exceeding 1 MW has been under discussion in recent past in view of the various

interpretations floated in the context. The Government of India (Ministry of Power and

Ministry of Law) in its latest interpretation on 30.11.2011 has articulated that Section 42 of the

Act makes it mandatory for all consumers with load exceeding 1 MW to be open access

consumers and that the tariffs for such consumers shall not be regulated by SERCs.

Even as the central government is pushing state for mandatory implementation of Open

Access (OA) for bulk power consumers, an analysis by a regulators body has revealed that

contrary to expectations, the consumers in 12 states have had to pay more for power under the

new regime.

22 NATIONAL POWER TRAINING INSTITUTE

Page 30: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Open Access at various levels is the hallmark of electricity reforms and the regime has

been effective in 20 states since January 2009 on an optional basis. Under the Open Access

regime, bulk consumers enter into bilateral deals with discoms and stay outside the ambit of the

regulated tariff system.

3.2 PROBLEM STATEMENT

Due to continuous shifting of bulk consumer distribution licensee and losing their

paying consumer and if the process will remain continue then the time will reach when

distribution licensee will remain with only subsidised of non-paying consumer. Under the

Electricity Act, Open Access consumers have to pay Open Access charges including wheeling

and standby charges and cross-subsidy surcharge, besides the cost of electricity. But this

charges are not upto the mark and to minimize the loss of distribution licensee following things

should also need to consider:

i) Ideally, the net effect of subsidy and cross subsidy should need to be zero but in

reality it is not zero because the AT & C losses and theft has not considered in cross subsidy

surcharge formula.

ii) Need to define who will pay the Cross subsidy of Renewable? if its obligation has

removed from paying Cross Subsidy Surcharge for its promotion,

iii) Need to solve the problem of forecasting which distribution licensees are facing.

3.3 SECTIONS OF EA-2003 GOVERNING OPEN ACCESS

Captive Generation – Section 9 (2)

Every person, who has constructed a captive generating plant and maintains and operates such

plant, shall have the right to open access for the purposes of carrying electricity from his

captive generating plant to the destination of his use: Provided that such open access shall be subject to availability of adequate transmission facility

and such availability of transmission facility shall be determined by the Central Transmission

Utility or the State Transmission Utility, as the case may be Provided further that any dispute

regarding the availability of transmission facility shall be adjudicated upon by the Appropriate

Commission.

23 NATIONAL POWER TRAINING INSTITUTE

Page 31: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Functions of CTU – Section 38 (2) (d) The functions of the Central Transmission Utility shall be to provide non-discriminatory open access to its transmission system for use by- (i) any licensee or generating company on payment of the transmission charges; or (ii) any consumer as and when such open access is provided by the State Commission under

subsection (2) of section 42, on payment of the transmission charges and a surcharge thereon,

as may be specified by the Central Commission: Provided that such surcharge shall be utilised for the purpose of meeting the requirement of

current level cross-subsidy: Provided further that such surcharge and cross subsidies shall be progressively reduced and

eliminated in the manner as may be specified by the Central Commission: Provided also that such surcharge may be levied till such time the cross subsidies are not

eliminated Provided also that the manner of payment and utilisation of the surcharge shall be specified by

the Central Commission: Provided also that such surcharge shall not be leviable in case open access is provided to a

person who has established a captive generating plant for carrying the electricity to the

destination of his own use.

Functions of STU – Section 39 (2) (d) The functions of the State Transmission Utility shall be to provide non-discriminatory open access to its transmission system for use by-

(i) any licensee or generating company on payment of the transmission charges ; or

(ii) any consumer as and when such open access is provided by the State Commission

under subsection (2) of section 42, on payment of the transmission charges and a surcharge

thereon, as may be specified by the State Commission:

Provided that such surcharge shall be utilised for the purpose of meeting the

requirement of current level cross-subsidy: Provided further that such surcharge and cross subsidies shall be progressively reduced and

eliminated in the manner as may be specified by the State Commission: Provided also that the manner of payment and utilisation of the surcharge shall be specified by the State Commission. 24 NATIONAL POWER TRAINING INSTITUTE

Page 32: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Provided also that such surcharge shall not be leviable in case open access is provided to a

person who has established a captive generating plant for carrying the electricity to the

destination of his own use.

Wheeling Charges – Section 42 (2)

The State Commission shall introduce open access in such phases and subject to such

conditions, (including the cross subsidies, and other operational constraints) as may be specified within one

year of the appointed date by it and in specifying the extent of open access in successive phases

and in determining the charges for wheeling, it shall have due regard to all relevant factors

including such cross subsidies, and other operational constraints: Provided that such open access may be allowed before the cross subsidies are eliminated on

payment of a surcharge in addition to the charges for wheeling as may be determined by the

State Commission: Provided further that such surcharge shall be utilised to meet the requirements of current level

of cross subsidy within the area of supply of the distribution licensee : Provided also that such surcharge and cross subsidies shall be progressively reduced

and eliminated in the manner as may be specified by the State Commission: Provided also that such surcharge shall not be leviable in case open access is provided to a

person who has established a captive generating plant for carrying the electricity to the

destination of his own use.

Additional Surcharge – Section 42 (4)

Where the State Commission permits a consumer or class of consumers to receive supply of

electricity from a person other than the distribution licensee of his area of supply, such

consumer shall be liable to pay an additional surcharge on the charges of wheeling, as may be

specified by the State Commission, to meet the fixed cost of such distribution licensee arising

out of his obligation to supply.

Functions of State Commission – Section 86 (1)

The State Commission shall discharge facilitate intra-state transmission and wheeling of

electricity; 25 NATIONAL POWER TRAINING INSTITUTE

Page 33: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

3.4 Categorization of Open Access

On the basis of location of buying and selling entity, the open access is categorized as:

Inter State Open Access:

When buying and selling entity belongs to different states. In this case CERC regulations

are followed. It is further categorized as:

1. Short Term Open Access (STOA): open access allowed for the period of less

than one month.

2. Medium Term Open Access (MTOA): open access allowed for a period of 3

months to 3 years.

3. Long Term Open Access (LTOA): open access allowed for a period of 12

years to 25 years.

** If suppose you require open access for two months, then you should re – apply for STOA

before the expiry of first month.

Intra State Open Access:

When buying and selling entity belongs to same state. In this case SERC regulations are

followed. It is further categorized as STOA, MTOA, and LTOA and the duration of

which depends on the respective state open access regulations.

Types of Transactions:

In general the buyer and seller of electricity can go for bilateral or collective transactions.

In bilateral transactions a PPA is signed between the buyer and seller, which is generally

facilitated by a trader for a little margin. In case of collective transactions the electricity is

traded through exchanges, by exchange members for a very small margin fixed by

commission. Currently India has two exchanges PXIL and IEX.

26 NATIONAL POWER TRAINING INSTITUTE

Page 34: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

3.5 Open Access Charges:

There are several charges to be paid by open access consumers to distribution licensee,

transmission licensees and other related entities, other than the power purchase cost paid to the

generator or supplying entity. These charges include:

Connectivity Charges PoC Charges Transmission Charges Transmission Losses Wheeling Charges Wheeling Losses Cross Subsidy Surcharge SLDC Charges RLDC Charges

** In addition to these charges the open access consumers has also to fulfil the renewable

purchase obligation (RPO), in which they have to purchase a part of their total consumption

through electricity generated from renewable energy.

3.6 PROCEDURE FOR ALLOTMENT OF OPEN ACCESS:

Long Term Open Access

i) An application for long-term access shall be submitted to the nodal agency; ii) The application shall contain the details, such as capacity needed, point(s) of injection,

point(s) of drawl, duration of availing open access, peak load, average load and such other

additional information that may be specified by the nodal agency: Provided that the nodal

agency shall issue necessary guidelines, procedure and application forms within 30 days of

commencement of these regulations.

iii) The application shall be accompanied by a non-refundable application fee of Rs one lakh

payable in the name and in the manner to be decided by the nodal agency;

27 NATIONAL POWER TRAINING INSTITUTE

Page 35: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

iv) Based on system studies conducted in consultation with other agencies involved including

other transmission licensees, the nodal agency shall, within 30 days of receipt of the

application, intimate to the applicant whether or not the long-term access can be allowed

without further system strengthening: Provided that where the long-term access can be allowed without further system strengthening,

this shall be allowed immediately after entering into commercial agreements.

v) If, in the opinion of the nodal agency, further system strengthening is essential before

providing the long-term access, the applicant may request the nodal agency to carry out the

system studies and preliminary investigation for the purpose of cost estimates and completion

schedule for system strengthening;

vi) The nodal agency shall carry out the studies immediately on receipt of request from the

applicant under clause (v) above and intimate results of the studies within 90 days of receipt of

request from the Central / State transmission Unit.

vii) The applicant shall reimburse the actual expenditure incurred by the nodal agency for

system strengthening studies: Provided that the fee of rupees one lakh paid by the applicant shall be adjusted against the

actual expenditure to be reimbursed by the applicant.

Short Term Open Access i) A short-term customer shall submit an application for transmission access to the nodal

Regional Load Despatch Centre.

ii) The application shall contain the details, such as capacity needed, point or points of

injection,point or points of drawl, duration for availing of open access, peak load, average load

and such other additional information that may be laid down by the Regional / State Load

Dispatch Centre.

iii) The application shall be accompanied by a non-refundable application fee of Rupees five

thousand only; Provided that in case of application for access on the date of the application or

on the following day, the application fee may be deposited within next three working days of making of application. 28 NATIONAL POWER TRAINING INSTITUTE

Page 36: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

iv) The reserved transmission capacity shall not be transferred by a short-term customer to any other customer.

3.7 ROLE OF DIFFERENT AGENCIES IN OPEN ACCESS

1. NLDC (National Load Dispatch Centre)

Section 26. (National Load Dispatch Centre) of the Act stipulates that:

(1) The Central Government may establish a centre at the national level, to be known as the

National Load Dispatch Centre for optimum scheduling and dispatch of electricity among the

Regional Load Dispatch Centres.

(2) The constitution and functions of the National Load Dispatch Centre shall be such as may

be prescribed by the Central Government.

Note : Provided that the National Load Dispatch Centre shall not engage in the business

of trading in electricity.

2. RLDC (Regional Load Dispatch Centre)

Section 27. (Constitution of Regional Load Dispatch Centre) of the Act stipulates that:

(1) The Central Government shall establish a centre for each region to be known as the

Regional Load Dispatch Centre having territorial jurisdiction as determined by the Central

Government in accordance with section 25 for the purposes of exercising the powers and

discharging the functions under this Part. (2) The Regional Load Dispatch Centre shall be operated by a Government company or any

authority or corporation established or constituted by or under any Central Act, as may be

notified by the Central Government. Provided that until a Government company or authority or

corporation referred to in this sub-section is notified by the Central Government, the Central

Transmission Utility shall operate the Regional Load Dispatch Centre.

Note : Provided further that no Regional Load Dispatch Centre shall engage in the business of generation of electricity or trading in electricity.

29 NATIONAL POWER TRAINING INSTITUTE

Page 37: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

3. SLDC (State Load Dispatch Centre)

Section 31. (Constitution of State Load Dispatch Centre) of the Act stipulates that: --- (1) The State Government shall establish a Centre to be known as the State Load Dispatch

Centre for the purposes of exercising the powers and discharging the functions under this Part. (2) The State Load Dispatch Centre shall be operated by a Government company or any

authority or corporation established or constituted by or under any State Act, as may be notified

by the State Government. Provided that until a Government company or any authority or

corporation is notified by the State Government, the State Transmission Utility shall operate the

State Load Dispatch Centre. Note : Provided further that no State Load Dispatch Centre shall engage in the business

of trading in electricity.

4. CTU (Central Transmission Utility)

Section 38. (Central Transmission Utility and functions) of the Act stipulates that: (1) The Central Government may notify any Government company as the Central Transmission Utility. Note : Provided that the Central Transmission Utility shall not engage in the business of generation of electricity or trading in electricity. One of the functions of Central Transmission Utility is to provide non-discriminatory Open Access to its transmission system for use by – (i) any licensee or generating company on payment of the transmission charges; or (ii) any consumer as and when such open access is provided by the State Commission under

subsection (2) of section 42, on payment of the transmission charges and a surcharge thereon,

as may be specified by the Central Commission.

4. STU (State Transmission Utility) Section 39. (State Transmission Utility and functions) of the Act stipulates that: (1) The State Government may notify the Board or a Government company as the State Transmission Utility.

30 NATIONAL POWER TRAINING INSTITUTE

Page 38: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Note : Provided that the State Transmission Utility shall not engage in the business of trading in electricity. One of the functions of State Transmission Utility is to provide non-discriminatory open access

to its transmission system for use by- (i) any licensee or generating company on payment of the transmission charges ; or (ii) any consumer as and when such open access is provided by the State Commission under

subsection (2) of section 42, on payment of the transmission charges and a surcharge thereon,

as may be specified by the State Commission. The Load Dispatch Centres, transmission utilities

are barred from trading n power in order to ensure non-discriminatory open access to all the

generators/ consumers.

3.8 Open Access in Gujarat

GERC notified Open Access Regulation in 2005

State of Gujarat has implemented intra-state ABT w.e.f. 05.04.2010 which is pre-

requisite for implementation of open access

Subsequently, GERC Open Access Regulation 2011 notified as per model Regulation of

Forum of Regulators

State providing adequate infrastructure support to open access consumers in the state

Wheeling of electrical power from captive power plant of an industrial company to the

other industrial units within the same company or to any/all industrial units of its group

companies is allowed. Minimum quantity of power to be wheeled shall not be less than

5% of the installed capacity of the captive power plant or 5MW, whichever is more,

among the group companies taken together subject to the condition that supplying

company consumes at least 50% of the generated power.

31 NATIONAL POWER TRAINING INSTITUTE

Page 39: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Open Access Rules:

GERC Long Term Customer

Full Transmission charges shall be determined as per the Terms & Conditions of

tariff notified by appropriate Commission from time to time.

Rs.2970/MW/day for the year 2013-14

Period --exceeding12 year but not exceeding 25 years

Exit option for customer available by paying compensation

Medium Term Customer

Full Transmission Charges

Allowed on available margins

Rs.2970/MW/day for the year 2013-14

Period– exceeding 3months but not exceeding 3 years

Exit option available by paying compensation.

Priority over Short Term Open Access

Short Term Customer

Intra-state

ST-Rate = 0.25 x [TSC / AV-cap]/365

Rs.742.5 /MW/day for the year 2013-14

Period ----less than 3 months and not exceeding 6 months in a year

Transmission Charges: Connectivity and Open Access relationship Connectivity should always be simultaneously applied with either Medium Term Open Access

or Long Term Open Access

Open Access users may take undue advantage of taking connectivity and then trading in short

term

Many Generators demand connectivity as merchant plants and then trade power under short

term open access as per the availability in market.

Captive power plants also seek connectivity and trade the surplus power. 32 NATIONAL POWER TRAINING INSTITUTE

Page 40: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Captive user and Merchant power plants find consumers within Gujarat for trading power as

third party sale

Eventually disparity among Open Access users, mainly DISCOMs who pay for the existing

network

Consumers’ grievance due to such disparity

Power not availed by such open access consumers within contract demand is being backed

down/sold at lower price in market for which fixed cost is payable by DISCOMs . 33 NATIONAL POWER TRAINING INSTITUTE

Page 41: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

15% Electricity duty is applicable but same is also applicable for purchase under open

access

Power purchase by Open access user in range of Rs. 3.75-5.43/unit as against the supply

of power by DISCOM at the rate of Rs. 5.73/unit

34 NATIONAL POWER TRAINING INSTITUTE

Page 42: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Impact of Open Access

-Per unit fixed cost works out to Rs. 2.07 & DISCOMs recovers approx. Rs. 0.50/unit as fixed

charge from HT consumers

-Retail energy charges includes partial recovery towards fixed charges Open access consumers pays around 55 paisa/unit (39 paisa- cross subsidy & 16 paisa –

wheeling & transmission

Power not availed by such open access consumers is being backed down/sold at lower price in

market for which fixed cost is payable by DISCOMs

Reasons for Thrust in Open Access

Open access is crucial for

• Mobilizing larger private investment in generation through guaranteed access to

credible buyers.

• Enhancing competition amongst generators and suppliers to have option for consumers.

• Investment promotion objective is of higher priority in view of the prevailing electricity

shortages.

The Problems of Open Access

Captive power plants are not being granted open access or third party sales by the state load

dispatch centers who may, in most cases, be under instruction to try and capture the power

within the state by pressurizing the captive power producers to sell within the state at a price

much lower than what would be available to them if the power was exported outside the state.

Although State Load Dispatch Centers are supposed to function as independent entities, it has

been found that since SLDCs are manned by officers of the State Electricity Boards, who are on

deputation, they are susceptible to pressure being exerted on them through their parent

organizations and officials of the state government which prevents them from functioning as

independent entities.

35 NATIONAL POWER TRAINING INSTITUTE

Page 43: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

There are many ways in which open access transactions are frustrated by SLDCs. Some of them are:

(1) The simplest way for not granting open access is to not respond to the request. So the

moment the SLDC receives a request for open access, they do not respond.

(2) The second way for SLDCs to refuse open access is to ask for an NOC from the State

Electricity Board.

This puts the entire issue of grant of open access into a loop and results in unending delay. Invariably, the State Electricity Boards raise an objection stating that (1) there was

an agreement with a generating company to sell power to the SLDCs or (2) the State is

facing shortage and therefore the power should not be allowed to be exported outside the

state. This results in tremendous pressure on the surplus power generator who is then arm-

twisted into agreeing to a lower rate for sale to the State Electricity Board since he realizes that

his open access application is not going to be considered in the near future. Even if there is a

response from the State Electricity Board, the SLDC is instructed informally to avoid giving

open access. The SLDC then quotes transmission constraints as a reason for not granting

open access. One interesting example was when a large mineral based industry was told that it

should discontinue negotiations for sale of its surplus power with third parties at Rs.4 per

kilowatt hour or else they would not receive black start power from the grid whenever their

plant was down. This resulted in the industry selling the power to the grid for 95 paise per

kilowatt hour and the grid then sold the captive power for a sum of Rs.7, making a super profit.

In another case, open access was denied by a State Government entity and the matter was

referred all the way up to CERC but in spite of the CERC order, the concerned SLDC, on

instructions from the local powers that be, refused to grant open access to a captive power plant

having a surplus for sale to third parties. In some cases there are some State Government policy

constrictions which prohibit the sale of power outside the state, of any private sector captive

power plant having surplus power, although the State Electricity utility is happily selling that

power outside the state at a large profit.

36 NATIONAL POWER TRAINING INSTITUTE

Page 44: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

In another instance, it was noticed that open access was denied purely on the basis of the whims

and fancies and likes and dislikes of the State Load Dispatch Center, based on a prejudicial

mind set against certain industrial houses and traders of power.

Possible solutions for Denial of Open Access for Captive Power Plants

The issue of denial of open access by State Load Dispatch Centres (SLDC) assumes

significance because if the SLDC denies a generating company open acces at any point in time

then there is no alternative for the generating company to succumb to the pressure of the state

or to shut off the plant.

This has been noticed as a new phenomena occurring in agro-based power plants which prefer

to shut down rather than supply at a loss because of the huge escalation in agro-based fuel

prices.

There is a possible solution whereby the regulations are changed once more wherein the nodal

RLDC approves the transaction and coordinates with all the SLDCs for open access for captive

power plants. In this situation in case of a denial of open access by the SLDC it may be

possible if the industry has installed an SEM meter conforming to the requirements of the

RLDC it can then inject power on the UI basis into the state grid. The RLDC then subtracts that

quantum of power from the state account and the transaction is carried on from thereafter as a

bilateral transaction on the basis of UI. In this option there is a customer who is willing to buy

power at a bilateral price from the generating station and in spite of the non approval of the

open access request by the SLDC the transaction is completed using the UI mechanism.

In other words the transaction from the generating company into the state grid is settled as a UI

transaction, the transaction from the RLDC to the buyer is settled as a bilateral transaction or if

the buyer agrees the UI transaction and the settlement between the generator and the buyer is

done directly after the plus-minus of the UI charges versus the bilateral rate agreed and the

account is settled. In a third option it is possible that if the industry has the necessary metering

system which is RLDC compliant it can directly schedule the power to the RLDC through the

state system and take this payment on a UI settlement basis directly from the RLDC. The

CERC has come up with a very nascent concept paper on the subject but it has not moved

forward. 37 NATIONAL POWER TRAINING INSTITUTE

Page 45: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

ABT Settlement

All this does not augur well for the development of confidence in the Indian power sector by

private investors. It must be emphasized that the Government of India has taken a conscious

decision to move away from managing and monitoring infrastructure projects and it has wooed

the private sector to come in and invest. In this context consumer choice and open access are

great tools for de-risking merchant, independent and captive power generation investments and

in this context this strategy of frustrating the private sector from getting third party open access

is the single largest deterrent for private sector investments and in the negligible success of

mainstreaming captive power.

The other set of issues which are connected to open access is the settlement mechanism for

variation in generation. No state has an intrastate ABT mechanism in place; with a result that

the state utilities/discoms charge exorbitant temporary power tariffs for overdrawals by the

captive power plant and, interestingly, pay them nothing for injecting surplus power into the

grid beyond the schedule. The excuse given is that there is no intra-state ABT and therefore the

generating company is bound by state policy and tariffs, even if the power transaction is

interstate in nature.

38 NATIONAL POWER TRAINING INSTITUTE

Page 46: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Comparison of cost of power through Intra-State Open Access Effective

**Net cost of

Open

* Net OA

*** Tariff

power from

Difference

S. No. STATES

Access

Charge

(Discom)

Open Access

(Rs/ kWh)

Charges

(Rs./kWh)

(Rs./kWh)

(Rs./kWh)

(Rs./kWh)

1 Assam 1.61 2.61 5.61 3.25 2.36

2 Chhattisgarh (Short term) 0.52 0.88 3.88 3.38 0.50

3 Haryana 0.72 0.98 3.98 4.57 -0.59

4 Himachal Pradesh 0.84 1.20 4.20 3.04 1.16

5 Karnataka (BESCOM) - ST 0.66 0.89 3.89 4.85 -0.96

6 Maharashtra (MSEDCL area) - LT 0.24 0.59 3.59 4.53 -0.94

7 Orissa ( WESCO) 1.29 1.69 4.69 2.91 1.78

8 Punjab ( short term) 1.29 1.65 4.65 5.09 -0.44

9 Rajasthan 0.62 0.88 3.88 3.9829 -0.10

10 Uttar Pradesh ( short term) 0.13 0.53 3.53 4.29 -0.76

11 Madhya Pradesh - ST 0.79 0.94 3.94 4.57 -0.63

12 Uttarakhand ( Long term) 0.67 1.27 4.27 3.9 0.37

13 Gujarat - LTOA 0.79 1.27 4.27 7.39 -3.12

14 West Bengal - short term 2.28 2.68 5.68 3.95 1.73

15 Tamil Nadu 2.00 2.35 5.35 3.96 1.39

16 Delhi 0.49 1.57 4.57 4.05 0.52

17 Jharkhand 0.73 2.54 5.54 4.48 1.06

18 Andhra Pradesh 0.39 0.82 3.82 3.49 0.34

19 Kerala 1.70 2.21 5.21 3.94 1.27

20 Bihar ( HTS) 2.13 2.45 5.45 4.35 1.11

OA charges for a consumer of 5MW at 11 KV (33 KV in some cases) seeking OA for a

month.

** This includes transmission & wheeling losses (Rs/kWh) calculated assuming power

purchase cost as Rs 3/kWh

*** Tariff for an embedded consumer of 5MW at 11 KV (33 KV in some cases).

39 NATIONAL POWER TRAINING INSTITUTE

Page 47: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Chapter4: SALE OF POWER THROUGH SHORT TERM MARKET

TRANSACTIONS

Short-term transactions of electricity” refers to the contracts of less than one year period, for

electricity transacted (inter-state & intra-state) through Inter-State Trading Licensees and

directly by the Distribution Licensees, Power Exchanges (Indian Energy Exchange Ltd (IEX)

and Power Exchange India Ltd (PXIL)), and Unscheduled Interchange (UI). The objectives of

the report are: (i) to observe the trends in volume and price of the short-term transactions of

electricity; (ii) to analyse competition among the market players; (iii) to analyse effect of

congestion on volume of electricity transacted through power exchanges; (iv) to provide

information on volume and price of Renewable Energy Certificates (RECs) transacted through

power exchanges; and (v) to disclose/disseminate all relevant market information.

Short Term Transactions could be electricity transacted under

* Bilateral Transactions (either direct or through trader)

* Energy Exchanges

* Unscheduled Interchange (UI) (not a market mechanism but

considered under short term transactions)

Volume of Short-term Transactions of Electricity

During the month of June 2013, total electricity generation excluding generation from

renewable and captive power plants in India was 76108.30 MUs

of the total electricity generation, 8845.33 MUs (11.62%) were transacted through

short-term, comprising of 4733.45 MUs (6.22%) through Bilateral (through traders and term-

ahead contracts on Power Exchanges and directly between distribution companies), followed

by 2167.76 MUs (2.85%) through day ahead collective transactions on Power Exchanges

(IEX and PXIL) and 1944.12 MUs (2.55%) through UI (Table-1 & Figure-2).

Of the total short-term transactions, Bilateral constitute 53.51% (37.02% through

traders and term-ahead contracts on Power Exchanges and 16.49% directly between

distribution companies) followed by 24.51% through day ahead collective transactions on

Power Exchanges and 21.98% through UI (Table-1& Figure-1). Daily volume of short-term

transactions is shown in Table-17 & Figure-3.

The percentage share of electricity traded by each trading licensee in the total volume 40 NATIONAL POWER TRAINING INSTITUTE

Page 48: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

of electricity traded by all trading licensees is provided in Table-2 & Figure-4. The trading

licensees undertake electricity transactions through bilateral and through power exchanges.

Here, the volume of electricity transacted by the trading licensees includes bilateral

transactions and the transactions undertaken through power exchanges. There were 43

trading licensees as on 30.06.2013, of which only 21 have engaged in trading during June

2013. Top 5 trading licensees had a share of 72.70% in the total volume traded by all the

licensees.

Herfindahl-Hirschman Index (HHI) has been used for measuring the competition

among the trading licensees. Increase in the HHI generally indicates a decrease in

competition and an increase of market power, whereas decrease indicates the opposite. A

HHI below 0.15 indicates non-concentration, a HHI between 0.15 to 0.25 indicates moderate

concentration and a HHI above 0.25 indicates high concentration. The HHI computed for

volume of electricity traded by trading licensees (inter-state & intra-state) was 0.1698 for the

month of June 2013, which indicates that there was moderate concentration of market power

(Table-2).

The volume of electricity transacted through IEX and PXIL in the day ahead market

was 2114.56 MUs and 53.20 MUs respectively. The volume of total Buy bids and Sale bids

was 2578.34 MUs and 4191.51 MUs respectively in IEX and 72.79 MUs and 182.26 MUs

respectively in PXIL. The gap between the volume of buy bids and sale bids placed through

power exchanges shows that there was less demand in IEX (0.62 times) and PXIL (0.40

times) when compared with the supply offered through these exchanges.

The volume of electricity transacted through IEX and PXIL in the term-ahead market

was 11.48 MUs and 4.60 MUs respectively (Table-6 & Table-7).

Price of Short-term Transactions of Electricity

(i) Price of electricity transacted through Traders: Weighted average sale price has

been computed for the electricity transacted through traders and it was `4.36/kWh. Weighted

average sale price was also computed for the transactions during Round the Clock (RTC),

Peak, and Off-Peak periods separately, and the sale prices were `4.37/kWh, `3.98/kWh and

`4.06/kWh respectively. Minimum and Maximum sale prices were `2.96/kWh and `6.22/kWh

respectively (Table-3 & 4).

41 NATIONAL POWER TRAINING INSTITUTE

Page 49: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

(ii) Price of electricity transacted Through Power Exchanges: Minimum, Maximum and

Weighted Average Prices have been computed for the electricity transacted through IEX and

PXIL separately. The Minimum, Maximum and Weighted Average prices were

`0.90/kWh, `20.00/kWh and `2.52/kWh respectively in IEX and `0.80/kWh, `5.00/kWh and `2.15/kWh respectively in PXIL (Table-5). The price of electricity transacted through IEX and PXIL in the term-ahead market was

`2.71/kWh and `2.60/kWh respectively (Table-6 and Table-7).

(iii) Price of electricity transacted Through UI: All-India UI price has been computed

for NEW Grid and SR Grid separately. The average UI price was `1.64/kWh in the NEW Grid

and `2.67/kWh in the SR Grid. Minimum and Maximum UI prices were `0.00/kWh and

`10.80/kWh respectively in the New Grid, and `0.00/kWh and `9.06/kWh respectively in the

SR Grid

42 NATIONAL POWER TRAINING INSTITUTE

Page 50: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

VOLUME OF ELECTRICITY TRANSACTIONS:

Table-1: VOLUME OF SHORT-TERM TRANSACTIONS OF ELECTRICITY

% to

Sr.No Short-term transactions Volume Volume of % to Total

1 Bilateral 4733.45 53.51% 6.22%

(i) Through Traders and 3274.56 37.02% 4.30%

(ii) Direct 1458.89 16.49% 1.92%

2 Through Power Exchanges 2167.76 24.51% 2.85%

(i) IEX 2114.56 23.91% 2.78%

(ii) PXIL 53.20 0.60% 0.07%

3 Through UI 1944.12 21.98% 2.55%

Total 8845.33 100.00% 11.62%

Total Generation 76108.30 _ _ Source: NLDC

Page 51: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive
Page 52: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive
Page 53: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Chapter 5: SALE OF SURPLUS POWER THROUGH POWER EXCHANGE

Captive Power Plants can sell their surplus power through power exchanges also. Electricity

trading through Power Exchanges (PX) is hitherto introduced in many electricity markets. In

India, two power exchanges viz., Indian Energy Exchange (IEX) and Power Exchange of India

Ltd. (PXIL) are functioning with guidance from Central Electricity Regulatory Commission

(CERC). Exchanges in India have only two years of experience and are continuously evolving.

Evolution of power exchange depends on the experiences and lessons from international power

exchanges. Nord Pool power exchange (Elspot) is being considered as a standard exchange

design. Design and implementation issues of a power exchange or power market, in general,

depend on the market supplies and demands, liquidity, economy etc. Philosophy of exchange

design may vary from country to country or exchange to exchange (working in the same

country). In India, electricity market is supply deficit (in some regions) and has a mix of different

generation technologies. PX is a trading center where utilities, power marketers, and other

electricity suppliers submit price and quantity bids to sell energy or services, and potential

customers submit offers to purchase energy or services. Key points of a power exchange include:

-facility for trading of electricity

-foster the development of competition

- transparency

- liquidity The idea of trading through an exchange enables the traders to discover the best price in the

market and to find the optimum buyer or seller for trade. Power exchange introduces

transparency in the market clearing and reduces counter-party credit risk. Exchange manages

trades, clears market and settles financial transactions. In the electricity market, the exchange is

synchronized with Transmission System Operator (TSO) to get technical clearance for

transacting power over the grid.

Trading should be done in an efficient manner to provide quality and affordable power to end

users. Power exchange formation could prove to be a mile stone in the above mentioned purpose.

Page 54: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Power Exchange (PX) directly operates wholesale energy markets, such as day-ahead and hour-

ahead markets, while the real-time market for energy balancing and the market for the ancillary

services may be operated directly by the TSO or by PX on behalf of TSO and under specific

technical requirements. The TSO controls and operates the transmission grid and facilitates

transactions and transmission avoiding influence on the generation schedules created by the PX. Success factor of a PX can be measured with the following inputs:

- Number of participants in PX

-Liquidity in the market

-Market growth in terms of traded volume

-Competitiveness of fee structure

INDIAN ENERGY EXCHANGE

Broad Features

The broad features of power Exchange are given below.

Approved and Regulated by Central Electricity Regulatory Commission

Nationwide, Online and Electronic platform

Voluntary participation.

Neutral, Unbiased and Transparent

Offer Market for Electricity, Renewable Energy Certificates, Energy Efficiency

Certificates, etc.

Exchange time-line consistent with time-line of Load Despatch Centres

The activities of the Exchange are carried out in accordance with the “Central

Electricity Regulatory Commission (Power Market) Regulations, 2010, dated

20th January 2011”, “Central Electricity Regulatory Commission (Open Access in

inter-State Transmission) Regulations, 2008”, dated 25.01.2008, as revised from

time to time and Procedure for scheduling of collective transaction issued by the

Central Transmission Utility (PGCIL) and the Bye-Laws, Rules and Business

Rules of the Exchange.

Page 55: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

The Exchange shall offer products for different time horizons so as to offer total

solution to the market participants. Honorable Commission has desired the

Exchange be a market based institution. We propose to add variety in terms of

products offered and method of bid-matching process and would evolve

corresponding rules, bye-laws for clearing, settlement, margins, deposits, market

surveillance etc.

IEX Day-Ahead Market

On a daily basis the Exchange will offer a double side closed auction for

delivery on the following day, which is termed as day-ahead market. Price

discovery would be through double side bidding and buyers and suppliers

shall pay/receive uniform price.

Day Ahead Market operations will be carried out in accordance with the

‘Procedure for scheduling of collective transactions’ issued by the Central

Transmission Utility (PGCIL), ‘CERC (Open Access in inter-State

Transmission) Regulations, 2008’ ,its modifications issued from time to time

and the Bye-Laws, Rules and Business Rules of the Exchange.

Process of Closed-Bidding Auction

o Bid accumulation period (Bidding phase)

During the auction sessions on each Trading Day, bids entered by

Members on the IEX Trading Platform are automatically stored in the

Central Order Book without giving rise to Contracts. During this phase,

bids entered can be revised or cancelled. Bid accumulation period shall

start at 10.00 AM and will end at 12.00 Noon.

o Auction period

At the end of the bidding session, the IEX Trading Platform will

Page 56: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

seek to match bids for each 15 minute time block. After the price

determination phase is concluded, the Members, whose bids have

been partially or fully executed, will be provided all relevant trade

information regarding each contract traded on the IEX Trading

Platform.

o Price Determination Process (Provisional)

All purchase bids and sale offers will be aggregated in the

unconstrained scenario. The aggregate supply and demand curves will

be drawn on Price-Quantity axes. The intersection point of the two

curves will give Market Clearing Price (MCP) and Market Clearing

Volume (MCV) corresponding to price and quantity of the

intersection point. Results from the process will be preliminary

results. Based on these results the Exchange will work out provisional

obligation and provisional power flow. Funds available in the

settlement account of the Members shall be checked with the Clearing

Banks and also requisition for capacity allocation shall be sent to the

NLDC. In case sufficient funds are not available in the settlement

account of the Member then his bid (s) will be deleted from further

evaluation procedure.

o Price Determination Process (Final)

Based on the transmission capacity reserved for the Exchange by the

NLDC on day ahead basis by 2.00 PM, fresh iteration shall be run at

2.30 PM and final Market Clearing Price and Volume as well as Area

Clearing Price and Volume shall be determined. These Area Clearing

Prices shall be used for settlement of the contracts.

o Settlement

On receipt of final results, obligations shall be sent to Banks for Pay In

from buying Members at 2.30 PM and will take confirmation of the

same from the Bank. At 3.00 PM final results will be sent to

Page 57: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

NLDC / SLDCs for incorporating in final schedules. Once a

transaction is scheduled it shall be considered as deemed delivery.

Day-ahead Market

Delivery Point

Delivery point for the purpose of contract, shall be reckoned as the periphery of

Regional Transmission System in which the grid-connected exchange entity is located. The

same shall be used for the purpose of payment of transmission charges in cash and

transmission losses in kind. For example, delivery point for a state -embedded entity in

Maharashtra shall be WR periphery.

Day-ahead Scheduling of Exchange traded contracts

The Exchange traded contracts will be aggregated for each region and State for each

hour. This will also give net contractual flows between regions and/or bid areas. After

the schedules are issued by NLDC/SLDCs, the delivery shall be deemed to have been

completed.

Transmission Capacity, Transmission Charges and Losses

o Levy of transmission charges

Following Transmission Charges shall be payable by the Members for the traded contracts:

Transmission Charges for respective Regional Transmission System, as made applicable under the Central Electricity Regulatory

Commission (Open Access in inter-State Transmission) Regulations,

2008.

Transmission Charges for respective State Transmission Licensee, as decided by the concerned State Electricity Regulatory Commission. In

Page 58: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

absence of any direction or order from concerned SERC, in this

respect, the provisions as stipulated in the Central Electricity

Regulatory Commission (Open Access in inter-State Transmission)

Regulations, 2008 shall be applicable.

Socialized Scheduling and Operating Charges for trades on the Exchange. The Exchange shall pay such charges based on Central

Electricity Regulatory Commission (Open Access in inter -State

Transmission) Regulations, 2008 to NLDC and SLDCs. Such charges

shall be socialized over all transactions within respective State(s) and

Region(s).

Any other charges as specified by CERC.

TransmissionLosses: All grid connected exchange entities shall pay, in kind, the transmission losses from delivery

point to its grid connection point. Transmission losses, for the Regional Transmission System,

as decided by the NLDC for Collective transactions, shall be accounted for at the time of

scheduling. Similarly, transmission losses for the State Transmission Licensees, as prescribed

by the respective SERC, shall also be accounted for at the time of scheduling.

Contracts Offered

Contract

Trading

Matching

Intra-day Contracts Trading on delivery day

few hours before delivery.

Day-ahead Contingency Trading to a day before

delivery and after DAM

Continuous trading

Contracts

auction.

session.

Trading upto 1 Week in

Daily Contracts advance for any calendar

day.

Page 59: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Weekly Contracts

Trading upto 2 Weeks in Uniform Price Auction

advance.

Scheduling

Selected trades sent to Nodal Agency i.e. RLDC of Buyer State after

collecting SLDC clearance.

Scheduling Procedure as per Procedure for Scheduling of Bilateral

Transaction, issued by CTU.

IEX files an application to the concerned RLDC.

Margins & Settlement

Collect requisite margin before trading and delivery (Initial margin,

additional margins, other margins)

Reservation of transmission capacity by Nodal RLDC.

Issue of Schedules by concerned RLDCs on daily basis

Financial Settlement by IEX

Benefits:

Transparency

IEX offers a transparent, national-level platform for trading electricity in India

leading to a vibrant power market.

Access a diversified portfolio

IEX offers a broader choice to generators and distribution licensees at the national-

level so that they can trade in smaller quantities and smaller number of hours

without additional overheads.

Page 60: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Payment security

IEX stand in as the counter-party for all trades; so participants need not be

concerned about the risk-profile of the other party.

Minimal transaction overheads/charges

All charges are displayed on the IEX trading terminals; so there is no room for

negotiation. The cost of transactions through IEX is much less than any other

mode of transaction.

Efficient portfolio management

IEX enables participants to precisely adjust their portfolio as a function of

consumption or generation. Participants, especially distribution licensees, are

enabled to precisely manage their consumption and generation pattern.

Hedging UI risks

IEX provides a tool to hedge against adverse movements in electricity prices.

Thus, price risks are minimised.

Market development

IEX has plans to launch a range of products to facilitate development of power

markets in India in such a way that investment in capacity enhancement is

encouraged.

Benefits to Captives from the Exchange • Security against Defaults – Financial mechanism where a Clearing House is responsible for

settlements with Exchange as a counter party shall provide a credible settlement mechanism that

insures sellers against defaults

• Transmission capacity assignment – Power Producers would not have to bother about getting

Page 61: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

transmission capacity assigned over inter-regional power links (and getting it renewed every

three months) as the Exchange shall be responsible for getting capacities allocated to successful

transactions

• Ease in Decision making – Since it is difficult for both, Captive and Renewable Power Producers

to make firm long term commitments for assured supply, clarity on quantum of power and the price

at which it can be sold on a day ahead basis would facilitate decision making.

Key issues being faced by Captive Power Producers

• Supplier Constraints • Low flexibility to enter into long term fixed contracts • Self-consumption of Captive owners has hourly and seasonal trends; Renewables such as Wind

power producers cannot commit a firm supply. As a result, they are not in a position to assess the

quantum of power that they would be able to trade on a long term basis • Lack of robust Payment Security mechanisms that protects against defaults

• Market related • Lack of an Institutionalized Power Trading Market that – • Allows Buyers and Suppliers to discover each other • Operates on a day ahead basis – Buyers and suppliers who do not have long term visibility

find day ahead markets useful for their requirements • Provides sufficient liquidity • Hedges risks of both – Buyers and Suppliers • Is affordable – low transaction costs

• Regulatory issues • Open access related charges – High cross-subsidy surcharges, wheeling charges etc may render

the Buyer’s proposition of procuring external power non-viable • High loss allocation (commercial losses also allocated) • Tariff Related – No relaxation in contract demand for a Discom consumer who procures part of

his power requirement from external sources may lead to loss of Load factor rebates • Lack of standby support/ Disproportionate standby support charges

Page 62: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

• Rate mandated for sale of power to Distribution Utility may be non-economical • Short term transmission capacity allocation • Grid support/parallel operation charges

• Technical issues • Grid connectivity issues • Lack of a mechanism such as Intra-state ABT for UI settlement

• Others • Dismantling of transmission/distribution line on disconnection • Electricity (Amendment) Act Provision – The amended Act, in force from June

15, 2007 provides that no licence shall be required for supply of electricity generated

from a captive generating plant to any licencee and to any consumer. • Captive Power Producers are; therefore, free to sell surplus power to consumers/ licensees

without the need for license

Page 63: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

Chapter 6: RECOMMENDATIONS

Captive generation is an important means to making competitive power available. Appropriate

Commission should create an enabling environment that encourages captive power plants to

be connected to the grid.

Such captive plants could inject surplus power into the grid subject to the same regulation as

applicable to generating companies. Firm supplies may be bought from captive plants by

distribution licensees using the guidelines issued by the Central Government under section 63 of

the Act.

Short term market transaction is the best way a captive power plant can sell its surplus power.

Short Term Market is on a rising trend in India led by volumes growth in Power exchange

Volume growth in Power Exchanges has resulted in reducing the average cost of

power purchased.

Flexibility to Sellers and Buyers- no long term commitments, meet your specific

requirements-can be few hours also.

Relatively simpler mechanism to purchase cheaper power, with minimum investment.

The opportunities are immense, and the industry should come forward and claim that is rightfully

theirs.

We should make the process clean and transparent, and make the industry understand that they

will not only be saving on electricity bills but also shall be getting a more consistent and reliable

supply of electricity.

The power market should open up, and it’s high time; we should now start treating electricity as

a market instrument rather than a social instrument.

Page 64: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

WHAT NEEDS TO BE DONE-NEXT STEPS Key issues related to sale of power by Captive Power Producers have been discussed earlier

however, some crucial issues that must be sorted out at the earliest are as follows:

• Intra-State Settlement Mechanism – Very few states have mechanisms such as Intra-state ABT

for settling Unscheduled Interchanges among the constituents. As a result, it becomes difficult

for power producers to sell power freely to the buyer of their choice. Every state is designing

Intra-state ABT system in its own way.

• Additionally, other necessary provisions such as Balancing and Settlement Code, ABT

compliant metering should be done by the concerned Regulators/ State Utilities, availability of

appropriate software

• Open Access related charges, where they are found to be stifling the decision of buyers to

procure external power, should be reviewed

• Other support required by such buyers such as standby support, grid connectivity etc should be

facilitated

• Payment Security – can pool operate with high probability of default by cash strapped

Discoms.

• SLDC continues to operate on behalf of the Discoms.

Page 65: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

The Road Ahead:

It is therefore clear that captive power plants which can be put to use and added on to the grid at

short notice can do so provided the various bottlenecks created artificially by certain sections in

the incumbent organizations are removed. The way forward also includes a need in the UI rate to

follow the oil price increases so that a tariff signal can be given to locally based stations, both

captive and otherwise to schedule power during periods of shortage. This may allow the injection

of roughly 20-30 thousand megawatts of power on to the grid which would give the grid security

in the short to medium term.

There are a huge number of constraints and disincentives imposed on captive power plants by

local authorities which need to be done away with. We need to federalize the captive and

private power sector so that uniform rules can be made applicable to these projects across the

country. These rules would particularly include uniform and low taxation on fuels, exemption

from any local taxation in inter-state transactions, and a strong disincentive for refusing open

access by state load dispatch centers. While the country waits with bated breath in darkness, this

could be a quick way forward in meeting the power shortages in the near future.

Page 66: STUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM · PDF fileSTUDY OF IMPLEMENTATION OF OPEN ACCESS MECHANISM FOR SALE OF SURPLUS POWER BY CAPTIVE POWER PLANTS At ... In India, captive

BIBLIOGRAPHY

P.R. Shukla, D. B. (2004). Captive Power Plants: Case Study of Gujarat.Central Electricity Authority

Article: Captive Power Generation by V Ranganathan and Damodar Mall

www.cercind.gov.in

www.indianpowersector.com

www.indianelectricity.com

www.infraline.com

www.rajsldc.com

www.orierc.org

www.mercindia.org.in

www.en.wikipedia.org/wiki/Electricity_sector_in_India