Structural DesignProgram Review

Massachusetts Department of TransportationSeptember 20-23, 2011

Page 2: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Purpose of Review

Provide a service to MassDOT management Identify best practices Recognize areas of excellence Document policies & practices Identify opportunities for improvement

Page 3: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Outline Review Team Review Process General Observations Commendable Practices Opportunities for Improvement Discussion

Page 4: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Review Team

Olu Adeyemi – FHWA, Division Office, Cambridge Tom Saad – FHWA, Resource Center, Matteson Jamal Elkaissi – FHWA, Resource Center, Denver Derrell Manceaux – FHWA, Resource Center,

Denver Mike Arpino – FHWA, Division Office, Cambridge Guatam Sen - MassDOT, Boston Edmund Newton - MassDOT, Boston Craig Shike – Oregon DOT

Page 5: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Schedule

Tuesday Kick off Meeting Deputy Chief Engineer Director of Project Development Design and Project Managers ABP, In-House and Consultant Managers Hydraulics Engineer

Wednesday State Bridge Engineer ABP, In-House and Consultant Designers Roadway Design, Environmental and Planning Engineers Materials Division

Page 6: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Schedule

Thursday Geotechnical Engineers Construction Materials Control District Office Engineers Consultants

Friday Close Out

Page 7: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

General Observations

Professional and Motivated Staff Good Communications, but Specific

Suggestions for Improvement Dynamic Work Environment / Chain of

Command Numerous Major Advancements in last Five

Years

Page 8: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Opportunities for Improvement

Page 9: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Success due to leadership’s commitment to implement new practices and innovative delivery methods

ABP ABC FAST 14 DBE / DUCE (District Bridge Engineer-District

Utility Constructability Engineer) Design Build Implementation

Page 10: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Development, standardization and implementation of “State of the Practice” procedures

Design manuals Standard structural details NEXT beam LRFD procedures

Page 11: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Flexibility of staff to adapt to multiple reorganizations

ABP Design Build Special Project team New District Positions In-House Design

Page 12: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Expanded partnership with districts, consultants, and traveling public

ABP Design Build Manuals Development Expedited Project Delivery Environmental: Context Sensitive Design &

Bridge Aesthetics

Page 13: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Improvement in specific practices and procedures

Process of public involvement for project development is good

Decision matrix for implementing ABC technologies

Standard details Bridge design manual developed and updated

in-house

1/2

Page 14: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Improvement in specific practices and procedures (cont’d)

Forefront on crash tested bridge rails and transitions

All utility relocations must appear on plans Record of Design Report – evaluating

Consultants Use of VIRTIS Ratings as check of design

2/2

Page 15: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Opportunities for Improvement

Page 16: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Training & professional development/need for better communication

Need for Structural Engineer career path Training for Structural and Consultant

engineers Recognition / reward system Develop effective team environment Implement rotational assignments Succession Planning No incentive for PE license

Page 17: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Establish In-House bridge design

Track design hours / cost Consultant review section does not have

project authority Technician to maintain standard details and

CADD support In-house highway design capacity needs to be

developed More focus on bridge design effort

Page 18: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Clearly document roles & responsibilities

In some cases, engineers do not understand full scope of responsibilities

Districts challenging roles and responsibilities Consultants receive conflicting comments in

plan reviews Authority unclear

Page 19: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

QC/QA

Inconsistent QC practices QA procedures not clearly defined /

standardized Some reviews are redundant Can use bridge load rating as valid QC method

Page 20: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Tools required

Update software Substructure structural software Civil-3d locks computer Adobe WORD

Scanner Update computer hardware

Page 21: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Additional recommendations

Need for Hydraulics Program Review Applied research Use of electronic transfer of drawings and

plans/shop drawings Update Standard Specifications Maintenance Manual Capital improvement plan for preventive

maintenance

Page 22: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Response to ADA request regarding staffing levels following reorganization

Limits on hydraulic and geotechnical capabilities

Increased work load for in-house staff - identify where scoping will be conducted

Page 23: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Schedule for development of final report

Submit draft report to Review Team for comments (Nov 2011)

Comments incorporated (Jan 2012) Final report (Feb 2012)

Page 24: Structural Design Program Review Massachusetts Department of Transportation September 20-23, 2011.

Additional topics…..questions??