  • Date:Feb.29,2012Ref.No.:PPEP001Rev.00

    METHODSTATEMENTSTRINGINGOF30KVOVERHEADLINE

    FOR

    2X30MWCFPPINPOMALAAPT.ANTAM(PERSERO)Tbk,INDONESIA

    FEBRUARY2012PT.WASAMITRAENGINEERING

  • 1

    TABLE OF CONTENT

    Page

    1. Work Procedure and Job Safety Analysis .......................................................... 2

    1.1 Preparation ................................................................................................ 2

    1.2 Personal Protective Equipment ................................................................. 2

    1.3 Others. ....................................................................................................... 2

    2. Method Statement .............................................................................................. 2

    2.1 General Condition ...................................................................................... 2

    2.2 Preparation Work ............................................................................................ 2

    2.3 Procedure .................................................................................................. 3

    2.4 Others ........................................................................................................ 4

    3. Location of Work. ............................................................................................... 4

    4. Attachment

    a. Power Plan Layout

  • PT. WASA MITRA ENGINEERING POMALAA CFPP 2 X 30MW

    STRINGING OF 30KV OVERHEAD LINE

    2

    Method Statement for Installation of 30kV Conductor (Crossing with existing 20kV PLNs Overhead Line)

    1. Work Procedure and Job Safety Analysis. 1.1 Preparation

    1) Man Power.

    Safety Induction for workers by Safety Officer. Tool Box meeting before start of work.

    2) Necessary tools.

    All necessary electrical tools shall be passed inspection.

    3) Work Permit.

    Permit shall be obtained from PLN & local government.

    4) Installation of scaffolding.

    Install of scaffolding for work access and inspection before use.

    1.2 Personal Protective Equipment

    Appropriate equipment, e.g. helmet, safety shoes, goggle, masker, safety

    harness and other equipment, shall be given to related persons before

    commencing work.

    1.3 Others.

    1) Barricade, sign board and temporary protection.

    To be kept in container or job side and to be placed as required, refer to

    each activity.

    2) First aid box must be available on job site.

    2. Method Statement 2.1 General Condition

    Height of existing 20kV tower or pole is 13 meters, for new 30kV pole is 10

    meters. Therefore, installation of 30kV overhead line will be under 20kV

    existing PLNs transmission line.

    2.2 Preparation Work.

    1) Ensure all the necessary electrical and hand tools complete already.

    2) Ensure that storage of materials not obstruct to road traffic and public

    facilities.

  • PT. WASA MITRA ENGINEERING POMALAA CFPP 2 X 30MW

    STRINGING OF 30KV OVERHEAD LINE

    3

    3) Puller preparation

    - Placement of engine puller in place has been determined previously

    - Dig a hole for anchor engine

    4) Preparation tensioner

    - Placement of a tensioner in place has been determined previously

    - Transporting and Placing Conductor on location tensioner

    - Preparing Conductor on Drum Stand (drum jack)

    5) Installation of roller

    - Installation of roller for conductors at pole to be done

    6) Hold the rope

    - Connecting the rope puller and tensioned with polypropylene 12 mm

    7) Stringing Wire Rope 12 mm

    - Stringing wire rope 12 mm with polypropylene 12 mm which had

    been held earlier.

    2.3 Procedure.

    1) Before start the work, existing 20kV line must be shut down for a while.

    2) Install scaffolding at the existing 20kV pole span, which crossing with

    new 30kV line.

    3) After the existing 20kV transmission line shut down, ensure that no

    electrical power at existing conductor cable using grounding device or

    Jin Pole.

    4) Install the permanent safety nets under the 20kV transmission line

    which crossing with new 30kV line and install warning sign under 20kV

    line for safety guidance.

    5) After point 3 and 4 finish, 20kV line can be operated.

    6) During stringing work, the contractor shall take all necessary steps to

    insure proper temporary grounding of the cables and equipment.

    7) Ensure new pole at crossings with existing 20kV line shall be finish

    before stringing work.

    8) Install scaffolding at new pole.

    9) First Conductor phase Stringing

    - Held the rope polypropylene 12 mm

    - Pulling the wire rope 12 mm with polypropylene 12 mm which had

    been held earlier

    - Pull the conductor and polypropylene 12 mm with wire rope 12 mm

  • PT. WASA MITRA ENGINEERING POMALAA CFPP 2 X 30MW

    STRINGING OF 30KV OVERHEAD LINE

    4

    - Pulling the wire rope 12 mm with polypropylene 12 mm

    - Repeat the procedure until it is fixed three conductors

    10) Second Conductor phase Stringing

    - Repeat the first phase Stringing

    11) Third Conductor phase Stringing

    - Repeat the second phase Stringing

    12) Place the tension insulator sets

    - Place the tension insulator sets in tower

    - Conductor pieces one by one and "press" in the tension clamp

    conductor to be connected to the insulator sets.

    - Repeat the procedure to all the conductors

    2.4 Others

    1) Cleaning area after work finished.

    2) At the work area of cabling works shall be provide of security and safety

    person for control activity.

    3. Location of Work As per attached drawing

  • ATTACHMENT

  • PT Antam (Persero) Tbk, 2 x 30 MW CFPP In Pomalaa, Indonesia Inquiry Documents of M&E Erection Work Page 93 of 109

    Crossing withexisting 20kV PLNoverhead line

    New 30kVtransmission line

    20kV PLNoverhead line

    1234Crossing