Strand Debonding in Pretensioned Beams

265
SCHOOL OF CIVIL ENGINEERING INDIANA DEPARTMENT OF TRANSPORTATION r V ••••••••••'3«0«***«*»«**'"'*«»««*»««ft JOINT HIGHWAY RESEARCH PROJECT Part 1 Final Report FHWA/INDOT/JHRP-92-24 Strand Debonding in Pretensioned Beams - Precast Prestressed Concrete Bridge Girders with Debonded Strands Continuity Issues O.A. Abdalla, J.A. Ramirez, and R.H. Lee i : : ,t> e % PURDUE UNIVERSITY

Transcript of Strand Debonding in Pretensioned Beams

Page 1: Strand Debonding in Pretensioned Beams

SCHOOL OF

CIVIL ENGINEERING

INDIANA

DEPARTMENT OF TRANSPORTATION

r V•••••••••••'3«0«***«*»«**'"'*«»««*»««ft

JOINT HIGHWAY RESEARCH PROJECT

Part 1 Final Report

FHWA/INDOT/JHRP-92-24

Strand Debonding in Pretensioned Beams- Precast Prestressed Concrete BridgeGirders with Debonded Strands

Continuity Issues

O.A. Abdalla, J.A. Ramirez, and R.H. Lee

i

:

:

,t>e%

PURDUE UNIVERSITY

Page 2: Strand Debonding in Pretensioned Beams
Page 3: Strand Debonding in Pretensioned Beams

JOINT HIGHWAY RESEARCH PROJECT

Part 1 Final Report

FHWA/INDOT/JHRP-92-24

Strand Debonding in Pretensioned Beams

- Precast Prestressed Concrete Bridge

Girders with Debonded Strands

Continuity Issues

OJi. Abdalla, JA. Ramirez, and R.H. Lee

Page 4: Strand Debonding in Pretensioned Beams

Digitized by the Internet Archive

in 2011 with funding from

LYRASIS members and Sloan Foundation; Indiana Department of Transportation

http://www.archive.org/details/stranddebondingiOOabda

Page 5: Strand Debonding in Pretensioned Beams

Purdue University

Ed)

School of Civil EngineeringFinal Report

Strand Debonding in Pretensioned Beams - Precast Prestressed Concrete Bridge

Girders with Debonded Strands.

Part 1, Continuity Issues

June 1, 1993

Proj.No. :C-36-56B

File No. : 7-4-28

To: Vincent P. Drnevich, Director

Attached is Part 1, of 2, Final Report of a research project entitled, "Strand Debonding in

Pretensioned Beams" By O.A. Abdalla, J. A. Ramirez, and R.H. Lee. The report considers

the comments of the advisory committee.

Respectfully submitted,

Julio A. Ramirezyand R.H. Lee, Co-Principal Investigators

cc: A. G. Altschaeffl

P. L. Bourdeau

M. D. BowmanM. J. Cassidy

L. M. Chang

S. Diamond

J. J. Dillon

W. L. Dolch

V. P. Drnevich

A. A. Fendrick

J. D. Flicker

K. R. Hoover

R. B. Jacko

L. S. Jones

R. H. Lee

C. W. Lovell

R. H. Lowry

D. W. Lucas

B. G. McCullouch

B. K. Partridge

J. A. Ramirez

G. F. Rorbakken

C. F. Scholer

G. B. Shoener

K. C. Sinha

D. L. Tolbert

R. Vancleave

C. A. Venable

T. D. White

L. E. WoodJ. R. Wright

t \CIVILE

ENGINEERINGPURDUEUNIVERSITY

1284 Civil Engineering Building • West Lafayette. IN 47907-1284

Page 6: Strand Debonding in Pretensioned Beams

TECHNICAL REPORT STANDARD TITLE PAGE

1. Report No.

FAWA/IND0T/JHRP-92

2. Government Accession No.

4. Title and Subtitle

Debonding in Pretensioned Beams-Precast

Prestressed Concrete Bridge Girders with Debonded

Strands- Part 1, Continuity Issues

,8. Performing Organ. lotion Report No.

FHWA/INDOT/JHRP-92

10. Worlr Unit No.

11. Contract or Grant No.

7. Author(j)

O.A. Abdalla, J. A. Ramirez, R.H. Lee

9. Performing Organization Name and Address

Joint Highway Research ProjectPurdue University1284 Civil Engineering Building

12. Sponsoring Agency Nome and Addres*

Indiana Department of TransportationState Office Building100 N. Senate Ave.

Indianapolis, IN 46204IS. Supplementary Note»

Conducted in cooperation with the U.S. Department of Transportation, Federal

Highway Administration, NCP H401A2362

3. Recipient' i Catolog No.

S. Report Date

Junft L 19936. Performing Organization Code

13. Type of Report and Period Covered

Final ReportExecutive SummaryT,,nP 1

,1 q«q-M a y 11 1QQ^

14. Sponsoring Agency Code

16. Abstroet

This report summarizes an experimental investigation carried out to evaluate

the effects of strand debonding on the behavior of precast pretensioned bridge

members made continuous with a cast-in-place slab and diaphragm. Shear and

flexural capacity were evaluated and the experimental results compared to the

results obtained using the PCA and CTL (proposed) analytical methods.

Four continuous specimens were fabricated and tested. Three specimens con-

sisted of Type-I AASHTO girders continuous with a cast-in-place slab and diaphragm

The fourth specimen consisted of Indiana Type CB-27 box girders also continuous

with cast-in-place slab and diaphragm.The effect of time-dependent creep and shrinkage deformations on the capacity

of the girders at the continuous supports was investigated in this study. Also

addressed in this report is the effect of limiting the stress at the extreme

compression fiber, near the continuous suppose, to allowable working stress

values on the load carrying capacity of continuous members.

17. Key Words

Flexural strength, shear strength,blanketed strands, continuous bridges,precast construction

19. Security Closslf. (of nSls report)

Unclassified

18. Distribution Statement

No restriction. This document is avail-able to the public through the NationalTechnical Information ServiceVirginia 22161

20. Security Classlf. (of this page)

Unclassified

21. No. of Pages 22. Price

Form DOT F 1700.7 (8-89)

Page 7: Strand Debonding in Pretensioned Beams

11-

ACKNOWLEDGEMENTS

Thanks are extended to the advisory committee members especially Mr. Scott

Herrin and Mr. Steve Toillion for their suggestions and helpful comments in finalizing

the report.

The prestressed concrete girders tested in this investigation were manufactured by

Hydro Conduit Corporation in Lafayette, Indiana. Their cooperation and contributions

in the instrumentation, manufacture and transportation of the beams are also

appreciated.

Sincere thanks are expressed to Karl Schmid and Chris Ogg who tested the first two

specimens. Thanks are extended to Russ Maurey, Doug Cleary and Hendy Hassan for

their help during the experimental phase of this project

Financial support was provided by the Federal Highway Administration and the

Indiana Department of Transportation through the Joint Highway Research Project,

School of Civil Engineering, Purdue University, West Lafayette, IN. Their cooperation

and encouragement are appreciated.

Page 8: Strand Debonding in Pretensioned Beams

Ill

TABLE OF CONTENTS

Page

LIST OF TABLESV1

LIST OF FIGURESvu

NOTATION xx

ABSTRACT xxm

CHAPTER 1 - INTRODUCTION .

l

CHAPTER 2 EXPERIMENTAL PROGRAM 3

2.1 Objective and Scope J

2.2 Description and Fabrication of Test Specimens •4

2.2.1 Precast Beams Construction and Instrumentation 4

2.2.2 Slab and Diaphragm Construction 6

2.3 Materials

2.3.1 Concrete...'

2.3.2 Prestressing Steel'

2.3.3 Non-Prestressed Reinforcement 8

2.4 Continuous Tests°

2.4.1 Specimen 1jjj

2.4.1.1 Cracking10

2.4.1.2 Deflectionsll

2.4. 1.3 Concrete Bottom Fiber Strains ll

2.4.1.4 Stirrup Strains12

2.4.1.5 Longitudinal Bar Strains 12

2.4. 1.6 Strand Strains13

2.4.2 Specimen 214

2.4.2.1 Cracking14

2.4.2.2 Deflections15

2.4.2.3 Concrete Bottom Fiber Strains 15

2.4.2.4 Stirrup Strains 15

2.4.2.5 Longitudinal Bar Strains 16

2.4.2.6 Strand Strains 16

Page 9: Strand Debonding in Pretensioned Beams

- IV

Page

2.4.3 Specimen 3 17

2.4.3.

1

Cracking 17

2.4.3.2 Deflections 18

2.4.3.3 Concrete Bottom Fiber Strains 18

2.4.3.4 Stirrup Strains..... 19

2.4.3.5 Longitudinal Bar Strains 19

2.4.3.6 Strand Strains 19

2.4.4 Specimen 4 21

2.4.4.1 Cracking.... 21

2.4.4.2 Deflections 22

2.4.4.3 Concrete Bottom Fiber Strains 22

2.4.4.4 Stirrup Strains 23

2.4.4.5 Longitudinal Bar Strains 23

2.4.4.6 Strand Strains 23

2.5 Summary 24

CHAPTER 3 - TIME-DEPENDENT EFFECTS ...26

3.1 PCA Method 26

3.2 CTL Method 28

3.3 Evaluation of Time-Dependent Effects 28

3.4 Summary 32

CHAPTER 4 - SUPERIMPOSED LOAD EFFECTS 33

4.1 Introduction 33

4.1.1 Effective Strand Stress 33

4.1.2 Continuity for Superimposed Load.............. ....34

4.1.3 Flexural Cracking..... 35

4. 1.4 Web-Shear Cracking 36

4.1.5 Flexure-Shear Cracking 40

4.1.6 Ultimate Shear Strength 43

4.1.7 Flexural Capacity of Negative Moment Region 45

4.1.8 Bottom Fiber Stress Evaluation 48

4.1.9 Summary 52

CHAPTER 5 - SUMMARY AND CONCLUSIONS 54

5.1 Summary 54

5.2 Conclusions 55

5.3 Future Work 58

LIST OF REFERENCES 59

Page 10: Strand Debonding in Pretensioned Beams

- V -

Page

APPENDICES

Appendix A - Time-Dependent Restraint Moments 62

Page 11: Strand Debonding in Pretensioned Beams

- VI

LIST OF TABLES

Table Page

4.1 Effective Strand Stress 47

4.2 Web-Shear Cracking Loads at Critical Section (H/2) 47

4.3 Web-Shear Cracking Loads at Initial Crack Location 48

4.4 Flexure-Shear Cracking Loads at Initial Crack Location 50

4.5 Flexure-Shear Cracking Loads at Critical Section 51

4.6 Flexure-Shear Cracking Loads at Critical Section

with a Reduced Number of Effective Strands 52

4.7 Shear Failure Loads 54

4.8 Development Length 56

4.9 Number of Effective Strands 58

4.10 Flexural Failure Loads 59

Page 12: Strand Debonding in Pretensioned Beams

vu -

LIST OF FIGURES

FigurePaSe

2.1 Development of Continuity with Precast Girders 67

2.2 Continuous Test Setup for Specimen 1 68

2.3 Continuous Test Setup for Specimen 2 69

2.4 Continuous Test Setup for Specimen 3 70

2.5 Continuous Test Setup for Specimen 4 • 7

1

2.6 Composite Girder Cross-section and Details (Specimen 1) 72

2.7 Composite Girder Cross-section and Details (Specimens 2 and 3) 73

2.8 Composite Girder Cross-section and Details (Specimen 4) 74

2.9 Strand Debonding Scheme and Instrumentation (Specimen 1) 75

2.10 Strand Debonding Scheme and Instrumentation (Specimen 2) 76

2.11 Strand Debonding Scheme and Instrumentation (Specimen 3) 77

2.12a Strand Debonding Scheme and Instrumentation

Beam with 0% Debonding (Specimen 4) 78

2.12b Strand Debonding Scheme and Instrumentation

Beam with 50% Debonding (Specimen 4) 79

2.13 Reinforcement Cage for Specimens 1, 2 and 3 .80

2. 14 Reinforcement Cage for Specimen 4

Prior to Placement of Voids 81

Page 13: Strand Debonding in Pretensioned Beams

VU1 -

Figure Page

2.15 Location of Stirrup Reinforcement and Instrumentation

(Specimen 1) 82

2. 16 Location of Stirrup Reinforcement and Instrumentation

(Specimen 2) 83

2.17 Location of Stirrup Reinforcement and Instrumentation

(Specimens 3 and 4) 84

2.18 Unshored Construction Method for I-beam Specimens 85

2.19 Unshored Construction Method for Box-girder Specimen 86

2.20 Deck Reinforcement Instrumentation for Specimen 1 87

2.21 Slab Longitudinal Steel Instrumentation for Specimens 2 and 3 .....88

2.22 Slab Longitudinal Reinforcement Instrumentation for Specimen 4 89

2.23 Variation of Uniaxial Compressive Strength of Concrete

with Age (Specimen 1) 90

2.24 Variation of Uniaxial Compressive Strength of Concrete

with Age (Specimen 2) 91

2.25 Variation of Uniaxial Compressive Strength of Concrete

with Age (Specimen 3) 92

2.26 Variation of Uniaxial Compressive Strength of Concrete

with Age (Specimen 4) 93

2.27 Measured Stress-Strain Behavior of Prestressing Strands (Specimen 1) 94

2.28 Measured Stress-Strain Behavior of Prestressing Strands

(Specimens 2 and 3) 95

2.29 Measured Stress-Strain Behavior of Prestressing Strands (Specimen 4) 96

2.30 Measured Stress-Strain Behavior of Mild Steel

#6 Bar, Grade 60 (Specimen 1).. 97

2.31 Measured Stress-Strain Behavior of Mild Steel

#6 Bar, Grade 60 (Specimens 2 and 3) 98

Page 14: Strand Debonding in Pretensioned Beams

- IX -

FigurePage

2.32 Measured Stress-Strain Behavior of Mild Steel

#6 Bar, Grade 60 (Specimen 4) "

2.33 Measured Stress-Strain Behavior of Mild Steel

#3 Bar, Grade 60 (Specimen 1) 10°

2.34 Measured Stress-Strain Behavior of Mild Steel

#3 Bar, Grade 60 (Specimens 2 and 3) 1Q 1

2.35 Measured Stress-Strain Behavior of Mild Steel

#3 Bar, Grade 60 (Specimen 4) 102

2.36 Loading System for Continuous Tests 103

2.37 Load Cells to Measure Applied Loads • 1Q3

2.38 Deck Cracking over Continuous Support at Completion of Tests

(Specimen 1)104

2.39 Deck Cracking over Continuous Support at Completion of Tests

Longitudinal View (Specimen 1) -104

2.40 Crack Pattern of 0% Debonded Beam at Completion of Continuous Tests

(Specimen 1)105

2.41 Crack Pattern of 50% Debonded Beam at Completion of Continuous Tests

(Specimen 1)105

2.42 Top View of Location of Dial Gages and LVDT's for Specimen 1 106

2.43 Load-Deflection Relationship, Initial Load Phase

Deflection Under Load P (Specimen 1) 107

2.44 Load-Deflection Relationship, Final Load Phase

Deflection Under Load P (Specimen 1) 108

2.45 Load-Deflection Relationship, Initial Load Phase

Midspan Deflection (Specimen 1) 109

2.46 Load-Deflection Relationship, Final Load Phase

Midspan Deflection (Specimen 1) HO

2.47 Location of Surface Strain Gages (Specimen 1) Ill

Page 15: Strand Debonding in Pretensioned Beams

X -

Figure Page

2.48 Compressive Strain at Continuous Support

Initial Load Phase (Specimen 1) 112

2.49 Compressive Strain at Continuous Support

Final Load Phase (Specimen 1) 113

2.50 Stirrup Strains at Continuous Support, Initial Load Phase

Beam with 50% Debonding (Specimen 1) 114

2.51 Stirrup Strains at Continuous Support, Final Load Phase

Beam with 50% Debonding (Specimen 1) 115

2.52 Stirrup Strains at Continuous Support, Initial Load Phase

Beam with0% Debonding (Specimen 1) 116

2.53 Stirrup Strains at Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 1) 117

2.54 Strain in Slab Longitudinal Steel at Centerline of Diaphragm

Initial Load Phase (Specimen 1) 118

2.55 Strain in Slab Longitudinal Steel at Centerline of Diaphragm

Final Load Phase (Specimen 1) ..119

2.56 Strand Strain at 44.5 in. from Continuous Support, Final Load Phase

Beam with 50% Debonding (Specimen 1) 120

2.57 Strand Strain at 65.5 in. from Continuous Support, Final Load Phase

Beam with 50% Debonding (Specimen 1) 121

2.58 Strand Strain at 86 in. from Continuous Support, Final Load Phase

Beam with 50% Debonding (Specimen 1) 122

2.59 Strand Strain at 39 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 1) 123

2.60 Strand Strain at 63 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 1) 124

2.61 Strand Strain at 84 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 1) 125

2.62 Flexure-Shear Crack at Second Debonding Point

Page 16: Strand Debonding in Pretensioned Beams

XI -

Figure Page

in 67% Debonded Beam (Specimen 2) .126

2.63 Crack Pattern at Continuous Support, Fully Bonded Beam(Specimen 2) 127

2.64 Crack Pattern at Continuous Support, 67% Debonded Beam(Specimen 2) 127

2.65 Top View of Location of Dial Gages, LVDT's and Surface Gages

(Specimens 2 and 3) 128

2.66 Load-Deflection Relationship, Initial Load Phase

Deflection Under Load P (Specimen 2) 129

2.67 Load-Deflection Relationship, Final Load Phase

Deflection Under Load P (Specimen 2) 130

2.68 Load-Deflection Relationship, Initial Load Phase

Midspan Deflection (Specimen 2) 131

2.69 Load-Deflection Relationship, Final Load Phase

Midspan Deflection (Specimen 2) 132

2.70 Top View of Location of Surface Gages at Continuous Support

(Specimens 2, 3 and 4) 133

2.71 Compressive Strain at Continuous Support

Initial Load Phase (Specimen 2) 134

2.72 Compressive Strain at Continuous Support

Final Load Phase (Specimen 2) 135

2.73 Stirrup Strains at Continuous Support, Initial Load Phase

Beam with 67% Debonding (Specimen 2) 136

2.74 Stirrup Strains at Continuous Support, Final Load Phase

Beam with 67% Debonding (Specimen 2) 137

2.75 Stirrup Strains at Continuous Support, Initial Load Phase

Beam with 0% Debonding (Specimen 2) 138

2.76 Stirrup Strains at Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 2) 139

Page 17: Strand Debonding in Pretensioned Beams

Xll

Figure Page

2.77 Strain in Slab Longitudinal Steel at Centerline of Diaphragm

Initial Load Phase (Specimen 2) 140

2.78 Strain in Slab Longitudinal Steel at Centerline of Diaphragm

Final Load Phase (Specimen 2).... 141

2.79 Strand Strain at 47 in. from Continuous Support, Final Load Phase

Beam with 67% Debonding (Specimen 2) 142

2.80 Strand Strain at 77 in. from Continuous Support, Final Load Phase

Beam with 67% Debonding (Specimen 2) 143

2.81 Strand Strain at 88 in. from Continuous Support, Final Load Phase

Beam with 67% Debonding (Specimen 2) 144

2.82 Strand Strain at 45 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 2).. 145

2.83 Strand Strain at 77 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 2) 146

2.84 Strand Strain at 89 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 2) 147

2.85 Beam With 83% Debonding at Completion of Initial Load Phase

(Specimen 3).... 148

2.86 Beam With 0% Debonding at Completion of Initial Load Phase

(Specimen 3) 148

2.87 Beam With 83% Debonding at Completion of Final Load Phase

(Specimen 3) 149

2.88 Beam With 0% Debonding at Completion of Final Load Phase

(Specimen 3) 149

2.89 Deck Cracking over Continuous Supports

at Completion of Initial Load Phase

(Specimen 3) 150

2.90 Deck Cracking over Continuous Supports

at Completion of Final Load Phase

(Specimen 3) 150

Page 18: Strand Debonding in Pretensioned Beams

- Xlll -

FigurePage

2.91 Load-Deflection Relationship, Initial Load Phase

Deflection Under Load P (Specimen 3) • 151

2.92 Load-Deflection Relationship, Final Load Phase

Deflection Under Load P (Specimen 3) 152

2.93 Load-Deflection Relationship, Initial Load Phase

Midspan Deflection (Specimen 3) 153

2.94 Load-Deflection Relationship, Final Load Phase

Midspan Deflection (Specimen 3) 154

2.95 Compressive Strain, 4 inches from Continuous Support

Initial Load Phase (Specimen 3) 155

2.96 Compressive Strain, 23 inches from Continuous Support

Final Load Phase (Specimen 3) • 156

2.97 Compressive Strain at Continuous Support

Final Load Phase (Specimen 3) 157

2.98 Stirrup Strains at Continuous Support, Initial Load Phase

Beam with 83% Debonding (Specimen 3) • 158

2.99 Stirrup Strains at Continuous Support, Final Load Phase

Beam with 83% Debonding (Specimen 3) 159

2.100 Stirrup Strains at Continuous Support, Initial Load Phase

Beam with 0% Debonding (Specimen 3) 160

2.101 Stirrup Strains at Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 3) 161

2.102 Strain in Slab Longitudinal Steel at Centerline of Diaphragm

Initial Load Phase (Specimen 3) 162

2.103 Strain in Slab Longitudinal Steel at Centerline of Diaphragm

Final Load Phase (Specimen 3) 163

2.104 Strand Strain at 84 in. from Continuous Support, Final Load Phase

Beam with 83% Debonding (Specimen 3) 164

2.105 Strand Strain at 42 in. from Continuous Support, Final Load Phase

Page 19: Strand Debonding in Pretensioned Beams

XIV

Figure Page

Beam with 0% Debonding (Specimen 3) 165

2.106 Strand Strain at 66 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 3)..... 166

2.107 Strand Strain at 84 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 3) 167

2.108 Beam With 50% Debonding at Completion of Initial Load Phase

(Specimen 4) 168

2.109 Beam With 50% Debonding at Completion of Final Load Phase

(Specimen 4) 169

2.1 10 Beam With 0% Debonding at Completion of Final Load Phase

(Specimen 4).... 170

2. 1 1

1

Deck Cracking over Continuous Supports

at Completion of Initial Load Phase

(Specimen 4) 171

2.1 12 Deck Cracking over Continuous Supports

at Completion of Final Load Phase

(Specimen 4) 172

2.1 13 Top View of Location of Dial Gages, LVDT's and Surface Gages

(Specimen 4) 173

2.1 14 Load-Deflection Relationship, Initial Load Phase

Deflection Under Load P (Specimen 4) 174

2.1 15 Load-Deflection Relationship, Final Load Phase

Deflection Under Load P (Specimen 4) 175

2.1 16 Load-Deflection Relationship, Initial Load Phase

Midspan Deflection (Specimen 4) 176

2.117 Load-Deflection Relationship, Final Load Phase

Midspan Deflection (Specimen 4) 177

2.1 18 Compressive Strain at Continuous Support

Initial Load Phase (Specimen 4) 178

Page 20: Strand Debonding in Pretensioned Beams

- XV

_. PageFigure

2.119 Compressive Strain at Continuous Support

Final Load Phase (Specimen 4).179

2. 120 Stirrup Strains at Continuous Support, Final Load Phase

Beam with 50% Debonding (Specimen 4)18U

2.121 Stirrup Strains at Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 4)181

2. 122 Strain in Slab Longitudinal Steel at Centerline of Diaphragm

Initial Load Phase (Specimen 4)182

2.123 Strain in Slab Longitudinal Steel at Centerline of Diaphragm

Final Load Phase (Specimen 4)183

2. 124 Strand Strain at 48 in. from Continuous Support, Final Load Phase

Beam with 50% Debonding (Specimen 4)184

2.125 Strand Strain at 60 in. from Continuous Support, Final Load Phase

Beam with 50% Debonding (Specimen 4)185

2.126 Strand Strain at the Point Load, Final Load Phase

Beam with 50% Debonding (Specimen 4)186

2.127 Strand Strain at 48 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 4)187

2.128 Strand Strain at 60 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 4)188

2.129 Strand Strain at the Point Load, Final Load Phase

Beam with 0% Debonding (Specimen 4) 189

3.1 Variation with Time of Support Restraint Moment

Considering Shrinkage Modification after 28 days

and Effects of Slab Top steel after 30 Days (Specimen 1) 190

3.2 Variation with Time of Support Restraint Moment

Considering Shrinkage Modification after 28 days

and Effects of Slab Top steel after 30 Days (Specimen 2) 191

3.3 Variation with Time of Support Restraint Moment

Considering Shrinkage Modification after 28 days

Page 21: Strand Debonding in Pretensioned Beams

XVI -

Figure Page

and Effects of Slab Top steel after 30 Days (Specimen 3) 192

3.4 Variation with Time of Support Restraint Moment

Considering Shrinkage Modification after 28 days

and Effects of Slab Top steel after 30 Days (Specimen 4)......... 193

3.5 Variation with Time of Support Restraint MomentConsidering Shrinkage Modification and

and Effects of Slab Top steel after 3 Days (Specimen 1) 194

3.6 Variation with Time of Support Restraint MomentConsidering Shrinkage Modification and

Effects of Slab Top steel after 3 Days (Specimen 2) 195

3.7 Variation with Time of Support Restraint Moment

Considering Shrinkage Modification and

Effects of Slab Top steel after 3 Days (Specimen 3) 196

3.8 Variation with Time of Support Restraint MomentConsidering Shrinkage Modification and

Effects of Slab Top steel after 3 Days (Specimen 4) 197

4.1 Beam Models used in the Analysis of I-beams 198

4.2 Analytical Models of Specimen 4 199

4.3 Variation of Continuity Moment due to Superimposed Load (P)

Initial Load Phase (Specimen 1) 200

4.4 Variation of Continuity Moment due to Superimposed Load (P)

Initial Load Phase (Specimen 2) 201

4.5 Variation of Continuity Moment due to Superimposed Load (P)

Initial Load Phase (Specimen 3) 202

4.6 Variation of Continuity Moment due to Superimposed Load (P)

Initial Load Phase (Specimen 4) 203

4.7 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 4 (Specimen 1) 204

4.8 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 6 (Specimen 1) 205

Page 22: Strand Debonding in Pretensioned Beams

xvu

Figure Page

4.9 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 8 (Specimen 1) 206

4.10 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 7 (Specimen 1) 207

4. 1

1

Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 4 (Specimen 2) 208

4.12 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 6 (Specimen 2) 209

4.13 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 8 (Specimen 2) 210

4. 14 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 7 (Specimen 2) 21

1

4.15 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 4 (Specimen 3) 212

4.16 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 6 (Specimen 3) 213

4.17 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 8 (Specimen 3) 214

4.18 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 7 (Specimen 3) 215

4.19 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 4 (Specimen 4) 216

4.20 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 6 (Specimen 4) 217

4.21 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 8 (Specimen 4) 218

4.22 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 7 (Specimen 4) 219

4.23 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Page 23: Strand Debonding in Pretensioned Beams

- XV1U -

Figure Page

Gage 4 Location (Specimen 1) 220

4.24 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 6 Location (Specimen 1) 221

4.25 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 8 Location (Specimen 1) 222

4.26 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 7 Location (Specimen 1) 223

4.27 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 4 Location (Specimen 2) 224

4.28 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 6 Location (Specimen 2) 225

4.29 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 8 Location (Specimen 2) 226

4.30 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 7 Location (Specimen 2) 227

4.3

1

Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 4 Location (Specimen 3) 228

4.32 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 6 Location (Specimen 3)..... 229

4.33 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 8 Location (Specimen 3) 230

4.34 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 7 Location (Specimen 3) 231

4.35 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 4 Location (Specimen 4) 232

4.36 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 6 Location (Specimen 4) 233

4.37 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 8 Location (Specimen 4) 234

Page 24: Strand Debonding in Pretensioned Beams

XIX

Figure Page

4.38 Compressive Stress Distribution at the Bottom of Girder, Final Load Phase

Gage 7 Location (Specimen 4) 235

Page 25: Strand Debonding in Pretensioned Beams

- XX -

NOTATIONS

Ac = cross sectional area of composite section

Aj = cross sectional area of deck slab

Ag

= cross sectional area of precast girder

Aps = total area of prestressing steel

Av = cross-sectional area of the stirrups

bw = web width of the girder

d = distance from the extreme compression fiber to the centroid of the

longitudinal tension reinforcement

e = base of the Naperian logarithms (2.7183)

Edi= modulus of elasticity of deck concrete at time tj

Ed = modulus of elasticity of deck concrete at 28 days

Eg

= modulus of elasticity of girder concrete

ec = distance between the top of the girder and the centroid of composite section

es= eccentricity of prestressing force from the centroid of composite section

fd= stress due to unfactored dead load, at extreme fiber of section where

tensile stresses are caused by externally applied loads

fr = modulus of rupture of concrete

fpc = compressive stress at the centroid of the composite section, or at the

junction of the web and flange when centroid lies within the flange,

due to both prestressing and the moment resisted by the precast member

Page 26: Strand Debonding in Pretensioned Beams

- XXI -

acting alone

fpe = compressive stress, due to prestressing, at extreme fiber of section where

tensile stresses are caused by externally applied loads

fpu= specified tensile strength of prestressing strands, psi

fpy

= specified yield strength of prestressing strands, psi

fy

= yield strength of nonprestressed reinforcement

fc= compressive strength of concrete

h = deck slab thickness

H = total depth of composite girder

I = moment of inertia of the composite section

Ict = cracked transformed moment of inertia of composite section

MCT= moment causing flexural cracking at section due to applied loads

Md= mid-span dead load moment

Mmax= maximum factored bending moment at section due to externally applied loads

Mp

= mid-span prestressing moment on composite section

Mr= restraint moment

M s= differential shrinkage moment

n = ratio of modulus of elasticity of slab concrete to the modulus

of elasticity of girder concrete

s = stirrup spacing

t = time in days

Vci= nominal shear strength provided by concrete when diagonal cracking

Page 27: Strand Debonding in Pretensioned Beams

- XX11 -

results from combined shear and moment

Vcw = nominal shear strength provided by concrete when diagonal cracking

results from excessive principal tensile stress in the web

Vd = shear force at section due to unfactored dead load

Vj = factored shear force at section due to externally applied loads

Vs= nominal shear strength provided by web reinforcement

y t= distance from the centroid of the section to extreme fiber in tension

AMsj= change in differential shrinkage moment at time step i

es= differential shrinkage strain

esdi = shrinkage strain in deck at time tj

esdu = deck concrete ultimate shrinkage strain

esgi= shrinkage strain in girder at time tj

£sgu = girder concrete ultimate shrinkage strain

Aesi= change in differential shrinkage strain at time step i

*¥ = change in creep coefficient

Page 28: Strand Debonding in Pretensioned Beams

xxm -

ABSTRACT

This report summarizes an experimental investigation carried out to evaluate the

effects of strand debonding on the behavior of precast pretensioned bridge members

made continuous with a cast-in-place slab and diaphragm. Shear and flexural capacity

were evaluated and the experimental results compared to the results obtained using the

analytical methods.

Four continuous specimens were fabricated and tested. Three specimens consisted

of Type-I AASHTO girders continuous with a cast-in-place slab and diaphragm. The

fourth specimen consisted of Indiana Type CB-27 box girders also continuous with

cast-in-place slab and diaphragm.

The effect of time-dependent creep and shrinkage deformations on the capacity of

the girders at the continuous supports was investigated in this study. Also addressed in

this report is the effect of limiting the stress at the extreme compression fiber, near the

continuous support to allowable working stress values on the load carrying capacity of

continuous members.

Page 29: Strand Debonding in Pretensioned Beams

-

1

CHAPTER 1

INTRODUCTION

The economical benefits that can be gained from the construction of bridges

composed of simple span precast prestressed I-beams made continuous with cast-in-

place concrete decks have made this type of construction a very popular one. The

determination of time-dependent and ultimate moments at the continuous support

presents a major difficulty in the design of this type of bridge structure. Several

methods have been proposed to estimate the restraint moments which will develop at

the continuous support. The method most commonly used to date was first published by

the Portland Cement Association in 1961 and extended in 1969 , since then, various

computer programs have been developed to further refine the analysis and design of this

type of structure (Sinno and Furr [1972], Tadros et al [1975], Suttikan [1978] and

Glikinetal[1987]).

Debonding of strands at end regions of pretensioned members is a technique which

is used extensively to control normal stresses in pretensioned members. By debonding

the strands, expensive draping hardware can be eliminated and labor costs can also be

reduced. However, the end regions of pretensioned beams with debonded strands at

interior supports of continuous multi-span bridges deserve further consideration.

Current AASHTO [1989] design specifications limit the stress in the extreme

compression fiber at interior girder ends to 0.6 fc . This requirement specifies

consideration of effects of prestressing and negative live load bending. This limitation

often results in additional debonding requirements. Debonding strands to meet the

stress requirement may be counterproductive and cause deleterious effect on the shear

Page 30: Strand Debonding in Pretensioned Beams

2-

strength.

Recent analytical studies (Oesterle et al [1989]) indicated that time-dependent

effects and construction timing can be of major influence on the effective continuity at

pier supports under vehicle loads. Herein, the PCA [1969] and the proposed

Construction Technology Laboratory [1989] analytical methods will be discussed and

their predicted level of continuity compared to the experimental results from four

prestressed precast two-span continuous beams with a composite concrete slab and

various amounts of debonding. The first three specimens consisted of Type-I AASHTO

girders made continuous with a 48 x 4 inch cast-in-place concrete slab and diaphragm.

The fourth specimen consisted of Indiana State Type CB-27 box girders made

continuous with a cast-in-place 36 x 4 inch composite slab and diaphragm.

The results from the continuous tests reported herein, will be used to evaluate the

normal stresses induced by prestressing with various debonding schemes, time-

dependent effects, as well as those caused by the applied superimposed load on the

composite structure in the region adjacent to the continuous supports of multi-span

bridges. In addition, the flexural and shear behavior of this type of structure at the

continuous support will be evaluated. This report is Part- 1 of a two part final report for

the research study "Behavior of Pretensioned Bridge Members with Debonded Strands".

Part two will include the results on the performance of simply supported pretensioned

bridge members with debonded strands.

Page 31: Strand Debonding in Pretensioned Beams

-3-

CHAPTER2

EXPERIMENTAL PROGRAM

2.1 Objective and Scope

The objectives of the tests conducted in this phase of the research study were to

evaluate, at continuous supports of pretensioned precast beams, (a) the combined

effects of time-dependent deformations; (b) the stress in the extreme compression fiber

at the ends of the girder due to prestressing and superimposed loads; and (c) the

ultimate capacity of precast prestressed bridges with debonded strands and a cast in

place composite concrete deck (see Figure 2.1). The test specimens are shown in

Figures (2.2-2.5). The specimen details are shown in Figures (2.6-2.8). The precast

beams were virtually identical except for the strand debonding scheme near the ends

(A-B) of the beams tested as shown in Figures (2.2-2.5). The prestressing strands of the

second beam (C-D) were always fully bonded throughout the entire length. The first

two specimens in this study were tested by Schmid [1991] and Ogg [1991].

All the continuous I-beam specimens consisted of two full scale Type-I AASHTO

girders made continuous with a cast-in-place slab and diaphragm. In Specimen 1

(Schmid [1991]) beam A-B had 6 strands (50%) debonded at each end as shown in

Figure (2.2). Specimen 2, tested by Ogg [1991], had 6 of the strands (50%) debonded

at end A, and 8 strands (67%) debonded at end B (see Figure 2.3). Beam A-B in

Specimen 3 had 8 of the strands (67%) blanketed at end A, while 10 of the strands were

blanketed (83%) at the continuous end B as shown in Figure (2.4). The precast beams

in Specimen 4 were Indiana State Type CB-27 box girders. Beam A-B in Specimen 4

Page 32: Strand Debonding in Pretensioned Beams

4-

had 50% debonding at the interior support B and at support A (see Figure 2.5).

The precast beams were made continuous by means of a cast-in-place slab and

diaphragm. The slab was reinforced with #6 bars in the longitudinal and transverse

directions. In addition, four strands from each girder were embeded into the diaphragm

following standard specifications of the Indiana Department of Transportation. The

continuous structure was tested under a static two-point load system.

The continuous test set-up was designed such that the continuous test would cause

appreciable damage only to the interior seven-feet of the beam adjacent to the

continuous support as shown in Figures (2.2-2.5). The outside seventeen feet towards

the simply supported end of the beam remained elastic and uncracked after the

completion of the continuous test. Upon completion of each of the continuous tests the

continuity between the two beams was broken and each undamaged portion of the

beams was further tested over a simply supported span.

2.2 Description and Fabrication of Test Specimens

2.2. 1 Precast Beams Construction and Instrumentation

The precast pretensioned beams were manufactured at the Hydro Conduit

Corporation plant in Lafayette, Indiana. The test beams were cast in pairs, each

individual beam being 308 inches long. The beams were cast in a single prestressing

bed.

The prestressing steel, in both girders, consisted of stress relieved (Specimen 1) and

Lo-Lax (Specimens 2, 3 and 4) Grade 270, uncoated seven-wire strands, 0.5 inch

Page 33: Strand Debonding in Pretensioned Beams

diameter. All the strands in the test beams were straight throughout the entire length.

Each strand was initially tensioned with a force of 2200 pounds (Specimen 1) and 3000

pounds (Specimens 2,3 and 4). Prestressing of the strands was performed from one end

only, each individual strand at a time. The surface condition of the strands was

considered as weathered.

After the initial stressing, electrical resistance strain gages were then affixed onto

the strands, at the desired locations. The strain gages were aligned along one helix of

the strand. The resulting strain in the prestressing steel, due to the initial pull force of

28,900 pounds (Specimens 1, 2 and 3) and 30,983 pounds (Specimen 4), was then

measured using an automated data acquisition system. Figures (2.9-2.12) show the

locations of the strand instrumentation for the test specimens.

The prestressing steel in the beam with debonded strands was then encapsulated to

the desired length using plastic tubing. Both ends of the tubes covering the strands were

taped shut to effectively isolate the strand from the concrete. The locations of the

debonding points for the test specimens are shown in Figures (2.2-2.5).

The shear reinforcement for all the specimens consisted of vertical stirrups made of

#3 Grade 60 bars, spaced at 4 inches on center over the entire length of the beams. The

stirrups were assembled in the form of a cage by tack welding them to the mild

reinforcement at the top of the precast beams as shown in Figures (2.13) and (2.14).

The stirrup instrumentation is shown in Figures (2.15-2.17).

The reinforcing cage was then placed in the casting bed, and all the stirrups were

tied to the strands using plastic ties. Lifting loops were provided at the ends of each

Page 34: Strand Debonding in Pretensioned Beams

beam. Concrete was then poured in a single layer and consolidated using portable

vibrators. After the forms of both beams were filled, the concrete was struck even with

the top of the steel forms and then roughened to a depth of 0.25 inch. Along with the

beams, thirty 6x12 inch cylinders and nine 6 x 6 x 22 inch flexural beams were also

cast and cured in the same conditions as the beams.

The prestressing force was transferred to the beams using the standard flame cutting

procedure. The prestressing strands were detensioned one strand at a time. After the

prestress release, the strain in the strands was recorded and the girders were then

removed from the prestressing bed and shipped to the laboratory. Upon arrival, the

beams were set on four supports in the testing area awaiting the casting of the deck slab

and diaphragm.

2.2.2 Slab and Diaphragm Construction

The formwork for the cast-in-place concrete deck slab and diaphragm was

constructed from lumber and plywood. The forms were then placed on the precast

beams so that the slab self-weight, together with the forms, was supported entirely by

the simply supported precast beams following unshored construction practice, (see

Figures 2.18-2.19). The forms for the continuity connection were tailored to the

diaphragm dimensions. The forms were sealed and oiled before placing the deck slab

reinforcing mat

The slab longitudinal reinforcing steel consisted of 8 #6 bars. The slab transverse

reinforcement, for Specimens 2, 3 and 4, consisted of #6 bars at 18 inches on centers

tied to the longitudinal steel with plastic ties. The deck slab in Specimen 1 had no

Page 35: Strand Debonding in Pretensioned Beams

7-

transverse reinforcement. The diaphragm was reinforced with a cage made of #3 bars

tied to the strands projecting from the ends of the precast beams. Three bars of the slab

longitudinal steel were instrumented using electrical resistance strain gages at five

locations along the specimens as shown in Figures (2.20), (2.21) and (2.22).

A batch of concrete was used for the cast-in-place slab and diaphragm. Compaction

was accomplished using portable vibrators. After the forms were filled, the surface of

the concrete was leveled using a lumber screed and finished with steel trowels. Thirty

6x12 inch concrete cylinders and nine 6 x 6 x 22 inch flexure beams were cast from the

same batch of concrete. The slab, the concrete cylinders and flexure beams were cured

in the laboratory. The forms were removed three days after the casting of the slab.

2.3 Materials

2.3.1 Concrete

The girders were cast using the standard 6000 psi concrete mix for pretensioned

bridge members in the State of Indiana. The concrete compressive strength was

monitored using the standard 6x12 test cylinders. The compressive strength of the

concrete used in the precast beams and the cast-in-place slab and diaphragm, for the

different test specimens, is shown in Figures (2.23-2.26).

2.3.2 Prestressing Steel

The prestressing steel, in both girders, consisted of stress relieved (Specimen 1) and

Lo-Lax (Specimens 2, 3 and 4) Grade 270, uncoated seven-wire strands, 0.5 inch

diameter (cross-sectional area of 0.153 in2

). The stress-strain behavior of the strand is

Page 36: Strand Debonding in Pretensioned Beams

-8

shown in Figures (2.27-2.29). Strains were measured by means of electrical resistance

strain gages attached to the strand as in the test beams. The yield stress, the ultimate

strength, and the modulus of elasticity of the strand were determined from these tests.

2.3.3 Non-Prestressed Reinforcement

Standard deformed Grade 60, #6 bars were used as the nonprestressed top

reinforcement in the precast beams and the deck slab reinforcing mat. The properties of

these bars were determined from tension tests. The stress-strain behavior of the #6 bars

is shown in Figures (2.30-2.32).

The stirrup reinforcement consisted of deformed Grade 60, #3 bars. The stress-

strain curve for the stirrup steel is shown in Figures (2.33-2.35).

2.4 Continuous Tests

The continuous tests arrangement is shown in Figures (2.2-2.5). The ends of the

beams were resting on four concrete blocks fixed to the laboratory floor by gypsum

grout. At the interior supports, each beam was resting on greased rollers placed between

two steel plates. One of the plates was grouted to the concrete block and the other was

attached to the bottom of the beam. The reactions at the outer ends of the beams were

transmitted to the concrete blocks supporting them, through load cells resting on steel

plates. The magnitude of the end reactions was monitored at different intervals as the

slab and diaphragm concrete reached the desired strength. This allowed the evaluation

of time-dependent effects related to creep due prestressing and differential shrinkage

between deck and girder concrete.

Page 37: Strand Debonding in Pretensioned Beams

-9

External loads were applied by hydraulic rams mounted on a vertical reaction frame

anchored to the laboratory floor. The loading system employed in this study is shown in

Figure (2.36). The applied loads were monitored using load cells resting on steel plates

grouted to the top surface of the slab as shown in Figure (2.37). Equal static loads were

applied, in small increments, at two symmetrical locations. After each increment, the

loads were kept constant, while careful observation of cracks was made. Applied loads,

end reactions, strains and vertical displacements were measured and recorded using an

automated data acquisition system.

Page 38: Strand Debonding in Pretensioned Beams

-10-

2.4.1 Specimen 1

The continuous beam test for Specimen 1 was conducted in three phases. In the

first phase, the applied load P was increased up to a load of 100 kips, then the specimen

was completely unloaded. This loading sequence will be referred to as the initial load

phase. In the second phase, the load P was increased by 10 kip increments up to 100

kips, then decreased in 10 kip steps to 50 kips. The load was then increased using 10

kip increments up to 100 kips to complete one cycle. This procedure was repeated twice

ending at 100 kips. The beam was completely unloaded in 10 kip steps. In the final

loading phase, the specimen was loaded up to 100 kips, then completely unloaded and

loaded back to 100 kips. This was followed by two cycles between 100 and 50 kips in

50 kip intervals. Upon completion of the second cycle back to 100 kips, the load was

increased up to a load of 140 kips. At this point the continuous test was concluded. This

last stage will be referred to as the final load phase. At each load increment, data was

recorded using an automated data acquisition system. The recorded data included strain

gage readings, applied loads, end reactions, and deflections. Deflections were

monitored with LVDT's along with manual readings of mechanical deflection gages.

During the final load phase, the loading frame swayed out of plane at a load of 140

kips, which was near the maximum capacity of the hydraulic rams. At this point it was

decided to end the test.

2.4.1.1 Cracking

Flexural cracking of the deck occurred at a load of 24 kips over the continuous

support. Web-shear cracking occurred near stirrup STIB1R for the 50% debonded

Page 39: Strand Debonding in Pretensioned Beams

-11

girder and near stirrup STTC1R for the fully bonded girder. Crack patterns of the deck

at the end of the final load phase are shown in Figures (2.38) and (2.39). Web-shear

cracking occurred in both girders at an applied load of 90 kips. The crack patterns for

the two beams were similar as shown in Figures (2.40) and (2.41). In the 50%

debonded girder, a flexure-shear crack originating from the bottom flange occurred near

the strand debonding point at a load of 140 kips. No flexure-shear cracks occurred in

the fully bonded girder.

2.4.1.2 Deflections

Deflections were measured on both sides of the beam at the centerline of each span

and under the applied load. Placement of the LVDT's and dial gages is shown in

Figure (2.42). Load-deflection curves for the initial and final phases of this test are

shown in Figures (2.43-2.46). Deflections for the fully bonded girder and the 50%

debonded girder are plotted on the same graph for comparison. As can be seen from

these figures, there is no significant difference in the load-deflection relationship for the

two girders up to a load of 140 kips. At the 140 kip load level, a flexure-shear crack

developed in the 50% debonded beam near the debonding point. This crack caused a

small increase in the deflection when compared to the 0% debonded beam.

2.4.1.3 Concrete Bottom Fiber Strains

Bottom fiber concrete strains were monitored using surface strain gages at the

bottom of the girder near the interior support. Location of these gages is shown in

Figure (2.47). Figures (2.48) and (2.49) show the concrete strain versus the applied load

for the initial and final load phases respectively. Surface gages 4 and 6 were located on

Page 40: Strand Debonding in Pretensioned Beams

12-

the 50% debonded beam, while gages 7 and 8 were on the fully bonded girder. These

gages were affixed on to the beam after continuity was established. Therefore, only

strains due to superimposed load P were recorded. This explains the similar results

obtained for both beams.

2.4.1.4 Stirrup Strains

Four stirrups were instrumented in each beam near the interior support (see Figure

2.15). The strain readings for the four stirrups in each beam are plotted on the same

graph for the initial and final load phases. Typical load versus strain curves are shown

in Figures (2.50-2.53). By analyzing Figures (2.50) and (2.52), the web-shear cracking

load of 90 kips in both beams is verified. From the figures it is apparent that higher

strains occurred in the web reinforcement of the 50% debonded girder. Stirrup IC4 in

the 0% debonded beam showed little increase in strain compared to stirrup IB4 in the

50% debonded beam; this reflects the greater extent of shear cracking in the debonded

girder.

2.4.1.5 Longitudinal Bar Strains

Three bars in the cast-in-place slab over the continuous supports were

instrumented to measure the strains in the reinforcing bars. Location of these gages is

shown in Figure (2.20). Load versus strain curves for the deck bars, at the centerline of

the diaphragm, are shown in Figures (2.54) and (2.55). Figure (2.54) is for the initial

load phase, while Figure (2.55) is for the final load phase. It can be seen that none of

these bars reached yield.

Page 41: Strand Debonding in Pretensioned Beams

-13-

2.4.1.6 Strand Strains

Typical strains in the prestressing strand are shown in Figures (2.56-2.58) for the

debonded beam and Figures (2.59-2.61) for the fully bonded beam. The instrumentation

scheme is shown in Figure (2.9). As expected, the strains in the strands showed no

significant change throughout the entire range of loading with the exception of the

strands on the beam with 50% debonding. A large sudden increase in strain was

indicated by the strain gages near the debonding point due to flexure-shear cracking as

shown in Figure (2.56)

Page 42: Strand Debonding in Pretensioned Beams

-14

2.4.2 Specimen 2

Specimen 2 was also loaded in three stages. In the initial stage, the continuous

beam was loaded in increments from zero load to 100 kips to induce cracking. The

second load phase consisted of three cycles of loadings between 50 and 100 kips. After

unloading, the final load stage starting at zero continued to 100 kips then back to 50

kips then to the maximum load of 162 kips. The test was terminated at the 162 kips load

level because the available loading system capacity was exhausted. A description of the

test results is presented next.

2.4.2.1 Cracking

The first crack appeared on the deck above the continuous support at a load of 25

kips. The first diagonal crack appeared at 70 kips in both the fully bonded and the 67%

debonded beams. These cracks appeared in the web near the ends of the girder at the

continuous support. Additional web-shear cracks formed as the load was increased to

100 kips. The subsequent cycles of load up to 100 kips caused no additional new

cracks, only growth of existing ones.

Subsequent loading up to 162 kips caused additional shear cracking to occur. The

increase in loading to 130 kips caused a flexure-shear crack to originate at the bottom

flange near the second debonding point at a distance of 77 inches from the centerline of

the interior support (see Figure 2.62). The fully bonded beam never displayed any

positive moment flexure-shear cracks. Figures (2.63-2.64) illustrate the crack patterns

at the continuous support.

Page 43: Strand Debonding in Pretensioned Beams

15

2.4.2.2 Deflections

Figure (2.65) shows the location of the LVDT's and the dial gages used to measure

the vertical deflection. The load-deflection behavior of the continuous structure is

illustrated in Figures (2.66-2.69). The fully bonded beam deflected less than the

debonded beam. The fully bonded girder has a relatively linear load-deflection

relationship up to 162 kips. The debonded girder displayed the same type of behavior

up to 125 kips. After 125 kips, larger deflections were observed at smaller load

increments for the debonded beam. The 125 kip load level corresponds to the load level

just prior to the first visible sign of a flexure-shear crack in the debonded girder.

2.4.2.3 Concrete Bottom Fiber Strains

The location of the surface strain gages used to measure the compressive strains at

the continuous supports is shown in Figure (2.70). The bottom fiber strains of the

precast sections are shown in Figures (2.71-2.72). The gages were placed on the girders

24 days prior to the casting of the slab. The measured strains are due to the applied

superimposed load, the added weight of the unshored deck, and shrinkage and creep

effects between the deck and precast sections. These readings do not reflect the effect of

the initial prestressing.

2.4.2.4 Stirrup Strains

Figures (2.73-2.76) show the load stirrup-strain relationships. Figure (2.16) shows

the location of the instrumented stirrups for Specimen 2. None of the stirrups yielded

during this tesL Overall, the 67% debonded beam initially displayed larger stirrup

Page 44: Strand Debonding in Pretensioned Beams

16-

strains than the fully bonded beam. Also due to flexure-shear cracking the stirrup into

the span (IB4) showed significandy large strains in the debonded beam.

2.4.2.5 Longitudinal Bar Strains

The negative moment reinforcement in the top slab over the continuous support

consisted of 8 # 6 bars. The load-strain relationship is illustrated in Figures (2.77-2.78)

and the location of the strain gages is shown in Figure (2.21). None of the instrumented

bars yielded during the test.

2.4.2.6 Strand Strains

Figures (2.79-2.84) show some typical strain readings from both the debonded and

fully bonded beams during the final load phase. Figure (2.10) shows the locations of the

strand strain gages for Specimen 2. The debonded girder showed linear load-strain

relationship up to the 130 kips load level. The 130 kips load level corresponds to the

first flexure-shear crack in the debonded beam (see Figure 2.62). Sudden increase in

the strain can be seen when the flexure-shear crack occurred.

As expected, the fully bonded beam displayed linear load-strain relationship

throughout the test. The gages located near the applied load typically indicated greater

strain increases.

Page 45: Strand Debonding in Pretensioned Beams

- 17

2.4.3 Specimen 3

The continuous test for Specimen 3 was conducted in three phases. In the initial

phase the load was increased up to 100 kips. In the second phase the structure was

unloaded to 50 kips. The load was then increased to 100 kips and unloaded to 50 kips.

This was followed by another cycle between 50 kips and 100 kips. The specimen was

then completely unloaded. In the final loading phase the beam was loaded

incrementally up to a maximum load of 164 kips.

2.4.3.1 Cracking

The first flexural crack was noticed on the deck slab over the interior supports at a

load of 25 kips. The first inclined crack in the web was observed in the beam with 83%

debonding near the interior support at a load of 70 kips. Additional cracks formed in the

web as the load was increased to 90 kips. These cracks were parallel to the first inclined

shear crack. Figure (2.85) shows the end IB of the beam with 83% debonding after the

completion of the first test.

The first inclined crack in the beam with 0% debonding developed at a load of 77

kips near the continuous support. No new cracks were observed in this beam until a

load of 97 kips was reached, at which time three parallel inclined cracks formed in the

web. The end IC of the beam with 0% debonding after the initial loading phase is

shown in Figure (2.86).

A flexure-shear crack formed in the beam with 83% debonding at a load of 91 kips.

This crack originated as a flexural crack at the second debonding point, a distance of 66

Page 46: Strand Debonding in Pretensioned Beams

-18

inches from the center line of the interior support (see Figure 2.87).

In the second and in the final load phase, additional inclined cracks formed in the

web of both beams near the continuous support. These cracks were parallel to the

cracks from the first phase. The interior region of the continuous beam at the end of the

final load phase is shown in Figures (2.87) and (2.88). The cracking patterns of the slab

over the continuous support after the completion of the initial and final load phases of

the test are shown in Figures (2.89) and (2.90) respectively.

2.4.3.2 Deflections

The vertical deflection under the point loads and at the mid-span of each beam,

was measured using linear variable differential transformers (LVDT's), and mechanical

dial gages as shown in Figure (2.65). The load-deflection behavior of the continuous

beam at the point of application of the superimposed load and at midspan of each beam

is shown in Figures (2.91-2.92) and Figures (2.93-2.94) respectively. The curves show

that the behavior of the two beams is similar in every respect up to the initiation of the

flexure-shear cracking. The reduction in the stiffness upon flexure-shear cracking of the

beam with 83% debonding is clearly indicated in these figures.

2.4.3.3 Concrete Bottom Strains

The concrete strains were measured using surface gages placed at the bottom of

the precast beams near the continuity connection as shown in Figure (2.70). Three

gages were affixed on both sides of each girder. The measured strains were due to

creep and shrinkage and the superimposed load. Strains due to the prestressing force

Page 47: Strand Debonding in Pretensioned Beams

-19

were not included in these readings. The relationship between the applied load and the

concrete strains near the continuous support is presented in Figures (2.95) and (2.96).

Large changes in strain were shown in the strain near the continuous support when

web-shear cracking occurred as shown in Figure (2.95). Away from the support the

debonded beam showed larger strains when the flexure-shear crack opened as indicated

in Figure (2.96). Figure (2.97) shows the measured bottom fiber strains for the final

load phase.

2.4.3.4 Stirrup Strains

The instrumented stirrups near ends IC and IB are shown in Figure (2.17). Typical

load versus measured strain behavior is shown in Figures (2.98-2.101). All stirrups

showed no significant strain until they were crossed by inclined cracks. However, none

of the stirrups reached its yielding point. The increase in strain at web-shear cracking is

clearly indicated in these figures.

2.4.3.5 Longitudinal Bar Strains

The longitudinal reinforcement in the deck slab was instrumented as shown in

Figure (2.21). The applied load versus strain curves for the longitudinal steel in the slab

at the continuous supports are shown in Figures (2.102) and (2.103). The resulting

strain was approaching the yield value of these bars.

2.4.3.6 Strand Strains

The measured strains in the prestressing strand (see Figure 2.11) near the

continuous supports during the final load phase are shown in Figures (2. 104-2. 107).

Page 48: Strand Debonding in Pretensioned Beams

-20

Sudden increase in the strain occurred in the beam with 83% debonding near the point

load at 134 kips. This increase in strain was due to a flexure-shear crack that opened

near the third debonding point a distance of 84 inches from the centerline of the interior

support However, the resulting stress did not reach the yielding strength of the strand.

In the beam with 0% debonding, the strains varied linearly with the applied load as

shown in Figures (2.105-2.107).

Page 49: Strand Debonding in Pretensioned Beams

21

2.4.4 Specimen 4

Specimen 4 was tested under a loading sequence similar to that of Specimens 2 and

3. In the initial phase the load was increased up to 100 kips. In the second loading phase

the structure was unloaded to 50 kips. The load was then increased to 100 kips and next

unloaded to 50 kips. This was followed by another cycle between 50 kips and 100 kips.

The specimen was then completely unloaded. In the final loading phase the continuous

box girder was loaded incrementally up to a maximum load of 176 kips.

2.4.4.1 Cracking

The first fiexural crack occurred on the top of the deck slab over the centerline of

interior support diaphragm at a load of 27.5 kips. The first inclined shear crack was

observed in the beam with 50% debonding near the interior support at a load of 94.5

kips. This inclined crack appeared on one side of the beam. No additional cracks

formed in the initial loading phase. A web-shear crack occurred on the 50% debonding

side during the final loading phase at a load of 1 18 kips. The crack patterns of the beam

with 50% debonding near the continuous support at the end of the initial and final load

phases are shown in Figures (2.108-2.109).

The first inclined shear crack in the beam with 0% debonding developed at a load of

136 kips on one side of the beam only. On the opposite side of the beam the first

inclined shear crack did not occur until a load of 150 kips.

Additional inclined cracks formed in the webs of both beams near the continuous

support when the load was increased to the maximum level of 176 kips. The crack

Page 50: Strand Debonding in Pretensioned Beams

22

pattern of the beam with 0% debonding at the continuous end during the initial and the

final loading phases is shown in Figure (2.110). The cracking patterns of the slab over

the continuous support after the completion of the first and the second phases of the test

are shown in Figures (2.111) and (2.112) respectively. It can be seen that, in both

girders, no flexure-shear cracks formed under this loading.

2.4.4.2 Deflections

The vertical deflection under the point loads and at mid-span of each beam, was

measured using LVDT's on one side of the beam, and mechanical dial gages on the

other side as shown in Figure (2.113). The load-deflection behavior of the continuous

beam measured at the points of application of the superimposed load is shown in

Figures (2.114-2.115). The deflection at midspan of bothbeams is given in Figures

(2.116-2.117). The curves show that, up to a load of 176 kips the behavior of the two

beams is similar in spite of the difference in the amount of debonding. This can be

explained by the absence of flexure-shear cracking in the positive moment region of the

continuous beam.

2.4.4.3 Concrete Bottom Strains

The location of the strain gages used to measure the concrete strains at the bottom

fibers of the precast beams near the continuity connection is shown in Figure (2.70).

These gages registered strains due to the time-dependent deformations in addition to the

effect of the superimposed load. The concrete strains due to prestressing were not

recorded. The relationship between the applied load and the concrete strains near the

continuous support is presented in Figures (2. 1 1 8) and (2. 1 19).

Page 51: Strand Debonding in Pretensioned Beams

23-

2.4.4.4 Stirrup Strains

The instrumented stirrups near ends IC and IB are shown in Figure (2.17). Typical

load versus measured strain in the stirrups during the final loading phase is plotted in

Figures (2.120) and (2.121). The initial loading phase caused no significant strain in the

stirrups. The beam with 50% debonding showed higher strains in the final load phase.

However no yielding was observed in the stirrup reinforcement.

2.4.4.5 Longitudinal Bar Strains

The longitudinal reinforcement in the deck slab was instrumented as shown in

Figure (2.22). The applied load versus strain curves for the longitudinal steel in the slab

at the continuous supports are shown in Figures (2.122) and (2.123). Since, none of

these bars reached its yielding strength it can be concluded that the ultimate capacity of

the continuity connection was not reached in this test.

2.4.4.6 Strand Strains

Figures (2.124-2.129) show the relationship between the applied load and the strains

in the strand at different locations near the interior support and under the point load.

Linear increase in the strand strains with the applied load was shown by these gages.

No substantial increase in strains were recorded. This is explained by the absence of

flexure-shear cracking.

Page 52: Strand Debonding in Pretensioned Beams

24-

2.5 Summary

This chapter contains the description, fabrication and testing of the specimens in

this study. The behavior of continuous-composite precast prestressed bridges with

debonded strands and a cast-in-place composite slab was examined. The continuous

structures were tested under the effect of monotonic concentrated loads applied at two

symmetrical locations.

Crack patterns, load-deflection curves, stirrup strains, strand strains, longitudinal bar

strains and the concrete bottom fiber strains near the continuous supports are presented

in this chapter for all the specimens. The load-deflection curves showed that the

behavior of the beams with debonded strands is similar to the behavior of the fully

bonded beams up to the initiation of flexure-shear cracking. After flexure-shear

cracking the debonded beams showed larger deflections. The strains at the extreme

compression fiber near the continuous supports also indicated the same behavior with

considerable increase upon flexure-shear cracking.

The debonded beams showed larger stirrup tensile strains. Also higher strains were

induced in the prestressing strand of the debonded beams when flexure-shear cracking

occurred.

Chapter 3 will deal with the evaluation of the effect of creep and shrinkage at the

continuous supports. The time-dependent restraint moments obtained from the test will

be compared to the predicted values using the PCA and CTL methods.

In chapter 4, a comparison of the experimental results of the superimposed load

Page 53: Strand Debonding in Pretensioned Beams

-25-

tests with the theoretical analysis based on the PCA and CTL methods, will be

presented. The flexural as well as the shear capacity near the continuous supports will

be evaluated and discussed.

Chapter 5 contains a summary of this phase of the research, the conclusions drawn

from the test data and future research needs with respect to the use of strand debonding

in continuous pretensioned bridge members.

Page 54: Strand Debonding in Pretensioned Beams

-26-

CHAPTER3

TIME-DEPENDENT EFFECTS

3.1 PCA Method

In a pretensioned bridge girder, prestress will usually cause the member to camber.

If the member is simply supported, the ends will tend to rotate. When members are

made continuous, their ends are restrained from any further rotation due to creep

deformations resulting from the prestressing. As a result a positive restraint moment

may occur at the pier (positive moment produces tension in the bottom of the girder ).

Furthermore, in this type of composite construction, the slab is cast some time after the

girders. The subsequent shrinkage of the girders will be less than that of the slab. The

rotation caused by the moment resulting from the differential shrinkage strain, and

creep effects due to dead load would produce a negative restraint moment at the

continuous supports. The final restraint moment is the sum of the previously mentioned

effects.

The Portland Cement Association conducted experimental and analytical research

to determine the long term-effects of creep and shrinkage at the continuous support of a

two-span beam (see Mattock [1961]). This investigation was extended later by

Freyermuth in 1969, for the design of multi-span continuous highway bridges. This

work also offers guidelines for the design of the continuity connection between adjacent

girders. The 1969 PCA method proposed by Freyermuth is used in current INDOT

design practice for predicting the restraint moments at the interior supports of precast

pretensioned girders.

Page 55: Strand Debonding in Pretensioned Beams

-27

As suggested by Mattock [1961] and Freyermuth [1969] the differential shrinkage

moment at any time is given by:

M,=€IEdAd (ec+-|) (3.1)

es= differential shrinkage strain (assumed uniform over the

thickness of the slab)

Ed = modulus of elasticity of deck concrete

A<j = cross-sectional area of deck slab

(ec+— ) = distance between middepth of deck slab and centroid of the

composite section.

h = slab thickness

ec = distance between the top of the girder and the centroid of

composite section

The final restraint moment, Mr , at the interior support of a two-span continuous

beam is given by:

Mr=(| Mp-Md ) (1- e"*) - | Ms

i^|— (3.2)

Where

Mp= moment caused by the prestressing force about the centroid of the

composite section.

Md = mid-span moment due to dead load.

*P = increase in creep coefficient after continuity was created,

e = base of the Naperian logarithms (2.7 1 83)

Page 56: Strand Debonding in Pretensioned Beams

28-

3.2 CTL Method

The Construction Technology Laboratory method developed by Oesterle, Glikin

and Larson [1989], for the analysis of precast prestressed beams made continuous,

incorporates the effect of the stiffness and length of the connection between the precast

girders at the continuous supports. Also, the calculation of the shrinkage restraint

moment component accounts for the compatibility between the girders and the deck

when shrinkage occurs. This procedure is a modified version of the original PCA

method. The computer program BR1DGERM was developed at CTL to calculate the

time dependent restraint moments. Different time dependent functions were presented

for girder concrete creep, deck concrete shrinkage and girder concrete shrinkage. These

functions were suggested by ACI Committee 209 [1982].

The analysis in BRIDGERM is conducted by superimposing the restraint moment

increments calculated over a series of time intervals. For each time step, the three

components of change in restraint moments, differential shrinkage, dead load creep, and

prestress creep, are calculated using the rate of creep method. The calculated increment

of restraint moment is then added to the sum from the preceding time step to determine

the restraint moment at the end of an interval.

3.3 Evaluation of Time-Dependent Effects

The evaluation of the predicted restraint moment at continuous supports due to

creep and shrinkage deformations by the 1969 PCA method proposed by Freyermuth,

and the recendy developed CTL approach , was conducted using the results from the

experimental program previously described. The restraint moments, determined from

Page 57: Strand Debonding in Pretensioned Beams

29-

the experimental program, were calculated using the end reaction measurements at

supports A and D shown in Figures (2.2-2.5). The end support reactions were measured

at suitable intervals after the deck and diaphragm were cast. The changes with time in

the reaction values, due to differential shrinkage and creep effects, were used to

calculate the restraint moments at the interior support up to the time of application of

the concentrated superimposed loads.

In the case of a symmetric two-span continuous girder, the restraint moments at the

interior support are directly proportional to the change in the reaction at the end

support. A decrease in the end support reaction corresponds to a negative restraint

moment at the interior support, on the other hand, an increase in the reaction indicates a

positive restraint moment The measured end reactions and the resultant restraint

moments due to the measured end reactions are presented in Tables (A.l) through

(A.4).

The predicted interior support restraint moments using the CTL and the 1969 PCA

methods are shown in Figures (3.1-3.4) together with the experimental values. The

vertical axis represents the value of the restraint moment at the interior support. The

horizontal axis starts with the age of the girder corresponding to casting of the slab up

to the first application of the superimposed load P. It can be seen from Figures (3.2)

and (3.4) that the results obtained using the PCA method are in close agreement with

the test results for early ages of beam at the time continuity is established.

The CTL method values were calculated using the Equations (3.3) and (3.4) given

below, for the increment of differential shrinkage restraint moment: (Equation (3.3) is

Page 58: Strand Debonding in Pretensioned Beams

-30-

used when the deck slab age is less than 28 days, and after 28 days Equation (3.4) is

used)

AMsi^AEgiEflAd (ec+—

)

(3.3)

8A£ si = (£sdi-£sdi-l)

-(esgi

_esgi-l)

£sdi= shrinkage strain in deck at time tj

esgi= shrinkage strain in girder at time ti

Edi = modulus of elasticity of deck concrete at time t;

Ad = cross-sectional area of deck slab

(ecH— ) = distance between middepth of deck slab and centroid of the

composite section

h = slab thickness

ec= distance between the top of the girder and the centroid of

the composite section

and,

... A£slEdl Ad h, ,_ .,AM S1

= ——— (ec+-) (3.4)E^Ad 2

1+E

gA

g

where:

Ag= cross secdonal area of precast girder

Eg= modulus of elasdcity of girder concrete

This modification is not available in the PCA method. At the end of the evaluation

Page 59: Strand Debonding in Pretensioned Beams

31-

time, deck slab age was 44 days for specimen 1, 38 days for specimen 2, 22 days for

specimen 3, and 34 days for specimen 4.

Further improvement of the CTL method was achieved by using the formula

suggested by Dischinger (see Oesterle [1989]), to account for the restraining action

against deck shrinkage of the reinforcement in the deck slab. The estimate of the

restraining moments obtained using the CTL method with the Dischinger modification

starting 3 days after continuity was established and the PCA method values are

compared with the test results in Figures (3.5), (3.6), (3.7) and (3.8). With this

modification the CTL predicted restraint moments showed better agreement with the

experimental results for both young and old girder ages at the time continuity was

established.

Figure (3.4) indicates that positive restraint moment due to creep and shrinkage

deformations developed at the continuous supports of Specimen 4. It is deemed that the

larger amount of prestressing acting in the precast box girders caused higher positive

restraint moments at the interior supports. The box girders were prestressed by 20

strands, whereas the I-beams were prestressed by 12 strands. The larger effect of creep

deformations under the prestressing force was reflected by the positive restraint

moment. Furthermore, the cross-sectionai area of the deck slab in the box specimen is

less than that in the I-beams. Consequendy, the shrinkage restraint moment, which

counteracts the positive moment due to creep under prestressing, was less in the box

beams. It can be concluded that positive moment reinforcement could be needed in the

cast-in-place diaphragm if tensile stresses exceed the concrete cracking capacity. It

Page 60: Strand Debonding in Pretensioned Beams

32-

raust be noted that the girder age at the time continuity was established was a lot

higher for the I-beam specimens than for the box beam specimen. This allowed for

larger shrinkage induced restraint moments in the I-beam specimens.

3.4 Summary

The time-dependent restraint moments, determined using the end reaction

measurements were compared to the results obtained using the PCA and CTL methods.

The comparison showed that the restraint moments calculated using the PCA method

were in good agreement with the measured values when continuity was established at

early ages of the precast girders. The CTL method showed improved agreement with

the test results when the restraint of the slab reinforcing steel was accounted for at an

earlier age of continuity. In this case, the CTL method had a better agreement with test

results in the instances where continuity was established at later ages of the precast

girders.

In the next chapter the analysis of the results obtained from testing the continuous

members under the effect of the superimposed load will be presented. Summary,

conclusions and future work are presented in chapter 5.

Page 61: Strand Debonding in Pretensioned Beams

-33

CHAPTER 4

SUPERIMPOSED LOAD EFFECTS

4.1 Introduction

The superimposed load test results obtained in this study are compared to the

theoretical values predicted using the PCA and CTL methods. The PCA method

assumes full structural continuity for the calculation of the restraint moments due to

superimposed loads. The beam support in the diaphragm region is assumed to be a

knife edge support. The CTL method on the other hand considers the finite length and

stiffness of the diaphragm between the precast girders. Figure (4.1) shows the two

different interior connection models used in this study for the I-beam specimens. With

the CTL method, one model employs an uncracked section of the composite girder and

the other a cracked section. Figure (4.2) shows the interior connection modeling used to

analyze the results of Specimen 4 (box-beam specimen). The composite beam cross-

section was used in the analysis for both types of specimens.

4.1.1 Effective Strand Stress

Strains in the prestressing strands were measured by electrical resistance strain

gages. The measured strain was converted to stress by multiplying it by the modulus of

elasticity of the prestressing strand. Table (4.1) gives the effective strand stress at the

time of application of the superimposed load. These values were used in all the

calculations performed in this investigation.

Page 62: Strand Debonding in Pretensioned Beams

34

Table (4.1)

Effective Strand Stress

Specimen No. BeamEffective Strand Stress

(ksi)

1 50% Debonded 133.7

Fully Bonded 126.1

2 67% Debonded 153.7

Fully Bonded 140.7

3 83% Debonded 164.0

Fully Bonded 160.0

4 50% Debonded 164.1

Fully Bonded 161.1

4.1.2 Continuity for Superimposed Loads

The behavior of precast girders made continuous with a cast-in-place diaphragm

and slab was examined by studying the variation of the continuity moment developed

at the interior support due to the superimposed load P. The moment at the interior

support was calculated based on the end reaction measurements due to the applied load

during the first phase of loading. A comparison between the predicted values, by

linear-elastic analysis for the negative moment at the interior support using a rigid

connection assumption (current approach) and a flexible connection (CTL Method),

with the measured experimental values is shown in Figures (4.3-4.6). It can be seen

that prior to the observed cracking of the diaphragm region, the predicted continuity

moment from the rigid connection approach (PCA), the CTL approach, and the

measured values are in reasonable agreement.

Page 63: Strand Debonding in Pretensioned Beams

-35-

After cracking, the PCA method (rigid connection) considerably overestimates the

moment at the interior support. With the flexible connection approach (CTL), the

calculated values after diaphragm region cracking are obtained using the cracked

transformed section of the composite girder and modifying the stiffness of the short

span between girder ends (flexible connection). As can be seen from Figures (4.3-4.6),

this modification results in an improved conservative estimate of the experimentally

determined values.

4.1.3 Flexural Cracking

The predicted continuity moment required to produce flexural cracking in the

diaphragm region was calculated using the following equation:

MCT=— (4.1)ny

t

where:

M CT= moment causing flexural cracking at section due to applied loads

fr = modulus of rupture of deck slab concrete

fr =7.5a/F7

I = moment of inertia of the composite section

y t= distance from the centroid of the section to the extreme fiber in tension

n = ratio of modulus of elasticity of slab concrete to the modulus

of elasticity of girders concrete

The predicted flexural cracking loads according to the PCA and CTL methods are

compared to the observed cracking loads in Table (4.2). The effects of creep and

Page 64: Strand Debonding in Pretensioned Beams

36

shrinkage were included in this analysis.

Table (4.2)

Flexural Cracking Loads

Specimen No. ModelPredicted Load

(kips)

Observed Load

(kips)

obs/pred

1 PCA 35 24 0.69

CTL 44 24 0.55

2 PCA 38 25 0.66

CTL 43 25 0.58

3 PCA 36 25 0.69

CTL 41 25 0.61

4 PCA 60 27.5 0.46

CTL 69 27.5 0.40

It can be seen that both methods overestimated the flexural cracking load in the

diaphragm region. The PCA method gives slightly closer values to the test results,

since higher negative bending moments are obtained by this method at the interior

supports.

4.1.4 Web-Shear Cracking

After further cracking of the deck had occurred, the next stage of cracking observed

in the continuous members was inclined shear cracking near the continuous support.

Web-shear cracks are diagonal cracks that form in the web near the centroid of the

member. The critical section for web-shear cracking was taken as H/2 away from the

face of the interior support (H is the total depth of the composite beam). The ACI

[1989]/AASHTO [1989] web-shear cracking capacity is determined as follows:

Page 65: Strand Debonding in Pretensioned Beams

37-

Vcw= (3.5 Vf% + 0.3 fpc ) bw d (4.2)

where:

Vcw =nominal shear strength provided by concrete when diagonal cracking results

from excessive principal tensile stress in the web

fc = compressive strength of concrete

fpc = compressive stress (after allowance for prestress losses) at the centroid

of the composite section, or at the junction of the web and flange when centroid

lies within the flange, due to both prestressing and the moment resisted

by the precast member acting alone

bw = web width of the girder

d = distance from the extreme compression fiber to the centroid of the longitudinal

tension reinforcement

Using the calculated value of Vcw , the superimposed load required to produce web-

shear cracking was found by conventional linear-elastic analysis using the analytical

models specified by PCA and CTL methods (see Figures 4.1 and 4.2). Tables 4.3 and

4.4 present the results of the web-shear cracking analysis, and give a comparison of the

web-shear cracking loads for the beams with debonded strands and the fully bonded

beams. Table (4.3) gives the web-shear cracking loads at the critical section, H/2 away

from the continuous support. Table (4.4) gives the web-shear cracking loads based on

the web-shear cracking capacity at the locations where these cracks observed. The two

methods used in the analysis underestimated the web-shear cracking capacity of both

the debonded and fully bonded I-beams. However, these methods overestimated the

web-shear cracking loads for the continuous box girder. The better agreement for the

I-beam specimens was obtained, as expected, using the cracked section for the

diaphragm region. This was not the case for the box beam specimen.

Page 66: Strand Debonding in Pretensioned Beams

38

Table (4.3)

Web-Shear Cracking Loads at Critical Section (H/2)

Predicted Load Observed Load obs/predSpecimen No. Beam

(kips) (kips)

1 50% Debonded

PCA 57 90 1.58

CTL-UC 56 90 1.61

CTL-CR 59 90 1.53

Fully Bonded

PCA 68 90 1.32

CTL-UC 67 90 1.34

CTL-CR 71 90 1.27

2 67% Debonded

PCA 54 70 1.30

CTL-UC 54 70 1.30

CTL-CR 56 70 1.25

Fully Bonded

PCA 63 70 1.11

CTL-UC 63 70 1.11

CTL-CR 66 70 1.06

3 83% Debonded

PCA 49 70 1.43

CTL-UC 49 70 1.43

CTL-CR 51 70 1.37

Fully Bonded

PCA 66 77 1.17

CTL-UC 66 77 1.17

CTL-CR 68 77 1.13

4 50% Debonded

PCA 116 94.5(118) 0.81

CTL-UC 116 94.5(118) 0.81

CTL-CR 122 94.5(118) 0.77

Fully Bonded

PCA 144 136(150) 0.94

CTL-UC 144 136(150) 0.94

CTL-CR 151 136(150) 0.90

Page 67: Strand Debonding in Pretensioned Beams

-39

Table (4.4)

Web-Shear Cracking Loads at Initial Crack Location

Specimen No. BeamPredicted Load

(kips)

Observed Load

(kips)

obs/pred

1 50% Debonded

PCACTL-UCCTL-CR

56

56

58

90

90

90

1.61

1.61

1.55

Fully Bonded

PCACTL-UCCTL-CR

67

67

70

90

90

90

1.34

1.34

1.29

2 67% Debonded

PCACTL-UCCTL-CR

53

53

55

70

70

70

1.32

1.32

1.27

Fully Bonded

PCACTL-UCCTL-CR

65

65

68

70

70

70

1.08

1.08

1.03

3 83% Debonded

PCACTL-UCCTL-CR

50

50

52

70

70

70

1.40

1.40

1.35

Fully Bonded

PCACTL-UCCTL-CR

58

58

61

77

77

77

1.33

1.33

1.26

4 50% Debonded

PCACTL-UCCTL-CR

122

122

129

94.5(118)

94.5(118)

94.5(118)

0.77

0.77

0.73

Fully Bonded

PCACTL-UCCTL-CR

131

131

138

136(150)

136(150)

136(150)

1.04

1.04

0.99

The early web-shear cracking in the box-beam specimen was caused by the

difference in the thickness of the walls on the two sides of the beam. In both beams, one

wall had a thickness of 4 3/8 inches while the other had a thickness of 5 5/8 inches. The

values in parentheses in Tables 4.3 and 4.4 were the observed loads when web-shear

Page 68: Strand Debonding in Pretensioned Beams

-40-

cracking occurred in the thicker walls. In general, the better agreement was obtained for

fully bonded specimens. For the I-beam specimens with debonded strands the predicted

values were more conservative than for the fully bonded specimens.

4. 1 .5 Flexure-Shear Cracking

The final stage of cracking that occurred in the continuous members was flexure-

shear cracking. Flexure-shear cracking results from diagonal cracks that extend from

already existing flexural cracks. The ACI/AASHTO flexure-shear capacity is given by

the following expression:

r ViMcrVd = 0.6 Vf

'

c bw d + Vd +— (4.3)Mmax

where:

Vd = shear force at section due to unfactored dead load

V; = factored shear force at section due to externally applied loads

Mmax = maximum factored bending moment at section due to externally applied loads

MCT = moment causing flexural cracking at section due to externally applied loads

MCT =— (6Vf7T+fpe-fd)

y t

I = moment of inertia of composite section

y t= distance from centroid of composite section to extreme tension fiber

fpe = compressive stress, due to effective prestressing, at extreme fiber of section where

tensile stresses are caused by externally applied loads

fd = stress due to unfactored dead load, at extreme fiber of section where

tensile stresses are caused by externally applied loads

Page 69: Strand Debonding in Pretensioned Beams

41-

Using the calculated values of Vci , the flexure-shear cracking loads were evaluated

using elastic analysis with the diaphragm idealized as suggested by PCA and CTL

methods. Table (4.5) summarizes the predicted flexure-shear cracking loads and the

corresponding test results for the four test specimens.

For Specimen 1, the flexure-shear cracking loads were calculated at the point of

application of the superimposed load. The flexure-shear crack occurred near the

debonding point, a distance of 44.5 inches from the continuous support. Since the

debonding point was near the point of inflection, very high loads would be required to

produce flexure-shear cracking at that location. Flexure-shear cracking loads for the

beam with 67% debonding in Specimen 2 were calculated at the second debonding

point, located at a distance of 77 inches from the continuous support. For the fully

bonded beam, flexure-shear cracking loads were calculated at the point load. For

Specimen 3, flexure-shear cracking occurred at the second debonding point, located at a

distance of 66 inches from the continuous support. The predicted loads required to

produce flexure-shear cracking at that location were calculated. For the fully bonded

beam the analysis was carried at the point load. Flexure-shear cracking loads for both

beams in Specimen 4 were evaluated at the location of the applied load.

The results obtained using CTL method with the cracked transformed section of the

diaphragm region, coupled with the ACI/AASHTO equations, although providing the

better agreement, substantially overestimated the flexure-shear cracking loads for the

debonded I-beams. This finding in the continuous specimens agrees with the earlier

flexure-shear cracking observed in simply supported members with debonded strands.

Page 70: Strand Debonding in Pretensioned Beams

42

Table (4.5)

Flexure-Shear Cracking Loads

Specimen No. BeamPredicted Load

(kips)

Observed Load

(kips)

obs/pred

1 50% Debonded

PCA 215 140 0.65

CTL-UC 220 140 0.64

CTL-CR

Fully Bonded

173 140 0.81

PCA 204 - -

CTL-UC 209 - -

CTL-CR 164 - -

2 67% Debonded

PCA 272 130 0.48

CTL-UC 272 130 0.48

CTL-CR 194 130 0.67

Fully Bonded

PCA 237 - -

CTL-UC 237 - -

CTL-CR 193 - -

3 83% Debonded

PCA 325 91 0.28

CTL-UC 331 91 0.27

CTL-CR 179 91 0.51

Fully Bonded

PCA 232 - -

CTL-UC 234 - -

CTL-CR 191 - -

4 50% Debonded

PCA 439 - -

CTL-UC 442 - -

CTL-CR 343 - -

Fully Bonded

PCA 432 - -

CTL-UC 434 - -

CTL-CR 337 - -

note:

(-) means no flexure-shear cracking was observed

Page 71: Strand Debonding in Pretensioned Beams

43-

4.1.6 Ultimate Shear Strength

In these tests, shear failure of the girders did not occur since the maximum applied

loads were below the shear failure loads of the beams. The shear force at which shear

failure was likely, was calculated by adding the lower value of Vcw and V CI ,to the

contribution of the web reinforcement, V s . The shear strength provided by the web

reinforcement was calculated by the following equation:

_ Ayfy d(4 4)

Vs"s

where:

Vs= nominal shear strength provided by web reinforcement

f = yield strength of web reinforcement

Av= cross-sectional area of the stirrups

d = distance from extreme compression fiber to the centroid of longitudinal

tension reinforcement

s = stirrup spacing

Table (4.6) gives the shear failure loads calculated using the PCA and CTL models.

As mentioned before shear failure did not occur in these tests. Specimen 3 was loaded

up to 164 kips. However shear failure did not occur as predicted by PCA and CTL

methods.

Page 72: Strand Debonding in Pretensioned Beams

-44

Table (4.6)

Shear Failure Loads

Specimen No. BeamPredicted Load

(kips)

Observed Maximum Load

(kips)

obs/pred

1 50% Debonded

PCA 177 140 0.79

CTL-UC 176 140 0.80

CTL-CR

Fully Bonded

183 140 0.77

PCA 196 140 0.71

CTL-UC 194 140 0.72

CTL-CR 205 140 0.68

2 67% Debonded

PCA 172 162 0.94

CTL-UC 172 162 0.94

CTL-CR 179 162 0.91

Fully Bonded

PCA 191 162 0.85

CTL-UC 191 162 0.85

CTL-CR 199 162 0.81

3 83% Debonded

PCA 167 164 0.98

CTL-UC 167 164 0.98

CTL-CR 174 164 0.94

Fully Bonded

PCA 194 164 0.84

CTL-UC 194 164 0.84

CTL-CR 201 164 0.82

4 50% Debonded

PCA 226 176 0.78

CTL-UC 226 176 0.78

CTL-CR 238 176 0.74

Fully Bonded

PCA 255 176 0.69

CTL-UC 255 176 0.69

CTL-CR 268 176 0.66

note:

Shear failure did not occur .however, maximum load can still be used for comparison purposes

Page 73: Strand Debonding in Pretensioned Beams

-45

4.1.7 Continuity Moment Evaluation

The continuous cast-in-place deck slab was reinforced with 8 #6 Grade 60 bars over

the interior supports. The strain gages on this reinforcement indicated that yielding did

not occur at the maximum applied loads for all beams tested.

Based on the assumptions that plane sections remain plane after bending, and that

no slip occurs between the concrete and steel, the negative moment at the section near

the diaphragm was calculated from the readings of the strain gages placed on the

longitudinal slab reinforcement. These values are compared in Table (4.7) with the

required continuity moments, without load factors and with <j)=1.0, according to PCA

and CTL design methods. The negative bending moment calculated based on end

reaction readings and the predicted nominal flexural capacity in accordance with

current AASHTO [1989] specifications are also shown in Table (4.7).

Although, the forces induced in a composite structure by creep and shrinkage of

concrete would be relevant in checking the allowable stress levels, before cracking of

the diaphragm region, they need not be included in ultimate strength checks. These

stresses are relieved by cracking of concrete and yielding of reinforcing steel. It has

been shown that (Mattock [1961]) the deformations due to creep and shrinkage do not

influence the ultimate load capacity of continuous beams of the type considered in this

study.

Page 74: Strand Debonding in Pretensioned Beams

46

iiI

a 1

•3

•i

$

•5 § | s.35

E ss i

I?u pa

If

1

§ §

<Ua.

ueo&V5

(N ^* Ov «">

Ov O Ov 90T in * <r

S S ©

00 rr\ — —— r-> oo ^m f*"i ^ en

w-i o — r»r~ — rj —m wi m in

en — o\»-i v> mwi *C >©

r-O

CN 00 Ov >*«-l T w-i —*o r- r- oo

IT

*0 3

Page 75: Strand Debonding in Pretensioned Beams

47-

It can be seen from Table (4.7) that, the CTL method with cracked diaphragm

showed better agreement with the measured continuity moment. These findings confirm

the results shown in Figures (4.3-4.6). It is also clear that the PCA method is extremely

conservative for design purposes in the negative moment region if no redistribution is

accounted for, and it could also lead to unconservative estimate of the bending moment

in positive moment regions. Finally, when compared to current AASHTO predicted

capacity for all specimens, both the PCA and CTL methods are conservative. Actual

failure of the diaphragm region did not occur in these tests.

Table (4.8) shows, that in spite of the reduction in the measured maximum positive

moment caused by flexure-shear cracking in the debonded beams compared to the fully

bonded ones of Specimens 2 and 3, the PCA method resulted in lower estimates of the

positive bending moments in the span of these beams. It must be noted that the flexure-

shear cracking in Specimen 3 occurred during the first loading phase (P=91 kips) while

in Specimen 2 occurred during the final loading phase. This would explain the larger

difference between the measured positive moments in Specimen 3. The CTL method

with cracked section gives a better estimate of the measured values in the positive

moment region.

Page 76: Strand Debonding in Pretensioned Beams

-48

Table (4.8)

Positive Bending Moment at the Point Load

Specimen No.

Positive Bending Moment

Based on Pmax (ft-k)

Measured Positive MomentBased on End

Reaction Readings

(ft-k)

PCACTL

uncracked

diaphragm

cracked

diaphragm

DebondedBeam

Fully Bonded

Beam

1

(Pmax=140k)

2

(Pmax=162k)

3

(Pmax=164k)

4

(Pmax=176k)

339

393

398

428

331

390

395

424

429

488

491

556

503

538

439

676

514

598

548

682

4.1.8 Bottom Fiber Stress Evaluation

Current AASHTO Specifications limit the service load stresses in the extreme

compression fiber at interior girder ends to 0.6 fc . This requirement specifies

consideration of "effects of prestressing and negative live load bending". However, the

specifications do not clearly define how far from the girder ends this allowable stress

should apply. The Indiana Department of Transportation in trying to promote

uniformity in design, requires that the allowable compressive stresses shown in Table

(4.9) be followed.

Page 77: Strand Debonding in Pretensioned Beams

49

Table (4.9)

Allowable Compressive Stresses at Girder Ends (INDOT)

Location Allowable stress

At the girder end

2 ft. from the girder end

All other locations

0.6 fc

0.5 fc

0.4 fc

Debonding of strands in the end regions of a prestressed concrete beam is often

necessary to meet this stress requirement. However, to prevent excessive reduction in

the shear strength near the girder ends, INDOT further requires that no more than 50%

of the total number of strands be debonded. It also suggests not to debond an entire row

of strands.

The compressive stresses at the girder ends in the continuous specimens were

monitored using the surface gages shown in Figure (2.47) and Figure (2.70). The

measurements obtained from the surface gages due to time-dependent deformations and

the applied loads during the final loading phase were added to the calculated strains due

to the effective prestressing at the same locations. The corresponding value of stress

was calculated using the well known Hogenstad stress-strain relationship for concrete

(see Lin and Bums [1981]). These stresses were then converted to a dimensionless

quantity K, the stress factor, which is equal to the calculated bottom fiber stress divided

by the compressive strength of the girder concrete.

Page 78: Strand Debonding in Pretensioned Beams

-50-

The strain gages labeled 4 and 6 were placed on the beams with debonded strands.

The gages 7 and 8 were placed on the fully bonded beams. In Specimen 1, gages 6 and

7 were 3 inches away from the ends of the beams, and gages 4 and 8 were 25 inches

away from the ends. In Specimens 2, 3, and 4 gages 6 and 7 were at a distance of 10

inches from the ends, while gages 4 and 8 were at 29 inches from the end.

To evaluate the behavior of the compression region near the interior supports, the K

factors calculated from strain gage readings and from measured end reactions are

compared in Figures (4.7-4.22). The measured end reactions included the effects of

creep and shrinkage as well as the applied superimposed load.

In each specimen the stresses calculated from the readings of gages 6 and 7 are

higher than those from the measured end reactions. However, the stresses at these

locations are affected by the compressive reaction at the interior supports.

To compare the stresses from analysis to the measured values, the stresses were

calculated using the PCA method and CTL method, with cracked diaphragm, and

compared to the experimental results obtained from end reactions measurement in

Figures (4.23-4.38). It can be seen that CTL method shows better agreement with test,

based on reaction measurements, however gives low estimate when compared to strain

gages due to effect of reaction near the supports.

It is worth mentioning that, the time-dependent restraint moment due to creep and

shrinkage need not be included in computing the bottom fiber stresses after flexural

cracking of the diaphragm region had occurred. The stresses due to creep and shrinkage

deformation were relieved by cracking on top of the concrete diaphragm. Table (4.10)

Page 79: Strand Debonding in Pretensioned Beams

51-

compares the measured end reactions at three stages: before continuity was established,

before cracking of the diaphragm region and after cracking of the diaphragm region. It

can be seen that on cracking of the diaphragm, the end reactions changed towards the

initial values before continuity was established. The measured values of the end

reaction shown in Table (4.10) were taken under zero applied superimposed load. This

confirmed that the stresses due to creep and shrinkage were relieved after cracking of

the deck above the diaphragm region.

Table (4.10)

Variation of End Reactions

Measured End Reaction

Specimen No.

(kips)

Before Continuity Before Cracking After Cracking

1 1.2 0.75 2.09

2 6.49 4.28 6.55

3 6.23 4.50 6.48

4 8.16 9.92 9.35

The measured compressive stress at the location of Gages 4 and 8 in Specimen 1 did

not exceed the allowable limit of 0.4 fc . However, the stresses computed using the

PCA method as shown in Figures (4.23) and (4.25) exceeded the allowable limit.

Therefore it can be concluded that evaluating stresses at these locations using the PCA

method would be quite conservative.

In Specimens 2 and 3 the measured stresses based on end reaction measurements at

Gage 8 location exceeded the allowable limit of 0.4 fe specified by INDOT (see

Page 80: Strand Debonding in Pretensioned Beams

52

Figures 4.29 and 4.33). The compressive stress obtained using the PCA method at this

location was found to be 0.6 fc . This confirmed that exceeding the allowable limit of

0.4 fc did not influence the service load behavior of the fully bonded beam. The results

obtained from Specimen 4 confirmed the previously mentioned observation that the

PCA method overestimated the bottom fiber stresses at the interior supports of

continuous beams.

The bottom fiber stresses based on strain measurements at the location of Gages 6

and 7 in Specimens 2 and 3 exceeded the allowable stress limit of 0.6 fc . It can be

concluded that exceeding the allowable stress limit did not affect the linear behavior of

the fully bonded beams. It is worth noting that at these locations the lateral restraint

provided by the diaphragm provided beneficial confinement to the end region of the

beams at the continuous support.

4.1.9 Summary

The behavior of the test specimen under the effect of the superimposed load is

presented. Shear as well as flexural behavior were examined in this chapter. The PCA

and CTL methods were used to predict the test results. The PCA method assumes full

continuity at the interior supports. The CTL method considers the finite length and

stiffness of the diaphragm between the precast girders. The CTL method gave closer

values to the test results after flexural cracking of the diaphragm by incorporating the

cracked transformed section of the composite girders at the diaphragm region.

Measured values based on end reaction readings showed that the time-dependent

restraint moments due to creep and shrinkage were released after cracking of the

Page 81: Strand Debonding in Pretensioned Beams

53-

diaphragm region. A comparison of values from strain gage readings and end reaction

measurements indicated that the presence of a support reaction results in an increase on

the compressive stress at girder ends above that induced by bending moments. The

PCA method resulted in an overestimation of the bottom fiber stresses at end regions

located 25 and 29 inches from the beam ends at the continuous support. Measured

values of the bottom fiber stress using strain gage readings at 3 and 10 inches from the

end of the girder showed values in excess of 0.6 fc in specimens 2 and 3. In this region

of the member, the PCA method provided a conservative estimate of the bottom fiber

stresses. The CTL method provided the better agreement with measured values based

on end reaction readings at all gage locations. A summary and conclusions drawn from

the experimental program in this report will be presented in the following chapter.

Page 82: Strand Debonding in Pretensioned Beams

-54-

CHAPTER5

SUMMARY AND CONCLUSIONS

5.1 Summary

This report presents the results of an experimental investigation directed towards

evaluating three types of behavior in pretensioned concrete bridges. Four two-span

composite specimens with different strand debonding schemes were fabricated and

tested to evaluate: (1) time-dependent effects due to creep and shrinkage deformations

of prestressed precast bridge girders made continuous with a cast-in-place slab, (2)

shear and flexural behavior of prestressed girders with debonded strands at continuous

supports, and (3) compressive stresses near the ends of pretensioned girders at

continuous supports.

The time-dependent behavior was examined by establishing continuity between two

prestressed precast girders using a cast-in-place slab and diaphragm. The restraint

moments that developed at the continuous supports due to prestress induced creep of

the precast girders, and of differential shrinkage between the precast girders and the

cast-in-place slab were experimentally determined. The predicted restraint moments

obtained using the PCA and CTL methods were compared with the measured values

from the variation in the end support reactions.

The continuity behavior of the test specimens for the applied superimposed loads

was examined by comparing the measured continuity moments with the corresponding

values predicted using the PCA and CTL analytical methods.

Page 83: Strand Debonding in Pretensioned Beams

55-

The results obtained from testing the continuous structures under the effect of a

static two-point loading were used to evaluate the ACI/AASHTO provisions for shear

and flexural cracking loads at continuous supports of multi-span precast-pretensioned

bridges.

The bottom fiber stresses at the continuous supports of pretensioned girders, due to

effective prestressing and applied loads, were estimated using the PCA and CTL

models. The predicted stresses were compared with the measured test values to evaluate

both methods.

5.2 Conclusions

From the observations and analysis of the continuous tests the following

conclusions can be made:

1. The time-dependent creep and shrinkage deformations in this type of construction

induced restraint moments at the continuous supports. Positive restraint moments

were measured at the interior support of the continuous composite box-beam

specimen.

2. The time-dependent restraint moments computed using the PCA method were in

good agreement with the test values when continuity was established at early

ages of the precast girders. Large differences were observed when continuity was

established at late ages of the precast members. The CTL method gave improved

correlation with measured results when the modification to account for restraint

of the top steel was introduced at an earlier age of the cast-in-place slab concrete.

Page 84: Strand Debonding in Pretensioned Beams

-56

3. Similar behavior was exhibited by both the debonded girders and the fully

bonded girders, in regard to deflections under the effect of the superimposed

loads, up to the formation of flexure-shear cracking. The debonded beams had

larger deflections after flexure-shear cracking than the fully bonded beams where

flexure-shear cracking did not occur.

4. Before cracking of the top slab in the diaphragm region both the PCA and CTL

methods yielded reasonable and conservative estimates of the measured

continuity moment due to the applied superimposed loads based on end reaction

measurements. After cracking, however, the CTL method using the cracked

transformed section of the composite girder at the diaphragm region gave better

results than the PCA method. The PCA method significanUy overestimated the

bending moments at the continuous supports after flexural cracking.

Consequently, using the PCA method resulted in the flexural requirements in the

positive moment regions being underestimated, even though flexure-shear

cracking led to a reduction in the positive moment due to further redistribution.

5. The flexural capacity at the continuous support was further examined using the

results of the strain gages in the slab negative moment continuity reinforcement

over the interior supports. It was confirmed that the PCA method gave very

conservative estimates of the continuity moment. The theoretical results obtained

by the CTL method with the cracked diaphragm assumption gave an improved

conservative estimate of the negative moments at interior supports for all the

beams tested.

Page 85: Strand Debonding in Pretensioned Beams

57

6. The time-dependent restraint moment due to creep and shrinkage need not be

included in computing the bottom fiber stresses after flexural cracking of the slab

over the diaphragm region. Also the time-dependent restraint moments should not

be included in the calculation of the ultimate load of the continuous beams. These

moments were relieved by flexural cracking of the concrete slab over the

diaphragm.

7. The ACI/AASHTO equations coupled with the PCA and CTL models gave

conservative estimates of the web-shear cracking loads for the fully bonded as

well as the debonded I-girders . These models yielded slightly unconservative

estimates of the test values for the box girders.

8. Flexure-shear cracking developed in the I-shaped beams earlier than predicted by

PCA and CTL methods in the positive moment region. It was noted that

debonding the prestressing strands in the positive moment regions of these beams

resulted in the premature opening of these cracks. All flexure-shear cracks

originated in the bottom flange of the girders at the debonding points located near

the applied loads. It was noticed that flexure-shear cracking reduced the positive

bending moment at the applied superimposed load location indicating further

redistribution of moments.

9. Strand debonding in the negative moment region near the continuous supports did

not significantly influence the web-shear cracking capacity of the girders. Direct

comparison of the ultimate shear capacity can not be made since no shear failure

was observed in these tests.

Page 86: Strand Debonding in Pretensioned Beams

-58-

10. The measured compressive strains at the continuous supports were affected by

the compressive reaction at the supports. However, away from the supports the

measured bottom stresses from the surface gages were in excellent agreement

with the values computed from end reaction measurements. Comparison of the

measured stresses with the theoretical results, indicated that both the PCA and

CTL methods underestimated the compression fiber stresses, based on strain

measurements, near the continuous supports. However, away from the support

the PCA method substantially overestimated the bottom fiber stresses, while the

CTL method with cracked diaphragm showed a much improved agreement.

11. Based on strain gage readings at the end regions near the continuous support, the

compressive stresses exceeded the 0.6 fc limit. However no detrimental effect on

the service load behavior of the beams was observed during the tests.

5.3 Future Work

Future research is needed to determine the available capacity for redistribution at

the continuous support of precast pretensioned concrete girder bridges with debonding.

members.

Page 87: Strand Debonding in Pretensioned Beams

-59

LIST OF REFERENCES

Page 88: Strand Debonding in Pretensioned Beams

60

REFERENCES

1. ACI Committee 318, "Building Code Requirements for Reinforced Concrete

(ACI 318-77)." American Concrete Institute, Detroit, Michigan, December 1989,

353 pp.

2. ACI Committee 209, "Prediction of Creep, Shrinkage and Temperature Effects in

Concrete Structures." American Concrete Institute, Special Publication SP-76,

Detroit, Michigan 1982, pp. 193-300.

3. American Association of State Highway and Transportation Officials , 1989,

"Standard Specifications for Highway Bridges." Fourteenth Edition, Washington,

D.C.

4. Freyermuth, C. L., "Design of Continuous Highway Bridges With Precast,

Prestressed Concrete Girders." J. Prestressed Concrete Institute, Vol.14, No. 2,

April 1969, pp. 14-39.

5. Glikin, J. D., Larson, S. C, and Oesterle, R. G., "Computer Analysis of Time

Time Dependent Behavior of Continuous Precast, Prestressed Bridges."

Computer Application in Concrete Technology. American Concrete Institute,

Special Publication Sp-106, Detroit, Michigan 1987, 37 pp.

6. Lin, T., Y., and Burns, N., H., "Design of Prestressed Concrete Structures." John

Wiley and Sons, Third Edition, 1981, 646 pp.

7. Mattock, A. H., "Precast-Prestressed Concrete Bridges, 5. Creep and Shrinkage

Studies." J. PCA Research and Development Laboratories, Vol.3, No.2 .May

1961, pp. 32-66.

8. Oesterle, R. G., Glikin, J. D., and Larson, S. C, "Design of Precast Prestressed

Bridge Girders Made Continuous." NCHRP Report No.322, Transportation

Research Board, Washington D.C, November 1989, 300 pp.

9. Ogg, C, J., "Continuous Precast Pretensioned Beam with Debonded Strands: Test

No.2." M.Sc. Thesis, Department of Civil Engineering, Purdue University,

Indiana, December 1991, 136 pp.

10. Schmid, K., E., "Continuous Precast Pretensioned Beam with Debonded Strands:

Test No.l." M.Sc. Thesis, Department of Civil Engineering, Purdue University,

Indiana, August 1991, 147 pp.

1 1. Sinno, R., and Furr, H. L., "Computer Program for Predicting Prestress Loss and

Camber." J. Prestressed Concrete Institute, Vol.17, No. 5, September-October

1972, pp. 27-38.

12. Suttikan, C, "A Generalized Solution for Time-Dependent Response and

Strength of Noncomposite and Composite Prestressed Concrete Beams." Ph.D

Thesis, The University of Texas At Austin 1978, 386 pp.

Page 89: Strand Debonding in Pretensioned Beams

-61-

13. Tadros, M. K., Ghali, A., and Dilger, W. H., "Time-Dependent Prestress Loss and

Deflection In Prestressed Concrete Members." J. Prestressed Concrete Institute,

Vol.20, No.3, May-June 1975, pp. 86-98.

Page 90: Strand Debonding in Pretensioned Beams

-62

Appendix A - Time-Dependent Restraint Moments

Page 91: Strand Debonding in Pretensioned Beams

-63-

Table(A.l)

Restraint Moments for Specimen 1

Age of girder Measured end Change in Restraint

Reaction Reaction Moment(days)

(kips) (kips) (ft-k)

113 1.2 0.0 0.0

123 -0.49 -1.69 -40.6

130 -0.47 -1.67 -40.1

140 0.17 -1.03 -24.7

157 0.75 -0.45 -10.8

The end reaction due to self-weight of girdep=3.44 kips

The end reaction due to slab weight (simple supports)=2.39 kips

(-) Restraint moment represents tension at the top of the cross-section

Page 92: Strand Debonding in Pretensioned Beams

64

Table (A.2)

Restraint Moments for Specimen 2

Age of girder Measured end Change in Restraint

(days)Reaction Reaction Moment(kips) (kips) (ft-k)

49 6.49 0.00 0.0

50 5.62 -0.87 -21.17

51 5.85 -0.64 -15.57

52 5.58 -0.91 -22.14

53 5.21 -1.28 -31.15

54 4.99 -1.50 -36.50

55 4.87 -1.62 -39.41

56 4.52 -1.92 -47.93

57 4.26 -2.23 -54.26

58 4.12 -2.37 -57.66

59 4.02 -2.47 -60.10

60 3.82 -2.67 -64.96

61 3.87 -2.62 -63.72

62 3.83 -2.66 -64.72

86 4.28 -2.21 -53.77

The end reaction due to self-weight of girder=3.69 kips

The end reaction due to slab weight (simple supports)=2.80 kips

(-) Restraint moment represents tension at the top of the cross-section

Page 93: Strand Debonding in Pretensioned Beams

65-

Table (A.3)

Restraint Moments for Specimen 3

Age of girder Measured end Change in Restraint

/ J —\ Reaction Reaction Moment(days)

Grips) Grips) (ft-k)

91 6.23 0.0 0.0

92 5.15 -1.08 -26.28

93 5.38 -0.85 -20.68

94 5.19 -1.04 -25.31

95 4.74 -1.49 -36.26

96 4.42 -1.81 -44.04

97 4.58 -1.65 -40.15

98 4.44 -1.79 -43.56

99 4.18 -2.05 -49.88

100 4.06 -2.17 -52.80

101 3.99 -2.24 -54.51

102 3.81 -2.42 -58.89

103 3.98 -2.25 -54.75

104 4.09 -2.14 -52.07

105 3.97 -2.26 -54.99

106 4.05 -2.19 -53.17

107 4.26 -1.97 -47.94

108 4.29 -1.94 -47.13

110 4.32 -1.91 -46.48

111 4.26 -1.97 -47.94

113 4.50 -1.73 -42.09

The end reaction due to self-weight of girdep=3.X4 kips

The end reaction due to slab weight (simple supports)=2..V) kips

(-) Restraint moment represents tension at me top of the cross-section

Page 94: Strand Debonding in Pretensioned Beams

-66-

Table (A.4)

Restraint Moments for Specimen 4

Age of girder Measured end Change in Restraint

(days)Reaction Reaction Moment(kips) (kips) (ft-k)

26 8.16 0.0 0.0

27 7.48 -0.68 -16.5

28 7.48 -0.68 -16.5

29 7.75 -0.41 -10.0

30 7.85 -0.31 -7.5

31 7.96 -0.20 -4.9

32 8.05 -0.11 -2.7

33 8.03 -0.13 -3.2

34 8.21 0.06 1.5

36 8.77 0.61 14.8

38 9.17 1.00 24.3

39 9.10 0.94 22.8

40 9.43 1.27 30.9

41 9.47 1.31 31.9

42 9.44 1.28 31.1

43 9.48 1.32 32.2

45 9.46 1.30 31.6

46 9.50 1.35 32.9

47 9.56 1.40 34.1

48 9.53 1.37 33.3

49 9.34 1.18 28.7

50 9.36 1.20 29.2

51 9.36 1.20 29.2

52 9.46 1.30 31.6

53 9.42 1.26 30.7

54 9.59 1.43 34.8

55 9.75 1.59 38.7

57 9.44 1.28 31.1

58 9.65 1.49 36.3

59 9.92 1.76 42.8

The end reaction due to self-weight of girder=6.67 kips

The end reaction due to slab weight (simple supports)=1.93 kips

(-) Restraint moment represents tension at the top of the cross-section

Page 95: Strand Debonding in Pretensioned Beams

\

\

^

67-

PRECAST GIRDER PRECAST GIRDER

ISTAGE 1 - PRECAST GIRDER IN PLACE

REINFORCEMENT^

ISTAGE 2 - REINFORCEMENT AT SUPPORT

CAST-IN-PLACE CONCRETE "\

ISTAGE 3 - COMPLETED STRUCTURE

Situ-cast deck slab v ^ « , Deformed bar reinforcement^

Situ-cast "

diaphragm

7=\

PierJ

Precast Girder

Reinforcement in Deck Slab

7

/

7

Figure (2. 1 ) Development of Continuity with Precast Girders.

Page 96: Strand Debonding in Pretensioned Beams

a.o

E

E

oeo

co

c1)

e—ouQ.00

£a,3*-»

on—

e/3

3O3C

•—

a

e3

E

Page 97: Strand Debonding in Pretensioned Beams

co

t/3

e

Iu-JQ.CO

s

e2

3

ac—

5

m

3ao

Page 98: Strand Debonding in Pretensioned Beams

oCD«c

'5

o

COC

oa.175

a.3

c/5

3O3_C

c

a

3

tu

Page 99: Strand Debonding in Pretensioned Beams

oO

Cu

oua,en

s

CO

Hv.-a3e

oU

U

Page 100: Strand Debonding in Pretensioned Beams

-72-

cueo<DQ.C/3

aC<n

coao«>t/5

I

t/3

2uha•u

-ac5•-*

Oa.

EoU

3

Page 101: Strand Debonding in Pretensioned Beams

-73-

LO

H^CD

ADE TERS

oc zOlu-o

^ cc =<C COCQt-CD®

CD CD oCD CD CDLU LU UJo Q Q< •a: <coc oc cco o ooc cc cc< < «cCD CO COCD <T CO=*fc * *

LD LO

LO

CM

e/5

C

oQ.00

c-acca

c,o

o

oo

P

U"E

a

oa.

£

3

Page 102: Strand Debonding in Pretensioned Beams

74-

Cast-in-place slab

fc' = 4333 psi

2.625"

4"f±L

2.875"^

1.5"

27"

5,L>K- 26"- <-5"1

18.5"

5.5"

i i 4 X S i * *4-

i\« | mS9 • • ^* ft i >!

X.

^N

#6 @ 15"

#4@18"

#5, Grade 60

#4@15"

#3, Grade 60 @ 4"

fci = 5600 psi

fc' = 6732 psi

#6, Grade 60

A.2" ±

P-£f1/2" Lo - Laax

Grade 270 Strand (Area = 0.153 in.2

)

Figure (2.8) Composite Girder Cross-section and Details (Specimen 4).

Page 103: Strand Debonding in Pretensioned Beams

-75

LU

Eto

O)

03a

m

Een05CO

a a

sinto

3inc»

>k

,r

3oCO

''

V

o -

oa -

< -

V

||

A

A

i

CO

ml

I & in

ato

in

w

« 11IS»®

««••

E

a>

E09

•®

1111^\*® o

T3

E

8into

3in10

la

A

in

CO

V

AA

V

co -

V;l

A

CD

!!!!

3

COCO

oen

>£- £ £>

c:

U

oua.CO

cU

-3c

v, Ea:o\r.

(50

c

0< _g

Q—c-

5/3

5

Page 104: Strand Debonding in Pretensioned Beams

-76

CuE

Q.CO

c_o

ss

E2*--

C

"Oc

<u

E<uJ=oen

Page 105: Strand Debonding in Pretensioned Beams

-77

UJ ___

.

i i

ECO

s-

C5 •* -r

'J3

1

i

t

k

S * 111

i

*aa

O)

!

1rU tJ ill

CD \y

i ,^,

,

E; k

(0

aBUJ

1! 1

t k

1

r1

i

33

1 i 1

[i '

I I I I

E(UCO

o>

03O u-^

<k A >k

COO]

o

E

^^ CO

E

<

eU

oua.on

ec

BU

T3B.-3

uSuj=oC/3

B

B

Q

c/3

Page 106: Strand Debonding in Pretensioned Beams

78-

Q £

S °g 3*

7^ T-r

O)

09

ECOco00

« X

g s? \

A A A A

toCM

- mes4

53

co £

O O

co

O <

toCT1

to

T T

• •

too

c

£o<uQ.

W)c'oc

uQ#o

S<U

oa

eo

c-J

e3Gc

ocauE—oC/J

ooc•3coX)<u

Qa

i

23

E

Page 107: Strand Debonding in Pretensioned Beams

-79

7

o>

03o

ECOOSCO

X

AAA

toCO

ra

m

CSJ CO

Ki

l\ in

t ttt

C

uuQ.on

-acS

.-C

uQ

oin

c

cuE

e

•aeCO

u5/5

e

s

ac

oo

Page 108: Strand Debonding in Pretensioned Beams

-80-

Figurc (2.13) Reinforcement Cage for Specimens 1, 2, 3, and 5

Page 109: Strand Debonding in Pretensioned Beams

-81-

c

£

Iv. T3

o>CD u_« o

-«u £Eug

c

-1

Ci

-

II

a.

c

Page 110: Strand Debonding in Pretensioned Beams

EcuCO

CM

-B-

182-

Q) a a.= - =

S-'w

in r

k

3

ICO

f

@ k

C/>

C3.3 3w

CO4k

CMr

>S^_ k

3

n r

k

a

<1^ f

LUJ i

Ere OCO 7r

•c>- oCU Qj £3.

= 5 =

u

o

en

co

c

c/3

Ci—

i

•aces«-»

CuEu

Ic

saJon

oc,o

es

-J

in

tN

3

Page 111: Strand Debonding in Pretensioned Beams

-83

Cu£—oaa.CO

c

Cu

c

-aca

cu

o

CO

z

Page 112: Strand Debonding in Pretensioned Beams

-84

o ^^

enSo

o tECM

Eam

ito

CD

i

I

i

i

I

t

1

1

(M'

k

D

COt

k

3

ft

k

3

t

i

u 5

I"E °

5i

p/ 4n

ito

(

I

i

J

-

O'

@ \

a.3 3k-

CM'

V^ k

3

n r

ak

LUCM

s1

;LU

E3

CO\f

5

C

I• »-«

00

§

c

E

W5C

!cuE

Ic

1

00'—

oc.9—

<N

a> as a.

3-5

Page 113: Strand Debonding in Pretensioned Beams

85

Figure (2.18) Unshored Construction Method for I-beam Specimens

Page 114: Strand Debonding in Pretensioned Beams

-86

Figure (2.19) Unshored Construction Method for Box-girder Specimen

Page 115: Strand Debonding in Pretensioned Beams

87-

c = go

.S » g

- « g

-=>*

[352

US

[)^

IN

US

115

ti-

ll"

[]JP

IIS

CJCM C ]«»

~* *

«

4'

/ XT7k i.

Bu

'J

ya.on

eo

BUE

BUEuu

o

MuQQor>

ri

3

Page 116: Strand Debonding in Pretensioned Beams

88

~~i *

ii«3 n* nS

v *

•ac«

C

1

8a.c/3

llS

[]r-

[]"•

cm

[|CO

US

— » i,

-H[)•

co—

2c

8

e

I3—•5bc

n- u~

W

[|n

S N

s «

— .2o a.

•s •=•

a •

M r-

xjyto M

-*

1.—-

Page 117: Strand Debonding in Pretensioned Beams

89

nS ii?

- = >*

00

•c

US

lit-

[]»

Cl^

US

T *

[]«

[]'-

""5

[j~

4 *

t »|« >|< »i< >

WWWVVVVWIr

m 3C3 •=

cu

I'33Q.00

Cc

B

Uu

•9s—'5bc

1on

-

Page 118: Strand Debonding in Pretensioned Beams

90

f'c

(psi)

7000

6000-

5000-

4000-

3000-

2000 -

1000

50

Precast Beams

Cast-in-place Slab

T T100 150

Age (Days)

200 250

Figure (2.23) Variation of Uniaxial Compressive Strength

of Concrete With Age

Specimen 1

Page 119: Strand Debonding in Pretensioned Beams

-91 -

f1 c

(psi)

x~—-— .••'"

6000-

5000- /4000-

K3000-

\Precast Beams

i\

.' Cast-in-place Slab

2000-

1000-

o\J1 1 1 1 1 1 1

20 40 60 80 100 120 140

Age (Days)

Figure (2.24) Variation of Uniaxial Compressive Strength

of Concrete With Age

Specimen 2

Page 120: Strand Debonding in Pretensioned Beams

92

p1 c

(psi)-

5000- / ._

4000-;

!

3000-

Precast Beams

2000-

>V

1000-;i

\Zast-in-place Slab

o1 1 1 1 1 1 1 1 1 1

20 40 60 80 100 120 140 160 180 200 220

Age (Days)

Figure (2.25) Variation of Uniaxial Compressive Strength

of Concrete With Age

Specimen 3

Page 121: Strand Debonding in Pretensioned Beams

93-

20 40 60 80 100 120 140

Age (Days)

Figure (2.26) Variation of Uniaxial Compressive Strength

of Concrete With Age

Specimen 4

Page 122: Strand Debonding in Pretensioned Beams

94-

-

Stress

(ksi)

f = 255 ksi fpu = 280 ksi

250-

Z\)\) —

150- Modulus of Elasticity=28500 ksi

100-

50-

o

(

1

> 50001 1 1 1

10000 15000 20000 25000 300

Strain ( \i— )

in

Figure (2.27) Measured Stress-Strain Behavior

of Prestressing Strands (Stress Relieved)

Specimen 1

Page 123: Strand Debonding in Pretensioned Beams

-95

Stress

(ksi)

300

250

200-

150

100-

50-

fpy

= 252 ksi fpu = 280 ksi

Modulus of Elasticity=29 1 00 ksi

T10000 15000 20000

inStrain ( u. — )

in

Figure (2.28) Measured Stress-Strain Behavior

of Prestressing Strands (Specimens 2 and 3)

1

25000 30000

Page 124: Strand Debonding in Pretensioned Beams

-96

Stress

(ksi)

o\nt —f = 264 ksi fpu = 284 ksi

250-

200-

150-

Modulus of Elasticity=28600 ksi

100-

50-

o

1

[ 1

) 50001

100001 1 1

15000 20000 25000 30C

Strain ( u. — )in

Figure (2.29) Measured Stress-Strain Behavior

of Prestressing Strands (Specimen 4f oj*J- 5j

Page 125: Strand Debonding in Pretensioned Beams

97-

S tress

(ksi)

50-

40 J

10-

fy= 62 ksi

Modulus of Elasticity=30000 ksi

I I I I 1 1 1

2000 4000 6000 8000 10000 12000 14000 16000

Strain ( u.— )

in

Figure (2.30) Measured Stress-Strain Behavior of Mild Steel

#6 Bar, Grade 60 (Specimen 1

)

Page 126: Strand Debonding in Pretensioned Beams

98-

80

Stress

(ksi)

fy= 62 ksi

Modulus of Ealsticity=30000 ksi

~~l 1 1 1 1 1 1

2000 4000 6000 8000 10000 12000 14000 16000

inStrain ( u. — )

in

Figure (2.31) Measured Stress-Strain Behavior of Mild Steel

#6 Bar, Grade 60 (Specimens 2 and 3)

Page 127: Strand Debonding in Pretensioned Beams

99

80

Stress

(ksi)

fv = 64 ksi

Modulus of Elasucity=28600 ksi

1 1 1 1 1 I

2000 4000 6000 8000 10000 12000 14000 16000

inStrain ( u. — )

in

Figure (2.32) Measured Stress-Strain Behavior of Mild Steel

#6 Bar, Grade 60 (Specimen 4)

Page 128: Strand Debonding in Pretensioned Beams

100-

100

80-

Stress

(ksi)

60

40-

20-

fy=72 ksi

Modulus of Elasticity=28 100 ksi

5000 10000 15000 20000 25000

Strain ( u\ — )

in

Figure (2.33) Measured Stress-Strain Behavior of Mild Steel

#3 Bar, Grade 60 (Specimen 1)

Page 129: Strand Debonding in Pretensioned Beams

- 101 -

100

80-

Stress

(ksi)

60-

40

20

fv =72 ksi

Modulus of Elasticitv=28l00 ksi

11

1 I

5000 10000 15000 20000 25000

• inStrain ( u. — )

in

Figure (2.34) Measured Stress-Strain Behavior of Mild Steel

#3 Bar, Grade 60 (Specimens 2 and 3)

Page 130: Strand Debonding in Pretensioned Beams

102

100

80

Stress

(ksi)

60-

40

20-

fy=71 ksi

5000

Modulus of Elasticity=280OO ksi

10000 15000

1^

20000 25000

inStrain ( u. — )

in

Figure (2.35) Measured Stress-Strain Behavior of Mild Steel

#3 Bar, Grade 60 (Specimen 4)au>*A. s)

Page 131: Strand Debonding in Pretensioned Beams

103

Figure (2.36) Loading System for Continuous Tests

Figure (2.37) Load Cells to Measure Applied Loads

Page 132: Strand Debonding in Pretensioned Beams

- 104-

TT

mCi+

V.K.1G3

r

Figure (2.38) Deck Cracking over Continuous Support at Completion

of Tests (Specimen 1)

Figure (2.39) Deck Cracking over Continuous Support at Completion

of Tests, Longitudinal View (Specimen 1)

Page 133: Strand Debonding in Pretensioned Beams

- 105 -

Figure (2.40) Crack Pattern of 0% Debonded Beam at Completion

of Continuous Tests (Specimen 1)

Figure (2.41 ) Crack Pattern of 50% Debonded Beam at Completion

of Continuous Tests (Specimen 1

)

Page 134: Strand Debonding in Pretensioned Beams

106

0) gg O« —

' =

,_ •cV oayO

c a.

-Ja.

00

w tru 0> o

0> _l

CO

u as osi a

~*—

?

«> 93

<TI ifUo™ 09tfl K1— ^O o=»—I aa c<= rom ••—

toorCOCD

ia

re ,p

w 9

c

1ouaon

HQ>J•acS3

<o

a"3

Q

co

• *•**•

a.

3

Page 135: Strand Debonding in Pretensioned Beams

- 107 -

Load

(Kips)

Beam with bonded strands

Beam with debonded strands

i r~

0.05 0.10 0.15 0.20 0.25

Deflection Under Load P (inch)

0.30

Figure (2.43) Load-Defiection Relationship, Initial Load Phase

Specimen 1

Page 136: Strand Debonding in Pretensioned Beams

108-

Load

(Kips)

140

120-

100-

80-

60-

40

20-

Beam with bonded strands

Beam with debonded strands

1 1 1 1

1

0.00 0.05 0.10 0.15 0.20 0.25 0.30

Deflection Under Load P (inch)

Figure (2.44) Load-Deflection Relationship, Final Load Phase

Specimen 1

Page 137: Strand Debonding in Pretensioned Beams

-109

100

90

80-

70-

60-

Load

(Kips)

Beam with bonded strands

Beam with debonded strands

T0.00 0.05 0.10 0.15 0.20

Midspan Deflection (inch)

0.25 0.30

Figure (2.45) Load-Deflection Relationship, Initial Load Phase

Specimen 1

Page 138: Strand Debonding in Pretensioned Beams

- no

Load

(Kips)

140

120-

100-

80-

60-

40-

20-

Beam with bonded strands

Beam with debonded strands

11

1 I I

0.00 0.05 0.10 0.15 0.20 0.25 0.30

Midspan Deflection (inch)

Figure (2.46) Load-Deflection Relationship, Final Load Phase

Specimen 1

Page 139: Strand Debonding in Pretensioned Beams

- Ill -

TT^

\\

oCO

£

o>D

i_ trU QJ O— C O-CO

1CDCM

03 03 aeo —J S^o

iCM

EroCO

CO

CO

oo

pCO

ir>n

roQ

V O-CD

oS

CO

ss

cJ

u

to

u

Oc-

':•:

1:

CO<Do

3

cc—

-r

32X)

Page 140: Strand Debonding in Pretensioned Beams

-112-

Load

(Kips)

/•

s

/

Gage No.4

Gage No.6

Gage No.7

Gage No.8

~\ 1 1 1 1

1

100 150 200 250 300 350 400

Strain ( )i— )

in

Figure (2.48) Compressive Strain at Continuous Support

Initial Load Phase (Specimen 1)

Page 141: Strand Debonding in Pretensioned Beams

113

140

120-

100-

Load

(Kips)

80-

60-

40

20-

-75 200

/

Gage No.4

Gage No.

6

. . . . Gage No.7

....&.... GageNo.8

300 400 500 600

in

Strain ( u. — )

in

Figure (2.49) Compressive Strain at Continuous Support

Final Laod Phase (Specimen 1

)

Page 142: Strand Debonding in Pretensioned Beams

114-

Load

(Kips)

t~ —i

1 1 1 r

50 100 150 200 250 300 350 400

Strain ( u,— )

in

Figure (2.50) Stirrup Strains at Continuous Support, Initial Load Phase

Beam With 50% Debonding (Specimen 1

)

Page 143: Strand Debonding in Pretensioned Beams

-115

140

120

100- -

Load

(Kips)

80-

60-

40

20-

500 1000

Strain ( jj.

1500

in

m

_ Gage IB1

_ GageIB2

. Gage IBS

.. GageIB4

2000 2500

Figure (2.51) Stirrup Strains at Continuous Support, Final Load Phase

Beam With 50% Debonding (Specimen 1)

Page 144: Strand Debonding in Pretensioned Beams

116-

Load

(Kips)

100

90

80-

70-

60-

50-j|•I

'i

40-j

30-

20-

10-

:!

200

Gage IC1

Gage IC2

. . GageIC3

GageIC4

400 600

inStrain ( )i — )

in

800 1000

Figure (2.52) Stirrup Strains at Continuous Support, Initial Load Phase

Beam With 0% Debonding (Specimen 1)

Page 145: Strand Debonding in Pretensioned Beams

117-

140

1500 2000

in

2500

Strain ( u. — )

in

Figure (2.53) Stirrup Strains At Continuous Support, Final Load Phase

Beam With 0% Debonding (Specimen 1

Page 146: Strand Debonding in Pretensioned Beams

118-

100

90-

80-

70-

60-

Load

(Kips)

Gage No. 7

Gage No. 8

Gage No. 9

1200

inStrain (ii— )

in

Figure (2.54) Strain in Slab Longitudinal Steel at Centerline of Diaphragm

Initial Load Phase (Specimen 1)

Page 147: Strand Debonding in Pretensioned Beams

- 119-

Load

(Kips)

ItU — :1

i

(

120-)

/ /.-" /

100- :' r'

/ 1

;' 1 /' /

80-

/ /

60-•' / /

.•'/ // Gage No. 7

.•'/' //40-

£yGage No. 8

Gage No. 9

20-

i

\i i i i 1 1 1

200 400 600 800 1000 1200 1400 1600

mStrain ( p. — )

in

Figure (2.55) Strain in Slab Longitudinal Steel at Centerline of Diaphragm

Final Load Phase (Specimen 1

)

Page 148: Strand Debonding in Pretensioned Beams

- 120-

140

120-

100-

Load

(Kips)

80

60-

40

20-

4000

,.... GagelBl

. _ _ Gage IB2

Gage IB3

4500 5000

Strain ( jll— )

in

5500 6000

Figure (2.56) Strand Strain at 44.5 in. from Continuous Support, Final Load Phase

Beam with 50% Debonding (Specimen 1)

Page 149: Strand Debonding in Pretensioned Beams

- 121

140

120-

100-

Load

(Kips)

80

60-

40-

20-

3500 3750

(

4000

Strain ( \i

in

m

Gage IB4

Gaee IB5

4250 4500

Figure (2.57) Strand Strain at 65.5 in. from Continuous Support. Final Load Phase

Beam with 50% Debonding (Specimen 1)

Page 150: Strand Debonding in Pretensioned Beams

122

3400 3600 3800 4000

inStrain ( ji — )

in

4200 4400

Figure (2.58) Strand Strain at 86 in. from Continuous Support, Final Load Phase

Beam with 50% Debonding (Specimen 1)

Page 151: Strand Debonding in Pretensioned Beams

123-

3800 4000 4200 4400

inStrain ( u. — )

in

Figure (2.59) Strand Strain at 39 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 1)

Page 152: Strand Debonding in Pretensioned Beams

-124-

3800 4000 4200

inStrain ( u.— )

in

4400

Figure (2.60) Strand Strain at 63 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 1)

Page 153: Strand Debonding in Pretensioned Beams

- 125

140

120-

100

Load

(Kips)

80-

60-

40

20-

3250 3500 3750 4000

m

4250 4500

Strain ( u. — )

in

Figure (2.61) Strand Strain at 84 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 1)

Page 154: Strand Debonding in Pretensioned Beams

- 126-

Figure (2.62) Flexure-Shear Crack at Second Debonding Point

in 67% Debonded Beam (Specimen 2)

Page 155: Strand Debonding in Pretensioned Beams

- 127

Figure (2.63) Crack Pattern at Continuous Support

Fully Bonded Beam (Specimen 2)

Figure (2.64) Crack Pattern at Continuous Support

(i7'v Dcbondcd Beam (Specimen 2)

Page 156: Strand Debonding in Pretensioned Beams

- 128

03 03 O1 f

CM

CM

s-I

03 Q3 O

" CO

•_ trCO QJ O

O

o ra,?

a03 03

03

raco

uo O)o

a)t/! -C d je1— -

ra uO o O>03> a> COa

O 13 COC ra orat;S 3

ro

03 Eoo

CO BraO

03

03 1ora

XI t= uc O ca OO o

COC3Irao

ra

C3COCOran3CO03

03k-Ueoo

a

c/3

U00

o0)

U3on

•accs

HQ>

OSoCOoo

c.2C3

o-J'—o

m3

3oo

E

Page 157: Strand Debonding in Pretensioned Beams

129

100

Load

(Kips)

Beam with bonded strands

Beam with debonded strands

0.05 0.10

Deflection Under Load P (inch)

0.15

Figure (2.66) Load-Deflection Relationship, Initial Load Phase

Specimen 2

Page 158: Strand Debonding in Pretensioned Beams

- 130-

162

150-

125-

100

Load

(Kips)75-

50-

25-

Beam with bonded strands

Beam with debonded strands

0.15 0.30

Deflection Under Load P (inch)

0.45

Figure (2.67) Load-Deflection Relationship, Final Load Phase

Sepecimen 2

Page 159: Strand Debonding in Pretensioned Beams

-131

100

90-

80

70-

60-

Load

(Kips)

0.00

Beam with bonded strands

Beam with debonded strands

0.05 0.10 0.15 0.20 0.25

Midspan Deflection (inch)

0.30

Figure (2.68) Load-Deflection Relationship, Initial Load Phase

Specimen 2

Page 160: Strand Debonding in Pretensioned Beams

132-

162

150-

125-

100-

Load

(Kips)75-

50-

25-

Beam with bonded strands

Beam with debonded strands

0.15 0.30

Midspan Deflection (inch)

0.45

Figure (2.69) Load-Deflection Relationship, Final Load Phase

Specimen 2

Page 161: Strand Debonding in Pretensioned Beams

- 133 -

T-3

c/;

O

'Si

Q,

3c

u

c/5

sa«O"_>

la3

c3

I

IE

1

II

Page 162: Strand Debonding in Pretensioned Beams

-134-

Load

(Kips)

100

90^

80

70-

60-

50-

40-

30-

20-

10-

100

Gage No. 4

Gage No. 6

m - - Gage No. 7

A Gage No. 8

11 1 1

300 400 500 600 700 800

inStrain ( a— )

in

Figure (2.71) Compressive Strain at Continuous Support

Initial Load Phase (Specimen 2)

Page 163: Strand Debonding in Pretensioned Beams

135

200 400 800 1000 1200 1400

inStrain ( U.— )

in

Figure (2.72) Compressive Strain at Continuous Support

Final Load Phase (Specimen 2)

Page 164: Strand Debonding in Pretensioned Beams

136

1000 1250 1500 1750

Strain ( u. — )

in

Figure (2.73) Stirrup Strains at Continuous Support, Initial Load Phase

Beam With 67% Debonding (Specimen 2)

Page 165: Strand Debonding in Pretensioned Beams

137

m

2500

Strain ( u — )

in

Figure (2.74) Stirrup Strains at Continuous Support. Final Load Phase

Beam With 61% Debonding (Specimen 2)

Page 166: Strand Debonding in Pretensioned Beams

138

100.

250 500 750

Strain ( u.— )in

i r

1000 1250 1500 1750

in

Figure (2.75) Stirrup Strains at Continuous Support, Initial Load Phase

Beam With 0% Debonding (Specimen 2)

Page 167: Strand Debonding in Pretensioned Beams

139

Strain ( u. — )

in

500

Figure (2.76) Stirrup Strains at Continuous Support, Final Load Phase

Beam With 0% Debonding (Specimen 2)

Page 168: Strand Debonding in Pretensioned Beams

140

Load

(Kips)

Gage No, 7

Gage No. 8

Gage No. 9

inStrain ( u. — )

in

1000

Figure (2.77) Strain in Slab Longitudinal Steel at Centerline of Diaphragm

Initial Load Phase (Specimen 2)

Page 169: Strand Debonding in Pretensioned Beams

- 141

Load

(Kips)

162

150-

125

100-

75-

50

25-

Gage No. 7

Gage No. 8

Gase No. 9

250 500 750 1000 1250 1500 1750

Strain ( u.— )

in

Figure (2.78) Strain in Slab Longitudinal Steel at Centerline of Diaphragm

Final Load Phase (Specimen 2)

Page 170: Strand Debonding in Pretensioned Beams

- 142-

162

150-

125-

100

Load

(Kips)75

50

25-

4750

Gage IB 1

Gage IB2

5000 5250 5500

inStrain ( u. — )

in

Figure (2.79) Strand Strain at 47 in. from Continuous Support, Final Load Phase

Beam with 67% Debonding (Specimen 2)

Page 171: Strand Debonding in Pretensioned Beams

- 143

162

150-

125-

100-

Load

(Kips)75-

50-

25-

4000

Gage IB4

Gage IB5

4750 5500 6250 7000 7750

c inStrain ( u.

—in

Figure (2.80) Strand Strain at 77 in. from Continuous Support. Final Load Phase

Beam with 67% Debonding (Specimen 2)

Page 172: Strand Debonding in Pretensioned Beams

144-

Load

(Kips)

4000 4750 5500 6250 7000 7750

inStrain ( u_ — )

in

Figure (2.81) Strand Strain at 88 in. from Continuous Support, Final Load Phase

Beam with 67% Debonding (Specimen 2)

Page 173: Strand Debonding in Pretensioned Beams

145

162

150-

125

100

Load

(Kips)75

50-

25

3800

Gage IC1

Gage IC2

4000 4200 4400

inStrain ( u. — )

in

Figure (2.82) Strand Strain at 45 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 2)

Page 174: Strand Debonding in Pretensioned Beams

- 146

162

150-

125-

100-

Load

(Kips)75-

50-

25-

4000

Gage IC5

Gage IC6

Gage IC7

4250 4500 4750

in

1^

5000 5250

Strain ( u— )in

Figure (2.83) Strand Strain at 77 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 2)

Page 175: Strand Debonding in Pretensioned Beams

147

Load

(Kips)

40(H) 4250 4500

Strain ( 11— )in

4750 000

Figure (2.84) Strand Strain at 89 in. from Continuous Support. Final Load Phase

Beam with 0% Debonding (Specimen 2)

Page 176: Strand Debonding in Pretensioned Beams

148

Figure (2.85) Beam with 83% Debonding at Completion of

Initial Load Phase (Specimen 3)

Figure (2.86) Beam with 0% Debonding at Completion ofInitial Load Phase (Specimen 3)

Page 177: Strand Debonding in Pretensioned Beams

149

Figure (2.87) Beam with 83% Debonding at Completion of

Final Load Phase (Specimen 3)

Figure (2. XX) Beam with 0% Debonding at Completion of

Final L(Md Phase (Specimen 3)

Page 178: Strand Debonding in Pretensioned Beams

150

V l ^f.**

Hw^~T^^^^

'"'feyK v ~ 'i

SSBB5*? si JI -jj^si

iTfrMnir

/ ^yv -'r.,-- flP

f^^w X/'wi

V27, .,,

2^1

SSI- I

Figure (2.89) Deck Cracking over Continuous Supports at Completion

of Initial Load Phase (Specimen 3)

Figure (2.90) Deck Cracking over Continuous Supports at Completionof Final Load Phase (Specimen 3)

Page 179: Strand Debonding in Pretensioned Beams

151-

Load

(Kips)

0.00

Beam with bonded strands

Beam with debonded strands

0.05 0.10 0.15 0.20 0.25

Deflection Under Load P (inch)

0.30

Figure (2.91) Load-Deflection Relationship. Initial Load Phase

Specimen 3

Page 180: Strand Debonding in Pretensioned Beams

-152

164-

150-

125-

Load

(Kips)

Beam with bonded strands

Beam with debonded strands

11 1

0.20 0.40 0.60 0.80

Deflection Under Load P (inch)

1.00

Figure (2.92) Load-Deflection Relationship, Final Load Phase

Specimen 3

Page 181: Strand Debonding in Pretensioned Beams

153

Load

(Kips)

Beam with bonded strands

Beam with debonded strands

0.00 0.05 0.10 0.15 0.20 0.25 0.30

Midspan Deflection (inch)

Figure (2.93) Load-Deflection Relationship, Initial Load Phase

Specimen 3

Page 182: Strand Debonding in Pretensioned Beams

154-

Load

(Kips)

164

150

125-1

100

75-

50-

25-

Beam with bonded strands

Beam with debonded strands

I I I I I

0.00 0.20 0.40 0.60 0.80 1.00

Midspan Deflection (inch)

Figure (2.94) Load-Deflection Relationship, Final Load Phase

Specimen 3

Page 183: Strand Debonding in Pretensioned Beams

- 155

Load

(Kips)

100T90-

80

70

60-

50-

40-

30

20-

10-

i)

Beam with debonded

strands

25 50

Beam with bonded

strands

75 100 125 150 175 200

in .

Strain m- )

in

Figure (2.95) Compressive Strain. 4 inches from Continuous support

Initial Load Phase (Specimen 3)

Page 184: Strand Debonding in Pretensioned Beams

156

Load

(Kips)

100

90-

80-

70-

60-

50-

40

30-

20-

10-

200

Beam with bonded strands

Beam with debonded strands

400 600

in

800 1000

Strain ( |i — )

in

Figure (2.96) Beam Compressive Bottom Strain, 23 inches from Continuous Support

Initial Load Phase (Specimen 3)

Page 185: Strand Debonding in Pretensioned Beams

157

164

150-

125-

100-

-^ =

\ / i

i••

T •'

a: i /a: /

Load /

«Kips) 75 _ i ' /J ' /i /i i /^ ' / . Gase No.

4

50-.'1 / /

Gaee No.

6

T ' /

* /- _ Gage No.

7

25-1 / /

T ' /*"!

' /

:

* /

A Gaae No.8

--i« '

11

500 1000 1500 2000

Strain ( uin

in

Figure (2.97) Compressive Strain at Continuous Support Final Load Phase

(Specimen J)

Page 186: Strand Debonding in Pretensioned Beams

- 158

Load

(Kips)

500 1000

inStrain

(fi— )

in

1500

Figure (2.98) Stirrup Strains at Continuous Support, Initial Load Phase

Beam With 83% Debonding (Specimen 3)

Page 187: Strand Debonding in Pretensioned Beams

159

164 -r-

150-

125-

100

Load

' Kips) 75.

50

25-

, .

} /.*"/ / ."

/ <••S >:

/ / .

J s/ s/ // /

I y-

/

•'

fiage IB1

__ GageIB2

5(H) 1000 1500

in

Strain ( u. — )

in

Gage IBS

Ga°e 1B4

20(H) 15(H)

Figure (2.99) Stirrup Strains at Continuous Support. Final Load Phase

Beam With 83% Debonding (Specimen 3)

Page 188: Strand Debonding in Pretensioned Beams

-160

Load

(Kips)

1000

inStrain ( u\ — )

in

1500

Figure (2.100) Stirrup Strains at Continuous Support, Initial Load Phase

Beam With 0% Debonding (Specimen 3)

Page 189: Strand Debonding in Pretensioned Beams

- 161-

iut —^.' _

150-/

125-

I

100-:

/

Load

(Kips) 75 _i

/

Gaee IC1

50- i

:

;

c

Gage IC2

. GageIC3

25-E

c

E

t

1

/Gage IC4

-

1

5001

1000[

1500 2000 251

Strain i fi— )

in

Figure (2.101) Stirrup Strains At Continuous Support. Final Load Phase

Beam With 0% Debonding (Specimen 3)

Page 190: Strand Debonding in Pretensioned Beams

162-

Load

(Kips)

Gage No. 7

Gage No. 8

Gage No. 9

in

1

I I

250 500 750 1000 1250 1500

Strain ( u. — )

in

Figure (2.102) Strain in Slab Longitudinal Steel at Centerline of Diaphragm

Initial Load Phase (Specimen 3)

Page 191: Strand Debonding in Pretensioned Beams

163

Load

(Kips)

500 1000 1500 2000 2500

inStrain ( u - )

in

Figure (2.103) Strain in Slab Longitudinal Steel at Centerline of Diaphragm

Final Load Phase (Specimen 3)

Page 192: Strand Debonding in Pretensioned Beams

164-

Load

(Kips)

5500 6000 6500 7000 7500

inStrain ( u. — )

in

Figure (2.104) Strand Strain at 84 in. from Continuous Support, Final Load Phase

Beam with 83% Debonding (Specimen 3)

Page 193: Strand Debonding in Pretensioned Beams

- 165

164

150-

125-

100

Load

(Kips)75-

50-

25-

Gage IC2

Gage IC4

3500 4000 4500 5000 5500 6000 6500 7000

Strain m — )

in

Figure (2.105) Strand Strain at 42 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 3)

Page 194: Strand Debonding in Pretensioned Beams

166

164-

150-

125-

100

Load

(Kips)75-

50

25-

3500 4000

Gage IC5

Gage IC6

Gage IC7

Gage IC8

4500—I

5000

inStrain ( \i — )

in

5500 6000

Figure (2.106) Strand Strain at 66 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 3)

Page 195: Strand Debonding in Pretensioned Beams

- 167-

164

150-

125-

100-

Load

(Kips)75

50-

25

Gage IC10

Gage 1C 12

4800 4900 5000 5100 5200 5300 5400

inStrain ( u — )

in

Figure (2.107) Strand Strain at 84 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 3)

Page 196: Strand Debonding in Pretensioned Beams

- 168

co•f*

jgex

I

Eo

2^ea c

i.'•

c S

1"So a.3 C/3O wQ s

9 £u-i

S «.s o£ J6 "33 "3t> 'Spa £s~\H

1

1

oo©

Page 197: Strand Debonding in Pretensioned Beams

169

^

til

t

T

'o

uy

'

'

¥: r

•' -I' *

'

- • -

•>!-,

a.

EoU

_, ^

*-• Tc3

SB B0)

T. !

c—B a- ua a.«> i/;

P o#

! . _Cm a.JZ g~ C3

J

E!"1

"3

u Baa

rj

Z3

Page 198: Strand Debonding in Pretensioned Beams

- 170-

co

Icu

60

o c1-

e^ -co a.

5 "9

!3» .5

2360

Page 199: Strand Debonding in Pretensioned Beams

- 171

"

- i

I i

A /

Ji,

1 i

4

•c;-:

*'pi

,< ' ' '

;

<

mm"

j 1

' ' 'Y

/

/I

i

-

t

i

J 1

> ^ i \

c

—jQ.

E5U—?3

CO

e2aa.3 ^^

C/3 TTy; E3 <UO3 EC oQ oC D.o onU >-'

uu> ~z

O 2

c—

-^ Cu _5U 3

1

J

E

'-I

E

Page 200: Strand Debonding in Pretensioned Beams

172

co

• ^*t-t

jy

EoU*-*

03

V.+-*

3a.a,

co ^= Fc £

.5 o6 aCj£•— <uU or:

> 5° /F^^C "d

2 g

U 13 £Q o

CN

oi

E

Page 201: Strand Debonding in Pretensioned Beams

173

i_ t:0)03

03 _|o CO

o

o

w •cCD a: oC t=

S-«3o _i 3

CO

k_ eQJ a) o

cz O-oj

~*—

*

s-S

a o> a,—J O)T=> == ro

asS3Uo— .a— cQ o

ra oT= £= o.",=a> —

= «o t=o o

o

o

* I

saro

C3

s

1 § SO _l CJ

oua.00

Uso

•J

ac«

ocCO

>-enjMca

£

5

o

I

r I

UcCO

10 u

Page 202: Strand Debonding in Pretensioned Beams

- 174

Load

(Kips)

Beam with bonded strands

Beam with debonded strands

11 1

0.00 0.05 0.10 0.15 0.20 0.25

Deflection Under Load P (inch)

0.30

Figure (2.114) Load-Deflection Relationship, Initial Load Phase

Specimen 4

Page 203: Strand Debonding in Pretensioned Beams

176

175

Load

(Kips)

150-

125-

100-

75-

50-

25-

Beam with bonded strands

Beam with debonded strands

0.00 0.05 0.10 0.15 0.20 0.25 0.30

Deflection Under Load P (inch)

Figure (2.1 15) Load-Deflection Relationship, Final Load Phase

Specimen 4

Page 204: Strand Debonding in Pretensioned Beams

-176-

Load

(Kips)

90- /'

80-/

70-

60-

50-

40-

30-.y Rpam with honrfprl stranrls

20-J .„ Beam with debonded strands

10-

1 1 1 1 1 1

0.00 0.05 0.10 0.15 0.20 0.25

Midspan Deflection (inch)

0.30

Figure (2.1 16) Load-Deflection Relationship, Initial Load Phase

Specimen 4

Page 205: Strand Debonding in Pretensioned Beams

- 177 -

Load

<Kips)

176

150-

125

100

75-

50-

25

Beam with bonded strands

Beam with debonded strands

0.00 0.05 0.10 0.15 0.20 0.25 0.30

Mid-span (inch)

Figure (2.1 17) Load-Deflection Relationship, Final Load Phase

Specimen 4

Page 206: Strand Debonding in Pretensioned Beams

178-

Load

(Kips)

....... Gage No. 4

Gage No. 6

. B _ _ Gage No. 7

_A Gage No. 8

150 200

Strain ( u — )in

Figure (2.118) Compressive Strain at Continuous Support

Initial Load Phase (Specimen 4)

Page 207: Strand Debonding in Pretensioned Beams

179 -

176

150

125-

100-

Load

(Kips)75-

50-

25-

Gage No. 4

Gage No. 6

m _ _ Gage No. 7

A Gage No. 8

400

Strain ( u— )in

Figure (2.119) Compressive Strain at Continuous Support

Final Load Phase (Specimen 4)

Page 208: Strand Debonding in Pretensioned Beams

180

176

150-

125-

ioo-:

Load

(Kips)75-;

50 -

25-

Gage IB 1

Gage IB2

Gage IB

3

Gage IB4

500 1000 1500

inStrain ( p. — )

in

2000 2500

Figure (2.120) Stirrup Strains at Continuous Support

Final Load Phase, Beam With 50% Debonding (Specimen 4)

Page 209: Strand Debonding in Pretensioned Beams

181

125 h

100 -

Load

(Kips)75-

50-?

25

Gage IC1

Gage IC2

Gage IC3

Gage IC4

500 1000 15(H)

inStrain ( u — )

in

2000 2500

Figure (2.121) Stirrup Strains At Continuous Support

Final Load Phase, Beam With 0% Debonding (Specimen 4)

Page 210: Strand Debonding in Pretensioned Beams

182-

Load

(Kips)

Gage No. 7

Gage No. 8

Gage No. 9

1250 1500

Strain ( u. — )in

Figure (2.122) Strain in Slab Steel

at Centerline of Diaphragm, Initial Load Phase

(Specimen 4)

Page 211: Strand Debonding in Pretensioned Beams

- 183-

176

150

125-

Load

(Kips)

100

75-

50-

25-

Gage No. 7

Gage No. 8

Gage No. 9

1250

Strain ( \i — )in

Figure (2.123) Strain in Slab Longitudinal Steel

at Centerline of Diaphragm, Final Load Phase

(Specimen 4)

1750

Page 212: Strand Debonding in Pretensioned Beams

184

176

150-

125-

100-Load

(Kips)

75-

50

25-

5000 5200 5400

Strain ( u— )

in

5600 5800

Figure (2.124) Strand Strain at 48 in. from Continuous Support, Final Load Phase

Beam with 50% Debonding (Specimen 4)

Page 213: Strand Debonding in Pretensioned Beams

- 185 -

176

150-

125-

100-Load

(Kips)

75-

50-

25-

2500

I

Gage IBS

Gage IB 11

Gage IB 13

3000 3500 4000

in

Strain ( ll— )

in

4500 5000

Figure (2.125) Strand Strain at 60 in. from Continuous Support, Final Load Phase

Beam with 50% Debonding (Specimen 4)

Page 214: Strand Debonding in Pretensioned Beams

-186

Load

(Kips)

176

150-

125

100-

75

50^

25-

i

i

i

14

A— -A

i

4

Gage IB 16

Gage IB 17I

..GageIB18 /

A .... A ....GageIB20 /

GageIB21/

/

( t

-£-1 1 1^

4000 4250 4500 4750 5000 5250 5500 5750

Strain ( u. — )

in

Figure (2.126) Strand Strain at the Point Load, Final Load Phase

Beam with 50% Debonding (Specimen 4)

Page 215: Strand Debonding in Pretensioned Beams

- 187

176

150

125

100-Load

(Kips)

75-

50

25-

4750 5000

Gage IC4

Gage IC6

Gage IC7

5250

Strain ( \i — )

5500 5750

min

6000

Figure (2.127) Strand Strain at 48 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 4)

Page 216: Strand Debonding in Pretensioned Beams

188-

Load

(Kips)

1 /O-n

150-

1 > »-=*-/ \

/ \

i \

; \

/ 1

i i

i

V

' 1

125-

i

i

1 Pi /

i

100-

i /

I75-

i 1

il

*

)

50- i Gage IC10

25-/'

f/ /

/ •

it

t

iGage IC12

a GageIC13

... A ...GageIC14

i /

i1

1 "1 i 1

4750 5000

P

5250 5500

in

5750 6000

Strain ( \i— )

in

Figure (2.128) Strand Strain at 60 in. from Continuous Support, Final Load Phase

Beam with 0% Debonding (Specimen 4)

Page 217: Strand Debonding in Pretensioned Beams

189

4500 5000 5500

Strain ( u. — )

in

6000 6500

Figure (2.129) Strand Strain at the Point Load, Final Load Phase

Beam with 0% Debonding (Specimen 4)

Page 218: Strand Debonding in Pretensioned Beams

190

Moment

(ft-k)

-25-

-50-

-75-

-100-

125-

450-

Test

CTL method

PCA method

157

3 120 130 140 150 160 170

Time (Days)

Figure (3.1) Variation with Time of Support Restraint Moment

Considering Shrinkage Modification after 28 Days

and Effects of Slab Top Steel after 30 Days

Specimen 1

Page 219: Strand Debonding in Pretensioned Beams

191 -

-25-

-50-

Moment -75 -

(ft-k)

-100-

-125-

-150

48 60

Test

CTL method

PCA method

1 T"

70 80

Time (Days)

•it,

<><) 100

Figure (3.2) Variation with Time of Suppon Restraint Moment

Considering Shrinkage Modification after 2S Days

and Effects of Slab Top Steel after 30 Days

Specimen 2

Page 220: Strand Debonding in Pretensioned Beams

-192-

Moment

(ft-k)

-25-

-50-

-75-

-100

-125-

-150-

-175-

I

9091

Test

CTL method

PCA method

95 115

Time (Days)

120

Figure (3.3) Variation with Time of Support Restraint Moment

Considering Shrinkage Modification after 28 Days

and Effects of Slab Top Steel after 30 Days

Specimen 3

Page 221: Strand Debonding in Pretensioned Beams

193 -

26 30 35 40 45

Time (Days)

Figure (3.4) Variation with Time of Support Restraint Moment

Considering Shrinkage Modification after 28 Days

and Effects of Slab Top Steel after 30 Days

Specimen 4

Page 222: Strand Debonding in Pretensioned Beams

- 194-

-25-

-50-

Moment -75 -

(ft-k)

-100-

-125-

-150

Test

CTL method

PCA method

Application of

bve load

3 120 130 140

Time in Days

1 157 I

150 160 170

Figure (3.5) Variation with Time of Support Restraint Moment

Considering Shrinkage Modification and

Effects of Slab Top Steel after 3 Days

Specimen 1

Page 223: Strand Debonding in Pretensioned Beams

195

-25-

-50-

Moment -75

(ft-k)

-100-

-125

-150

Test

CTL method

PCA method

48

Application of

live load

60 70 80

Time (Days)

;<.

'Ml I X)

Figure (3.6) Variation with Time of Support Restraint Moment

Considering Shrinkage Modification

and Effects of Slab Top Steel after 3 Days

Specimen 2

Page 224: Strand Debonding in Pretensioned Beams

-196

Moment

(ft-k)

V-i» >i

O-25- \ .

\

"***\.

\ '• .•"•• Ssv^

-50-\

'•...x^^^

-75-^ .„ Test

"^ CTL method

100-N - -m- - PCA method

X125-

Application of .

150-

175-

live load

1 1 1 113 1

91 100 105

Time (Days)

110 115 120

Figure (3.7) Variation with Time of Support Restraint Moment

Considering Shrinkage Modification after 3 Days

and Effects of Slab Top Steel after 3 Days

Specimen 3

Page 225: Strand Debonding in Pretensioned Beams

197-

70-

60-

50-

40- /

loment

(ft-k)

30-

20-

10-

0h

-10-

—^^

X

^^^ X/•^^"^ X^ X Application of

_^>* : ^ Live Load

\ * Test\ x

-20-\

••' X' CTL method

' X'mr- - - - PCA methiKl

-30-

-40-

\ /

-50'

' ' ' 1 1 1 <q26 30 35 40 45 50 55

Time (Days)

Figure (3.8) Variation with Time of Support Restraint Moment

Considering Shrinkage Modification and

Effects of Slab Top Steel after 3 Days

Specimen 4

Page 226: Strand Debonding in Pretensioned Beams

-198

w

r'

9

Lr^31.5*

1mCOT-

T

03

ECO05

fb

incm

inCM

<H

inCMinCM

M

o

"3c<u

"809

P

8s

03 03 T5 «

Page 227: Strand Debonding in Pretensioned Beams

199-

E.2

2 cd

£3-c/>cum

t

1

ItoCO

1

> _r»CM

09

O

ECOCD

itf-

fH

CM

<H

CM

U^J

eu

uuQ.GO'<-

oc/)

8

u—

"3c<

CM

daM

o ^CD "c3

.£= CM

as "33

Page 228: Strand Debonding in Pretensioned Beams

200-

500

400-

- 300

Moment(ft-k)

200-

- 100 .. PCA Rigid Connection

_ CTL Flexible Connection

.... Test Measurements

n r50 75

Load P (Kips)

100 125

A ll 11

25.25 ft 25.25 ft

A.he-

11 11:»i< :»ic

il—*^

-j) Rigid Connection

Flexible Connection

24 ft. 2.5 ft 24 ft.

Figure (4.3) Variation of Continuity Moment due to

Superimposed Load (P), Initial Load Phase

Specimen 1

Page 229: Strand Debonding in Pretensioned Beams

201

500

400-

- 300-

Moment(ft-k)

200-

100- PCA Rigid Connection

CTL Rexible Connection

Test Measurements

~i r50 75

Load P (Kips)

25 100 125

~nr -q Rigid Connection

25.08 ft. 25.08 ft.

JST 11 iL -j^ Flexible Connection

24.33 ft. 1.5 ft 24.33 ft

Figure (4.4) Variation of Continuity Moment due to

Superimposed Load (P), Initial Load Phase

Specimen 2

Page 230: Strand Debonding in Pretensioned Beams

500

400-

-202-

300-

Moment(ft-k)

- 200-

100- PCA Rigid Connection

CTL Flexible Connection

Test Measurements

50 75

Load P (Kips)

100 125

he25.08 ft.

XL -q_ Rigid Connection

25.08 ft.

JST -q_ Flexible Connection

24.33 ft 1.5ft 24.33 ft.

Figure (4.5) Variation of Continuity Moment due to

Superimposed Load (P), Initial Load Phase

Specimen 3

Page 231: Strand Debonding in Pretensioned Beams

-500

400-

300-

Moraent

(ft-k)

200

203

100- PCA Rigid Connection

CTL Flexible Connection

. . . . Test Measurements

-| r50 75

Load P (Kips)

25 100 125

25.08 ft.

-j^ Rigid Connection

25.08 ft.

12. XL

24.33 ft. 1.5ft 24.33 ft.

—D. Flexible Connection

Figure (4.6) Variation of Continuity Moment Due to

Superimposed Load (P), Initial Load Phase

Specimen 4

Page 232: Strand Debonding in Pretensioned Beams

204

K factor

1.0 -r

0.9-

0.8-

0.7-

0.6-

0.5-

0.4-

0.3-

0.2-

0.1-

0.0-

20

Test (Gages)

Test (Reactions)

40 60 80

Load (Kips)

100

~~

1

120 140

Figure (4.7) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 4 (Specimen 1)

Page 233: Strand Debonding in Pretensioned Beams

-205-

K factor

1.0

0.9-

0.8-

0.7-

0.6-

0.5-

0.4

0.3-

0.2

0.1

0.0

Test (Gages)

Test (Reactions)

40 60 80

Load (Kips)

100 120 140

Figure (4.8) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 6 (Specimen 1

)

Page 234: Strand Debonding in Pretensioned Beams

206

K factor

1.0

0.9-

0.8

0.7-

0.6-

0.5-

0.4-

0.3-

0.2-

0.1-

0.0

20

Test (Gages)

Test (Reactions)

40 60 80

Load (Kips)

100 120 140

Figure (4.9) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 8 (Specimen 1)

Page 235: Strand Debonding in Pretensioned Beams

-207

K factor

1.0

0.9-

0.8

0.7

0.6-

0.5-

0.4-

0.3-

0.2-

0.1-

0.0

20

Test (Gages)

Test (Reactions)

40 60 80

Load (Kips)

100 120 140

Figure (4.10) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 7 (Specimen 1

)

Page 236: Strand Debonding in Pretensioned Beams

208

K factor

1.0

0.9

0.8

0.7

0.6

0.5

0.4

0.3

0.2

0.1-

0.0

Test (Gages)

Test (Reactions)

20 40 60 80 100

Load (Kips)

T T120 140 162

Figure (4.11) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 4 (Specimen 2)

Page 237: Strand Debonding in Pretensioned Beams

209-

K factor

1.0

0.9-

0.8-

0.7-

0.6

0.5-

0.4-

Test (Gages)

Test (Reactions)

0.3-

20 40 60 80 100

Load (Kips)

162

Figure (4.12) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 6 (Specimen 2)

Page 238: Strand Debonding in Pretensioned Beams

210-

K factor

1.0

0.9

0.8-1

0.7

0.6-

0.5-

0.4

0.3

0.2-

0.1

0.0

Test (Gages)

Test (Reactions)

20 40

-| 1 T"60 80 100

Load (Kips)

120 140 162

Figure (4.13) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 8 (Specimen 2)

Page 239: Strand Debonding in Pretensioned Beams

211

K factor

1.0

0.9-

0.8-

0.7-

0.6

0.5-

0.4

0.3-

0.2-

0.1-

0.0

20 40

Test (Gages)

Test (Reactions)

~]I I

60 80 100

Load (Kips)

120 140 162

Figure (4.14) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 7 (Specimen 2)

Page 240: Strand Debonding in Pretensioned Beams

-212

K factor

1.0

0.9-

0.8-

0.7-

0.6-

0.5-

0.4-

03-

0.2-

0.1-

0.0

Test (Gages)

Test (Reactions)

20 40 60 80 100 120 140 164

Load (Kips)

Figure (4.15) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 4 (Specimen 3)

Page 241: Strand Debonding in Pretensioned Beams

- 213 -

K factor

1.0

0.9-

0.8-

0.7

0.6-

0.5

Test (Gages)

Test (Reactions)

20 40 60 80 100

Load (Kips)

1 T~120 140 164

Figure (4.16) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 6 (Specimen 3)

Page 242: Strand Debonding in Pretensioned Beams

214

K factor

1.0

0.9-

0.8-

0.7

0.6-1

0.5-

0.4-

03-

0.2-

0.1-

0.0

Test (Gages)

Test (Reactions)

~i r20 40

~i 1 r~60 80 100

Load (Kips)

1^ 1^

120 140 164

Figure (4.17) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 8 (Specimen 3)

Page 243: Strand Debonding in Pretensioned Beams

215

K factor

1.0

0.9-

0.8-

0.7-

0.6-

0.5-

Test (Gages)

Test (Reactions)

60 80 100

Load (Kips)

120 140 164

Figure (4.18) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 7 (Specimen 3)

Page 244: Strand Debonding in Pretensioned Beams

-216-

K factor

1.0

0.9-

0.8-

0.7-

0.6-

0.5-

0.4-

0.3-

0.2-

0.1-

0.0I

25

Test (Gages)

Test (Reactions)

T T50 75 100

Load (Kips)

125 150 176

Figure (4.19) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 4 (Specimen 4)

Page 245: Strand Debonding in Pretensioned Beams

217

K factor

1.0

0.9-

0.8-

0.7

0.6-

0.5

0.4

0.3^

0.2

0.1

0.0

25 50

Test (Gages)

Test (Reactions)

-i r-

75 100

Load (Kips)

125 150 176

Figure (4.20) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 6 (Specimen 4)

Page 246: Strand Debonding in Pretensioned Beams

218-

K factor

1.0

0.9-

0.8-

0.7

0.6-

0.5-

0.4

0.3

Test (Gages)

Test (Reactions)

0.2-.

0.1-

0.0

25 50 75 100

Load (Kips)

125 150 176

Figure (4.21) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 8 (Specimen 4)

Page 247: Strand Debonding in Pretensioned Beams

219

K factor

1.0

o.<M

0.8

0.7

0.6-

0.5-

0.4

0.3-1

Test (Gages)

Test (Reactions)

1^

75 100

Load (Kips)

176

Figure (4.22) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 7 (Specimen 4)

Page 248: Strand Debonding in Pretensioned Beams

-220-

K factor

1.0

0.9

0.8-

0.7-

0.6-

0.5-

0.4

0.3-

0.2

0.1-

0.0

Test

PCA method

CTL method

20 40~~

i

r~60 80

Load (Kips)

100 120 140

Figure (4.23) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 4 Location (Specimen 1)

Page 249: Strand Debonding in Pretensioned Beams

221

K factor

1.0

0.9-

0.8-

0.7-

0.6-

0.5

0.4-

0.3-

0.2-

0.1

0.0

Test

PCA method

CTL method

60 80

Load (Kips)

140

Figure (4.24) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 6 Location (Specimen 1

)

Page 250: Strand Debonding in Pretensioned Beams

222

K factor

1.0

0.9-

0.8-

0.7-

0.6-

0.5-

0.4

0.3

0.2-

0.1-

0.0

Test

PCA method

CTL method

20 40 60 80

Load (Kips)

100 120 140

Figure (4.25) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 8 Location (Specimen 1

)

Page 251: Strand Debonding in Pretensioned Beams

223

K factor

1.0

0.9-

0.8-

0.7-

0.6-

0.5

0.4

0.3-

0.2

0.1-

0.0

20 40

Test

PCA method

CTLmethcxl

—1 1~"

60 80

Load (Kips)

100 120 140

Figure (4.26) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 7 Location (Specimen 1

)

Page 252: Strand Debonding in Pretensioned Beams

-224

K factor

1.0

0.9-

0.8-

0.7-

0.6-

0.5

0.4^

Test

PCA method

CTL method

60 80 100

Load (Kips)

Figure (4.27) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 4 Location (Specimen 2)

Page 253: Strand Debonding in Pretensioned Beams

-225-

K factor

1.0

0.9 -|

0.8

0.7-

0.6-

0.5

0.4

0.3

0.2^

0.1

0.0

Test

PCA method

CTL method

20 40 60 80 100

Load (Kips)

120 140 162

Figure (4.28) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 6 Location (Specimen 2)

Page 254: Strand Debonding in Pretensioned Beams

226-

K factor

1.0

0.9-

0.8-

0.7-

0.6-

0.5-

0.4-

0.3-

0.2-

0.1-

0.0

Test

PCA method

CTL method

20 40 60 80 100

Load (Kips)

120 140 162

Figure (4.29) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 8 Location (Specimen 2)

Page 255: Strand Debonding in Pretensioned Beams

227-

K factor

1.0

0.9-

0.8-

0.7-

0.6-

0.1-

0.0

Test

PCA method

CTL method

20 40 60 80 100

Load (Kips)

120 140 162

Figure (4.30) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 7 Location (Specimen 2)

Page 256: Strand Debonding in Pretensioned Beams

228

K factor

1.0

0.9-

0.8-

0.7

0.6-

0.5

0.4^

Test

PCA method

CTL method

60 80 100

Load (Kips)

164

Figure (4.31) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 4 Location (Specimen 3)

Page 257: Strand Debonding in Pretensioned Beams

-229

K factor

1.0

0.9

0.8-

0.7-

0.6-

0.5

Test

PCA method

CTL method

I

60 80 100

Load (Kips)

120 140 164

Figure (4.32) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 6 Location (Specimen 3)

Page 258: Strand Debonding in Pretensioned Beams

230

K factor

1.0

0.9-

0.8-

0.7

0.6

0.5-

0.4-

03-

0.2-

0.1-

0.0

Test

PCA method

CTL method

1^ 1^

20 40T T

60 80 100

Load (Kips)

120 140 164

Figure (4.33) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 8 Location (Specimen 3)

Page 259: Strand Debonding in Pretensioned Beams

231

K factor

1.0

0.9-

0.8-

0.7-

0.6

Test

PCA method

CTL method

80 100

Load (Kips)

120 140 164

Figure (4.34) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 7 Location (Specimen 3)

Page 260: Strand Debonding in Pretensioned Beams

-232-

K factor

1.0 -r

0.9-

0.8-

0.7-

0.6-

0.5-

0.4-

0.3-

0.2-

0.1-

0.0-

Test

PCA method

CTL method

25 50~

i

r~75 100

Load (Kips)

125 150 176

Figure (4.35) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 4 Location (Specimen 4)

Page 261: Strand Debonding in Pretensioned Beams

233-

K factor

1.0

0.9-

0.8-

0.7-

0.6-

0.5

0.4 -I

Test

PCA method

CTL method

75 100

Load (Kips)

76

Figure (4.36) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 6 Location (Specimen 4)

Page 262: Strand Debonding in Pretensioned Beams

-234-

K factor

1.0

0.9-

0.8-

0.7-

0.6-

0.5

0.4

0.3-

0.2-

0.1-

0.0

Test

PCA method

CTL method

25 50

-

1

r~75 100

Load (Kips)

125 150 176

Figure (4.37) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 8 Location (Specimen 4)

Page 263: Strand Debonding in Pretensioned Beams

235

K factor

1.0

0.9

0.8

0.7

0.6

0.5

0.4

Test

PCA method

CTL method

75 100

Load (Kips)

Figure (4.38) Compressive Stress Distribution at

The Bottom of Girder, Final Load Phase

Gage 7 Location (Specimen 4)

Page 264: Strand Debonding in Pretensioned Beams
Page 265: Strand Debonding in Pretensioned Beams

:- I

z

-

z