STRUCTURAL METHODOLOGY REPORT UNDERPINNING TO …

3
1 202087R001Rev0 Structural Methodology Report 23 September 2021 People Architecture [email protected] Attention: Steven Christoforidis Dear Steven STRUCTURAL METHODOLOGY REPORT – UNDERPINNING TO EXISTING WALLS OF THE EXISTING HOUSE AT 5 REGENT STREET PUTNEY This report has been prepared at your request to address the methodology and sequence of the proposed underpinning works to the existing brick walls for the proposed excavation and construction of the new basement storage rooms. This is to confirm that we have examined the above existing building to determine its structural suitability for the proposed alterations as noted below, and as shown on the Architectural Drawings. We confirm that the existing building is suitable, provided that the proposed new structural work is carried out in accordance with the methodology and construction sequence indicated below and to the future specifications and drawings prepared by a suitably experienced and qualified practicing consulting structural engineer. If works are carried out in accordance with our design and construction methodology this will pose negligible risk to neighbouring properties. Methodology 1. Install underpinning beams to support the existing timber bearers and remove the existing isolated brick piers. 2. Underpin both the internal and external walls with either mass concrete or brickworks to the level of 300mm below the base of the excavation if still in soil otherwise if in rock to 50- 100mm below subgrade level (to be confirmed by final design). 3. Proceed with excavation and construction of the basement storage rooms. Construction Sequence This section should be read in conjunction with the attached markup. 1. Remove existing flooring for head height clearance as required during construction. 2. Install underpinning steel beams to support the existing subfloor bearers. 3. Demolish existing isolated brick piers. 4. Begin local excavation in soil and underpin the internal brick wall with either mass concrete or brick works. The underpinning should follow the sequence of A, B, C, D and E as per the attached markup. 5. Underpin the external brick walls with either mass concrete or brick works. The underpinning should follow the sequence of 1, 2, 3 and 4 as per the attached markup. This will require the existing roof over the patio to be temporarily propped. 6. Prepare subgrade for sub-base installation of granular material to be specified by engineer.

Transcript of STRUCTURAL METHODOLOGY REPORT UNDERPINNING TO …

Page 1: STRUCTURAL METHODOLOGY REPORT UNDERPINNING TO …

1

202087R001Rev0 Structural Methodology Report

23 September 2021

People Architecture

[email protected]

Attention: Steven Christoforidis

Dear Steven

STRUCTURAL METHODOLOGY REPORT – UNDERPINNING TO EXISTING WALLS OF THE

EXISTING HOUSE AT 5 REGENT STREET PUTNEY

This report has been prepared at your request to address the methodology and sequence of the

proposed underpinning works to the existing brick walls for the proposed excavation and

construction of the new basement storage rooms.

This is to confirm that we have examined the above existing building to determine its structural

suitability for the proposed alterations as noted below, and as shown on the Architectural

Drawings. We confirm that the existing building is suitable, provided that the proposed new

structural work is carried out in accordance with the methodology and construction sequence

indicated below and to the future specifications and drawings prepared by a suitably experienced

and qualified practicing consulting structural engineer. If works are carried out in accordance with

our design and construction methodology this will pose negligible risk to neighbouring properties.

Methodology

1. Install underpinning beams to support the existing timber bearers and remove the existing isolated brick piers.

2. Underpin both the internal and external walls with either mass concrete or brickworks to the level of 300mm below the base of the excavation if still in soil otherwise if in rock to 50-100mm below subgrade level (to be confirmed by final design).

3. Proceed with excavation and construction of the basement storage rooms.

Construction Sequence

This section should be read in conjunction with the attached markup.

1. Remove existing flooring for head height clearance as required during construction.

2. Install underpinning steel beams to support the existing subfloor bearers.

3. Demolish existing isolated brick piers.

4. Begin local excavation in soil and underpin the internal brick wall with either mass concrete or brick works. The underpinning should follow the sequence of A, B, C, D and E as per the attached markup.

5. Underpin the external brick walls with either mass concrete or brick works. The underpinning should follow the sequence of 1, 2, 3 and 4 as per the attached markup. This will require the existing roof over the patio to be temporarily propped.

6. Prepare subgrade for sub-base installation of granular material to be specified by engineer.

Page 2: STRUCTURAL METHODOLOGY REPORT UNDERPINNING TO …

2

7. Pour the concrete base slab with a spoon drains adjacent to the new underpinning walls.

8. Construct pits and other drainage items as per the civil engineers’ recommendations.

The underpinning works and base slab are to be carried out in the sequence above, and the elements are to be designed in accordance with the following:

1. Is in accordance with the relevant requirements of the Building Code of Australia- NCC Part 3.0 Structural Provisions Volume 2 - 2019, Amendment 1; and

2. Is in accordance with the following relevant Standards Australia Codes:

AS/NZS 1170.0-2002 Structural Design Actions: Part 0 - General Principles

AS/NZS 1170.1-2002 Structural Design Actions: Part 1 – Permanent, Imposed and Other Actions

AS/NZS 1170.2-2021 Structural Design Actions: Part 2 - Wind Actions

AS 1170.4-2007 Structural Design Actions: Earthquake Actions in Australia

AS 1720.1-2010 Timber Structures: Part 1 - Design Methods

AS 2870-2011 Residential Slabs and Footings - Construction

AS 3600-2018 Concrete Structures

AS 3700-2018 Masonry Structures

AS 4100-2020 Steel Structures

AS 4678-2002 Earth Retaining Structures

General Comments

We noted that whilst every measure can be taken from a structural design perspective to preserve

the structural integrity of the adjacent structures, there are other factors outside of the parameters

of structural design that can adversely affect the satisfactory performance of the shoring system

such as improper construction techniques or errors, geotechnical issues not predicted in the report,

environmental issues, unforeseen activities occurring outside of the site and so on. it is therefore of

paramount importance that the construction methodology proposed by the builder is reviewed and

monitored by the structural and geotechnical engineers.

The recommendations and opinions expressed in the above report include explicit references to

issues that must be addressed during the construction and detailed structural design phase of this

project. Should these recommendations not be implemented then STRUCTURE Consulting

Engineers accept no responsibility for the performance of the proposed and existing structures.

Yours sincerely,

Wayne Teng

Senior Engineer

Tonkin

Enc Tonkin Markup on Architectural Sketch Design Rev 2

Page 3: STRUCTURAL METHODOLOGY REPORT UNDERPINNING TO …

WALL TYPES EXISTING WALL

DEMOLISHED

PROPOSED

SITE B

DY

SITE BDY

SITE BDY

SITE BDY

MEDIA

LAUNDRY

FAMILYDECK

KITCHEN

POOL

DECK

LAWN

WC

BEAM OVER (2.12 U/S)

80

12345

ABSORPTI ON PITABSORPTI ON PIT

RL 41.06RL 40.90

RL 40.14CH 2.275M

RL 40.06CH 2.40M

RL 41.06

BEAM OVER (2.27 U/S)

39 40 41 42

43

4039 4240.4

41.2 41.4 41.6 41.8 42.442.2

42.442.2

New double hung window 600Hx960W/1600SILL

Existing ground level over

Underpinning of existing foundation with new masonry foundation walls

New AG line to perimeter of newfoundation walls & connected to existing absorption pit in the rear yard

41

Remove access door& part wall

39.839.639.439.2

RL 40.06CH 2.40M

STORAGE

STORAGE

STORAGE

BEAM OVER (2.27 U/S)

BEAM OVER (2.12 U/S)

Excavation depth for strip footings approx. 2.4m

Excavation depth for strip footings approx. 1.4m

Excavation depth for strip footings approx. 2.4m

Excavation depth for strip footings approx. 1.8m

6580 4190 3840 7151

1886

5400

4500

3149

6580 4190 5416 10760

PROPOSED AREA 41M21 1

NEW BEAM OVER (2.27 U/S)

NEW BEAM OVER (2.27 U/S)

RL 40.06CH 2.40M

2

2

LEGENDPROPOSED ALTERATIONS & ADDITIONS

WORKS SUBJECT TO BUILDING CERTIFICATE

SCALE

FOR REVIEWDRAWING NUMBERPROJECT ISSUE

NORTH

REVISION

registration no. [email protected] 788 324

DRAWING TITLE

1 : 100 @ A3

SK102/ P2

LOWER GROUND FLOOR PLAN

ALTERATIONS & ADDITIONS5 REGENT ST PUTNEY NSW 2112

1M 5M 10M

Issue Date Description

P1 11/12/20 Prelodgment Issue

P2 15/01/20 Prelodgment Issue

FSR CALCULATION

Site Area= 570M2FSR = 0.5:1Max GFA = 285M2

Existing GFA = 33 (LG) + 130m2 (GF) + 52m2 (FF) = 215m2Existing FSR = 215/570 = 0.37:1

Proposed GFA = 74 (LG) + 130m2 (GF) + 52m2 (FF) = 256m2Proposed FSR = 256/570 = 0.45:1

A

A B C

A

BC

DE

A

Width of ExistingFooting

Length 1100 max

UNDERPINNING DETAIL TO INTERNALBRICK WALL Sequence A, B, C, D and E

1

1

2 31 2

1

1

23

123

21

32

13

1 3 2

UNDERPINNING DETAIL TO EXTERNALBRICK WALL Sequence 1, 2 and 3

Length 1100 max

Width 750 for mass concrete900mm for brick works

Item 1: Remove floor forhead height clearanceduring construction

Item 2: Underpin existingbearers with steel beams

Item 3: Demolish existingisolated brick piers

TONKIN MARKUP ON ARCHITECTURAL SKETCH DESIGN REV 2