Strategic Capital Planning and Capital Budgeting

39
2015 Capital Link 1 www.caplink.org Terry Glasscock, Senior Project Consultant, Capital Link Rick Breuer, CEO, Community Memorial Hospital November 17, 2015 Sponsored by the National Rural Health Resource Center and the Federal Office of Rural Health Policy Rural Health Capital Readiness Webinar Series Strategic Capital Planning and Capital Budgeting

Transcript of Strategic Capital Planning and Capital Budgeting

Page 1: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 1 www.caplink.org

Terry Glasscock, Senior Project Consultant, Capital Link

Rick Breuer, CEO, Community Memorial Hospital

November 17, 2015 Sponsored by the National Rural Health Resource Center and the Federal Office of Rural Health Policy

Rural Health Capital Readiness Webinar Series

Strategic Capital Planning and Capital Budgeting

Page 2: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 2 www.caplink.org

About this Webinar Series

• Offered and developed by Capital Link through support from the National Rural Health Resource Center (NRHRC) and in cooperation with the Federal Office of Rural Health Policy

• Capital Link has 15+ years of experience with community health capital project planning and financing

• April 2015, NRHRC released a capital needs assessment prepared by Capital Link: - 41% of Critical Access Hospitals and 100% of Rural Health Clinics have

plans to expand or replace existing sites - Raising equity/cash reserves most common project barrier (56%) - Other challenges: grant funding, fundraising, staff time, cash

fluctuations

Page 3: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 3 www.caplink.org

About this Webinar Series

• The response: - Capital Project Readiness Manual and Toolkit - Webinar Series:

• November 17 - Strategic Capital Planning and Capital Budgeting

• November 24 - Operational Considerations for Facility Planning, and Capital Project Management

• December 1 - Laying the Groundwork for a Capital Campaign

• December 3 - Business Planning and Financial Projections for Capital Projects

Page 4: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 4 www.caplink.org

Strategic Capital Planning

Terry Glasscock, Senior Project Consultant, Capital Link

Page 5: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 5 www.caplink.org

Strategic Capital Planning

• Capital Planning cannot take place in a silo

• Every aspect of what you do must be taken into consideration.

• Capital investments must be earned…before and after you complete them

• Strategic Planning is critical for strategic managing

• And strategic management is essential!

• At no time in our history has it been so important to manage strategically!

Page 6: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 6 www.caplink.org

Why Now?

• Congress’ own Commission on Entitlement Reform reported that SS, Medicare, Medicaid and interest on the national debt will exceed all federal income by 2030!

• International Monetary Fund: The United States must either decrease benefits for Medicare and Medicaid by 50% or increase taxes by 60% to maintain solvency of those programs.

Page 7: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 7 www.caplink.org

Number of Workers Per Retiree

5 4.5

4

3

2

1990 2000 2010 2020 2030

Page 8: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 8 www.caplink.org

Federal Receipts vs. Entitlements

0

2

4

6

8

10

12

14

16

18

20

22

1970 1975 1980 1985 1990 1995 2000 2005 2010 2015 2020 2025 2030 2035 2040

Baseline SS, Medicare, and Medicaid Baseline receipts (includes JGTRRA)

Continue at same rate

Page 9: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 9 www.caplink.org

MedicaidMedicare

Social Security, Medicare & Medicaid

Outlays as a Percentage of GDP 1990-2075

0

2

4

6

8

10

12

14

16

18

20

22

24

1990 2000 2010 2020 2030 2040 2050 2060 2070

Social Security

Source: C. Eugene Steurle and Adam Carasso, (Budget Crisis at the Door), The Urban Institute, 2003. Based on data from the Congressional Budget Office, “A 125Year Picture of the Federal Government’s Share of the Economy, 1950-2075,” July 3, 2002, table 2.

Page 10: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 10 www.caplink.org

Defense 51%

Social Security

13% Medicare 0%

Medicaid 1%

Safety Net 6%

International Affairs

5%

Transportation 4%

Interest 6%

Everything Else 14%

1962

Defense 23%

Social Security 20%

Medicare 13% Medicaid

10%

Safety Net 13%

International Affairs

1%

Transportation 2%

Interest 6%

Everything Else 12%

2011

Medicaid Medicare S.S. 43%

Safety Net S.S. 20%

Federal Government Spending

Page 11: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 11 www.caplink.org

Healthcare Costs

• 1900 – 3% GDP (Gross Domestic Product).

• 1964 – 6% GDP.

• 1994 – 15% GDP.

• 2020 – 25% GDP.

Per person expenditure for healthcare:

• 1965 - $205

• 2000 - $4637

• 2010 - $8233

Page 12: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 12 www.caplink.org

Page 13: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 13 www.caplink.org

First - A Word on Systems and Change

• Why do 70% of change initiatives fail?

• Because we try to put new ideas into the old system.

• The old system is designed to strangle innovation – ideas die of starvation.

• Some aren’t comfortable thinking “outside of the box”…

• Understand how systems work…or don’t work

• Xerox

Page 14: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 14 www.caplink.org

Key Strategic Planning Components

Page 15: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 15 www.caplink.org

Self-Assessment

• What you do

• Why you do it

• How you do it

• What you do well

• What you could do better

• Operational capacity

• Financial capacity

• Physical capacity

• Irony of Strategic Planning: most effort needed

Page 16: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 16 www.caplink.org

Environmental Scan

• You can’t manage what you don’t know

• What lies ahead (environmental scan)

• Demographic shift (overwhelming)

• Government healthcare policy

• Government fiscal policy

• National and global economy

• Local economy

• Invite stakeholders to provide input - Community - Patients, Providers, staff - Government: local, state, federal - Other social services

• There is no “future” there are possible “futures”

Page 17: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 17 www.caplink.org

Impact Evaluation

• What possibilities did we find in landscaping

• What are the operating and financial implications of each of those possibilities.

• Listing the possibilities and the impacts on the CHC of each one

• Prioritizing the probabilities

• Analyzing the impact on each possibility

• Capital Needs, human resources, connections

Page 18: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 18 www.caplink.org

Goal Setting

• Specific

• Measurable

• Attainable

• Realistic

• Timely

Page 19: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 19 www.caplink.org

Action Plan

• “What if” planning

• Contingent Action Plan

• “Back-to-the-Future” planning

• Immediate Action Plan

• Maximizing positive possibilities

• Minimizing negative possibilities

• Timeline estimates for intervention

• Community Activation

Page 20: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 20 www.caplink.org

Now…back to Capital planning.

Page 21: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 21 www.caplink.org

Master Capital Plan – Long Term

• Determine expansion priorities (based on market/community/policy/environment analysis)

• Facility inventories: - Capacity - Effectiveness - Maintenance needs (often overlooked after expanding) - Financial sustainability

• Prioritize and set capital budgeting goals: operational and financial

Page 22: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 22 www.caplink.org

Work with What Capital You’ve Got – Near Term

• Facility Maximization Plan: - Define new organizational program plan (and site-specific as

applicable) - Select most effective/efficient method of delivery for each program - Define staffing plan (for each site as applicable) - Identify adjustments or reorganization needed within existing physical

space to meet new program goals

Page 23: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 23 www.caplink.org

The Board’s Role in Strategic Capital Planning*

• Board involvement suggested in capital planning issues: - Establishing capital budgeting process (existing facilities and

expansions) - Finalizing expansion priorities

• For planning a new project: - Project scope, Budget, Timeline - Architect, site selection and final design option - Loans/financing structure

*NACHC Publication, 2006

Page 24: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 24 www.caplink.org

Community Support

• Identify resources - People - Institutions - Businesses - Organizations

• Process plan - Objective - Priority - Action needed - Community person - Who will make contact

Page 25: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 25 www.caplink.org

Giving the Needed Time

• Not being trapped in a room for a week but an iterative process

• Set a timeline

• Identify teams (and outside help) for information gathering and development of various action plans - meet as group to discuss implications and prioritize

• Talk as full group when considering mission and vision – all should buy in – ownership is truly critical

Page 26: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 26 www.caplink.org

The Capital Budgeting Process

Rick Breuer, CEO, Community Memoria Hospital and Sunnyside Health Care Center

Page 27: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 27 www.caplink.org

For Profit, Corporate World

• Maximize Shareholder Wealth

• Return on Investment - Multiple tools

Page 28: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 28 www.caplink.org

Non Profit, Healthcare World

• Still care about returns, if measurable

• Ties to mission and strategy

Page 29: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 29 www.caplink.org

Timing

• Concurrent with Operating Budget - Target Operating Budget leads to:

• Budgeted Cash Flow Statement • Budgeted Balance Sheet • Goals for $$ Balance, others as applicable • Backs you into a max Capital spend

» Can obviously go lower – this is a backstop - Committing Funds for Next Year

• Identify Potential Needs for next 3-5 Years

Page 30: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 30 www.caplink.org

Type of Need

• New

• Replace

• Replace if…

• Departmentally prioritized, with explanations

Page 31: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 31 www.caplink.org

First Review

• Senior Management - Ensure someone on team understands every item listed - Already on prior 3-5 year lists? - Fits in to support strategic initiatives? - Funding sources available specific to item? - Compute return on investment, if applicable - Create initially prioritized list - Develop estimate of cutoff

Page 32: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 32 www.caplink.org

Second Review

• Medical Staff - Entire prioritized list, with estimated cutoff - Include explanations and request for feedback

• Items to add • Items not felt necessary • Items to reprioritize

- Importance of follow up with MD and department - Make any changes to list based on feedback

Page 33: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 33 www.caplink.org

Third Review (if applicable)

• Building Committee - Focus on building and fixtures

• Strategic Planning Committee - Tie to strategic initiatives

• Finance Committee - Focus on evaluating returns where available

Page 34: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 34 www.caplink.org

Final Review

• Senior Management - Makes all changes based on feedback from previous

stakeholders - Presents to applicable governance group(s) for approval - Usually in tandem with Operating Budget

• Flex Options Mid-Year

Page 35: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 35 www.caplink.org

Back to Timing

• Timing of Strategic Planning Sessions related to Budget - Ability to influence budgets based on info from planning

sessions - Ability to tweak planning based on realities seen in budget

projections - Ability to use 3-5 year needs in both directions

Page 36: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 36 www.caplink.org

Capital Budgets & Strategic Planning

• Essential to the Plan

• Common flaw in planning process – not devoting the resources necessary to carry out agreed upon plan

• Domino effect

Page 37: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 37 www.caplink.org

Capital Budgeting

• Not just an annual exercise

• Will help build a stronger Balance Sheet

• Will help build relationship with lenders

• Key part of overall financial planning

• Key part of strategic planning

Page 38: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 38 www.caplink.org

Questions?

Page 39: Strategic Capital Planning and Capital Budgeting

2015 Capital Link 39 www.caplink.org

Main Office

Massachusetts

Allison Coleman

Chief Executive Officer

[email protected]

Susan Petrie

Chief Operating Officer

Tel: 617-988-2248

[email protected]

Steve Rubman

Director of Data & Information Systems

Tel: 617-988-2299

[email protected]

Dan Woodman

Project Consultant

Tel: 617-988-2202

[email protected]

Regional Offices

California

Tony Skapinsky

Project Consultant

Tel: 805-544-2355

[email protected]

Louisiana

Jonathan Chapman

Director of CHC Advisory Services

[email protected]

Missouri

Mark Lurtz

Senior Director of Partnership Development

Tel: 636-244-3082

[email protected]

Rhode Island

Rebecca Polan

Project Consultant

Tel: 401-846-3109

[email protected]

South Carolina

Terry Glasscock

Senior Project Consultant

Tel: 781-789-684

[email protected]

West Virginia

Cindy Barr

Operations & Facilities Planner

Tel: 304-876-6996

[email protected]

Contact Us