STRUCTURAL ENGINEERING CONCEPTS, PLC · structural engineering concepts, plc Miller, of O'Donnell &...
Transcript of STRUCTURAL ENGINEERING CONCEPTS, PLC · structural engineering concepts, plc Miller, of O'Donnell &...
1
0
February 25, 2014
Mr. Butch Stoneman
Technical Foundations, Inc.
P.O. Box 50282
Richmond, VA 23250
SUBJECT: UVA Student Housing – 1000 West Main – Probe Hole Results
Dear Mr. Stoneman:
We forgot to include the Probe Hole results in yesterday’s letter detailing the pile load tests and subsequent
recommendations. Please find the summaries on page 2 of P-1 through P-5 that were drilled on February 6th.
The probe hole information provided us with valuable information on how far a 16” auger could be advanced into the
soft weathered rock. Probe Holes P-1, P-2 and P-3 hit refusal at depths of 78’, 55’ & 60’ respectively. Holes P-4 & P-5
were terminated at depths of approximately 80’. Let me know if you have any questions.
Sincerely yours,
STRUCTURAL ENGINEERING CONCEPTS, PLC
Jonathan H. Smith, P.E. Project Manager
STRUCTURAL ENGINEERING CONCEPTS, PLC P .O. Box 1 74 6 | Mid l o th i an , VA 23 11 3 | Phon e 8 04 . 56 1 . 0 98 1 | Fax 8 04 . 56 1 . 18 19 | ww w. seconce p t s p l c . c om
Depth Time Description Depth Time Description
0-5' 2:56 Red brown dirt, gravel 0-5' 12:14 Red and brown dirt/gravel
5-10' Dark brown dirt and sand, gravel 5-10' Red and brown moist dirt/gravel
10-15' Dry light brown dirt and sand 10-15' Dry-moist dark brown dirt
15-20' Dry light brown dirt and sand 15-20' Dry-moist dark brown dirt
20-25' Dry light brown dirt and sand weathered small rocks 20-25' Dry light brown dirt/small rocks
25-30' Dry light brown dirt and sand 25-30' Dry light brown dirt/small rocks
30-35' Dry light brown dirt and sand 30-35' Dry light brown dirt/small rocks
35-40' Dry light brown dirt and sand 35-40' 12:22 Dry light brown dirt and sand/weathered rock
40-45' 3:07 Dry light brown dirt and sand 40-45' 12:24 Dry light brown dirt and sand/weathered rock
45-50' Dry light brown dirt and sand 45-50' 12:26 Dry light brown dirt and sand/weathered rock
50-55' 3:17 Dry light brown dirt and sand, larger more weathered rock 50-55' Dry light brown dirt and sand/weathered rock
55-60' 3:20 Dry light brown dirt and sand, larger more weathered rock 55-60' 12:34 Dry darker brown dirt, weathered rock
60-65' 3:22 Dry light brown dirt and sand, larger more weathered rock 60-65' 12:37 Dry brown dirt, weathered rock
65-70' Dry light brown dirt, weathered rock 65-70' Dry brown dirt/sand, weathered rock
70-75' 3:30 Dry light brown/light grey dirt, weathered rock 70-75' Dry brown dirt/light grey dirt, weathered rock
75-80' 3:33 78' Refusal 77-78' 2 minutes 75-80' 12:53 78' - Dry brown /light grey dirt, weathered rock
Depth Time Description Depth Time Description
0-5' 2:05 Red dirt, gravel 0-5' 10:05 Dry light brown dirt and sand/gravel
5-10' Dark brown dirt, gravel 5-10' Dry light brown dirt and sand/gravel
10-15' Redish brown dirt 10-15' 10:08 Dry light brown dirt and sand/gravel
15-20' Light brown dirt and sand 15-20' Dry light brown dirt and sand/gravel/ small rocks
20-25' Light brown dirt and sand 20-25' Dry light brown dirt and sand/gravel/ small rocks
25-30' Light brown dirt and sand, weathered rock 25-30' 10:18 Dry light brown dirt and sand/gravel/ small rocks
30-35' 2:12 Dry light brown dirt, weathered rock 30-35' 10:20 Dry light brown dirt and sand/gravel/ small rocks
35-40' 2:14 Dry light brown dirt, weathered rock 35-40' 10:22 Dry darker dirt and sand/small rocks
40-45' 2:17 Dry light brown dirt, weathered rock 40-45' 10:24 Dry darker dirt and sand/ weathered rock
45-50' Dry light brown dirt, weathered rock 45-50' 10:26 Dry darker dirt and sand/ weathered rock
50-55' 2:28-2:31 Dry light brown dirt, weathered rock 50-55' Dry darker dirt and sand/ weathered rock
55-60' 55' - Auger Refusal 54-55' 3 minutes 55-60' 10:41 Dry light grey dirt and sand/ weathered rock
60-65' 10:44 Dry light grey dirt and sand/ weathered rock
65-70' 10:46 Dry grey dirt and sand/ partial weathered rock
70-75' 11:10 Dry brown dirt and sand, weathered rock
Depth Time Description 75-80' 11:13 82' - Dry brown dirt and sand, weathered rock
0-5' 1:17 Dry Brown dirt
5-10' Dry dark brown dirt
10-15' Moist redish brown dirt
15-20' Dry light brown dirt and sand, small rocks
20-25' 1:21 Dry light brown dirt and sand, small rocks
25-30' Dry light brown dirt and sand, small rocks
30-35' 1:24 Dry light brown dirt and sand, small weathered rocks
35-40' 1:26 Dry light brown dirt and sand, small weathered rocks
40-45' 1:30 Dry light brown dirt and sand, weathered rock
45-50' Dry light brown dirt and sand,large weathered rocks
50-55' Dry darker brown dirt and sand, weathered rock
55-60' 60' Refusal 59-60' 3 minutes, light brown weathered rock
UVA CA Ventures- Probe Pile P-1 Summary
UVA CA Ventures- Probe Pile P-2 Summary
UVA CA Ventures- Probe Pile P-3 Summary
UVA CA Ventures- Probe Pile P-4 Summary
UVA CA Ventures- Probe Pile P-5 Summary
2
1
0
February 24, 2014
Mr. Butch Stoneman
Technical Foundations, Inc.
P.O. Box 50282
Richmond, VA 23250
SUBJECT: UVA Student Housing – 1000 West Main – Auger Cast Pile Load Tests
Dear Mr. Stoneman:
We have reviewed the data from the load tests performed on TP-1 and TP-2. TP-1 was installed on February 7th
to a
depth of 50 feet below existing grade. The testing began on February 17th but was not completed until February 19
th due
to a malfunctioning jack that had to be corrected. TP-2 was installed on February 10th
to a depth of 46 feet below
existing grade. The testing of TP-2 occurred on February 20th. The depths for the test piles were determined from
information collected during the drilling of probe holes P-1 through P-3. We wanted TP-1 to extend into dense
weathered rock in order to get the pile capacity by skin friction and end bearing. For TP-2 we wanted to test the skin
friction values so we terminated the pile in Soft Weathered Rock. The load tests were performed in general accordance
with ASTM D1143 and the piles were loaded to a maximum compressive load of 271.875 tons (543.75 kips). TP-1 was
able to hold the maximum load with acceptable deflections which can be seen on the graph summarizing the load test
data on page 3. TP-2 was loaded to the same maximum load but at deflections greater than 2”. A portion of the data
has been omitted from the graph on page 4 since it wasn’t relevant in determining the ultimate compressive capacity of
the pile.
TP-1
Typically the ultimate capacity of auger cast piles is equal to the load at which the measured settlement equals PL/AE +
(0.15+0.008D), where D is the diameter of the pile. This is called the Davisson Offset method. For D=16” the equation
reduces to PL/AE + 0.278”. The PL/AE term represents the elastic deflection of the pile. The measured deflections for
TP-1 never exceeded the elastic deflection of the pile so we did not plot the Davisson Offset line on the graph on page
3. It is our opinion that TP-1 has an ultimate compressive capacity of more than 270 tons (540 kips). Using a factor a
safety of 2.0 gives an allowable compressive capacity of 135 tons (270 kips). We attempted to back calculate the skin
friction and end bearing values based on the results of the load test while adjusting for the portion of the pile above EL.
474 (proposed top of production pile elevation). The results yielded a higher end bearing value than what is general
recommended by GEC-8. Although we believe these higher values can be supported by the load test it is our opinion
that these higher values should not be consistently counted on for production piles.
TP-2
The measured deflections for TP-2 exceeded the Davisson Offset threshold at just over 150 tons (300 kips). Due to the
amount of pile settlement that occurred we believe that the pile achieved its capacity through skin friction and not from
end bearing. It is our opinion that the ultimate compressive capacity of TP-2 is approximately 150 tons (300 kips).
Using a factor of safety of 2.0 gives an allowable compressive capacity of 75 tons (150 kips). We back calculated the
skin friction values based on the results while taking into consideration the portion of the pile above EL. 474.
STRUCTURAL ENGINEERING CONCEPTS, PLC P .O. Box 1 74 6 | Mid l o th i an , VA 23 11 3 | Phon e 8 04 . 56 1 . 0 98 1 | Fax 8 04 . 56 1 . 18 19 | ww w. seconce p t s p l c . c om
2
Compressive Capacity
Based on the variability of the soft weathered rock we feel that it would be prudent to limit the allowable compressive
capacity to 100 tons. While higher capacities can be achieved it would require that all piles be extended to “refusal”
which may lead to piles with varying depths even for those in the same pile cap. Using an allowable compressive
capacity of 100 tons will make it easier to specify a consistent pile length for each portion of the site. We believe that
using 16” diameter auger cast piles with an allowable capacity of 100 tons will result in a 20-25% reduction in the
overall number of piles compared to the number of 75-ton allowable piles shown on Sheet S2.00a (Design Development
Set 2/7/14). This should result in significant savings for the owner. The pile lengths will vary across the site due to the
differing depths to and thickness of the soft weathered rock and dense weathered rock layers. The piles will generally
range in depth from 35’-40’ when installed from EL. 474. We also want to point out that no probe holes or test piles
were done on the upper (West) portion of the site. A minimum of one test pile should be performed on this portion of
the site to verify the results. This can be done while production piles are being installed on the portion of the site which
was the subject of the probe hole and test pile program.
Uplift Capacity
The uplift capacity of the piles is a result of skin friction. Based on our calculations we believe that the 16” diameter
auger cast piles will provide an allowable uplift capacity of at least 75 tons at the same pile lengths necessary to achieve
the 100 ton allowable compressive capacities.
Lateral Capacity
The lateral capacity of TP-1 and TP-2 were not tested. Performing a lateral load test at these piles would provide little
benefit since the test would be performed at or near existing grades. The proposed production piles would be at or near
EL. 474. Based on our experience with projects having similar soil conditions it is our opinion that allowable lateral
capacities of 3.5-4 tons (7-8 kips) is reasonable for 16” diameter auger cast piles that utilize a steel reinforcing cage for
the top 10’-15’ of each pile. Slightly higher lateral capacities may be able to be accomplished but would likely require
heavier reinforcing steel cages. Once O’Donnel & Naccarato has determined the quantity and placement of the piles
they can then provide the lateral load to be used for the final pile design. Some piles may not need to provide lateral
capacities which would reduce the reinforcing steel requirements of those piles to a single center bar.
Please let me know if you have any questions.
Sincerely yours,
STRUCTURAL ENGINEERING CONCEPTS, PLC
Jonathan H. Smith, P.E. Project Manager
3
4
FROEHLING & ROBERTSON, INC.
Engineering Stability Since 1881
6181 Rockfish Gap Turnpike Crozet, Virginia 22932-3330 I USA T 434.823.5154 I F 434.823.4764
HQ: 3015 DUMBARTON ROAD RICHMOND, VA 23228 USA T 804.264.2701 F 804.264.1202 www.fandr.com
VIRGINIA • NORTH CAROLINA • SOUTH CAROLINA • MARYLAND • DISTRICT OF COLUMBIA • EASTERN EUROPE
A Minority-Owned Business
F&R Project No. 71R-3010 January 23, 2014 Campus Acquisitions Holdings, LLC 161 N. Clark Street, Suite 4900 Chicago, Illinois 60601 Attention: Mr. Steve Bus Subject: Addendum No. 2 to report of Report of Geotechnical Study University of Virginia Student Housing Charlottesville, Virginia Dear Mr. Bus: This letter is issued as Addendum No. 2 to F&R’s Report of Geotechnical Study for the project stated
above dated November 26, 2013, to provide recommendations regarding the mat foundation
system, as an alternative to the deep foundation system as recommended in F&R’s geotechnical
report. Unless noted otherwise herein, the recommendations given in F&R’s original geotechnical
report are still considered applicable.
Bearing pressure information was provided in an email and telephone correspondence with Michael
Miller, of O'Donnell & Naccarato structural engineering, including the electronically provided “Max
Soil Bearing Pressure Plan” dated 1/15/14. In addition to the subsurface data collected by F&R, we
have reviewed the borings logs developed from a previous exploration of the project site in a report
by Gooch Engineering entitled “Geotechnical Services – Holsinger Sqaure”, dated June 26, 2000. It
should be understood that the analysis provided herein is based on the assumption that the boring
data on the Gooch Engineering boring logs is accurate and was obtained with general adherence to
the industry standards. The Gooch exploration consisted of eleven test borings drilled to depths
ranging from 30 feet to 36 feet below the ground surface, and we have designated these borings as
GB-1 through B-11. The location and surface elevation of each Gooch boring was obtained from the
above mentioned report and should be considered approximate with respect to this addendum.
Based on the bearing pressures provided and the anticipated finished floor level at El 477, we have
calculated settlement estimates at each boring location shown on the attached Boring Location
Plan. The estimated settlements range from approximately 0.5 inches up to 3.8 inches; refer to the
table provided below.
Campus Acquisitions Holdings, LLC UVA Student Housing – Charlottesville, VA 71R-3010 2 January 23, 2014
Boring
No.
Estimated
Settlement
(inches)
Boring
No.
Estimated
Settlement
(inches)
B-1 0.5 GB-1 0.7
B-2 0.7 GB-2 0.7
B-3 0.8 GB-3 1
B-4 0.8 GB-4 0.8
B-5 0.6 GB-5 1
B-6 3.8 GB-6 1
B-7 3 GB-7 3
B-8 1 GB-8 1
B-9 1 GB-9 1
B-10 1.8 GB-10 2.1
B-11 0.9 GB-11 0.7
B-12 0.8
We understand that for the mat foundation to be feasible, settlements should be limited to 1 inch
or less. Based on the above settlement estimates, some degree of ground improvement will be
required for the areas of the site where the anticipated settlements are greater than 1 inch, in
order to proceed with the mat foundation option. The approximate limits of the area where ground
improvement would be needed is indicated on the Boring Location Plan; portions of the site that
fall outside the identified “limits of ground improvement” should not require improvement. Design
and implementation of ground improvement options should be discussed with a specialty
contractor (i.e. Technical Foundations, Hayward-Baker, Subsurface Construction).
We understand, based on our email and telephone correspondence, Pressure Grouting is being
considered as a method of ground improvement for this site. Though this option may improve the
subsurface materials as needed to achieve the required settlement tolerances, we understand that
it is difficult to design a site specific grouting plan because the degree of soil improvement is not
easily quantified without performing some post injection testing (i.e. Dilatometer or Cone
Penetration Testing). Therefore, the amount of grout injections and grout volumes may be difficult
to estimate for a cost benefit analysis prior to construction.
Alternatively, based on our discussions with specialty contractors, we understand that the desired
settlement control can be accomplished with more predictable results by using compacted stone
columns such as “Vibro Piers”. Vibro-Piers consist of a network of compacted stone columns that
are developed from the bottom-up and can extend up to 50 feet below the ground surface. This
network of stone columns along with the soil profile creates a stiffer composite material to provide
FR
OEH
LIN
G &
R
OB
ER
TS
ON
, IN
C
Eng
inee
rin
g S
tab
ility
Sin
ce 1
88
1
618
1 R
ock
fish
Gap
Tu
rnp
ike,
Cro
zet,
VA
22
93
2
T 4
34
.82
3.5
15
4 |
F 4
34
.82
3.4
76
4
Drawing No.
1
Bo
rin
g Lo
cati
on
Pla
n
Clie
nt:
Cam
pu
s A
cqu
isit
ion
s H
old
ings
, LLC
Pro
ject
: Un
ive
rsit
y o
f V
irgi
nia
Stu
den
t H
ou
sin
g
F&R
Pro
ject
No
.: 7
1R
301
0
Dat
e:
Jan
uar
y, 2
014
Sc
ale
: 1
” =
40’
B-1
B-2
B-3
B-4
B-5
B-6
B-7
B-8
B-9
B-11
B-12
GB-11
GB-7
GB-9
GB-8
GB-6
GB-5
GB-4
GB-1
GB-2
= Recommended Limits of Ground Improvement
GB-3
GB-10
B-10
400
410
420
430
440
450
460
470
480
490
500
510
510915
24
34
41
50/5
50/5
50/5
50/3
50/2
50/2
50/1
B-1761512
16
21
15
19
22
50/6
50/5
50/5
50/1
B-2
891012
8
14
26
13
51
51
38
42
50/5
50/3
B-37546
7
9
13
14
25
50/6
50/5
50/3
50/3
50/1
B-4
SUBSURFACE PROFILEProfile Name: 1
Elev
atio
n (f
t)
Plot Based on Elevation
City/State: Charlottesville, VirginiaProject: UVA Student HousingClient: Campus Acquisitions Holdings, LLC
Froehling & Robertson, Inc.
Project No: 71R3010
R
ELEV
_LAN
DSC
APE_
8.5X
11 7
1R-3
010.
GPJ
F&
R.G
DT
11/
22/1
3
400
410
420
430
440
450
460
470
480
490
500
510
30332250/6
61
50/4
50/5
50/4
50/1
50/1
50/1
50/5
50/1
50/4
50/4
50/1
B-5
4454
16
6
6
9
25
18
25
49
31
50/5
B-6 3366
9
13
7
9
33
46
50/5
50/1
50/4
B-7
4559
16
17
25
27
34
50/4
50/5
50/2
B-8
SUBSURFACE PROFILEProfile Name: 2
Elev
atio
n (f
t)
Plot Based on Elevation
City/State: Charlottesville, VirginiaProject: UVA Student HousingClient: Campus Acquisitions Holdings, LLC
Froehling & Robertson, Inc.
Project No: 71R3010
R
ELEV
_LAN
DSC
APE_
8.5X
11 7
1R-3
010.
GPJ
F&
R.G
DT
11/
22/1
3
400
410
420
430
440
450
460
470
480
490
500
510
13434
55
55
50/5
50/3
50/6
50/3
50/2
50/1
50/1
50/1
B-10
127917
53
50/6
50/6
50/6
50/4
50/1
B-11
2181919
34
24
42
56
51
50
50/6
50/5
50/4
50/4
50/6
50/5
B-12
36914
20
48
43
50/5
50/5
50/4
50/2
50/2
50/6
50/1
50/1
50/2
B-9
SUBSURFACE PROFILEProfile Name: 3
Elev
atio
n (f
t)
Plot Based on Elevation
City/State: Charlottesville, VirginiaProject: UVA Student HousingClient: Campus Acquisitions Holdings, LLC
Froehling & Robertson, Inc.
Project No: 71R3010
R
ELEV
_LAN
DSC
APE_
8.5X
11 7
1R-3
010.
GPJ
F&
R.G
DT
11/
22/1
3
430
440
450
460
470
480
490
500
510
14
9
13
17
22
53
50/4
GB-1
9
8
12
11
33
44
60
GB-1015
28
79
100
60
62/3
GB-11
14
12
22
25
34
18
24
GB-2
17
16
12
14
28
20
17
GB-3
12
64
33
22
100
46/2
GB-4
7
9
16
10
31
45
GB-5
6
11
12
16
35
33
GB-6
5
9
10
14
12
13
GB-7
5
10
50
100
100
100
GB-8
3
67
81
100
100/3
100/3
GB-9
SUBSURFACE PROFILEProfile Name: Gooch
Elev
atio
n (f
t)
Plot Based on Elevation
Project No: 71R3010
Froehling & Robertson, Inc.
Client: Campus Acquisitions Holdings, LLCProject: UVA Student HousingCity/State: Charlottesville, VA
R
ELEV
_LAN
DSC
APE_
11X1
7 U
VA S
TUD
ENT
HO
USI
NG
.GPJ
F&
R.G
DT
1/2
3/14
FROEHLING & ROBERTSON, INC.
Engineering Stability Since 1881
6181 Rockfish Gap Turnpike Crozet, Virginia 22932-3330 I USA T 434.823.5154 I F 434.823.4764
HQ: 3015 DUMBARTON ROAD RICHMOND, VA 23228 USA T 804.264.2701 F 804.264.1202 www.fandr.com
VIRGINIA • NORTH CAROLINA • SOUTH CAROLINA • MARYLAND • DISTRICT OF COLUMBIA • EASTERN EUROPE
A Minority-Owned Business
F&R Project No. 71R-3010 November 11, 2014 Campus Acquisitions Holdings, LLC 161 N. Clark Street, Suite 4900 Chicago, Illinois 60601 Attention: Mr. Ryan Boody Subject: Addendum No. 3 to report of Report of Geotechnical Study University of Virginia Student Housing Charlottesville, Virginia Dear Mr. Boody: This letter is issued as Addendum No. 3 to F&R’s Report of Geotechnical Study for the project
indicated above dated November 26, 2013, to provide updated recommendations regarding the
project’s foundation system, for we understand the building has been redesigned since our last
addendum. Unless noted otherwise herein, the recommendations given in F&R’s original
geotechnical report are still considered applicable.
The latest grading and building information was provided in an email correspondence with Mr.
Mark Miller, RA, including the electronically provided floor plans and building elevations by
emArchitecture, dated 10/30/14. Preliminary loading information was also provided in an email by
James W. Behler, PE, SECB, of O'Donnell & Naccarato, on 11/4/14. Column loads for western and
eastern portions of the proposed building will be up to 400 kips and 600 kips, respectively. We
understand that in order to reduce the amount of shoring needed for the project, the western
portion of the building will no longer consist of a basement, but rather provide at-grade parking at
El 498.75. The eastern portion will still consist of two levels of below grade parking with the P1
level at El 479.
We do not recommend the implementation of a mat foundation system due to the newly proposed
tiered configuration of the building. A deep foundation system consisting of auger cast piles with a
120 ton allowable compression capacity is still considered feasible, but we anticipate piles would be
required throughout the entire building footprint due to differential settlement concerns.
However, based on the loads and grading plan provided, we note the proposed structure may also
be supported by a shallow foundation system bearing on a combination of firm residual soils and
improved subgrades (stone columns).
Campus Acquisitions Holdings, LLC UVA Student Housing – Charlottesville, VA 71R-3010 2 November 11, 2014
We recommend that shallow foundations be designed for a net allowable bearing pressure not to
exceed 5,000 pounds per square feet (psf). To reduce the possibility of localized shear failures,
column and wall footings should be a minimum of 3 feet and 2 feet wide, respectively. We
recommend that all exterior footings be placed a minimum of 2 feet below finished exterior grades,
which should also be adequate to protect exterior footings against the effects of frost.
Settlement estimates using the provided preliminary loading information indicate that some degree
of ground improvement will be required for the areas of the site where the anticipated settlements
are greater than 1 inch, in order to proceed with the spread footings. The approximate limits of the
area where ground improvement would be needed below foundations is outlined on the Boring
Location Plan; portions of the site that fall outside the identified “limits of ground improvement”
should not require improvement.
Based on the subsurface data, the proposed lowest floor levels, and the structural loads, we
recommend that the ground improvement consist of stone columns. Stone columns are typically
constructed in groups under the wall and column footings to create a stiffer composite material and
control settlements to tolerable levels. Stone columns are proprietary systems which are designed
and constructed by specialty contractors using specialized drilling and tamping equipment. Due to
the relatively high groundwater levels recorded at the site, we recommend stone columns be
installed by bottom feed methods. Stone columns can also be installed using open hole drilling
techniques, but this method is generally not practical for sites with high groundwater levels. The
size, depth, and spacing of the stone columns is part of the design by the specialty contractor,
however, it is typical that the columns extend to depths of 10 to 30 feet below the bottom of
footing (depths of up to 50 feet are possible). Once the stone columns are installed, conventional
shallow foundations, as described above, can then be constructed.
Because the stone columns achieve much of their benefit by increasing the lateral confinement
within the surrounding soil matrix, excavations around stone columns after they are constructed
can be problematic. The stone column designer should provide more specific restrictions with
respect to excavating near the columns. This should be considered by the construction team when
planning the sequencing of the various aspects of the project such as the basement, underground
utilities, etc. In particular, we have found that in many cases where the structure has a partial
basement, that a second mobilization is required for the installation of either the deep foundation
option (i.e. auger cast piles or the stone columns) within the western portion of the building which
will be at grade. We do not recommend installation of either system prior to excavation and
construction the proposed north-south trending basement wall because of undermining
considerations.
FR
OEH
LIN
G &
R
OB
ER
TS
ON
, IN
C
Eng
inee
rin
g S
tab
ility
Sin
ce 1
88
1
618
1 R
ock
fish
Gap
Tu
rnp
ike,
Cro
zet,
VA
22
93
2
T 4
34
.82
3.5
15
4 |
F 4
34
.82
3.4
76
4
Drawing No.
1
Bo
rin
g Lo
cati
on
Pla
n
Clie
nt:
Cam
pu
s A
cqu
isit
ion
s H
old
ings
, LLC
Pro
ject
: Un
ive
rsit
y o
f V
irgi
nia
Stu
den
t H
ou
sin
g
F&R
Pro
ject
No
.: 7
1R
301
0
Dat
e:
No
vem
ber
, 20
14
Scal
e:
1”
= 4
0’
B-1
B-2
B-3
B-4
B-5
B-6
B-7
B-8
B-9
B-11
B-12
GB-11
GB-7
GB-9
GB-8
GB-6
GB-5
GB-4
GB-1
GB-2
= Recommended Limits of Ground Improvement
GB-3
GB-10
B-10
400
410
420
430
440
450
460
470
480
490
500
510
510915
24
34
41
50/5
50/5
50/5
50/3
50/2
50/2
50/1
B-1761512
16
21
15
19
22
50/6
50/5
50/5
50/1
B-2
891012
8
14
26
13
51
51
38
42
50/5
50/3
B-37546
7
9
13
14
25
50/6
50/5
50/3
50/3
50/1
B-4
SUBSURFACE PROFILEProfile Name: 1
Elev
atio
n (f
t)
Plot Based on Elevation
City/State: Charlottesville, VirginiaProject: UVA Student HousingClient: Campus Acquisitions Holdings, LLC
Froehling & Robertson, Inc.
Project No: 71R3010
R
ELEV
_LAN
DSC
APE_
8.5X
11 7
1R-3
010.
GPJ
F&
R.G
DT
11/
22/1
3
400
410
420
430
440
450
460
470
480
490
500
510
30332250/6
61
50/4
50/5
50/4
50/1
50/1
50/1
50/5
50/1
50/4
50/4
50/1
B-5
4454
16
6
6
9
25
18
25
49
31
50/5
B-6 3366
9
13
7
9
33
46
50/5
50/1
50/4
B-7
4559
16
17
25
27
34
50/4
50/5
50/2
B-8
SUBSURFACE PROFILEProfile Name: 2
Elev
atio
n (f
t)
Plot Based on Elevation
City/State: Charlottesville, VirginiaProject: UVA Student HousingClient: Campus Acquisitions Holdings, LLC
Froehling & Robertson, Inc.
Project No: 71R3010
R
ELEV
_LAN
DSC
APE_
8.5X
11 7
1R-3
010.
GPJ
F&
R.G
DT
11/
22/1
3
400
410
420
430
440
450
460
470
480
490
500
510
13434
55
55
50/5
50/3
50/6
50/3
50/2
50/1
50/1
50/1
B-10
127917
53
50/6
50/6
50/6
50/4
50/1
B-11
2181919
34
24
42
56
51
50
50/6
50/5
50/4
50/4
50/6
50/5
B-12
36914
20
48
43
50/5
50/5
50/4
50/2
50/2
50/6
50/1
50/1
50/2
B-9
SUBSURFACE PROFILEProfile Name: 3
Elev
atio
n (f
t)
Plot Based on Elevation
City/State: Charlottesville, VirginiaProject: UVA Student HousingClient: Campus Acquisitions Holdings, LLC
Froehling & Robertson, Inc.
Project No: 71R3010
R
ELEV
_LAN
DSC
APE_
8.5X
11 7
1R-3
010.
GPJ
F&
R.G
DT
11/
22/1
3
430
440
450
460
470
480
490
500
510
14
9
13
17
22
53
50/4
GB-1
9
8
12
11
33
44
60
GB-1015
28
79
100
60
62/3
GB-11
14
12
22
25
34
18
24
GB-2
17
16
12
14
28
20
17
GB-3
12
64
33
22
100
46/2
GB-4
7
9
16
10
31
45
GB-5
6
11
12
16
35
33
GB-6
5
9
10
14
12
13
GB-7
5
10
50
100
100
100
GB-8
3
67
81
100
100/3
100/3
GB-9
SUBSURFACE PROFILEProfile Name: Gooch
Elev
atio
n (f
t)
Plot Based on Elevation
Project No: 71R3010
Froehling & Robertson, Inc.
Client: Campus Acquisitions Holdings, LLCProject: UVA Student HousingCity/State: Charlottesville, VA
R
ELEV
_LAN
DSC
APE_
11X1
7 U
VA S
TUD
ENT
HO
USI
NG
.GPJ
F&
R.G
DT
1/2
3/14