STRATEGIC PLAN 2010 -2015 - mops.gov.gymops.gov.gy › ... › 2017 › 05 ›...
Transcript of STRATEGIC PLAN 2010 -2015 - mops.gov.gymops.gov.gy › ... › 2017 › 05 ›...
STRATEGIC PLAN
2010 -2015
‘Towards Renewal & Reconstruction”
SEPTEMBER, 2010
1
TABLE OF CONTENTS Page
Executive Summary 2
PART 1. INTRODUCTION 5
A. Background 5
B. Drivers for institutional transformation 9
i. Justice Sector Reform Strategy 9
ii. Modernization Initiatives in the Justice Sector. 9
iii. Stakeholders‘ Expectations. 9
iv. Past Studies: 2004 -2009 10
v. The Changing face of Crime 10
vi. Impact of Judicial Processes 11
PART 2. SITUATIONAL ANALYSIS: 12
I. The Criminal Justice Sector – Key Issues 12
II. Parole Board 13
III. The Citizens‘ Security Problem in Guyana 13
IV. GPS: Organizational Capacity Assessment: (i) Motivation; 14
V. (ii) Capacity; (iii) Environment Scan: PESTLE Analysis;
(iv) Performance
VI. SWOT 27
VII. Critical Strategic Issues 28
PART 3. THE STRATEGIC DIRECTION 29
I. Vision Statement 29
II. Statement of Values (operating Principles) 29
III. Vision of the Community (Offenders) 30
IV. GPS‘ Mission 30
PART 4. GOALS, OBJECTIVES, STRATEGIES, ACTIVITIES 30
I. Strategic Plan 2001 -2011: Accomplishments 30
II. GPS in 2020; Critical Success Factors 33
III. Goals, Objectives, Key Performance Indicators, Activities 34
(a) Strategic Goals 34
(b) The Strategic Framework for Organizational Renewal &
Reconstruction 35
PART 5. IMPLEMENTATION 41
I. Results Framework - 5 Year Action Plan: 2010 - 2015 41
II. Implementation Arrangements 48
III. Monitoring and Evaluation 50
IV. Stakeholder Analysis 51
V. Managing Change in the Guyana Prison Service 53
ADDENDUM: ORGANIZATIONAL ARRANGEMENTS FOR THE 60
IMPLEMENTATION OF THE SP – MOHA’S PROPOSAL
ABBREVIATIONS AND ACRONYMS 63
ANNEXES See [VOLUME 11]
A. Stakeholders‘ Consultation Report
B. Reporting Formats
C. Communication Management Plan
D. Organizational Profile Data
E. Best Practices Websites.
2
EXECUTIVE SUMMARY This Strategic Plan reflects the recommendations that were identified by the Minister and his Ministry,
during the period of review of the Draft Strategic Plan.
The Plan for the Guyana Prison Service was developed, in keeping with the TOR for this intervention - as
a highly participatory process involving a wide cross section of staff, the prisoners themselves, external
stakeholders including Visiting Committees, as well as key decision-makers from the MOHA. The views
of these stakeholders, together with conclusions developed from a review of relevant documents,
inclusive of the major studies undertaken over the past decade, provided an integrated body of
information that enabled a determination of the desired future profile of the GPS, and the means by which
this state could be achieved.
The environmental scan allowed for an organizational assessment of GPS in terms of its capacity,
motivation, and performance; while a corresponding PESTLE analysis enabled the identification of
environmental elements that are influencing factors on the institution‘s operations as well as projecting
possible future implications.
Flowing from the subsequent SWOT analysis, a number of internal strengths and weaknesses, external
opportunities and threats were identified and these highlighted the critical strategic issues that confront
the GPS and which should be addressed for enhanced organizational performance. These issues included:
(i) archaic, in some instances, dilapidated prison estates with inadequate security infrastructure; (ii)
overcrowding in prisons and its dysfunctional effects; (iii) absence of ‗after release‘ programmes for
inmates; (iv) poor working conditions/environment; inadequate staff capacity and inefficient use of
human resources; (v) inadequate organizational structure (especially at the administrative level); (vi)
inadequate Health and Safety practices; poor public image; (vii) inappropriate organization of the HR
function as well as dysfunctional policies and practices and finally,(viii) a largely untapped Prison
Enterprises‘ potential.
These concerns are consistent with those raised just over a decade ago when the first strategic plan was
developed, and, also with several studies / assessments undertaken thus far - the last report being the PSM
/ Nickram report of 2009. The situational analysis undertaken during the present strategic planning
exercise confirmed the congruency across assessments.
Accordingly, in support of the Vision and revised Mission articulated by GPS, the following strategic
goals were identified to be the pillars of the new Strategic Plan:-
3
Modernizing and Securing Prisons Estate Infrastructure.
Modernizing Penal Legislation and Restructuring GPS.
Enhancing Human Resource Management and Development In GPS.
Restructuring Prison Enterprises.
Strengthening inter-agency collaboration in the Criminal Justice System.
Promoting Successful Offender Re-Integration into Society.
Rebuilding Public Confidence and Trust.
Advancing Holistic Healthcare in Prisons.
The objectives and activities identified to give effect to these strategic goals emanate from the
recommendations listed in past reports; those from the present assessment, those from the Justice Reform
Strategy together with a choice of relevant ‗best practices‘ from around the world. These proposed
activities have been placed into a five-year implementation results-based matrix that includes measures of
achievement. An indicative costing for the implementation of the Plan is also included. This is in the sum
of one million, seven hundred and ninety thousand, and five hundred US dollars (US$1,790.500),
exclusive of the costs for the rehabilitation of buildings.
The Plan has made provision to fill the implementation gap which existed in the previous strategic plan
(2001 -2011), the result of which, at 2010, was little or no progression of the strategic goals that were
identified eleven years ago. The key to a successful organizational arrangement for the introduction of
reforms is the identification of dedicated (human and financial) resources to support the execution of the
intended improvements, specifically, the activities in the Strategic Plan. Structural arrangements,
including a new Unit, were originally recommended, but in the review of the Draft Strategic Plan, while
the principle of „dedicated resources” was accepted, the specific arrangements were not and the MOHA
has indicated an alternative structure to carry out this important task. This directive is included as an
Addendum to this report.
Finally, as requested in the TOR, a Communications Management Plan and guidelines for managing
change have been included as tools to support effective implementation. The onus is now on the GPS and
indeed the MOHA, as the parent organization, to demonstrate the political will and collective
commitment to support and indeed, reshape the Criminal Justice System. This can be made possible by
replicating a comprehensive approach to the „fourth pillar of the CJS‟ – the institutional strengthening of
GPS, within the framework of a context similar to that which was designed for the other CJS institutions
through the Citizens‟ Security and the Modernization of the Justice Administration System Programmes.
According to Nelson Mandela, speaking to the South African‘s prison staff in 1998…. ―The full
contribution, which our prisons can make toward a permanent reduction in the country‟s crime-rate,
lies also in the way in which they treat prisoners. We cannot emphasize enough the importance of both
4
professionalism and respect for human rights.” Such a position cannot be refuted, but this can only be
achieved if prison systems are able to provide the enabling environment which allows for the
strengthening of staff members‘ awareness and capacity. Simultaneously, a conducive physical
environment for staff and offenders is imperative, thereby engendering the desired behaviours that make
prisons safer and more productive.
This plan offers a definite start in this direction.
5
PART 1: INTRODUCTION
A. Background
(i) Brief Overview of the GPS
The Guyana Prison Service was established under the Prison Act # 26 of 1975. Chapter 11:01 is the
legislative basis for the GPS; establishing key parameters that include the articulation of the management
structure of the Prisons as well as the main powers and responsibilities of the key principals – the Director
of Prisons and the Deputy Director.
Although the functions of the GPS are not clearly adumbrated in the Act (as noted in the Report of the
Disciplined Forces (2004), such responsibilities are implied in Part 111: 217 – The purpose of training
and treatment of convicted prisoners shall be to establish in them the will to lead a good and useful
life on discharge, and to fit them to do so. Part 111: 281 Every prisoner shall be encouraged to
improve his standard of education and general knowledge and for this purpose the officer in charge
shall, so far as is practicable, arrange instructional classes. Special attention shall be paid to the
education of illiterate prisoners. Classes shall be arranged so that as little interference as possible
may be caused with working hours. From the foregoing, the GPS‘s main functions are perceived to rest
on two pillars – (a) Custodial and, (b) Corrections. The Act provides a sound framework within which the
GPS has functioned since 1975; however few revisions were made until 2009. The Prison (Amendment)
Bill 2009 has attempted to provide a legislative response to the most immediate of the numerous
challenges that have emerged over time. The Bill provides amendments to Clauses 2 to 12.
Notwithstanding these efforts, staff members were unanimous in desiring that a comprehensive review of
the Legislation should be undertaken that include issues of harmonization with similar legislation in the
region.
(ii) Governance
Since 1953, the GPS falls under the jurisdiction of the Minister of Home Affairs. Under the Act, the
Minister has powers that present an oversight framework for ensuring that the GPS functions effectively.
Accordingly, the Minister can (a) issue, as is/ becomes necessary, orders of executive nature; make rules
for the good management and governance of prison and prisoners and for carrying out the objects of the
Act. There is also legislative provision for both judicial and civilian oversight. The Minister is required
to appoint a Board of Visiting Justices as well as a Visiting Committee (civilians) for each prison.
Members may visit the prison at any time and may inspect any part of such prison, may inquire into and
examine the food, diet, clothing, treatment and conduct of prisoners; may hear complaints from prisoners;
may question any member of staff or prisoners and shall ascertain as far as possible whether the
provisions of the Act and / or the Prison Rules are being complied with. These bodies are expected to
submit periodic written reports to the Minister on their findings.
6
(iii) A Brief Profile of the Composition of the GPS
The GPS is comprised of a Headquarters situated in Georgetown and five Prison Locations. These are GT
Prisons; Mazaruni; New Amsterdam; Lusignan; Timehri; Mazaruni / Selby Hall. At the apex of the
structure, the Director of Prisons reports to the Minister of Home Affairs. A Deputy Director of Prisons
supports the Director in the Day –to-day functioning of the Service.
Each Prison Location is headed by an Officer-in-charge In keeping with the tradition of penitentiary
institutions; the GPS is a paramilitary organization. Most of its staff are prison officers engaged in
correctional, custodial and support functions. In recent years, The GOG has emphasized that correctional
functions should be given equal emphasis as custodial. In support of this policy, the Service has begun to
recruit professionals in the medical area as well as the welfare area, and efforts are being made to have
more staff involved in correctional activities. While such action is lauded, responsibilities are blurred and
ranks have complained of having to function in both correctional and custodial areas from time to time,
especially in the light of staff shortages in both the custodial and correctional functions. This is an issue
that needs an urgent review of the organizational structure of the GPS in order to clearly delineate the two
functions since unclear definition of roles and responsibilities can blur accountability.
(a) Prisoner Population
0
200
400
600
800
1000
1200
1400
Georget
own
Lusig
nan
N.A. M
ales
N.A. F
emal
es
Maz
aruni
Sible
y Hal
l
Tim
ehri
Authorised
1/1/2006
1/1/2007
1/1/2008
1/1/2009
1/1/2010
Actual Prison Population vs. Authorised Strength
As can be seen since 2006, in the GT Prisons, overcrowding is evident. An ex-Senior Superintendent of
Prisons indicated that overcrowding began to emerge in the 1970s. In the other prisons, except for
Mazaruni / Selby Hall, this pattern is replicated, in particular, from 2007 and steadily increasing. At
January 2010, prisoners‘ population across the five locations was in excess of its optimum capacity by
33%. Over the years under review, on average 56% of the population were remands. The ‗throughput‘ for
7
the system, i.e. the ratio between the number of prisoners admitted to the prisons and the number released
in any one year, and at least for Y 2009, could not be established since the relevant records were not in a
form that would readily present such information.
The majority of the inmates - 68 % - are within the age group 16 – 35. The range, broken down into three
sub divisions, that is, 18 – 23; 24 – 29; 30 - 35 reflects more or less the same percentages in every group,
namely 23%; 22% 23% respectively, confirming that more youth are involved in crime.
The MOHA is addressing the issue of overcrowding from several angles. These include (a) reviewing the
Parole Board with the aim of increasing the number of offenders released on parole; (b) increased
requests/ recommendations for Presidential Sentence reduction; (c) enforcing Segregation Policies and (d)
increased advocacy for a shift to greater use of alternative sentencing – community service,
(b) Staffing
The authorized1 staff establishment of the GPS is 502 positions. Actual staff at January 2010 was 389.
The table below presents the deployment of staff across the rank structure:
Table: Staff Establishment – Authorized vs. Actual according to Prison Location.
1 ―The post of APO is not created or recognized by the Act‟ and not part of the formal establishment or under the PSC. “They
cannot therefore independently perform the statutory duties of prison officers, but rather only an auxiliary role to Prison
Officers…: - Report of the Disciplined Forces Commission, May 2004; page 252.
POSITION / RANK A.E PHG
C
GT C
MAZ
C
N/A
C
LUS.
C
TRC C
Act. Str.
C
VAC.
Director of Prisons 01 1 1
Dep. Director of Prisons
01 1 1
Snr. Supt. Of Prisons 04 1 1 2 2
Supt. Of Prisons 05 1 1 1 1 1 1 4 2 +1
Asst. Supt. Of Prisons
12 1 6 1 1 1 2 12
Prison Consultant 01 1
Cadet Officer 03 1 1 2
Chief Prison Officer 21 3 5 1 2 6 1 17 1 3
Plant Maintenance Officer
01 1
Principal Prison Officer 11
36 3 15 7 5 1 3 34 2
Prison Trade Instructor
29 1 2 7 3 5 2 2 20 2 7
Master Baker 01 1
Principal Prison Officer 1
47 9 18 6 9 4 46 1
Launch Coxswain 01 1
Driver Mechanic 01 1
Prison Officer 236 13 50 24 30 23 14 154 82
Assistant Prison Officer
102 11 39 15 12 9 6 92 10
Total 502 43 3 143 2 60 69 42 27 384 5 113
8
The overall vacancy level is 23% and at the subordinate level (APOs and POs) 27%. 44.3% of the staff is
females with 55.7% males. 44% of staff is under age 35, 26% is between the ages 35 -44 years; while
30% is between the ages 45 – 60 years. 58% of staff has less than 10 years service; 32% has between 10 –
19 years of service and 10% has at least 20 years service. While there is still an appreciable level of
experience that reposes in the GPS, almost one third of the existing work force are likely to reach
retirement age between the next 5 to 10 years. There is therefore an urgent need to build capacity and plan
for succession, in particular at middle and senior management levels, in a systematic and comprehensive
manner.
Although the total number of prison officers may present the impression that there are adequate numbers
to serve the prison population, in effect there is a significant shortage of custodial staff at every location.
Staff therein are deployed to several functional areas but this is not formally reflected in any chart or other
staff deployment document. . The result is a prisoner / officer ratio that is unmanageable. One ready
example is the Georgetown Prisons where the total staff is 134 but only thirty-four (34) officers of this
number are available for custodial duties. Assuming a two shift system with equal numbers and a prison
population of one thousand, one hundred and fifteen (1,115), the officer to prisoner ratio is 1:65. If the
task force is included as part of the custodial grouping then this ratio becomes 1:39. These numbers
reveal, in real terms the supervision and security challenges that exist.
The Officer in Charge recommends 31 custodial staff per shift which, if combined with the task force,
would realize an officer to prisoner ratio of 1:27, still high when compared with best practice elsewhere
where more manageable numbers range between 1:6 to 1: 10.
On the short term, the Minister has indicated that later in 2010, there will be an aggressive movement
towards the recruitment of persons to fill the vacant positions in the establishment.
(iv) Public Perceptions of the GPS
Despite the changes over the decades, the physical structures and many of the operating modalities have
not seen a corresponding adjustment. The myriad of threats in the external environment has had its toll on
the institution in terms of resource availability and responsiveness to the changing dimensions of crime.
Accordingly, public perception of the Prison Service has steadily become unfavorable, with a
concentration on allegations of prisoner abuse. In 2000, the need for a strategic approach to the resolution
of the institution‘s several challenges was accepted and with the assistance of the British, a Strategic Plan
for the period - 2001 – 2011 was developed. This strategic framework needed to be complemented with a
second phase wherein an implementation strategy would have been charted. Unfortunately, this phase was
9
never undertaken. Never-the-less, the GPS has utilized the document as a frame of reference, and has
actually attempted the pursuit of several of the stated goals, albeit, not in a structured manner.
B. Drivers for Institutional Transformation of the GPS
(i) The Justice Sector Reform Strategy
The concern for citizen security and safety is high on the agenda of the Government. This is crucial for
the country‘s economic development which must be underpinned by the confidence of both local and
foreign investors to safely participate and indeed, usher in new investments. Against a spate of crime and
violence that commenced with the escape of five dangerous prisoners in 2004 and continued well into
2007, a key element of the Government‘s response was an extensive consultation surrounding the
Criminal Justice Sector – the result of which is a Justice Sector Reform Strategy (JSRS) for the period
2006 – 2010. This document has captured the views of hundreds of citizens across a wide range of
interested individuals and groups regarding the immediate and future challenges in an increasingly
dynamic global and local environment. The identified strategic goals and related initiatives unsurprisingly
take on a comprehensive stance encompassing all of the institutions in the system.
(ii) Modernization Initiatives in the Justice Sector
Since the JSRSt was approved by Cabinet, two loans were negotiated with the Inter American
Development Bank to commence its implementation. Together, they present a comprehensive approach to
the modernization of three elements of the Criminal Justice System. The Citizens Security Programme
seeks to facilitate the renewal of the Ministry of Home Affairs and the Guyana Police Force. The
Modernization of the Justice Administration Programme seeks to ensure the design and implementation
of reforms in the DPP, Ministry of Legal Affairs and the Courts. While the GPS was not included as a
part of these reforms, its importance, as aptly described by the Honorable Minister of Home Affairs, Mr.
Clement Rohee, as the ‗fourth frontier‘ of the CJS, is acknowledged by all. This acknowledgement was
demonstrated in the inclusion of the development of a Strategic Plan for the GPS as a cross- tranche
condition for the Policy Loan under the MJAS.
(iii) Stakeholders‟ Expectations
Various stakeholder groups continue to voice their concerns of the system and their views for positive
change. These groups range from human rights interests groups, to the media, to lawyers and to families
of offenders. During the situational analysis phase of this strategic planning process, consultation was
sought and realized with a number of key stakeholders identified by the GPS. The recommendations for
change have straddled a cross section of issues ranging from physical accommodation of the prisons to
access/ visitation practices for families. The details of these consultations are included in Annex 1 as they
coincide with the views that are well articulated in the JSRS.
10
(iv) Past Institutional Assessment Studies
As was referenced earlier, in 2004 the Report of the Disciplined Services Commission was tabled in
Parliament. The Commission was constituted by the National Assembly „to examine any natter relating
to the public welfare, public safety, public order, defense or security including the structure and
composition of the Disciplined Forces and make recommendations generally with a view to promoting
their greater efficiency‟. Since then, two other reports have emerged that refer to various aspects of the
functioning of the GPS. In the last semester of 2009, under the MJAs, a consultancy was commissioned to
Map the end-to-end processes of the Justice Institutions in Guyana and a Management Review of the
GPS was undertaken by the PSM and a report submitted and referred to as the Nickram Report. These
reports have all highlighted a number of important issues, with at least two of the four reports sharing
similar views on every issue discussed.
In summary, the issues identified for review in a strategic planning process are (i) archaic penal
legislation; autonomy and the GPS; (iii) organization structure and staff establishment; (iv) human
resource policies and practices including remuneration packages; (v) capacity issues including
deployment and utilization of human resources; (vi) archaic prison estates including security concerns;
(vii) prisoner welfare including rehabilitation programmes; (viii) use of technology; (ix) institutional
relations; (x) prison administration and (xii) judicial processes.
The situational analysis review undertaken in this process has also confirmed these areas as the critical
issues that confront the GPS. Of great importance is the fact that many of these issues were identified by
the members of the GPS during this participative strategic planning process. These recurring themes attest
to the fact that, while there are some attempts at improving / alleviating the effects of these issues, much
more can be achieved in a comprehensive strategic approach that speaks to the priorities indentified in the
Justice Sector Reform Strategy.
(v) The Changing Face of Crime
In addition to the foregoing, the changing face of crime has also added to the pressure for a
comprehensive approach by the GPS as it complements the efforts of the other Justice Institutions.
Offenders are now more sophisticated and influential as the narcotic trade continues to escalate along
with human trafficking involving women and children. Sexual offences are becoming more and more
prevalent and there is an escalating universal call for protection of the most vulnerable in all societies. At
the local level, the legislative response has implications for a higher rate of judicial decisions that may
well result in an increased complexity and number of offenders coming into the local penitentiary system.
Moreover, more youths are coming into the prisons for a number of offenses including those of violence
11
in one form or another. These youths are invariably, functionally illiterate, and in many instances, school
drop-outs from predominantly single parent families.
The present systems and structures, while laudable in view of the numerous constraints, are inadequate to
effectively respond to the rehabilitation needs of offenders, i.e. inculcating new mindsets and useful skills
as well as confidence to take their place in society in a lawful manner. With these elements in place, their
chances against re-offending will be increased. The realization of such a profile of the released offender
demand responses that speak in a more in-depth, and sustained programmatic approach to the educational,
emotional and psychological needs, in particular, of the more mentally challenged offenders. The
implications are therefore to build on the very useful programmes that exist, and into which, much effort
and thought have been applied even as the organizational structure is realigned and the capacities of all
staff - correctional and custodial- strengthened.
(vi) Impact of Judicial Processes
The efficiency of one part of the Criminal Justice System is paradoxically impacting negatively on the
functioning of the GPS. In recent years, with the increase in arrests for a wide range of felonies, more and
more cases are being brought before the Courts with requests for ‗no bail‘ in several instances. In many
instances, even if bail is set, offenders are in no position to post the required amount. As a result, for
example, the relative success that the GPF, DPP and also, the Courts have realized, regarding arrests and
convictions has seen the incarceration of more and more influential, controversial and prominent
prisoners.
Of concern to all, are the prolonged delays before matters are brought to court. Frequent postponements
of trial add to the frustration of all concerned. In recent times, the Courts have increasingly depicted the
tendency to impose fairly lengthy sentences for many convictions. The collective effect of these events
have contributed to the present high level of remand offenders and consequently to the progressive
overcrowded situation in the prisons, bring in its wake greater security challenges, temptations to staff
overworked and underpaid –in short, added challenges to a system that is already operating under
significant pressure. According to the Chang Report (2004) „Parliament creativity and wisdom should
not be stultified by executive or judicial omission‟. Many stakeholders opined that the Courts, as a
collective, must become more responsive to the realities of the day, in particular, the impact of judicial
decisions, displaying a willingness to shift towards international trends of alternative sentencing.
12
PART 11: SITUATIONAL ANALYSIS – MAIN FINDINGS
I. The Criminal Justice Sector – Key Issues
The Criminal Justice System comprises four important institutions whose activities collectively and
sequentially constitute a system that is expected to provide justice even as it underpins issues of citizen
safety and security. At the 10th Criminal Justice Conference, February 2005, South Africa, Pieter du
Rand of the Department of Justice and Constitutional Development (South Africa) posited ― … the justice
system is one of the most important pillars of our democracy. If it fails, our whole democracy is in
danger. The courts and their proper functioning are therefore crucial to our society.‖
This fundamental statement is applicable universally. As stated earlier, the effectiveness and efficiency of
the CJS is a strong as its weakest component. Failure or less than expected performance on the part of
any one of these institutions will mitigate the best efforts of the others. The indication therefore is for a
systemic approach to modernization and reforms if this important dimension of governance is to be
perceived as being effective. The system‘s value chain must be made operational with each institution‘s
performance adding value to the point of interface with the other.
A recent study by the Julian Laithe Consulting firm, procured under the MJAS project, assessed the
Justice Sector through the Mapping of the end-to-end Processes of Justice Institutions. A number of broad
issues were identified and presented in the final report (December, 2009). These are reproduced
hereunder:
‗the issues facing the Justice Sector in Guyana are similar to those in both Caribbean countries
and in other developing countries;
There are delays and bottlenecks throughout the Justice Sector;
There is a lack of joined-up partnerships working;
There is a culture that is hierarchical by nature and one content with the „status quo‟ rather than
one seeking constant improvement; and
Activities are not costed and performance management information is weak‟.
Other key observations in the report that are pertinent for consideration in the development of a new
Strategic Plan for the GPS are:
“There is little information sharing across and throughout the range of institutions. Few persons
(even among senior levels) were aware of the Justice Sector Reform Strategy or the progress of
its implementation as is being developed in the two major reform programmes in the Justice
Sector.
There is no interagency strategic planning process;
13
There is no single unit responsible for ICT in the Justice Sector. The lack of ICT support makes
the collection and sharing of information difficult, which in turn negatively impacts the decision-
making process; (some of these issues are being addressed in the Citizens‟ Security Program”).
These observations were confirmed in the environmental scan that was undertaken during this strategic
planning process. They contribute to the GPS‘s inability to respond effectively to its complex and
dynamic external environment. The GPS is a microcosm of the wider justice system; hence these broad
issues are present at the institutional level and impact on the overall performance of the institution. These
concerns will be addressed in later sections of this Plan.
II. PAROLE BOARD
The parole board is an advisory body to the Home Affairs Minister, to help him determine whether a
prisoner is eligible to be released on parole and what conditions should be attached to such release. It is a
system that is designed to allow rehabilitated prisoners a chance to serve part of their sentence in the
community. The Parole Board supervises the reintegration of offenders into the community.
In the Guyana Prison System there was an average of 670 convicted prisoners over the period 2005-2009;
of which a mere 3% of them applied for parole per year. Though 30 parole hearings are conducted on
average per year, only 10 of this number were recommended for parole. The actual numbers granted
parole represented 80% of those recommended. This is a mechanism that can contribute to a reduction in
the prison population, even as the concerns of victims and their families must remain critical factors that
must be considered as the effectiveness of the Parole Board is brought under review. As stated earlier, the
Ministry is addressing this issue.
III. The Citizens‟ Security Problem in Guyana
Reported crime escalated to an unprecedented high following the escape of five dangerous prisoners in
2002. A total of 21,842 crimes were reported between 2004 and 2008. 36 % of these
GENERAL PERFORMANCE INFORMATION: PAROLE BOARD
PERFORMANCE INDICATOR PERFORMANCE INDICATOR VALUES
FY2005 FY2006 FY2007 FY2008 FY2009
Parole petitions from the previous year 0 18 9 17 14
New parole petitions submitted 38 4 21 12 32
Number of parole hearings conducted 39 22 30 29 29
Number of parole recommended 10 8 3 18 11
Number of parole granted 9 8 2 14 8
Number of parole rejected/denied 8 0 0 4 5
Parole completed 12 7 5 6 3
Parolees being supervised and monitored 7 8 4 8 10
Parole petitions at the end of year 31 14 26 15 27
Parolees that withdrew their petitions and those that were released from prison 0 4 6 1 14
14
incidents – murder, manslaughter and rape were classified as serious crime. As a result of the subsequent
recapture and death of these convicted felons, and increased security measures since 2006 there has been
a steady decline in these statistics. The table below provides some useful insights into this social and
economic challenge.
Table: Types and Incidents of Crime: 2004 – 2008
Source: Criminal Investigations Department- Presented in MOLHS&SS: National Employment Report 2008.
IV. GPS: Organizational Capacity Assessment:
The internal analysis of the environmental scan – the organizational assessment – was undertaken using a
formal organizational assessment framework that has universal application. Specially developed for the
Inter American Development Bank by Professor Charles Lusthaus et al in 1995, this methodology was
introduced to a cadre of Government Officials in Guyana in 2000. In 2003, the methodology was used
extensively in the Design of the Public Sector Modernization Programme. In summary, the model posits
that organizational performance is a function of interplay of organizational motivation; organizational
capacity and the environment.
The findings emerging from the application of this model and the indicative conclusions are present
below.
(i) Motivation
Four factors are considered in this dimension – history, mission, culture and incentives - as collectively,
they influence the level of organizational motivation.
The GPS has historically been grouped with other military / paramilitary institutions and this may well
have enforced typical characteristics associated with this organizational form i.e. hierarchal, strict ‗chain
of command‘ observance embodied in the visible ‗command and obey‘ stance of its members. In addition,
the emergence of overcrowding and deteriorating conditions in prisons since 1991, the subsequent claims
of basic human rights infringement, the break-out of five dangerous prisoners in 2002 which led to years
of escalated violence related crime, have contributed to a strong negative image of the GPS.
Year Murder Man-
slaughter
Wounding
with Intent
Burglary
and
Breaking
Larceny Arson Rape Robbery Other Total
2004 131 8 123 2654 317 2 170 1336 170 4911
2005 142 8 160 2323 418 1 169 1564 169 4954
2006 163 10 129 1959 319 6 124 1623 124 4457
2007 115 1 101 1872 247 1 82 1236 82 3737
2008 158 6 75 1699 205 12 71 1486 71 3783
15
The traditional mission of the organization has reinforced the functions which are routinely carried out.
The extent to which this mission is known by staff, however, could not be determined.
From a survey of employees conducted across locations and ranks, the dominant culture in the GPS is
‗the hierarchy‘, typical of most military organizations and depicting the traditional "command and
control" model of organizations, where it is visible in standardized rules and procedures, control and
accountability and with clear authority for decision making reposed in leaders. While there also exists in
GPS, some subcultures that are less hierarchical, all staff in the sample indicated a preference for a new
culture that advocates shared values, beliefs and practices which emphasize issues of teamwork,
employee participation and consensus in work practices, relationships and behaviors.
Incentives within the GPS are limited, existing largely in Annual Awards Ceremonies where superior
performance at the individual level is rewarded. The more fundamental forms of incentives, such as
organizational and job autonomy, pay incentive schemes and simple recognition for a job well done, were
largely non-existent.
The history, mission, culture and incentive system of the GPS has had both positive and negative
influences on the institution. On the positive side, staff has always felt a sense of belonging in a
predictable environment and this has engendered a strong sense of institutional identity among, in
particular, the more senior officials of the institution. This has enabled the continuous effort towards the
upholding of the mandate of the institution and survival in the face of a sometimes hostile and critical
public. On the other hand, the same factors have contributed to a workforce that is largely resigned to the
operational reality, with little motivation, for many officers, especially at middle and subordinate levels to
be innovative, or at minimum, go beyond the ordinary. This has impacted negatively on the performance
of the institution, largely in its responsiveness to its service users.
(ii) Capacity
According to the Organizational Assessment Model, eight interrelated elements constitute the capacity of
an organization, affecting its performance. These are strategic leadership, organizational structure, human
resources, financial management, organizational infrastructure, program and service management, process
management and inter-organizational linkages. On the positive side, there is some degree of stability in
the upper grades of the GPS; the senior and middle level staff are committed to the organization as seen in
the fact that 42% of staff have between 10 to 20 years of service. This institutional ‗know-how‘
underpins the day-to-day institutional operations even as the citizenry is kept safe as prisoner escapees are
contained and minimal.
16
In addition, the GPS has developed a number of training programs for both staff and prisoners that is
enhancing capacities at both levels. Among the programmes deemed by the offenders themselves to be
values- changing are (a) Merundoi-Behavior Change proogramme through drama, Anger Management,
HIV Aids Awareness and Behavior Modification Program; remedial literacy and numeracy, CXC, music
and vocational training in the areas of tailoring, block-making, craft, carpentry, welding, catering and
farming. Offender training is constrained by ill equipped trade shops, inadequate space, and infrequency
of training courses, insufficient trade instructors and custodial staff which inhibits the release of offenders
to attend classes. Of even more importance, the existing policy does not permit the participation of
remands (although discretion is used sometimes based on declared interest). This latter policy does not
appear to be relevant given the reality of the extensive length of incarceration for many remand offenders.
These issues are all engaging the attention of the Minister and the Prison Administrators and some small
advancements have already been realized.
At the level of staff members, 34 courses are developed and administered by the Training, Welfare and
Corrections Division, including a Basic Recruit Training Program. Although this is not always possible,
generally, efforts are made to ensure that recruits are afforded some measure of orientation before being
deployed. Several staff members have expressed dissatisfaction regarding the training effort. Perceptions
range from statements insisting that training is insufficient, to claims of unclear selection criteria. In
support of these views, recommendations call for courses to be revamped to reflect the changing nature of
crime in order to increase the responsiveness and coping skills of relevant staff. A common reaction was
that the curricula for both offenders and officers should be revamped.
Prior to 2010, the utilization of resources approved for training in GPS was skewed towards officers. In
2010, at the instance of the Minister, for the first time, this budget was divided in a more equitable
manner to reflect training opportunities for both target groups.
The main areas of concern are (a) the inadequacy of the organization structure to support an equal focus
on the correctional aspect of the GPS‖ mandate. The organizational chart that was made available during
the assessment presented a ‗rank system‘ instead of a functional distribution with clear reporting
relationships; there was no distinction between custodial and correctional responsibilities, and
consequently, no visible career path for either stream. The chart also depicted gaps at the strategic apex.
(b) Staff capacity - just about 10% of staff are in receipt of education qualifications beyond a primary
education [i.e. associate degrees, undergraduate degrees and post graduate certification]; 17% of staff
possess CXC qualifications while just under three quarters of staff - 73% - have qualifications at the
level of primary school and vocational studies. While the latter may be sufficient for custodial
responsibilities, these statistics appear to suggest critical gaps might be existing at supervisory /
17
managerial levels as well as in the correctional area which is key to successful offender rehabilitation.
Data was unavailable to determine the scope of the academic gaps at the supervisory / management levels
but the indications are for increased formal academic exposure as well as management and other related
skills training (e,g. leadership; teambuilding; communications etc). This view was validated by key
informants during the internal assessment processes.
In the area of financial management, from the Auditor General‘s report over the period 2004 – 2008, a
number of recurring themes appear to indicate several weaknesses in the practice of the function. Specific
areas highlighted were stores and procurement management; accounting procedures and related recording
keeping; non- segregation of store keeping functions and inadequate inventory management of important
stocks such as fuel. Budgetary provisions have been inadequate over time despite increases in both
current and capital allocations over the past five years. Funds are insufficient to meet the annual operating
needs of the service, even on a break even basis. This has resulted in shortages of basic hygiene and
sanitary supplies to prisoners; reduction of the quantity of goods specified in supplier contracts, at the
point of transaction.
Infrastructure – prison estates. Generally, one key informant shared that the buildings across locations
reflect a harshly punitive atmosphere. This was confirmed on visits to locations during the assessment
with several cases verging on dilapidation, an unsurprising situation since no major rehabilitation has
been done to many of these buildings since the early 1900s.
In this critical area of rehabilitation, the MOHA, at the bequest of the GPS and supported by its own
oversight conclusions, has continuously mobilized resources during annual budget presentations in order
to effect the most critical repairs to buildings that have serious structural rehabilitation needs as a result
of their age. In addition, in 2010, a new block in the Georgetown Prisons is being erected.
Never=the=less, the need for increased activity, emanating from a more formal, comprehensive and
strategic approach, has been unanimously identified across the range of key informants.
Equipment and furnishings were equally archaic, trade/workshops small, cramped and largely inoperable;
no dining facilities exist at the Georgetown Prisons and offenders eat literally on their feet! In several
cases, basic furnishings for prisoners were very inadequate (a critical shortage of beds / mattresses etc.
results in several hammocks slung in the cells generating intense heat and further blocking light).
Automation and use of technology with inadequate electronic equipment (such as surveillance
cameras; electronic scanners etc), vital in supporting other security measures in the Locations were also
inadequate. Computer ‗know-how‟ was minimal, in relation to the total number of staff, and where it
18
existed, in almost every case this was at the basic level. With support from the Minister, the GPS has
developed a plan to address the technological gaps and these are now being considered at the policy level.
There is no formal HR structure in the GPS as a result of the absence of the requisite capacity. This
function is now centralized and administered / processed through a Board comprising MOHA staff, the
Head of TW&C and the Training Committee of the GPS. The Minister monitors the performance of this
body. Key informants within the Service were more or less unanimous that this practice has resulted in a
lengthy process for recruitment, elapsed periods of uncertainty as a result of blurred accountability. The
spin-off of this approach has seen a de-motivating impact on the entire GPS. Notwithstanding these
constraints, with the measures taken, some successes have been realized during 2009 -2010.
Appointments in some critical areas such as ‗welfare‘ have begun to emerge, but more of these skills are
needed
In addition, the GPS now has a Code of Ethics for its staff. Career management, however, is not properly
structured. Some attempt was made to deal with the issue of succession through the Cadet Scheme, but
other levels are not addressed. While there is also a Promotion Board, progression in the system is
sometimes blurred and staff claim to be unclear regarding the criteria that is sometimes applied in the
light of some supersession and undue delays. Indeed, the organization structure itself lends for some
ambiguity regarding career paths in areas requiring different skills set since the rank structure is
dominant. Some form of annual staff appraisal is in place but it was generally agreed that there is need for
improvement since the last appraisal was in 2008 and existing formats / instruments are being revised
internally with various models being examined.
There is no documented Occupational Health and Safety Policy in place nor are there any formal linkages
with the Occupational Health and Safety Division within the MOLHS&SS - a matter of great concern in
the light of the hazardous environment for both staff and offenders.
Program and service management
Planning is effected within the GPS, mainly at the onset of the Budget preparation period in August. This
is a joint exercise between the OCs and the Directorate of the GPS supported by the Finance Department.
Coherence between the annual work plans and the budget could not be assessed since the former
documents were not made available during the assessment. From key informants, formal evaluation
systems do not appear to be in place although some monitoring of the annual work plan‘s progress is
attempted at Monthly General Management Conferences. In addition, the Minister of Home Affairs
conducts weekly meetings with the Directorate and senior management with a view to resolving
bottlenecks to the advancement of planned programs. Formal systems to garner views from stakeholders
and to elicit feedback do not exist. Senior officers did not respond to short questionnaires that sought to
19
solicit their responses to issues of institutional performance. This may seem to indicate that practices may
not be comprehensively or formally institutionalized.
Process management
This factor was considered from four perspectives – problem-solving; decision-making; communications,
monitoring and evaluation. In the centralist dispensation that permeates this institution, these cross-
cutting functions are all discharged at the level of the General Management Conference as well as at the
MOHA. Key informants are of the opinion that although it was stated that OCs had a significant amount
of autonomy to deal with operational matters at their locations, the tendency was to have decisions
referred to the directorate. In addition it is clear that record systems are not as robust or up-to-date as they
should be since data required for this assessment had to be updated/ generated in some instances, and in
other instances were just not available. Moreover, there are no electronic databases that can readily
generate desired reports, or respond to operational queries. Comprehensive and timely information is
critical to sound problem-solving, decision-making, and monitoring and evaluating practices.
The general perception from across the range of persons interviewed was that communication in the GPS
is in need of enhancement. Most persons were unaware of the existence of the Strategic Plan that is
coming to an end, and in the case of those aware of its existence, they were unacquainted about the details
of its content.
Inter-organizational linkages
Chapter 11:01 identifies a number of agencies with whom the GPS must collaborate in order to satisfy its
mandate. Apart from the other institutions in the formal Criminal Justice System, and MOHA, key
agencies are the MOF, MOH, the MOE, the MLHSS&SS, in particular its Probation and Welfare
Services; MOA, MOAA, PSM and PSC. Collaboration is largely informal streaming from individual
connections. There are no formal relationships or mechanisms; hence there is an absence of deliberate,
ongoing and comprehensive engagements that would present a partnership approach to advancing the
aims of the GPS and the Criminal Justice System, as a whole.
Conclusion
Given the foregoing, while it is acknowledged that the GPS has still been able to maintain a relatively
safe prison environment, and has thereby contributed to the security of citizens, it is quite clear that
overall, the capacity of this institution is weak and in need of urgent institutional strengthening in order to
better position it to discharge its mandate in the criminal justice system.
20
(iii) Environment - PESTLE Analysis – Existing and Emerging Trends
These environmental trends were considered by a core of GPS staffers. The political, economic, socio-
cultural, legal and environmental dimensions were explored.
Among the several trends identified, those considered vital to the GPS and its future were - the present
policies of the government regarding the modernization of the justice sector; fiscal policies that are
engendering more revenue and better financial management at the macro level; slow economic growth
and private / external investment; continuing drug trafficking; increasing instances of abuse of children
and women.
Other trends include - significant number of students from all levels of the school system who have
dropped out from their programmes (although this number has started to decrease in 2007 over the 2005
figures, probably as a result of programmes directed to the attainment of related MDGs); perpetrators of
violent crime resorting to guns and being profiled as young men who are school drop-outs; a flurry of
legislation responding to high profile social ills such as child abuse, narcotics trafficking; juvenile
offenders etc; technological advances and more accessibility to the internet; increased training
opportunities in computer literacy .
These occurrences will have a direct impact on the GPS and its developmental plans for the future.
(v) Performance
This is reviewed from three dimensions, efficiency, effectiveness, relevance and financial viability.
(a) Efficiency
The aim is to determine whether outputs were achieved at the desired level and at the least costs. This was
difficult to measure since cost accounting is not practiced in the GPS and the required range of
information was not available. The analysis was therefore inconclusive since no one variable could be
isolated and attributed as the causal factor for the prevailing circumstances. One indicator that was of
particular interest was the cost to maintain a prisoner. The cost for this indicator was traced over the
period 2005 – 2009.
21
Figure : Prisoner Costs: 2005 – 2009
Cost per prisoner. (G$)
$0
$50,000
$100,000
$150,000
$200,000
$250,000
$300,000
$350,000
$400,000
$450,000
1/1
/20
05
1/1
/20
06
1/1
/20
07
1/1
/20
08
1/1
/20
09
Cost per prisoner. (G$)
Prisoner cost was calculated by dividing the Total Operating Cost (including Overheads) by the total
prisoner population for the relevant year. The statistics depict this cost increasing steadily from 2006. At
the end of 2009, the cost of per prisoner had moved from $G317, 953 to $G359, 301, a difference of $41,
348 or 12%. In fact, between 2008 and 2009 operating costs decreased by 7 %. This occurred as prisoner
population in 2009 decreased from 2008‘s totals by 5%. These figures should only be regarded as
indicative since from both observation and information from key informants including the prisoners
themselves, facilities as well as basic prisoners‘ needs are not adequately met.
(b) Effectiveness
Effectiveness is defined as the extent to which an organization is meeting its legislative mandate /
functional goals. The main goals of the GPS emerge from its two assumed functions; namely, (i) to ensure
that prison is safe, and that prisoners do not escape from custody; (ii) to retrain prisoners so that they can
live useful law-abiding lives after they leave the prison.
Keeping prisoners safe.
In 2009, approximately 23% of prisoners were ill enough to have to be taken to the hospital, be
hospitalized either at the infirmaries or at the GPHC. Although this number appears to be high, given the
constraints of severe overcrowding, especially at the GPHC, the conclusion can be made that the GPS
were able to contain serious illnesses somehow preventing major epidemics. Other possible measures that
can be used as measures of the effectiveness of programs in place to promote prisoner safety are number
of deaths based on illnesses contracted in the prisons in any one year; number of prisoners injured over
the past year; number of infractions; and the number of prisoners killed during infractions. During 2009, 9
Year Cost per
prisoner.
(G$)
1/1/2005 $317,953
1/1/2006 $304,601
1/1/2007 $308,008
1/1/2008 $388,224
1/1/2009 $359,301
22
prisoners died representing less than 1%; there were 90 cases of wounding as a result of infractions – an
average of 1 serious infraction every four days, which can be viewed as alarming given the possibilities of
these incidents escalating in view of the limited available custodial staff and even resulting into fatalities.
This level of conflict is however understandable in view of the serious overcrowding, especially at the GT
prison location.
Healthcare in Guyana‟s Prisons
The level of care that is legislatively mandated to be provided demands that at each prison, there should
be a resident GMO provided by the CMO, MOH. As a result of shortages of doctors nationally, the lack
of resident GMOs has been substituted by Medexes who are in turn supported by nurses. In emergencies,
prisoners are referred to the GHC. While this strategy has assisted in providing some level of full time
medical support, these personnel have suggested that there are operating with understaffing at 33% in the
case of Medexes and 60% in the case of nurses. The greatest shortage of nurses is at the GT location.
Since just over 51% of total prisoners are at GT Prisons, the Administration at GPS has treated this
location as the priority and with the cooperation of the CMO, a resident GMO is expected to be in place
in another month or two. In the last year or two, a Dental Clinic has become operational, as well as an
HIV/AIDS and Tuberculosis Clinic. Once a week mentally challenged offenders are able to meet with the
local psychologist. Given the numbers of such offenders, it is unlikely that the visits follow the
established standards within the constraints of time. While progress in the area of healthcare cannot be
denied, GPS still has a long way to go to meet international standards and ‗best practices‘.
Keeping citizens safe.
This objective can be measured by the number of escaped prisoners in any given period. Statistics were
examined over the period 2005 – 2009. On average prisoners breaking out was 0.8% - less than 1 %. In
this regard, the GPS has been very effective in containing prison break-outs, and by extension,
contributing to the safety and security of the citizenry, more so in the light of the critical problems of
overcrowding and staff shortages.
Retraining offenders for successful re-entry into society
As indicated earlier, several programmes are offered to offenders and staff in order to build overall
capacity for both groups. While training budgets have increased over the past five years the utilization of
funds have been skewed towards staff members. Despite the shift towards a more equitable distribution of
resources at the beginning of this year - 2010 - offenders believe, that training should be more systematic,
regular and programmed to better address their specific needs and interests.
23
One indicator of the success of rehabilitation programmes in the prison is the rate of recidivism, but this
in itself is subject to many other variables outside of the control of the GPS. Notwithstanding this reality,
in reviewing recidivism rates over the past five years, a steady increase is apparent. In fact within the time
frame, recidivism has increased by over 100%.
These trends suggest that the GPS needs to analyze profiles of recidivists as well as conducting a
comprehensive review of its rehabilitation programmes, developing an overall strategy aimed at
enhancing its contribution to a significant reduction of recidivism over the medium term. Although many
causal factors are outside its manageable control, a more proactive and comprehensive approach must
include structured partnerships within the wider justice system, key line ministries (e.g. MOE, MOHA,
MOLHS&SS), private sector as well as the community.
In summary, despite the several constraints, it can be said that the GPS has been partially effective in the
discharge of its responsibilities.
(c) Relevance
Relevance of the GPS‘ programs is assessed from a number of perspectives. These are the number of new
programmes over the last five years, changes of programs in relation to new trends and expressed
changing needs of service users; acceptance of programs and services by stakeholders; stakeholders‘
satisfaction of services provided and reputation of the GPS among its peers as well as the general public.
GPS has attempted to remain relevant by taking on board some new programmes for offenders that reflect
aspects of best practice in modern penitentiary systems. In addition, the TWG developed a proposal for
Sentence Management and in 2010, this has moved closer to implementation through the appointment by
the Minister of a Sentence Management Board. The general public perception and that of key informants /
stakeholders outside of the GPS, however, is a mixed one. Most stakeholder groups, even those more
Year Recidivists
1/1/2005 192
1/1/2006 246
1/1/2007 339
1/1/2008 364
1/1/2009 396
Number of Recidivists – 2005 -2009
0 50
100 150
200 250
300 350
400 450
1/1/2005 1/1/2006 1/1/2007 1/1/2008 1/1/2009
Recidivists
24
closely involved with the GPS, are unaware of the specific rehabilitation programmes that are offered and
therefore tend to judge the institution based on public opinion - this more often than not, from a negative
perspective. From others, including the offenders themselves, while it is acknowledged that behavior
change programmes can influence/ change values and behaviors, issues of access, regularity, continuity
and skills of training providers were cited as the shortfalls of the programmes.
(d) Financial Viability
The financial viability of the GPS is in question. During the five year period under review, on three
occasions, 2005, 2007 and 2008, actual expenditure exceeded budgeted by an average of 0.35%. For the
other two years, 2006 and 2009, the actual expenditure fell short of budgeted by an average of 1.83%. In
2009, actual expenditure increased over the 2005 figure by 62%.
With a largely unpredictable service user population (offenders) as sentencing continues with little
recognition of the overcrowding situation, it has become increasing difficult for the GPS to adequately
meet the indicative costs of servicing offenders in terms of basic needs requirements. Over the period
2005 -2009, funding has been made available under capital expenditure budgets, reflecting a 283%
increase by 2009. The budget line for Buildings presents a G$68 Million ‗hike‘ in 2009 over 2005,
reflecting an increase in allocation of 316%. This can well be indicative of the significant rehabilitation
costs given the age of these structures as well as the MOHA‘s attempt to correct deficiencies albeit with
limited resources. Yet, extensive rehabilitation remains to be done, including the seemingly insolvable
problem of the internal sewerage disposal that is a part of the wider solid waste disposal network in the
wards of Georgetown. This is a high risk health hazard which is exacerbated during the rainy season. This
situation is also in contravention of environmental standards. The cost effectiveness of continued
maintenance is therefore questionable, although it was reported during the end of this review that the
GWI is embarking upon a more comprehensive solution on the medium term.
In the area of financial / accounting processes, state audit reports indicate several weaknesses in record
keeping and observance of financial management / accounting standards and practices. From the
assessment, processes concerning PRISS revenue collection and accountability practices appear to be
blurred in terms of clearly defined responsibility and oversight roles between prison locations and prison
headquarters. In addition, operational systems across locations do not appear to be consistent. This is an
area that can benefit from a comprehensive review.
The organization‘s dependence on the Government’s subvention and its inability to exploit the
potential of its agriculture resources has placed the financial viability of the institution at risk.
Monitoring of its financial resources is done on a monthly basis at General Management Conference as
well as by the MOHA and the Ministry of Finance. Another spin-off from its dependence on Ministry
25
allocations is that significant action cannot be taken, in terms of quick decisions to deal with unplanned
events some of which may be classified as critical.
While the MOHA tries to respond as best as it could to emergency demands; its own ability is restricted
in terms of what can, in many instances, be the need to balance conflicting priorities from its other
agencies and deciding on what the priorities should be for submission, consideration and ultimately
decisions by the MOF.
Prison Enterprises
The Prison has the prospective to become self sufficient if the full potential of its various business
enterprises were to be realized. Recently, a Prison Enterprise Management Policy was developed/ and its
implementation has commenced. Agriculture is clearly the bedrock for self sufficiency but despite its
significant contribution to the Prisons‘ dietary expenses, there are several bottlenecks. These include the
inability to harness cash crops (vegetables), poultry and livestock as a result of insufficient staff to
supervise offenders on the farms. (Offenders themselves have complained of being idle for significant
parts of their day). Other key constraints revolve around access to adequate and timely working capital;
insufficient resources to acquire capital equipment necessary for larger scale farming. While a Strategic
Plan for this enterprise is in existence, this is not time bound. There is therefore no real pressure, at any
level, to execute activities in the absence of clear measurable targets. Recently, the Minister appointed an
Agriculture Board to provide oversight over this Enterprise. It is expected that the functioning of the
Board will benefit from some of the observations made in this report.
Other enterprises comprise furniture manufacturing; craft production, block-making and the acquisition of
contracts for various types of labour intensive jobs for the convicted offenders. In the case of the latter,
there are some contracts with a few organizations such as MCC; Food for the Poor; but much more can be
sourced if more custodial staff are recruited and retained. In this regard, the size of prisoner remission is
of some concern. This averages around G$300 – G$500 per day. Given the economic realities, these pay
levels should be examined within a comprehensive strategy to market and access more employment
opportunities for offenders.
Conclusion
It is acknowledged that given the realism of the context within which the institution operates,
performance cannot be perfect. In its determination to pursue its legislative mandate, an institution is
faced with the decision to make tradeoffs among the various elements of performance. However, this can
only be done in a context where good information is available for evaluating the choices and determining
the best tradeoff give the realism that must be confronted.
26
There was little evidence to suggest that a dedicated, systematic and comprehensive approach to the issue
of internal performance assessment was in place and this situation is compounded by the absence of
timely and comprehensive data to assess performance indicators. Although some indicators were
identified in the Annual Performance Statements demanded in the budgetary preparation processes, there
was no evidence that these indicators were tracked and used in the decision making processes.
While it was admitted that there are some staff who are less than professional and are involved in dubious
behaviors, the majority of staff in the GPS, from discussions and observations, appear to be committed
and execute a good job, under very difficult conditions - in an environment fraught with risk as well as the
long hours in any shift. The environmental scan revealed that most participants wanted to do a good job,
and desired to reverse the negative perceptions about the institution.
Many factors are beyond the manageable control of the GPS, but there are several adjustments to
processes, attitudes, policies that can be improved at little or no cost. This strategic plan provides the
opportunity for a renewed comprehensive approach to the task of organizational renewal. The
participatory approach undertaken in the strategic planning process that produced outputs which will
dictate the direction and content of this new Plan, should present a favorable environment for successful
implementation.
The next section of this document displays the SWOT Analysis that was undertaken by thirty-eight (38)
staffers from a cross section of the GPS.
27
V. Guyana Prison Service=: A SWOT Analysis
INTERNAL EXTERNAL Strengths
Notwithstanding the limited resources, the GPS is able to
successfully fulfill its‘ mandate.
GPS has a very experienced core of Senior Managers
who are able to share their working experiences with
junior staff in such a manner so as to allow the junior
ranks to readily grasp an appreciation of the job.
Employment of Welfare Officers who are tasked with
addressing the social and welfare concerns of inmates
Improving health care services; dental clinic, HIV
programme at the Georgetown Prison.
A sense of camaraderie and unity exist amongst staff
members.
A high level of commitment, loyalty, dedication and
purpose to the organization by staff in the face of all the
challenges that they encounter on the job, e.g.- long hours
of work, unfriendly working environment, limited
resources, yet remaining in the organization.
Opportunities for staff development exist within the
organization; academic upgrade, specialization.
A fair level of usage of security related technology;
cameras, scanners
Opportunities
For Government and other Agencies/Organizations to
establish technical and vocational training as well as
academic and job creation programmes to reduce the lure of
crime by vulnerable groups.
Recent legislation and policy statements from high –level
Government policy and decision makers to expand the
application of alternative sentencing by the courts.
Interest of religious bodies and NGOs as well as the
MOLH&SS for greater involvement of religious and non
governmental organization as well as the Ministry of
Human Services in after care/release programmes for
prisoners ; work opportunities, half way homes.
For improving crime prevention through the conduct of
public awareness programmes on the evils of crime.
For GPS to conduct a PR campaign highlighting the
positive contribution being made by the organiztion and to
refute the negative press.
For GPS to acquire appropriate monitoring and security
related technologies to address the greater influx of
prisoners,
Weaknesses
An outdated infrastructure that is in need of major
recapitalization.
Poor public image when compared with the that of the
other members of the disciplined services.
Failure to give due recognition upon retirement to those
who would have served the organization with distinction
for many years.
Blurred career path leading to the top of the organization.
Inexperience of staff, 58% of staff has less than 10 years
of service which may indicate that the organization lacks
key competencies at certain levels.
Positions within the organization not being filled in a
timely manner as evidenced by the 21% vacancy level.
A high employment rate for females (55%), in a
predominantly male setting; this may lead to reduced
effectiveness.
Poor working conditions; long hours of work, poor
condition of physical infrastructure, staff shortages,
inefficient use of human resources, reduced training
opportunities for staff if compared over the last decade
and lack of rewards for long and dedicated service to the
organization.
Potential for the spread of communicable diseases as a
result of overcrowding poses significant challenges to
maintaining a safe prison environment for inmates as well
as for staff.
Inability to effectively classify and segregate criminals
within the prison system because of overcrowding and
staffing issues.
Threats
Geographic Location of the GT Prisons: Absence of a
buffer zone around the perimeter of the prison compound
increases the security risk of external influences, presenting
a number of related challenges. The failure to comply with
the city by-laws regarding the height of buildings
constructed in the immediate vicinity of the prison poses
additional threats.
Drug trade leading to greater prison intake.
The high level of unemployment and poverty in the country
creates a fertile environment for the criminal enterprise.
The recent passing of new criminal legislation and its
implications of potentially increasing the prison population
as a result of a greater number of convictions.
The increased successful prosecution of criminals who are
very influential within the society; these individuals are
able to use their considerable power and influence within
and without the prison to create an unstable environment.
Inability to attract suitably qualified staff from a depleted
labour market.
Burgeoning unruly culture fostering dangerous prison
environment.
At the socio-cultural dimension, Proliferation of guns,
drugs and technological advancements poses new threats
with more violent and sophisticated crimes.
Poor perception of GPS staff by the public as a result of
negative publicity in the media.
28
(a) Critical Strategic Issues
Arising from the SWOT ANALYSIS, the critical strategic issues identified by GPS are presented below:
Insecure, archaic and somewhat dilapidated prison estate infrastructure.
Over crowding in prisons and its effects.
Absence of ‗after release‘ programmes for former inmates.
Poor working conditions/environment.
Inadequate staff capacity and inefficient use of human resources; (staff deployment).
Inadequate organization structure (key concerns being lack of clarity between the custodial and
the correctional functions as well as unclear career path for both aspects, especially at
administrative level).
Inadequate Health and Safety practices.
Poor Public Image.
Dysfunction in HR organization, policies and practices.
Potential of the Prison Enterprises largely untapped.
29
PART 111: THE STRATEGIC DIRECTION
The following Vision, Mission and Statement of Values were derived following a working session with
thirty- eight of GPS officers across ranks and locations:
a. VISION STATEMENT OF THE GUYANA PRISON SERVICE -Y 2020
Guyana Prison Service is a highly efficient correctional institution with modern technological facilities
and competent staff who empower and rehabilitate inmates through structured programmes thereby
contributing to reduced recidivism and increased public safety.
This vision has a time horizon of ten years although the GPS, conscious of its limitations and challenges,
has developed this 5 year plan as the first phase of this journey to excellence.
b. STATEMENT OF VALUES (OPERATING PRINCIPLES)
Loyalty, equity and commitment
We see these values as the bedrock to our behaviours at every level since they are critical to
high performance and retention of staff.
Efficiency
We are committed to ensuring optimum utilization of the resources entrusted in our
care.
Accountability
We are determined to hold every staff member accountable regardless of status or
rank.
Safety
We maintain a safe and secure environment for inmates and staff
Rehabilitation
We seek to provide effective training and retraining opportunities to offenders thus enabling
their successful reintegration into society
Integrity
We strive to inculcate high moral, ethical values and trustworthiness to offenders and staff as
well as to uphold and sustain the integrity and professional image of the Service.
Partnerships / collaboration – We aim to network with all members of the Criminal Justice
Sector and other agencies that are critical to the GPS successfully fulfilling its mandate and
contributing to that of the wider Criminal Justice System.
30
People –centered
The Guyana Prison Service endeavors to assist in the personal development and welfare of its
staff, thus enabling them to realize their highest possible potential and life goals.
c. VISION OF THE COMMUNITY SERVED (OFFENDERS)
Offenders who are empowered with changed mind-sets and skill to take their place as productive law
abiding citizens and successfully reintegrating into society through strong networks and community
business partnerships that are facilitated by the GPS.
In support of its articulated vision, the GPS has revised its Mission Statement to read as follows:
d. GPS’ MISSION STATEMENT
The Guyana Prison Service, as an integral part of the Criminal Justice System, utilizes
international standards and practices to provide a secure environment for staff and offenders.
Through these approaches, offenders are rehabilitated and reintegrated into society as law
abiding citizens, thus contributing to public safety, critical for national development.
PART IV. GOALS, OBJECTIVES, STRATEGIES, ACTIVITIES,
PERFORMANCE MEASURES
1. Strategic Plan 2001 -2011: Accomplishments
The current Strategic Plan was evaluated with the Director of the GPS. Essentially although the
Plan was accepted, this was not cascaded down throughout the institution. In addition, a second
phase was intended to develop an implementation / action plan. This was however, not
accomplished. Despite this omission, the GPS has explained that the Strategic Plan was used as a
frame of reference to inform its annual Capital Budget Estimates. The Assessment of the Plan‘s
Goals and activities are presented in the Table below:
31
(a) STATUS OF STRATEGIC PLAN 2001 -2011
GOAL ACTIVITIES PURSUED TO
REALIZE GOAL
STATUS
COMPLETE
D
ON-
GOING
NOT
ATTEMP
TED
COMMENTS
1. Review of
Prison Estate
(a) Review Prison Estates –
classify security status and
segregate / place prisoners
according to prison
classification.
X
More of an
‗ad hoc‘
approach;
responsive
to
immediate
needs
To be included in new strategic plan.
Some attempt has been made to categorize
prisoners; Lusignan for drug and first time
offenders, Timehri for pre release prisoners and
Mazaruni for long termed prisoners. There is still
a need to address the issue of overcrowding and
prisoners who display unusual behavior if
classification is going to be successfully
implemented.
(b) Review prison estate in
order to maximize resources. On-going
To be included in new strategic plan
( c) Identify and develop
information and security
technology to counter growing
sophistication of the criminal
environment.
Very
limited
progress.
To be included in new strategic plan
Scanners needed for Mazaruni and Lusignan
Prisons as well as a greater number of cameras at
the other locations.
2. Compilation
of Security and
Standards
Manual.
(a) Establish procedures and
standards in respect of the
administrative and operational
systems of the prisons.
X To be included in new strategic plan
(b) Establish specific
procedures in relation to the
treatment of specific categories
of prisoners.
X To be included in new strategic plan
3. Establishment
of Audit Systems
to Monitor
Implementation.
(a) To identify inspecting and
monitoring teams to determine
the extent of the
implementation of the Security
and Standard Manual.
X To be included in new strategic plan
4. Human
Resource
Development
and
Management.
(a) Recruitment of appropriate
and qualified staff to meet the
professional responsibilities of
the organization.
X
Two Welfare Officers have been employed and
four of five locations have a Medex assigned.
5 Registered nurses to be recruited.
To be included in new strategic plan
(b) Develop and implement
flexible contracting / recruiting
systems to satisfy the
professional responsibilities of
the organization
X
To be included in new strategic plan
Need to address the issue of a doctor being
stationed at the Prisons on a permanent basis
(c ) Review remuneration and
conditions of service to attract
and retain staff.
X
To be included in new strategic plan
32
GOAL
ACTIVITIES PURSUED TO
REALIZE GOAL
STATUS
COMPLET-
ED ON-GOING
NOT
ATTEMPT
ED
COMMENTS
(d) Develop and implement
intensive and specialized
training to satisfy the core
competencies gap in the GPS.
X To be included in new strategic plan
(d) To influence a more
favorable perception of the
organization‘s image. X
To be included in new strategic plan
Cultural presentations by prisoners and a more
visible role for the steel band.
5. Development
of a more
Constructive
Regime for
Prisoners.
(a) Re-organization and
Expansion of Prisoners‘
Retraining Programs. X
To be included in new strategic plan
Anger management programme introduced.
(b) Commercialize and Market
Prisoners‘ Labour, Skills and
Talents.
This is
being done
on a small
scale.
To be included in the new strategic plan
Low level of operation at present
(c ) To Improve health-care of
prisoners.
X To be included in the new strategic plan
Introduction of specialized services, HIV Clinic,
dental, chest and psychiatric clinics in place.
(d) Programs for prisoner
resettlement in communities as
responsible citizens. X To be included in the new strategic plan.
6. Advocate for
the
modernization of
Penal
Legislation.
(a) Review existing penal
legislation and advocate for its
modernization in keeping with
the rapidly changing penal
system.
Very
limited
progress in
this area.
To be included in the new strategic plan
Advocating for penal legislation reform is an on-
going exercise
7. Enhance
Active
Collaboration
with the wider
Criminal Justice
System.
(a) Participate actively in
periodic meetings with the
arms of the Criminal Justice
System.
X To be included in the new strategic plan
(b) Enhance collaboration with
Probation and Welfare.
X
To be included in the new strategic plan
Need to have a more formalized structure, although
there is a joint delivery in the Murandoi Training
for offenders (behavior change program).
( C) Advocacy for alternatives
to imprisonment
X
To be included in the new strategic plan
Advocacy for change needs to be done on a
continuous basis
(d) Address undue delay of
prisoners on remand and
awaiting trial.
X While this is out of manageable control of GPS,
some advocacy is undertaken.
33
II. The Guyana Prison Service in 2020: Critical Success Factors
The Critical Success Factors listed below represent the views of internal and external stakeholders as well
as the GPS itself. These are:
CRITICAL SUCCESS
FACTOR
CRITICAL SUCCESS FACTOR OUTCOME
1. Prison Estates 1. Modern, adequately furnished Prisons in safe locations with high level
technological enhancements and recreational facilities.
2. Visible Categorized and Segregated Offenders
3. Vibrant Prison Enterprises with Business Plans under implementation.
4. Prisoner Integrated Information System operational.
5. Employment Contracts for Prisoner External Workforce.
6. 70 % Reduction in Remand Prisoners.
7. Prisons operating as responsibility centers.
2. Legislative Framework
and Organization Structure
1. Modern organizational structure that reflects a clear distinction between the two
streams of responsibility – custodial and correctional. Clearly defined roles and
responsibilities enshrined in documented job descriptions and career paths.
2. Authentic staff establishment for each prison reflecting clear division of labor in
relation to the scope / volume of activity. (with 95% occupancy)
3. GPS - A truly semi-autonomous Agency with clear accountabilities and annual
targets and a formal Oversight Board.
4. Revised Legislative Framework.
3. GPS Staff 1.HR Strategy for all aspects of the function approved and implemented
2. Staffed HR Unit in GPS in operation.
3. Comprehensive Staff Development plan approved and implemented
4. Modern Training Facilities
5. Twinning Arrangements with other Penitentiary Institutions.
5. Performance Appraisal System in Place
6. Incentives Scheme in place
7. 100% staff compliance with Code of Ethics.
7. Updated Library.
8. Public Relations Strategy implemented.
4. Rehabilitation
Programmes
1. A Rehabilitation Strategy; Curricula reflecting Behavior Change Program as
well as Technical Vocational Training reflective of offender‘s needs.
2. Sentence Management Plans, Rehabilitation Plan in place for every inmate.
.3. Modern, well equipped, functioning Trade Shops
5. Partnerships For
Integrated and Enhanced
CJS performance and
Offender Reintegration
1. Functioning Network of NGOs, Private Sector and selected Government
Agencies (e.g. MOLHS&SS) for reintegration.
2. Re-Integration Policy approved
3. MOUs with Key Stakeholders in operation for training, research, problem-
solving; advocacy.
4. Statutory Round Table comprising a Network of CJS institutions meeting
quarterly.
6. Financial Viability 1. Financial Management Flexibilities including a revolving revenue Fund.
2. Independent Internal Audit Unit reporting directly to the Minister and the Board.
3 Functioning PRISS in place.
4. Computerized Accounting System compatible with IFMAS.
34
111. Goals , Objectivities, Strategies, Activities, Key Performance Indicators
The Strategic Direction, the Existing State of the GPS, the Critical Success Factors and the status of the
previous Strategic Plan have provided a ready basis for the identification of the Strategic Goals that would
began the journey towards the future that GPS has envisaged for itself. Although the Vision projects a 10
year horizon, this plan speaks to the first five years of that vision. These goals provide the building blocks
for the transformation of the GPS.
(a) Strategic Goals
1. Modernizing and Securing Prisons Estate Infrastructure.
2. Modernizing Penal Legislation and Restructuring GPS.
3. Enhancing Human Resource Management and Development In GPS
4. Restructuring Prison Enterprises.
5. Strengthening inter-agency collaboration in the Criminal Justice System.
6. Promoting Successful Offender Re-Integration into Society.
7. Rebuilding Public Confidence and Trust.
8. Advancing Holistic Healthcare in Prisons.
These strategic goals will form the pillars upon which the Plan will be developed. For each Strategic
Goal, objective (s) will be identified with the corresponding performance measures and the activities
necessary to achieve these objectives. These will be closely aligned to the critical success outcomes in the
preceding section. In addition, the activities which are still valid and not fully implemented from the
previous strategic plan together with the proposals from reports from the period 2004 to 2009 that are
relevant to the present situational needs, as well as those from the Justice Reform Strategy will all be
considered for possible inclusion.
35
(b) The Strategic Framework for Organizational Renewal and Reconstruction
GOALS OBJECTIVES STRATEGY ACTIVITIES PERFORMANCE MEASURES
1. Modernize and
make secure Prison
Estate Infrastructure.
1a. To improve at least 60% of prisons
by the end of 2015 thereby promoting
the well being and safety of 100% of
staff and offenders.
Rationalize, rehabilitate
and secure existing
prison facilities.
1. Develop a Strategic Rehabilitation Prison Estates Plan.
2. Conduct a needs assessment of furnishings and security and
communication equipment for prisons, based on futuristic
projections and changing challenges. Include CCTV
Surveillance with on and off site monitoring.
3. Develop / Update Prison Classification, Segregation and
Security Strategy, protocols, standards, manuals and Action
Plan (inclusive of drug offenders and those mentally
challenged) together with the rationalization of each prison
facility to optimize its potential and usage.
4.
Number of offenders easily
identifiable according to their
classification.
Number of violent infractions /deaths
No. of escapees.
Number of staff injured during
infractions in prison
Incidents of cross-infection
No. of offenders found with weapons.
1b. To enhance strategic evidence-
based decision-making in the GPS by
the end of 2011.
Use of ICTs to underpin
information systems
1. Develop and implement a comprehensive management
information system for the GPS with provision for
connectivity to other IT systems in the CJS.
2. Procure computers and other electronic equipment to support
this transformation.
3. Establish an MIS Unit and train all staff in order to maximize
and fully utilize the system.
Availability of cost per prisoner;
health cost per prisoner; training cost
per prisoner;
No. of decisions that emerge from
MIS information.
Number of statistical reports
generated from MIS six months post
establishment.
2. Modernize Penal
Legislation and
Restructure the GPS.
2a. To harmonize and align the
legislative framework for the GPS
with local, regional and international
conventions and agreements by the
end of 2011.
Comprehensive revision
and modernization of
existing penal legislation.
1. Conduct a comprehensive revision of Chapter 11:01,
harmonizing it with existing / new legislation in the sector
and aligning with international best practices. Consider the
Revised Legislation already enacted in 2009 and 2010.
2. Develop regulations where necessary.
3. Orient / train all GPS staff regarding the amended governing
legislation.
Number of judicial decisions that are
in conflict with Chap.11:01
Number of staff members unaware of
Amendments 6 months after
enactment.
2b. To rationalize & modernize the
structure of the GPS no later than the
end of 2011 to realize its legislative
mandate.
Comprehensive re-
engineering/
restructuring of the GPS.
1. Comprehensive restructuring of the GPS (with
implementation strategy) in keeping with modern trends in
penitentiary administration as well as the peculiarities of the
local context and its demands and the need for flexibilities
balanced with strong yet ‗hands-off‘ MOHA oversight
structures (including a Prisons Inspectorate) and mechanisms.
2. Determine the best mix of competencies required and
establish staff establishment requirements & Job
Descriptions. Include a clear career path.
Number of professional and specialist
staff recruited for related new job
positions in GPS.
Re-offending rates within three years
after release.
No of offenders who have undertaken
behavioral programmes akin to their
offense.
2 c. To contribute to organizational
efficiency by the end of 2011 through
enhanced work processes
Reengineering of core
work processes.
1. Review, improve and automate, where practical,
financial, accounting and administrative processes.
2. Train staff in new work processes.
Number of audit queries ;Number of
financial reports submitted on time to
MOF; Average administrative
transaction processing time.
3. Enhance Human
Resource Management
and Development in
GPS.
3a. To increase by the first semester
of 2012, the GPS‟s capacity to attract
and retain quality staff to support its
operations.
Demonstrate that
Human Resources are the
most precious of
resources in the GPS.
1. Establish a Human Resource Management Unit within the
GPS with clearly documented protocols for users and
providers yet compatible with and complementary to the
overriding HR systems within the Public Sector. Relationship
with the MOHA should reflect a desired level of flexibilities.
Average Time taken to fill vacancies.
Average promotion waiting period.
Number of persons trained from
every functional unit; Average Time
to resolve disciplinary matters. Rate
of absenteeism; Staff turnover rate.
36
GOALS OBJECTIVES STRATEGY ACTIVITIES PERFORMANCE MEASURES
2. Train staff in HR methodologies and development; operating
manuals, performance indicators and standards for all
processes.
3. Design & Implement a recruitment strategy to Strengthen
Costodian Staff numbers. (career path in place; must have SC
powers) and to fill vacancies across the Board.
No. of HR related complaints
No of additional staff recruited in
custodial department.
4. Develop an HR strategy that addresses all aspects of the
function including recruitment and selection, training and
development, performance appraisal, promotion, discipline,
compensation, incentives and rewards; welfare, occupational
safety and health, staff deployment.
5. Develop and support the implementation of a Performance
Management System for the GPS. Performance Appraisal
System must include evaluation of management.
Number of accidents among staff on
the job.
Number of staff working in excess of
an 8 hour shift.
Annual Number of divisional targets
met.
3b. To present to the labour market by
the end of 2014, GPS as an attractive
and rewarding career option.
Develop and implement
an HR ethic that will
motivate and attract
qualified persons.
1. Review and develop proposal for enhanced conditions of
service yet within the framework of other institutions in the
justice system on the medium term but with provision for
future enhancements associated with the financial
performance of prison enterprises.
2. Develop protocols for all HR processes.
3. Develop flexible contracting/recruiting systems to
satisfy the professional responsibilities of the prison
service.
4. Establish a Planning and Research Unit to include
strategic planning, manpower forecasting and planning. 5. Develop a marketing Strategy to ‗sell‘ the new GPS to
graduating students from secondary and tertiary institutions.
6. Conduct a feasibility Study into the issue of demilitarization
of the Service.
Number of new professional staff
recruited.
Number of resignations and years of
service of these leavers.
Number of staff on contract.
Number of new qualified employees
taking up their first appointments in
the GPS.
3c. To consolidate the human capital
within the GPS commencing no later
than the middle of 2013.
Comprehensive demand
driven training in the
GPS.
7. Upgrade the existing Training Policy in the light of the
renewed thrust of the GPS.
8. Conduct a needs assessment, review existing training
program and develop and implement a comprehensive Staff
Development Programme for staff at all levels in the Prison
Service. Emphasis on Middle management training by
establishing core competencies
9. Develop /Review/ Upgrade and implement a coaching and
mentoring system for the GPS.
10. Develop a Library to support staff development.
Number of training days per year for
each staff member.
Number of vacancies in core
functional areas.
% of persons trained in specialist and
managerial areas.
Cost of training per staff member.
4. Restructuring
Prison Enterprises and
strengthen financial
management systems..
To ensure the financial viability of the
GPS by increasing enterprise
revenues in at least 3 Pilot
enterprises by 70 % over the 2009
baseline by 2015.
Harness the potential of
each enterprise,
prioritize; mobilize
funding to support
sustainable
implementation and
strengthening accounting
systems and processes.
1. Conduct feasibility Studies to determine the priorities in a
phased approach towards the resuscitation of these
enterprises.
2. Development Business Plans and mobilize required
resources, exploring possible private sector partnerships/
sponsorships.
3. Establish a small dedicated unit to manage these enterprises.
4. Design and implement a cost accounting system for all
Number of approved projects for
prison enterprises.
Number of private sector sponsorship
/ partnerships.
% increase in revenues from pilot
enterprises. [Baseline year 2010].
37
GOALS OBJECTIVES STRATEGY ACTIVITIES PERFORMANCE MEASURES
enterprises including PRISS.
5. Restructure the PRIS including the Remission Policy for
convicted prisoners, putting in place transparent processes
and oversight mechanisms.
% increase in annual earnings per
prisoner.{baseline year 2010}.
.
.
6. Strengthen the Internal Audit Unit that reports directly to the
PS, MOHA/ Minister with appropriate training.
7. Develop a Strategy to enable the GPS to be more self
financing, reducing Government Subvention on the long
term.
8. Develop an M&E Framework for internal use.
Number of negative State Audit
queries.
Increase in annual revenue earnings
per year.[baseline year 2010].
Number of Reported incidents of
irregularities.
5 Strengthening
inter-agency
collaboration in
the Criminal
Justice System.
[For
Improvements In
Judicial
Processes].
To reduce the number of remand
prisoners by 80% by the end of 2013,
thereby eliminating the chronic
overcrowding.
Formalized statutory
interactions with the
institutions of the
Criminal Justice System
and other ancillary
agencies such as the
Probation Service.
Statutory Round Table comprising a Network of CJS institutions
to identify and pursue joint developmental initiatives in the
judicial System established and functioning
Number of MOUs / Letters of
Agreement in place between GPS and
Stakeholder Agencies.
Number of Justice issues resolved 1
year after the formation of CJS Round
Table Network RECOMMENDED AREAS TO REDUCE PRESENT AND
POTENTIAL REMANDS:
Advocate for the implementation of the existing alternative
sentencing strategy – community Service.. Maintain surveillance
on its implementation.
Civic awareness and education programmes to promote societal
acceptance on new sentencing strategy.
Juvenile Liaison/ Community Program (in GPF) for ‗at risk’
youth (13 – 18) Barbados model proposal.
A policy and programme of community mediation, to settle
domestic conflicts involving minor crime proposed.
Programme of shared research and training at the strategic level
developed and implemented.
Protocols on legal and security movements for prisoners on
remand.; Requirements for Prisoner Movements for Court
Appointments.
Policy on Coercive Control of Prisoners – Restraining Devices
and isolation.
Number of offenders served with
alternative sentences.
Number of petty crimes / minor
domestic conflicts resolved through
community mediation.
Number of ‗at risk‘ youth involved in
Juvenile non-incarceration
programmes.
% reduction in remands at GT prison
(baseline Y2010)
Number of alternative sentences one
year after visits by Justices.
6. Promoting
Successful
Offender Re-
Integration into
Society.
To contribute to the reduction of
recidivism by 50% by the end of 2015.
More aggressive
rehabilitation programs.
1. Conduct a formal comprehensive audit of offenders who
have at least a minimum of 1 year remaining on their
sentences as well as for remand prisoners to determine
retraining and rehabilitation needs. (The results can be used
to update existing sentence management plans).
2. Revisit existing curricula and combine into a comprehensive
Rehabilitation Strategy that reflects ‗best practice‘ around
the globe and is inclusive of both the remand and convicted .
3. Collaborate closely with the MOE to ensure that training
offered is replicated from / aligned with existing Education
curricula to address accreditation concerns and to receive
MOE certification endorsement on completion of programs.
Number of offenders- convicted and
remands - graduating with
certification accredited / endorsed by
MOE.
Number of facilitators from the
formal education system.
Number of offender complaints
regarding involuntary incompletion of
approved courses.
38
GOALS OBJECTIVES STRATEGY ACTIVITIES PERFORMANCE MEASURES
4. Enter MOU arrangements with MOE and NGOs to secure
assistance of state institutions and NGOs to provide
instructors and teachers on a periodic basis. 5. Develop protocols to ensure offender release to participate
fully in selected and approved rehabilitation interventions,
considering issues of transfer etc.
6. Develop protocol to ensure collaboration with MOE in the
selection of Trainers, instructors for delivery of academic and
technical vocational training and the delivery of Distance
Education of Prisoners thru; ICTs.
7. Post Discharge Preparation:
8. Marketing Prisoners‘ labour.
9. Establishing Protocols relating to:
(a) Management Provident Fund – including Access by released
prisoners.
(b) Develop a Financing Model based on Services provided to
Prisoners.
10. Review operating protocols of the Parole Board with a view
to increasing the number of paroled offenders ( measure to
reduce overcrowding).
11. Develop a proposal to implement the recommendation from
the TWC and JLC report to implement a Transitional
correctional facility (a ‗half- way house‘) as part of the
preparatory efforts for the pre-release of prisoners.
12. Develop a constructive regime of activities geared to
beneficially occupy prisoners‘ time at every facility.
13. Design and implement After-release support protocols in
collaboration with the Probation Service (MOLHS&SS);
NGOs, Private Sector and other selected Government
Agencies to foster better reintegration.
14. Develop Protocols (including criteria) for the
Reduction of Prisoners‘ Sentences.
Success rate of candidates (offenders
and staff) undertaking CXC and GTI
examinations.
Number of offenders registered/
transferred to Transitional
correctional facilities.
No of hours of ‗idle‘ time per
offender (convicted and remand).
7. Rebuilding
Public
Confidence and
Trust.
7(a) To seek to reverse the public‟s
perception of the GPS by 60 % by the
end of 2015 over the base line survey
in 2010 to officially polled public
opinion.
Comprehensive Public
Relations campaign.
1. Develop an Implementation Strategy to establish the proposed Public Relations Unit and to have it functioning inclusive of a PR strategy).
2. Conduct baseline surveys to determine the scope and depth of public perceptions.
3. Establish a Network of Stakeholders – fostering collaboration at this wider level. (establish operating protocol, e.g. GPS to provide periodic updates on its programmes and initiatives and to solicit their perceptions, recommendations to enhance the image of the GPS)/
% Reduction of negative perceptions
at polled surveys post public relations
campaign.
39
GOALS OBJECTIVES STRATEGY ACTIVITIES PERFORMANCE MEASURES
(7b) 70% reduction by 2015 of
negative media reports.
Developing and
enforcing a ‗zero‘
tolerance for
unprofessional and
unethical behavior by
prison officers at every
level.
1. Develop and implement a Quality Management System to
support a culture of professionalism, quality service and
integrity.
2. Revise Disciplinary Code including corresponding protocols
to reflect international standards, to enforce compliance with
the existing Code of Ethics and to enable speedy redress of
unethical behavior.
3. Comparative review of media reports over a three year period
– 2012 -14.
Number of positive stories in the
media regarding the GPS.
8. Promoting
Holistic
Healthcare in
Prisons.
(a)To safeguard the physical,
psychological, emotional & and
spiritual well being of Staff &
Offenders.
Adopting a
comprehensive approach
to health & well-being in
GPS.
1. Holistic Healthcare Strategy with Action Plan implemented.
2. Staff exposed to awareness sessions
3. Initial program of initiatives funded.
4. Occupational Safety & Health Policy and Action Plan
approved & implemented.
70% Reduction in number of allegations of physical abuse by staff. Reduction in work place accidents by 60% over baseline year (Y2010).
40
PART V. IMPLEMENTATION
1. RESULTS FRAMEWORK: 5 YEAR ACTION PLAN
2010 – 2015
.
41
5 Year Action Plan – Results Framework with Indicative Costs and Responsibilities
KEY PARAMETERS BENCHMARKS RESPONSIBILITY INDICATIVE COST (US$)
Base Year (2010)
Year 1 (2011) Year 2 (2112) Year 3 (2013) Year 4 (2014) Year 5 (2015)
Mission Base Target Target level The Guyana Prison Service as an integral part of the
Criminal Justice Sector provides Offenders and Staff with a
safe environment in confirmation with internationally
accepted standards and practices.
These approaches facilitate Offenders rehabilitation and
reintegration as law abiding citizens thus contributing to
public safety, critical to national development.
SP Approved by Cabinet Sponsors for the Plan identified.
Technical
Assistance for the
Implementation of
the Strategic Plan
mobilized and
Agreements signed.
By the end of this Strategic Plan’s execution. 70% towards this Vision
Guyana Prison Service is a highly efficient correctional institution
with modern technological facilities and competent staff who
empower and rehabilitate inmates through structured programmes
thereby contributing to reduced recidivism and increased public
safety.
Director Of Prisons
$1,755,550. (includes 10% contingencies) Refurbishing of 3 prisons(estimate) ($3,000,000.)
Goal 1: Prison Estate Infrastructure Modernized and made
Secure.
Obj.1: Offenders and staff well-being and safety improved
through rationalization and rehabilitation of prison
infrastructure.
60% reduction in
violent infractions in all
Prisons
Activities:1.Prison Classification, Segregation and
Security Strategy, protocols, standards, manuals and
Action Plan approved.
2.Prison facilities rationalized to optimize potential and
usage.
Strategy & Action Plan [Firm] approved by cabinet. 30 % implemented 50 % implemented 60 0% implemented
70% implemented in 5
prisons.
Minister, MOHA;
GMC
(consultancy support
- regional)
$25,000
Strategic Rehabilitation Prison Estates(inclusive of the
refurbishing of Trade shops) Plan developed.
For this Phase(2011-2015) 3 Prison Locations () 100% rehabilitated]
Proposal approved by Minister MOHA.
Master Plan completed and approved.(firm) 50 % of Trade Shops
refurbished
70% of Trade Shops
refurbished and in
operation.
Rehabilitation of 2
Prison Locations 100%
Completed.
3 Prison Locations: 100%
rehabilitation completed
(inclusive of 100% of
Trade shops refurbished).
Minister ,MOHA;
GMC (consultancy
support- local
engineering firm)
$200,000.
$3,000,000
Needs assessment of furnishings and security and
communication equipment for prisons completed. 100%= 3 Prisons
DOP
(consultancy support
- local)
10,000
Furnishings for 3 prisons and security equipment for 5
prisons secured and installed. 20% of Security equipment installed for 5 prisons.
Security equip: 20%; furnishing: 30%
Security equip: 20%; furnishing: 30%
Security equip: 10%; furnishing:
30% of furnishings; 40% security equipment in storage.
DOP
300,000
Obj. 2. Strategic evidence-based decision-making in the
GPS strengthened
Comprehensive MIS (IT) system designed and installed
(inclusive of hardware, software; provision for WAN,
LAN; wireless connectivity; Broadband Internet}
MIS System designed ; Offenders’ database completed IT consultancy firm]
100% Equipment procured & 100% system in Place- 30% staff using system
70% of staff using the system.
100% staff understand and can use the system
70 % increase in the quantity and quality of prisoner data. Available 50 % Increase in number of statistical reports
DOP
(consultancy support
- firm)
400,000
MIS Unit established and functioning with trained staff.
Creation of MIS Unit approved for 2012 Budget.
100% MIS Staff trained. Unit in place, functioning.
Minister; DOP; GMC_GPS
Counterpart
Funds
Goal 2: Penal Legislation modernized and restructured
2a. The legislative framework for the GPS with local,
regional and international conventions and agreements
harmonized and aligned by the end of 2011.
100 % reduction in judicial decisions in conflict with Chap.11:01
42
KEY PARAMETERS BENCHMARKS RESPONSIBILITY INDICATIVE COST Base Year
(2010) Year 1 (2011) Year 2 (2012) Year 3 (2013) Year 4 (2014) Year 5 (2015)
Comprehensive revision of Chapter 11:01completed and
enacted by Parliament (including regulations, where
necessary).
100% (Individual
Consultant) Minister; DOP (local consultancy support)
$10,000.
All GPS staff oriented/ trained regarding the amended
governing legislation harmonized aligned.
) 100% (Consultant
DOP (MOLA support)
$1,500
2b. GPS structure modernized and strengthened
GPS’s restructured with new functional areas, new organization chart and Job descriptions; revised staff establishment.
(Consultancy) Restructuring of GPS 100% completed Structure approved by OP; PSM
60 % increase in offenders in programmes related
to their offenses.
% 75 % increase in offenders in programmes related to their
offenses.overbaseline year 2010.
Minister; DOP; GMC (consultancy support – regional firm)
$40,000.
Implement the new structure.- Staff in place& Trained 50% staff 80%staff 95% staff
2c. Core work processes strengthened
Financial, accounting, PRISS, procurement, stores, administrative processes, reviewed and automated.
100% processes Improved & implemented.- 30% automated.
100% processes automated (consultant)
GMC-GPS (consultancy support - local).
$25,000
Goal 3: Human Resource Management and Development in GPS Enhanced.
3a. GPS’s capacity to attract & retain staff increased. At least 50% decrease in younger staff leaving GPS.
Human Resource Management Unit within the GPS functioning with
clearly documented protocols for users and providers
Unit functioning. 100% staff recruited.
Minister, PS,MOHA, DOP (consultancy support – local)
$10,000 Counterpart
funds to finance unit
HR strategy that addresses all aspects of the function developed and
approved
Strategy approved . Strategy being implemented. 20%
Strategy being implemented 50%
Strategy being implemented 70%
Strategy being implemented 100%
GMC-GPS (consultancy support for strategy design– local)
$10,000
As part of the HR Strategy, a recruitment strategy to strengthen the
number of custodial staff and their elevation to the status of
Supernumerary Constable implemented. A clear career path for
custodial staff is reflected in the strategy.
100 % completed and approved
Staff trained in HR methodologies/ protocols and operating manuals,
performance indicators and standards for all processes
100% Staff GMC-GPS (consultancy support – local)
$4,000
Performance Management System for the GPS developed and
approved for implementation. Training of staff, manuals included)
Staff trained. System functioning. GMC-GPS (consultancy support – local)
$15,000
3b. GPS seen as an attractive and rewarding career option on the
labour market (by 2014)
30 % increase of young persons joining GPS in both streams.
43
KEY PARAMETERS BENCHMARKS
RESPONSIBILITY INDICATIVE
COST Base Year
(2010) Year 1 (2011) Year 2 (2012) Year 3 (2013) Year 4 (2014) Year 5 (2015)
Conditions of service (inclusive of salary structure) in GPS reviewed
and proposal for enhancements completed including flexible
contracting / recruiting systems to satisfy professionals / specialist.
New conditions approved.
100% new conditions in force.
Minister, GMC $6,000
Planning, Research & Resource Mobilization Unit established.
Approved and functioning.
100% Staff trained in additional related specialized areas
Minister, PS, MOHA; DOP
Counterpart funding
Marketing Strategy to ‘sell’ the new GPS to graduating students developed.
Strategy approved. 100% implemented. General Management Conference, GPS
$4,000
Feasibility Study into the issue of demilitarization of the Service completed.
Stakeholder Consultation.
GMC_GPS (External Consultancy Supp.}
$15,000
3c. Human capital within the GPS consolidated (2013)
60% of staff with
positive appraisals
Training Policy for GPS developed/ upgraded.
Approved by
cabinet.
Training Board; TWC (Consultancy)
4,000
Comprehensive Staff Development Programme for staff at all levels in the Guyana Prison Service developed & implemented.
Staff
Development
Program
approved.
30% of Program
implemented
Additional 40% of
programme
implemented.
Final 30% of
programme
implemented.
Training Board; TWC (Consultancy)
5,000
Coaching and mentoring system for the GPS functioning.
100% staff
oriented.
50% staff in
program. 80% of staff in program
Training Board; TWC In-house
Training facilities and equipment upgraded.
Needs assessment report approved.
100% equipment in place.
Refurbished central
facility.
TWC; DOP
$150,000
Technical Library(for staff and inmates)in place
60% staff & 30%
inmates using
facility.
85% staff and 50%
inmates using
facility
70% of inmates using
facilities.
Minister; O/C,TWC;
DOP
$100,000
Goal 4. Prison Enterprises restructured and financial management systems strengthened.
4a. Financial viability of the GPS enhanced through increased enterprise revenues.
70% increase in
revenues from 3 pilots
Feasibility study to determine the priorities in the resuscitation of the Prison Enterprises conducted including a Strategy for GPS to be more self self-financing.
Study completed Strategy approved by cabinet
Minister; Oversight Board; DPP; DOP
(consultancy support) $6,000
Proposal for the resuscitation of 3 prison enterprises as a pilot approved by cabinet
3 prison enterprise resuscitation plans approved..
Minister; DDOP; Task Force
In-house
Business Plans developed and private sector partnerships/ sponsorships secured.
100% of Pilot enterprises’ Business Plans approved
3 enterprises‘ revenue
increase by 60%
DDOP; Task Force (consultancy )
10,000
44
KEY PARAMETERS BENCHMARKS RESPONSIBILITY INDICATIVE COST Base Year
(2010) Year 1 (2011) Year 2 (2012) Year 3 (2013) Year 4 (2014) Year 5 (2015)
Prisons Enterprise Management Unit established.
Approved in new org. structure. Provision in 2012 Budget.
Staff recruited and trained.
Minister/ DOP In-house
PRISS including the Remission Policy restructured.
New Proposals Approved
Staff trained and updated system in operation.
DDOP; MOHA; Task Force
In-house
Cost accounting system for all enterprises including PRISS
developed and implemented.
Completed & system approved.
70% of system in operation
100% of system in operation.
DDOP; Task Force (Consultancy)
10,000
Internal Audit Unit that reports directly to the PS, MOHA/
Minister strengthened (systems and training of staff,
manuals)
System approved. Provision in 2012 Budget.
Minister, PS,MOHA (consultancy )
5,000
M&E Framework for internal review in operation
(including establishing baseline for all relevant indicators
and training of staff).
100% completed and internally approval
Planning Unit Staff trained. System 100% operable.
DOP; DDOP; OC, TWC $15,000.
Goal 5. Strengthening inter-agency collaboration in the
Criminal Justice System for Improvements In Judicial
Processes.
5a. Number of remand prisoners reduced
50% reduction in remands over BL.
80% reduction in remands over Base Line
Statutory Round Table comprising a Network of CJS
institutions to identify and pursue joint developmental
initiatives in the judicial System established and
functioning.
Exploratory Consultation completed
CJS agencies sign MOUs. Strategy & action Plan approved.
Statutory meetings in operation; at least 3 priority issues resolved.
3 other priority issues resolved.
DOP Initiating Role
RECOMMENDED AREAS TO REDUCE PRESENT AND
POTENTIAL REMANDS: GPS- initiating role
Monitoring the implementation of the existing alternative
sentencing strategy.
DOP; O/C, TWC In-house
Civic awareness and education programmes to promote
societal acceptance on new sentencing strategy.
DOP; O/C, TWC In-house
Juvenile Liaison/ Community Program (in GPF) for ‗at
risk’ youth (13 – 18) Barbados model proposal.
DOP; O/C, TWC In-house
A policy and programme of community mediation, to settle
domestic conflicts involving minor crime proposed.
DOP; O/C, TWC In-house
Programme of shared research and training at the strategic
level developed and implemented..
DOP; O/C, TWC In-house
Protocols on legal and security movements for prisoners on
remand/transfers developed.
Protocols approved
DOP; O/C In-house
Policy on Coercive Control of Prisoners, use of restraining
devices and isolation developed.
Policy approved
DOP; O/C In-house
45
KEY PARAMETERS BENCHMARKS RESPONSIBILITY INDICATIVE COST Base Year
(2010) Year 1 (2011) Year 2 (2012) Year 3 (2013) Year 4 (2014) Year 5 (2015)
Goal 6. Successful Offender Re-Integration into Society
promoted and achieved.
6a. To contribute to the reduction of recidivism. 50% reduction over BL Comprehensive audit of offenders – convicted and remands
to determine retraining and rehabilitation needs completed. Rehabilitation Needs’ Report for 100% prisoners completed.
O/C, TWC; Welfare Officers
In-house
Comprehensive Rehabilitation Strategy, inclusive of both
the remand and convicted approved and implemented.
Strategy & New Curricula Approved
DOP; O/C TWC; MOE (consultancy support –NECERD / BIT-MOLHS&SS)
$5,000
Formal collaboration with the MOE to ensure that training
offered is replicated from / aligned with, existing
Education curricula; support for teachers & instructors in
addition to other related areas (Ref: Chap. 11:01)
formalized and in operation.
MOU signed
20% of Programs‟
certification endorsed
by MOE 30% of Programs‟
certification
endorsed by MOE
Evaluation report by Planning Unit accepted. 45% of facilitators / instructors supported from formal education system.
30% increase in Offenders writing CXC. 80% pass rate.
60% of Programs‟
certification endorsed by
MOE; 50% of facilitators / instructors supported from formal education system.
DOP; O/C TWC; MOE; Training Board
In-house.
MOU arrangements with other state institutions and NGOs
in various levels of collaboration executed and functioning. Exploratory consultation Report.
MOU signed with at least 3 NGOs and 5 State agencies.
At least four statutory meetings held for each MOU agreement every year commencing from Yr 2 - 2012. .
DOP; DDOP; OC/TWC
In-house
Policies and protocols to ensure offender release to
participate fully in selected and approved rehabilitation
interventions approved & implemented. 100% Policies approved.
Baseline Report: satisfaction Levels.
Evaluation report by Planning Unit accepted.
30% of Offenders’ Satisfied with Corrections Programmes. Survey Reports.
70% increase in satisfaction levels among Offenders.
GMC-GPS
In-house
After-Release Strategy (including the establishment of a
Transitional correctional facility - a ‗half- way‘ house &
indicative costings) approved and implemented.
Strategy and Action Plan Approved by Cabinet.
Facility operational.
60% of Offenders exposed to ‘after-Release’ Programme & facility in lawful economic activity.
Minister; GMC; OC/TWC; (consultancy support –regional)
(Includes Refurbishment of a building- estimate) $250,000
A constructive regime of activities geared to beneficially
occupy prisoners‘ time at every facility approved and
implemented.
Proposal approved. 100% Staff oriented.
Implementation completed Evaluation report
by Planning Unit accepted
75% of offenders express satisfaction with daily routines.
DDOP; OC/TWC; OCs- All Locations.
In-house.
A Protocol to ensure collaboration with the MOE in the
selection of trainers /instructors for the delivery of
academic , technical & vocational training and the delivery
of distance education for prisoners approved and
implemented.
Protocol approved and included in OU with MOE
First Set of Distance Education Courses delivered to 5% of offenders across Locations.
40% of Inmates across Locations receive formal academic upgrading programmes by Distance Education mode.
In-house
A strategy for the marketing of prison labour developed
and implemented.
Protocol Approved Implementation of Strategy commenced.
Contracts for Prisoner labour increased by 60% over Base Line numbers.
In-house $10,000
46
KEY PARAMETERS BENCHMARKS RESPONSIBILITY INDICATIVE COST Base Year
(2010) Year 1 (2011) Year 2 (2012) Year 3 (2013) Year 4 (2014) Year 5 (2015)
Protocols for the management of Provident Funds in After Release Support Programme approved and implemented
Protocol Approved Provision in 2013’s Budget.
At the end of 2015, 150 Offenders benefit from the Provident Funds
GMC; Minister; DOP; In-House
Financial model based on services provided by prisoners developed and implemented.
Protocol Approved
Earnings of 100% of Prisoners selected for prisoner Service increased by 100%.
GMC; Minister; DOP; DDOP
5,000
Operating procedures for the Parole Board reviewed.
Protocol Approved
Number of offenders receiving parole increased by at least 100% over Base Line numbers.
GMC; Minister; DOP; DDOP
In-House
After-release support protocols developed and implemented in collaboration with the Probation Services (MOLHS&SS); NGOs, Private Sector & Government Agencies.
Proposal Approved
100% of released offenders from 2013 receive after-release support spearheaded through GPS and the Probation Services (MOLHS&SS).
GMC; Minister; DOP; DDOP
Consultancy support $15,000
Protocol for the reduction of Prisoners’’ sentences by the President approved and implemented.
Protocols Approved
At least 5 prisoners per year from 2013 receive reduced sentences (by Presidential Prerogative).
GMC; Minister; DOP; DDOP
In-house
Goal 7. Public Confidence and Trust Rebuilt. GMC; Minister; DOP; DDOP
7(a) To seek to reverse the public’s perception of the GPS GMC; Minister; DOP; DDOP
Action Plan to establish the proposed Public Relations Unit and implement a PR Strategy approved and implemented.
PR Strategy Approved
PR UNIT in operation. Provision in 2012 Budget.
GMC; Minister; DOP; DDOP
$15,000 Counterpart funds to finance Unit.
Conduct baseline surveys to determine the scope and depth of public perceptions
Baseline poll results
20% reversal 60% reversal GMC; Minister; DOP; DDOP
(Includes survey costs) $30,000
Network of stakeholders established to solicit their perceptions, recommendations to enhance the image of the GPS.
Network Established
Statutory meetings held commencing 2012
GMC; Minister; DOP; DDOP
7 (b). Negative media reports reduced. Baseline media reports results
30% reversal in negative media reports.
70% reversal GMC; Minister (Includes survey costs) $15,000
Develop and implement a Quality Management System to support a culture of professionalism, quality service and integrity.
Implementation Plan approved
70% reversal in negative perceptions of released offenders and GPS staff.
GMC; Minister $55,000
47
The indicative financial resources required to finance this Strategic Plan is estimated to be in the Sum of US$1, 790, 500. An additional sum of US$3,000,000 has been proposed to
finance the refurbishing of 3 prisons (including the completion of the refurbishment of Trade shops) subject to adjustment after the receipt of Engineering estimates.
KEY PARAMETERS BENCHMARKS RESPONSIBILITY INDICATIVE COST Base Year (2010) Year 1 (2011) Year 2 (2012) Year 3 (2013) Year 4 (2014) Year 5 (2015)
Disciplinary Code including corresponding protocols revised and implemented.
80% reduction in allegations of misconduct/ mistreatment of offenders
GMC; Minister In-House
Comparative review of media reports over a three year period – 2012 -14. Completed
Baseline established by PR UNIT
Comparative Report on media perceptions show consistency regarding improved GPS image.
GMC; Minister In-house
Goal 8: Promoting Holistic Health Care in Prisons GMC; Minister
8(a)To safeguard the physical, psychological, emotional & and spiritual well being of Staff & Offenders.
Reduction of selective range of inmates’ illnesses
55% reduction of drugs dependent offenders
70% Reduction in number of allegations of inmates’ confrontations.
GMC; Minister In-house
Holistic Healthcare Strategy with Action Plan
implemented.
Staff exposed to awareness sessions
Initial program of initiatives funded.
Stakeholder consultation report
Prison Health Audit HH Strategy approved
30% Implementation progress.
Evaluation of HH Strategy Implementation Report (Planning Unit).
50% 0f Action Plan implemented.
Minister, MOHA, DOP; O/C, TWC; MOH; Probation;
$50,000
Strengthening collaboration with the MOH in keeping with
Chapter 11:01 MOU signed Additional
preventative Health-care Clinics established in identified Prison Locations.
Full-time GMOs at all identified key Locations in the GPS.
Minister, MOHA, DOP; O/C, TWC; MOH
In-house
Occupational Safety & Health Policy and Action Plan
approved & implemented. Strategy approved
Implementation of Protocols throughout GPS.
Joint audit with OS&H Unit & Internal Audit , MOHA
Reduction in work related accidents by 60% over baseline year (Y2010).
DDOP/ MLHS&SS interagency collaboration
In-house
11. IMPLEMENTATION ARRANGEMENTS
The implementation of and organizational change cannot be successfully achieved without a deliberate
mechanism dedicated to the task at hand. The figure below depicts the structure that was recommended to
address the day-to-day administration of this Strategic Plan.
This recommendation has not been accepted by the MOHA and the alternate arrangements identified
by the Ministry are presented as an Addendum to this Report.
The Oversight Body at the MOHA is expected to be chaired by the Hon. Minister of the Ministry of
Home Affairs. This body will oversee the implementation of the Strategic Plan from a policy perspective,
acting as a filter as initiatives are fleshed out, providing policy guidance as is indicated; clearing emerging
bottlenecks at the strategic governmental level and ensuring that required ratification, approval and final
policy decisions are granted.
OVERSIGHT BODY FOR GPS
REFORM
MINISTER [Chairman]
DIRECTOR OF PRISONS (Chairman & Program Manager)
Strategic Planning Steering
Committee
Planning, Research & Resource
Mobilization Unit
Technical Support Officer
(Technical Lead to Project Team
for Strategic Plan 2010-2015)
Planning & Research
Assistant
[PR&RMU]
Proposed Core Functions
Support overall planning effort of GPS
Under direction, initiate action to advance the various
initiatives indicated for each respective year.
Take follow-up action on Decision emanating from the
GMC or the Oversight Body in MOHA
Track planned activities started to ensure that matters are
progressed.
Ensure that activities for which local funding is required
are included in the annual Budget
Identify opportunities for new sources of funding to
support initiatives through discussions with donor
community and private sector Prepare project proposals;
positional papers.
Support advocacy efforts of GPS in inter-agency
collaboration.
Conduct research into best practices in all areas of prison
Administration.
Ensure that activities in the SP remain relevant and
responsive.
DEPUTY DIRECTOR OF
PRISONS
[Project Manager for Strategic
Plan 2010-2015]
49
The immediate champion of this Strategic Plan is the Director of Prisons. The Strategic Plan becomes
another program within the range of his responsibility as the ultimate program manager of the programs
financed for the Prison Service, in addition to his other role as Chairman of the Strategic Planning
Steering Committee. This Committee was already established during the environmental scan phase of
the Strategic Planning process. In this implementation phase, the Committee is envisaged to comprises,
the Directorate, Officers-in-Charge of Prisons, the O/C of the TWC, The Finance Officer, The Agriculture
Manager, Security Managers and a representative of the Junior Officers‘ Association. Consideration
should be given to include, as well as, a credible representative of the Inmates / Offenders.
The Committee is expected to provide the enabling environment to facilitate innovation and
organizational learning in this process of change and reconstruction. In so doing, key functions would
include monitoring and evaluation of the progress of annual plans and targets, facilitating the smooth
implementation of the various initiatives, resolving bottlenecks, referring issues that demand high policy
level support or intervention to the Oversight Body at MOHA and identifying and supporting the
mobilization of funding from non- traditional sources. Meetings should be held at monthly intervals. It is
recommended that there should be quarterly meetings between this Steering Committee and the
recommended high profile Oversight Body, supported with formal documented reports that set out clearly
the achievements against planned activities, the emerging issues and the facilitating action required to
advance the implementation of the Plan.
The Deputy Director of Prisons is responsible for managing the implementation of the Strategic Plan. He
will be accountable to the DOP for its effective discharge. The DDOP will have at his disposal, the
support and input from a Project Team (Strategic Management) comprising a cross section of GPS staff,
similar to that which existed during the planning phase. This team will function as the Change Team for
the GPS, the critical mass of staff who will assist in championing and leading the transformation through
involvement in the design of initiatives, facilitating activities that are assigned to them, and of most
importance, demonstrating the new values articulated during the planning process. Their role in
reshaping the culture of the GPS is critical.
As is common in introducing reforms, there is a need for dedicated resources – human and financial – to
the effort. In this regard the critical human resource requirement will be discharged by a new Unit-
Planning, Research & Resource Mobilization, which is proposed to be established as a permanent and
much needed function within the GPS. The Unit, under the direct supervision of the DDOP, will be the
hub of the reform effort, responsible for the day to day coordination of the implementation of this
50
Strategic Plan. The Head of the Unit, the Technical Support Officer (Strategic Management), will be the
Technical Lead of the Project Team.
Initially, the recommended staffing numbers are conservative, although it is essential that the principal
position be filled by someone with substantial experience in organizational planning and analysis
skills. The incumbent should have, at minimum, an undergraduate degree in the area of public
administration or management; business administration; economics or planning and research. In addition,
at least five years experience in a planning or project development environment or at a strategic level of
an organization would be beneficial. This person will be supported by a Planning & Research Assistant
with similar academic qualifications but a lesser range of experience is acceptable. It is critical that the
right skills be sourced since the Unit is expected to operate with minimal day-to-day supervision,
performing a staff/ advisory function to the Directorate. To the extent that the Unit is efficient, the
contribution to the overall advancement and successful implementation of the Strategic Plan cannot be
overstated. Recruitment may well have to be from outside of the GPS.
111. MONITORING AND EVALUATION
The successful implementation of this Strategic Plan demands on-going monitoring and evaluation of
project activities throughout the life of this Plan. This reality adds another element of justification to the
establishment of a small but competent group dedicated to ensuring that advancements are realized. At the
operational level, the Policy, Research & Resource Mobilization Unit (PR&RMU) will provide progress
reports that compares actual achievements against what was planned, on a monthly basis, to the Strategic
Planning Steering Committee (SPSC). The variance is identified and explained. This report should
indicate physical progress as well as financial progress. A separate section should list all outstanding /
emerging issues in a format that would enable follow-up until resolution. To ensure that there is not a late
response to issues emerging between meetings, an early alert system should be pursued so that factors that
can seriously derail planned timelines should be immediately reported to the DDOP, so that mitigating
action may be determined and followed. A suggested reporting format is presented in Annex 2.
In addition to monthly reporting, the PR&MU is required to ensure that baseline data exists for all
indicators listed in the Results Matrix and that data collection continues periodically to enable the
tracking of targets set. The Unit is required to conduct evaluation of initiatives in place to determine early
impact. This is important to allow for adjustments in order to better achieve the end benchmarks of this
Plan.
51
At the Strategic level, as indicated in the previous section, the SPSC, will formally report on progress to
the Oversight Body at MOHA, on a quarterly basis. In this regard, the Head of the PR&RU will function
as Secretary to the SPSC, providing the details of the implementation for the reporting period. The
Minister has the authority to request information or reports as well as additional meetings.
At the end of the life of this Plan, a final evaluation will be undertaken by the Internal Audit of the
MOHA, to determine lessons learnt as a new cycle of planning is taken on board to continue the journey
for excellence through the established culture of continuous improvement.
1V. STAKEHOLDER ANALYSIS
The purpose of the stakeholder analysis is to understand (a) the level of power of each stakeholder group;
(b) the level of interest in the GPS and (c) the potential impact of stakeholders‘ expectations on the
strategies that the GPS has agreed upon to improve the institution and its performance.
During the strategic planning process a meeting was held with the Directorate to conduct an analysis of
the stakeholders regarding the possible specific interests of each stakeholder group in relation to the GPS,
its plans, operations and future endeavors. In addition, the level of power was assessed in terms of control
of strategic resources (internal & external); level of influence, position in the CJS hierarchy and control of
the environment.
The conclusions are intended to be used to manage stakeholders‘ expectations during the implementation
of the strategic plan so as to minimize any possible conflict or threat to the implementation of the SP
along the journey. These are presented below:
52
(a) Stakeholder Power /Interest Matrix
LEVEL OF INTEREST
LOW HIGH
LOW
LEVEL
OF
POWER
HIGH
(b) Implications from the Analysis
The allocation of stakeholders in the quadrants above indicates the type of relationship that GPS will have
to establish with each stakeholder group. All the groups must be managed since events can suddenly
emerge that will change their stance and the composition of the Matrix can be altered in an instance.
Accordingly, information sharing is the main mechanism that will be employed since knowledge brings
understanding. However, the range of information, frequency and depth, will be determined based on the
level of power and influence of each cluster of stakeholders.
A – Power is Low but Interest is Low:
Less power, and little interest.
Active support of this group may have an
influence on the attitude of the more
powerful stakeholders.
1. Ministry Of Amerindian Affairs
2. Public Service Commission
B - Power is low but Interest is High
Because of their high interest, not withstanding
low power, can influence the more powerful
stakeholders. They can be champions who can
support the strategies.
1. Parole Board
2. Prisons Visiting Committees
3. Guyana Human Rights Association
4. Religious Organizations
5. Food For The Poor
C: Power is High and Interest is Low
While powerful, these stakeholders‘ interest
is low.
TASK: Build strategies that will address
their expectations.
1. Supreme Court
2. Magistrate Court
3. Director of Public Prosecution
4. Ministry Of Education
5. Public Utilities
6. Public Service Ministry
7. Public Service Commission.
8. Private Sector
9. Donor Agencies
D Power is high and Interest is High
Most difficult group since they are in a
powerful position to block or support new
strategies an d their interest in the GPS is high
Solution: Test out new strategies / ideas with
them before taking a final position.
1. Minister of Home Affairs
2. Ministry of Home Affairs
3. Ministry of Legal Affairs
4. Guyana Police Force
5. Ministry of Finance
6. Ministry of Labour Human Services
& Social Security
7. The Probation and Welfare
Department
8. Ministry of Health
9. Office of The President/Defense
Board
10. Guyana Defence Force
11. Inter-American Development Bank
12. Ministry of Agriculture
53
The immediate and most critical group is in quadrant D, since they can either facilitate or block the
strategies identified for implementation. Since their support is critical, they will have to be engaged and
the entire Strategic Plan ‗sold‘ to them so that they can champion the initiatives that are planned. GPS
intends to have them involved as much as is practical before and during implementation, keeping them
regularly informed, seeking advice and soliciting their input as new processes, structures etc are being
designed. One of the first activities planned is to engage in discussions around this draft plan in order to
receive their reactions to proposed reforms, before the document is finalized.
The other group to engage is in quadrant C. While at the moment their interest in the GPS is low, this
can easily change if some ‗trigger‘ emerges that transforms their level of interest, causing them to
reposition to quadrant D. GPS plans to periodically engage them to test their likely reactions to the
reforms that are in the SP so that, where necessary, they can be brought on board minimizing potential
conflict. Finally, efforts will be made to engage quadrant C stakeholders as allies. Although they have
little power, their high interest can work for or against a successful implementation since they can
influence the more powerful agencies in Quadrant D.
The task is therefore a challenging one to effectively manage the stakeholders of this institution. The
important insights gained from this piece of analysis will be factored into the communications
management plan, thereby promoting a better level of collaboration and success.
V . MANAGING CHANGE IN THE GUYANA PRISON SERVICE
(a) Introduction
The GPs is facing what can be termed as ‗transformational change’ in the Vision it has set itself, given
its present position. Despite the fact that this journey into change has commenced with participation of
just about a third of the Institution‘s workforce, representing a cross section of ranks and location, there is
always resistance.
In recognition, this supporting mechanism seeks to identify a path that will mitigate the barriers to a new
way of existing as an organization, ensuring that despite cultures and subcultures that may not necessarily
embrace new values, ideas, and work practices, a dedicated effort would have been exerted so that this
plan brings about some level of sustainable improvement and positive change for both staff and offenders.
54
(b) Factors that cause change to be unsustainable
It is important to understand before talking about change management a bit about the context within
which the change will occur. From evaluations across the world, there are common themes associated
with failure to maintain organizational change successfully. These include:
Leaders presenting intended change as an option.
Focusing on process- ‗what is to be done‟ rather on the tangible end results -„what is to be
achieved‟.
Similarly, over concentration on results without trying to understand people‘s fears, feelings – a
great mistake which can result in a deterioration of morale and subsequently employee
commitment.
Forgetting to give staff timely feedback despite the involvement during the planning phase and
not continuing to involve them in the implementation, thus leading to resentment and covert
opposition.
When leadership does not ‘walk the talk’, not demonstrating their commitment to the behaviors
that are demanded from the values articulated by they themselves and staff, as a collective.
No adjustments in existing reward or recognition systems; allowing the same schemes to
remain although staff is expected to respond / comply with the change.
Delegating the leading of the change to an outsider (e.g. a change consultant / expert).
These factors are highlighted for emphasis since such considerations are the basis for successfully
proceeding with reforms that will, especially in this instance, bring about significant change to the ‘way
we do things around here’.
(c) Proven Strategies for Managing Change
Research into organizations that have experienced change reveal that no one strategy presents the perfect
fit. Indeed managing change calls for a mix of strategies, especially when change is ‗transformational‘ –
multifaceted, seeking to install a number of improvements, more or less simultaneously.
Experts have identified the four strategies that are invariably used when introducing new initiatives into
an organization:
STRATEGY DESCRIPTION
Empirical-Rational People are rational and will follow their self-
interest — once it is revealed to them. Change is
based on the communication of information and
the proffering of incentives.
55
Normative-Reductive People are social beings and will adhere to
cultural norms and values. Change is based on
redefining and reinterpreting existing norms
and values, and developing commitments to new
ones.
Power-Coercive People are basically compliant and will generally
do what they are told or can be made to do.
Change is based on the exercise of authority and
the imposition of sanctions.
Environmental-Adaptive People oppose loss and disruption but they adapt
readily to new circumstances. Change is based on
building a new organization and gradually
transferring people from the old one to the new
one.
(d) Guidelines for selecting a strategy
The consensus of change management experts is that the selection of an appropriate strategy is
contingent on the prevailing circumstances2:
Scope and Scale. This can vary from the minor ―tweaking of a process within a unit to the complete
transformation of the entire organization. The larger the scope and scale, the more likely a broad mix
of strategies will be required with Power-Coercive playing a central role.
Degree of Resistance. Strong resistance argues for a coupling of Power-Coercive and
Environmental-Adaptive strategies. Weak resistance or concurrence argues for a combination of
Empirical-Rational and Normative- Reductive strategies.
Target Population. Large populations argue for a mix of all four strategies, something for everyone
so to speak.
The Stakes. High stakes argue for a mix of all four strategies. When the stakes are high, nothing can
be left to chance.
The Time Frame. Short time frames argue for a Power-Coercive strategy. Longer time frames argue
for a mix of Empirical-Rational, Normative-Reductive, and Environmental-Adaptive strategies.
Expertise. Having available adequate expertise at making change argues for some mix of the
strategies outlined above. Not having it available argues for reliance on the power-coercive strategy.
Dependency. This is a classic double-edged sword. If the organization is dependent on its people,
management's ability to command or demand is limited. Conversely, if people are dependent upon the
2 Nickols, Fred. Change Management: www.nickols.us
56
organization, their ability to oppose or resist is limited. (Mutual dependency almost always signals a
requirement for some level of negotiation).
(e) Recommended Strategy
Based on the organizational assessment of GPS, the recommended strategy to manage change in GPS
would of necessity, have to be mixed. It has already been established that the change will be
transformational. Against this quantum leap that is indicated, there are several weaknesses within the
institution. The gap in staff capacity; the likelihood of strong resistance, give the prevailing culture and
values; the absence of significant change in structure and organizational routines for several years, the
reliance on manual systems will collectively present ‗fear of the unknown‘ despite the stated goals and the
desire for a different culture. The stakes for success are high, since the need to restore public trust by
improving performance, is high.
The conditions of the GPS favors the Power-Coercive strategy for managing change but as a result of the
range of reforms and the size of the institution, a mixture of strategies is indicated with the Power -
Coercive being the most dominant. The change management strategy should therefore employ a
significant degree of authority in instituting the new initiatives, but this should be tempered with
communicating information and offering incentives; redefining and reinterpreting existing norms and
values, and developing commitments to new ones. This strategy is somewhat reflected in the
Communications Management Plan.
(f) Methodology
Tips for Successful Change Management: “A Blueprint for Successful Change Management3
1. Create a sense of urgency for the change and clearly articulate what the future will look like.
There needs to be clarity - clarity of the need, clarity of the vision and clarity of the actions
required.
2. There needs to be a strong, emotionally engaged, aligned and cascading coalition of leadership
support.
3. Trust in the leadership must exist. The best change plans will not endure if trust is not created and
nurtured.
4. Leaders of change must “walk the talk”. Gandhi was quoted as saying "Be the change you want
in the world". However, it was his actions, not his words that delivered this message.
5. Leaders must have the courage to face and overcome difficult and deep-seeded cultural issues.
3 Markowsky, Jim. X• Factor Solutions London (2010).
57
6. Ask stakeholders the right, powerful questions. Actively listening, empathizing, understanding
and documenting the answers to these questions can provide one of the greatest impacts on a
change effort.
7. Create 2-way, face-to-face communications to discover stakeholder concerns, needs, and ideas.
Informal consultations/ discourses such as Meetings and „Lunch and Learn‟ events are very
effective ways to engage stakeholders in this way.
8. Create „quick wins‖. Celebrate successes early and often. Provide recognition to those going out
of their way to help.
9. Admit your mistakes, misunderstandings and oversights. Ask for help. ―Get the ship back on
course‟.
(g) An Initial Action Plan for Managing Change.
The following initiatives should be discussed among the critical mass of champions, and timelines
agreed upon to put in place the suggestions. This should be done well in advance of the actual
implementation of the Strategic Plan.
Activity Responsibility Timeline Comments
Install the Project Team/ Change Agents
(the same Strategic Planning groups)
SP Steering
Committee
Before the SP is
formally launched.
They should represent a cross
section of the GPS and be
committed to supporting the
vision and its implications.
Develop a Code of behavior for all Project
Team Members and have them sign off on it. SP Steering
Committee
Within one month
of the
commencement of
the
Implementation
This should be a participative
effort. [Behavior that is
inconsistent with the change that
is supposed to be advocated will
undermine change processes].
Identify a Budget for Change Management
Activities.
DDOP / Technical
Lead.
Before the SP is
formally launched.
Include in Budget 2011.
Commence a programme of team building
for all of the persons who will be associated in
leading the change.
SP Steering
Committee
Within one month
of the ‗roll-out‘ of
the SP.
This should be done preferably
before the SP Launch.
Assign members of the Project / Change
Team to champion various initiatives of the
Strategic Plan.
SP Steering
Committee
Three months after
the SP commences
implementation
Should take into account area of
expertise of each member.
Develop an incentives scheme to reward
desired behavior.
SP Steering
Committee
Three months after
the SP commences
implementation
Include in Budget for 2011.
Develop feedback mechanism for staff,
external stakeholders and offenders to
periodically monitor the perceptions.
Technical Lead,
PR&RMU
Three months after
the SP commences
implementation
Surveys and suggestion boxes.
Identify pockets of resistance and determine
the impact of such opposition. Project /Change
Team
Three months after
the SP commences
implementation
Identify and implement steps to
reduce resistance.
Break up cliques / redeploy relevant staff where resistance is strongest [when efforts
to diffuse fail and opposition covert], to other
functional areas.
SP Steering
Committee
Six months after
the SP commences
implementation
If this fails, and resistance persists,
transfer out of the institution.
58
In summary, the key message in any change programme is that information is important. Employees need
to know, on a timely basis, the basic but important essentials of what is happening in their organization:
when, why, who, what and by whom. However, of even greater importance in this opaque but inevitable
aspect of organizational reality, employees need to be involved in the process to be truly engaged - to feel
a sense of belonging and ownership which would go a long way towards engendering commitment.
These tenets should be the central themes as the GPS moves into this next phase of the Strategic Planning
process.
59
ADDENDUM
60
GUYANA PRISON SERVICE
ADDENDUM TO THE STRATEGIC PLAN 2010 – 2015.
IMPLEMENTATION ARRANGEMENTS – MINISTRY OF HOME AFFAIRS’ PROPOSAL
The Organizational arrangements for the Implementation of the Guyana Prison Service’s Strategic Plan, as articulated by the
Minister of Home Affairs, are presented below:
A. Organizing for Implementation of the Plan.
OVERSIGHT BODY
MINISTER of HOME
AFFAIRS
GUYANA PRISON SERVICE
STRATEGIC PLANNING
COMMITTEE / SECRETARIAT
DEPUTY DIRECTOR
OF PRISONS
MONITORING AND
EVALUATION
Technical Analyst
PROJECT
MANAGEMENT
Prison Management
Officer
PUBLIC
RELATIONS &
COMMUNITY
AWARENESS
Technical Officer
PLANNING,
RESEARCH &
RESOURCE
MOBILIZATION
Technical Officer
Analyst
Analyst
62
B. Roles and Responsibilities in the Implementation of the Strategic Plan.
There shall be an Oversight Body with responsibility for the provision of overall policy guidance,
support to and oversight for the Strategic Planning Committee that will be accountable for the
Implementation of this Strategic Plan for the period 2010 to 2015. The members of this Oversight
Body shall be appointed by the Minister of Home Affairs.
In support of the day-to-day implementation of the Strategic Plan, the Strategic Planning Steering
Committee will ensure that the necessary activities are implemented within the defined timeframe, and
also that the SP remains relevant to the priorities of the administration.
Consequently, the Committee will have under its purview a wide range of areas that is deemed
necessary for effective implementation. These are (a) Planning, Research and Resource Mobilization;
Public Relations and Community Awareness; Monitoring and Evaluation and Prison Project
Management. Each of these functional areas will have a Technical Officer or Analyst and in the case of
the Prison Project Management area, a Prison Management Officer. These persons, along with the
Deputy Director of Prisons and the Analyst attached to that office will constitute the Steering
Committee. Because of their ongoing interaction in these key areas, they will also function as the
Secretariat for the implementation of the reforms in specific activities. An Analyst, dedicated to the
Steering Committee, will ensure that there is follow through action on the decisions that are taken at
this forum.
It is anticipated that the indicative new Technical positions will be filled through the relevant
recruitment channels and processes.
63
ABBREVIATIONS AND ACRONYMS
APO Assistant Prison Officer CMO Chief Medical Officer CXC
Caribbean Examination Council
DDOP Deputy Director of Prisons
DOP Director of Prisons DPP Director of Public Prosecution GMC General Management Committee GMO Government Medical Officer GPF
Guyana Police Force
GPHC Georgetown Public Hospital GPS Guyana Prison Service GT Georgetown GTI Government technical Institute HR HIV/AIDS
Human Resource Human Immunodeficiency Virus / Acquired
Immune Deficiency Syndrome ICT Information Communication Technology
JLCS Julian Laithe Consulting Services JSRS Justice Sector Reform Strategy M&CC Mayor and City Council MDG Millennium Development Goal MIS Management Information System MJAS Modernization of the Justice Administration
Programme MOA Ministry Of Agriculture MOAA Ministry Of Amerindian Affairs MOE Ministry Of Education MOF Ministry of Finance MOH Ministry of Health MOHA Ministry Of Home Affairs MOLHS&SS Ministry of Labour Human Services and Social
Security MOU Memorandum of Understanding NCERD National Center for Educational Research and
Development NGO Non Governmental Organization OC Officer in Charge PESTLE
Political, Economic, Social, Technological, Legal and Environment
64
PO Prison Officer PR Public Relations PR&RMU Planning, Research & Resource Mobilization
Unit PRISS Prisoners’ Self Support Scheme PS Permanent Secretary PSC Public Service Commission PSM Public Service Ministry SP Strategic Plan SPSC Strategic Planning Steering Committee
SWOT Strengths, Weaknesses, Opportunities, Threats
TA Technical Assistance TW&C Training, Welfare and Corrections