Structural Integrity Management and Risk Based Inspection – Recent Developments

download Structural Integrity Management and Risk Based Inspection – Recent Developments

of 54

description

Structural Integrity Management and Risk Based Inspection – Recent Developments

Transcript of Structural Integrity Management and Risk Based Inspection – Recent Developments

  • G. Abdel Ghoneim, Ph.D., P.E.08 December 2009

    Structural Integrity Management and Risk Based Inspection Recent DevelopmentsSNAME Texas Section Meeting

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    2

    Agenda

    Introduction Gulf of Mexico Activity SIM and RBI Fundamentals Recent Standards Challenges Summary

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    309 December 2009

    GOM Platform Activity

    Source: MMS0

    100

    200

    300

    400

    500

    600

    700

    800

    900

    400

    WaterDepth(ft)

    N

    o

    .

    o

    f

    S

    t

    r

    u

    c

    t

    u

    r

    e

    s

    19451972

    19731982

    19832009

    Source: MMS, B.J. Kruse, III

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    4

    GOM Platform Decommissioning

    GoM Platform Vintage (Years)

    15%

    25%

    30%

    30%

    30

    Total ~ 3,900 Platforms

    Average Removal Age ~ 16 years

    Source: MMS, B.J. Kruse, III, K. S. Patterson, WISTA Oct 2008

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    5

    The Issues

    Source: O'Connor, BP, M. Lalani, June 2007

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    6

    API RPs and Guidelines API 2A-WSD, Recommended Practice for Planning Designing and Constructing Fixed

    Offshore Platforms Working Stress Design.

    API 2A-LRFD, Recommended Practice for Planning Designing and Constructing Fixed Offshore Platforms Load and Resistance Factor Design.

    API Bulletin 2TD, Guidelines for Tie-downs on Offshore Production Structures for Hurricane Season.

    API 2T, Recommended Practice for Planning Designing and Constructing Tension Leg Platforms.

    API 2FPS, Recommended Practice for Planning Designing and Constructing Floating Production Systems.

    API 2SK, Recommended Practice Design and Analysis of Stationkeeping Systems for Floating Structures.

    API 2RD, Recommended Practice Design of Risers for Floating Production Systems (FPSs) and Tension-Leg Platforms (TLPs).

    API 2I, Recommended Practice In-Service Inspection of Mooring Hardware for Floating Drilling Units.

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    7

    API 2HINS Inspection Initiator Process

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    8

    Destroyed GoM Platforms

    2 3

    148

    3 2 3 3

    40

    7 7

    47

    69

    2

    60

    0

    10

    20

    30

    40

    50

    60

    70

    80

    1948 1961 1964 1965 1969 1974 1979 1985 1992 2002 2004 2005 2005 2008 2008

    Year

    N

    u

    m

    b

    e

    r

    o

    f

    P

    l

    a

    t

    f

    o

    r

    m

    s

    D

    e

    s

    t

    r

    o

    y

    e

    d

    2.00E-04

    1.00E-03

    5.00E-04

    1.00E-03

    5.00E-044.00E-04

    1.00E-050.00E+00

    2.00E-04

    4.00E-04

    6.00E-04

    8.00E-04

    1.00E-03

    1.20E-03

    Stiff, 2009 Stiff, 2009 Stahl, et.al.,2000

    THIC, 1992 Stahl, 1986 ISO 19901-2,2004

    ISO 19902,2008

    Source

    A

    n

    n

    u

    a

    l

    F

    a

    i

    l

    u

    r

    e

    P

    r

    o

    b

    a

    b

    i

    l

    i

    t

    y

    SRRSR =

    100SRRSR =

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009 9

    Platform Structural AnalysisLoad exposure

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    10

    Safety format (LRFD vs. WSD)

    FactorResistance

    Load and Resistance

    P

    r

    o

    b

    a

    b

    i

    l

    i

    t

    y

    D

    e

    n

    s

    i

    t

    y

    MeanLoad

    MeanResistance

    FactorLoad

    CharacteristicResistanceLoad

    Characteristic

    Requirement Rd

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    11

    SIM Process

    Management of Change

    CompanyPolicy

    Reporting and Communication

    InformationManagement

    Organization andPersonnel

    Audits andReviews

    ContingencyPlans

    SIM Process

    Develop Integrity Management Plan (IMP) forStructure / System

    Implement IMP for theStructure / System

    Learning and Improvement

    Hazard Evaluation andRisk Assessment

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009 Slide 12

    Principles of Asset Integrity Management Integrity management life cycle activities

    Evaluate Risk

    Maintain

    Inspect

    Monitor Integrity

    Plan survey

    InspectRecordfindings

    Evaluate findings

    Filter findings

    Assess risk(incl. SRS)

    Update risk status Update overall

    inspection plan

    Plan follow upactions

    Do follow-up actions

    Integrity

    FindingsActions

    Inspection plan

    12

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    13WCT

    Seminar April 26,

    Why SIM - Ageing Problem? The contribution of structural failure to the total number of historic

    accidents is less than 10% based on worldwide data (Kvitrud, et. al., 2001).

    The reliability of a structure against environmental loads may become unacceptable in extended lifetime. Subsidence, degradation and changes to the original design may occur at a higher rate in extended platform life.

    Lack of data on the structure (e.g. drawings, steel type, welding procedures, inspection results and details about earlier repairs etc.) may result in higher uncertainty.

    Using a systematic approach for evaluating whether a structure is safe for use beyond its initial design life, taking the above mentioned issues into account, is the objective of SIMS.

    The SIM system has proven invaluable even for relatively newer structures both fixed and floating.

    Ersdal, G. Ph.D. Thesis, U of Stavanger, October 2005

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    14

    Ageing & Need for SIM & RBI

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    15

    What is Risk-Based Inspection (RBI)?

    Strategic process for lowering risk and lowering cost An integrated, data-based methodology that factors risk into inspection

    decision making

    Risk analysis includes not only probability of failure (PoF) but also consequence of failure (CoF)

    A qualitative and quantitative process for managing structurres/equipment based on risk analysis

    A systematic process that establishes and prioritises risk levels for each component in the structure

    RBI is an important element in the SIM system.

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    16

    Input data

    Condition Evaluation

    Action plans

    Observations

    Events / History

    Inspection results

    MonitoringAnalyses / (re-)design

    Condition evaluations(sections and components)

    Activities plan Inspection plan

    Inspections

    Monitoring results

    Operating req. & limits

    ORBIT : Main principles

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    17

    Terminology Robustness RSR Push-over/Time-domain Assessment/Re-assesment Risk/Reliability RBI Design Life Standards/Regulations Limit States WSD/ASD and LRFD Design Criteria Joint Flexibility SRS Load Factor

    Fatigue/Fracture Failure Safety Category Consequence of Failure Category Strength Hazards Acceptability Criteria Air Gap Wave-in-Deck Probabilistic Methods Bayesian Approach Degradation Fitness-for-purpose SIMS Bias

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    18

    The Two Main Steps of RBI

    Expected RISK Cost

    0

    1

    2

    3

    4

    5

    6

    1.0E-04 1.0E-03 1.0E-02 1.0E-01Target Failure Probability Level

    N

    o

    r

    m

    a

    l

    i

    s

    e

    d

    E

    x

    p

    e

    c

    t

    e

    d

    C

    o

    s

    t

    Expected Inspection CostExpected Failure Cost

    Expected Repair CostTotal Expected Risk Cost

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    19

    Key Concepts

    The Key Concepts of RBI

    RISK = Probability of Failure XConsequence of

    FailureGFF Item DFX

    Age

    Damagetype/rate

    Insp.effective.

    Damage areaItem repair

    Other repairsInjury

    Business int.Env. clean up

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    20

    Consequence models estimate:- Heat radiation levels from fires- Gas dispersion distances- Durations of fires- Explosion pressures- Number of fatalities per accident- Environmental effect

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    21

    Reducing Risk

    Inspection frequencies Inspection scope / thoroughness Inspection tools / techniques Inspection practices (internal vs. external) Building more Redundancies Maintenance Proper use/understanding the limitations Emergency response Trained crew Effective communication lines Local knowledge

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    22

    Marine Safety Regulations

    Classification Societies

    Rules

    Rules

    Classification of Mobile Offshore Units

    Formal Safety Assessment

    Step 1 HazardIdentification

    Step 2Risk

    Assessment

    Step 5Decision Making

    Recommendations

    Step 3Risk Control Options

    Step 4Cost Benefit Assessment

    International Maritime

    Organization

    MODU Code

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    23

    Risk Assessment Hazard review

    Hazard checklist

    HAZOP (hazard and operability study)

    FMECA (failure modes, effects and criticality analysis)

    SWIFT (structured what-if analysis)

    Risk matrices

    Risk ranking

    Structured judgement

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    24

    Risk Assessment

    Major accident

    Controls

    THREATS CONSEQUENCES

    Accident Scenario

    Management System

    Fault trees

    Event trees

    Bow tie diagrams

    Rules and standards

    Engineering judgement

    Risk criteria

    Cost-benefit analysis

    Company values

    Unacceptableregion

    I

    n

    c

    r

    e

    a

    s

    i

    n

    g

    i

    n

    d

    i

    v

    i

    d

    u

    a

    l

    r

    i

    s

    k

    s

    a

    n

    d

    s

    o

    c

    i

    e

    t

    a

    l

    c

    o

    n

    c

    e

    r

    n

    s

    Tolerableregion

    Broadly acceptableregion

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    25

    Quantitative Methods

    Weather Outcome

    Severe 50% fatalities0.01

    Rough 30% fatalities0.09

    Evacuation1.0E-04 Moderate 10% fatalitiesper year 0.4

    Calm 5% fatalities0.5

    Severe5%

    Rough28%

    Moderate41%

    Calm26%

    Historical data analysis

    Fault tree analysis

    Event tree analysis

    Consequence modelling

    Evacuation modelling

    Risks and uncertainties

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    26

    Influences on Technique Selection

    Decision context

    Lifecycle stage

    Major hazard potential

    Novelty/non-standard

    Uncertainty

    Views/perceptions

    Techniques

    Practicality

    Strengths and weaknesses

    Good practice

    Efficiency

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    27

    Traditional Inspection Planning vs. RBI Planning

    Traditional

    Inspection based on experience (usually by previous failures/breakdowns)

    Inspection effort driven by likelihood of failure

    Reactive fire fighting, running behind the ball

    Use of appropriate / Inappropriate NDT techniques

    RBI

    Inspection based on experience andsystematic (risk) review

    Inspection effort driven by risk, i.e. likelihood of failure and consequences of failure

    Pro-active planning and execution of inspections

    Systematic identification of appropriate NDT techniques

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    28

    Suitable and Sufficient Inspection Planning

    Suitable techniques appropriate for the assessment being made

    Sufficient adequate to show the risks are ALARP, without requiring further elaboration

    S in g le co m p o n e n t co n sid d e re d ; D e sig n l ive = 20 y r

    1 .0E-06

    1 .0E-05

    1 .0E-04

    1 .0E-03

    1 .0E-02

    0 2 4 6 8 10 12 14 16 18 20S e rv ic e tim e in y e a rs

    F

    a

    i

    l

    u

    r

    e

    p

    r

    o

    b

    a

    b

    i

    l

    i

    t

    y

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    29

    RBI Investment and Savings

    $400,000

    $65,000$85,000$50,000

    $500,000

    $675,000

    $250,000

    $550,000$600,000

    $0$100,000$200,000$300,000$400,000$500,000$600,000$700,000$800,000

    Total $ Savings = $1.1MROI = 22:1

    RBIStudyInvest

    Inspect& MaintSavings

    ProdCost

    Savings

    RBIStudyInvest

    Inspect& MaintSavings

    ProdCost

    Savings

    RBIStudyInvest

    Inspect& MaintSavings

    ProdCost

    Savings

    Total $ Savings = $650,000ROI = 8:1

    Total $ Savings = $1.25MROI = 19:1

    Chemical Plant Chemical Plant -- 200200Pressure VesselsPressure Vessels

    Refinery Refinery -- 3535Pressure VesselsPressure Vessels

    Refinery Refinery -- 5050Pressure VesselsPressure Vessels

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    30

    $100,000$200,000$300,000$400,000$500,000$600,000$700,000$800,000

    $65,000$50,000

    $500,000

    $675,000

    $75,000

    $550,000$600,000

    $0

    Total $ Savings = $1.1MROI = 22:1

    RBIStudyInvest

    Inspect& MaintSavings

    ProdCost

    Savings

    RBIStudyInvest

    Inspect& MaintSavings

    ProdCost

    Savings

    RBIStudyInvest

    Inspect& MaintSavings

    ProdCost

    Savings

    Total $ Savings = $1.52MROI = 20:1

    Total $ Savings = $1.25MROI = 19:1

    Chemical Plant Chemical Plant -- 200200Pressure VesselsPressure Vessels

    Offshore InstallationOffshore InstallationPiping & VesselsPiping & Vessels

    Refinery Refinery -- 5050Pressure VesselsPressure Vessels

    $1,520,000

    rbi invesment & savings

    Typical ROI = 8:1

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    31

    ORBIT Structure

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    32

    RBI Detailed Assessment

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    33

    RBI Detailed Assessment

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    34

    Inspection PlanningChallenges: No general standard, guideline or common industry practice available

    for inspection planning for structures

    SIMS

    RBI analysis

    ORBIT/Profast

    RBI analysis report

    Member condition Inspection history

    Updated Master RBI Table- RBI Input and results

    Inspection plan (FIPs)

    RBI Analysis Process

    SIMS FIPs Upload

    Orbit Workflow ManagerOrbit Workflow Manager

    New fatigue analysis results

    Updated FIPs

    (input and results)

    Master RBI Table (2004)- Fatigue point identification - fatigue damage rates - Analysis Method Fatigue- Analysis Method Collapse- consequence of member failure- preferred inspection method- etc.

    Only done ones

    New RBI Analysis results (Profast jnl files & database

    New fatigue analysis

    Fatigue Master Table

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    35

    Relevant DNV Publications RP-F107 Pipeline Risk Assessment RP-G101 RBI of Topsides Equipment OS-E304 Offshore Mooring Steel Wire Ropes OSS-121 Class base on Risk Assessment OSS-303 Risk Based Verification OSS-304 Risk Based Verification of Offshore Structures

    Available online: webshop.dnv.com

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    36

    DNV RP-F107 Pipeline Risk AssessmentCost Benefit Analysis Risk Matrix

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    37

    DNV RP-G101 RBI of Topsides Equipment

    Maintenance Management System

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    38

    DNV RP-G101 RBI of Topsides Equipment

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    39

    DNV RP-G101 RBI of Topsides Equipment

    ISO 17776 (2000)

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    40

    Push-over Analysis

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    41

    SIM System

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    42

    Decision Time

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    43

    To document safe use until end of production Date for change in platform operation(from manned to unmanned)

    Cost and scheduling of structural mitigation

    Objective Reassessment of Jacket Platforms:

    Structural Operational Challenges

    To document safe use until end of production Date for change in platform operation(from manned to unmanned)

    Establish evacuation criteria Cost and scheduling of structural mitigation Inspection planning

    Objective Reassessment of Jacket Platforms:

    Wave diffraction Earthquake / Accidental Loads

    COG

    Structural modifications/ Weight Management

    Subsidence of seabed/Possible WiD

    Foundationcapacity

    DeckStrength

    Platform strength

    New Env.Criteria

    Fatigue strength &Inspection planning

    Large amount of

    information

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    44

    Some Challenges

    Wave-in-deck-load (WiD) and load on jacket (WoJ) and variation with time

    -30

    -20

    -10

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    2.2 2.7 3.2 3.7 4.2 4.7 5.2 5.7 6.2 6.7 7.2 7.7 8.2 8.7 9.2 9.7

    Time (sec)

    F

    x

    (

    M

    N

    )

    -30

    -20

    -10

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    F

    z

    (

    M

    N

    )

    Fx - Total (inc. "jet" effect)Fx - WoJ (incl. "jet" effect)Fx - WoJ (without "jet" effect)Fx - WiD (Comflow)Fz - WoJ Fz - WiD (Comflow)

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    45

    Challenges (contd)

    Determination of failure criteria P

    delta

    Excessive deformation

    P

    Axial joint deformation, delta

    Elasticflexibility

    Dynamic behavior- Rise time for wave-in-deck load coincide with one quarter of platform

    lowest eigenperiod

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    46

    New vs. Old

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    47

    NORSOK STANDARD N-006, March 2009

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    48

    NORSOK Assessment Principles Requirements to in-service inspection planning and structural integrity management

    of jacket structures in general may be found in ISO 19902, Clause 23.

    Requirements to inspection and condition monitoring are given in ISO 19903, Chapter 14.

    Requirements to in-service inspection, monitoring and maintenance are given in ISO 19904-1, Chapter 18.

    Shut-down and unmanning procedure shall be implemented in order to ensure that there is less than 5x10-4 annual probability of the facility being exposed to environmental actions exceeding the structural capacity determined according to the ALS, with personnel onboard.

    In cases of pollution risk or main safety function impairment it should be shown that the combined probability of a structural failure and leakage that could lead to significant pollution is less than 1x10-4 per year.

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    49

    API RP 2SIM (Draft) ToC

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    50

    API RP 2SIM (Draft)

    Data Evaluation Strategy Program

    Managed systemfor archive andretrieval of SIMdata and other

    pertinent records

    Evaluation ofstructural integrity

    and fitness forpurpose;

    development ofremedial actions

    Overall inspectionphilosophy &strategy andcriteria for in-

    service inspection

    Detailed workscopes forinspection

    activities andoffshore execution

    to obtain qualitydata

    SIM Process and Document Organization

    Data Evaluation Strategy ProgramInitiatorTriggered

    Assessment

    Yes

    No

    Source: Draft API RP 2SIM

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    51

    API RP 2SIM (Draft) RBI Intervals

    RiskCategory Inspection Interval Ranges

    High 3-years to 5-years

    Medium 6-years to 10-years

    Low 11-years or greater

    Notes:a) The timing for the first underwater periodic inspection should be determined

    from the date of platform installation or when the baseline inspection was completed.

    b) Risk-based intervals should be adjusted to verify uninterrupted cathodic protection of the platform. This should be based on data evaluation from prior inspections.

    Assessment Initiator(See 4.3.5)

    Assessment Category(See 4.3.4.4)

    Assessment Information(See 7.3)

    InadequateDeck Height?(see 4.3.5.1)

    Simple Method(see 7.5)

    Design Level Method

    (see 7.6)

    Ultimate Strength Method

    (see 7.7)

    Alternative Methods(see 7.8)

    YES

    Assessment MethodsSection 7

    Assessment Criteria

    - Design Level- Ultimate Strength- Environmental Load

    Assessment CriteriaSections 8, 9

    - Assessment Type- Assessment Category

    - Assessment Criteria- Load Approach

    RSR Criteria

    - Assessment Category

    - Minimum RSR

    Pass Assessment? Mitigation and Risk Reduction Section 9

    Document(see 4.2)

    Consequence of Platform Failure (see 4.3.4)

    MitigationAnd Risk

    Assessment

    AssessmentMethod

    Assessment Category

    and Assessment Information

    Source: Draft API RP 2SIM

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    52

    API 2A 20th and 21st Ed. RSRs

    Assessment Category Reserve Strength Ratio (RSR)

    A-1 High 1.21

    A-2 Medium 0.8

    A-3 Low 0.62

    1. This RSR is applicable only for continued use of the platform for its present purpose. Not applicable for Change-of Use conditions.

    2. Not to be used for water depth greater than 400 ft.

    Assessment Category Reserve Strength Ratio (RSR)

    API RP2A 19th Edition and

    Earlier

    API RP2A 20th Edition and Later

    A-1 High 1.6 2.0

    Assessment Category Reserve Strength Ratio (RSR)

    GoM L-1 (High) 1.6 for Central Region11.2 for Other Regions

    GoM L-2 (Medium) 1.2

    GoM L-3 (Low) 1.0

    Other U.S. Offshore Areas

    2.0

    1. Includes platforms located in the associated Transition Regions. The 100-year return period metocean conditions as defined in API RP2 MET should be used to compute the RSR.

    20th Ed. GOM

    20th Ed. Other U.S. Offshore Areas

    21st Ed. GOM

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    53

    Summary

    Structural Integrity Management (SIM) and Risk based inspection planning (RBI) are tools employed to develop bases for asset management and in-service inspection in order to extend the useful life of the structure and increase its reliability level.

    SIM is geared towards managing the asset data and communicating status to corporate management in a systematic manner.

    RBI entails: - A risk screening process in order to identify critical areas and summarize the failure

    modes. - The consequences of possible failures and repair strategy are established in close

    co-operation with the operator. - The costs of inspection and repair for failures are established.- Probabilistic progressive collapse analyses are performed for a number of

    representative mechanisms in the structures. - A cost optimal inspection strategy is established.

    Finally, a user friendly tailor made software is developed to to perform the life cycle management of the Assets.

  • Det Norske Veritas AS. All rights reserved.

    SIM and RBI Recent Developments

    SNAME Texas Section Meeting, 08 December 2009

    54

    Safeguarding life, property and the environment

    www.dnv.com

    Structural Integrity Management and Risk Based Inspection Recent DevelopmentsAgendaGOM Platform ActivityGOM Platform DecommissioningThe IssuesAPI RPs and GuidelinesAPI 2HINS Inspection Initiator ProcessDestroyed GoM Platforms Platform Structural AnalysisSafety format (LRFD vs. WSD) SIM ProcessPrinciples of Asset Integrity Management Integrity management life cycle activitiesWhy SIM - Ageing Problem?Ageing & Need for SIM & RBIWhat is Risk-Based Inspection (RBI)?Slide Number 16TerminologyThe Two Main Steps of RBIKey ConceptsSlide Number 20Reducing RiskMarine Safety RegulationsRisk AssessmentRisk AssessmentQuantitative MethodsInfluences on Technique SelectionTraditional Inspection Planning vs. RBI PlanningSuitable and Sufficient Inspection PlanningRBI Investment and Savingsrbi invesment & savingsORBIT StructureRBI Detailed Assessment RBI Detailed AssessmentInspection PlanningRelevant DNV PublicationsDNV RP-F107 Pipeline Risk AssessmentDNV RP-G101 RBI of Topsides EquipmentDNV RP-G101 RBI of Topsides EquipmentDNV RP-G101 RBI of Topsides EquipmentPush-over AnalysisSIM SystemDecision TimeSlide Number 43Some ChallengesChallenges (contd)New vs. OldNORSOK STANDARD N-006, March 2009NORSOK Assessment PrinciplesAPI RP 2SIM (Draft) ToCAPI RP 2SIM (Draft)API RP 2SIM (Draft) RBI IntervalsAPI 2A 20th and 21st Ed. RSRsSummarySlide Number 54