5
RCBC PROGRESS PHOTO 12 TH FLOOR WIRING ROOM DATA & VOICE CCTV

description

B1 to 34 th Floor Progress Photos of a Structured Cabling.August 2013 to Feb 2014

Transcript of Structured Cabling Photos

Page 1: Structured Cabling Photos

RCBC PROGRESS PHOTO12TH FLOOR WIRING ROOM

DATA & VOICE CCTV

Page 2: Structured Cabling Photos

RCBC PROGRESS PHOTO12TH LIBRARY ROOM

RACK 1 RACK 2 & 3 RACK 4

Page 3: Structured Cabling Photos

RCBC PROGRESS PHOTO10TH FLOOR WIRING ROOM

VOICE/DATA TERMINATION CABLE LADDER

Page 4: Structured Cabling Photos

RCBC PROGRESS PHOTO10TH FLOOR WORKING STATION

CABLE PULLING AND INSTALLATION OF CABLE

GUTTER

CABLE DISTRIBUTION AND I/O TERMINATION

Page 5: Structured Cabling Photos

RCBC PROGRESS PHOTO10TH FLOOR WORKING STATION

ROUGHING – INS LAY OUT AND CABLE PULLING FOR A.P.

ROUGHING – INS LAY OUT AND CABLE PULLING FOR A.P.